{"document":{"slug":"filing-er27-484-isone-large-loads","title":"ISO-NE, NEPOOL and the transmission owners file large-load tariff revisions under section 205","issued":"2026-11-13","accession":"20261113-5007","docket":"ER27-484-000","group":"ISO-NE filings","filer":"ISO New England Inc., NEPOOL Participants Committee and the Participating Transmission Owners","kind":"filing","file":"sources/originals/20261113-5007_01.pdf","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20261113-5007","sha256":"f56d92888c894551a2353c3192112961cd2943e4fe0cec6725ba4bb788c59e77","pages":99,"tokens":45666,"emptyPages":[]},"pages":[{"page":1,"startToken":0,"endToken":354,"text":"November 13, 2026 \n \nVIA ELECTRONIC FILING \n \nThe Honorable Debbie Anne Reese, Secretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC 20426 \n \nRe:  \nRevisions to ISO New England Inc. Transmission, Markets and Services Tariff \nRelated to the Integration of Large Loads to the Transmission System;  \nDocket No. ER27-___-000 \n \nRequests for an effective date of November 14, 2026, waiver of 60-days’ prior notice, \nand extended comment period of 24 days \n \nDear Secretary Reese: \n \nPursuant to section 205 of the Federal Power Act (“FPA”),1 ISO New England Inc. (“ISO-NE” \nor the “ISO”),2 joined by the New England Power Pool (“NEPOOL”) Participants Committee,3 the \nParticipating Transmission Owners Administrative Committee (“PTO AC”) on behalf of the \nParticipating Transmission Owners (“PTOs”) and the following PTOs:  Central Maine Power Company \n(“CMP”); Connecticut Transmission Municipal Electric Energy Cooperative (“CTMEEC”);4 \nEversource Energy Service Company (“Eversource”) on behalf of The Connecticut Light and Power \nCompany, Public Service Company of New Hampshire and NSTAR Electric Company; Fitchburg Gas \n \n1 16 U.S.C. § 824d. \n2 Capitalized terms not otherwise defined herein have the meanings ascribed thereto in the ISO New England Inc. \nTransmission, Markets and Services Tariff (“Tariff”).  Section II of the Tariff contains the ISO’s Open Access \nTransmission Tariff (“OATT”).    \n3 NEPOOL supported the Tariff Revisions, except the proposed Large Load Cost Recovery Agreement (new \nAttachment V to the OATT) and, accordingly, NEPOOL does not join this filing with respect to that agreement. \n4 CTMEEC is a non-jurisdictional utility pursuant to section 201(f) of the FPA, 16 U.S.C. § 824(f), and is expressly \nexcluded from the PTOs that must respond to the Federal Energy Regulatory Commission’s (“FERC” or \n“Commission”) June 18, 2026 Order Instituting Proceeding Under Section 206 of the FPA, ISO New England Inc., \n195 FERC ¶ 61,215, P 3 n.10 (2026) (“Show Cause Order”) order dismissing request for reh’g & clarification, 196 \nFERC ¶ 61,215 (2026).  Accordingly, CTMEEC joins this submission as a Filing Party only to the extent necessary \nto sponsor changes to its Schedule 21-CTMEEC in conformance with the proposed tariff changes sponsored by ISO-\nNE and the PTO AC."},{"page":2,"startToken":354,"endToken":866,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 2 of 99 \n \n \n \nand Electric Light Company (“Fitchburg”); Green Mountain Power Corporation (“GMP”); The \nNarragansett Electric Company d/b/a Rhode Island Energy (“RIE”); New England Power Company \nd/b/a National Grid (“National Grid”); New Hampshire Transmission, LLC (“NHT”); The United \nIlluminating Company (“UI”); Unitil Energy Systems, Inc. (“Unitil”); Vermont Electric Cooperative, \nInc. (“VEC”);5 Vermont Transco LLC (“VTransco”); and Versant Power (“Versant”) (together, the \n“Filing Parties”), submit this transmittal letter and proposed revisions to the Tariff (“Tariff Revisions”) \nto integrate Large Loads to the transmission system.  The Filing Parties submit that the Tariff Revisions \naddress all the issues discussed in the Show Cause Order.  As stated in Section III of this transmittal \nletter, ISO-NE and the PTOs respectfully request that, if the Commission accepts this section 205 filing, \nit terminate the proceeding related to the Show Cause Order in full. \n \nThe Tariff Revisions also include provisions relevant to the resource adequacy concerns that \nthe Commission expressed in the Show Cause Order.  ISO-NE discussed these resource adequacy \nconcerns and its anticipated response in its informational report on resource adequacy submitted to the \nCommission on July 20, 2026.6   \n \nThe Filing Parties respectfully request that the Commission waive the 60-day notice \nrequirement and accept the Tariff Revisions without modification or condition effective November \n14, 2026.  As explained in Section VII of this transmittal letter, this effective date will allow all \naffected parties to prepare to take advantage of the new transmission services for Large Loads.   \n \nThe Tariff Revisions related to use of the Dispatchable Asset Related Demand (“DARD”) \nmodel and the price-based re-dispatch mechanism7 for the new non-firm transmission services \nsubmitted as part of this filing (both described in Section IV.B.3 of this filing letter) are supported by \nthe Testimony of Dennis Cakert.  All other Tariff Revisions submitted as part of this filing under the \nISO’s section 205 rights are supported by the Affidavit of Alexander Rost (both are solely sponsored \nby the ISO).   \n \nI. \nDESCRIPTION OF THE FILING PARTIES AND COMMUNICATIONS \nISO-NE is the private, non-profit entity that serves as the Regional Transmission \nOrganization (“RTO”) for New England.  ISO-NE plans and operates the New England bulk power \nsystem and administers New England’s organized wholesale electricity markets pursuant to the \nTariff and the Transmission Operating Agreement (“TOA”) with the PTOs.  In its capacity as an \nRTO, ISO-NE has the responsibility to protect the short-term reliability of the New England \n \n5 VEC is a non-jurisdictional utility pursuant to section 201(f) of the FPA, 16 U.S.C. § 824(f), and is expressly \nexcluded from the PTOs that must respond to the Show Cause Order. VEC is reviewing its Schedule 21-VEC to \ndetermine if any proposed tariff changes sponsored by ISO-NE and the PTO AC require amendments to its Local \nService Schedule. \n6 ISO New Eng. Inc., Informational Report, Docket No. EL26-72-000 (July 20, 2026) (“Informational Report”). \n7 In Section III of the Tariff, “re-dispatch” appears hyphenated.  In the OATT, “redispatch” appears without a hyphen.  \nThe Tariff Revisions maintain this structure."},{"page":3,"startToken":866,"endToken":1440,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 3 of 99 \n \n \n \nControl Area and to operate the system according to reliability standards established by the \nNortheast Power Coordinating Council and the North American Electric Reliability Corporation. \nNEPOOL is a voluntary association organized in 1971 pursuant to the NEPOOL \nAgreement, and it has grown to include more than 560 members.  The Participants include all of \nthe electric utilities rendering or receiving service under the ISO-NE Tariff, as well as independent \npower generators, marketers, load aggregators, brokers, consumer-owned utility systems, end \nusers, developers, demand resource providers, and a merchant transmission provider.  Pursuant to \nrevised governance provisions accepted by the Commission,8 the Participants act through the \nNEPOOL Participants Committee.  The Participants Committee is authorized by Section 6.1 of \nthe Second Restated NEPOOL Agreement and Section 8.1.3(c) of the Participants Agreement to \nrepresent NEPOOL in proceedings before the Commission.  Pursuant to Section 2.2 of the \nParticipants Agreement, “NEPOOL provide[s] the sole Participant Processes for advisory voting \non [ISO-NE] matters and the selection of [ISO-NE] Board members, except for input from state \nregulatory authorities and as otherwise may be provided in the [ISO-NE] Tariff, TOA and the \nMarket Participant Services Agreement included in the [ISO-NE] Tariff.” \nThe PTOs9 are Transmission Providers providing Local Service on an open-access basis \nunder Schedule 21 of the OATT. Pursuant to the terms of the TOA among the PTOs and ISO-NE, \nthe PTOs own, physically operate and maintain Transmission Facilities in New England and ISO-\nNE has Operating Authority (as defined in Section 3.02 of the TOA) over all of the Transmission \nFacilities of the PTOs, including those used to provide Local Service under Schedule 21 of the \nOATT.  Section 3.04 of the TOA also grants the PTOs authority to submit filings to the \nCommission pursuant to section 205 of the FPA in matters affecting the rates, terms and conditions \nof Local Service under Schedule 21 and rates and charges, including cost allocation, for Regional \nTransmission Service under the OATT. \nSchedule 21 of the ISO OATT comprises two distinct parts.  First, under the common \nprovisions of Schedule 21 (“Schedule 21–Common”), the PTOs have collectively accumulated the \ncommon terms and conditions of Local Service applicable to transmission service over the local \nfacilities of all of the PTOs.  Second, each PTO has its own individual Schedule 21 schedule \n(“Local Service Schedule”), containing the rates, terms and conditions applicable to service over \nthe Local Facilities owned by that particular PTO. The Schedule 21 Local Service Schedules \n \n8 ISO New Eng. Inc. v. New Eng. Power Pool, 109 FERC ¶ 61,147 (2004). \n9 The PTOs are: Town of Braintree Electric Light Department; CMP; Chicopee Municipal Lighting Plant; Connecticut \nMunicipal Electric Energy Cooperative; CTMEEC; Eversource on behalf of The Connecticut Light and Power \nCompany, Public Service Company of New Hampshire and NSTAR Electric Company; Fitchburg; GMP; The City \nof Holyoke Gas and Electric Department; Town of Hudson Light and Power Department; Maine Electric Power \nCompany; Massachusetts Municipal Wholesale Electric Company; Town of Middleborough Gas & Electric \nDepartment; RIE; National Grid; New Hampshire Electric Cooperative, Inc.; NHT; Town of Norwood Municipal \nLight Department; Town of Reading Municipal Light Department; Shrewsbury Electric and Cable Operations; Town \nof Stowe Electric Department; Taunton Municipal Lighting Plant; UI; Unitil; VEC; Vermont Electric Power \nCompany, Inc.; Vermont Public Power Supply Authority; VTransco; Versant; and Town of Wallingford, CT, \nDepartment of Public Utilities, Electric Division."},{"page":4,"startToken":1440,"endToken":1683,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 4 of 99 \n \n \n \nprimarily contain the rates that would apply for transmission service over the Local Facilities \nowned by the particular PTO, and may also include terms and conditions of service in addition to \nthose contained in Schedule 21-Common. \nPursuant to Section 3.04 of the TOA, each PTO has the authority to submit filings under \nSection 205 of the FPA to establish and to revise the rates, terms and conditions of Transmission \nService under its individual Local Service Schedule affecting the facilities owned by that particular \nPTO.  In addition, the PTOs, acting jointly through the PTO AC, and in accordance with the TOA \nand Disbursement Agreement among the PTOs, have the authority to submit filings under Section \n205 of the FPA to establish and revise the common provisions of Local Service under Schedule \n21.  In this filing, the PTO AC is sponsoring the modifications to the common provisions of \nSchedule 21 on behalf of the PTOs.  While ISO-NE, as the RTO for New England, has operational \ncontrol over facilities used for Local Service, the PTOs, both individually and collectively, \ndetermine the rates, terms and conditions of transmission service over such facilities. \n \n \nCorrespondence and communications in this proceeding should be addressed to: \nISO NEW ENGLAND INC. \nMargoth Caley, Esq.* \nChief Regulatory Compliance Counsel \nISO New England Inc. \nOne Sullivan Road \nHolyoke, MA  01040 \nTel:  (413) 387-2408 \nFax:  (413) 535-4379 \nEmail: mcaley@iso-ne.com"},{"page":5,"startToken":1683,"endToken":1851,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 5 of 99 \n \n \n \nPTO AC \n \nDavid Burnham \nChair, Participating Transmission Owners \nAdministrative Committee \nEversource Energy \n56 Prospect Street \nHartford, CT 06103 \nTel: (860) 728-4506 \nEmail: david.burnham@eversource.com \n \n \n \nMary E. Grover, Esq.* \nChair, PTO AC Legal Working Group  \nc/o Eversource Energy \n247 Station Drive, SE100 \nWestwood, MA 02090 \nTel: (781) 441-8696 \nEmail: mary.grover@eversource.com \n \nCMP and UI \n \nNoelle M. Kinsch* \nAvangrid Networks, Inc. \n80 State Street, 12th Floor \nAlbany, NY 12207 \nTel: (518) 461-6984 \nEmail: noelle.kinsch@avangrid.com \n  \n \nJason N. Rauch* \nSenior Manager of Transmission and Regional \nEnergy Policy \nAvangrid Service Company \n83 Edison Drive \nAugusta, ME 04336 \nTel: (207) 629-2377 \nEmail: Jason.Rauch@avangrid.com \nCTMEEC \n \nAmber Martin Stone* \nGeneral Counsel \nConnecticut Municipal Electric Energy \nCooperative \n30 Stott Avenue \nNorwich, CT 06360 \nTel: (860) 383-1050 \nEmail: astone@cmeec.org \n \n \nHao Ni* \nAsset Performance Manager \nConnecticut Municipal Electric Energy \nCooperative \n30 Stott Avenue \nNorwich, CT 06360 \nTel: (860) 425-3229 \nEmail: hni@cmeec.org"},{"page":6,"startToken":1851,"endToken":1987,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 6 of 99 \n \n \n \n \nEversource \n \nThomas Lemon* \nSenior Counsel \nEversource Energy Service Company \n247 Station Drive, SE100 \nWestwood, MA 02090 \nTel: (781) 441-8692 \nEmail: thomas.lemon@eversource.com \n \n \n \nFitchburg and Unitil \n \nPatrick H. Taylor* \nUnitil Service Corp. \n6 Liberty Lane West \nHampton, NH 03842 \nTel: (603) 773-6544 \nEmail: taylorp@unitil.com \n \n \nDaniel Nawazelski* \nDirector, Rates & Revenue Requirements \n6 Liberty Lane West \nHampton, NH 03842 \nTel: (603) 379-3836 \nEmail: nawazelski@unitil.com \nGMP \n \nLiz Miller* \nExternal Coordinating Counsel \nElizabeth Miller PLC \nc/o Green Mountain Power Corp. \n163 Acorn Lane \nColchester, VT 05446 \nTel: (802) 522-3090 \nEmail: liz.miller@greenmountainpower.com \n \n \n \nJosh Castonguay* \nVP, Chief Innovation Officer, \nGeneration & Power Supply \nGreen Mountain Power Corp. \n163 Acorn Lane \nColchester, VT 05446 \nTel: (802) 324-8359 \nEmail: \njosh.castonguay@greenmountainpower.com"},{"page":7,"startToken":1987,"endToken":2154,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 7 of 99 \n \n \n \n \nRIE \n \nSteven M. Nadel* \nSenior Counsel \nPPL SERVICES CORPORATION \n645 Hamilton Street, Suite 700 \nAllentown, PA 18101 \nTel: (610) 774-4775 \nEmail: SMNadel@pplweb.com \n \n  \n \n \nKimberly B. Frank* \nK&L Gates LLP \n1601 K Street, N.W. \nWashington, D.C. 20006 \nTel: (202) 778-9064 \nEmail: kimberly.frank@klgates.com \nNational Grid \n \nChristopher J. Novak* \nSenior Counsel \nNational Grid \n170 Data Drive \nWaltham, MA 02451 \nTel: (617) 690-9964 \nEmail: chris.novak@nationalgrid.com \n \n \nTimothy J. Martin* \nPrincipal Program Manager – Wholesale Market \nStrategy \nNew England Regulation & Pricing \nNational Grid \n170 Data Drive \nWaltham, MA 02451 \nTel. (508) 244-7940 \nEmail: timothy.martin@nationalgrid.com \n \nNHT \n \nTravis M. Contratto* \nPrincipal Attorney – Federal Regulatory Affairs \nNextEra Energy Inc. \n801 Pennsylvania Avenue N.W., Suite 220 \nWashington, D.C. 20004 \nTel: (202) 904-5928 \nEmail: travis.contratto@nee.com \n \n \nEvan Yager* \nPresident \nNew Hampshire Transmission, LLC \n13 Executive Park Drive \nClifton Park, NY 12065 \nTel: (607) 221-8223 \nEmail: Evan.Yager@nexteraenergy.com"},{"page":8,"startToken":2154,"endToken":2516,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 8 of 99 \n \n \n \nVTransco \n \nLamiya N. Rahman* \nBlank Rome LLP \n1825 Eye Street N.W. \nWashington, D.C. 20006 \nTel: (202) 420-2662 \nEmail: lamiya.rahman@blankrome.com \n \n \n \nAlison Milbury Stone* \nSenior Legal Counsel \nVermont Transco LLC \n366 Pinnacle Ridge Road \nRutland, VT 05701 \nTel: (802) 712-5064 \nEmail: astone@velco.com \n \n \nNEPOOL \n \nEric K. Runge, Esq.* \nCounsel for NEPOOL \nDay Pitney LLP \nOne Federal Street \nBoston, MA  02110 \nTel:  (617) 345-4735 \nEmail: ekrunge@daypitney.com \n \n \n \nDavid Burnham \nVice Chair, NEPOOL Transmission Committee \nDirector, Transmission Policy \nEversource Energy \n56 Prospect Street \nHartford, CT 06103 \nTel: (860) 728-4506 \nEmail: david.burnham@eversource.com  \n \n \n*Persons designated for service.10 \n \nII. \nSTANDARD OF REVIEW \nThe Tariff Revisions are submitted pursuant to section 205 of the FPA, which “gives a utility \nthe right to file rates and terms for services rendered with its assets.”11  Under section 205, the \nCommission “plays ‘an essentially passive and reactive’ role”’12 whereby it “can reject [a filing] only \nif it finds that the changes proposed by the public utility are not ‘just and reasonable.’”13  The \nCommission limits this inquiry “into whether the rates proposed by a utility are reasonable – and [this \ninquiry does not] extend to determining whether a proposed rate schedule is more or less reasonable \nthan alternative rate designs.”14  The revisions filed herein “need not be the only reasonable \n \n10 The Filing Parties respectfully request a waiver of Section 385.203(b)(3) of the Commission’s regulations to allow \nthe inclusion of more than two persons on the service list in this proceeding. \n11 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002).   \n12 Id. at 10 (quoting City of Winnfield v. FERC, 744 F.2d 871, 876 (D.C. Cir. 1984)).   \n13 Id. at 9.  \n14 Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (“Cities of Bethany”); see ISO New Eng. Inc., 114 \nFERC ¶ 61,315, at P 33 & n.35 (2006) (citing Pub. Serv. Co. of N.M. v. FERC, 832 F.2d 1201, 1211 (10th Cir. 1987); \nCities of Bethany at 1136)."},{"page":9,"startToken":2516,"endToken":3036,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 9 of 99 \n \n \n \nmethodology, or even the most accurate.”15  As a result, even if an intervenor or the Commission \ndevelops an alternate proposal, the Commission must accept this section 205 filing if it is just and \nreasonable.16  \nIII. \nBACKGROUND AND EXECUTIVE SUMMARY \nA. \nBackground \nThe Show Cause Order is one of six show cause orders that the Commission simultaneously \nissued to all six RTO and Independent System Operators to address large and co-located load issues.  In \nthe Show Cause Order, the Commission directed ISO-NE and the PTOs, within 60 days of the order, to \neither:  \n(1) \nshow cause as to why the Tariff remains just and reasonable and not unduly discriminatory or \npreferential without provisions addressing:   \n(a) \nthe application process, study procedures, and ongoing operational requirements that \napply to Eligible Customers seeking transmission service on behalf of large loads;17  \n(b) \nadditional transparency concerning the network upgrade costs to provide transmission \nservice to Eligible Customers on behalf of large loads, a pro forma cost recovery \nagreement between ISO-NE, the relevant transmission owner and Eligible Customer \ntaking transmission service on behalf of the large load to mitigate the risk of cost shifting \namong transmission customers, and a mechanism to ensure such payments are \nappropriately credited towards transmission owners’ transmission revenue \nrequirements consistent with the Commission’s cost-of-service regulations;  \n(c) \nthe rates, terms, and conditions of service that apply to co-location arrangements;  \n(d) \ntransmission services that reflect Eligible Customers taking transmission service on \nbehalf of co-located loads, load with behind the meter generation, and flexible large \n \n15 Oxy USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) (citing Cities of Bethany at 1136).   \n16 Cf. S. Cal. Edison Co., 73 FERC ¶ 61,219, at 61,608 n.73 (1995) (“Having found the Plan to be just and reasonable, \nthere is no need to consider in any detail the alternative plans proposed by the Joint Protesters.” (citing Cities of \nBethany at 1136)).   \n17 ISO-NE’s Tariff defines an Eligible Customer as:  “(i) Any entity that is engaged, or proposes to engage, in the \nwholesale or retail electric power business is an Eligible Customer under the [Tariff].  (ii) Any electric utility \n(including any power marketer), Federal power marketing agency, or any other entity generating electric energy for \nsale or for resale is an Eligible Customer under the [Tariff]. . . .  (iii) Any end user taking or eligible to take unbundled \ntransmission service or Local Delivery Service pursuant to a state requirement that the Transmission Owner with \nwhich that end user is directly interconnected or the distribution company having the service territory in which that \nentity is located (if that entity is a retail customer) offer the transmission service or Local Delivery Service, or pursuant \nto a voluntary offer of such service by the Transmission Owner with which that end user is directly interconnected, or \nthe distribution company having the service territory in which that entity is located (if that entity is a retail customer) \nis an Eligible Customer under the [Tariff].”  Tariff §§ I.2 (Rules of Construction; Definitions), I.2.2 (Definitions)."},{"page":10,"startToken":3036,"endToken":3510,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 10 of 99 \n \n \n \nloads that are willing and able to limit their use of the transmission system under certain \nconditions; and \n(e) \nthe rates, terms, and conditions of service applicable to interconnection customers \nserving electrically proximate large load or co-located load; or  \n(2) \nexplain what changes to the Tariff would remedy the identified concerns if the Commission \nwere to determine that the Tariff has in fact become unjust and unreasonable or unduly \ndiscriminatory or preferential and, therefore, proceeds to establish a replacement Tariff.18   \n \nThe Commission also recognized that ISO-NE and/or the PTOs (to the extent the matters \naddressed in the Show Cause Order implicate aspects of the Tariff over which the PTOs have the filing \nrights) may elect to address some or all of the issues discussed in the Show Cause Order by proposing \nrevisions to the Tariff pursuant to their applicable FPA section 205 filing rights.19  The Commission \nstrongly encouraged this.20  The Commission stated that it would consider requests to hold, for up to 90 \ndays, all or certain aspects of the Show Cause Order proceeding in abeyance, including the deadline to \nrespond to the Show Cause Order, to provide ISO-NE and the PTOs time to work through the \nstakeholder processes to develop FPA section 205 filings to revise the Tariff to address the issues raised \nin the Show Cause Order.21  Accordingly, on August 3, 2026, ISO-NE and the PTO AC (on behalf of \nthe PTOs) submitted a motion to hold the Show Cause Order proceeding in abeyance.  The Commission \ngranted that motion on August 14, 2026.22  The 90-day abeyance allowed ISO-NE, the PTOs, and other \nstakeholders an opportunity to develop region-specific solutions to the concerns raised in the Show \nCause Order.    \nIn Section IV of this transmittal letter, ISO-NE and the PTOs explain how the Tariff \nRevisions address all of the Commission’s concerns in the Show Cause Order.  Additionally, \nSection V of this transmittal letter contains answers to the briefing questions that the Commission \nposed in the Show Cause Order.23 \n \nIn addition, in the Show Cause Order, the Commission recognized that the relative speed and \nconcentration at which large loads are seeking to interconnect appears to be outpacing the addition \nof new generation, which in turn heightens reliability risks and drives up costs to ratepayers.24  The \nCommission expressed its concern that ISO-NE and load serving entities are unable to plan adequate \n \n18 Show Cause Order at P 32. \n19 Id. at P 35. \n20 Id. \n21 Id. at P 36. \n22 ISO New Eng. Inc., 196 FERC ¶ 61,132 (2026). \n23 See Show Cause Order at P 124 (stating that any filings or Tariff changes submitted in response to the Show Cause \nOrder should address the Commission’s briefing questions). \n24 Id. at P 118."},{"page":11,"startToken":3510,"endToken":3958,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 11 of 99 \n \n \n \ngeneration to serve all load at the pace such load seeks to connect.25  Accordingly, the Commission \ndirected ISO-NE to submit a detailed informational report on any proposals under consideration in \nits stakeholder process to address the issue of resource adequacy to serve new large loads.26  The \nCommission strongly encouraged new proposals to the extent necessary to address these concerns.  \nThe ISO submitted its Informational Report on July 20, 2026.  In that report, the ISO explained that \ntwo related actions are necessary: requiring new large loads to “bring their own” incremental new \ncapacity (referred to in the Informational Report as new “generation”), and excluding certain new \nlarge loads from the load-side requirements of the capacity market (i.e., the Installed Capacity \nRequirement).  Accordingly, as explained in Section IV.E of this transmittal letter, the Tariff \nRevisions include language providing notice that Large Loads must bring their own new capacity, and \nthat certain large loads will be excluded from the capacity market’s Installed Capacity Requirement. \n \nISO-NE and the PTOs respectfully request that the show cause proceeding be terminated in \nfull if the Commission accepts this section 205 filing.  In support of this request, the description of \neach proposed Tariff Revision indicates which preliminary finding in the Show Cause Order is \nresolved by the Tariff Revision.    \n \nB. \nExecutive Summary \n1. \nThe Tariff Revisions Address the Five Categories of Reform in the Show \nCause Order \nThe Filing Parties submit that the Tariff Revisions address all of the Commission’s concerns in \neach of the five categories of reform of the Show Cause Order (i.e., efficient study processes, co-location \nrules, flexible load service, generation studies, and cost transparency).     \n   \na. Efficient Study Processes \nTo address this category of reform, the Tariff Revisions include a definition of Large Load, \nwhich is based on the characteristics of ISO-NE’s transmission system.  The definition includes a 50 \nMW load size, and a 60 kV interconnection voltage threshold.27  The ISO also developed exclusions \nfrom the definition based on the characteristics of the load, exclusions in other regions, and stakeholder \nfeedback.  Importantly, as described in Section IV.B.1 of this transmittal letter, the Tariff Revisions \ninclude language that accommodates the transition of a load into the definition of Large Load and \naccommodates existing commercial arrangements. \n \nIn addition, the Tariff Revisions include an application process that applies to Large Load \nEligible Customers seeking transmission service on behalf of Large Loads.  This process requires a non-\nrefundable application fee and sufficient readiness requirements to deter duplicative or speculative \n \n25 Id. \n26 Id. at P 119. \n27 See Section IV.A.1 of this transmittal letter."},{"page":12,"startToken":3958,"endToken":4402,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 12 of 99 \n \n \n \nrequests for transmission service.  The Tariff Revisions also include study procedures that address (1) \nevaluating whether a large load may be interconnected to the transmission system and served by the \nEligible Customer, and (2) determining whether network upgrades are necessary to provide \ntransmission service.  The study process  includes electromagnetic transient (“EMT”) studies, and the \nevaluation of alternative transmission technologies as potential solutions to accommodate requests for \ntransmission service.   \n \nMoreover, the Tariff Revisions include operational requirements for Large Load Transmission \nCustomers seeking transmission service on behalf of Large Loads, including the provision of hourly \nforecasts, telemetry data, communication channels, installation of equipment to enable the ISO to \nmonitor the impacts of Large Loads, ramp-rate and ride-through requirements, and requirements for \nprotection systems to limit withdrawals from the transmission system.  Under the operational \nrequirements, ISO-NE will also be able to coordinate the remote disconnection of a Large Load to \nmaintain reliability of the transmission system.   \n \nFinally, the Tariff Revisions include a pro forma Large Load Transmission Service Agreement, \nas well as a pro forma Large Load System Impact Study Agreement and a pro forma Large Load \nFacilities Study Agreement.   \n \nb. Co-location Rules \nTo address this category of reform, the ISO is proposing a definition of Behind-the-Meter \nGeneration along with a netting threshold of zero MW for Large Loads.  Effectively, the Tariff \nRevisions prohibit the netting of a Large Load with Behind-the-Meter Generation for settlement of \nwholesale services.  In addition, as explained in the next category of reform below, the ISO has \ndeveloped transmission services that recognize the ability of Large Loads (including co-located loads) \nto limit withdrawal from the transmission system under certain conditions. \n \nc. Flexible Load Service \nThe Tariff Revisions include three new transmission services: firm transmission service for \nLarge Loads that bring their own new capacity and have completed network upgrades; interim \ntransmission service (i.e.,, non-firm transmission service for Large Loads that are in the process of \nmeeting the requirements for firm service), and non-firm transmission service for flexible Large Loads \nthat are willing and able to limit their use of the transmission system under certain conditions.   \n \nIn building the framework for these new transmission services, ISO-NE was able to capitalize \non its DARD model,28 which will be used to register Large Loads.  This model allows the use of current \nISO forecasting, telemetry, and dispatch tools, requiring minimal adaptation and resulting in expedited \napplication.  Flexibility for non-firm transmission services will be achieved through a price-based \nre-dispatch mechanism.  Specifically, all or a portion of a Large Load’s non-firm transmission \n \n28 See Section IV.B.3.a of this transmittal letter."},{"page":13,"startToken":4402,"endToken":4891,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 13 of 99 \n \n \n \nservice will be re-dispatched when the Large Load’s applicable Locational Marginal Price \n(“LMP”) exceeds a Large Load Re-Dispatch Price of $250/MWh.29   \nd. Generation Studies \nTo address this category of reform, the Tariff Revisions include a definition of Electrically \nProximate Large Load, which is appropriately tailored to New England’s tightly networked \ntransmission system (i.e., an injection into the New England transmission system from a Large \nLoad Electrically Proximate Generator that is one or more substations away from a corresponding \nElectrically Proximate Large Load would likely not fully flow to the Electrically Proximate Large \nLoad in a manner that is effectively as if the Electrically Proximate Large Load and Large Load \nElectrically Proximate Generator were located at the same point, or connected radially).  \nAdditionally, the ISO and the PTOs have developed rules for the interconnection of Large Load \nCo-Located Generators and Large Load Electrically Proximate Generators.  As explained in \nSection IV.C of this transmittal letter, the interconnection studies for these generators may be \nconducted concurrently with a Large Load System Impact Study.   \ne. Cost Transparency \nTo address this category of reform, the Tariff Revisions require the ISO to provide, develop, \nmaintain, and post on its website, in an easily accessible, searchable and fillable format: (1) a \ncumulative list reflecting the Large Load Network Upgrades identified for each Large Load, \ncategorized by upgrade type; and (2) costs estimates for each identified Large Load Network \nUpgrade for each Large Load.  In addition, as described in Section IV.D.2 of this transmittal letter, \nthe PTOs have developed a pro forma Large Load Cost Recovery Agreement.  The agreement \ngoverns the construction of, cost responsibility for, and crediting of revenues associated with \nCommission-jurisdictional transmission facilities.  As indicated below, ISO-NE and the PTOs \nconsent to the Commission’s exercise of authority to modify and/or sever any element of the \nproposed Tariff changes with respect to these cost recovery provisions and agree to make any \nnecessary compliance filing. \n2. \nThe Tariff Revisions Address Resource Adequacy Concerns \nTo complement the Tariff Revisions that address the five categories of reform, ISO-NE is \nproposing revisions to address the Commission’s resource adequacy concerns.  The ISO \nappreciates that, in addition to its continuing work to ensure resource adequacy, it must explicitly \nconsider the potential impact of large loads on the markets.  While those loads have yet to \nmaterialize in New England, as described in Section IV.E of this transmittal letter, the ISO \nbelieves that two related actions are necessary: requiring new large loads to “bring their own” \nincremental new capacity, and excluding new large loads from the load-side requirements of the \ncapacity market (i.e., the Installed Capacity Requirement).  Accordingly, the Tariff Revisions \ninclude language providing notice that Large Loads must bring their own new capacity, and that \n \n29 See Section IV.B.3.b of this transmittal letter and Testimony of Dennis Cakert."},{"page":14,"startToken":4891,"endToken":5372,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 14 of 99 \n \n \n \ncertain large loads will be excluded from the capacity market’s Installed Capacity Requirement.  As \nthese are complex concepts, the Tariff Revisions outline these provisions in broad terms, with the \nobjective of giving large loads notice of this structure.  The region will work together over the \ncoming months to expand on the concepts and will make a separate filing with the Commission \nnext year. \n \nIn the sections below, the Filing Parties have organized the Tariff Revisions by the party with \nthe section 205 rights. Sections IV.A, IV.B and IV.E cover the Tariff Revisions offered by ISO-NE \npursuant to its section 205 filing rights.  Section IV.C describes the portion of the Tariff Revisions filed \njointly by the ISO and the PTOs, Section IV.D contains the Tariff Revisions offered by the PTOs \ncollectively, as well as the Tariff Revisions made by individual PTOs.  Section V contains answers to \nthe Commission’s briefing questions.  The final sections, offered jointly, are Section VI (the stakeholder \nprocess undertaken by the region); Section VII (a request for a waiver of 60-days’ prior notice, effective \ndate, and extended comment period); Section VIII (additional supporting information, as required by \nthe Commission’s regulations); and Section IX (a brief conclusion).    \n \nIV. \nDESCRIPTION OF THE PROPOSED TARIFF REVISIONS TO ADDRESS THE \nCOMMISSION’S CONCERNS IN THE SHOW CAUSE ORDER \nAs fully described in Sections IV.A, IV.B, and IV.C of this transmittal letter, ISO-NE and \nthe PTOs are proposing several Tariff Revisions in response to the Show Cause Order.  In addition, \nISO-NE is proposing Tariff Revisions to address the Commission’s resource adequacy concerns.  \nSpecifically: \n• In response to the Show Cause Order, under the joint section 205 rights of the ISO and the \nPTOs, Tariff Revisions (described in Section IV.A of this transmittal letter) are proposed \nin Section I.2.2 of the Tariff (Definitions)  \n \n• In response to the Show Cause Order, under the ISO’s section 205 rights, Tariff Revisions \n(described in Section IV.B of this transmittal letter) are proposed by the ISO in the \nfollowing Sections of the Tariff: \no Preamble to new Part II.J of the OATT \no New Section II.56 of the OATT \no New Section II.57 of the OATT \no New Section II.58 of the OATT \no New Section II.60 of the OATT \no New Section II.61 of the OATT \no New Section II.63 of the OATT \no New Attachments S (Large Load Transmission Service Agreement), T (Large Load \nSystem Impact Study Agreement), and U (Large Load Facilities Study Agreement) \nto the OATT \no Revisions in Schedules 2, 16, and 17 of the OATT \no Conforming revisions in Sections II.20.2 and II.20.3 of the OATT  \no Revisions in Sections III.1, III.2, and III.15 of the Tariff"},{"page":15,"startToken":5372,"endToken":5815,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 15 of 99 \n \n \n \n \n• In response to the Show Cause Order, under the joint section 205 rights of the ISO and the \nPTOs, Tariff Revisions (described in Section IV.C of this transmittal letter) are being \nproposed by the ISO and the PTOs in Schedules 22 and 23 to the OATT (respectively, \nLarge \nGenerator \nInterconnection \nProcedures \n(“LGIP”) \nand \nSmall \nGenerator \nInterconnection Procedures (“SGIP”))  \n \n• In response to the Show Cause Order, under the PTOs’ joint section 205 rights, Tariff \nRevisions (described in Section IV.D of this transmittal letter) are proposed in the \nfollowing Sections of the Tariff: \no New Section II.62 of the OATT30 \no New Attachment V of the OATT (Cost Recovery Agreement) \no Revisions to Schedule 1 of the OATT \no New Schedule 9A of the OATT \no Revisions to Schedule 21 Common \no Conforming revisions in Section II.21.2 of the OATT \n \nIn the event the Commission deems it necessary, and to help facilitate the Commission’s \nacceptance of this filing without delay, ISO-NE and the PTOs provide notice that they consent to \nthe Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff \nchanges with respect to the cost recovery provisions to the extent necessary and permitted under \nFPA section 205 and NRG Power Marketing, LLC v. FERC.31  In such event, ISO-NE and the \nPTOs consent to make a compliance filing consistent with such directive. \n• In response to the Show Cause Order, under the PTOs’ individual Section 205 rights, Tariff \nRevisions (described in Section IV.D.6) of this filing letter are proposed to certain PTOs’ \nrespective Local Service Schedules in the following Sections of the OATT: \no Schedule 21-CMP (proposed by CMP) \no Schedule 21-CTMEEC (proposed by CTMEEC) \no Schedule 21-ES (proposed by Eversource) \no Schedule 21-FG&E (proposed by Fitchburg) \no Schedule 21-GMP (proposed by GMP) \no Schedule 21-NEP (proposed by National Grid) \no Schedule 21-NHT (proposed by NHT) \no Schedule 21-RIE (proposed by RIE) \no Schedule 21-UI (proposed by UI) \no Schedule 21-UES (proposed by Unitil) \n \n30 Included in new Part II.J of the OATT. \n31 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017); see also N.Y. Indep. Sys. Operator, Inc., 188 \nFERC ¶ 61,051, at P 22 n.36 (2024) (“The United States Court of Appeals for the District of Columbia Circuit has \nheld that, in certain circumstances, the Commission has ‘authority to propose modifications to a utility’s [FPA section \n205] proposal if the utility consents to the modifications.’” (alteration in original) (citing NRG Power Mktg., 862 F.3d \nat 114-15))."