{"document":{"slug":"filing-er27-526-miso-large-loads","title":"MISO and its transmission owners file large-load review, cost recovery and transmission service revisions under section 205","issued":"2026-11-16","accession":"20261116-5323","docket":"ER27-526-000","group":"MISO filings","filer":"Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners","kind":"filing","file":"sources/originals/20261116-5323_01.pdf","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20261116-5323","sha256":"3cda4ad54863190c7fdfa4ad76bf92c64948f31fff7bf781166a9abb7b8a15d0","pages":67,"tokens":28241,"emptyPages":[]},"pages":[{"page":1,"startToken":0,"endToken":463,"text":"Midcontinent Independent \nSystem Operator, Inc. \n317.249-5400 \nwww.misoenergy.org \n720 City Center Drive \nCarmel, Indiana 46032 \n2985 Ames Crossing Road \nEagan, Minnesota 55121 \n1700 Centerview Drive \nLittle Rock, AR 72211 \n \nMichael Kessler \nManaging Assistant General Counsel \nDirect Dial:  317-753-9434 \nEmail:  mkessler@misoenergy.org \n \nNovember 16, 2026 \n \nVIA ELECTRONIC FILING \n \nThe Honorable Debbie-Anne Reese  \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC  20426 \n \nRe: \nMidcontinent Independent System Operator, Inc.’s  \nLarge Load Review, Cost Recovery and Transmission Services Filing \nDocket No. ER27-___-000 \n \nDear Secretary Reese: \n \nThe Midcontinent Independent System Operator, Inc. (“MISO”), and the MISO \nTransmission Owners1 through this filing,2 submit proposed revisions to its Open Access \nTransmission, Energy and Operating Reserve Markets Tariff (“Tariff”),3 concerning the \nintegration of Large Loads.4  This omnibus filing describes the proposals MISO has already \n \n1  \nThe MISO Transmission Owners for this filing consist of: AEP Indiana Michigan Transmission Company; \nAmeren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois \nCompany d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; Arkansas Electric Cooperative \nCorporation; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens Electric \nCorporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland \nPower Cooperative; Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric \nCooperative, Inc.; Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New \nOrleans, LLC; Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural \nElectric Cooperative, Inc.; Indiana Municipal Power Agency; International Transmission Company d/b/a ITC \nTransmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric Transmission Company, LLC; \nMidAmerican Energy Company; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company LLC; \nPrairie Power, Inc.; Republic Transmission, LLC; Southern Illinois Power Cooperative; Southern Indiana Gas & \nElectric Company (d/b/a CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency; \nWabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc. \n2  \nThis filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Part 35 of \nthe regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. § 35.1, et \nseq. \n3  \nUnless otherwise indicated by the text or context of this transmittal letter, all terms used herein have the definitions \nset forth in Module A of the Tariff. \n4  \nThe MISO Transmission Owners join this filing for the purpose of exercising their filing rights and supporting \nthe filing of the Large Load Cost Recovery Agreement and the Large Load Impacted Transmission Owner Cost \nRecovery Agreement.  Consistent with the MISO Transmission Owners Agreement, a majority of the MISO \nTransmission Owners voted in favor of filing the Large Load Cost Recovery Agreement and the Large Load"},{"page":2,"startToken":463,"endToken":1006,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 2 \n \nsubmitted in response to the Federal Energy Regulatory Commission’s (“Commission”) June 18, \n2026, Show Cause Order5 and presents additional proposals in response to that order that have \nbeen developed as MISO obtained the information and completed the design work necessary to \nbring those components forward.6 \n \nMISO’s response has proceeded through a series of related filings addressing different \naspects of Large Load integration.7  The Zero Injection Generator Interconnection Agreement \n(“ZGIA”), Interconnection Reliability Requirements for Large Loads (“IRR”), and Large Load \nAddition Resource Study (“LARS”) proposals addressed components that were ready for \nCommission review while work continued on the application, transmission service, and financial \nprovisions needed to address the remaining issues.  This filing explains how those proposals fit \ntogether with the further revisions described below.8 \n \nThe additional revisions addressed here9 establish the Large Load Project Review \n(“LLPR”) process and provide transmission service options reflecting a Large Load’s intended use \nof the Transmission System, including a Firm Service Step Up (“FSSU”) process to evaluate the \navailability of Network Integration Transmission Service (“NITS”), and Interim Network \nIntegration Transmission Service (“Interim NITS”).  