},{"page":16,"startToken":5815,"endToken":6215,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 16 of 99 \n \n \n \no Schedule 21-VTransco (proposed by VTransco) \no Schedule 21-VP (proposed by Versant) \n \n• To address the resource adequacy concerns that the Commission expressed in the Show \nCause Order, under the ISO’s section 205 rights, Tariff Revisions (described in \nSection IV.E of this transmittal letter) are proposed by the ISO in the following Sections \nof the Tariff: \no New Section II.59 of the OATT \no Revisions in Section III.12.1 of the Tariff \n \nA. \nTariff Revisions in Section I.2.2 of the Tariff (Definitions) \nIn response to the Show Cause Order, several definitions are being added in Section I.2.2 \nof the Tariff.32   \n \n1. Definition of Large Load \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it lacks a definition of large load, as a new category of load.33  \nThe Commission stated that an appropriate definition, including a load size and interconnection \nvoltage threshold, should be based on the characteristics of ISO-NE’s transmission system.  In \nresponse, ISO-NE proposes to add the following definition of Large Load in Section I.2.2 of the \nTariff: \nLarge Load is a commercial or industrial customer, located at a single site \nbehind one or more points of delivery, and that has a gross peak demand of 50 \nMW or greater, relative to its exempt demand as described in Part II.J of the \nOATT, interconnects to the transmission system, either directly or through a \nsystem primarily designed to serve the customer, at a voltage level of greater \nthan 60 kV.  Excluded from this definition are:  electrical energy support \nresources such as storage resources (e.g., pumped storage and battery energy \nstorage systems); emergency and municipal services resources such as \nhospitals, major medical complexes and water treatment facilities; \ntransportation and infrastructure resources other than dedicated electric vehicle \ncharging facilities, such as railroads and airports; and campus facilities that do \nnot have an aggregate exceeding 50 MW of dedicated computational, industrial \nor commercial process loads each 1 MW or greater, including but not limited to \na university campus without a major data center.   \n \n32 The ISO and the PTOs have joint section 205 rights over definitions used in Sections of the Tariff for which they \neach have section 205 rights. \n33 Show Cause Order at P 56."},{"page":17,"startToken":6215,"endToken":6744,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 17 of 99 \n \n \n \nThe definition includes a 50 MW load size which is reasonable for the New England \ntransmission system.  Specifically, based on survey response data and stakeholder discussions, the ISO \nbelieves that 50 MW strikes a reasonable balance between capturing loads with unique reliability \nimpacts while excluding loads in the 20 MW to 50 MW range that do not raise the same concerns.  As \nexplained in Section IV.B.1 of this transmittal letter, the 50 MW threshold will not consider existing \nexempt demand (i.e., the higher of (i) the maximum observed hourly gross MW load value in the ten \nyears prior to June 18, 2026; or (ii) a MW value specified in an existing service or operating agreement \nwith the applicable utility or the ISO as of June 18, 2026).34   \nThe definition also includes an interconnection voltage threshold of 60 kV which is appropriate \nfor New England because, while voltage levels below 60 kV are not expected to be able to support a 50 \nMW load size,35 the New England transmission system has some facilities below 69 kV nominal that \nmay be able to support a 50 MW load.  The Large Load definition applies to commercial and industrial \ncustomers, which includes, but is not limited to, manufacturing and computational loads.  The \nexclusions from the definition of Large Load were developed based on the characteristics of the load, \nexclusions in other regions, and stakeholder feedback.  Specifically, the exclusions cover loads related \nto electrical energy support, the delivery of critical services, and the support of critical infrastructure.  In \naddition, the exclusions consider campuses with mixed-use loads that are more residential in nature (i.e., \nloads that have different characteristics when compared to loads captured by the Large Load definition).  \nExemptions to the definition of Large Load that accommodate existing commercial arrangements are \ncontained in the preamble of new Part II.J of the OATT, and they are explained in Section IV.B.1 of \nthis transmittal letter. \n2. \nDefinition of Behind-the-Meter Generation \nIn the Show Cause Order, the Commission points out that the Tariff does not define the term \n“Behind the Meter Generation.”36  Accordingly, ISO-NE proposes to add the following definition of \nBehind-the-Meter Generation in Section I.2.2 of the Tariff: \nBehind-the-Meter Generation is generation directly connected to end-use \ncustomer load and located behind the end-use customer’s Retail Delivery \nPoint that reduces the amount of energy that would otherwise have been \nproduced on the electricity network in the New England Control Area, and \nis not separately metered in wholesale markets from the end-use customer \nload. \nIn addition, in the Show Cause Order, the Commission preliminarily found that the Tariff is \nunjust and unreasonable because it allows load with Behind-the-Meter Generation to net its Behind-the-\n \n34 The proposed framework for determining exempt demand is intended to respect existing commercial arrangements \nin which a load has the authority to withdraw a MW amount greater than the MW amount historically withdrawn from \nthe transmission system. \n35 This definition addresses the Commission’s concerns in PP 55-56 of the Show Cause Order.   \n36 Show Cause Order at P 87."},{"page":18,"startToken":6744,"endToken":7169,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 18 of 99 \n \n \n \nMeter Generation against its load for purposes of calculating Regional Network Service charges.37  To \naddress the Commission’s finding, and in keeping with the focus of the Show Cause Order, the ISO \nproposes a netting threshold of zero MW (which applies only to Large Loads).  In effect, the Tariff \nRevisions in Section III.1.10.5A(d)(i) of the Tariff provide that the Assigned Meter Reader for a Large \nLoad must “[s]ubmit Revenue Quality Metering for hourly and monthly settlement that represents gross \ndemand quantities for the Large Load, such that the Large Load’s Revenue Quality Metering is not \nnetted by other physical load, supply, or Behind-the-Meter Generation.”  Thus, this provision effectively \nprohibits the netting of a Large Load with Behind-the-Meter Generation for settlement of wholesale \nservices. \n3. \nDefinition of Electrically Proximate Large Load \nIn the Show Cause Order, the Commission stated that, for purposes of the order, \n“electrically proximate large load” means a large load, as defined in the order, that is \nsufficiently electrically close to the interconnection customer’s requested point of \ninterconnection, such that the impact on the transmission system of the combination of the \ngenerating facility and the load, with the exception of the transmission facilities between the \ntwo, will be effectively the same as if they were located at the same substation (e.g., large load \nthat is located no more than two substations away from the generating facility).38 The \nCommission stated that it will consider proposed revisions to this definition that ensure it is \nappropriately tailored to New England’s transmission system.39  Accordingly, ISO-NE \nproposes to add the following definition of Electrically Proximate Large Load in Section I.2.2 \nof the Tariff: \nElectrically Proximate Large Load is a configuration where a Large \nLoad’s Point of Delivery is located at (or directly connected radially through \ndedicated facilities to) the same substation and voltage level as a Generating \nFacility’s Point of Interconnection (or to the Generating Facility’s radially \ndedicated facilities that connect between the substation and its Point of \nInterconnection), \nsuch \nthat \nthe \nGenerating \nFacility’s \nPoint \nof \nInterconnection is sufficiently electrically close to the associated Large \nLoad’s Point of Delivery, such that the impact on the transmission system \nof the combination of the Generating Facility and the Large Load, with the \nexception of the transmission facilities between the two, will be effectively \nthe same as if they were located at the same point. \n \n37 Id. at P 100. \n38 Id. at P 110. \n39 Id."},{"page":19,"startToken":7169,"endToken":7587,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 19 of 99 \n \n \n \nThis definition is appropriately tailored to New England because the New England \ntransmission system is tightly networked.40  As a result, an injection into the transmission system \nfrom a Large Load Electrically Proximate Generator that is one or more substations away from a \ncorresponding Electrically Proximate Large Load would likely not fully flow to the Electrically \nProximate Large Load in a manner that is effectively as if the Electrically Proximate Large Load \nand Large Load Electrically Proximate Generator were located at the same point. \n4. \nOther Definitions \nIn Section I.2.2 of the Tariff, ISO-NE is also adding the following defined terms, which are used \nin the Tariff Revisions that address the Commission’s concerns in the Show Cause Order: \nCo-Located Large Load is a configuration where a Large Load’s Point of \nDelivery is located on the Interconnection Facilities of an existing or planned \nGenerating Facility.  \nFirm Contract Demand Service is a type of transmission service for Large \nLoads described in Section II.57.1.1 of the OATT.  \nInterim Contract Demand Service is a type of transmission service for Large \nLoads described in Section II.57.1.2 of the OATT.  \nLarge Load Affected Party is the entity that owns, operates or controls a Large \nLoad Affected System, or any other entity that otherwise may be a necessary \nparty to the Large Load study process.  \nLarge Load Affected System is any electric system that is outside the New \nEngland Control Area that may be affected by the proposed provision of \ntransmission service to a Large Load.  \nLarge Load Base Cases are the set of initial cases used to evaluate the impact \nof Large Loads, including:  (1) the latest available case used for performing \nNeeds Assessments; and (2) the latest available case used for a completed \nCluster Study or an ongoing Cluster Study.  \nLarge Load Co-Located Generator is a Generating Facility that is associated \nwith a Co-Located Large Load through a Non-Firm Large Load Generator \nArrangement.  \nLarge Load Contingent Facilities are those unbuilt Interconnection Facilities, \nLarge Load Interconnection Facilities, Network Upgrades, and Large Load \nNetwork Upgrades or a transmission project that is planned or proposed for the \n \n40 This definition addresses the Commission’s concerns in P 110 of the Show Cause Order.  In the Show Cause Order, \nthe Commission recognized that “the unique features of ISO-NE’s transmission system may warrant consideration of \na more limited definition of electrically proximate.”  Id. at P 113 n.268."},{"page":20,"startToken":7587,"endToken":7957,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 20 of 99 \n \n \n \nNew England Transmission System upon which the Large Load Transmission \nCustomer’s costs, timing, and study findings are dependent, and if delayed or \nnot built, could cause a need for restudies of the Large Load Transmission \nService Application or a reassessment of the Large Load Interconnection \nFacilities and/or Large Load Network Upgrades and/or costs and timing. \nLarge Load Cost Recovery Agreement is the agreement in the form of \nAttachment V to the OATT. \nLarge Load Distribution Upgrades are the additions, modifications, and \nupgrades to the Large Load Interconnecting Transmission Owner’s distribution \nsystem (i.e., facilities and equipment used to transmit electricity to ultimate \nusage points such as homes and industries directly from nearby generators or \nfrom interchanges with higher voltage transmission networks which transport \nbulk power over longer distances) at or beyond the Point of Delivery to facilitate \ninterconnection of the Large Load and render the transmission service necessary \nto serve the Large Load. Large Load Distribution Upgrades do not include \nLarge Load Interconnection Facilities. \nLarge Load Electrically Proximate Generator is a Generating Facility that is \nassociated with an Electrically Proximate Large Load through a Non-Firm \nLarge Load Generator Arrangement.  \nLarge Load Eligible Customer is the Eligible Customer that submits an \napplication for Firm Contract Demand Service or Non-Firm Contract Demand \nService on behalf of a Large Load.  \nLarge Load Entity is the entity that owns or controls the Large Load.  \nLarge Load Facilities Study is the study for Large Loads conducted pursuant \nto Section II.60 of the OATT.  \nLarge Load Facilities Study Agreement is the agreement described in Section \nII.60 of the OATT.  \nLarge Load Internal Affected Party is the entity that owns, operates or \ncontrols a Large Load Internal Affected System, or any other entity operating \nwithin the New England Control Area that otherwise may be a necessary party \nto the Large Load study process.  \nLarge Load Internal Affected System is any electric system that is within the \nNew England Control Area that may be affected by the proposed provision of \nservice to the Large Load.  \nLarge Load Interconnection Facilities are Large Load Interconnecting \nTransmission Owner’s Interconnection Facilities and Large Load Transmission"},{"page":21,"startToken":7957,"endToken":8339,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 21 of 99 \n \n \n \nCustomer’s \nInterconnection \nFacilities. \nCollectively, \nLarge \nLoad \nInterconnection Facilities include all facilities and equipment between the Large \nLoad and the Point of Delivery, including any modifications, additions or \nupgrades that are necessary to physically and electrically interconnect the Large \nLoad to the Administered Transmission System. Large Load Interconnection \nFacilities are sole use facilities and shall not include Distribution Upgrades, \nStand Alone Network Upgrades or Large Load Network Upgrades. \nLarge Load Interconnecting Transmission Owner is the Transmission \nOwner that owns, leases or otherwise possesses the controlling interest in the \nportion of the Administered Transmission System at the Point of Delivery for \nthe Large Load.  \nLarge Load Interconnecting Transmission Owner’s Interconnection \nFacilities are all facilities and equipment owned, controlled, or operated by \nLarge Load Interconnecting Transmission Owner from the Large Load Point of \nChange of Ownership to the Point of Delivery as identified in Appendix A to \nthe Large Load Transmission Service Agreement, including any modifications, \nadditions or upgrades to such facilities and equipment. Large Load \nInterconnecting Transmission Owner’s Interconnection Facilities are sole use \nfacilities and shall not include Large Load Distribution Upgrades and Large \nLoad Network Upgrades. \nLarge Load Material Modification is defined in Section II.60 of the OATT.  \nLarge Load Network Upgrades are those upgrades to the New England \nTransmission System, any Large Load Affected Systems and Large Load \nInternal Affected Systems as identified in a Large Load System Impact Study.   \nLarge Load Point of Change of Ownership is the point, as set forth in \nAppendix A to the Large Load Transmission Service Agreement, where Large \nLoad Transmission Customer’s Interconnection Facilities connect to the Large \nLoad Interconnecting Transmission Owner’s Interconnection Facilities. \nLarge Load Queue Position is the order of a valid Large Load Transmission \nService Application in the New England Control Area, relative to all other \npending Large Load Transmission Service Application(s) in the New England \nControl Area, that is established based upon the date and time of receipt of such \napplication by the ISO.   \nLarge Load Re-Dispatch Price is $250/MWh.  \nLarge Load Scoping Meeting is the meeting between representatives of the \nISO, the Large Load Eligible Customer, and the Transmission Owner(s), or any \nLarge Load Internal Affected Party as deemed appropriate by the ISO in"},{"page":22,"startToken":8339,"endToken":8751,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 22 of 99 \n \n \n \naccordance with applicable codes of conduct and confidentiality requirements, \nconducted for the purpose of discussing the proposed Large Load Transmission \nService Application, exchanging information, and refining information and \nmodels provided by Large Load Eligible Customer.  \nLarge Load Service Commencement Date is the date transmission service is \nto begin pursuant to the terms of a Large Load Transmission Service Agreement \nthat has been executed or filed unexecuted.  \nLarge Load Site Control is the exclusive right to develop, construct, operate \nand maintain the Large Load.  Large Load Site Control may be demonstrated \nby documentation establishing that, over the expected term of the Large Load \noperations, the entity proposing the Large Load will hold ownership or other \nexclusive rights over the property allowing for the construction, operation and \nmaintenance of the Large Load in the form of either:  (a) fee simple ownership \nof real property; (b) an easement; (c) a valid written leasehold or other \ncontractual interest in real property; (d) a duly executed written contract to \npurchase, acquire an easement, a license or leasehold interest in real property; \nor (e) for any federal or state property, has filed applications for required permits \nor authorizations to construct, operate and maintain the Large Load.  \nLarge Load Study Cases are the cases defined in Section II.60.2 of the OATT.  \nLarge Load Sufficiently Under Construction is a load that is determined by \nthe ISO to have provided sufficient evidence that it received major permits \nnecessary for construction of the project, achieved project financing closing, \nordered major equipment necessary for the construction of the project, and has \nstarted construction activities on the project site. \nLarge Load System Impact Study is the study for Large Loads conducted \npursuant to Section II.60 of the OATT.  \nLarge Load System Impact Study Agreement is the agreement described in \nSection II.60 of the OATT.  \nLarge Load Transmission Customer is the Large Load Eligible Customer \nthat has completed the large load service application and study procedures set \nforth in Sections II.58 and II.60 of the OATT, and executed a Large Load \nTransmission Service Agreement and receives Firm Contract Demand Service, \nInterim Contract Demand Service, or Non-Firm Contract Demand Service on \nbehalf of a Large Load.  \nLarge Load Transmission Customer’s Interconnection Facilities are all \nfacilities and equipment, as identified in Appendix A of the Large Load \nTransmission Service Agreement, that are located between the Large Load and"},{"page":23,"startToken":8751,"endToken":9170,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 23 of 99 \n \n \n \nthe Large Load Point of Change of Ownership, including any modifications, \nadditions, or upgrades to such facilities and equipment necessary to physically \nand electrically interconnect the Large Load Transmission Customer to the \nAdministered Transmission System. Large Load Transmission Customer’s \nInterconnection Facilities may be sole use facilities or subject to shared use \npursuant to arrangements filed with and approved by the Commission. \nLarge Load Transmission Service Agreement is the form of transmission \nservice agreement applicable to a Large Load Transmission Service Application \npertaining to a Large Load, that is included as Attachment S to the OATT.   \nLarge Load Transmission Service Application is a Large Load Eligible \nCustomer’s application, in the form of [missing word?] available on the ISO \nwebsite.   \nNon-Firm Contract Demand Service is a type of transmission service for \nLarge Loads described in Section II.57.1.3 of the OATT.  \nNon-Firm Large Load Generator Arrangement is an arrangement between \na Co-Located Large Load or Electrically Proximate Large Load and the \napplicable Co-Located Generator or Electrically Proximate Generator which \nsupports the Large Load taking Interim Contract Demand Service or Non-Firm \nContract Demand Service. \nB. \nTariff Revisions in Response to the Show Cause Order Proposed by the ISO \nUnder the ISO’s Section 205 Rights \n1. \nPreamble in New Part II.J of the OATT – Transition to New Large Load \nTransmission \nServices \nto \nAccommodate \nExisting \nCommercial \nArrangements \nThe preamble in new Part II.J of the OATT – Transmission Services for Large Loads \nestablishes that Firm Contract Demand Service, Interim Contract Demand Service, and Non-Firm \nContract Demand Service will be provided by the ISO pursuant to the applicable terms and \nconditions of the OATT starting on June 1, 2028.41  As stated in this provision of the Tariff, these \nterms and conditions are not intended to supersede any applicable state or local laws or regulations \nnor do they authorize operations that would violate state or local laws and regulations.  As \nexplained in Section VII of this transmittal letter, the June 1, 2028 implementation date will \nprovide the ISO with sufficient time to develop the necessary software for the new transmission \nservices for Large Loads. \n \n \n41 In the preamble to new Part II.J of the OATT, ISO-NE has included language to establish that any capitalized terms \nused in new Part II.J of the OATT but not defined in Section I.2.2 of the Tariff will have the meanings ascribed to \nthem in Schedule 22 to the OATT."},{"page":24,"startToken":9170,"endToken":9631,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 24 of 99 \n \n \n \nTo address the Commission’s direction in the Show Cause Order that the ISO avoid \ndisrupting existing commercial arrangements,42 in the preamble to new Part II.J of the OATT, the \nISO has also included language that accommodates existing commercial arrangements as well as \nthe transition of a load into the definition of Large Load.  Specifically, under ISO-NE’s proposal, \nthe MW value of exempt demand for a load in operation or determined by the ISO to be a Large \nLoad Sufficiently Under Construction prior to June 18, 2026, shall be determined as the greater \nof:  (i) its measured maximum observed hourly gross peak in the 10 years prior to June 18, 2026; \nor (ii) the MW value specified in a service or operational agreement with the applicable utility or \nISO as of June 18, 2026.  Consistent with these parameters, as of the effective date of Part II.J of \nthe OATT, exempt demand will not be treated as a Large Load and will not be subject to Part II.J \nof the OATT.  \nIn addition, an existing load or a Large Load Sufficiently Under Construction as of Jun  18, \n2026, will be defined as a Large Load when its gross peak demand increases by 50 MW or more \nrelative to its exempt demand.  Transmission service for the exempt demand will transition to Firm \nContract Demand Service and the load will be subject to Section II.63 of the OATT (operational \nrequirements) but will be exempt from the application and study process in Part II.J of the OATT \nand the requirements of Section II.59 of the OATT (designation of capacity).  The increased \ndemand relative to exempt demand will be subject to all requirements in Part II.J of the OATT. \nFurthermore, a load that is not in operation or is determined by the ISO to not be a Large \nLoad Sufficiently Under Construction as of June 18, 2026, will be treated as a Large Load if and \nwhen it meets the Large Load definition.  Finally, a Large Load that is not in operation or is \ndetermined by the ISO to not be a Large Load Sufficiently Under Construction as of June 18, 2026, \nbut has a system impact study agreement with the applicable Large Load Interconnecting \nTransmission Owner prior to June 1, 2027, will not be subject to the study requirements of Part \nII.J of the OATT, but will be subject to all other requirements of Part II.J of the OATT.  This \napproach will obviate the need to restart study efforts performed consistent with the requirements \nof Part II.J of the OATT that are already in progress. \n \n42 Show Cause Order at P 35."},{"page":25,"startToken":9631,"endToken":9870,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 25 of 99 \n \n \n \nThe June 18, 2026 parameter in the Preamble of new Part II.J of the OATT does not impose \nany obligations.  Rather, it is a historical date used as a marker to establish the parameters for the \nexemptions to the Large Load definition.43  The exemptions are illustrated below. \nExempt demand can be illustrated with the following example: \n \n \nThe illustration below shows the transition of a load that, for example, does not exist on \nJune 18, 2026 (i.e., the historical date used as a parameter), so it has no exempt demand for the \npurpose of determining whether the Large Load 50 MW threshold has been met.  When \ndetermining if the load is a Large Load, all future load additions are measured cumulatively: \n \n \n \n \n43 The proposed June 18, 2026 parameter is similar to other parameters in the Tariff.  For example, Section \nIII.13.1.1.1.2 of the Tariff – Resources Never Previously Counted as Capacity, which was submitted as part of the \nISO’s February 15, 2007 Forward Capacity Market rules, established capacity participation parameters based on \ninvestments made prior to January 1, 2007.  See ISO New Eng. Inc., Filing Containing Revisions to Market Rules \nImplementing the FCM Settlement Agreement, Docket Nos. ER07-546-000 & ER07-547-000 (Feb. 15, 2007), \naccepted by ISO New Eng. Inc., 119 FERC ¶ 61,045, order on reh’g & clarification, 120 FERC ¶ 61,087 (2007)."},{"page":26,"startToken":9870,"endToken":10174,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 26 of 99 \n \n \n \nThe following chart summarizes the exemptions from the definition of Large Load: \n \n \n2. \nNew Section II.56 of the OATT – Establishment of New Large Load \nTransmission Services \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable or unduly discriminatory or preferential because it does not contain \nprovisions addressing with sufficient clarity and consistency transmission services that reflect a \ncustomer’s willingness and ability to limit its energy withdrawal from the transmission system \nunder certain conditions.44  The Commission specifically referred to the following transmission \nservices: (1) an interim non-firm network transmission service while network upgrades are being \nconstructed; and (2) permanent firm and non-firm contract demand transmission services \n(transmission service up to a specified MW quantity, i.e., the contract level, on a firm or non-firm \nbasis).45 \n \nIn response to the Show Cause Order, new Section II.56.1 of the OATT establishes that a \nLarge Load Eligible Customer may apply for the provision of Firm Contract Demand Service and \nNon-Firm Contract Demand Service, and the ISO will deem an application for Firm Contract \nDemand Service sufficient to support a related need for Interim Contract Demand Service.  These \nthree new transmission services for Large Loads are described in Section IV.B.3 of this transmittal \nletter.  New Section II.56.2 of the OATT establishes that upon completion of the application, study, \nand service agreement requirements set forth in new Section IV.58 of the OATT, each of the three \ntypes of transmission services must be taken and paid for by each Large Load Transmission \nCustomer that obtains the transmission service on behalf of a Large Load.  \n \n44 Show Cause Order at PP 3, 14, 91, 99. \n45 Id. at P 103."},{"page":27,"startToken":10174,"endToken":10697,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 27 of 99 \n \n \n \n3. \nNew Section II.57 of the OATT and New Section III.1.10.5A of the Tariff \n– Nature and Flexibility of New Large Load Transmission Services \nThe nature of each of the new types of transmission services is described in new Section II.57 \nof the OATT.  Under new Section II.57.1 of the OATT, Firm Contract Demand Service, Interim \nContract Demand Service, and Non-Firm Contract Demand Service are the transmission services that \nthe ISO provides to a Large Load Transmission Customer and allow a Large Load Transmission \nCustomer to serve a Large Load located in the New England Control Area.  New Sections II.57.1.1, \n57.1.2, and 57.1.3 of the OATT define each of the three transmission services as follows: \n \nFirm Contract Demand Service is a firm transmission service provided to a \nLarge Load Transmission Customer for a specific contracted MW value that \ncan never be exceeded. All identified Large Load Network Upgrades shall be \nin service before a Large Load Transmission Customer can be provided Firm \nContract Demand Service for a Large Load.  Firm Contract Demand Service \nshall be provided after meeting the requirements of Section II.59 of the OATT.46   \n \nInterim Contract Demand Service is a temporary, non-firm transmission \nservice provided to a Large Load Transmission Customer requesting Firm \nContract Demand Service before Large Load Network Upgrades are \ncompleted and placed into service, and before the Large Load Transmission \nCustomer has designated, or has caused to be designated, sufficient capacity \nresources to serve the Large Load pursuant to Section II.59 of the OATT. \nInterim Contract Demand Service shall be available for a term of no more \nthan seven years, or the length of time required to place the required Large \nLoad Network Upgrades in-service, whichever is longer.47 \n \nNon-Firm Contract Demand Service is non-firm transmission service \nprovided to Large Load Transmission Customers.  Large Load Transmission \nCustomers shall not be required to designate capacity resources for a Large \nLoad that is provided Non-Firm Contract Demand Service.48 \n \nNew Section II.57 of the OATT also establishes general terms and conditions for the three \ntransmission services.  First, new Section II.57.1.4 of the OATT establishes that a Large Load \nTransmission Customer receiving Interim Contract Demand Service or Non-Firm Contract \nDemand Service for a Large Load is subject to the price-based redispatch provisions of Section \nIII.1.10.5A of the Tariff (which are explained in Section IV.B.3.b of this transmittal letter).  \n \n46 New Section II.57.1.1 of the OATT.  As explained in Section IV.E of this transmittal letter, under new Section II.59 \nof the OATT, to receive the requested amount of Firm Contract Demand Service for a Large Load, the Large Load \nEligible Customer is required to designate, or cause to be designated, sufficient new capacity resources to meet the \nrequested amount of Firm Contract Demand Service for the Large Load. \n47 New Section II.57.1.2 of the OATT. \n48 New Section II.57.1.3 of the OATT."},{"page":28,"startToken":10697,"endToken":11195,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 28 of 99 \n \n \n \nSecond, new Section II.57.1.5 requires a Large Load Transmission Customer to comply with other \napplicable OATT requirements, including:  (i) obtaining or providing Ancillary Services pursuant \nto Section II.4 of the OATT;49 (ii) complying with all applicable creditworthiness and financial \nassurance requirements set forth by the ISO and Large Load Interconnecting Transmission Owner, \nincluding but not limited to the ISO New England Financial Assurance Policy and the ISO New \nEngland Billing Policy; and (iii) paying for real power losses associated with its scheduled service \nas calculated and recovered through the Loss Component of the Locational Marginal Prices \n(“LMP”) as further provided for in the ISO New England Operating Documents.50  Third, new \nSection II.57.2 of the OATT establishes the ISO and PTO responsibilities for the planning, \nconstruction, operation, and maintenance of the Pool Transmission Facility (“PTF”).51  Finally, \nunder new Section II.57.3 of the OATT, a Large Load Transmission Customer is entitled to use \neach of the three types of transmission services for any of the uses specified in Part II.J of the \nOATT.52 \n \na. \nDARD Model \nIn order for a Large Load Transmission Customer to be able to receive Firm Contract Demand \nService, Interim Contract Demand Service, or Non-Firm Contract Demand Service for a Large Load, \nunder new Section III.1.10.5A(a)(i) of the Tariff, the Large Load Transmission Customer shall (or shall \ncause to) register the Large Load as a DARD.53  Use of the DARD model allows for the timely and \nstreamlined implementation of non-firm transmission services because it utilizes current ISO \nforecasting, telemetry, and dispatch tools, requiring minimal adaptation that results in expedited \napplication.  Specifically, the DARD model integrates Large Loads into the market optimization \nsolution, simplifying dispatch timing, quantity and priority, which makes electronic dispatch \nsignificantly more efficient than manual dispatch.  The DARD model also allows a Large Load \nTransmission Customer to combine multiple services on behalf of a single Large Load, as described in \nExample #3 below.  In addition, the DARD model leverages existing infrastructure for forecasting and \ntelemetry, further streamlining implementation.   \n \nA DARD is scheduled and settled at the nodal level, which provides situational awareness \nfor ISO System Operations in the Real-Time dispatch and next day planning horizons.  The \nfollowing are the operational parameters for the DARD model: \n \n• Maximum Consumption (“MaxCons”) \no Represents the expected/forecasted operating level \no Improves operational planning, forecasting, and situational awareness \n \n49 A similar requirement applies to Regional Network Service under Section II.15.1 of the OATT. \n50 A similar requirement applies for Regional Network Service under Section II.15.3 of the OATT. \n51 A similar requirement applies for Regional Network Service under Section II.15.2 of the OATT. \n52 A similar requirement applies for Regional Network Service under Section II.15.4 of the OATT. \n53 See Section IV.B.3.a of this transmittal letter."},{"page":29,"startToken":11195,"endToken":11520,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 29 of 99 \n \n \n \no Supports reliable Real-Time operations \n \n• Minimum Consumption (“MinCons”) \no Defines the lower bound for price-based dispatchable flexibility \n \n• Manual Response Rate \no Establishes predictable operational response \no Supports balancing and management of transmission constraints \n \n• Price Pairs \no Allows economic re-dispatch of Non-Firm Contract Demand Service/Interim \nContract Demand Service before emergencies occur \no Integrates portion of Large Loads receiving Non-Firm Contract Demand \nService/Interim Contract Demand Service into electronic and/or market dispatch \no Uses Non-Firm Large Load Re-Dispatch Price and forecasted demand values or \nother price-quantity pair voluntarily offered (or caused to be offered) by the Large \nLoad Transmission Customer \n \nDuring normal operations, dispatch occurs between MaxCons and MinCons, and it is managed \nthrough market signals and economic dispatch (specifically, the Large Load Re-Dispatch Price \ndescribed below combined with forecasted demand values or other voluntarily provided price-quantity \npair data).  The dispatch is automated and predictable, which allows operators to effectively manage \nLarge Load Transmission Customers receiving firm and non-firm transmission services on behalf of \nLarge Loads under normal conditions, even when non-firm transmission service is re-dispatched.  For \na Large Load Transmission Customer that exclusively receives Firm Contract Demand Service on \nbehalf of a Large Load, absent a voluntarily submitted Demand Bid, its MaxCons and MinCons will \nboth be set to the lesser of its Firm Contract Demand Service MW or its forecasted demand MW, which \nensures no price-based redispatch occurs.   \n \nDuring operations, electronic dispatch between MaxCons and MinCons occurs based on price-\nquantity pairs (which may be the Large Load Re-Dispatch Price described below combined with \nforecasted demand values).  Full reduction or disconnection between MinCons and zero MW \nconsumption is managed manually through ISO/Local Control Center operating instructions.  This \nallows for load reductions to address emergency conditions involving load shedding.  Restoration \nindication and control are achieved through a combination of electronic and manual dispatch.  The \nfollowing examples illustrate the DARD model:"},{"page":30,"startToken":11520,"endToken":11533,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 30 of 99"},{"page":31,"startToken":11533,"endToken":11836,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 31 of 99 \n \n \n \n \n \n \nb. \nPrice-Based Re-Dispatch Mechanism \nFlexibility for non-firm transmission services (i.e., Interim Contract Demand Service and \nNon-Firm Contract Demand Service) will be achieved through a price-based re-dispatch \nmechanism.  Specifically, consistent with the “non-firm” flexibility of Interim Contract Demand \nService and Non-Firm Contract Demand Service, all or a portion of a Large Load’s Interim \nContract Demand Service and Non-Firm Contract Demand Service will be re-dispatched when the \nLarge Load’s applicable LMP exceeds a Large Load Re-Dispatch Price of $250/MWh.  Using a \nstatic price streamlines implementation, and the proposed price reduces cost shifting in the energy \nmarkets.   \n \nThis method of providing non-firm transmission service is just and reasonable for several \nreasons.  First, transmission service over the regional transmission facilities in New England is provided \nto Transmission Customers based on economic dispatch rather than through an advance reservation \nsystem; thus, using a re-dispatch price to achieve non-firm transmission service for Large Load \nTransmission Customers is consistent with that construct while achieving the Commission’s \nexpectation regarding non-firm transmission service.  Second, using a static price streamlines \nimplementation and is manageable.  Third, the proposed price reduces cost shifting in the energy \nmarkets54 by re-dispatching large loads when the energy price is at a relatively high price for the region \nas the proposed re-dispatch price has occurred in approximately only 1% of hours in New England \n(based on hourly Load Zone prices) from 2021-2025.  Fourth, the proposed re-dispatch price is aligned \nwith the penalty factor for Replacement Reserves; conceptually, since the region is willing to forgo \n \n54 The price-based re-dispatch mechanism is consistent with the Commission’s emphasis on the need for the avoidance \nof cost shifting and affordability for consumers.  See Testimony of Dennis Cakert on Behalf of ISO New England Inc. \nat 15 attached hereto."},{"page":32,"startToken":11836,"endToken":12458,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 32 of 99 \n \n \n \nReplacement Reserves (a voluntary reliability service) at $250/MWh, it is reasonable to forgo service \nto non-firm Large Loads at $250/MWh.55    \n \nNotably, the proposed price-based re-dispatch mechanism does not require submission of a \nDemand Bid for the Large Load.  Rather, submitting a Demand Bid for the Large Load is optional.  \nSpecifically, under new Section III.1.10.5A(b)(i) of the Tariff, the Large Load Transmission Customer \nmay elect to submit (or cause to be submitted)56 Demand Bids for the Large Load in the Day-Ahead \nand Real-Time Energy Markets.  A submitted Demand Bid MW cannot exceed the Large Load’s total \ntransmission services, and the Demand Bid price for Interim Contract Demand Service or Non-Firm \nContract Demand Service may not exceed the Large Load Re-Dispatch Price.  Absent a submitted \nDemand Bid, the ISO will schedule the Large Load’s consumption in the energy markets based on its \nforecasted demand, transmission services MW, and the Large Load Re-Dispatch Price.  This treatment \naligns with the treatment of conventional load assets, except for the following:  (i) the Large Load’s \nforecasted demand is submitted to the ISO, rather than estimated by the ISO; (ii) the Large Load’s \nmaximum consumption is capped (i.e., by the sum of its transmission service MW); and (iii) Large Load \nnon-firm MW are re-dispatchable (i.e., based on price).   \nThe price-based re-dispatch mechanism is reflected in new Section III.1.10.5A(c)(i) of the \nTariff, which requires the ISO to schedule the Large Load to withdraw energy based on the lesser of the \nLarge Load’s forecasted demand and the sum of the Large Load’s transmission services MW pursuant \nto the Large Load’s Transmission Service Agreement.  If the Large Load Transmission Customer elects \nto submit Demand Bids pursuant to new Section III.1.10.5A(b)(i) of the Tariff, then the ISO must \nschedule the Large Load to withdraw energy based on the lesser of the Large Load’s Demand Bid MW \nand the sum of the Large Load’s transmission services MW pursuant to the Large Load Transmission \nService Agreement.  Under new Section III.1.10.5A(c)(ii) of the Tariff, the ISO is required to send a \nDispatch Instruction to redispatch all or a portion of the Large Load’s Interim Contract Demand Service \nand/or Non-Firm Contract Demand Service based on the Large Load’s applicable Locational Marginal \nPrice and the Large Load Re-Dispatch Price.  Note that, under new Section III.1.10.5A(a)(ii), the Large \nLoad Transmission Customer shall comply with (or cause to be complied with) all applicable \nrequirements in the ISO New England Operating Documents including, but not limited to, forecasting, \ntelemetry, ramp rates, and following Dispatch Instructions.  In addition to demand flexibility, under new \nSection III.1.10.5A(b)(ii) of the Tariff, a Large Load Co-Located Generator and/or Large Load \nElectrically Proximate Generator may achieve all or a portion of re-dispatch for a Large Load with non-\nfirm service, so long as the combination of demand flexibility and associated generation is equal to the \nrequired amount of re-dispatch.  \nThe ISO commits to reviewing the Large Load Re-Dispatch Price through the NEPOOL \nstakeholder process beginning in 2027 and, after that stakeholder process, proposing any revised \nprice that can be implemented for June 1, 2028 to FERC; and (2) the ISO commits to reviewing \n \n55 The Testimony of Dennis Cakert further supports the use of a $250 Large Load Re-Dispatch Price at 10-17. \n56 Under the Tariff Revisions, the Large Load Entity may take actions on behalf of the Large Load Eligible \nCustomer/Large Load Transmission Customer, which is obligated to comply with all applicable Tariff requirements."},{"page":33,"startToken":12458,"endToken":12937,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 33 of 99 \n \n \n \nother price-based approaches to support non-firm transmission services in the stakeholder process \nfor an implementation date after June 1, 2028.  In doing so, the ISO will explore other price-based \nmethodologies to support non-firm transmission service that continue to maintain consistency with \nCommission policy and precedent regarding large load integration, efficient markets, and use of \nthe transmission system. \n4. \nNew Section II.58 of the OATT – Application Process to Evaluate the \nProvision of Large Load Transmission Services \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it lacks sufficiently clear and consistent Tariff provisions \nestablishing the application process that will be used when the ISO evaluates the provision of \ntransmission service to Eligible Customers on behalf of large loads.57  In response to the Show \nCause Order, new Section II.58 of the OATT establishes such application process, and provides \nthat the ISO will start accepting Large Load Transmission Service Applications on June 1, 2027.58  \nThis will allow the ISO to process applications and conduct studies while the necessary software \nis developed for the ISO to begin providing the new transmission services for Large Loads on \nJune 1, 2028. \n \nNew Section II.58.1 of the OATT sets forth the conditions precedent for receiving Firm \nContract Demand Service, Interim Contract Demand Service, or Non-Firm Contract Demand \nService, including:  (i) completing an application; (ii) providing deposits; (iii) completion of study \nprocess under Part II.J of the OATT; (iv) completing technical arrangements in new Sections \nII.58.5 and II.58.6 of the OATT; (v) executing a Large Load Transmission Service Agreement (or \nthe filing of a non-executed agreement); and (vi) execution of a Large Load Cost Recovery \nAgreement. \n \nThe ISO will accept Large Load Transmission Service Applications from Large Load \nEligible Customers on a rolling basis and will assign a Large Load Queue Position for inclusion \nin the Open Access Same-Time Information System (“OASIS”) list of all Large Load \nTransmission Service Applications in its Control Area once an application is deemed complete.59  \nPursuant to new Section II.58.2 of the OATT, to be complete, a Large Load Transmission Service \nApplication must include: \n \n• Information pertaining to the party requesting service, and a statement that the party is, or \nwill become, a Large Load Transmission Customer under the OATT; \n \n57 Show Cause Order at P 57. \n58 A Large Load Transmission Service Application form will be available on the ISO website. \n59 Under new Section II.58.2 of the OATT, the ISO will complete its review of a Large Load Transmission Service \nApplication and issue a notice within 20 days of receiving an application.  If a deficiency is identified, the Large Load \nEligible Customer must cure within 15 days of receipt of the notice."},{"page":34,"startToken":12937,"endToken":13285,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 34 of 99 \n \n \n \n• Large Load’s gross peak demand (MW) and the type and level of each transmission service \nrequested;60  \n• Proposed Large Load Point of Delivery; \n• Demonstration of Large Load Site Control; \n• Large Load Interconnecting Transmission Owner’s interconnecting facilities study report \nfor the Large Load; \n• Technical data, as required in Appendix 1 to the Large Load Transmission Service \nApplication; \n• Simulation models and accompanying model acceptance testing documentation; \n• An affidavit stating that there are no duplicative applications associated with the proposed \nLarge Load in the form of Appendix 2 to the Large Load Transmission Service \nApplication; and \n• Fees and deposits (which the Large Load Entity can provide on behalf of the Large Load \nEligible Customer) \no Initial, non-refundable application fee of $50,000 \no Study deposit of $150,000 (unused balances will be refunded) \n \nThe requirements to provide the Large Load Interconnecting Transmission Owner’s \ninterconnecting facilities study report for the Large Load and an affidavit stating that there are no \nduplicative applications associated with the Large Load, as well as the application fee and study \ndeposit fee, are designed to address the Commission’s concern that the Tariff lacks provisions to \ndeter speculative or duplicative requests for transmission service by Eligible Customers on behalf \nof Large Loads.61    \n \nPursuant to new Section II.58.2 of the OATT, after the ISO determines that the Large Load \nTransmission Service Application is complete, the ISO will issue a notice and will tender a Large \nLoad System Impact Study Agreement to the Large Load Eligible Customer.   \n \nNew Section II.58.3 of the OATT requires the ISO to maintain on its OASIS a list of all \nLarge Load Transmission Service Applications in its Control Area, and describes the information \n \n60 Interim Contract Demand Service is a temporary form of transmission service provided until the requirements for \nFirm Contract Demand Service are met and, therefore, Interim Contract Demand Service is not a type of service that \ncan be requested in a Large Load Transmission Service Application. \n61 Show Cause Order at PP 49, 54."},{"page":35,"startToken":13285,"endToken":13809,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 35 of 99 \n \n \n \nthat will be included on the OASIS for each application.62  In addition, in the Show Cause Order, \nthe Commission expressed its concern with the apparent lack of transparency regarding the \nassignment of network upgrades, and their associated costs, that are needed to provide transmission \nservice to Eligible Customers on behalf of large loads.63  In response to the Show Cause Order, \nnew Section II.58.4 of the OATT requires the ISO to develop, maintain, and post on its website, \nin an easily accessible, searchable and fillable format:  (1) a cumulative list reflecting the Large \nLoad Network Upgrades identified for each Large Load, categorized by upgrade type; and (2) cost \nestimates for each identified Large Load Network Upgrade for each Large Load. \n \nNew Section II.58.5 of the OATT provides that transmission service to the Large Load \nTransmission Customer will not commence until the Large Load Interconnecting Transmission \nOwner and Large Load Transmission Customer (or Large Load Entity on its behalf) have \ncompleted installation of all equipment including direct connection facilities and protection \nsystems necessary for the Large Load to reliably withdraw energy at the Point of Delivery (and \nany additional requirements imposed under the OATT and the ISO New England Planning \nProcedures to ensure the reliable operation of the New England Transmission System).  Under the \nsame section, the ISO is required to exercise reasonable efforts to complete such arrangements as \nsoon as practicable, taking into consideration the Large Load Service Commencement Date.64    \n \nFinally, new Section II.58.6 of the OATT requires the Large Load Transmission Customer \nto construct, install, operate and maintain (or to cause these actions) all facilities on the Large Load \nside of the Point of Delivery.  The provision of transmission services will be conditioned upon the \nconstruction, installation, operation and maintenance of all facilities on the Large Load side of \neach Point of Delivery necessary to reliably deliver capacity and energy from the New England \nTransmission System to the Large Load.65 \n \n5. \nNew Section II.60 of the OATT – Study Procedures to Evaluate the \nProvision of Large Load Transmission Services \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it lacks sufficiently clear and consistent Tariff provisions \nestablishing the study procedures that will be used when ISO-NE evaluates the provision of \ntransmission service to Eligible Customers on behalf of large loads.66  In response to the Show \nCause Order, new Section II.60 of the OATT establishes Large Load study procedures.    \n \n \n62 The information includes the Large Load’s gross peak demand, location by county and state, status of the application \nincluding queue position, types of transmission service requested, and date of the application.  The ISO is also required \nto post Large Load System Impact Study reports. \n63 Show Cause Order at P 64. \n64 Similar requirements apply to Regional Network Service under Section II.16.3 of the OATT. \n65 Similar requirements apply to Regional Network Service under Section II.16.4 of the OATT. \n66 Show Cause Order at P 57."},{"page":36,"startToken":13809,"endToken":14400,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 36 of 99 \n \n \n \na. Study Timelines \nUnder new Section II.60.1 of the OATT, within 15 days of the ISO’s notice to the Large \nLoad Eligible Customer that its Large Load Transmission Service Application is complete, the \nISO must hold a Large Load Scoping Meeting that includes the ISO, the Large Load Eligible \nCustomer, the Large Load Interconnecting Transmission Owner, any appropriate Large Load \nAffected Party, and any appropriate Large Load Internal Affected Party.  The purposes of the Large \nLoad Scoping Meeting are to discuss the estimated timeline for completing the Large Load System \nImpact Study, to exchange pertinent information and analyze it, and to discuss any other \ninformation to facilitate the study procedures.67  Within seven days after the Large Load Scoping \nMeeting, the Large Load Eligible Customer must execute the Large Load System Impact Study \nAgreement.68   \n \nUnder new Sections II.60.2, II.60.3, and II.60.4 of the OATT, the ISO and the Large Load \nInterconnecting Transmission Owner must use reasonable efforts consistent with Good Utility \nPractice to complete the Large Load System Impact Study69 within 90 days of the execution of the \nLarge Load System Impact Study Agreement.70  Under new Section II.60.5 of the OATT, the ISO \nholds the Large Load System Impact Study report review meeting within seven days of issuing the \nLarge Load System Impact Study report, and the Large Load Eligible Customer has 15 days from \nthe receipt of the Large Load System Impact Study report to review the study results.   \n \nNew Sections II.60.3 and II.60.4 of the OATT provide for additional analyses as needed.  \nSpecifically, if the EMT or Cluster Study and other study71 coordination screens show the need \nfor additional study, then the ISO will perform the required study in an additional study window \n(where any required analyses can be done in parallel).  The additional study will be performed \nwithin 120 days after the Large Load System Impact Study report review meeting is held.72    \n \n67 The Filing Parties are required to bring to the meeting personnel and other resources as may be reasonably required \nto accomplish the purposes of the meeting in the time allocated for the meeting.  The duration of the meeting must be \nsufficient to accomplish its purposes. \n68 The form Large Load System Impact Study Agreement is being added in this filing as Attachment T to the OATT. \n69 The ISO and the Large Load Interconnecting Transmission Owner must utilize existing studies to the extent \npracticable. \n70 At the request of the Large Load Eligible Customer or at any time the ISO or Large Load Interconnecting \nTransmission Owner determines that it will not meet the required time frame for completing the Large Load System \nImpact Study, the ISO shall notify the Large Load Eligible Customer as to the schedule status of the Large Load \nSystem Impact Study.   \n71 This allows coordination with Cluster Studies and other studies, such as state jurisdictional affected system operator \nstudies.  Additional details for this screen will be provided in ISO New England Planning Procedures. \n72 This is consistent with Southwest Power Pool, Inc.’s (“SPP”) Commission-approved High Impact Large Load study \nprocess.  Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at PP 14-15 (2026) (describing SPP’s EMT study process \nrequirements); id. at P 62 (finding that SPP’s proposed EMT study requirements for High Impact Large Loads \n(“HILLs”) will help to ensure the reliable integration of Transmission Customers’ HILLs into SPP’s transmission \nsystem)."},{"page":37,"startToken":14400,"endToken":14851,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 37 of 99 \n \n \n \n \nThe study procedures also include an optional Large Load Facilities Study in new \nSection II.60.6 of the OATT.  If the Large Load Eligible Customer elects to have a Large Load \nFacilities Study conducted, then the ISO will tender a Large Load Facilities Study Agreement \nwithin 30 days of the Large Load System Impact Study report review meeting or the conclusion \nof any additional study window, whichever is later.  The Large Load Eligible Customer has 15 \ndays to execute the Large Load Facilities Study Agreement.  The ISO and the PTO(s) will use \nreasonable efforts to perform the study within 90 days.   \n \nOnce the studies are complete, under new Section II.60.7 of the OATT, the ISO, the Large \nLoad Eligible Customer, and the Large Load Interconnecting Transmission Owner must negotiate \nand execute the Large Load Transmission Service Agreement.  The ISO must tender a Large Load \nTransmission Service Agreement within 20 days after it issues the final Large Load System Impact \nStudy report or final Large Load Facilities Study report, whichever is later.  The parties to the \nagreement will have 60 days to negotiate, at the end of which the Large Load Eligible Customer \nmust elect to execute the agreement or request the filing of an unexecuted agreement.  Otherwise, \nthe ISO will deem the Large Load Transmission Service Application withdrawn. \n \nb. \nLarge Load Material Modification \nUnder new Section II.60.8 of the OATT, at any time during the Large Load study process, \nthe following would constitute a Large Load Material Modification that requires the submission \nof a new Large Load Transmission Service Application: \n \n• A decrease of more than 60% to the Large Load’s gross peak demand (MW); \n• Any increase to the Large Load’s gross peak demand (MW), or any increase to the level of \nFirm Contract Demand Service being requested; \n• Any change to the Non-Firm Large Load Generator Arrangement details impacting the \nLarge Load; \n• A modification to the Point of Delivery that is not agreed upon by the ISO, the Large Load \nInterconnecting Transmission Owner, and the Large Load Eligible Customer; and \n• A commencement date for the transmission service that extends for more than three years \nfrom the original commencement date or a commencement date that is more than seven \nyears from the date of the Large Load Transmission Service Application, unless an \nextension request is made to the ISO and the ISO deems the request to be non-material \n \nIn addition, during the study period, the following would constitute a Large Load Material \nModification that requires the submission of a new Large Load Transmission Service Application: \n• A decrease of the total transmission service requested; and"},{"page":38,"startToken":14851,"endToken":15402,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 38 of 99 \n \n \n \n• Any deficiencies in the models associated with the Large Load, Large Load Co-Located \nGenerator, or Large Load Electrically Proximate Generator that are identified by the ISO \nand take more than 15 days to address \n \nAfter the study period, any modifications that significantly alter the performance of the \nstudied project would constitute a Large Load Material Modification and, as such, would require \nthe submission of a new Large Load Transmission Service Application. \nc. \nLarge Load System Impact Study Scope \nNew Section II.60.2 of the OATT provides that the Large Load System Impact Study must \nevaluate the impact of the proposed Large Load on the reliability and operation of the New England \nTransmission System.  The study must consider the Large Load Base Cases as well as all Large \nLoad facilities, any capacity designated under new Section II.59 of the OATT that is available at \nthe time of the study, and any associated Large Load Co-Located Generators or Large Load \nElectrically Proximate Generators (and with respect to (iii) below, any identified Large Load \nNetwork Upgrades associated with such higher queued Large Load facilities) that, on the date the \nstudy is commenced:  (i) are directly interconnected to the New England Transmission System; \n(ii) are interconnected to Large Load Affected Systems and may have an impact on the Large Load \nTransmission Service Application; (iii) have a pending higher queued Large Load Transmission \nService Application to receive service from the New England Transmission System and may have \nan impact on the Large Load Transmission Service Application; and (iv) have no Queue Position \nbut have executed a Large Load Transmission Service Agreement or requested that an unexecuted \nLarge Load Transmission Service Agreement be filed with the Commission (the “Large Load \nStudy Cases” for the Large Load System Impact Study). \n \nNew Section II.60.2 of the OATT also provides that the Large Load System Impact Study \nwill consist of short circuit analysis, stability analysis, power flow analysis (including thermal \nanalysis and voltage analysis), system protection and controls analysis, EMT screening, Cluster \nStudy and other study coordination screening, and any other analyses that the ISO deems necessary \nin consultation with the Large Load Interconnecting Transmission Owner.  The analysis must meet \nthe requirements of reliability standards and ISO New England Planning Procedures, including \nthose related to ride-through, ramp rates, and control technologies and/or protection schemes. \n \nNew Section II.60.2 also provides that, as described in ISO New England Planning \nProcedures, the Large Load System Impact Study will recognize the unique operational \ncharacteristics of Large Loads that are willing and able to limit their energy withdrawals under \ncertain conditions, which may lessen or avoid the need for certain network upgrades.73  \n \n73 The ISO New England Planning Procedures will be updated to allow for load associated with Non-Firm Contract \nDemand Service to reduce its output to mitigate thermal violations at shoulder and peak load in the Large Load System \nImpact Study.  However, load associated with Non-Firm Contract Demand Service will not be reduced to resolve \nthermal violations at light load.  The intent of these study assumptions is to ensure that a Large Load that is being \nserved by a Large Load Transmission Customer taking Non-Firm Contract Demand Service will be able to operate"},{"page":39,"startToken":15402,"endToken":15847,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 39 of 99 \n \n \n \n \nNew Section II.60.4 of the OATT describes the Cluster and other study coordination.  \nSpecifically, this new provision states that the 90-day Large Load System Impact Study period \nwill include a Cluster and other study coordination screening to determine whether additional study \nis required to account for the combined impacts of a Cluster under study according to Schedules \n22, 23, and 25 of the OATT, other studies as described in ISO New England Planning Procedures, \nand a Large Load System Impact Study.  If the Cluster Study and other study coordination \nscreening uncovers the need for additional analysis, then the ISO is required to publish a \npreliminary Large Load System Impact Study report within the 90-day timeline that includes the \nresults of the stability analysis, steady state analysis, short circuit analysis, protection analysis, \nEMT screening analysis, and Large Load Network Upgrades and preliminary cost estimate.  If the \nCluster Study and other coordination screening determines that there are combined impacts that \nneed to be studied in detail, then the ISO shall use reasonable efforts consistent with Good Utility \nPractice to complete the additional coordination analysis (i.e., with the Cluster and other studies) \nand publish a final Large Load System Impact Study report within 120 days of publishing the \npreliminary Large Load System Impact Study report. \nd. \nLarge Load System Impact Study Report \nNew Section II.60.2 of the OATT provides that the Large Load System Impact Study report \nmust state the assumptions upon which it is based and the results of the analysis, as well as provide \nthe requirements or potential impediments to providing the requested transmission service, \nincluding a preliminary indication of the cost and length of time that would be necessary to correct \nany problems identified in those analyses and implement the transmission service.  The report will \nprovide:  \n \n• A list of facilities that are required as a result of the Large Load Transmission Service \nApplication and a non-binding good faith estimate of cost responsibility; \n• A non-binding good faith estimated time to construct; and \n• A protection and controls assessment to determine the required protection upgrades and controls \nThe report may also provide an identification of the likely permitting and siting process \nincluding easements and environmental work.   \n \ne. \nEvaluation of Alternative Transmission Technologies \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it lacks clear and consistent provisions requiring the evaluation \nof alternative transmission technologies as potential solutions to accommodate an Eligible \n \nunder a reasonable set of conditions, while also minimizing or potentially avoiding the need for Large Load Network \nUpgrades."},{"page":40,"startToken":15847,"endToken":16350,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 40 of 99 \n \n \n \nCustomer’s request for transmission service on behalf of a Large Load.74  In response to the Show \nCause Order, new Section II.60.2 of the OATT requires the Large Load System Impact Study to \nevaluate the use of static synchronous compensators, static volt ampere reactive (“VAR”) \ncompensators, advanced power flow control devices, transmission switching, synchronous \ncondensers, voltage source converters, advanced conductors, and tower lifting.  The ISO must \nevaluate each identified alternative transmission technology and determine, in the manner \ndescribed in the ISO New England Planning Procedures, whether the technologies should be used, \nconsistent with Good Utility Practice, Applicable Reliability Standards, and Applicable Laws and \nRegulations.  The ISO must include an explanation of the results of its evaluation for each \ntechnology in the Large Load System Impact Study report. \n \nf. \nLarge Load Facilities Study Procedures \nUnder new Section II.60.6 of the OATT, if a Large Load System Impact Study indicates \nthat Large Load Network Upgrades are needed to supply the Large Load Eligible Customer’s \nservice or to mitigate indirect impacts on Merchant Transmission Facilities (MTF) or Other \nTransmission Facilities (OTF), within 30 days of the issuance of the Large Load System Impact \nStudy report, the ISO must tender a Large Load Facilities Study Agreement75 to the Large Load \nEligible Customer.   \n \nFor a Large Load Transmission Service Application to remain a Completed Application, \nthe Large Load Eligible Customer can either execute the agreement or waive (in writing) the Large \nLoad Facilities Study within 15 days of the ISO’s tender.  If the Large Load Eligible Customer \nneither elects to execute the agreement nor waives the Large Load Facilities Study Agreement, \nthen the Large Load Transmission Service Application will be deemed withdrawn.76   \n \nIf the Large Load Eligible Customer executes the agreement, then the ISO and any affected \nPTO(s) will use due diligence to complete the required Large Load Facilities Study within 90 days.  \nIf the ISO and any affected PTO(s) cannot meet that deadline, then the ISO must notify the Large \nLoad Eligible Customer and provide an estimate of the additional time needed, as well as an \nexplanation for the reasons that additional time is required.   \n \nWhen completed, the Large Load Facilities Study will include a +/-20% good faith estimate \nof the Large Load Eligible Customer’s appropriate share of the cost of any required Large Load \nNetwork Upgrades, and the time required to complete such construction and initiate the requested \nservice.  The Large Load Eligible Customer is required to provide acceptable security to the \naffected PTO(s) or other entities that will construct the new facilities or upgrades equivalent to the \ncosts of those facilities or upgrades (consistent with commercial practices as established by the \nUniform Commercial Code).  \n \n74 Show Cause Order at P 59. \n75 The form Large Load Facilities Study Agreement is being added in this filing as Attachment U to the OATT. \n76 The study deposit (minus administrative costs incurred) will be returned with Interest."},{"page":41,"startToken":16350,"endToken":16897,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 41 of 99 \n \n \n \n \ng. \nCoordination of Studies to Support a Non-Firm Large Load Generator \nArrangement \nUnder new Section II.60.9 of the OATT, the ISO may perform studies to support the \ninterconnection of a Large Load Co-Located Generator or a Large Load Electrically Proximate \nGenerator to support a Non-Firm Large Load Generator Arrangement with a Co-Located Large \nLoad or an Electrically Proximate Large Load concurrent with the applicable Large Load System \nImpact Study.  These studies must meet the requirements of Schedules 22 and 23 of the OATT for \na Large Load Co-Located Generator or Large Load Electrically Proximate Generator.  The Large \nLoad Eligible Customer must identify the Large Load Co-Located Generator or Large Load \nElectrically Proximate Generator and specify the details of the Non-Firm Large Load Generator \nArrangement in order to reflect the Large Load Co-Located Generator or Large Load Electrically \nProximate Generator and the details of the Non-Firm Large Load Generator Arrangement in the \nstudies performed to support Interim Contract Demand Service or Non-Firm Contract Demand \nService.  The Large Load Eligible Customer will be responsible for 50% of all Large Load System \nImpact Study costs if the study includes a Large Load Co-Located Generator or Large Load \nElectrically Proximate Generator.  All non-Interconnection Facility upgrades identified in a Large \nLoad System Impact Study must be considered Large Load Network Upgrades and will be the sole \nresponsibility of the Large Load Transmission Customer, regardless of the participation of a Large \nLoad Co-Located Generator or Large Load Electrically Proximate Generator. \n \n6. \nNew Section II.61 of the OATT – Remote Disconnection of a Large Load \nand Load Shedding \nIn the Show Cause Order, the Commission expressed concern that the Tariff “does not \nrequire the transmission customer to enable ISO-NE to remotely disconnect large loads when \nnecessary to maintain reliability of the transmission system . . . as well as the terms and conditions \nunder which ISO-NE may remotely disconnect the large load.”77  In response to the Show Cause \nOrder, new Section II.61 of the OATT requires the ISO and the Large Load Transmission \nCustomer to establish re-dispatch and Load Shedding procedures with the objective of responding \nto contingencies on the New England Transmission System.  New Section II.61.1 of the OATT \nprovides that the parties shall implement such programs during any period when the ISO \ndetermines that a system contingency exists and such procedures are necessary to alleviate the \ncontingency, up to and including the capability to coordinate the remote disconnection of the Large \nLoad.78  The ISO is required to notify all affected Large Load Transmission Customers in a timely \nmanner of any scheduled reduction of service. \n \n77 Show Cause Order at P 62. \n78 As is the case under Section II.20.1 of the OATT, which applies to Regional Network Service, the ISO will contact \nthe Local Control Center to coordinate the reduction of service.  The ISO will include the conditions under which it \nwill require the Large Load Transmission Customer to remotely disconnect the Large Load in Operating Procedure \nNo. 7 – Action in an Emergency and/or Operating Procedure No. 19 – Transmission Operations.  ISO New England \nOperating Procedure No. 7: Action in an Emergency (OP-7), ISO New England Inc. (June 17, 2026), https://www.iso-"},{"page":42,"startToken":16897,"endToken":17400,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 42 of 99 \n \n \n \n \nIn addition, under new Section II.61.2 of the OATT, during any period when the ISO \ndetermines that a transmission constraint exists on the New England Transmission System, and \nsuch constraint may impair its reliability, the ISO is required to take whatever actions, consistent \nwith Good Utility Practice, that are reasonably necessary to maintain the reliability of the system.  \nIf reliability can be maintained by redispatch reduction of Interim Contract Demand Service or \nNon-Firm Contract Demand Service, the ISO will initiate procedures pursuant to new Section II.63 \nof the OATT without regard to ownership.  \n \nMoreover, new Section II.61.3 of the OATT states that, to the extent that a system \ncontingency exists on the New England Transmission System and the ISO determines that it is \nnecessary for Large Load Transmission Customers taking Firm Contract Demand Service to shed \nload, the parties shall shed load in accordance with the ISO New England Operating Documents.  \n  \nFinally, under new Section II.61.4 of the OATT, the ISO reserves the right, consistent with \nGood Utility Practice and on a not unduly discriminatory basis, to redispatch reduction of Non-Firm \nContract Demand Service and Interim Contract Demand Service, or reduction of Firm Contract Demand \nService79 for purposes of adjusting, changing or repairing lines, substations and facilities, and in cases \nwhere continuing the transmission services would endanger persons or property.  The ISO can also take \nthose actions in the event of adverse conditions or disturbances on the New England Transmission \nSystem or any other system directly or indirectly interconnected with it, in order to limit the extent or \ndamage of those conditions or disturbances, prevent damage to generating or transmission facilities, or \nexpedite restoration of service.80    \n  \n \n7. \nNew Section II.63 of the OATT – Operational Requirements for Large Load \nTransmission Customers \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it lacks provisions addressing ongoing operational \nrequirements for transmission customers taking transmission service on behalf of large loads.81  \nThe Commission expressed concerns that the Tariff does not require transmission customers to \nprovide the ISO hourly forecasts, telemetry data, and other data to ensure sufficient visibility or \nspecify requirements for maintaining communication channels between the ISO and the \ntransmission customer on behalf of the Large Load.82  The Commission also expressed concerns \n \nne.com/static-assets/documents/rules_proceds/operating/isone/op7/op7_rto_final.pdf; ISO New England Operating \nProcedure No. 19 – Transmission Operations, ISO New England Inc. (June 16, 2026), https://www.iso-ne.com/static-\nassets/documents/rules_proceds/operating/isone/op19/op19_rto_final.pdf. \n79 The ISO is required to provide as much advance notice as practicable before reducing the transmission services. \n80 Any redispatch or reduction shall be not unduly discriminatory relative to the Large Load Transmission Customers’ \nuse of the Transmission System on behalf of its Large Loads. \n81 Show Cause Order at P 62. \n82 Id."},{"page":43,"startToken":17400,"endToken":17944,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 43 of 99 \n \n \n \nthat the Tariff does not specify ramp rate or ride-through requirements with which the \ntransmission customer taking transmission service on behalf of the large load must comply, and \nthat the Tariff does not specify requirements for necessary control technologies and/or protection \nsystems that may be necessary to limit a transmission customer’s withdrawals from the \ntransmission system as appropriate.83     \n \nIn response to the Show Cause Order, new Section II.63 of the OATT establishes operational \nrequirements that the Large Load Transmission Customer is required to comply with or cause to be \ncomplied with, which means that the Large Load Entity may comply with the requirements on behalf \nof the Large Load Transmission Customer.  New Section II.63 of the OATT includes the same customer \nobligations and general network terms and conditions that currently apply to Regional Network Service \nunder Section II.B of the OATT.  For example, new Section II.63.2(f) of the OATT requires the Large \nLoad Transmission Customer to submit:  hourly demand consumption forecasts, redispatch capability, \nload power factor or reactive power injection/withdrawal performance, underfrequency load shedding \ncapability, block load shedding capability, disturbance/interruption reports, protection system setting \nconformance, protection system testing and maintenance conformance, planned changes to protection \nsystems, metering testing and maintenance conformance, planned changes in transformation capability, \nconformance to harmonic and voltage fluctuation limits, and dead station tripping.84  New Section \nII.63.2 also includes the same requirements that currently apply to Regional Network Service under \nSection II.B of the OATT related to:  electrical supply, maintenance outage procedures,85 operational \nobligations, notice of transmission service interruptions, access and control, Point of Delivery, \nmaintenance of equipment (with the addition of the ability for the ISO to request monitoring), \nemergency system operations, and cost responsibility.    \n \nIn addition to the requirements that currently apply to Regional Network Service, for Large \nLoads, new Section II.63.2 of the OATT requires the reporting of monitoring equipment testing \nand maintenance conformance,86 conformance to induced sub-synchronous oscillations, ride-\nthrough limits and ramp rate limits.  Furthermore, for Large Loads, new Sections II.63.2(b), (c), \nand (d) of the OATT require the Large Load Transmission Customer to comply with, respectively, \n \n83 Id. \n84 The ISO will develop detailed requirements for large loads related to:  demand forecast information for various time \nhorizons (including hourly forecasts), telemetry data and other metering data as necessary to ensure sufficient \nvisibility, and maintaining communications between the ISO and the Large Load Transmission Customer.  These \ndetailed requirements will be included in Operating Procedure No. 14 – Technical Requirements for Assets and \nResources, or Operating Procedure No. 18 – Metering and Telemetering Criteria. \n85 The ISO will update Operating Procedure No. 5 – Resource Maintenance and Outage Scheduling to incorporate \nprocedures associated with Large Loads. \n86 The ISO will develop detailed requirements for Large Loads related to monitoring equipment, including the \ninstallation of equipment such as Phasor Measurement Units, Digital Fault Recorders or other Point-On-Wave \nmonitoring equipment.  These details will be included in Operating Procedure No. 22 – Disturbance Monitoring \nRequirements.  In addition, outage reporting procedure and communication protocols will be documented in Operating \nProcedure No. 2 – Maintenance of Communications, Computers, Metering and Computer Support Equipment."},{"page":44,"startToken":17944,"endToken":18482,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 44 of 99 \n \n \n \nthe ramp rate requirements specified in the ISO New England Operating Procedures,87 the ride-\nthrough requirements specified in ISO New England Planning Procedures and ISO New England  \nOperating Procedures, and the requirements of the Large Load Transmission Service Agreement \nand ISO New England Operating Procedures with regard to the operation and maintenance of \nnecessary control technologies and/or protection systems to limit withdrawals from the \ntransmission system.   \n \nImportantly, under new Section II.63.3 of the OATT, if the Large Load equipment fails to \nperform consistent with the obligations specified in the OATT, then the Large Load Transmission \nCustomer will be deemed to be in default and service may be suspended immediately and subject \nto a termination through an ISO filing with the Commission.  