In addition, and as part of the LLPR process, \nMISO and its Transmission Owners propose Tariff revisions and two pro forma cost recovery \nagreements (the Large Load Cost Recovery Agreement and Large Load Impacted Transmission \nOwner Cost Recovery Agreement), which are designed to mitigate the risk of cost shifting among \n \nImpacted Transmission Owner Cost Recovery Agreement.  See Agreement of Transmission Facilities Owners To \nOrganize The Midcontinent Independent System Operator, Inc., A Delaware Non-Stock Corporation, Rate \nSchedule FERC No. 1, Appendix K § II. \n5  \nMidcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,123 (2026) (“Show Cause Order”) (identifying the issues \nconcerning large and co-located loads that are the subject of the section 206 proceeding).   \n6  \n16 U.S.C. § 824d; 18 C.F.R. §§ 35.3, 35.13 (2026). \n7  \nAs proposed in MISO’s IRR filing, a Large Load is defined as “Load with Demand of 50 MW or more associated \nwith any facility or aggregation of facilities located at a single substation behind one or more Point(s) of \nWithdrawal from the Transmission System that is owned, operated, or controlled by: (a) a single entity, or (b) a \ngroup of entities that will coordinate with respect to the profile of the Load.  Large Load does not include Load \nused exclusively for charging an Electric Storage Resource.”   \n8  \nMISO, Transmittal Letter, Zero Injection Generator Interconnection Agreement, Docket No. ER26-3552-000, at \n1–2, 5–7 (Aug. 18, 2026) (“ZGIA Transmittal”) (reserving transmission service and electrically proximate load \nissues for later proposals); MISO, Transmittal Letter, Interconnection Reliability Requirements for Large Loads, \nDocket No. ER26-3650-000, at 1, 4 (Aug. 28, 2026) (“IRR Transmittal”) (identifying additional study, service, \nand cost protection work); MISO, Transmittal Letter, Large Load Addition Resource Study, Docket No. ER27-\n25-000, at 14–15, 20–21 (Oct. 2, 2026) (“LARS Transmittal”) (anticipating further transmission service and cost \nprotection provisions). \n9  \nThis transmittal letter frequently quotes proposed Tariff revisions to facilitate its explanation.  In the event of a \nconflict between the Tariff language as discussed in this letter and that reflected in the attached Tariff sheets, \nMISO intends that the language in the attached Tariff sheets control."},{"page":3,"startToken":1006,"endToken":1481,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 3 \n \nTransmission Customers  resulting from a Transmission Customer’s taking of Transmission \nService on behalf of a Large Load.10 \n \nMISO requests that the Commission accept the proposed revisions effective 90 days from \nthe date of this filing (i.e., February 14, 2027).  MISO recognizes this filing includes significant \nTariff revisions and introduces new processes and cost recovery mechanisms that impact the \nbroader stakeholder community.  In response to OMS and other stakeholder requests for MISO to \nsupport an extended comment period, MISO proposes a 30-day comment period to allow \nstakeholders sufficient time to evaluate and comment on the proposals being presented in this \nfiling.  This extended comment period reasonably balances the need for additional time for \nstakeholder review while maintaining the urgency presented by the Show Cause Order and works \nwell within MISO’s requested 90-day effective date request.  \n \nI. \nEXECUTIVE SUMMARY \n \nMISO to date has been able to successfully manage the integration of large loads leveraging \nexisting MISO tools and quickly recognized the need for additional frameworks and processes to \nsupport reliable, efficient, and cost-effective integration given projected trends for f faster and \ndramatic demand growth across the region.  To this end, MISO, its Transmission Owners, state \nregulatory authorities, and broad stakeholder community have been working collaboratively to \nsupport the reliable, cost-effective, and efficient integration of large loads.  Over the past two years \nMISO has been developing new processes and tools to provide additional transparency, efficient \nreliability standardization, integrated solutions for generation and new transmission service \nofferings with stakeholders to meet the challenge.  The MISO Large Load Working Group has \nbeen an effective clearing house for such efforts and is providing a constructive, collaborative \nforum to develop these solutions.  This group met over thirteen times in the last eight months with \nan average of 400 people and a peak of 1000 people participating in each session.  This process \nincluded over 100 MISO presentations to stakeholders and over 400 feedback responses from \nstakeholders. \n   \nMISO recognizes the need for balanced solutions to support the diverse interests of \nstakeholders and state policies across the MISO region.  While these differing perspectives can \nmake unanimity- difficult to achieve, they contribute to a robust stakeholder process and better-\ninformed outcomes that ultimately drive the enormous value that MISO membership brings to \ncustomers in terms of reliability, cost-effectiveness and policy enablement. \n  \nThe Commission’s Show Cause Order provided important support for MISO’s ongoing \nefforts to develop solutions for responsible and reliable integration of large loads.  By identifying \nspecific priorities and encouraging incremental filings as solutions matured, the Commission \nestablished a framework that enabled stakeholders and MISO to advance improvements without \nwaiting for a single comprehensive package. \n \n10  Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and \nAttachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery \nAgreement)."},{"page":4,"startToken":1481,"endToken":1958,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 4 \n \n \nIn response, MISO has already filed several proposals responsive to the Show Cause Order \nthat are currently pending before the Commission, including Zero Injection-GIA, Large Load \nInterconnection Reliability Requirements, and the Load Additions Resource Study.  Collectively \nthese filings represent meaningful progress toward more timely, transparent, reliable, and cost-\neffective large load integration, which appropriately mitigates cost shifts to other Transmission \nCustomers.   \n  \nThe additional package of solutions in this filing and the companion filing11 complement \nMISO’s pending Large Load filings and directly address the remaining concerns identified in the \nShow Cause Order.  MISO’s filings, in the aggregate, reflect its compliance with the timelines and \nscope of the Show Cause Order.  At the same time, MISO recognizes that Large Load integration \nwill continue to evolve.  These filings represent an important milestone, not an endpoint.  MISO \nremains committed to further enhancing its planning, operational, and market frameworks as \nexperience is gained and system needs grow.  The Large Load Working Group will continue to \nserve as the primary stakeholder forum for evaluating, developing and refining additional solutions \nto support ongoing integration of Large Loads across the MISO region. \n  \nThe filings before the Commission are the product of an extremely robust, albeit expedited, \nstakeholder process conducted within the timelines established by the Show Cause Order.  MISO \nadvanced solutions that incorporated substantial stakeholder feedback while remaining consistent \nwith MISO’s filing rights and jurisdictional responsibilities.  MISO worked closely with its \nTransmission Owners to develop this joint filing and appropriately recognize their respective roles, \nrights, and responsibilities.  MISO also engaged the Organization of MISO states through regular \ndiscussions throughout the development of this package of filings.  \n \nWhile full alignment was not achieved on every aspect of the proposals, stakeholder and \nstate regulator input materially informed the resulting framework.  MISO is confident that the \ncollective set of filings before the Commission provides state regulators with additional \ntransparency, information and tools to help fulfill their responsibilities to retail electricity \ncustomers, consistent with the objectives outlined in the Show Cause Order.  The solutions also \npreserve flexibility for states to advance their individual policy objectives, including the use of \ndetailed information and analyses provided through MISO’s planning and operational processes. \n \nThe proposals included in the filing provide a robust foundation for integrating Large \nLoads in a manner that supports reliability, protects Transmission Customers from cost shifts \nrelated to new Large Loads, and provides additional transmission service options consistent with \nthe Commission’s objectives for co-located loads, behind the meter generation arrangements and \nflexible Large Loads.  Specifically, this filing addresses the following elements identified in the \nShow Cause Order: \n \n \n11  MISO is contemporaneously submitting its Grid Responsive Integration Transmission Services (“GRITS”) \nproposal as a separate FPA Section 205 filing. The GRITS filing addresses the Show Cause Order requirement \nthat MISO evaluate the need for both firm and non-firm contract demand transmission service."