If the information required in new \nSection II.63.2(f) of the OATT is not provided in a timely manner, then the ISO is required to issue \na notice of such failure to the Large Load Transmission Customer.  If the information is not \nprovided or the issues related to providing the information are not resolved within the timeframe \nestablished by the ISO, then the ISO may suspend service until the information is provided or the \nissue is resolved. \n \n8. \nNew Attachments S, T, and U to the OATT – Large Load Transmission \nService Agreement, Large Load System Impact Study Agreement, and \nLarge Load Facilities Study Agreement \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it lacks pro forma provisions in a transmission service \nagreement between the ISO and the transmission customer taking transmission service on behalf \nof a Large Load to memorialize terms such as equipment requirements, data requirements, and \nremote disconnect capability.88  In response, the ISO is proposing to add new Attachment S – \nLarge Load Transmission Service Agreement to the OATT.  The parties to this agreement are the \nISO and the Large Load Transmission Customer.  Under the agreement, the ISO agrees to provide \nand the Large Load Transmission Customer agrees to take and pay for the selected transmission \nservices (i.e., Firm Contract Demand Service and/or Non-Firm Contract Demand Service), and for \nInterim Contract Demand Service, as applicable, in accordance with the provisions of the ISO New \nEngland Operating Documents and the provisions of the agreement.  The agreement requires a \ndescription of the Large Load that will be served by the Large Load Transmission Customer and \nwill specify the date when service is to commence as well as the Point(s) of Delivery.  The \nagreement also requires a description of, as applicable, a designated capacity resource(s) or a Non-\nFirm Large Load Generator Arrangement.89  The Tariff is incorporated and made a part of the \n \n87 The ISO will specify the ramp rate requirements in Operating Procedure No. 14 – Technical Requirements for \nAssets and Resources. \n88 Show Cause Order at P 63. \n89 The following will be specified in Appendix A to the Large Load Transmission Service Agreement:  Point of \nDelivery and Large Load Point of Change of Ownership, Large Load Transmission Customer’s Interconnection \nFacilities, Large Load Interconnecting Transmission Owner’s Interconnection Facilities, Large Load Network"},{"page":45,"startToken":18482,"endToken":19077,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 45 of 99 \n \n \n \nagreement and, therefore, the agreement memorializes the terms and conditions submitted in this \nsection 205 filing.  The Large Load Transmission Customer may terminate the agreement after \ngiving the ISO 30 days’ written notice.  To resume provision of services, a new Large Load \nTransmission Service Application is required.   \n \nIn addition, to implement the study procedures in new Section II.60 of the OATT, the ISO \nproposes to add Attachment T to the OATT – Large Load System Impact Study Agreement, which \nis an agreement between the ISO, the Large Load Eligible Customer, the Large Load \nInterconnecting Transmission Owner and, if applicable, the Interconnection Customer for a Large \nLoad Co-Located Generator or Large Load Electrically Proximate Generator, under which the \nLarge Load Eligible Customer elects and the ISO performs the Large Load System Impact Study.  \nThe agreement describes the basis for the Large Load System Impact Study, as well as the contents \nof the Large Load System Impact Study report.  The agreement requires the Large Load Eligible \nCustomer to provide a deposit in the amount of $150,000, which will be applied toward the cost \nof the study and the development of the agreement and its attachments.  The agreement includes \nan estimated time for completion, as well as a total estimated cost of the study (any difference \nbetween the deposit and the cost of the study will be paid by or refunded to the Large Load Eligible \nCustomer).  If the Large Load System Impact Study includes a Large Load Co-Located Generator \nor Large Load Electrically Proximate Generator, then the Large Load Eligible Customer will be \nallocated 50% of the cost of the study, and the remaining 50% will be paid by the Interconnection \nCustomer for the Large Load Co-Located Generator or Large Load Electrically Proximate \nGenerator.  In accordance with Part II.J of the OATT, in performing the study, the ISO and the \nLarge Load Interconnecting Transmission Owner must coordinate with Large Load Affected \nParties and Large Load Internal Affected Parties.90 \n \nTo further implement the study procedures in new Section II.60 of the OATT, the ISO also \nproposes to add Attachment U to the OATT – Large Load Facilities Study Agreement, which is \nan agreement between the Large Load Eligible Customer and the ISO.  The purpose of the study \nis to determine detailed engineering, design and cost of the facilities, upgrades, and special \nprotection systems necessary to satisfy the Large Load Eligible Customer’s interconnection for the \nproject or provide the transmission service as indicated by the Large Load System Impact Study.  \nUnder the agreement, the Large Load Eligible Customer will provide all necessary information \nand technical data.  If the ISO determines that additional studies are needed to complete the Large \nLoad Facilities Study, then if the Large Load Eligible Customer elects to proceed, it will pay for \nthe additional studies.  The agreement contains a scope of work, the estimated timeline for \ncompletion of the study, estimated costs (to be paid or caused to be paid by the Large Load Eligible \n \nUpgrades, Large Load Distribution Upgrades, Large Load Network Upgrades to Large Load Affected Systems and/or \nLarge Load Internal Affected Systems, Large Load Contingent Facilities, and a description of automatic control \ntechnologies limiting withdrawals. \n90 The Large Load System Impact Study Agreement also includes the following miscellaneous terms and conditions: \naccuracy of information, disclaimer of warranty, force majeure, liability and indemnification, third party beneficiaries, \nterm and termination, governing law, severability, counterparts, amendment, survival, independent contractor, no \nimplied waivers, successors and assigns, and due authorization."},{"page":46,"startToken":19077,"endToken":19611,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 46 of 99 \n \n \n \nCustomer), and a prepayment schedule.  The ISO will invoice the Large Load Eligible Customer \nfor expenses, with any invoiced amounts to be paid or refunded as appropriate.  At the completion \nof the study, the ISO will provide a report to the Large Load Eligible Customer, and use of the \nstudy will be at the Large Load Eligible Customer’s sole risk.91   \n \n9. \nRevisions in Schedules 2, 16, and 17 of the OATT \nSchedule 2 establishes the rules for provision of VAR Service, which helps maintain \ntransmission voltages on the New England Transmission System.  Qualified resources receive \ncredits for providing VAR Service, which are then charged to Transmission Customers.  In \naccordance with the beneficiary pays principle of cost allocation, a Transmission Customer’s \ncharge for VAR Service is based on their pro rata share of Regional Network Load and Through \nor Out Service.  Large Load Transmission Customers receiving Firm Contract Demand Service, \nInterim Contract Demand Service, and/or Non-Firm Contract Demand Service will benefit from \nmaintained transmission voltages and should therefore be allocated their pro rata share of costs for \nVAR Service.  \nTo charge a Large Load Transmission Customer their pro rata share of Schedule 2 VAR \nService costs, the following changes are required:  (1) establish the Large Load Transmission \nCustomer as an entity that can be charged for VAR Service; (2) establish that demand from all \nLarge Load Transmission Customers, as calculated in OATT Section II.62, is added to demand \nfrom all Transmission Customers’ Regional Network Load and Through or Out Service to \ncalculate total demand for VAR Service and the charge rate for VAR Service; and (3) establish \nthat a Large Load Transmission Customer’s charge for VAR Service is equal to total costs for VAR \nService multiplied by the Large Load Transmission Customer’s pro-rata share of demand.  \nSchedule 16 establishes the rules for provision of Blackstart Service,92 which helps restore \nthe system following a partial or complete shutdown of the New England Transmission System. \nEligible resources receive credits for providing Blackstart Service, which are then charged to \nTransmission Customers.  In accordance with the beneficiary pays principle of cost allocation, a \nTransmission Customer’s charge for Blackstart Service is based on their pro rata share of Regional \nNetwork Load.  Large Load Transmission Customers receiving Firm Contract Demand Service, \nInterim Contract Demand Service, and/or Non-Firm Contract Demand Service will benefit from \n \n91 The Large Load Facilities Study Agreement also includes the following general terms:  no interconnection or \nwheeling rights/no interruption of service, indemnification, disclaimer of damages, duration, termination, dispute \nresolution/voluntary arbitration, Commission jurisdiction over certain disputes/equitable relief, confidential \ninformation, miscellaneous (assignment, governing law, enforceability, no waiver, notice, force majeure, use of \nsubcontractors, no third party beneficiary, entire agreement, signature authorization, definitions, and counterparts).  \n92 The Commission has found that, regardless of whether a co-located load withdraws energy from the transmission \nsystem, co-located load relies on and benefits from regulation service and black start service, and concluded that \nEligible Customers taking one of the new transmission services on behalf of co-located load must pay for these \nancillary services on a gross demand basis. Show Cause Order at P 96."},{"page":47,"startToken":19611,"endToken":20130,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 47 of 99 \n \n \n \nsystem restoration and should therefore be allocated their pro rata share of costs to provide \nBlackstart Service.  \nTo charge a Large Load Transmission Customer their pro rata share of Schedule 16 \nBlackstart Service costs, the following changes are required:  (1) establish the Large Load \nTransmission Customer as an entity that can be charged for Blackstart Service; (2) establish that \ndemand from all Large Load Transmission Customers, as calculated in new Section II.62 of the \nOATT, is added to demand from all Transmission Customers’ Regional Network Load to calculate \ntotal demand for Blackstart Service and the charge rate for Blackstart Service; and (3) establish \nthat a Large Load Transmission Customer’s charge for Blackstart Service is equal to total costs \nfor Blackstart Service multiplied by the Large Load Transmission Customer’s pro rata share of \ndemand.  \nSchedule 17 establishes the rules for recovery of costs associated with Interconnection \nReliability Operating Limits - Critical Infrastructure Protection (“IROL-CIP”) Costs, which helps \nprotect the Bulk Electric System Cyber Systems and Assets.  IROL-Critical Facility Owners \nreceive credits for their applicable costs, which are then charged to Transmission Customers.  A \nTransmission Customer’s charge is based on their pro rata share of Regional Network Load and \nThrough or Out Service, in accordance with the beneficiary pays principle of cost allocation.  Large \nLoad Transmission Customers receiving Firm Contract Demand Service, Interim Contract \nDemand Service, and/or Non-Firm Contract Demand Service will benefit from protection of Bulk \nElectric System Cyber Systems and Assets and should therefore be allocated their pro rata share \nof IROL-CIP Costs.  \nTo charge a Large Load Transmission Customer their pro rata share of Schedule 17 IROL-\nCIP Costs, the following changes are required:  (1) establish the Large Load Transmission \nCustomer as an entity that can be charged for IROL-CIP Costs; (2) establish that demand from all \nLarge Load Transmission Customers, as calculated in new Section II.62 of the OATT, is added to \ndemand from all Transmission Customers’ Regional Network Load and Through or Out Service \nto calculate total demand for IROL-CIP Costs; and (3) establish that a Large Load Transmission \nCustomer’s charge for IROL-CIP Costs is equal to total IROL-CIP Costs multiplied by the Large \nLoad Transmission Customer’s pro rata share of demand.    \n10. \nConforming Revisions to Sections II.20.2 and II.20.3 of the OATT \nSection II.20.2 of the OATT is being revised to include “any Large Load Transmission \nCustomer’s use of the PTF on behalf of its Large Loads” in the types of use of the PTF that cannot \nbe unduly discriminated in redispatch under that provision.  The term “Large Load Transmission \nCustomers” is being added in Section II.20.3 of the OATT as a conforming revision in the language \nthat currently applies to Regional Network Service.  Specifically, the revisions in Section II.20.3 \nof the OATT specify that Large Load Transmission Customers (along with Transmission \nCustomers) will bear the costs of the ISO’s implementation of least-cost redispatch procedures in \nresponse to a transmission constraint in accordance with the ISO New England Operating \nDocuments."},{"page":48,"startToken":20130,"endToken":20672,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 48 of 99 \n \n \n \n11. \nRevisions in Sections III.1, III.2, and III.15 of the Tariff \nThe ISO is proposing revisions in Section III.1.7.19.2.2.2 to establish that a Large Load is \nineligible to provide Real-Time Reserves.  The revisions state that “[f]or a [DARD] associated with a \nLarge Load, all components of the Real-Time Reserve Designation shall be zero.”  Similarly, the \nrevisions in Section III.1.8.1 establish that a Large Load is ineligible to provide Day-Ahead Ancillary \nServices (i.e., day-ahead reserves).  Accordingly, the revisions exclude DARD with a Large Load from \neach Day-Ahead Ancillary Services Offer.  At this time, the ISO proposes to prohibit a Large Load \nfrom providing reserves because a Large Load is not required to bid into the energy markets.  To allow \nLarge Loads with Demand Bids submitted by the Large Load Transmission Customer to provide \nreserves while also prohibiting Large Loads for which the Large Load Transmission Customer has not \nsubmitted Demand Bids without bids from providing reserves would require the ISO to create two \ndifferent energy market models for Large Loads, which would significantly delay the proposed \nimplementation date of June 1, 2028.  In the future, the ISO is open to exploring Tariff revisions that \ncould allow a Large Load with demand flexibility to provide reserves, provided that the Large Load \nTransmission Customer submits Demand Bids and completes capability auditing.   \nAdditionally, in Sections III.2.5 – Calculation of Nodal Real-Time Prices and III.2.6.1 – \nCalculation of Day-Ahead Locational Marginal Prices, the words “and re-dispatchable non-firm loads” \nare being added as conforming changes because re-dispatchable loads (such as Large Loads receiving \nInterim Contract Demand Service and Non-Firm Contract Demand Service) can set, respectively, \nReal-Time Prices and Day-Ahead Locational Marginal Prices.   \nMoreover, in Section III.15.8.5.2.1 of the Tariff – Charges Associated with Dispatchable Asset \nRelated Demands, the Tariff Revisions state that the adjustment to a load serving entity’s Coincident \nPeak Contribution resulting from a DARD associated with a Large Load must be based on the Large \nLoad’s Interim Contract Demand Service and Non-Firm Contract Demand Service.  As such, the \nrevisions exclude Large Loads receiving Interim Contract Demand Service and Non-Firm Contract \nDemand Service from capacity cost allocation.  This aligns with the beneficiary pays principle because \na Large Load Transmission Customer receiving Interim Contract Demand Service and/or Non-Firm \nContract Demand Service on behalf of a Large Load is excluded from the calculation used to determine \nthe Installed Capacity Requirement and is re-dispatched prior to a Capacity Scarcity Condition \n(“CSC”).  \nC. \nTariff Revisions in Response to the Show Cause Order Proposed by the ISO \nand the PTOs Under Joint ISO/PTOs Section 205 Rights \nIn the Show Cause Order, the Commission preliminarily found that the Tariff appears to \nbe unjust and unreasonable because it does not contain provisions allowing an interconnection \ncustomer to seek the generator interconnection service(s) that reflects the operational dynamics of \nserving either:  (1) an electrically proximate large load; or (2) a co-located load.93  In response to \nthe Show Cause Order, to establish a study and agreement process for Large Load Co-Located \n \n93 Show Cause Order at P 111."},{"page":49,"startToken":20672,"endToken":21213,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 49 of 99 \n \n \n \nGenerators and Large Load Electrically Proximate Generators, the Tariff Revisions include:  (i) \nmodifications to the LGIP contained in Schedule 22 of the OATT, and the addition of a Large \nLoad Co-Located Generator/Large Load Electrically Proximate Generator LGIA (“LLCELGIA”) \nas new Appendix 13 to the LGIP; and (ii) modifications to the SGIP contained in Schedule 23 of \nthe OATT, and the addition of a Large Load Co-Located Generator/Large Load Electrically \nProximate Generator SGIA (“LLCESGIA”) as new Appendix 12 to the SGIP.9495   \n \nNew Sections 14 in the LGIP and SGIP contain the rules for Large Load Co-Located \nGenerators and Large Load Electrically Proximate Generators.  New Sections 14.1 of the LGIP \nand SGIP provide that Large Load Co-Located Generators and Large Load Electrically Proximate \nGenerators are only subject to Sections 3.7 (Withdrawal), 12 (Construction of Interconnecting \nTransmission Owner Interconnection Facilities and Network Upgrades), 13 (Miscellaneous), 14 \n(Large Load Co-Located Generators and Large Load Electrically Proximate Generators), \nAttachment D to Appendix 1 (Large Load Co-Located Generator/Large Load Electrically \nProximate Generator Interconnection Application), and Appendix 13 to the LGIP \n(LLCELGIA)/Appendix 12 to the SGIP (LLCESGIA).  The provision requires that Sections 3.7, \n12, and 13 be interpreted in such manner as to apply to Large Load Co-Located Generators and \nLarge Load Electrically Proximate Generators.  Said differently, Large Load Co-Located \nGenerator and Large Load Electrically Proximate Generator shall be treated synonymously with \nInterconnection Customer under such sections. \nNew Sections 14.2 of the LGIP and SGIP establish the Large Load Co-Located \nGenerator/Large Load Electrically Proximate Generator interconnection process.  New Sections \n14.2 provide that, under a Non-Firm Large Load Generator Arrangement, the Large Load Co-\nLocated Generator or Large Load Electrically Proximate Generator must be deemed to be \nproviding all of its output to the Co-Located Large Load or Electrically Proximate Large Load, \nmust not have the right to inject any energy onto the Administered Transmission System except as \npermitted by the definitions of Electrically Proximate Large Load and Large Load Electrically \nProximate Generator, must receive zero MW of Network Resource Interconnection Service \n(“NRIS”), and must only be granted the right to physically interconnect at a designated Point of \nInterconnection (“POI”) in the LLCELGIA/LLCESGIA. \n \n \n94 The Tariff Revisions in Schedules 22 and 23 to the OATT also include revisions in the definitions of Contingent \nFacilities and Interconnection Study to include terms related to Large Loads.  In Schedules 22 and 23 of the OATT, \nthe Tariff Revisions also add the following definitions, as appropriate: Large Load Co-Located Generator/Large Load \nElectrically Proximate Generator Impact Studies, Large Load Co-Located Generator/Large Load Electrically \nProximate Generator LGIA, Large Load Co-Located Generator/Large Load Electrically Proximate Generator \nInterconnection Application, and Large Load Co-Located Generator/Large Load Electrically Proximate Generator \nSGIA.  In Schedule 23 to the OATT, the definitions of Small Generating Facility and SGIA Deposit have been moved \nand cleaned-up. \n95 The ISO is also making clean up changes to correct inadvertent grammar and terminology errors in the following \nSections of Schedules 22 and 23: 3.2.1.3, 4.2.3.1.2, 4.2.3.3, 4.4.1, 4.4.5, 8.1, and 8.3."},{"page":50,"startToken":21213,"endToken":21791,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 50 of 99 \n \n \n \nUnder new Sections 14.2.1 of the LGIP and SGIP, the ISO must start accepting Large Load \nCo-Located Generator/Large Load Electrically Proximate Generator Interconnection Applications \nunder the LGIP/SGIP on June 1, 2027.  The applications are for Interconnection Customers to \nrequest to physically interconnect to the Administered Transmission System at a designated POI \nwith zero MW of NRIS.  The application forms are included as Attachments D to Appendix 1 of \nthe LGIP and SGIP.  Applications must be accompanied by a written certification from the Large \nLoad Eligible Customer (or Large Load Entity on its behalf) that the Large Load Co-Located \nGenerator/Large Load Electrically Proximate Generator has been designated to serve its Co-\nLocated Large Load or Electrically Proximate Large Load.  Applications must also include the \ntechnical data required in Appendix 1 to the LGIP and SGIP, a non-refundable application deposit \nof $50,000 in cash, a refundable deposit of $150,000 in cash,96 and proof of Site Control for the \nLarge Load Co-Located Generator/Large Load Electrically Proximate Generator.   \n \nNew Sections 14.2.2 of the LGIP and SGIP contain the provisions for the Large Load Co-\nLocated Generator/Large Load Electrically Proximate Generator Impact Studies.  The study scope \nis described in new Sections 14.2.2.1 of the LGIP and SGIP.  Specifically, studies may consist of \nreactive power, short circuit/fault duty, stability analyses, and/or other appropriate studies.  Steady-\nstate (thermal/voltage) analyses may also be performed as necessary to ensure that all required \nreliability conditions are studied.  If the Large Load Co-Located Generator or Large Load \nElectrically Proximate Generator includes an electric storage resource, the ISO will use a system \nload level as defined in its planning procedures when studying the charging mode of the electric \nstorage resource.  To the extent required, studies will be coordinated with Internal Affected \nSystems and Affected Systems.   \n \nImportantly, under new Sections 14.2.2.1 of the LGIP and SGIP, the study of Large Load \nCo-Located Generator/Large Load Electrically Proximate Generator may be conducted as part of \nthe Large Load System Impact Study for the associated Co-Located Large Load or Electrically \nProximate Large Load (this study is described in the Tariff Revisions in new Part II.J of the \nOATT).  This study must consider the full capability of the facility to ensure the acceptability of \nthe proposed control technology needed to restrict the ability of the Large Load Co-Located \nGenerator or Large Load Electrically Proximate Generator to inject energy onto the Administered \nTransmission System.  The reactive power, short circuit/fault duty, stability, and steady-state \nanalyses for a Large Load Co-Located Generator or Large Load Electrically Proximate Generator \nmust identify any Interconnection Facilities necessary to interconnect the Large Load Co-Located \nGenerator or Large Load Electrically Proximate Generator.  All non-Interconnection Facility \nupgrades identified in this study as needed to reliably interconnect both the Large Load and the \nGenerating Facility must be classified as Large Load Network Upgrades with costs allocated under \nthe Large Load Cost Recovery Agreement in Attachment V of the OATT.   \n \nIf the study of the Large Load Co-Located Generator or Large Load Electrically Proximate \nGenerator is conducted after the Large Load System Impact Study has been completed, then the \n \n96 The study deposit will be refundable, minus all costs incurred by the ISO in the event of a withdrawal of an \napplication prior to the completion of the studies."},{"page":51,"startToken":21791,"endToken":22360,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 51 of 99 \n \n \n \nLarge Load Co-Located Generator or Large Load Electrically Proximate Generator will be studied \non its own and, if Network Upgrades are required to accommodate the Large Load Co-Located \nGenerator or Large Load Electrically Proximate Generator, then the study must terminate and the \nInterconnection Customer will be required to submit an Interconnection Request to participate in \nthe next Cluster Study conducted under the LGIP or SGIP if it seeks to proceed. \n \nNew Sections 14.2.2.2 of the LGIP and SGIP provide that the Interconnection Customer \nfor the Large Load Co-Located Generator or Large Load Electrically Proximate Generator will be \nallocated 50% of the cost of the Large Load System Impact Study (with the remaining 50% to be \npaid by the Large Load Transmission Customer under Part II.J of the OATT).  However, if the \nstudy of the Large Load Co-Located Generator or Large Load Electrically Proximate Generator is \nconducted after the Large Load System Impact Study has been completed, then the Interconnection \nCustomer must be responsible for all costs.  Under new Sections 14.2.2.3 of the LGIP and SGIP, \nthe study results will be communicated to the Interconnection Customer in the manner described \nin new Part II.J of the OATT, regardless of whether the study is conducted as part of the Large \nLoad System Impact Study.  \n \nNew Sections 14.3 of the LGIP and SGIP require the ISO to maintain on its OASIS a list \nof all Large Load Co-Located Generator/Large Load Electrically Proximate Generator \nInterconnection Applications in its Control Area.  The list must identify:  nameplate generating \ncapability, location by county and state, substation or transmission line or lines where the \ninterconnection will be made, projected Initial Synchronization Date, status of the application, and \ndate the ISO received the application. \n \n \nUnder new Sections 14.4 of the LGIP and SGIP, the following constitute Material \nModifications for a Large Load Co-Located Generator/Large Load Electrically Proximate \nGenerator such that a new application will be required for study:  (i) any increase in capability; (ii) \ndecrease of more than 60% of the capability originally studied; (iii) any change to a Non-Firm \nLarge Load Generator Arrangement that impacts the Large Load Co-Located Generator or Large \nLoad Electrically Proximate Generator; (iv) a modification to the POI that is not agreed upon by \nthe ISO, the Interconnection Customer, and the Interconnecting Transmission Owner; (v) an \nextension to the Commercial Operation Date that exceeds three (3) years from the Commercial \nOperation Date or that is more than seven (7) years from the date of the Large Load Co-Located \nGenerator/Large Load Electrically Proximate Generator Interconnection Application, unless an \nextension request is made to the ISO and the ISO deems the extension to be non-material; (vi) \nduring the study period any modifications to the Large Load Co-Located Generator, Large Load \nElectrically Proximate Generator, or Large Load models that take more than15 Calendar Days to \naddress; and (vii) after the study period, any requested modification that significantly alters the \nperformance of the studied project. \n \n \nFinally, new Sections 14.5 of the LGIP and SGIP provide that the interconnection of a \nLarge Load Co-Located Generator or Large Load Electrically Proximate Generator will be \ngoverned by the LLCELGIA (Appendix 13 to the LGIP)/LLCESGIA (Appendix 12 to the SGIP).  \nThe agreements must be developed and negotiated at the Interconnection Customer’s expense, in"},{"page":52,"startToken":22360,"endToken":22893,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 52 of 99 \n \n \n \naccordance with these new provisions.  Specifically, within 20 days of the ISO’s issuance of the \nfinal impact study report, the ISO must tender an LLCELGIA/LLCESGIA, and the ISO, \nInterconnection Customer and Interconnecting Transmission Owner will have 60 Calendar Days \nto negotiate the agreement, including all its construction milestones.  At the end of the 60-day \nperiod, the Interconnection Customer must either request to execute the LLCELGIA/LLCESGIA \nor request the filing of an unexecuted LLCELGIA/LLCESGIA with the Commission.  \nSimultaneously with the execution of the LLCELGIA/LLCESGIA, the Interconnection Customer \nmust provide continued proof of 100% Site Control for the Large Load Co-Located Generator or \nLarge Load Electrically Proximate Generator, and security in an amount and form required by the \nInterconnecting Transmission Owner to secure the construction of any Interconnection Facilities \nneeded to support the interconnection of the Large Load Co-Located Generator or Large Load \nElectrically Proximate Generator. \n \n \nThe LLCELGIA and LLCESGIA are versions of, respectively, the Large Generator \nInterconnection Agreement (Appendix 11 to the LGIP) and Small Generator Interconnection \nAgreement (Appendix 11 to the SGIP) adapted to address the interconnection of a Large Load Co-\nLocated Generator or Large Load Electrically Proximate Generator, which will have a Non-Firm \nLarge Load Generator Arrangement and will interconnect with zero MW of Network Resource \nInterconnection Service. \n \n \nIn addition to the changes in the LGIP and SGIP, to address the Show Cause Order’s \nfindings that co-location can reduce transmission system impacts,97 under new Section \nIII.1.10.5A(b)(ii), the Large Load Transmission Customer may, or may cause to, use energy supply \nfrom a Large Load Co-Located Generator or Large Load Electrically Proximate Generator to \nachieve re-dispatch requirements for Interim Contract Demand Service and/or Non-Firm Contract \nDemand Service pursuant to Section III.1.10.5A(c)(ii) (which requires the ISO to send a Dispatch \nInstruction to redispatch all or a portion of the Large Load’s Interim Contract Demand Service \nand/or Non-Firm Contract Demand Service based on the Large Load’s applicable Locational \nMarginal Price and the Large Load Re-Dispatch Price).  Furthermore, to address the Show Cause \nOrder’s considerations on cost shifting,98 new Section III.1.10.5A(d)(ii) of the Tariff provides that \nthe Assigned Meter Reader for the Large Load must submit Revenue Quality Metering for hourly \nand monthly settlement that represents gross supply quantities for Large Load Co-Located \nGenerators and/or Large Load Electrically Proximate Generators associated with a Large Load, \nsuch that the generator’s Revenue Quality Metering is not netted with any other load or supply.99 \n \n \n97 Show Cause Order at PP 111-17. \n98 Id. at P 97. \n99 The Commission has found that, regardless of whether a co-located load withdraws energy from the transmission \nsystem, co-located load relies on and benefits from regulation service and black start service, and concluded that \nEligible Customers taking one of the new transmission services (discussed below) on behalf of co-located load must \npay for these ancillary services on a gross demand basis.  Show Cause Order at P 96.  Gross metering results in charges \nfor ancillary services, including regulation service, based on the Large Load’s gross load."},{"page":53,"startToken":22893,"endToken":23558,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 53 of 99 \n \n \n \nIn Order No. 2023, the Commission was clear that its final rule was “not intended to divert or \nslow the potential progress of” efforts to address interconnection queue management issues and \ntransmission providers were explicitly encouraged “to continue to innovate to remedy their identified \ninterconnection queue management issues.”100  Consistent with that guidance, the Commission stated \nthat RTOs could propose deviations from the requirements adopted in the final rule and those deviations \nwould be evaluated in light of the independent entity variation standard.101  Though the changes \nproposed herein mark a deviation from Order No. 2023 in certain respects, such changes are \nnevertheless consistent with the Commission’s goal, as expressed most recently in Order No. 2023, “to \nensure that interconnection customers are able to interconnect to the transmission system in a reliable, \nefficient, transparent, and timely manner, thereby ensuring that rates, terms, and conditions for \nCommission-jurisdictional services are just, reasonable, and not unduly discriminatory or \npreferential.”102  Although the proposed Tariff Revisions meet the just and reasonable standard on its \nmerits, to the extent necessary and appropriate, the Commission also could approve such revisions under \nthe independent entity variation standard, which was recently reaffirmed in Order No. 2023. \nD. \nPTOs’ Tariff Revisions in Response to the Show Cause Order \n1. \nNew Section II.62 of the OATT \nThe new Section II.62 in the Tariff Revisions is the provision under which the applicable \ndemand for a Large Load Transmission Customer is determined.  Firm Contract Demand is \ncalculated as the amount of Firm Contract Demand Service requested by the Large Load Eligible \nCustomer on its Large Load Transmission Service Application, while Non-Firm Contract Demand \nand Interim Contract Demand are calculated based on the coincident load of the Large Load \nTransmission Customer during the Monthly Peak.  To avoid disrupting service arrangements for \n \n100 Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC ¶ 61,054, at PP 10, \n1765 (“We do not intend to disrupt . . . ongoing transition processes or stifle further innovation.”), limited order on reh’g, 185 \nFERC ¶ 61,063 (2023), order on reh’g & clarification, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC \n¶ 61,134 (2024), aff’d sub nom., Advanced Energy United v. FERC, 185 F.4th 186 (D.C. Cir. 2026). \n101 The Commission has granted independent entity variations from Order No. 2023 where the RTO/Independent System \nOperator demonstrates that the proposed variation:  (1) is just and reasonable and not unduly discriminatory or preferential; \nand (2) accomplishes the purposes of the order.  Order No. 2023 at P 19; see Standardization of Generator Interconnection \nAgreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103, at PP 822-27 (2003) (“With respect to an RTO or \n[Independent System Operator] . . . we will allow it to seek ‘independent entity variations’ from the Final Rule pricing and \nnon-pricing provisions.  This is a balanced approach that recognizes that an RTO or [Independent System Operator] has \ndifferent operating characteristics depending on its size and location and is less likely to act in an unduly discriminatory \nmanner . . . .  The RTO or [Independent System Operator] shall therefore have greater flexibility to customize its \ninterconnection procedures and agreements to fit regional needs.”), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, \nat P 759  (“[T]here is a rational basis for giving RTOs and [Independent System Operators] more flexibility . . . .  The foremost \nreason for different treatment is the fact that an RTO or [Independent System Operator] is independent and is less likely to act \nin an unduly discriminatory manner . . . .  The RTO or [Independent System Operator] also may have operating characteristics \n. . . that require more flexibility than provided by the ‘regional differences’ justification.”), order on reh’g, Order No. 2003-B, \n109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom., Nat’l Ass’n of \nRegul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007). \n102 Order No. 2023 at P 37."},{"page":54,"startToken":23558,"endToken":24092,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 54 of 99 \n \n \n \nexisting loads which have been served reliably for many years using the existing transmission \nsystem, demands exempt from Part II.J consistent with the methodology described above that then \ntransition to FCDS for additional demand above such exempt demand (so long as that additional \ndemand can be separately metered) shall be billed at the rate established for that demand as of \nJune 18, 2026, as may be later amended or revised.  The new Section II.62 is necessary, just, and \nreasonable because it provides the calculation for the demand that is used in the billing calculations \nof the new proposed Schedule 9A. \n2. \nNew Attachment V of the OATT (Large Load Cost Recovery Agreement) \nConsistent with the Show Cause Order, the Tariff Revisions include a new pro forma cost \nrecovery agreement designed to ensure that large loads “are ultimately responsible for the costs \nincurred to provide transmissions service, including the cost of network upgrades” and to remedy \nthe Commission’s preliminary finding that the Tariff “lacks adequate mechanisms to mitigate the \nrisk of cost shifting among transmission customers.”103  However, the PTOs believe that a cost \nrecovery agreement among ISO-NE, the relevant transmission owner, and the Eligible Customer \ntaking transmission service on behalf of large loads is an insufficient guarantor of preventing the \ncost-shifting concerns raised by the Commission in the Show Cause Order.  As the Commission \nis aware and notes throughout the Show Cause Order, Eligible Customers may not be (and often \nare not) the large loads actually interconnecting to the transmission system but instead may be the \napplicable electric distribution company (“EDC”) or load-serving entity applying for service on \nbehalf of the large load.  In the case where a cost recovery agreement is solely among the Eligible \nCustomer, applicable PTO, and ISO-NE, a default or failure to come online by the large load itself \nwould not adequately protect either the EDCs or other wholesale transmission customers from cost \nshifting for the reasons described below. \n \nAccordingly, the PTOs are proposing a pro forma Large Load Cost Recovery Agreement \n(“LLCRA”)104 as Attachment V to the OATT among the Large Load Interconnecting \nTransmission Owner (“LLITO”), the Large Load Eligible Customer, and the Large Load Entity \n(the entity owning the proposed Large Load Facility).  Under the LLCRA, no transmission service, \nwholesale service, distribution service, or other electrical service, FERC-jurisdictional or \notherwise, is being provided.  Rather, the LLCRA governs the construction of, cost responsibility \nfor, and crediting of revenues associated with Commission-jurisdictional transmission facilities \nthat are used to provide Commission-jurisdictional transmission service to Large Load Facilities.  \nAs explained below, a contract need not itself provide jurisdictional service to be subject to section \n205 of the FPA; the LLCRA is jurisdictional because it directly and significantly affects \nCommission-jurisdictional transmission rates and services.  The LLCRA establishes the terms and \nconditions under which the LLITO will construct and the Large Load Entity will compensate the \nLLITO for both sole-use facilities necessary to interconnect the Large Load Facility (“Direct \n \n103 Show Cause Order at PP 74-75. \n104 Capitalized terms not otherwise defined in this section have the meaning set forth in the OATT or the LLCRA, as \napplicable."},{"page":55,"startToken":24092,"endToken":24672,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 55 of 99 \n \n \n \nAssignment Facilities”) and LLITO’s Network Upgrades105 identified as part of the OATT’s Large \nLoad interconnection process. \n \nThe Large Load Entity will pay for the Direct Assignment Facilities on a reimbursable \nbasis, and no costs for such facilities will flow into transmission rates.  As consideration for the \nconstruction of LLITO’s Network Upgrades, so that there is no increase in transmission rates for \nother transmission customers caused by the interconnection of the Large Load Facility to the \ntransmission system, the Large Load Entity will pay a Cost Recovery Charge, when necessary, to \nbe credited against the LLITO’s transmission revenue requirements.  The combination of the Large \nLoad Transmission Customer’s payment for its applicable transmission service, which supports \nthe costs of the entire transmission network, with the Large Load Entity’s payment of the Cost \nRecovery Charge and the associated crediting will ensure that the construction of LLITO’s \nNetwork Upgrades and those facilities’ inclusion in transmission rates will result in no increase in \nthe transmission rates of other customers.  The Large Load Entity will also agree to pay an Exit \nFee in the event of early termination of the LLCRA or disconnection of the Large Load Facility \nequal to the Net Book Value of the LLITO’s Network Upgrades.  The Exit Fee will likewise be \ncredited against the LLITO’s revenue requirements, further ensuring that the costs of LLITO’s \nNetwork Upgrades will not be shifted to other transmission customers.  \n \nThe LLCRA also contains provisions to ensure that (1) the Large Load Entity posts \nadequate security to ensure that in the event of default or disconnection by the Large Load Facility \nno costs will be shifted to either the Large Load Eligible Customer as EDC or to other transmission \ncustomers; (2) establishes a contractual obligation for the Large Load Entity to comply with ISO-\nNE operational requirements; (3) lays out milestones for construction for the Direct Assignment \nFacilities and LLITO’s Network Upgrades (“Required Facilities”); and (4) industry standard and \npreviously FERC-approved terms and conditions to ensure a just and reasonable cost recovery \nagreement, including confidentiality, tax, insurance, termination, and dispute resolution \nprovisions. \n \nFor the reasons explained below, the PTOs believe that the LLCRA offers a surer guarantee \nof a large load both paying their fair share of transmission charges and preventing cost shifting to \nother transmission customers, which the PTOs agree is of paramount importance.  Contractual \nprivity between the Large Load Entity and the LLITO ensures that construction arrangements, \nincluding milestones, scheduling, billing, and cost responsibility are effected with minimal issue.  \nFurthermore, should an EDC as Large Load Eligible Customer enter into a separate cost recovery \nagreement with the Large Load Entity in order to indemnify itself against failure of the Large Load \nFacility to materialize or otherwise effect compliance with ISO-NE operational or tariff \n \n105 Similar to network upgrade arrangements for generators under Schedules 22, 23, and 25 of the OATT, under Article \n10 of the LLCRA the Large Load Entity will separately contract for the construction of network upgrades on non-\nLLITO systems (Large Load Affected Systems and Large Load Internal Affected Systems) both internal to ISO-NE \nand external (such as in NYISO).  Such agreements will be outside of the pro forma LLCRA and shall be filed with \nthe Commission pursuant to FPA section 205 for approval or acceptance.  Likewise under Article 10, the Large Load \nEntity agrees to contract for any distribution system upgrades identified by the Large Load System Impact Study."},{"page":56,"startToken":24672,"endToken":25230,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 56 of 99 \n \n \n \nrequirements, that agreement may be of uncertain jurisdictional provenance from the outset, \ncreating significant regulatory and litigation risk.  Other arrangements for the indemnification of \nan EDC by a Large Load Entity are likewise potentially fraught, especially under what mechanism \nan EDC could require such an indemnity in light of a state obligation to serve a new load in its \nterritory.  And in the absence of such indemnity, an EDC Eligible Customer would be legally \nresponsible for the costs allocated to it under a cost recovery agreement without meaningful \nrecourse, with potentially disastrous consequences for both transmission and retail customers. \n \n \nThe PTOs recognize that a pro forma agreement to which the Large Load Entity, which may be \na retail customer of an EDC, is a party warrants careful jurisdictional analysis.  However, and as more \nfully explained below, the LLCRA directly and significantly affects Commission-jurisdictional \ntransmission rates and services and therefore falls within the Commission’s section 205 authority, meets \nthe jurisdictional tests cited by the Commission in this and other large load proceedings, is consistent \nwith other agreements approved or accepted by the Commission without jurisdictional issues, and \nspecifically is readily distinguishable from the Tri-State Generation and Transmission Association \norder and the jurisdictional pitfalls described therein.106  Finally, it is through direct contractual privity \nwith the large load that no cost shifting for network upgrades can be assured.  To the extent that the \nCommission finds that certain provisions of the LLCRA are impermissible on jurisdictional grounds, \nthe PTOs respectfully request that the Commission undertake an analysis of how a pro forma cost \nrecovery agreement between the applicable transmission owner and a large load could be \njurisdictionally acceptable.  The PTOs note that no jurisdictional objections regarding the LLCRA were \nraised by NEPOOL stakeholders, including applicable state entities, as part of the ISO-NE and \nNEPOOL stakeholder process for the development of this filing.  While NEPOOL supports the LLCRA \nas part of the package of proposed Tariff Revisions, NEPOOL takes no position on the PTOs’ legal \narguments regarding jurisdiction related to the LLCRA. \n \n \nAccordingly, the PTOs respectfully request that the Commission accept the LLCRA as a just \nand reasonable agreement to address the cost-shifting issues raised in the Show Cause Order. \na. \nOperation and Provisions of the LLCRA \n \nThe LLCRA is a cost recovery agreement between the LLITO, the Large Load Eligible \nCustomer, and the Large Load Entity that provides for the construction of LLITO’s Network Upgrades \nand the sole-use facilities necessary to effect the reliable interconnection of the Large Load Facility \nconsistent with the upgrades and facilities identified in the Large Load System Impact Study, and \ndescribes the cost allocation for those facilities to be constructed.107  Specifically, each article of the \nLLCRA does the following: \n \n106Tri-State Generation & Transmission Ass’n, 193 FERC ¶ 61,070 (2025) (“Tri-State”).  The Commission \nsubsequently accepted Tri-State Generation and Transmission Association, Inc.’s (“Tri-State”) revised High Impact \nLoad tariff and agreement.  Tri-State Generation & Transmission Ass’n, 196 FERC ¶ 61,127 (2026) (“Tri-State II”). \n107 The LLCRA contains provisions that address the instance where the Large Load Eligible Customer and the Large \nLoad Entity are one and the same.  Under the Tariff Revisions, the Large Load Eligible Customer also becomes a \nLarge Load Transmission Customer once transmission service is being provided to that customer under the OATT."},{"page":57,"startToken":25230,"endToken":25679,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 57 of 99 \n \n \n \n• Article 1 of the LLCRA establishes the definitions of several terms, including LLITO’s \nNetwork Upgrades and Direct Assignment Facilities, that are not otherwise defined in the \nOATT.  For convenience and clarity, the definitions of other terms otherwise defined in the \nOATT have likewise been included.   \n• Article 2 of the LLCRA establishes a 40-year Initial Term and then renews the LLCRA on an \nannual basis unless otherwise agreed to by the parties in writing,108 establishes both voluntary \nand involuntary termination procedures, allocation of costs following termination, and survival \nof obligations following termination of the LLCRA.   \n• Article 3 obligates the LLITO to file the LLCRA if required, such as in the case of a \nnonconforming LLCRA. \n• Article 4 describes the LLITO’s obligation to design, procure, and construct the Direct \nAssignment Facilities and LLITO’s Network Upgrades on terms consistent with the LGIA and \nother Commission-jurisdictional construction agreements,109 including procurement and \ncommencement of construction.  Article 4 also provides for the construction of the Large Load \nEntity’s Interconnection Facilities (“LLEIF”), certain tax treatments related to the Direct \nAssignment Facilities, and states that no electrical or transmission service is being provided \npursuant to the LLCRA. \n• Article 5 describes testing and inspecting arrangements both before and after the commercial \noperation date of the Large Load Facility. \n• Article 6 describes the metering obligations of the Parties, including check meters and metering \ndata. \n• Article 7 describes the communications obligations of the Large Load Entity, including Remote \nTerminal Unit and telemetry requirements. \n• Article 8 describes the operational and compliance obligation of each Party under the \nagreement, including (1) compliance with ISO New England Operating Documents and NERC \nReliability Standards; (2) outages and interruption authority and coordination; (3) system \nprotection and control obligations; and (4) use of the Direct Assignment Facilities and LLEIF \nby third parties. \n• Article 9 describes the LLITO and Large Load Entity maintenance obligations, including the \nLarge Load Entity’s obligation to pay for operating and maintenance expenses for the Direct \nAssignment Facilities as more fully described in an LLITO-specific Appendix C-1. \n• Article 10 describes the performance, credit support, and cost recovery obligations of the \nLLCRA, including the LLEIF, the Direct Assignment Facilities, and LLITO’s Network \nUpgrades.  Article 10 obligates the Large Load Entity to pay the Cost Recovery Charge \ndescribed in Appendix C-2, provide initial and ongoing Credit Support sufficient to cover both \n \n108 The term of the LLCRA renews following the Initial Term in order to ensure ongoing payments for Direct \nAssignment Facilities operation and maintenance charges, as well as ongoing obligations and rights of all Parties. \n109 See OATT Schedule 22, Appendix 11, Large Generator Interconnection Agreement at Article 5."},{"page":58,"startToken":25679,"endToken":26062,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 58 of 99 \n \n \n \ninitial construction as well as the Exit Fee for early termination of the LLCRA, and pay the Exit \nFee in the event of termination, disconnection, or cessation of operation.  Article 10 also \nobligates the Large Load Entity to enter into other agreements for the construction of needed \ndistribution system upgrades and Large Load Network Upgrades on systems other than the \nLLITO’s. \n• Article 11 provides invoicing procedures for the LLCRA, including a final invoice and true-up \nfor charges relating to the Direct Assignment Facilities and interest for late or missing payments. \n• Article 12 lays out the obligations and rights of each Party during a system emergency. \n• Article 13 states that the LLCRA is conditioned on any necessary regulatory requirements, \ndescribes the governing law of the LLCRA, and incorporates the OATT by reference. \n• Article 14 describes the notice provisions and obligations of the LLCRA. \n• Article 15 excuses performance under the LLCRA by a party due to Force Majeure as that term \nis defined in the OATT. \n• Article 16 describes Events of Default by any Party, and remedies for such Events of Default \nand further survival provisions. \n• Article 17 provides for indemnity, exclusion of consequential damages, and insurance \nrequirements for the Parties. \n• Article 18 provides for the requirements and rights of any Party to assign the LLCRA. \n• Article 19 provides that all provisions of the agreement are severable. \n• Article 20 provides for comparability and code of conduct compliance. \n• Article 21 describes the confidentiality obligations of the Parties under the LLCRA, including \nCritical Energy/Electric Infrastructure Information (“CEII”). \n• Article 22 creates notice obligations for each Party relating to the release of Hazardous \nSubstances as that term is defined in the OATT. \n• Article 23 describes information acquisition and provision requirements by the Parties. \n• Article 24 describes the information access and audit rights of the Parties under the LLCRA. \n• Article 25 creates obligations and rights relating to subcontracting to each party. \n• Article 26 provides for dispute resolution under the LLCRA. \n• Article 27 states certain representations, warranties, and covenants of each Party, including good \nstanding and authority to enter into the LLCRA. \n• Article 28 provides for miscellaneous legal provisions to ensure the clarity, legality, and \nenforceability of the LLCRA, as well as procedures for amending the LLCRA."},{"page":59,"startToken":26062,"endToken":26479,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 59 of 99 \n \n \n \n• Appendix A of the LLCRA describes the Large Load Facility, its Interconnection Point, and all \nfacilities to be constructed pursuant to the LLCRA.  Appendices A-1 and A-2 will include \ndiagrams of such facilities and interconnection and will be deemed CEII. \n• Appendix B describes the milestones for the construction of the facilities under the LLCRA as \nwell as required dates for certain LLCRA obligations. \n• Appendix C is a technical description of the Large Load Facility. \n• Appendix C-1, consistent with similar operation and maintenance provisions in ISO-NE, will \nbe specific to each LLITO and will describe the mechanism under which the LLITO will charge \nfor operation and maintenance for the Direct Assignment Facilities. \n• Appendix C-2 describes the Cost Recovery Charge and the Exit Fee, including the specific \ncalculation of each. \n• Appendix D will describe the specific credit support requirements of the LLITO, consistent with \nthe requirements of Article 10 of the LLCRA. \n• Appendix E describes the notice addresses of each Party. \nb. \nCost Allocation Mechanisms of the LLCRA \n \nThe LLCRA utilizes four mechanisms to ensure that the costs of serving the Large Load Facility \nare not passed on to other transmission customers: (1) direct assignment of costs, both initial and \nongoing, for the Direct Assignment Facilities; (2) payment of the Cost Recovery Charge when necessary \nto eliminate any transmission rate increases caused by the interconnection of the Large Load Facility \nand the construction of LLITO’s Network Upgrades; (3) payment of an Exit Fee, as applicable, upon \ntermination of the LLCRA; and (4) adequate Credit Support to cover the cost of the Direct Assignment \nFacilities and LLITO’s Network Upgrades prior to commercial operation and the Exit Fee and all \nassociated charges following commercial operation.  If the Large Load Eligible Customer and the Large \nLoad Entity are the same entity, that entity is responsible under the LLCRA for these payments and the \nCredit Support. \n \ni. \nDirect Assignment Facilities \n \nThe Direct Assignment Facilities, analogous to Interconnecting Transmission Owner’s \nInterconnection Facilities in a generator context, are sole-use facilities which will be constructed by the \nLLITO and paid for on a reimbursable basis by the Large Load Entity, consistent with the Commission’s \ncost-causation principles for sole-use facilities.  Following the construction of the Direct Assignment \nFacilities, the Large Load Entity will also pay for operation, maintenance, repair, and replacement of \nsuch facilities consistent with the individual LLITO’s methodology currently in place for analogous \ngenerator interconnection facilities.110 \n \n \n110 See LLCRA Article 10."},{"page":60,"startToken":26479,"endToken":26987,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 60 of 99 \n \n \n \nii. \nCost Recovery Charge \n \nThe Cost Recovery Charge is the primary mechanism under which the PTOs will prevent cost \nshifts to other transmission customers caused by the interconnection of the Large Load Facility.  Under \nArticle 10 and Appendix C-2 of the LLCRA, the Cost Recovery Charge will be billed monthly to the \nLarge Load Entity and will be calculated in the following manner: \nAnnual Cost Recovery Charge = Large Load Revenue Requirement – Applicable \nTransmission Service Payments \nThe Large Load Revenue Requirement is the gross cost of LLITO’s Network Upgrades multiplied by \nthe applicable Regional or Local Carrying Charge Factor and represents the revenue requirement impact \nof those upgrades.  The applicable transmission service payments are the payments made by the Large \nLoad Eligible Customer for the applicable transmission service reserved on behalf of the Large Load \nFacility (FCDS, NFCDS, or ICDS).  This difference is the net impact of the upgrades on transmission \nrates, and payment (and associated crediting) of this amount holds other transmission customers \nharmless from the rate impacts of LLITO’s Network Upgrades. \n \niii. \nExit Fee \n \nIn the event the LLCRA terminates and uncovered rate impacts remain for LLITO’s Network \nUpgrades, the Large Load Entity will pay the Exit Fee described in Article 10 and Appendix C-2.  The \nExit Fee is equal to the Net Book Value of LLITO’s Network Upgrades along with Decommissioning \nCosts, and will, like the Cost Recovery Charge, be credited against the applicable transmission revenue \nrequirement to avoid cost shifting to transmission customers. \n \niv. \nCredit Support \n \nThe LLCRA also requires the Large Load Entity to post sufficient financial assurance (“Credit \nSupport”) both prior to commercial operation to cover the costs of the Direct Assignment Facilities and \nLLITO’s Network Upgrades111 as well as subsequent to commercial operation to cover the cost of the \nExit Fee and any ongoing amounts due under the LLCRA.112  Due to differing financial assurance \npolicies among the PTOs, the specific form, process, and amounts for Credit Support will be described \nin a PTO-specific Appendix D to be negotiated by the Parties, but nevertheless complying with Article \n10 of the LLCRA.  Provision of Credit Support throughout the term of the LLCRA will ensure that the \nLLITO is fully covered in the event of default or insolvency by the Large Load Entity, and in turn \nensures that no costs caused by such default or insolvency will be passed on to other customers. \n \nc. \nThe LLCRA Meets the FPA Section 205 Standard \n \nIn the Show Cause Order, and in acting on the Secretary of Energy’s Advance Notice of \nProposed Rulemaking on large loads, the Commission recognized the extraordinary growth in requests \n \n111 See id. Article 10.6.  Credit Support provided under Article 10.6 will be consistent with the individual milestone \nschedule contained in Appendix B. \n112 See Show Cause Order at P 80 (preliminarily finding that a cost recovery agreement “should include a credit support \n(or other financial security) requirement sufficient to secure the obligations” to pay the amounts owed)."},{"page":61,"startToken":26987,"endToken":27576,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 61 of 99 \n \n \n \nby data centers and other unprecedentedly large loads to interconnect to the transmission system.113  It \nis essential that every Commission-jurisdictional transmission operator have a just and reasonable \nprocess to efficiently and fairly interconnect these loads and ensure that other transmission customers \ndo not bear the costs of interconnecting these large loads, both in the interest of fairness and cost-\ncausation principles as well as affordability.  As the Show Cause Order likewise points out, \nCommission-jurisdictional cost recovery arrangements for network upgrades caused by large loads are \nan essential part of a just and reasonable transmission tariff.114  Accordingly, in the Show Cause Order \nthe Commission contemplated a pro forma cost recovery agreement between ISO-NE, the applicable \ntransmission owner, and the eligible transmission customer, who was procuring transmission service \neither for itself as the owner of a proposed large load or on behalf of a large load as an EDC. \n \nHowever, the eligible transmission customer/ISO-NE/transmission owner cost recovery \nagreement construct is insufficient to ensure that such cost recovery arrangements are effective, just, \nand reasonable.  The eligible transmission customer is often a simple pass-through obtaining \ntransmission service on behalf of a different entity which owns and operates the proposed load.  In such \ncases, which would be mandatory in jurisdictions that do not allow unbundling of transmission service, \nif the large load failed to materialize, it would be the EDC, the retail electric utility, which would be \nlegally responsible for the cost impacts of the large load’s network upgrades, which could easily run to \nthe hundreds of millions of dollars.  In that case, the EDC would need to rely on an entirely separate \nagreement with the large load itself in order to indemnify itself against such a massive risk, and it is \nuncertain under what mechanism the EDC could compel the large load to enter into such an unfavorable \narrangement given an EDC’s obligation to serve loads in its service territory consistent with state law.   \n \nSuch potentially massive liability poses an unjust and unreasonable risk either to transmission \ncustomers (due to nonpayment for the large load’s network upgrades causing cost shifting) or to EDCs \nand their customers (due to the liability for the cost impact of those upgrades).  Even if such back-end \nindemnifications could be arranged, asking a party to accept, without indemnification in the agreement \nitself, a potential nine-figure liability for network upgrades that party is not causing is neither just nor \nreasonable.  Accordingly, the only just and reasonable method for recovering costs associated with a \nlarge load’s network upgrades is through a cost recovery agreement to which the large load itself is a \nparty.  Accordingly, the PTOs propose that the pro forma LLCRA between the applicable transmission \nowner, eligible customer, and large load is a just and reasonable cost allocation mechanism that \naddresses the cost recovery and cost-shifting issues raised by the Show Cause Order.115  The \n \n113 See id. at PP 1, 6-8; Interconnection of Large Loads to the Interstate Transmission System, 195 FERC ¶ 61,045, at \nP 2 (2026); Interconnection of Large Loads to the Interstate Transmission System, Advance Notice of Proposed \nRulemaking, Docket No. RM26-4-000 (Oct. 23, 2025). \n114 See Show Cause Order at PP 64, 74, 78 (preliminarily finding that, “in order to prevent unjust and unreasonable \ncost shifting among transmission customers, it appears necessary” to require a cost recovery agreement). \n115Jurisdictional concerns of the LLCRA are discussed in the section titled “The LLCRA is subject to the \nCommission’s jurisdiction,” infra."},{"page":62,"startToken":27576,"endToken":28145,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 62 of 99 \n \n \n \nCommission also recognized and allowed for other jurisdictional cost-recovery arrangements in the \nShow Cause Order, including arrangements similar to the proposed LLCRA.116 \n \nThe Show Cause Order expressly invited this showing.  Although the Commission declined to \npreliminarily find that cost recovery agreements with the large load customer are necessary, it directed \n“further briefing on whether it would be appropriate for such an agreement to substitute for the \nrequirement on the Eligible Customer to enter into a cost recovery agreement with the transmission \nowner, if the agreement with the large load customer provided comparable or greater protection against \ncost shifting among transmission customers than an agreement between the transmission owner and the \nEligible Customer would.”117  The Commission further recognized that “there may be a variety of \npossible approaches to protect customers from significant cost shifts associated with network upgrades \ntriggered by large loads,”118 and asked that any Section 205 filing “explain which of the Commission’s \nabove directives their filing addresses and how it resolves them.”119  The LLCRA responds directly to \ndirective (1)(b) of the Show Cause Order and to the Commission’s briefing request. \n \nThe LLCRA provides greater protection than the Eligible Customer construct in at least four \nrespects.  First, it places the payment obligation on the entity whose request causes the Network \nUpgrades, consistent with the cost-causation principle that rates must “reflect to some degree the costs \nactually caused by the customer who must pay for them.”120  Second, the Cost Recovery Charge is \ncalculated from the actual revenue requirement of LLITO’s Network Upgrades, net of transmission \nservice payments, so that the protection scales with the cost actually incurred rather than with a fixed \nrevenue commitment.  That design responds to Commissioner Chang’s concern that “bilateral \nagreements that simply provide transmission revenue contributions untethered from any assessment of \nthe actual cost of providing transmission service induced by individual large loads may be insufficient \nto adequately protect other customers against unjustified cost shifts.”121  Third, the Exit Fee, equal to \nthe Net Book Value of LLITO’s Network Upgrades plus Decommissioning Costs, addresses the \nmismatch between long-lived transmission investment and shorter-term load commitments.  Fourth, \nCredit Support posted directly by the Large Load Entity secures these obligations throughout the term, \nconsistent with the Commission’s preliminary finding that a cost recovery agreement should include \n \n116 See Show Cause Order at P 79 (“To reduce duplicative credit requirements and transaction costs, we direct further \nbriefing on whether it would be appropriate for such an agreement to substitute for the requirement on the Eligible \nCustomer to enter into a cost recovery agreement with the transmission owner, if the agreement with the large load \ncustomer provided comparable or greater protection against cost shifting among transmission customers than an \nagreement between the transmission owner and the Eligible Customer would.”). \n117 Id. \n118 Id. at P 122. \n119 Id. at P 35; see also id. at PP 3, 32 (setting out directive (1)(b)). \n120 Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004); see Show Cause Order at P \n78 & n.186. \n121 Show Cause Order, concur op. (Comm’r Chang) at P 4.  Commissioner See likewise observed that “cost-recovery \nagreements between a transmission owner and a large load customer itself could satisfy an Eligible Customer’s \nfinancial security requirements.”  Id., concur op. (Comm’r See) at P 4."},{"page":63,"startToken":28145,"endToken":28644,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 63 of 99 \n \n \n \ncredit support “sufficient to secure” the obligations owed, and with its recognition that credit support \nposted by a large load may be relied upon “to avoid creating duplicative credit support requirements.”122 \n \nThe LLCRA’s methodology for the Cost Recovery Charge also falls within the range the \nCommission anticipated.  While the Commission preliminarily found that a minimum contribution \nshould be based on the level of transmission service requested, it expressly recognized that “there may \nbe other just and reasonable methods for determining this minimum contribution, including methods \nthat account for potential timing differences between when costs are incurred to develop needed \nNetwork Upgrades and the pace at which the large load ramps toward energizing at its full level of \nrequested service.”123  Because the Cost Recovery Charge equals the Large Load Revenue Requirement \nless the Applicable Transmission Service Payments in each period, it automatically accounts for such \nramp-period timing differences.  Finally, consistent with the Commission’s expectation that cost \nrecovery payments “will be appropriately credited toward transmission owners’ transmission revenue \nrequirements consistent with the Commission’s cost-of-service regulations,” the Cost Recovery Charge \nand any Exit Fee are credited against the LLITO’s transmission revenue requirement.124 \n \nAs a construction and cost recovery agreement, the correct parties for the LLCRA are the \nLLITO, the Large Load Eligible Customer, and the Large Load Entity.  The LLITO constructs the \nfacilities described in the LLCRA, the Large Load Entity pays for those facilities through both direct \nassignment and the Cost Recovery Charge and Exit Fee, and the Large Load Eligible Customer is a \nnecessary party both to provide information necessary for the calculation of payments under the \nagreement, alignment with tariff processes, and operational and system requirements. \n \nIn addition to being the surest guarantor of cost recovery for large load network upgrades and \nassociated facilities, having the Large Load Entity as a party to the LLCRA brings significant benefits \nto all stakeholders in the large load interconnection process.  By creating direct contractual obligations \nfor communications, information sharing, design, engineering, construction, and credit support rather \nthan requiring that the Large Load Eligible Customer be a pass-through to the Large Load Entity, the \nentire large load interconnection process becomes much more efficient and legally certain even though \nno electric service is being provided under the LLCRA.  The LLCRA likewise becomes an efficient \nmechanism under which the Large Load Eligible Customer can meet the numerous requirements \n(including deposits, information provision, and other compliance obligations) of the OATT in an \nefficient and effective manner.  Billing and payments for the pertinent cost recovery are likewise \nstreamlined, as is an elimination of the complexity of the Large Load Entity (being the entity ultimately \nresponsible for LLCRA costs consistent with the Commission’s cost-causation principles) providing \nbackstop financial assurance and indemnification for the Large Load Eligible Customer in order to avoid \nadverse outcomes. \n \n \n122 Id. at P 80. \n123 Id. \n124 Id. at P 81 (citing 18 C.F.R. part 101)."},{"page":64,"startToken":28644,"endToken":29152,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 64 of 99 \n \n \n \nFinally and as described above, the LLCRA meets the burden of section 205 of the FPA by \nbeing a just and reasonable solution, even if alternative solutions may exist.  Under section 205, a \nutility’s proposal “need not be the only reasonable methodology, or even the most accurate,”125 and the \nCommission plays “an essentially passive and reactive role” in evaluating it.126  As members of the \nCommission have emphasized, Section 205 is a “relatively capacious standard . . . that allows [the \nCommission] to accept a potentially broad range of proposals provided they are shown to be just and \nreasonable and not unduly discriminatory or preferential.”127  The Commission reaffirmed this principle \nin its most recent large load order, explaining that “[f]or filings made under FPA section 205, the \nCommission evaluates whether the proposal in the filing is just and reasonable, and not whether \nalternative proposals are more or less reasonable than the filing party’s proposal.”128  The LLCRA as \nproposed meets the concerns raised by the Commission in the Show Cause Order and represents the \nresults of an extensive stakeholder process, including being part of the Tariff Revisions passing a two-\nthirds advisory vote at the NEPOOL Transmission Committee and a two-thirds advisory vote of the \nentire NEPOOL Participants Committee. \n \nd. \nThe LLCRA is subject to the Commission’s jurisdiction \nAlthough the LLCRA does not itself provide transmission or interconnection service, it is \nsubject to the Commission’s jurisdiction under section 205 because it directly and significantly affects \nCommission-jurisdictional transmission rates and services.  The LLCRA allocates and recovers the \ncosts of Commission-jurisdictional transmission facilities (LLITO’s Network Upgrades and the Direct \nAssignment Facilities) that are constructed to enable jurisdictional transmission service to Large Load \nFacilities, and it requires that the resulting payments be credited against the LLITO’s Commission-\njurisdictional transmission revenue requirement.  The Commission has already found that cost recovery \nagreements of this kind “directly affect Commission-jurisdictional transmission rates” and “should be \nfiled with the Commission.”129  At the same time, the LLCRA does not impermissibly intrude on \njurisdictional areas solely reserved to the states, including retail sales of electricity and siting and \nconstruction decisions associated with load and transmission facilities.  No jurisdictional concerns for \nthe LLCRA were raised as part of the NEPOOL stakeholder process.  Accordingly, it is within the \nCommission’s authority to accept and approve the LLCRA as just and reasonable consistent with \nsection 205 of the FPA. \n \n \n125 Oxy USA, 64 F.3d at 692. \n126 Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (quoting City of Winnfield, 744 F.2d at \n871). \n127 Show Cause Order, concur op. (Comm’r LaCerte) at P 3 (citing Oxy USA, 64 F.3d at 692; City of Winnfield, 744 \nF.2d at 874-75). \n128 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 29 (2026) (“PJM IRAS Order”) (citing Cities of Bethany, \n727 F.2d at 1136); see also id. at P 50. \n129 Show Cause Order at P 79."},{"page":65,"startToken":29152,"endToken":29659,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 65 of 99 \n \n \n \ni. \nThe LLCRA directly and significantly affects Commission-\njurisdictional transmission rates and services and does not \nimpermissibly intrude on state authority \nIn the Show Cause Order, the Commission based its assertion of jurisdiction in part on it having \njurisdiction over “transmission of electricity in interstate commerce, including all facilities used for such \nsale and transmission.”130  Furthermore, the Commission recognizes that its jurisdiction extends to not \nonly “the rates, charges, and classifications” of such service, but also “practices directly affecting such \ntransmission of electricity.”131  In terms of the transmission study process and the construction of \nnetwork upgrades necessary to interconnect Eligible Customers, the Commission found that such a \nstudy process “directly affects Commission-jurisdictional transmission rates” and is accordingly \njurisdictional.132 \n \nIn addition to the study processes and facilities used for transmission, the Commission also has \njurisdiction over the costs of upgrades to the transmission system and ensuring that the costs of those \nupgrades do not result in unjust, unreasonable, or unduly preferential transmission rates due to cost \nshifting or other concerns.133  Accordingly, any rate or practice that directly affects such rates by \nensuring that such cost shifting does not occur is subject to the Commission’s jurisdiction so long as it \ndoes not intrude on areas reserved solely for the states. \n \nSection 205(c) of the FPA requires every public utility to file not only its rates and charges for \njurisdictional transmission, but also “the classifications, practices, and regulations affecting such rates \nand charges, together with all contracts which in any manner affect or relate to such rates, charges, \nclassifications, and services.”134  Section 205(a) requires that all “rules and regulations affecting or \npertaining to” jurisdictional rates be just and reasonable, and section 206(a) extends the Commission’s \nremedial authority to any “rule, regulation, practice, or contract affecting” such rates.135  The Supreme \nCourt has endorsed “a common-sense construction of the FPA’s language, limiting FERC’s ‘affecting’ \njurisdiction to rules or practices that ‘directly affect the wholesale rate,’”136 and the Commission has \napplied that construction to practices directly affecting transmission rates.137  The filing obligation is \nfurther informed by the Commission’s rule of reason, under which the statute “must reasonably be read \nto require the recitation of only those practices that affect rates and services significantly, that are \n \n130 Id. at P 44 (emphasis added) (citing 16 U.S.C. § 824(b)(1)). \n131 Id. (citing FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278 (2016) (“EPSA”)). \n132 Id. at P 45. \n133 See id. at P 66. \n134 16 U.S.C. § 824d(c); see PacifiCorp, 127 FERC ¶ 61,144, at P 9 (2009) (“PacifiCorp”); ALLETE, Inc., 161 FERC \n¶ 61,013, at P 13 (2017) (“ALLETE”). \n135 16 U.S.C. §§ 824d(a), 824e(a). \n136 EPSA, 577 U.S. at 278 (quoting Cal. Indep. Sys. Operator Corp. v. FERC, 372 F.3d 395, 403 (D.C. Cir. 2004)) \n(cleaned up). \n137 Show Cause Order at PP 44-45, 66."},{"page":66,"startToken":29659,"endToken":30230,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 66 of 99 \n \n \n \nrealistically susceptible of specification, and that are not so generally understood as to render recitation \nsuperfluous.”138   \n \nCritically, the Commission’s jurisdiction under these provisions does not depend on whether a \ncontract itself provides transmission service.  In PacifiCorp, the Commission found that facilities \nagreements between PacifiCorp and the Bonneville Power Administration were jurisdictional because, \n“while they do not themselves provide for transmission service, all of the contracts involve the \nconstruction or replacement of facilities or equipment on PacifiCorp’s transmission system in order for \nPacifiCorp to provide jurisdictional transmission service,” and a portion of the project costs was paid \nby PacifiCorp’s customers; “[t]his being the case, such agreements affect or relate to jurisdictional \ntransmission service and rates.”139  The Commission then held that, where a third party pays the utility \nfor work on the utility’s facilities, the agreement must be on file “because [the third party’s] payment \nsignificantly affects or relates to PacifiCorp’s rates and services.”140  The Commission rejected the \nargument that only certain enumerated categories of agreements must be filed, explaining that “the \nCommission has never stated that its jurisdiction is limited to just these specific kinds of contracts,”141 \nand it characterized the agreements as “in the nature of contracts providing contributions in aid of \nconstruction – essentially, they provide a pre-payment of expenses that would otherwise be recoverable \nin rates over time – and must be filed.”142  The Commission likewise required filing of an agreement \nunder which a generation developer paid for interconnection-related facilities that PacifiCorp would \nown, because those payments “constitute ‘a charge connected to jurisdictional service’ and would affect \nPacifiCorp’s rates.”143 \n \nThe LLCRA presents a far stronger case for jurisdiction than the agreements in PacifiCorp.  \nUnder the LLCRA, the Large Load Entity pays the LLITO for the construction of Direct Assignment \nFacilities on the LLITO’s transmission system, which is precisely the type of third-party payment for \nwork on a utility’s facilities that the Commission found “significantly affects or relates to” jurisdictional \nrates and services.  More fundamentally, the Cost Recovery Charge and Exit Fee are calculated by \nreference to the revenue requirement and Net Book Value of LLITO’s Network Upgrades, which are \nCommission-jurisdictional facilities whose costs are recovered through Commission-jurisdictional \ntransmission rates, and those payments are credited directly against the LLITO’s transmission revenue \nrequirement.  As the Commission explained in the Show Cause Order, “[t]he costs of those upgrades to \nthe transmission system (i.e., network upgrades) necessary to provide transmission service to Eligible \nCustomers on behalf of large loads are inputs to jurisdictional transmission rates, and thus directly affect \n \n138 PacifiCorp at P 9 (citing City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985)); see also ALLETE at \nP 13 (rule of reason permits utilities to forgo filing contracts that deal only with matters of “practical insignificance”) \n(quoting Pub. Serv. Comm’n of N.Y. v. FERC, 813 F.2d 448, 454 (D.C. Cir. 1987)). \n139 PacifiCorp at P 10. \n140 Id. at P 12; see id. at P 13. \n141 Id. at P 14. \n142 Id. at P 16 (citing Prior Notice and Filing Requirements Under Part II of the Federal Power Act, 64 FERC ¶ \n61,139, at 61,982, 61,988-92 (“Prior Notice Order”), order on clarification, 65 FERC ¶ 61,081 (1993)). \n143 Id. at P 19 (quoting Prior Notice Order, 64 FERC at 61,993)."},{"page":67,"startToken":30230,"endToken":30783,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 67 of 99 \n \n \n \nthe Commission-jurisdictional rates paid by transmission customers.”144  An agreement that determines \nwhether, and to what extent, those costs are borne by the Large Load Entity rather than by other \ntransmission customers necessarily affects jurisdictional transmission rates directly, not remotely or \nindirectly. \n \nThe Commission’s decision in ALLETE confirms that the LLCRA lies well above the \nsignificance threshold.  There, the Commission found that three pre-construction agreements for the \nGreat Northern Transmission Line need not be filed because they “act as a guide for development \nactivities that must occur prior to construction” and only “[i]n limited respects . . . provide terms and \nconditions related to cost sharing that could potentially affect rates for future jurisdictional services.”145  \nThe Commission emphasized that “jurisdictional activity related to the Great Northern Transmission \nLine project is addressed in additional agreements” that ALLETE had filed, including a construction \nmanagement agreement and a system improvements agreement under which ALLETE would construct \nupgrades and its counterparty would contribute to their cost.146  The Commission also made clear that \napplying the rule of reason to excuse filing “does not make an agreement non-jurisdictional.”147  The \nLLCRA is not a preliminary development framework.  It is the operative agreement that governs the \ndesign, procurement, and construction of jurisdictional transmission facilities, allocates their costs, and \nfixes the payments that will be credited against transmission rates over a 40-year Initial Term.  It is \ntherefore analogous to the construction and cost-contribution agreements that ALLETE filed and the \nCommission accepted, not to the preliminary agreements the Commission found it need not review. \n \nThe LLCRA’s structure also tracks agreements the Commission has long treated as \njurisdictional even though they do not themselves convey transmission service.  The Commission has \nexplained that “interconnection is part and parcel of transmission of electric energy in interstate \ncommerce, and thus interconnection service is part and parcel of jurisdictional transmission service,”148 \nand it has exercised that jurisdiction over the interconnection of wholesale load to the transmission \nsystem.149  The D.C. Circuit affirmed the Commission’s standardized interconnection agreements, \nobserving that “interconnections appear to be relationships between parties with respect to electricity \n \n144 Show Cause Order at P 66. \n145 ALLETE at P 14. \n146 Id. at PP 7, 14 & nn.11-12 (citing ALLETE, Inc., Construction Management Agreement, Docket No. \nER17-1147-000 (Apr. 28, 2017) (delegated letter order accepting Construction Management Agreement), and \ndelegated letter orders issued April 28, 2017 in Docket Nos. ER17-1148-000, ER17-1149-000, and ER17-1150-000 \naccepting the Operation and Maintenance Agreement, Transmission Capacity Exchange Agreement, and System \nImprovements Agreement); see also ALLETE, Inc., Transmittal Letter, Docket No. ER17-1144-000, Attachment A \n(Mar. 10, 2017) (describing System Improvements Agreement); Midcontinent Indep. Sys. Operator, Inc., 149 FERC \n¶ 61,161 (2014) (accepting Multi-Party Facilities Construction Agreement). \n147 Id. at P 14 n.24 (citing LG&E Energy Mktg., Inc., 123 FERC ¶ 61,147, at P 12 & n.20 (2008)). \n148 Pac. Gas & Elec. Co., 115 FERC ¶ 61,193, at P 36 (2006); see Tenn. Power Co., 90 FERC ¶ 61,238, at 61,761 \n(2000); Order No. 2003, 104 FERC ¶ 61,103, at P 9. \n149 Pac. Gas & Elec. Co., 109 FERC ¶ 61,392, at P 37 (2004); Pac. Gas & Elec. Co., 115 FERC ¶ 61,193, at PP 36-38; \nsee Show Cause Order at P 44 & nn.128-29."},{"page":68,"startToken":30783,"endToken":31325,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 68 of 99 \n \n \n \nflowing over facilities” and that, “[b]y establishing standard agreements [the Commission] has exercised \nits jurisdiction over the terms of those relationships.”150  Generator interconnection service “in and of \nitself does not convey transmission service,”151 yet the construction and cost-responsibility provisions \nof generator interconnection agreements are plainly jurisdictional.  The LLCRA’s construction \nprovisions are modeled on Article 5 of the Large Generator Interconnection Agreement in Schedule 22 \nof the OATT, and the Tariff already allocates the costs of network upgrades needed to accommodate \nRegional Network Service requests in the same manner as generator upgrades under Schedule 11.152 \n \nThe LLCRA, as a cost allocation and construction agreement for the construction of \nCommission-jurisdictional transmission facilities, with associated terms and conditions consistent with \nother Commission-jurisdictional agreements, thus falls cleanly within the jurisdictional space described \nabove.  Accordingly, the specific jurisdictional issue is whether the LLCRA impermissibly intrudes on \njurisdiction reserved for the states under Commission precedent and the FPA. \n \nThe Commission also recognized in the Show Cause Order such areas of state authority, \nrecognizing “that states will continue to regulate: (1) the specific terms of retail sales to large load; (2) \nwhich entities may make retail sales within their borders, including which entities are legally permitted \nto provide electricity to retail large load customers; and (3) any siting decisions and construction \nassociated with the large load project.”153  The LLCRA does not intrude on any of these areas.  The \nLLCRA does not specify terms of retail sales or distribution of electricity to any customer, does not \ndetermine which entities are permitted to make retail sales or provide electricity to retail customers, and \nleaves all siting and construction decisions associated with the Large Load Network Upgrades to the \nstate’s authority the same as any other Commission-jurisdictional agreement or rate for the construction \nof transmission facilities.  To the extent that the Commission does determine that any provisions of the \nLLCRA do constitute an intrusion on such areas, the PTOs respectfully request that the Commission \nidentify such intrusions so that a fully jurisdictional LLCRA between the LLITO, the Large Load Entity, \nand the Large Load Eligible Customer may be submitted and approved. \n \nThe Show Cause Order makes clear that the Commission’s finding that cost recovery \nagreements with large load customers should be filed “is in no way intended to preempt or interfere \nwith the ability of states to implement ratepayer protection measures designed to mitigate cost shifting \namong retail customers, such as through state-jurisdictional large load tariffs.”154  The LLCRA is fully \nconsistent with that cooperative-federalism framework.  The Cost Recovery Charge and Exit Fee are \ntransmission-level charges calculated from the revenue requirement of Commission-jurisdictional \nfacilities and credited against the LLITO’s Commission-jurisdictional transmission revenue \nrequirement; they do not set the price, quantity, or terms of any retail sale.  States retain full authority to \n \n150 Nat’l Ass’n of Regul. Util. Comm’rs, 475 F.3d at 1280-82. \n151 Show Cause Order at P 111 n.258. \n152 See OATT Schedule 22, Appendix 11, Large Generator Interconnection Agreement, Article 5; OATT Schedule \n11; Show Cause Order at P 23 (citing ISO-NE Tariff § II.19.4). \n153 Show Cause Order at P 46. \n154 Id. at P 79 n.188."},{"page":69,"startToken":31325,"endToken":31902,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 69 of 99 \n \n \n \ndetermine “how Commission-approved rates are collected among the relevant retail consumers,”155 and \nnothing in the LLCRA limits a state’s authority to adopt additional retail-level protections.  In accepting \na transmission security agreement between a transmission-owning utility and a retail data center \ncustomer, the Commission likewise confirmed that the state commission “retains authority to establish \nterms of retail service” between the utility and the customer.156  \n \nIn the Show Cause Order, the Commission acknowledged several cost recovery agreements \ndirectly between the large load and the transmission owner that were accepted by the Commission \nconsistent with the standard of section 205 of the FPA.157  In the ISO-NE region, the Commission has \naccepted numerous viability study agreements filed by the PTOs that were contracts directly between \nthe applicable transmission owner and a prospective Large Load Entity, demonstrating that the sole fact \nof a potential retail customer being a party to an agreement does not raise jurisdictional questions under \nthe FPA.158  The Commission has likewise accepted under section 205 agreements between \ntransmission owners and other entities to perform transmission-related services, including construction \nrelated to the undergrounding of a transmission line requested by a property developer.159  The LLCRA, \nas a service and construction agreement between a transmission owner and another entity, is likewise a \njurisdictional agreement. \n \nThese accepted agreements include agreements with large loads that are retail customers and \nwill not themselves take service under an OATT.  In ComEd, the utility filed a Transmission Security \nAgreement with a data center developer that would be “a ComEd retail customer that will not take \ntransmission service under the PJM Open Access Transmission Tariff,” explaining that it was filing \nunder Section 205 because the agreement’s provisions “may be construed as affecting rates and \npractices for FERC jurisdictional transmission service.”160  The Commission accepted the agreement, \nnoting the utility’s attestation that shortfall payments and early or partial termination fees would be \ncredited against its transmission revenue requirement.161  Similarly, the Commission accepted a \nconstruction service agreement between AES Ohio and Amazon Data Services governing new \ntransmission facilities needed to serve a data center that would be served exclusively under a state-\n \n155 Id. at P 67 (citing PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 167 (2025)). \n156 Commw. Edison Co., 194 FERC ¶ 61,109, at P 23 (2026) (“ComEd”). \n157 Show Cause Order at P 67 & n.172 (citing Commw. Edison Co., 194 FERC ¶ 61,106 (2026); ComEd, 194 FERC ¶ \n61,109; Commw. Edison Co., 194 FERC ¶ 61,110 (2026); Commw. Edison Co., 194 FERC ¶ 61,113 (2026); PECO \nEnergy Co., 193 FERC ¶ 61,148 (2025); Dayton Power & Light Co., 192 FERC ¶ 61,103 (2025); Dayton Power & \nLight Co., 189 FERC ¶ 61,220 (2024)); id. at P 79 & n.187. \n158 See id. at P 8 n.26 (citing NSTAR Elec. Co., Docket No. ER21-2696-000 (Oct. 14, 2021) (delegated order); Pub. \nServ. Co. of N.H., Docket No. ER24-2522-000 (Aug. 30, 2024) (delegated order); NSTAR Elec. Co., Docket No. \nER25-1796-000 (May 27, 2025) (delegated order); NSTAR Elec. Co., Docket No. ER25-1795-000 (May 27, 2025) \n(delegated order); The Conn. Light & Power Co., Docket No. ER26-1158-000 (Mar. 18, 2026) (delegated order); The \nConn. Light & Power Co., Docket No. ER26-1597-000 (Apr. 21, 2026) (delegated order)). \n159See The Narragansett Elec. Co., Docket No. ER16-986-000 (March 21, 2016) (delegated order). \n160 ComEd, 194 FERC ¶ 61,109, at P 3. \n161 Id."},{"page":70,"startToken":31902,"endToken":32335,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 70 of 99 \n \n \n \njurisdictional retail tariff.162  The LLCRA serves the same function as these agreements, but on a pro \nforma, non-discriminatory basis available to every Large Load Entity in New England. \n \nNor does the participation of the Large Load Entity, rather than only an Eligible Customer, place \nthe LLCRA outside the Commission’s jurisdiction.  Section 205(c)’s filing obligation attaches to the \npublic utility and reaches “all contracts which in any manner affect or relate to” its jurisdictional rates \nand services, without regard to the identity of the counterparty.163  The counterparties in PacifiCorp \nwere the Bonneville Power Administration and a generation developer, and the Commission found the \nagreements jurisdictional based on their effect on PacifiCorp’s rates and services, not on the \ncounterparty’s status.164  The Show Cause Order itself confirms that agreements between a transmission \nowner and a large load customer “directly affect Commission-jurisdictional transmission rates,” \nwhether entered into “voluntarily or pursuant to state law.”165 \n \nii. \nThe LLCRA is not analogous to the agreement found non-\njurisdictional in the Tri-State Order \n \nIn 2025, the Commission specifically ruled on the jurisdiction of an agreement governing the \ninterconnection of large loads in Tri-State.  In that proceeding, a FERC-jurisdictional transmission \nowner, Tri-State, proposed a High Impact Load (“HIL”) Tariff, with an associated High Impact Load \nAgreement (“HILA”) to be executed between Tri-State and the EDCs for whom Tri-State provided \ntransmission service.166  Specifically, the HILA required the applicable EDC to enter into an agreement, \nknown as a Member Contract with High Impact Load (“MCHIL”),167 with a large load retail customer \nunder which that customer would agree to certain terms and conditions associated with the electric \nservice the EDC would provide to that customer, including minimum load and energy requirements and \nenergy and demand limits.168  Tri-State asserted that placing these contractual obligations on the EDC \nwas jurisdictional because the HILA was “in connection with the . . . sale of electric energy.”169 \n \nThe Commission rejected the HILA (and accordingly the HIL Tariff) on jurisdictional grounds, \nfinding that the HILA constituted “an impermissible intrusion on retail rate regulation.”170  The Order \nfound that the HILA effectively set specific terms and conditions of retail service by requiring the EDC \n \n162 Dayton Power & Light Co., 189 FERC ¶ 61,220. \n163 16 U.S.C. § 824d(c). \n164 See PacifiCorp at PP 10, 12, 19. \n165 Show Cause Order at P 79. \n166 Tri-State at PP 1, 11. \n167 Id. at P 12. \n168 Id. at PP 48-49. \n169 Id. at P 24. \n170 Id. at P 45."},{"page":71,"startToken":32335,"endToken":32863,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 71 of 99 \n \n \n \nto execute an MCHIL with its large load retail customer.171  Specifically, the Commission held that \nsetting “a minimum amount of energy that a large load customer must purchase at retail” rendered the \nHILA outside of its jurisdiction.172  More generally, the Commission found that “Tri-State has not \nprovided a sufficient basis for the Commission to find that its proposal does not regulate the terms and \nconditions of a HIL Customer's retail service in ways that are beyond the Commission's authority.”173  \nFinally, the Commission noted that “specification of terms of sale at retail is a job for the states alone.”174 \n \n \nThe LLCRA and the HILA in Tri-State are not analogous.  The LLCRA is an agreement for the \nconstruction of FERC-jurisdictional facilities and the cost allocation for the construction of those \nfacilities, both as directly assigned to the beneficiary of sole-use facilities (the Direct Assignment \nFacilities) or the payment of the Cost Recovery Charge to hold other ratepayers harmless from the rate \nimpacts on transmission service caused by the construction of necessary Network Upgrades consistent \nwith the agreement.  No electric service, whether retail, wholesale, transmission, or distribution, is being \nprovided pursuant to the LLCRA, and the LLCRA places no terms and conditions on the retail service \nbeing provided to a large load customer.  Under the Tariff Revisions, transmission service will be \nprovided to the Large Load Entity either directly if the Large Load Entity is the Large Load Eligible \nCustomer, or through the Large Load Eligible Customer on behalf of the Large Load Entity consistent \nwith a bundled state retail rate.  Wholesale and retail electric purchases and sales will likewise be \nprovided through the ISO-NE markets and a state-approved retail electric supplier or through the \napplicable EDC.   \n \nThe PTOs do not dispute that “specification of terms of sale at retail is a job for the states \nalone,”175 but the LLCRA provides no such specifications.  The LLCRA does not establish minimum \nand maximum energy requirements, which from an Eligible Customer standpoint will be the provisions \nof the OATT and from an Eligible Customer-retail customer standpoint will be determined by the \nultimate retail tariff or contract between the Eligible Customer and the retail customer.  None of the \ngrounds for which the Commission rejected the HILA are present in the LLCRA, and accordingly Tri-\nState has no bearing on the LLCRA’s jurisdictional status. \n \nThe LLCRA is also distinguishable from Tri-State on a second, independent ground.  As \ndescribed above, the HILA operated by requiring the EDC to impose terms of retail service on its retail \ncustomer.  The LLCRA, by contrast, operates at the transmission level: it addresses the construction of \nCommission-jurisdictional transmission facilities and ensures that their costs, which are inputs to \nCommission-jurisdictional transmission rates, are not shifted to other transmission customers, which is \nprecisely the subject matter the Show Cause Order identified as within the Commission’s authority.176  \n \n171 Id. \n172 Id. at P 48. \n173 Id. at P 49. \n174 Id. at P 50 (internal quotation marks omitted) (citing EPSA, 577 U.S. at 280). \n175 Id. \n176 Show Cause Order at PP 66, 79."},{"page":72,"startToken":32863,"endToken":33370,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 72 of 99 \n \n \n \nThe LLCRA does not require any EDC to enter into any retail contract, and it imposes no minimum \npurchase obligation, demand limit, or other term of retail service.  \n \nThe Commission’s subsequent treatment of Tri-State’s revised proposal reinforces the point.  In \nTri-State II, the Commission accepted a revised High Impact Load tariff and agreement.  In the later \nPJM proceeding, parties distinguished the accepted Tri-State tariff on the ground that, unlike PJM’s \nproposal, it left the distribution utility discretion to determine whether and how retail customers would \nbe affected.177  The LLCRA likewise leaves every decision regarding the terms of retail service with \nthe EDC and the state regulator, and, unlike the original HILA, it does not condition transmission service \non the execution of any retail contract. \n \niii. \nThe LLCRA avoids the jurisdictional defects identified in the \nPJM IRAS Order \nMost recently, the Commission rejected the core of PJM’s large load proposal, the Interim \nResource Adequacy Service (“IRAS”) framework, in part because certain aspects of the proposal \n“appear[ed] to present an impermissible intrusion on retail rate regulation.”178  The Commission \nidentified three defects in the proposed tariff language: provisions that “appear[ed] to place obligations \ndirectly on Eligible New Large Loads, which are, for the most part, retail customers”; provisions that \n“appear[ed] to dictate which retail customers taking retail service will be curtailed”; and a compensation \nframework that “appear[ed] to establish a retail rate.”179  The Commission further found that the \nproposal appeared to allow a retail regulator to set a wholesale rate.180  Applying EPSA, the Commission \nreiterated that a regulation that “specifies terms of sale at retail” exceeds its authority, no matter how \ndirect or dramatic its effect on wholesale rates.181  The LLCRA presents none of these defects. \n \nFirst, the LLCRA does not dictate which retail customers will be served or curtailed.  It contains \nno curtailment, load-reduction, or priority-of-service provision; the curtailment priority of a Large Load \nFacility, like that of any other load, remains governed by the OATT, applicable Reliability Standards, \nand state-jurisdictional retail arrangements.  Second, the LLCRA does not establish a retail rate.  The \nCommission objected that the IRAS tariff created “a framework whereby retail customers will be paid \nby other retail customers” for a purported wholesale service, without specifying which wholesale \ncustomer would be paid or how.182  The LLCRA’s payment stream is entirely different and fully \nspecified: the Large Load Entity pays the Cost Recovery Charge, any Exit Fee, and the costs of the \nDirect Assignment Facilities to the LLITO, and those amounts are credited against the LLITO’s \n \n177 Tri-State II, 196 FERC ¶ 61,127; see PJM IRAS Order at PP 72 (summarizing arguments distinguishing Tri-State \nII), 66 & n.158 (summarizing PJM’s reliance on Tri-State II, 196 FERC ¶ 61,127, at P 68). \n178 PJM IRAS Order at P 77. \n179 Id. \n180 Id. at P 83. \n181 Id. at P 79 (citing EPSA, 577 U.S. at 279-80). \n182 PJM IRAS Order at P 82."},{"page":73,"startToken":33370,"endToken":33840,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 73 of 99 \n \n \n \nCommission-jurisdictional transmission revenue requirement, to the benefit of all transmission \ncustomers.  No retail customer is compensated, and no amount is collected from other retail customers.  \nThird, the LLCRA does not allow a state regulator or an EDC to set or vary a Commission-jurisdictional \ncharge.183  The Cost Recovery Charge methodology, the Exit Fee, and the credit support requirements \nare fixed in the filed pro forma agreement and may be changed only by a filing with the Commission. \n \nThe PTOs recognize that the LLCRA, unlike the IRAS tariff as described in PJM’s transmittal, \ncontemplates that the Large Load Entity, which may be a retail customer, will undertake contractual \nobligations directly.  That feature does not bring the LLCRA within the defect the Commission \nidentified.  The obligation the Commission found problematic was a mandatory tariff obligation, \nimposed on a class of retail customers, to curtail their service, which is a term of the retail sale itself.184  \nThe Commission contrasted that obligation with a non-firm transmission service that is “affirmatively \na voluntary option.”185  The Large Load Entity’s obligations under the LLCRA are assumed voluntarily, \nand they concern only the construction, cost recovery, and credit support for Commission-jurisdictional \ntransmission facilities; none governs the price, quantity, or conditions of any retail purchase of \nelectricity.  The Show Cause Order and ComEd confirm that agreements between transmission owners \nand retail large load customers that allocate the costs of transmission facilities are Commission-\njurisdictional.186 \n \nFinally, the Commission gave decisive weight to “the plain language of the Tariff, as proposed,” \nrejecting the IRAS framework in part because that language was inconsistent with the transmittal letter’s \ndescription of obligations running only to Electric Distributors.187  The operative provisions of the \nLLCRA match the description in this transmittal letter: no provision of the LLCRA establishes \nminimum or maximum energy purchases, demand limits, curtailment obligations, or retail \ncompensation.  The PJM IRAS Order also reaffirmed that “the rapid emergence of large loads presents \na shared regulatory challenge that implicates both federal and state authority,” and that states have “a \ncrucial role to play” in designating which retail customers must be curtailed when the system is \nstressed.188  The LLCRA respects that division: it addresses only the recovery of the costs of \njurisdictional transmission facilities and leaves curtailment priority and all terms of retail service to the \nstates. \n \n \n183 Cf. id. at P 83 (finding that the IRAS tariff appeared to allow a retail regulator to set a wholesale rate). \n184 Id. at PP 77, 81. \n185 Id. at P 108. \n186 Show Cause Order at P 79; ComEd, 194 FERC ¶ 61,109. \n187 PJM IRAS Order at P 81. \n188 Id. at P 95 (citing PJM Interconnection, L.L.C., 196 FERC ¶ 61,245, at P 161 (2026))."},{"page":74,"startToken":33840,"endToken":34334,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 74 of 99 \n \n \n \niv. \nThe LLCRA addresses the concerns identified in the Show \nCause Order \nThe PTOs anticipate that the Commission may ask why the LLCRA departs from the three-\nparty construct described in the Show Cause Order.  As explained above, the Show Cause Order did not \nforeclose alternatives.  It expressly sought briefing on substituting an agreement with the large load \ncustomer where that agreement affords comparable or greater protection, and it invited regionally \ntailored Section 205 proposals.189  Individual Commissioners reinforced that invitation, noting that “the \ndoor remains open to other creative, regionally-specific ideas to protect consumers,”190 and that “cost-\nrecovery agreements between a transmission owner and a large load customer itself could satisfy an \nEligible Customer’s financial security requirements.”191  The LLCRA retains the Large Load Eligible \nCustomer as a party, so that the Eligible Customer’s tariff obligations, information, and transmission \nservice payments remain integrated with the cost recovery mechanism, while placing the financial \nobligation on the entity that causes the costs. \n \nThe PTOs also note that, unlike the individually negotiated agreements discussed above, \nwhich the Commission accepted on the basis that the Mobile-Sierra presumption applied,192 the \nLLCRA is a pro forma agreement of general applicability.  The Commission will therefore review the \nLLCRA under the ordinary just-and-reasonable standard, and any non-conforming LLCRA must be \nfiled pursuant to Article 3.  This structure provides the transparency and Commission oversight that \nmembers of the Commission have identified as important when relying on cost recovery agreements \nto protect other customers.193 \n3. \nRevisions to Schedule 1 of the OATT \nThe proposed tariff revisions to Schedule 1 of the OATT (“Schedule 1”) require that Large \nLoad Transmission Customers pay for Scheduling, System Control and Dispatch Service \nconsistent with other ISO-NE transmission customers.  Large Load Transmission Customers shall \nbe required to pay the scheduling and dispatch surcharge in an amount equal to that customer’s \ndemand for FCDS, NFCDS, and ICDS as determined by Section II.62 of the OATT multiplied by \nthe Monthly Scheduling and Dispatch Surcharge Rate as determined by Section II.C of Schedule 1.  \nRevisions to Section II.C of Schedule 1 now include Large Load Transmission Customers’ \ntransmission demand from the prior calendar year in the calculation of the Scheduling and \n \n189 Show Cause Order at PP 35, 79, 122. \n190 Id., concur op. (Comm’r Rosner) at P 2. \n191 Id., concur op. (Comm’r See) at P 4. \n192 See ComEd, 194 FERC ¶ 61,109, concur op. (Comm’rs Swett, Chairman, and LaCerte) at P 1 (explaining that the \norder accepts the agreement “based on the Commission’s determination that the Agreement qualifies for the Mobile-\nSierra presumption”). \n193 See id., concur op. (Comm’r Chang) at P 1 (expressing concern that “reliance on bilaterally-negotiated agreements, \nparticularly ones shielded from meaningful Commission review by the Mobile-Sierra presumption, may not be \nsufficient to ensure that customers are protected against unjust cost shifts from new large loads”)."},{"page":75,"startToken":34334,"endToken":34833,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 75 of 99 \n \n \n \nDispatch Surcharge Rate by subtracting prior year Schedule 1 revenues for such transmission \ndemand in the calculation of the Scheduling and Dispatch Surcharge Rate. \n \nThis revision is necessary, just and reasonable to ensure that Large Load Transmission \nCustomers are subject to the same costs and charges required of similarly situated transmission \ncustomers in ISO-NE.  Failure to make Large Load Transmission Customers subject to these \ncharges could result in inadvertent cost shifting if other transmission customers paid for \nscheduling, system control and dispatch that was exercised, in part, to the benefit of the Large \nLoad Transmission Customers. \n \n4. \nNew Schedule 9A of the OATT \nThe proposed new Schedule 9A to the OATT establishes the rates to be charged for Large Load \nTransmission Customers taking FCDS, NFCDS, and/or ICDS. This schedule is necessary, just, and \nreasonable to ensure that Large Load Transmission Customers are subject to the same costs and charges \nrequired of other transmission customers in New England. More specifically, the rates for FCDS, \nNFCDS, and ICDS will be numerically identical to the RNS rate. \n \n5. \nRevisions to Schedule 21-Common \nThe proposed revisions to Schedule 21-Common of the OATT create transmission services \nover Local Facilities that parallel the transmission services proposed in Part II.J of the OATT.194  \nSpecifically, the revisions create three new transmission services to be offered by the PTOs \nconsistent with their individual Local Service Schedules (which are revised as described below) \nunder Schedule 21: Local Firm Contract Demand Service (“LFCDS”), Local Non-Firm Contract \nDemand Service (“LNFCDS”), and Local Interim Contract Demand Service (“LICDS”).  These \ntransmission services are substantially identical and analogous to the regional FCDS, NFCDS, and \nICDS proposed in Part II.J of the OATT, and will be billed based on Local Network Service rates \n(as opposed to Regional Network Service rates) consistent with the revised Local Service \nSchedules.  Unlike other loads, loads associated with a Large Load Transmission Customer will \nnot be studied under Schedule 21-Common, but instead, consistent with Part II.J of the OATT, \nwill be studied by the ISO through the proposed large load study process described herein. \nThe revisions to Schedule 21-Common are necessary, just, and reasonable in order to effect \nthe transmission of electric energy to a Large Load associated with a Large Load Transmission \nCustomer across the Non-PTF portion of the New England Transmission System.  Without these \nrevisions, a Large Load Transmission Customer could not procure transmission service consistent \nwith the Commission’s concerns raised in the Show Cause Order across local transmission systems \nin ISO-NE.  By the same reasoning, the revisions to the Local Service Schedules are necessary, \njust, and reasonable in order to implement these new transmission services.  Due to the congruence \nand parallel nature of these new local transmission services to the regional services described by \n \n194 NEPOOL takes no position on the proposed Schedule 21 revisions to the Tariff.  Schedule 21 is not subject to \nNEPOOL review and advisory vote."},{"page":76,"startToken":34833,"endToken":35298,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 76 of 99 \n \n \n \nISO-NE, the justness and reasonableness of the services rests on the same reasons given by ISO-\nNE, and are incorporated herein.  The PTOs’ individual Local Service Schedules are also being \nrevised as described below. \n \n6. \nRevisions to Local Service Schedules in Schedule 21 of the OATT \na. \nRevisions to Schedule 21-CMP \nThe proposed revisions add a new Part IV to Schedule 21-CMP governing Local Contract \nDemand Transmission Service for Large Loads. The new provisions establish Firm, Non-Firm, \nand Interim service options, incorporate the applicable regional Large Load requirements, and \nspecify the related operating, reliability, curtailment, cost-allocation, and rate treatment for service \nover CMP’s local transmission facilities. The proposed revisions also make conforming changes \nto CMP’s local study procedures, billing provisions, agreements, and calculation of Local Network \nTransmission System load. \n \nb. \nRevisions to Schedule 21-CTMEEC \nCTMEEC proposes limited revisions to Schedule 21-CTMEEC to account for the addition \nto the OATT and Schedule 21-Common of new transmission service types available to Large Load. \nSpecifically, CTMEEC proposes changes to Schedule 21-CTMEEC to add references to Firm \nContract Demand Service, Non-Firm Contract Demand Service, and Interim Contract Demand \nService in: (1) the definition of Customer’s Schedule 12C Costs Load contained in § I.1.2; (2) the \nNature of Service description contained in § II.1; (3) the text of § II.2.2 describing a Transmission \nCustomer’s obligation to pay Schedule 12C Costs; and (4) Attachment CTMEEC-A, which \ncontains CTMEEC’s form of Schedule 12C Cost Responsibility Agreement. The changes also \nrevise the Customer Default provisions contained in § I.2.3 to make clear that for a Transmission \nCustomer taking Firm Contract Demand Service, Non-Firm Contract Demand Service, or Interim \nContract Demand Service, the applicable Cost Recovery Agreement will govern, clarify the \ndetermination of a customer’s Schedule 12C Costs Load contained in § II.2.4, and correct minor \nformatting or grammatical errors throughout Schedule 21-CTMEEC. \n \nc. \nRevisions to Schedule 21-ES \nEversource proposes revisions to Schedule 21-ES (Parts A and B) to account for the \naddition to the OATT and Schedule 21-Common of three new transmission service types available \nto Large Load Transmission Customers. Specifically, Eversource proposes revisions to \nSchedule 21-ES (Parts A and B) to add references to Local Firm Contract Demand Service, Local \nNon-Firm Contract Demand Service, and Local Interim Contract Demand Service in: (1) the \ndefinitions of Customer’s Monthly Local Service Load, Customer’s Monthly Schedule 12C Costs \nLoad, and the applicable transmission system Local Service Load contained in § I.1 (Parts A and \nB); (2) new Sections IV, V, and VI (Parts A and B) detailing the nature of the three new types of \ntransmission service, as well as provisions governing real power losses, redispatch, interruption, \ncurtailment, load shedding, operating requirements and cost responsibility; (3) the provisions"},{"page":77,"startToken":35298,"endToken":35819,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 77 of 99 \n \n \n \ngoverning the calculation of and a Transmission Customer’s obligation to pay Local Service \ncharges and Schedule 12C Costs contained in Section VII (Parts A and B), Schedule ES-2 (Part \nA) and Schedule ES-3 (Part B); and (4) Attachment ES-E (Part A) and Attachment ES-C (Part B), \nwhich contain Eversource’s form of Schedule 12C Costs Responsibility Agreement. In addition, \nthe changes also revise the Customer Default provisions contained in § I.3.3 (Part A) and I.4.3 \n(Part B) to make clear that for a Large Load Transmission Customer taking Firm Contract Demand \nService, Non-Firm Contract Demand Service, or Interim Contract Demand Service, the applicable \nCost Recovery Agreement will govern. The revisions also include conforming, clarifying, \nadministrative, and formatting changes throughout Schedule 21-ES and the associated rate \nschedules and attachments. \n \nd. \nRevisions to Schedule 21-FG&E and Schedule 21-UES \nFitchburg and Unitil propose revisions to Schedule 21-FG&E and Schedule 21-UES, \nrespectively, to account for the addition to the OATT and Schedule 21-Common of three new \ntransmission service types available to Large Load Transmission Customers. Specifically, \nFitchburg and Unitil propose changes to Schedule 21-FG&E and Schedule 21-UES to add \nreferences to Local Firm Contract Demand Service, Local Non-Firm Contract Demand Service, \nand Local Interim Contract Demand Service in: (1) common service provisions (2) Customer \nDefault provisions, Section II.8.4 to make clear that for a Large Load Transmission Customer \ntaking Firm Contract Demand Service, Non-Firm Contract Demand Service, or Interim Contract \nDemand Service, the applicable Cost Recovery Agreement will govern; (3) Rates and Charges, \nSection 9; (4) New Sections III, IV and V addressing Local Firm Contract Demand Service, Local \nNon-Firm Contract Demand Service, and Local Interim Contract Demand Service provisions; and \n(5) Revision to Schedule 1, Local Scheduling, System Control and Dispatch Service to include \nnew transmission service types. \ne. \nRevisions to Schedule 21-GMP \nGMP proposes company-specific revisions to Schedule 21-GMP implementing the ISO \nand PTO proposed Large Load changes to the OATT and Schedule 21-Common.  The proposed \nchanges incorporate the new transmission services available to Large Load Transmission \nCustomers, in a new Section IV that sets forth the terms and conditions applicable to GMP Local \nContract Demand Service including Real Power Losses, Load Shedding and Curtailment, Cost \nResponsibility, Charges for Local Contract Demand Service including Determination of Large \nLoad Transmission Customer’s Contract Demand and Monthly Demand Service Charge. GMP has \nalso made changes to other Sections to reflect this new service, specifically: referring to the \nrequirement to adhere to state law and regulatory orders and to arrange and pay for local \ndistribution service; including a new definition in Section 1 of “Transmission Customer” so that \nall Local Service customers, including Large Load Transmission Customers, are clearly covered \nby that term throughout; revising the definition of Load Ratio Share; and revising Sections 4.3 and \n7 to make clear that the applicable Cost Recovery Agreement governs the Customer Default and \nCreditworthiness provisions for a Transmission Customer taking Local Contract Demand Service. \nChanges to Section 13.2 regarding the determination of GMP’s monthly transmission peak specify"},{"page":78,"startToken":35819,"endToken":36322,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 78 of 99 \n \n \n \nthat GMP will subtract the coincident peak of all Firm Large Load Transmission Customers and \nadd the Firm Contract Demand in the Determination of Green Mountain’s Transmission Peaks.  \nRevisions to Schedule 1 provide that the Large Load Transmission Customer’s Schedule 1 charge \nis the monthly rate multiplied by the Large Load Transmission Customer’s Contract Demand.  \nRevisions also include other minor conforming, clarifying, administrative, and formatting changes \nthroughout Schedule 21-GMP. \n \nf. \nRevisions to Schedule 21-RIE \nRIE proposes to revise its Local Service Schedule to include the three new transmission \nservices offerings available to a Large Load.  The revisions extend local requirements such as \nmetering and losses, protection requirements, load shedding and curtailment, and direct-\nassignment charges to Large Loads and provide clarifying cross-references to the Large Load \ninterconnection procedures in Part II.J of the ISO-NE OATT. \nAdditionally, during its review of Schedule 21-RIE, a small number of edits and corrections \nwere identified, e.g., outdated terminology and organizational references, provisions carried \nforward from predecessor tariffs, and cross-references and section numbering.  These corrections \nand ministerial changes improve the clarity, readability, and usability of Schedule 21-RIE. \ng. \nRevisions to Schedule 21-NEP \nNational Grid’s proposed revisions amend Schedule 21-NEP to bring the Large Load \ntransmission service framework set out in Part II.J and Schedule 21 of the ISO-NE OATT into \nNEP’s Local Service Schedule. First, the revisions establish three new local services under \nSchedule 21-NEP: Local Firm Contract Demand Service, Local Non-Firm Contract Demand \nService, and Local Interim Contract Demand Service. These services are added to the definition \nof Local Service Annual Transmission Revenue Requirement in Section 1.11, to the Purpose \nstatement in Section 2, and to the heading and introductory provisions of Part II. A new provision \nin Part II states that these services shall be provided in accordance with Schedule 21, Part II.J of \nthe ISO-NE OATT, and Schedule 21-NEP, and shall permit a Large Load Transmission Customer \nto serve a Large Load through NEP's Transmission System. Section 24 is revised so that NEP’s \nexisting local service rates and charges may apply to the new contract demand services. The \ndefinition of Network Load in Section 1.15 is amended to exclude any Large Load, or portion of \na Large Load, served under the Firm, Interim, or Non-Firm Contract Demand Services or their \nlocal counterparts. Conforming revisions extend provisions that previously applied only to \nNetwork Customers to “other Transmission Customers” as well. These include real power losses \n(Section 19), power factor requirements and penalties (Sections 20.1 and 24.5), redispatch cost \nresponsibility and system reliability (Sections 23.2 and 23.3), and the individual charges in Section \n24 and Attachment OCC.  \n \nSecond, the revisions make clear that Large Load interconnection and study requests \nproceed under Part II.J of the ISO-NE OATT, not under NEP’s existing local procedures. \nSections 1.7.1, 2(c), and 22.1 are amended to state that the Large Load interconnection process is"},{"page":79,"startToken":36322,"endToken":36893,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 79 of 99 \n \n \n \nset forth in Part II.J. Attachments C (Form of System Impact Study Agreement), D (Form of \nFacilities Study Agreement), and H (Methodology for Completing System Impact Study) are each \namended to provide that they shall not apply to transmission service requests on behalf of a Large \nLoad. Attachment H further provides that the ISO will study such requests in coordination with \nNEP. Attachment E (Policy and Practices for Protection Requirements) is revised to apply to a \nLarge Load interconnection only to the extent not inconsistent with the Large Load protection \nrequirements under Part II.J and the applicable ISO New England Operating Procedures, which \ngovern in the event of a conflict.  \n \nThe revisions further align Schedule 21-NEP with the Large Load Transmission Service \nAgreement and the Large Load Cost Recovery Agreement. Section 4.2 provides that, where a \nTransmission Customer is taking any of the contract demand services, the terms of the applicable \nLarge Load Cost Recovery Agreement shall govern billing disputes. Section 4.3 provides that \ntermination costs and the Exit Fee for Large Load Network Upgrades and Direct Assignment \nFacilities owed by a Large Load Entity shall be determined and paid in accordance with that \nagreement. Section 24.6 applies the Direct Assignment Facility Charge to Direct Assignment \nFacilities directly assigned to a Large Load Transmission Customer, except to the extent such costs \nare recovered under a Large Load Cost Recovery Agreement, so that such costs are not recovered \ntwice. Section 23.1 requires Large Load Transmission Customers to comply with load shedding \nand curtailment procedures established under the ISO-NE OATT, the applicable ISO New England \nOperating Documents, the applicable Large Load Transmission Service Agreement, and Schedule \n21-NEP. The same section provides that redispatch may not unduly discriminate among NEP’s \nNative Load Customers, Network Customers, and other Transmission Customers in their use of \nthe Non-PTF to serve Network Load or Large Load. Attachment OCC provides that its charges \napply to a Large Load Transmission Customer only to the extent provided in the applicable Large \nLoad Transmission Service Agreement or Large Load Cost Recovery Agreement. Attachment F \nprovides that the insurance requirements of Article 17 of the applicable Large Load Cost Recovery \nAgreement shall govern in lieu of Attachment F to the extent of any inconsistency. The \nCreditworthiness Policy in Attachment L is extended to Large Load Eligible Customers, Large \nLoad Transmission Customers, and Large Load Entities, and to Large Load Transmission Service \nAgreements and Large Load Cost Recovery Agreements. Any financial assurance required under \na Large Load Cost Recovery Agreement is in addition to, and not in lieu of, the Policy’s \nrequirements, except to the extent that agreement provides otherwise. Section 3.1.4 of \nAttachment L is amended to provide that, for a Large Load Entity, the required security shall \ninclude security for the Exit Fee, equal to the Net Book Value of the Large Load Network Upgrades \nconstructed by NEP plus estimated decommissioning costs, as determined under the applicable \nLarge Load Cost Recovery Agreement. Finally, the revisions make several ministerial corrections: \n \n• updating NERC’s name to the North American Electric Reliability Corporation;  \n• replacing “Local Network Service Load” with “Local Service Load” and conforming \nrelated terms;  \n• capitalizing “Network Load” as a defined term in Sections 2(c), 22.1, and 24.13;  \n• revising the Part II heading and its corresponding Table of Contents reference; and"},{"page":80,"startToken":36893,"endToken":37347,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 80 of 99 \n \n \n \n• correcting the line references in the Local Network Load Dispatch Surcharge Rate formula \nin Attachment OCC, Exhibit 5. \n \nh. \nRevisions to Schedule 21-NHT \nNHT proposes revisions to Schedule 21-NHT to incorporate three new transmission service \ntypes available to Large Load Transmission Customers: Local Firm Contract Demand Service, \nLocal Non-Firm Contract Demand Service, and Local Interim Contract Demand Service. The \nproposed revisions add new Parts IV, V, and VI addressing service availability, operating \nrequirements, real power losses, load shedding, curtailment, and cost responsibility. The revisions \nalso update applicable definitions, customer default provisions, and transmission service charges, \nincluding the addition of Schedules 7A and 8A, to align Schedule 21-NHT with the proposed \nchanges to the OATT and Schedule 21-Common. Additional conforming, clarifying, and \nadministrative revisions are included. \n \ni. \nRevisions to Schedule 21-UI \nThe United Illuminating Company proposes revisions to Schedule 21-UI to establish the \nterms and conditions governing Firm, Non-Firm, and Interim Local Contract Demand Service for \nLarge Loads served over UI’s Local Network. The revisions align UI’s local service provisions \nwith the new regional Large Load framework in the ISO New England Transmission, Markets and \nServices Tariff and address service availability, reliability and operating requirements, load \nshedding and curtailment, customer cost responsibility, and the rates and charges applicable to \neach form of Local Contract Demand Service. The proposed revisions also make conforming \nchanges to UI’s definitions, study procedures, billing provisions, Schedule 12C cost recovery, and \ncalculation of local transmission loads and rates. \n \nj. \nRevisions to Schedule 21-VTransco \nThe changes proposed to Schedule 21-VTransco are intended to align Vermont Transco \nLLC's Local Service Schedule with changes proposed by ISO-NE and other PTOs in order to \nintegrate three new service categories for large loads connecting to Non-PTF.  These revisions \ninclude: adding definitions for Large Load Transmission Customer, Local Firm Contract Demand \nService, Local Interim Contract Demand Service, Local Non-Firm Contract Demand Service, \nMonthly Local Firm Contract Demand, Monthly Local Interim Contract Demand, Monthly Local \nNon-Firm Contract Demand, and Transmission Customer; revising the existing definitions for \nLoad Ratio Share and VTransco’s Monthly Transmission System Peak; revising the Customer \nDefault provision to clarify that the default provisions of the applicable Large Load Cost Recovery \nAgreement shall also apply for Transmission Customers taking Local Firm Contract Demand \nService, Local Non-Firm Contract Demand Service, or Interim Contract Demand Service; clarifying \nthe Redispatch Charge for Local Network Service to clarify that Local Network Customers shall pay a \nLoad Ratio Share of any dispatch costs allocated between the Local Network Customer, any Large Load \nTransmission Customer, and VTransco; including under new Sections IV, V, and VI of Schedule 21-\nVTransco provisions implementing Local Firm Contract Demand Service, Local Non-Firm Contract"},{"page":81,"startToken":37347,"endToken":37795,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 81 of 99 \n \n \n \nDemand Service, and Local Interim Contract Demand Service, which set forth the nature of the services, \nrates and charges, real power losses, load shedding and curtailment requirements (and redispatch \nrequirements for Local Non-Firm Contract Demand Service), operating requirements, and cost \nresponsibility; and revising Schedule 1 (Scheduling, System Control and Dispatch Service) to set forth \nSchedule 1 charges for the new large load service categories. \n \nk. \nRevisions to Schedule 21-VP \nVersant Power proposes revisions to Schedule 21-VP to account for the addition to the \nOATT and Schedule 21-Common of three new transmission service types available to Large Load \nTransmission Customers. Specifically, Versant Power proposes changes to Schedule 21-VP to add \nreferences to Local Firm Contract Demand Service, Local Non-Firm Contract Demand Service, \nand Local Interim Contract Demand Service (collectively, “Local Contract Demand Service”) in: \n(1) § 1 (Definitions), including a new definition of Local Contract Demand Service in § 1.6A; (2) a \nnew Part IV (Local Contract Demand Service), which includes a preamble and new Sections 22 \nthrough 26 describing the nature of the three new types of transmission service; (3) the provisions \ngoverning the rates and charges applicable to Local Contract Demand Service in Schedule 1-VP \n(Scheduling, System Control and Dispatch Service), Schedule 7-VP (Charges For Wholesale \nCustomers Interconnected on the BHD System - Firm), and Schedule 8-VP (Charges For \nWholesale Customers Interconnected on the BHD System - Non-Firm); (4) Attachment C-VP \n(Methodology to Assess Available Transfer Capability); (5) Attachment D-VP (Methodology for \nCompleting a System Impact Study); (6) Attachment G-VP (Local Network Operating \nAgreement); and (7) Attachment P-VP (Determination of Charges). The revisions also include \ncertain conforming, clarifying, administrative, and formatting changes in the foregoing sections, \nas well as correction of certain typographical errors. \n7. \nConforming Revisions in Section II.21.2 of the OATT \nThe term “Large Load Transmission Customers” is being added in Section II.21.2 of the \nOATT as a conforming revision in the language that currently applies to Regional Network \nService.  Specifically, the revision in Section II.21.2 of the OATT specifies that the coincident \naggregate load of all Network Customers and Large Load Transmission Customers will be \nincluded in the calculation of a Customer’s Monthly Regional Network Load. \nE. \nTariff Revisions in Response to the Commission’s Resource Adequacy \nConcerns Proposed by the ISO Under the ISO’s Section 205 Rights \nIn the Show Cause Order, the Commission recognized the reliability concerns created by the \naddition of Large Loads without concomitant additions of supply or demand-side resources.195  The \nCommission directed the ISO to outline its plans to ensure that adequate generation will be available \n \n195 Show Cause Order at P 4."},{"page":82,"startToken":37795,"endToken":38361,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 82 of 99 \n \n \n \nto serve existing and new Large Loads in an informational report.196  In compliance with the \nCommission’s directive, on July 20, 2026, the ISO submitted its Informational Report.  \n \nIn the Informational Report, the ISO described that, over the past decade, load in New \nEngland has been either flat or declining, and the region has generally been long on supply, with a \nrobust, largely uncongested transmission system that facilitates the delivery of supply to load.197  \nMoreover, unlike other regions of the country, New England has not yet encountered significant load \ngrowth attributable to the addition of Large Loads, such as data centers.198  Nonetheless, ISO-NE \nhas been planning for large loads by working with the region’s transmission owners to develop \nprotocols for tracking large loads, and incorporating large loads in its forecasting processes.199  \nThe ISO went on to explain that the region’s most recent Report on Capacity, Energy, Loads, \nand Transmission (the “CELT Report”) suggests that, into the next decade, electricity demand will \ngrow steadily, given electrification and other drivers.200  On the supply side, the CELT Report \nindicates adequate installed reserve margins.201  Nonetheless, the ISO is prepared for the factors that \nare not accounted for in the CELT Report and occur in the ordinary course of business, including \nwinter gas pipeline constraints, operating reserve requirements, unplanned outages, and reduced \navailability of imports during periods of high demand.202  Moreover, the ISO is undertaking  capacity \naccreditation changes that are part of the Capacity Auction Reforms (“CAR”) project.203   \n \n196 Id. at P 119. \n197 2025 Assessment of the ISO New England Electricity Markets, Potomac Economics, 4-5 & Figure 2 (June 2026), \nhttps://potomaceconomics.com/wp-content/uploads/2026/06/ISO-NE-2025-EMM-Report_Final.pdf \n(“Potomac \nAnnual Report”). \n198 Gordon van Welie, ISO-NE’s Response to Chairman David Rosner’s September 18, 2025 Letter Seeking a Dialogue \non Large Load Growth in New England, ISO New England Inc., 3 of PDF (Oct. 6, 2025), https://www.iso-\nne.com/static-assets/documents/100028/large-load-forecasting-isone-response.pdf. \n199 Al McBride, Planning for Large Loads in New England, ISO New England Inc. (May 20, 2026), \niso_large_loads_necpuc_symposium_mcbride.pdf. \n200 System Planning, 2026-2035 Forecast Report on Capacity, Energy, Loads, and Transmission, ISO New England \nInc., Tab 1.1 & Section 1 (May 1, 2026), 2026_celt.xlsx. \n201 Id. at Tab 1.1, Section 4.2. \n202 Regarding imports, see 2025 Annual Markets Report, ISO New England Inc., 39 (May 29, 2026), 2025-annual-\nmarkets-report.pdf (net interchange with Canadian and New York balancing areas combined was at its lowest level in \n13 years). \n203 As explained in the Informational Report, with the two-phase CAR project, ISO-NE is moving from a three-year \nforward to a prompt seasonal capacity market, which will incorporate updated and more accurate information on \nsupply and demand conditions.  The design also includes a marginal reliability impact-based accreditation \nmethodology.  This accreditation methodology will better reflect each technology’s contribution to resource adequacy, \nthereby sending appropriate price signals to capital markets regarding investment in new and existing resources of \ndifferent technology types as well as resource performance improvements.  The project is also introducing an \ninnovative approach to capturing the impacts of the region’s constrained gas system on the gas fleet’s resource \nadequacy contributions.  The ISO anticipates making its second filing for this project at the end of this year.  Should"},{"page":83,"startToken":38361,"endToken":38939,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 83 of 99 \n \n \n \nLarge Loads, however, are not the ordinary course of business.  They create unique \ncircumstances that, as described in this transmittal letter, require changes to the Tariff to facilitate \ntheir integration while ensuring system reliability.  They may also require new capacity at a speed \nand in amounts that are not typical, and that new resource development may be slowed by existing \npermitting and supply chain challenges.  In recognition of these realities, ISO-NE has concluded that \nNew England must, at a minimum (i) maintain its existing fleet through competitive markets that \nassure the fleet’s continued commercial viability in the near term; (ii) ensure these competitive \nmarkets will send appropriate price signals to provide incentives for cost-effective new resource \ndevelopment when needed; and (iii) maintain the competitive markets’ structure and stability in the \nface of the abrupt emergence of material amounts of Large Loads.     \nThe ISO also outlined in the CELT report why it believes that the markets are well-positioned \nto meet the first two objectives above, and how the region may need to adapt to maintain the markets’ \nfunctioning as reflected in the third objective.  In sum, the region’s over-arching wholesale market \nstructure is designed to, and has proven effective at, cost-effectively compensating generation and \nproviding incentives for new entry to reliably meet the needs of the consumers the markets were \ndesigned to serve.  This design includes not only the capacity market, which the ISO continues to \nenhance to address the region’s evolving system, but also the region’s energy market—through \nwhich the vast majority of generators’ revenue flows.  \nFrom an investor’s perspective, these markets work to provide that essential compensation \nbecause of three key factors.  First, New England’s forward power market prices, which guide \nresources’ future energy revenue expectations, are among the highest in the nation and remain \nelevated for coming years.204  Because of these high prices, some recent analyses indicate total \nwholesale market revenues are presently approaching the cost of new entry (“CONE”) for \ndispatchable combined cycle generation in the New England region.205  Second, as discussed above, \nNew England is now facing steady, incremental load growth over the coming decade due to \nincreasing electrification (even without large load development), further supporting that the forward \nmarket’s energy price signals are not likely to abate any time soon.   \n \nthe Commission approve this second filing, the ISO will administer its first prompt and seasonal auction in May 2028 \n(the date through which the region has previously procured capacity).  The ISO is focused on administering the \ncapacity auctions on schedule, as it believes such consistency is critical to the wholesale markets and to investors.  As \na core market principle, the ISO will continuously evaluate and work with stakeholders to ensure efficient price \nformation in the capacity market.   \n204 Maya Weber & Ronnie Turner, US EIA forecasts 8% drop in nation’s summer wholesale power prices from year \nago, \nS&P \nGlobal \n(July \n7, \n2026), \nhttps://www.capitaliq.spglobal.com/apisv3/spg-webplatform-\ncore/news/article?id=103582694&documentsource=1 (“PJM and ISO-NE are forecast to have the country’s highest \nprices this summer at $69/MWh and $64/MWh,” citing the Energy Information Administration’s July 2026 Short \nTerm Energy Outlook).  Looking further forward, annual average on-peak power contract prices for New England \nsystem power trading at the Intercontinental Exchange exceed $68/MWh for 2030 (ISO-NE calculations, trade data \nas of July 10, 2026).    \n205 Potomac Annual Report at 21, Figure 8."},{"page":84,"startToken":38939,"endToken":39551,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 84 of 99 \n \n \n \nFinally, investors value a stable market in which they have confidence, facilitated by a \ndependable regulatory environment.  New England has a longstanding and effective NEPOOL \nstakeholder process that collaboratively and thoughtfully produces market enhancements large and \nsmall.  This participatory, effective and efficient rule change process in New England helps to bolster \nconfidence in the stability of the region’s wholesale market.   \nFrom the ISO’s perspective, the existing competitive market structure has proven able to \nsend the appropriate capacity and energy price signals to provide incentives for new entry and \nmaintain existing supply in the ordinary course of business.  Tailored changes currently underway, \nincluding CAR, are appropriate to sustain the markets’ strength as the system evolves.206 \n \nThe ISO appreciates that, in addition to its continuing work to ensure resource adequacy, it \nmust explicitly consider the potential impact of Large Loads on the markets.  While those loads have \nyet to materialize in New England, as described in the Informational Report, the ISO believes that \ntwo related actions are necessary: requiring new Large Loads to “bring their own” incremental new \ncapacity (referred to in the Informational Report as new “generation”), and excluding new Large \nLoads from the load-side requirements of the capacity market (i.e., the Installed Capacity \nRequirement).  Accordingly, the Tariff Revisions include language providing notice that Large Loads \nmust bring their own new capacity, and that certain Large Loads will be excluded from the capacity \nmarket’s Installed Capacity Requirement.207 \n \n \n206 As the Commission required in the Informational Report, the ISO described pending projects that are intended to \ncreate incentives for new investment, retain the existing fleet, and deal with increased uncertainty and volatility.  Many \nof these projects are detailed in the ISO’s multi-year roadmap, which sets out present priorities through 2030, and \naddresses resource adequacy as well as operational uncertainty related to steeper ramps, the need for flexibility, and \nlimited energy constraints.  The projects most directly related to resource adequacy and operational uncertainty are:  \nthe reduction in the Pay for Performance rate; the CAR project; improvements to Surplus Interconnection Service; \nprobabilistic forecasting; uncertainty reserves; updated capacity market parameters, including revisions to the Cost of \nNew Entry (“CONE”) and net CONE; and work with the states to facilitate greater demand flexibility in the region.  \nIn the Informational Report, the ISO also mentioned past projects in the categories of resource adequacy and \noperational uncertainty:  the changes to generator interconnection practices in compliance with Order No. 2023, as a \nresult of which most speculative projects have left the queue, leaving it essentially with no backlog; the Day-Ahead \nAncillary Services Market, which compensates resources that provide the ancillary service capabilities necessary to \nmeet reliability requirements; and the development of the Probabilistic Energy Adequacy Tool and the Regional \nEnergy Shortfall Threshold, which, together, assess energy shortfall risk and guide consideration of mitigations (such \nas the need for additional resources). \n207 The Informational Report stated that “[s]ubject to discussion with stakeholders, ISO-NE anticipates including a \nstatement in its filing to comply with the June 18 Order that will put Eligible Customers on notice that large loads \nmust ‘bring your own new generation.’  Following a robust stakeholder process and resolution of operational issues, \nISO-NE anticipates filing the detailed supporting rules implementing this concept in 2027” and that “[s]ubject to \ndiscussion and review with stakeholders, ISO-NE anticipates including a statement in its filing to comply with the \nJune 18 Order that will put Eligible Customers on notice that the capacity market will exclude new large loads.  \nFollowing a robust stakeholder process, ISO-NE will file detailed rules implementing this concept in 2027.”  \nInformational Report at 7."},{"page":85,"startToken":39551,"endToken":40013,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 85 of 99 \n \n \n \nSpecifically, to establish the “bring your own new capacity” (“BYONC”) requirement, new \nSection II.59 of the OATT provides as follows:  \nTo receive the requested amount of Firm Contract Demand Service for a Large \nLoad, the Large Load Eligible Customer shall designate, or cause to be \ndesignated, sufficient new capacity resources to meet the requested amount of \nFirm Contract Demand Service for the Large Load.  Interim Contract Demand \nService shall be provided for the amount of requested Firm Contract Demand \nService until such sufficient capacity resources are designated and achieve \ncommercial operation. \n \nIn addition, to ensure that Large Loads are excluded from the Installed Capacity Requirement, \nthe following language is being added in Section III.12.1 of the Tariff:  “Large Loads receiving Interim \nContract Demand Service or Non-Firm Contract Demand Service shall be excluded from the calculation \nof the Installed Capacity Requirement and related values.”  \n \nFollowing a robust stakeholder process and resolution of operational issues, the ISO anticipates \nfiling the detailed supporting rules implementing these concepts with the Commission in 2027.  The \ntopics the ISO intends to discuss with stakeholders in 2027 related to BYONC includes, but is not \nlimited to: definition of “new” in “new capacity;” accreditation of designated resources; locational \nrequirements; load forecast and Installed Capacity Requirement; and Pay-for-Performance settlement. \n \nV. \nANSWERS TO BRIEFING QUESTIONS \n \nIn the Show Cause Order, the Commission directed further briefing on six questions.  \nConsistent with the descriptions for the proposed Tariff Revisions included in each of the previous \nsections of this transmittal letter, this section includes ISO-NE’s answers to questions A, B, D, E \nand F, and the PTOs’ answer to question C. \nA. \nHow should ISO-NE and the PTOs protect existing commercial arrangements, \nincluding:  (1) what would be a reasonable implementation period to ensure \nminimal disruption to such existing commercial arrangements, and (2) how to \nallow a reasonable amount of time to finalize ongoing agreements that are nearing \ncompletion as of the date such Tariff provisions are filed with the Commission.208 \nISO-NE plans to protect existing commercial arrangements through multiple mechanisms \nto address projects in different stages of development.  As described in Section IV.B.1 of this \ntransmittal letter, each existing load in operation or sufficiently under construction as of June 18, \n2026, will be exempt from the proposed Large Load definition and all associated requirements, \neven if it would otherwise meet the definition of a Large Load.  The MW value that is exempt will \nbe the greater of (i) a given load’s hourly historical gross peak in the ten years prior to June 18, \n2026; or (ii) a MW value specified in an existing service or operational agreement.  The exemption \n \n208 Show Cause Order at P 120."},{"page":86,"startToken":40013,"endToken":40530,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 86 of 99 \n \n \n \nwill hold until and unless a load adds an incremental 50 MW and otherwise meets the definition \nof a Large Load.  If a load transitions to a Large Load due to an increment of 50 MW or greater, \nthe previously exempt load will transition to being served by Firm Contract Demand Service \nwithout the associated study and capacity resource designation requirements but will be subject to \nLarge Load operational requirements.  The PTOs will continue to honor existing rate agreements \nif the previously exempt load can be metered separately from the incremental load. \nA load will be defined as a Large Load Sufficiently Under Construction if it is determined \nby ISO-NE to have provided sufficient evidence that it received major permits necessary for \nconstruction of the project, achieved project financing closing, ordered major equipment necessary \nfor the construction of the project, and has started construction activities on the project site.  A \nload determined to be a Large Load Sufficiently Under Construction as of June 18, 2026, will be \nexempt from the proposed Large Load definition and all associated requirements as if it were in \noperation. \nFurther, a Large Load will be exempt from the ISO-NE Large Load application and study \nrequirements if it has signed a study agreement with its interconnecting utility prior to the June 1, \n2027, implementation date for the ISO-NE Large Load application and study procedures.  Such \nLarge Loads will still be required to meet all other Large Load requirements, including operational \nrequirements and the BYONC requirement as a condition for its Large Load Transmission \nCustomer to receive Firm Contract Demand Service.  \nB. \nWhat, if any, potential impacts on regional and local transmission planning would \narise from the introduction of the new transmission services discussed herein?  For \nexample, when planning for load growth, how would transmission providers and \nplanners account for flexible large loads’ potential preference to take the new \ntransmission services, including potential uncertainties around the type, location, \nand quantity of such expected loads?209 \nLoads served under the new Firm Contract Demand Service, Interim Contract Demand \nService, and Non-Firm Contract Demand Service will be treated separately from loads served \nunder existing Regional Network Service and Local Network Service in the Regional and Local \nSystem Planning processes. This differing treatment will reflect the impacts of Large Loads on the \ntransmission planning process, as described below, and appropriately allocate costs for upgrades \ncaused by these Large Loads to the associated cost recovery agreement rather than to other \ncustomers, while maintaining system reliability.  \nOnce a Large Load has completed its Large Load System Impact Study, it will be included \nin models used in transmission planning studies, along with any required system upgrades \nidentified in the Large Load System Impact Study, and any generating capacity associated with \nthe Large Load.  Any unique characteristics of this load, including behavior unique to data center \nloads, will be represented by the most recently available models provided by the Eligible \nCustomer, whether received during the Large Load System Impact Study process, Large Load \n \n209 Id. at P 121."},{"page":87,"startToken":40530,"endToken":41067,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 87 of 99 \n \n \n \ncommissioning, or after the Large Load has begun commercial operation.  Uncertainty around the \ntype, location, and quantity of such loads will no longer be a factor, as the load’s characteristics \nand modeling data have already been established in the Large Load System Impact Study process. \nThe treatment of this load in transmission planning studies for the Regional System \nPlanning processes, including Needs Assessments, will depend on the type of load service under \nwhich the Large Load interconnected.  A Large Load receiving Firm Contract Demand Service \nwill be treated similarly to other firm retail loads in transmission planning studies.  The inclusion \nof the Large Load’s required upgrades, as identified in the Large Load System Impact Study, will \nensure that any reliability impacts directly attributable to the Large Load are mitigated, and not \ndesignated as regional reliability needs to be addressed through ratepayer-funded upgrades.  If \nfurther growth of load served under Regional Network Service or Local Network Service \ncombined with the presence of Large Loads leads to additional reliability concerns, these concerns \nwill be identified in a Needs Assessment and mitigated through regionally funded transmission \nupgrades identified in a Solutions Study or a competitive request for proposals. \nA Large Load receiving Non-Firm Contract Demand Service will also be initially included \nin system models used in Needs Assessments.  If the Needs Assessment identifies any voltage or \nstability criteria violations, these will be designated as needs and will proceed to a Solutions Study \nor a competitive request for proposals.  Additionally, any thermal criteria violations that would \npersist in the absence of loads receiving Non-Firm Contract Demand Service would be designated \nas needs and treated similarly.  If the Needs Assessment identifies thermal violations that are \ncaused or worsened by the presence of one or more loads receiving Non-Firm Contract Demand \nService, the load(s) will be curtailed to minimize or eliminate the criteria violation.  The violation \nwill only be designated a need to the extent that it is still present after the full curtailment of any \nrelevant loads receiving Non-Firm Contract Demand Service.  A Large Load receiving Interim \nContract Demand Service will be handled in a manner similar to loads receiving Firm Contract \nDemand Service or Non-Firm Contract Demand Service, depending on the timing of the load’s \nassociated capacity and upgrades relative to the year of study for any particular analysis. \nC. \nInclude information regarding potential structures for agreements between the \ntransmission owner/provider and an Eligible Customer to prevent unjust and \nunreasonable cost shifts among transmission customers related to network \nupgrades costs required for large loads.  Further, please include information on \nwhat an appropriate minimum level of cost recovery and financial security from an \nEligible Customer would be under any such agreements.210 \nAs explained in Section IV.D.2 above, the PTOs believe that the only sure way to prevent unjust \nand unreasonable cost shifts among transmission customers related to network upgrade costs required \nfor large loads is to establish the appropriate cost responsibility with the entity driving the need for such \nupgrades, consistent with the Commission’s cost-causation principles.211  The LLCRA in the Tariff \n \n210 Id. at P 122. \n211 See supra Section IV.D.2."},{"page":88,"startToken":41067,"endToken":41571,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 88 of 99 \n \n \n \nRevisions is one such agreement.  Given the uncertainty in the indemnification of an EDC Eligible \nCustomer by a large load served by that EDC for the cost of network upgrades, as well as the ability of \nthe EDC to compel (presumably under state law) such an indemnity, only an agreement including the \nLarge Load Entity itself sufficiently prevents cost shifting, including cost shifting caused by default of \nthe Large Load Entity.  As likewise explained above, the LLCRA is squarely within the Commission’s \njurisdiction and including the Large Load Entity as the entity responsible for paying so that cost shifting \ndoes not occur is a just and reasonable approach. \nFurthermore, and as illustrated by the LLCRA, the only appropriate level of cost recovery and \nfinancial security from the Large Load Entity is 1) cost recovery that ensures that none of the cost for \nthe Large Load Network Upgrades causes an increase in transmission rates and 2) financial security that \nensures that in the event of default or insolvency the entire value of either the cost of constructing the \nupgrades (pre-commercial operation and the inclusion of those updates in transmission rate base) or the \nnet book value of those upgrades (following those upgrades being placed in-service and included in \ntransmission rate base) as well as all other costs under the LLCRA is paid to the TO and credited against \nrates to avoid cost shifting. \nThe LLCRA addresses both concerns.  The obligation for the Large Load Entity to pay all costs \nassociated with the construction of the Required Facilities in the event of termination prior to \ncommercial operation of the facility ensures that the LLITO and its customers are not burdened with \nstranded costs in the event of early termination of the large load project.212  The Cost Recovery Charge \nensures that there is no transmission rate impact caused by the construction of LLITO’s Network \nUpgrades.213  Direct assignment of costs for the Direct Assignment Facilities ensures that the cost of \nsole-use facilities for the large load are borne solely by that load.214  The Exit Fee ensures that following \nthe termination or disconnection of the large load, the remaining net book value of LLITO’s Network \nUpgrades is paid and credited against transmission rates.215  Finally, the Credit Support ensures that \nsufficient security exists to cover all these cost-shifting prevention mechanisms in the event of default \nor insolvency by the Large Load Entity.216 \nD. \nFurther briefing regarding specific characteristics of providing transmission \nservice to Eligible Customers on behalf of large loads that warrant requirements \nbeyond those contemplated in the Show Cause Order.217 \nThe Show Cause Order acknowledges that “[t]he rapid addition and proliferation of large \nloads without commensurate additions of supply or demand-side resources presents resource \n \n212 See LLCRA Article 2. \n213 See id. Article 10 and Appendix C-2. \n214 See id. Articles 4 and 10. \n215 See id. Article 10. \n216 See id. \n217 Show Cause Order at P 123."},{"page":89,"startToken":41571,"endToken":42079,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 89 of 99 \n \n \n \nadequacy concerns”218 and the Commission strongly encouraged new proposals to address these \nconcerns.  To address resource adequacy concerns associated with the rapid addition of large loads, \nISO-NE proposes a BYONC requirement as a condition of Firm Contract Demand Service.  As \nexplained in Section IV.E of this transmittal letter, ISO-NE originally raised this concept in its \nInformational Report using the name “bring your own new generation” but has since refined the \nconcept during stakeholder discussions to more directly align with resource adequacy concerns \nassociated with supply capacity.  \nImportantly, the BYONC requirement is only a condition of Firm Contract Demand \nService.  Large Load Transmission Customers have the option to instead take Non-Firm Contract \nDemand Service and not be subject to the BYONC requirement.  