},{"page":5,"startToken":1958,"endToken":2412,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 5 \n \n• Large Load Project Review (LLPR) – The LLPR establishes a comprehensive application \nand evaluation process to assess the grid impacts associated with Transmission Service \nneeded to serve proposed Large Loads, including required Network Upgrades and \nassociated costs.  The LLPR also includes deposits, project milestones, and other \nsafeguards designed to discourage speculative Large Load requests.  \n• Large Load Transparency Dashboard – The results of the LLPR periodically will be \npublished to provide transparency into the location and estimated costs associated with \nLarge Load facilities in the MISO region, while protecting confidential information. \n• Cost Shifting Risk Among Transmission Customers – MISO and the MISO Transmission \nOwners have developed new Tariff language and pro forma cost recovery agreements \ndesigned to ensure that the costs incurred to provide Transmission Service to Large Load \nTransmission Customers, including the costs of Large Load Upgrades (defined herein), are \nborn by such customers and thereby avoid unfair cost shifts among Transmission \nCustomers.  The agreements leave retail regulatory authorities able to further disaggregate \ncosts as warranted. \n• Additional Transmission Services – The new Transmission Services available to Large \nLoads include Firm Service Step Up and Interim Non-Firm NITS service.  These offerings  \nbuild off existing NITS service and support the timely integration of Large Loads by \naligning Transmission Service with a Transmission Customer’s projected buildout and \noperational needs, while providing flexibility in how Transmission Service is obtained \nduring different stages of development. \n \nMISO appreciates the guidance provided by the Commission in the Show Cause Order and \nbelieves this filing, together with the companion GRITS filing, and MISO’s other pending Large \nLoad filings fully addresses the concerns identified by the Commission.  Taken together, these \nproposals represent a significant advancement in framework supporting Large Load integration, \nbuilding on processes and tools that MISO has already implemented.   \n \nAt the same time, MISO recognizes that the rapid growth of Large Loads will continue to \npresent new challenges and opportunities.  As a result, these filings should be viewed as an \nimportant milestone rather than an endpoint. MISO remains committed to working collaboratively \nwith stakeholders, Transmission Owners, states and the Commission to evaluate and develop \nadditional tools, processes, and solutions to support the reliable, efficient, transparent and cost-\neffective integration and operation of Large Loads in the MISO region.  \n \nII. \nBACKGROUND  \n \nThis omnibus filing brings together the history and substance of MISO’s response to the \nCommission’s Show Cause Order.  MISO has pursued that response through a series of related \nfilings, submitting individual proposals as the necessary information, stakeholder consideration, \nand proposed Tariff provisions became sufficiently developed.  The earlier submissions addressed \ncomponents that were ready to proceed while work continued on other elements of the response.  \nThis filing explains that progression, describes the relationship among the proposals already"},{"page":6,"startToken":2412,"endToken":2890,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 6 \n \nsubmitted, and presents the additional provisions that have since been developed.  The background \nbelow traces how that coordinated effort led to the present submission. \n \nA. The changing nature of load growth in the MISO region. \n \nThe MISO region is experiencing a change in the scale, concentration, and pace of new \nelectricity demand.  Large Load additions, including data centers and advanced manufacturing \nfacilities, can introduce substantial demand at a single location and seek service on schedules that \nare shorter than those traditionally required to develop supporting generation and transmission \ninfrastructure.  These developments require MISO, the Transmission Owners, and the entities \nserving those Loads to coordinate planning, investment, and operational requirements early in the \ndevelopment process to address the unique needs associated with such Large Load additions to the \ngrid.  As MISO explained in its July 20, 2026, Informational Report, conventional forecasting \nmethods were developed for more gradual and geographically dispersed growth; Large Load \nprojects present additional uncertainty concerning location, timing, and the demand that ultimately \nmaterializes.12 \n \nThe resulting challenge extends beyond identifying a physical point of connection.  MISO \nmust assess the transmission facilities needed to serve new demand, understand how the Load will \nbehave during normal operations and system disturbances, and coordinate the addition of resources \nneeded to support resource adequacy.  