Large Load Transmission \nCustomers taking Non-Firm Contract Demand Service on behalf of a non-firm Large Load are \nboth (i) exempt from capacity charges and (ii) required to reduce their wholesale service taken on \nbehalf of a non-firm Large Load prior to the region entering a CSC.  Re-dispatch reduction of Non-\nFirm Contract Demand Service will be achieved through the use of a DARD asset.  Large Load \nTransmission Customers may utilize Interim Contract Demand Service, which is a temporary non-\nfirm service provided prior to a Large Load Transmission Customer completing necessary \nupgrades and designating sufficient capacity to meet the BYONC requirement.  Interim Contract \nDemand Service will be treated the same as Non-Firm Contract Demand Service with respect to \ncapacity charges and service reductions.  Should a Large Load Transmission Customer utilizing \nInterim Contract Demand Service fail to designate sufficient capacity to meet the requirements of \nFirm Contract Demand Service within seven years or the length of time required to place the \nrequired Large Load Network Upgrades in-service, whichever is longer, its Interim Contract \nDemand Service will be permanently transitioned to Non-Firm Contract Demand Service. \nAs stated in Section IV.E of this transmittal letter, ISO-NE will further develop with \nstakeholders and propose, pursuant to FPA section 205, specific rules detailing which resources \nwill qualify to meet the BYONC requirement, the process to do so, and related matters require \nsignificant NEPOOL discussion.  For the purposes of this filing, the salient fact is that Large Load \nTransmission Customers will be placed on notice of the BYONC requirement for Firm Contract \nDemand Service as of November 14, 2026, the proposed effective date for the Tariff Revisions.  \nThe details of how a Large Load Transmission Customer may meet such a BYONC requirement \nwill be the subject of further stakeholder process and subsequent filing with the Commission.  \nTherefore, ISO-NE plans to engage with stakeholders in 2027 to develop a robust set of rules for \nBYONC resources, prior to the implementation of the proposed Large Load transmission services \nin 2028. \nE. \nTo what extent would ISO-NE allow an interconnection customer's generating \nfacility serving electrically proximate large load or large co-located load to \nparticipate in ISO-NE's energy and ancillary services market, and if ISO-NE were \n \n218 Id. at P 118."},{"page":90,"startToken":42079,"endToken":42587,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 90 of 99 \n \n \n \nto allow them to participate, what restrictions or mitigation would ISO-NE \napply?219 \nAn interconnection customer's generating facility serving an Electrically Proximate Large \nLoad or Co-Located Large Load in ISO-NE will be defined as a Large Load Co-Located Generator \nor Large Load Electrically Proximate Generator.  To align with the Show Cause Order’s \nconsiderations on cost shifting, the ISO proposes to meter Large Loads and any associated Large \nLoad Co-Located Generator or Large Load Electrically Proximate Generator separately based on \ngross demand and gross supply, such that the two are not netted.  Large Load Co-Located \nGenerators and Large Load Electrically Proximate Generators will be eligible to participate in the \nenergy market, with some restrictions depending on how they are studied and their zero MW NRIS.  \n \nAs explained in Section IV.C of this transmittal letter, a Large Load Co-Located Generator \nor Large Load Electrically Proximate Generator has access to a new interconnection process that \nprovides zero MWs of NRIS.  Under this process, the Large Load Co-Located Generator or Large \nLoad Electrically Proximate Generator can be included in the same expedited 90-day study process \nas its associated Large Load.  This service allows the Large Load Co-Located Generator or Large \nLoad Electrically Proximate Generator to achieve all or a portion of re-dispatch instructions for a \nLarge Load receiving Non-Firm Contract Demand Service or Interim Contract Demand Service \nby injecting energy supply, consistent with the Non-Firm Large Load Generator Arrangement.  \nHowever, this service does not allow the Large Load Co-Located Generators and Large Load \nElectrically Proximate Generator to net inject to the grid, because their net injections have not been \nstudied.  Therefore, a Large Load Co-Located Generator or Large Load Electrically Proximate \nGenerator may provide and receive credit for energy supply, on a gross supply basis, up to but not \nexceeding their associated Large Load’s gross demand. \n \nA Large Load Co-Located Generator and Large Load Electrically Proximate Generator \nmay subsequently elect to participate in a Cluster Study in order to increase its Interconnection \nService.  Through this process, the Large Load Co-Located Generator’s or Large Load Electrically \nProximate Generator’s net injections are studied, which could result in NRIS greater than zero \nMWs.  Therefore, a Large Load Co-Located Generator or Large Load Electrically Proximate \nGenerator that is subsequently studied in the cluster study process may provide and receive credit \nfor energy supply, on a gross supply basis, in excess of their associated Large Load’s gross \ndemand, but not exceeding their NRIS.   \n \nThe market mitigation rules in Market Rule 1 Appendix A, which apply to all other \nwholesale energy supply resources in ISO-NE, will apply to a Large Load Co-Located Generator \nand Large Load Electrically Proximate Generator.  These rules allow for consultation with the \nmarket monitor on resource-specific physical and financial parameters.  Large Load Co-Located \nGenerators and Large Load Electrically Proximate Generators will be eligible to participate in the \nancillary services markets, subject to the same requirements for other generators, including but not \nlimited to capability auditing.  \n \n219 Id. at P 124."},{"page":91,"startToken":42587,"endToken":43047,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 91 of 99 \n \n \n \n \nIn ISO-NE, all resources undergo capability auditing to provide ancillary services, such as \nreserves, regulation, and voltage.  A Large Load Co-Located Generator and Large Load \nElectrically Proximate Generator will receive the same treatment—once they complete the \ninterconnection process, the Large Load Co-Located Generator and Large Load Electrically \nProximate Generator may perform capability audits to demonstrate their ability to provide \nancillary services.  Therefore, Large Load Co-Located Generator and Large Load Electrically \nProximate Generator may provide ancillary services, subject to a performance auditing, which \naligns with the treatment of other supply resources.  \n \nThe same mitigation rules that apply to other sellers of ancillary services will apply to a \nLarge Load Co-Located Generator or Large Load Electrically Proximate Generator that provides \nancillary services. \n \nF. \nTo the extent that ISO-NE plans for the electrically proximate large load or large \nco-located load associated with an interconnection customer's generating facility \nfor resource adequacy purposes, would ISO-NE account for the generating \nfacilities serving electrically proximate large load or large co-located load in the \nresource adequacy construct?  If applicable, would ISO-NE allow the generating \nfacilities serving electrically proximate large load or large co-located load to \nparticipate in ISO-NE's capacity market?  If so, would ISO-NE accredit these \ngenerating facilities using the same method as other ISO-NE generating \nfacilities?220 \nAs discussed in Section IV.C of this transmittal letter and in the answer to question E above, \nISO-NE’s proposal creates an expedited interconnection pathway for generating facilities \nassociated with Co-Located Large Loads and Electrically Proximate Large Loads.  Such \ngenerating facilities are defined as Large Load Co-Located Generators and Large Load Electrically \nProximate Generators, respectively.  Under ISO-NE’s proposal, Large Load Co-Located \nGenerators and Large Load Electrically Proximate Generators will have access to an expedited \ninterconnection pathway and an associated limited interconnection service that only provides zero \nMWs of NRIS.  This process allows ISO-NE to study a Co-Located Large Load or Electrically \nProximate Large Load together with its associated Large Load Co-Located Generators or Large \nLoad Electrically Proximate Generators in the same study, outside of the generation cluster study \nprocess.  Generating facilities that utilize this expedited interconnection pathway will be allowed \nto operate in parallel to the ISO-NE transmission system, but not be allowed to inject power to the \ngrid, nor will they be given Capacity Network Resource Interconnection Service (“CNRIS”).  In \nother words, Large Load Co-Located Generators or Large Load Electrically Proximate Generators \nare not deliverable to their respective Load Zones within the New England Transmission System, \nand are limited to serving their associated Co-Located Large Load or Electrically Proximate Large \nLoad consistent with their Non-Firm Large Load Generating Arrangement.  Therefore, defined \nLarge Load Co-Located Generators and Large Load Electrically Proximate Generators that choose \n \n220 Id."},{"page":92,"startToken":43047,"endToken":43510,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 92 of 99 \n \n \n \nto utilize the expedited interconnection pathway will not be counted towards the region’s capacity \nfor resource adequacy purposes, will not participate in the capacity market, and will not be \naccredited using the same method as other ISO-NE generating facilities.  \nLarge Load Co-Located Generators and Large Load Electrically Proximate Generators that \nutilize this expedited interconnection process will not be eligible to meet the requirements of a \ndesignated resource necessary to fulfill the BYONC requirement for firm service because that \nprocess does not allow resources to obtain CNRIS.  These generating facilities will instead be \nallowed to achieve the re-dispatch reduction of non-firm service that a Large Load Transmission \nCustomer takes on behalf of the Large Load associated with such generating facilities, consistent \nwith their Non-Firm Large Load Generating Arrangement.  The re-dispatch benefit that a Large \nLoad Co-Located Generator or Large Load Electrically Proximate Generator provides to its \nassociated Large Load will be reflected in the Large Load System Impact Study.221 \nGenerating facilities that are co-located with or electrically proximate to a Large Load are \nnot precluded from pursuing other existing options for interconnection, including the Cluster Study \nprocess, to increase their Interconnection Service.  Should a generating facility that is co-located \nwith or electrically proximate to a Large Load choose to enter a Cluster Study to establish CNRIS, \nthey will be treated the same as any other similar generating facility with similar levels of \nestablished CNRIS with respect to capacity market participation and accreditation.  This process \nwill be required for new generating facilities aiming to become designated resources to fulfill a \nLarge Load Transmission Customer’s requirements for Firm Contract Demand Service on behalf \nof a Large Load, even if those generating facilities are co-located or electrically proximate to the \nLarge Load.  However, doing so may prevent such a generating facility from being used to achieve \nthe re-dispatch reduction associated with a Large Load Transmission Customer’s non-firm \ntransmission service. \n \nVI. \nSTAKEHOLDER PROCESS  \nThe Tariff Revisions were considered and supported in the NEPOOL stakeholder process.  \nOn November 3, 2026, the NEPOOL Transmission Committee, Reliability Committee, and \nMarkets Committee each voted in favor of recommending the Participants Committee’s support \nfor the Tariff Revisions.  At its November 12, 2026 meeting, the Participants Committee supported \nthe Tariff Revisions.222 \n \n221 A Large Load Co-Located Generator or Large Load Electrically Proximate Generator that is studied after the \ncompletion of the Large Load System Impact Study for its associated Large Load will be studied in an interconnection \nstudy separate from the Large Load System Impact Study. \n222 NEPOOL supported the Tariff Revisions, except the proposed Large Load Cost Recovery Agreement (new \nAttachment V to the OATT) and, accordingly, it does not join this filing with respect to that agreement."},{"page":93,"startToken":43510,"endToken":44159,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 93 of 99 \n \n \n \nVII. \nEFFECTIVE DATE; REQUESTS FOR WAIVER AND EXTENDED COMMENT \nPERIOD \nThe Filing Parties respectfully request that the Commission accept the Tariff Revisions to \nbecome effective on November 14, 2026, one day after filing.  Because the requested effective \ndate does not permit 60-days’ prior notice, the Filing Parties request waiver of the Commission’s \nprior notice requirements to permit the proposed Tariff Revisions to take effect on the day after \nfiling.  Good cause exists for the Commission to grant waiver of the 60-day prior notice \nrequirement.223  While the Filing Parties propose to commence the new transmission services \napplication and study processes starting June 1, 2027, and provide the new transmission services \nstarting June 1, 2028, a November 14, 2026 effective date for the Tariff Revisions is necessary to \nallow affected parties, e.g., Large Load developers, potential Large Load Eligible Customers, to \nprepare and modify behavior and development plans as necessary to best take advantage of the \nnew transmission services.  In other words, once approved and made effective by the Commission, \nthe Tariff Revisions would provide certainty as to the applicable rules and avenues for \ninterconnecting Large Loads.224      \nGiven the breadth of this filing, including the Tariff Revisions, and upcoming holiday, the \nISO respectfully requests that the Commission grant an extended comment period of 24 days, or \nuntil December 7, 2026, to ensure that interested parties have ample time to review the filing.   \nAs described in this transmittal letter, the ISO proposes to start providing the transmission \nservices on June 1, 2028.  This is the date when the development and testing for the suite of \nsoftware components needed for implementation of the transmission services and operational \nrequirements will be ready.  The ISO has initiated an expedited process, in parallel to this filing, \nto develop the necessary software updates to modify the existing DARD model for use by Large \nLoad Transmission Customers.  While the ISO has planned to shift resources and work plans to \nprioritize this effort, it is still critically important to follow all development procedures and testing \nplans as this new software will be integrated into real-time market operations.  The use of the \nDARD model leverages an existing asset framework, but even minor updates will result in impacts \n \n223 Id. (permitting the Commission to waive the notice requirement for “good cause shown”). \n224 See, e.g., Nw. Power Pool, 197 FERC ¶ 61,098, at P 23 n.43 (2026) (permitting effective date one day after filing \nand granting applicant’s request for waiver of the Commission’s 60-day prior notice requirement (citing 18 C.F.R. § \n35.11 (“Upon application and for good cause shown, the Commission may, by order, provide that a rate schedule or \ntariff, tariff or service agreement, or part thereof, shall be effective . . . prior to the date the rate schedule or tariff, tariff \nor service agreement would become effective in accordance with these rules.”)); Sentinel Energy Ctr., LLC, 189 FERC \n¶ 61,177, at P 14 (2024) (permitting effective date one day after filing and granting waiver of prior notice “in order \nfor the parties to receive the benefit of certain provisions of the Amended Agreement that need to be in effect during \nthe final phases of the construction, commissioning, and performance testing to be done in November or December, \n2024”); PJM Interconnection, L.L.C., 195 FERC ¶ 61,227, at P 29 (2026) (permitting effective date one day after \nfiling and stating “we find good cause to grant PJM’s request for waiver of the Commission’s 60-day prior notice \nrequirement to allow PJM’s requested effective date because it is necessary to provide certainty to [State Agreement \nApproach] Project developers, participants in the upcoming [Regional Transmission Expansion Plan] proposal \nwindow, and interconnection customers and developers regarding the status of the affected projects and the \nassumptions that will be used in PJM’s planning and interconnection processes”)."},{"page":94,"startToken":44159,"endToken":44542,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 94 of 99 \n \n \n \nto power system modeling systems, markets systems, settlement systems, the Customer Asset \nManagement System, forecasting applications, and dozens of other downstream applications.  \nDuring the time when the software is being developed, the ISO can conduct studies for Large \nLoads, and, accordingly, the ISO will start accepting Large Load Transmission Service \nApplications and Large Load Co-Located Generator/Large Load Electrically Proximate Generator \nInterconnection Applications starting on June 1, 2027. \nVIII. \nADDITIONAL SUPPORTING INFORMATION \n \nSection 35.13 of the Commission’s regulations generally requires public utilities to file \ncertain cost and other information related to an examination of traditional cost-of-service rates.225  \nHowever, the Tariff Revisions filed herein are not traditional “rates.”  Further, ISO-NE is not a \ntraditional investor-owned utility.  Therefore, to the extent necessary, the Filing Parties request \nwaiver of Section 35.13 of the Commission’s regulations.  Notwithstanding their request for \nwaiver, the Filing Parties submit the additional information enumerated below in substantial \ncompliance with relevant provisions of Section 35.13. \n \n35.13(b)(1) – Materials included herewith are as follows:  \n \n♦ \nThis transmittal letter; \n \n♦ \nTestimony of Dennis Cakert in support of the Tariff Revisions related to use of the \nDARD model and the price-based re-dispatch mechanism; \n \n♦ \nAffidavit of Alexander Rost in support of all other Tariff Revisions submitted under \nthe ISO’s section 205 rights; \n \n♦ \nMarked Tariff sections reflecting the Tariff Revisions proposed under the section \n205 rights of the ISO and under the joint section 205 rights of the ISO and the PTOs, \nas well as the Tariff Revisions in Section II.21.2 of the OATT and new Section \nII.62 of the OATT (both proposed under the joint section 205 rights of the PTOs); \n \n♦ \nClean Tariff sections incorporating the Tariff Revisions proposed under the section \n205 rights of the ISO and under the joint section 205 rights of the ISO and the PTOs, \nas well as the Tariff Revisions in Section II.21.2 of the OATT and new Section \nII.62 of the OATT (both proposed under the joint section 205 rights of the PTOs); \n \n♦ \nMarked Tariff sections reflecting the Tariff Revisions proposed under the joint \nsection 205 rights of the PTOs and under the individual section 205 rights of the \nPTOs;  \n \n \n225 18 C.F.R. § 35.13."},{"page":95,"startToken":44542,"endToken":44984,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 95 of 99 \n \n \n \n♦ \nClean Tariff sections incorporating the Tariff Revisions proposed under the joint \nsection 205 rights of the PTOs and under the individual section 205 rights of the \nPTOs; and \n \n♦ \nList of governors, utility regulatory agencies in Connecticut, Maine, Massachusetts, \nNew Hampshire, Rhode Island, and Vermont, and others to whom a copy of this \nfiling has been emailed. \n \n35.13(b)(2) – As noted above, the Filing Parties request that the Tariff Revisions become \neffective on November 14, 2026. \n \n35.13(b)(3) – Pursuant to Section 17.11(e) of the Participants Agreement, Governance \nParticipants are being served electronically rather than by paper copy.  The names and addresses \nof the Governance Participants are posted on the ISO-NE website at https://www.iso-\nne.com/participate/participant-asset-listings/.  A copy of this transmittal letter and the \naccompanying materials have also been sent electronically to the governors and electric utility \nregulatory agencies for the six New England states that comprise the New England Control Area, \nto the New England Conference of Public Utility Commissioners, and to the Executive Director \nof the New England States Committee on Electricity.  In accordance with Commission rules and \npractice, there is no need for the Governance Participants or the other entities described above to \nbe included on the Commission’s official service list in the captioned proceeding unless such \nentities become intervenors in this proceeding. \n \n35.13(b)(4) – A description of the materials submitted in this filing is contained in \nSection VIII of this transmittal letter.  \n \n35.13(b)(5) – The reasons for this filing are discussed in Section IV of this transmittal \nletter. \n \n35.13(b)(6) – The ISO and PTO AC’s respective approval of the Tariff Revisions is \nevidenced by this filing.  The PTO AC reviewed and provided input on the revisions to Section \nI.2.2 of the Tariff and Schedules 22 and 23 of the OATT, which are subject to the PTOs’ shared \nfiling rights with the ISO, at its October 29, 2026 meeting, and voted in accordance with the TOA \nand the Rate Design and Funds Disbursement Agreement among the PTOs.  With respect to \nNEPOOL’s support, as noted in Section VI of this transmittal letter, the revisions reflect the results \nof the Participant Processes required by the Participants Agreement and reflect the support of the \nNEPOOL Participants Committee.   \n \n35.13(b)(7) – The Filing Parties have no knowledge of any relevant expenses or costs of \nservice that have been alleged or judged in any administrative or judicial proceeding to be illegal, \nduplicative, or unnecessary costs that are demonstrably the product of discriminatory employment \npractices."},{"page":96,"startToken":44984,"endToken":45188,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 96 of 99 \n \n \n \nIX. \nCONCLUSION \nFor the foregoing reasons, the Filing Parties respectfully request that the Commission \naccept the Tariff Revisions as proposed herein, without modifications or conditions, so that they \ncan become effective on November 14, 2026, and terminate the show cause proceeding in full. \n \n \n \n \nRespectfully submitted, \n \n \nISO NEW ENGLAND INC. \n \nBy: /s/ Margoth Caley \nMargoth Caley \nChief Regulatory Compliance Counsel \nISO New England Inc. \nOne Sullivan Road \nHolyoke, MA 01040-2841 \n(413) 387-2408 \nmcaley@iso-ne.com \n \nCounsel for ISO New England \nNEPOOL PARTICIPANTS COMMITTEE \n \nBy: /s/ Eric K. Runge \nEric K. Runge \nDay Pitney LLP \nOne Federal Street \nBoston, MA 02110 \n(617) 345-4735 \nekrunge@daypitney.com  \n \nCounsel for New England Power Pool \nParticipants Committee \n \nPARTICIPATING TRANSMISSION \nOWNERS ADMINISTRATIVE \nCOMMITTEE \n \nBy:  /s/ Mary E. Grover \nMary E. Grover \nChair, PTO AC Legal Working Group  \nc/o Eversource Energy \n247 Station Drive, SE100 \nWestwood, MA 02090 \n(781) 441-8696 \nmary.grover@eversource.com \n \nCounsel for PTO Administrative \nCommittee \n \n \n \nCENTRAL MAINE POWER COMPANY and \nUNITED ILLUMINATING COMPANY \n \nBy:  /s/ Noelle M. Kinsch  \nNoelle M. Kinsch \nAvangrid Networks, Inc. \n80 State Street, 12th Floor \nAlbany, NY 12207 \n(518) 461-6984 \nnoelle.kinsch@avangrid.com \n \nCounsel for CMP and UI"},{"page":97,"startToken":45188,"endToken":45361,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 97 of 99 \n \n \n \n \nCONNECTICUT TRANSMISSION ELECTRIC \nENERGY COOPERATIVE \n \nBy:  /s/ Amber Martin Stone \nAmber Martin Stone \nGeneral Counsel \nConnecticut Municipal Electric Energy \nCooperative \n30 Stott Avenue \nNorwich, CT 06360 \n(860) 383-1050 \nastone@cmeec.org \n \nCounsel for CTMEEC \nEVERSOURCE ENERGY SERVICE \nCOMPANY as agent for THE \nCONNECTICUT LIGHT AND POWER \nCOMPANY, NSTAR ELECTRIC \nCOMPANY and PUBLIC SERVICE \nCOMPANY OF NEW HAMPSHIRE \n \nBy:  /s/ Thomas Lemon \nThomas Lemon \nEversource Energy Service Company \n247 Station Drive, SE100 \nWestwood, MA  02090 \n(781) 441-8692 \nthomas.lemon@eversource.com \n \nCounsel for Eversource \n \n \nFITCHBURG GAS AND ELECTRIC LIGHT \nCOMPANY and UNITIL ENERGY SYSTEMS, \nINC. \n \nBy:  /s/ Patrick H. Taylor \nPatrick H. Taylor \nUnitil Service Corp. \n6 Liberty Lane West \nHampton, NH 03842 \n(603) 773-6544 \ntaylorp@unitil.com \n \nCounsel for FG&E and UES \n \nGREEN MOUNTAIN POWER \nCORPORATION \n \nBy:  /s/ Liz Miller  \nLiz Miller \nExternal Coordinating Counsel \nElizabeth Miller PLC \nc/o Green Mountain Power Corp. \n163 Acorn Lane \nColchester, VT 05446 \n(802) 522-3090 \nliz.miller@greenmountainpower.com \n \nCounsel for GMP"},{"page":98,"startToken":45361,"endToken":45472,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 98 of 99 \n \n \n \n \nNEW ENGLAND POWER COMPANY d/b/a \nNATIONAL GRID \n \nBy:  /s/ Christopher J. Novak  \nChristopher J. Novak \nSenior Counsel \nNational Grid \n170 Data Drive \nWaltham, MA 02451 \n(617) 690-9964 \nChris.Novak@nationalgrid.com \n \nCounsel for National Grid \nTHE NARRAGANSETT ELECTRIC \nCOMPANY d/b/a RHODE ISLAND \nENERGY \n \nBy:  /s/ Steven M. Nadel  \nSteven M. Nadel \nSenior Counsel \nPPL SERVICES CORPORATION \n645 Hamilton Street, Suite 700 \nAllentown, PA 18101 \n(610) 774-4775 \nSMNadel@pplweb.com \n \nKimberly B. Frank \nK&L Gates LLP \n1601 K Street, N.W. \nWashington, D.C. 20006 \n(202) 778-9064 \nkimberly.frank@klgates.com \n \nCounsel for RIE"},{"page":99,"startToken":45472,"endToken":45666,"text":"The Honorable Debbie Anne Reese, Secretary \nNovember 13, 2026 \nPage 99 of 99 \n \n \n \nNEW HAMPSHIRE TRANSMISSION LLC \n \nBy:  /s/ Travis M. Contratto  \nTravis M. Contratto \nPrincipal Attorney – Federal Regulatory Affairs \nNextEra Energy Inc. \n801 Pennsylvania Avenue, N.W., Suite 220 \nWashington, D.C. 20004 \n(202) 904-5928 \ntravis.contratto@nee.com \n \nCounsel for NHT \n \nVERMONT ELECTRIC \nCOOPERATIVE, INC. \n \nBy:  /s/ Craig Silverstein   \nMarch Counsel LLC \n2001 L Street NW \nSuite 500 \nWashington, DC 20007 \n(202) 640-2100 \ncraig.silverstein@marchcounsel.com \n \nCounsel for VEC  \nVERSANT POWER \n \nBy:  /s/ Jeffrey M. Jakubiak  \nJeffrey M. Jakubiak \nMelinda J. Warner \nVinson & Elkins LLP \n1114 Avenue of the Americas, 32nd Floor \nNew York, NH 10036 \n(212) 237-0000 \nJJakubiak@velaw.com \nMWarner@velaw.com \n \nArielle Silver Karsh \nVP, Legal and Regulatory Affairs \nVersant Power \n970 Illinois Avenue \nBangor, ME 04401 \n(207) 973-2819 \narielle.silverkarsh@versantpower.com \n \nCounsel for Versant \n \nVERMONT TRANSCO LLC \n \nBy:  /s/ Lamiya N. Rahman  \nLamiya N. Rahman \nBlank Rome LLP \n1825 Eye Street, NW \nWashington, D.C. 20006 \n(202) 420-2662 \nlamiya.rahman@blankrome.com \n \nAlison Milbury Stone \nSenior Legal Counsel \nVermont Transco LLC \n366 Pinnacle Ridge Road \nRutland, VT 05701 \n(802) 712-5064 \nastone@velco.com \n \nCounsel for VTransco"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":2277,"startToken":0,"endToken":690},{"p":2,"at":2277,"title":"I. DESCRIPTION OF THE FILING PARTIES AND COMMUNICATIONS","method":"PDF bookmark","endPage":8,"endAt":813,"startToken":690,"endToken":2269},{"p":8,"at":813,"title":"II. STANDARD OF REVIEW","method":"PDF bookmark","endPage":9,"endAt":299,"startToken":2269,"endToken":2565},{"p":9,"at":299,"title":"III. BACKGROUND AND EXECUTIVE SUMMARY","method":"PDF bookmark","endPage":9,"endAt":339,"startToken":2565,"endToken":2570},{"p":9,"at":339,"title":"A. Background","method":"PDF bookmark","endPage":9,"endAt":343,"startToken":2570,"endToken":2571},{"p":9,"at":343,"title":"Background","method":"printed heading","endPage":11,"endAt":1510,"startToken":2571,"endToken":3738},{"p":11,"at":1510,"title":"B. Executive Summary","method":"PDF bookmark","endPage":11,"endAt":1514,"startToken":3738,"endToken":3739},{"p":11,"at":1514,"title":"Executive Summary","method":"printed heading","endPage":11,"endAt":1533,"startToken":3739,"endToken":3741},{"p":11,"at":1533,"title":"1. The Tariff Revisions Address the Five Categories of Reform in the Show Cause Order","method":"PDF bookmark","endPage":11,"endAt":1911,"startToken":3741,"endToken":3798},{"p":11,"at":1911,"title":"a. Efficient Study Processes","method":"PDF bookmark","endPage":12,"endAt":1469,"startToken":3798,"endToken":4158},{"p":12,"at":1469,"title":"b. Co-location Rules","method":"PDF bookmark","endPage":12,"endAt":2057,"startToken":4158,"endToken":4243},{"p":12,"at":2057,"title":"c. Flexible Load Service","method":"PDF bookmark","endPage":13,"endAt":239,"startToken":4243,"endToken":4438},{"p":13,"at":239,"title":"d. Generation Studies","method":"PDF bookmark","endPage":13,"endAt":1274,"startToken":4438,"endToken":4589},{"p":13,"at":1274,"title":"e. Cost Transparency","method":"PDF bookmark","endPage":13,"endAt":2273,"startToken":4589,"endToken":4739},{"p":13,"at":2273,"title":"2. The Tariff Revisions Address Resource Adequacy Concerns","method":"PDF bookmark","endPage":14,"endAt":1388,"startToken":4739,"endToken":5107},{"p":14,"at":1388,"title":"IV. DESCRIPTION OF THE PROPOSED TARIFF REVISIONS TO ADDRESS THE COMMISSION’S CONCERNS IN THE SHOW CAUSE ORDER","method":"PDF bookmark","endPage":16,"endAt":531,"startToken":5107,"endToken":5902},{"p":16,"at":531,"title":"A. Tariff Revisions in Section I.2.2 of the Tariff (Definitions)","method":"PDF bookmark","endPage":16,"endAt":711,"startToken":5902,"endToken":5935},{"p":16,"at":711,"title":"1. Definition of Large Load","method":"PDF bookmark","endPage":17,"endAt":2102,"startToken":5935,"endToken":6555},{"p":17,"at":2102,"title":"2. Definition of Behind-the-Meter Generation","method":"PDF bookmark","endPage":18,"endAt":909,"startToken":6555,"endToken":6886},{"p":18,"at":909,"title":"3. Definition of Electrically Proximate Large Load","method":"PDF bookmark","endPage":19,"endAt":639,"startToken":6886,"endToken":7266},{"p":19,"at":639,"title":"4. Other Definitions","method":"PDF bookmark","endPage":23,"endAt":1366,"startToken":7266,"endToken":8947},{"p":23,"at":1366,"title":"B. Tariff Revisions in Response to the Show Cause Order Proposed by the ISO Under the ISO’s Section 205 Rights","method":"PDF bookmark","endPage":23,"endAt":1480,"startToken":8947,"endToken":8967},{"p":23,"at":1480,"title":"1. Preamble in New Part II.J of the OATT – Transition to New Large Load Transmission Services to Accommodate Existing Commercial Arrangements","method":"PDF bookmark","endPage":26,"endAt":170,"startToken":8967,"endToken":9895},{"p":26,"at":170,"title":"2. New Section II.56 of the OATT – Establishment of New Large Load Transmission Services","method":"PDF bookmark","endPage":27,"endAt":84,"startToken":9895,"endToken":10187},{"p":27,"at":84,"title":"3. New Section II.57 of the OATT and New Section III.1.10.5A of the Tariff – Nature and Flexibility of New Large Load Transmission Services","method":"PDF bookmark","endPage":28,"endAt":1242,"startToken":10187,"endToken":10894},{"p":28,"at":1242,"title":"a. DARD Model","method":"PDF bookmark","endPage":31,"endAt":90,"startToken":10894,"endToken":11546},{"p":31,"at":90,"title":"b. Price-Based Re-Dispatch Mechanism","method":"PDF bookmark","endPage":33,"endAt":506,"startToken":11546,"endToken":12528},{"p":33,"at":506,"title":"4. New Section II.58 of the OATT – Application Process to Evaluate the Provision of Large Load Transmission Services","method":"PDF bookmark","endPage":35,"endAt":2214,"startToken":12528,"endToken":13628},{"p":35,"at":2214,"title":"5. New Section II.60 of the OATT – Study Procedures to Evaluate the Provision of Large Load Transmission Services","method":"PDF bookmark","endPage":36,"endAt":84,"startToken":13628,"endToken":13822},{"p":36,"at":84,"title":"a. Study Timelines","method":"PDF bookmark","endPage":37,"endAt":1449,"startToken":13822,"endToken":14635},{"p":37,"at":1449,"title":"b. Large Load Material Modification","method":"PDF bookmark","endPage":38,"endAt":561,"startToken":14635,"endToken":14935},{"p":38,"at":561,"title":"c. Large Load System Impact Study Scope","method":"PDF bookmark","endPage":39,"endAt":1484,"startToken":14935,"endToken":15630},{"p":39,"at":1484,"title":"d. Large Load System Impact Study Report","method":"PDF bookmark","endPage":39,"endAt":2494,"startToken":15630,"endToken":15783},{"p":39,"at":2494,"title":"e. Evaluation of Alternative Transmission Technologies","method":"PDF bookmark","endPage":40,"endAt":986,"startToken":15783,"endToken":15989},{"p":40,"at":986,"title":"f. Large Load Facilities Study Procedures","method":"PDF bookmark","endPage":41,"endAt":86,"startToken":15989,"endToken":16363},{"p":41,"at":86,"title":"g. Coordination of Studies to Support a Non-Firm Large Load Generator Arrangement","method":"PDF bookmark","endPage":41,"endAt":1742,"startToken":16363,"endToken":16609},{"p":41,"at":1742,"title":"6. New Section II.61 of the OATT – Remote Disconnection of a Large Load and Load Shedding","method":"PDF bookmark","endPage":42,"endAt":1935,"startToken":16609,"endToken":17194},{"p":42,"at":1935,"title":"7. New Section II.63 of the OATT – Operational Requirements for Large Load Transmission Customers","method":"PDF bookmark","endPage":44,"endAt":1362,"startToken":17194,"endToken":18161},{"p":44,"at":1362,"title":"8. New Attachments S, T, and U to the OATT – Large Load Transmission Service Agreement, Large Load System Impact Study Agreement, and Large Load Facilities Study Agreement","method":"PDF bookmark","endPage":46,"endAt":444,"startToken":18161,"endToken":19151},{"p":46,"at":444,"title":"9. Revisions in Schedules 2, 16, and 17 of the OATT","method":"PDF bookmark","endPage":47,"endAt":2547,"startToken":19151,"endToken":19991},{"p":47,"at":2547,"title":"10. Conforming Revisions to Sections II.20.2 and II.20.3 of the OATT","method":"PDF bookmark","endPage":48,"endAt":84,"startToken":19991,"endToken":20143},{"p":48,"at":84,"title":"11. Revisions in Sections III.1, III.2, and III.15 of the Tariff","method":"PDF bookmark","endPage":48,"endAt":2859,"startToken":20143,"endToken":20568},{"p":48,"at":2859,"title":"C. Tariff Revisions in Response to the Show Cause Order Proposed by the ISO and the PTOs Under Joint ISO/PTOs Section 205 Rights","method":"PDF bookmark","endPage":53,"endAt":1475,"startToken":20568,"endToken":23104},{"p":53,"at":1475,"title":"D. PTOs’ Tariff Revisions in Response to the Show Cause Order","method":"PDF bookmark","endPage":53,"endAt":1539,"startToken":23104,"endToken":23115},{"p":53,"at":1539,"title":"1. New Section II.62 of the OATT","method":"PDF bookmark","endPage":54,"endAt":705,"startToken":23115,"endToken":23673},{"p":54,"at":705,"title":"2. New Attachment V of the OATT (Large Load Cost Recovery Agreement)","method":"PDF bookmark","endPage":56,"endAt":2601,"startToken":23673,"endToken":25051},{"p":56,"at":2601,"title":"a. Operation and Provisions of the LLCRA","method":"PDF bookmark","endPage":59,"endAt":1141,"startToken":25051,"endToken":26234},{"p":59,"at":1141,"title":"b. Cost Allocation Mechanisms of the LLCRA","method":"PDF bookmark","endPage":59,"endAt":2114,"startToken":26234,"endToken":26385},{"p":59,"at":2114,"title":"i. Direct Assignment Facilities","method":"PDF bookmark","endPage":60,"endAt":84,"startToken":26385,"endToken":26492},{"p":60,"at":84,"title":"ii. Cost Recovery Charge","method":"PDF bookmark","endPage":60,"endAt":1241,"startToken":26492,"endToken":26664},{"p":60,"at":1241,"title":"iii. Exit Fee","method":"PDF bookmark","endPage":60,"endAt":1716,"startToken":26664,"endToken":26738},{"p":60,"at":1716,"title":"iv. Credit Support","method":"PDF bookmark","endPage":60,"endAt":2642,"startToken":26738,"endToken":26889},{"p":60,"at":2642,"title":"c. The LLCRA Meets the FPA Section 205 Standard","method":"PDF bookmark","endPage":64,"endAt":1428,"startToken":26889,"endToken":28866},{"p":64,"at":1428,"title":"d. The LLCRA is subject to the Commission’s jurisdiction","method":"PDF bookmark","endPage":72,"endAt":915,"startToken":28866,"endToken":33001},{"p":72,"at":915,"title":"iii. The LLCRA avoids the jurisdictional defects identified in the PJM IRAS Order","method":"PDF bookmark","endPage":74,"endAt":84,"startToken":33001,"endToken":33853},{"p":74,"at":84,"title":"iv. The LLCRA addresses the concerns identified in the Show Cause Order","method":"PDF bookmark","endPage":74,"endAt":1824,"startToken":33853,"endToken":34101},{"p":74,"at":1824,"title":"3. Revisions to Schedule 1 of the OATT","method":"PDF bookmark","endPage":75,"endAt":750,"startToken":34101,"endToken":34443},{"p":75,"at":750,"title":"4. New Schedule 9A of the OATT","method":"PDF bookmark","endPage":75,"endAt":1237,"startToken":34443,"endToken":34522},{"p":75,"at":1237,"title":"5. Revisions to Schedule 21-Common","method":"PDF bookmark","endPage":76,"endAt":306,"startToken":34522,"endToken":34880},{"p":76,"at":306,"title":"6. Revisions to Local Service Schedules in Schedule 21 of the OATT","method":"PDF bookmark","endPage":81,"endAt":2110,"startToken":34880,"endToken":37642},{"p":81,"at":2110,"title":"7. Conforming Revisions in Section II.21.2 of the OATT","method":"PDF bookmark","endPage":81,"endAt":2606,"startToken":37642,"endToken":37723},{"p":81,"at":2606,"title":"E. Tariff Revisions in Response to the Commission’s Resource Adequacy","method":"printed heading","endPage":85,"endAt":1569,"startToken":37723,"endToken":39777},{"p":85,"at":1569,"title":"V. ANSWERS TO BRIEFING QUESTIONS","method":"PDF bookmark","endPage":85,"endAt":1938,"startToken":39777,"endToken":39835},{"p":85,"at":1938,"title":"A. How should ISO-NE and the PTOs protect existing commercial arrangements,","method":"printed heading","endPage":86,"endAt":1766,"startToken":39835,"endToken":40290},{"p":86,"at":1766,"title":"B. What, if any, potential impacts on regional and local transmission planning would","method":"printed heading","endPage":87,"endAt":2664,"startToken":40290,"endToken":40929},{"p":87,"at":2664,"title":"C. Include information regarding potential structures for agreements between the","method":"printed heading","endPage":88,"endAt":2580,"startToken":40929,"endToken":41481},{"p":88,"at":2580,"title":"D. Further briefing regarding specific characteristics of providing transmission","method":"printed heading","endPage":89,"endAt":3127,"startToken":41481,"endToken":42040},{"p":89,"at":3127,"title":"E. To what extent would ISO-NE allow an interconnection customer's generating","method":"printed heading","endPage":91,"endAt":989,"startToken":42040,"endToken":42721},{"p":91,"at":989,"title":"F. To the extent that ISO-NE plans for the electrically proximate large load or large","method":"printed heading","endPage":92,"endAt":2287,"startToken":42721,"endToken":43376},{"p":92,"at":2287,"title":"VI. STAKEHOLDER PROCESS","method":"PDF bookmark","endPage":93,"endAt":84,"startToken":43376,"endToken":43523},{"p":93,"at":84,"title":"VII. EFFECTIVE DATE; REQUESTS FOR WAIVER AND EXTENDED COMMENT PERIOD","method":"PDF bookmark","endPage":94,"endAt":597,"startToken":43523,"endToken":44240},{"p":94,"at":597,"title":"VIII. ADDITIONAL SUPPORTING INFORMATION","method":"PDF bookmark","endPage":96,"endAt":84,"startToken":44240,"endToken":44997},{"p":96,"at":84,"title":"IX. CONCLUSION","method":"PDF bookmark","endPage":96,"endAt":89,"startToken":44997,"endToken":44998},{"p":96,"at":89,"title":"CONCLUSION","method":"printed heading","endPage":99,"endAt":1339,"startToken":44998,"endToken":45666}]}