At the same time, the uncertainty surrounding Large Load \ndevelopment makes it necessary to distinguish committed projects from speculative requests and \nto address the risk that investments made to serve a particular load may remain unrecovered if that \nLoad is delayed, reduced, or does not materialize.  MISO’s Large Load initiatives were developed \nto address these related planning, reliability, and cost recovery concerns.13 \n \nMISO has also recognized that certain Large Loads may be willing and able to limit their \nwithdrawals from the Transmission System.  That flexibility can support service before all \nfacilities needed for full firm service have been completed, or an ongoing arrangement under which \nonly a portion of the Load receives firm service.  Accommodating those different needs requires \nclear service rights, enforceable operating limits, and appropriate treatment of the customer’s \nplanning and financial obligations.  The development of additional Transmission Service options \ntherefore became a component of MISO’s broader Large Load work. \n \nB. MISO’s existing processes and the development of a dedicated stakeholder forum. \n \nMISO’s efforts to address these challenges began before the Commission issued its Show \nCause Order.  MISO had improved the Expedited Project Review (“EPR”) process within the \n \n12  MISO, Informational Report, Docket No. EL26-70-000, at 1-2 (July 20, 2026) (“Informational Report”); MISO, \nTransmittal Letter, Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650-000, at 2-\n3 (Aug. 28, 2026) (“IRR Transmittal”). \n13  Informational Report at 1-3; Motion of MISO to Hold Proceeding in Abeyance and Request for Shortened \nComment Period and Expedited Treatment, Docket No. EL26-70-000, at 2-5, 8-9 (Aug. 3, 2026) (“Abeyance \nMotion”)."},{"page":7,"startToken":2890,"endToken":3339,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 7 \n \nMISO Transmission Expansion Plan (“MTEP”) to facilitate timely study and approval of \ntransmission upgrades needed for large load additions.14  On the generation side, MISO developed \nthe temporary Expedited Resource Addition Study (“ERAS”) process to accelerate the \ninterconnection of resources addressing identified near-term resource adequacy and reliability \nneeds.15  These initiatives provided a foundation for additional tools tailored to the pace and \ncharacteristics of large load development.16  Those expedited processes addressed important near-\nterm needs, but MISO recognized that additional provisions were necessary to address the broader \nrelationship among load additions, generation development, transmission service, and system \noperations.   \n \nMISO also began consolidating stakeholder consideration of large load issues.  Following \na January 2026 Large Load Additions Workshop, MISO’s Steering Committee approved creation \nof the Large Load Working Group (“LLWG”) in March 2026.  The LLWG held its first meeting \non April 20, 2026, providing a dedicated forum for issues spanning markets, reliable operations, \nplanning, and resource adequacy.  Its early work included Interconnection Reliability \nRequirements, Firm Service Step Up arrangements, and the Zero-Injection Generation \nInterconnection proposal.  This work brought previously related but separately considered issues \ninto a coordinated large load work plan.17 \n \nC. The Show Cause Order and the opportunity to develop regional solutions. \n \nOn June 18, 2026, the Commission instituted a proceeding under section 206 of the Federal \nPower Act (“FPA”) to examine whether MISO’s Tariff remained just and reasonable in light of \nvarious concerns related to large and co-located load development.  The Commission identified \nconcerns regarding application and study procedures, operational requirements, network upgrade \ncost transparency and recovery, service for flexible and co-located loads, and generation serving \nassociated Loads.  It directed MISO and the Transmission Owners to respond to its preliminary \nfindings and address potential Tariff changes.18 \n \nThe Commission’s action reinforced work already underway while identifying additional \nmatters for stakeholder consideration.  The Show Cause Order also contemplated development of \nregional solutions through FPA section 205 filings and allowed requests for an abeyance of up to \n \n14  Furnish Testimony at 17-18.  \n15  MISO, Transmittal Letter, Expedited Resource Addition Study, Docket No. ER25-2454-000 (June 6, 2025) \n(“ERAS Transmittal”).  \n16  Abeyance Motion at 3-4; Informational Report at 6-7; MISO, Transmittal Letter, Zero Injection Generator \nInterconnection Agreement, Docket No. ER26-3552-000, at 4-6 (Aug.  18, 2026) (“ZGIA Transmittal”). \n17  Abeyance Motion at 3-4 & n.6; MISO, Transmittal Letter, Large Load Addition Resource Study, Docket No. \nER27-25-000, at 49-50 & nn.102-108 (Oct.  2, 2026) (“LARS Transmittal”). \n18  Midcontinent Indep.  Sys.  Operator, Inc., 195 FERC ¶ 61,212, PP 1-3, 33-39 (2026), errata notice, 196 FERC ¶ \n61,123 (2026) (“Show Cause Order”); Midcontinent Indep.  Sys.  Operator, Inc., 196 FERC ¶ 61,133, P 1 (2026) \n(“Abeyance Order”)."},{"page":8,"startToken":3339,"endToken":3809,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 8 \n \n90 days for that purpose.  MISO pursued that opportunity to coordinate the existing initiatives with \nadditional proposals responsive to the Commission’s concerns.19 \n \nOn July 20, 2026, MISO submitted the Informational Report addressing resource adequacy \nand initiatives to accelerate the addition of generation to serve emerging demand.  The Report \nexplained the respective roles of states, load serving entities, and MISO in supporting resource \nadequacy and described both existing reforms and additional proposals under development.  It \nidentified a zero injection interconnection process and a parallel study framework for associated \nload and generation as complementary approaches to facilitating timely service while accounting \nfor system needs.20 \n \nOn August 3, 2026, MISO requested that the proceeding be held in abeyance for 90 days.  \nThe Abeyance Motion described a series of anticipated section 205 filings covering Zero-Injection \nInterconnection Service, a Large Load definition and Interconnection Reliability Requirements, \ncoordinated Load and generation studies, Firm Service Step Up arrangements, and additional \nservice options for flexible Loads.  It also identified further work on application and study \nprocedures and Upgrades cost transparency.  MISO explained that the proposals needed to operate \ntogether and fit within MISO’s existing planning, interconnection, and service processes.21 \n \nThe Commission granted the requested abeyance on August 14, 2026.  It found that the \ndescribed stakeholder process would provide an opportunity to consider region-specific solutions \nand held the proceeding, including the responses and briefing questions, in abeyance for 90 days.22  \nThe Commission established November 16, 2026 as the revised response deadline and explained \nthat a timely FPA section 205 filing addressing its preliminary findings would suspend the filing \nrespondents’ obligation to respond and continue the abeyance pending further Commission \ndirection.  The Commission further explained that any issues not addressed by the FPA section \n205 filings would remain subject to the FPA section 206 proceeding instituted under the Show \nCause Order and encouraged respondents seeking termination to identify specifically which \nproposed revisions resolved which concerns.23 \n \nD. The earlier filings and the matters reserved for further development. \n \nDuring the abeyance period, MISO submitted proposals addressing those elements of its \nresponse that were sufficiently developed for Commission review.  Those submissions did not \npurport to resolve every issue in a single filing.  Instead, they advanced particular components \nwhile expressly identifying related matters for further development and subsequent submission.  \nThe resulting sequence provides important context for this omnibus filing: the present submission \n \n19  Show Cause Order P 37; Abeyance Motion at 4-5, 7-9; Abeyance Order PP 3-5. \n20  Informational Report at 1-4, 10-11.  The Report responded to the informational reporting requirement in Show \nCause Order P 122. \n21  Abeyance Motion at 3-5, 8-13. \n22  Abeyance Order at PP 8-9.  \n23  Id. at PP 8-11.  The Order established December 16, 2026, as the deadline for answers to responses.  Id.  P 9."},{"page":9,"startToken":3809,"endToken":4317,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 9 \n \nboth accounts for the proposals already filed and advances additional portions of the response that \nwere not ready for submission at those earlier stages.24 \n \nFirst, on August 18, 2026, MISO submitted its Zero Injection Generator Interconnection \nAgreement (“ZGIA”) proposal in Docket No. ER26-3552-000.  The filing proposed a form of \nGenerator Interconnection Agreement, a study process, and an agreement for generation serving \nLoad at the same substation without broader injections onto the Transmission System.  MISO had \nbegun developing the concept before the Show Cause Order and refined it through stakeholder \ndiscussion.  MISO limited the initial proposal to same-substation arrangements so that the zero \ninjection option could proceed while the separate questions presented by generation serving \nelectrically proximate Load were addressed through further work.25  The ZGIA proposal was \ndeliberately limited in scope.  This distinction is relevant to the present filing because a generator \ninterconnection pathway alone does not supply the complete Transmission Service and cost \nrecovery framework for the Load it serves.26 \n \nSecond, on August 28, 2026, MISO submitted its Interconnection Reliability Requirements \n(“IRR”) for Large Loads proposal in Docket No. ER26-3650-000.  That proposal included a Tariff \ndefinition of Large Load and requirements addressing data, models, telemetry, forecasting, and \noperational visibility, together with phasor measurement, ramp, and ride-through requirements for \nComputational Loads.  MISO proposed to place the applicable obligations on the Transmission \nCustomer taking service on behalf of the Large Load, reflecting that customer’s direct relationship \nwith MISO.  The proposal was intended to improve MISO’s ability to assess, observe, and manage \nLarge Load behavior.27  The IRR filing also distinguished requirements applicable to the \nTransmission Customer taking Transmission Service on behalf of the Large Load from the study \nprocedures used to identify system-level impacts and necessary transmission solutions.  MISO \nexplained that it already performed stability assessments through MTEP and EPR but would \naddress enhancements to the broader Load addition and Transmission Service study processes in \na later FPA section 205 filing.  The IRR proposal thus supplied the proposed operational \nrequirements to be incorporated into, and assessed through, the developing study framework.28 \n \nThird, on October 2, 2026, MISO submitted its Large Load Addition Resource Study \n(“LARS”) proposal in Docket No. ER27-25-000.  LARS proposed a coordinated process for \nstudying qualifying Load additions of at least 200 MW and associated new generation.  The \nproposal built upon experience with expedited load-side planning and coordinated the Load and \ngeneration studies through a common application framework.  It complemented ZGIA by \n \n24  ZGIA Transmittal at 1-2, 5-7; IRR Transmittal at 1, 4; LARS Transmittal at 3-4, 15, 20-21. \n25  ZGIA Transmittal at 1-2, 6-7.  MISO requested an October 18, 2026, effective date.  Id.  at 2.  This paragraph \ndescribes the submitted proposal; it does not state that the Commission accepted the proposal or its requested \neffective date. \n26  ZGIA Transmittal at 2, 7; LARS Transmittal at 3-4. \n27  IRR Transmittal at 1-4.  MISO requested a December 4, 2026 effective date.  Id.  at 2.  This paragraph describes \nthe proposal as submitted. \n28  IRR Transmittal at 4."},{"page":10,"startToken":4317,"endToken":4794,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 10 \n \naddressing qualifying Load and generation arrangements beyond the narrower same-substation, \nzero injection configuration.29  LARS also reflected the iterative nature of the stakeholder process.  \nMISO introduced the coordinated study concept at the July 16, 2026 LLWG meeting and sought \nfeedback on eligibility, readiness, and protections against speculative requests.  The proposal \nevolved from an initial 250 MW eligibility concept to the 200 MW threshold submitted to the \nCommission.  MISO’s LARS transmittal further anticipated a subsequent filing addressing the \nLoad study process, Transmission Service, and cost recovery provisions needed to complete other \nelements of the Large Load framework.30 \n \nE. The additional provisions now presented in this omnibus filing. \n \nWhile the ZGIA, IRR, and LARS proposals proceeded through separate filings, MISO \ncontinued developing the remaining application, study, service, and financial provisions.  Those \nmatters required additional information and coordination concerning how customers would request \nservice, how the necessary upgrades would be identified, what obligations would support the \nresulting investment, and what service could be provided under differing operating conditions.  \nThe present filing brings forward those additional proposals and explains how they relate to the \ncomponents previously submitted. The proposed LLPR process builds on the load-specific \nfunctions of EPR to establish a dedicated Tariff framework for a Transmission Customer taking \nservice on behalf of a Large Load to obtain Transmission Service. The LLPR includes standardized \napplications, recurring study cycles, identification of necessary Upgrades, and the integration of \nthe proposed interconnection reliability requirements.31  While only Transmission Owners were \neligible to submit requests to the EPR process, MISO is proposing that only Large Load \nTransmission Customers (in collaboration with the Transmission Owner) may submit an \napplication to the LLPR process.  \n \nThe cost recovery and transparency provisions ensure the Large Load Transmission \nCustomer pays the cost of the Large Load Upgrades required to provide Transmission Service, \nincluding if the expected Load does not arrive as anticipated or remain in service.  The proposed \ncost recovery agreements, related security, and cost transparency measures are intended to connect \nthe requested Transmission Service and necessary supporting investment with enforceable \nfinancial obligations.  The proposed framework includes Tariff revisions and a pro forma Large \nLoad Cost Recovery Agreement, and a pro forma Large Load Impacted Transmission Owner Cost \nRecovery Agreement, together with a publicly accessible dashboard providing high-level \ninformation about upgrades and estimated costs while protecting confidential information.32 \n \n \n29  LARS Transmittal at 1-6; see also Combined Notice of Filings No. 1, 91 Fed.  Reg.  64,362 (Oct.  8, 2026) (Docket \nNo. ER27-25-000; Oct.  2, 2026 filing; requested Dec.  2, 2026 effective date). \n30  LARS Transmittal at 3-4, 15, 20-21, 49-52. \n31  Furnish Testimony at 3; see Section D.1.c.ii-iii. \n32  Furnish Testimony at 21-23; Abeyance Motion at 12-13.  Detailed recovery, security, and accounting provisions \nremain subject to confirmation against the final pro forma agreements and supporting testimony."},{"page":11,"startToken":4794,"endToken":5274,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 11 \n \nThe service proposals address the separate question of how a customer may use the \nTransmission System once the relevant studies and prerequisites have been satisfied.  The \nproposed Interim Network Integration Transmission Service (“Interim NITS”) provides a non-firm \nTransmission Service option for participation of a Load progressing toward full firm Network \nIntegration Transmission Service (“NITS”) prior to the completion of required Upgrades.  The \nproposal also includes an optional Firm Service Step Up for loads progressing toward full firm \nservice.  These alternatives are intended to recognize different operating capabilities and \ndevelopment schedules while specifying the associated withdrawal limits, curtailment conditions, \nand customer obligations. \n \nAccordingly, this omnibus filing should be considered in the context of the full sequence \nof MISO’s submissions in response to the Show Cause Order.  The earlier filings addressed \ncomponents that could be brought forward first; the proposals submitted here reflect the further \ndevelopment of the application, study, cost recovery, transparency, and service provisions \ndescribed above.  Together, that history explains both the timing and the scope of the present filing.  \nThe sections that follow identify the relief sought, describe the additional Tariff revisions proposed \nhere, and explain how this submission and the previously filed proposals comprehensively address \nthe Commission’s concerns identified in the Show Cause Order. \n \nIII. \nLARGE LOAD APPLICATION AND STUDY PROCESS \n \nIn the Show Cause Order, the Commission directed MISO develop an “application process, \nstudy procedures, and ongoing operational requirements that apply to Eligible Customers seeking \ntransmission service on behalf of large loads.”33  The Commission recognized that MISO and the \nMISO Transmission Owners may have existing Load integration processes that included studies \nfor Transmission Service to Large Loads but sought documentation of clear and consistent \nprocedures in MISO’s Tariff that address the characteristics and challenges associated with \ninterconnecting Large Loads in order to avoid disputes about how studies will be conducted, deter \nspeculative or duplicative requests for Transmission Service to serve Large Loads, and help avoid \nexcessive and unnecessary Upgrades.34 MISO has worked with the Transmission Owners, \ndevelopers of Large Loads, and other stakeholders to develop the Large Load Project Review \n(“LLPR”) process proposed herein.  LLPR provides a clear and consistent study process that will \nbe required for evaluating all requests for Transmission Service to serve Large Loads.35  The LLPR \nprocess addresses the goals of the Show Cause Order by providing a clear and consistent study \nprocess that is tailored to the needs and challenges associated with Large Load integrations and \nwhich provides the necessary framework for implementing the other Large Load reforms sought \nby the Show Cause Order.36  The LLPR is also a uniform process that provides increased speed \nand certainty to Large Load Transmission Customers in identifying the Network Upgrades needed \n \n33  Show Cause Order at P 3.  \n34  Id. at PP 49, 55-57. \n35  Furnish Testimony at 3-4.  \n36  Id. at 20-21."},{"page":12,"startToken":5274,"endToken":5734,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 12 \n \nto provide Transmission Service to Large Load Transmission Customers.37  LLPR also promotes \naccountability, deters speculative or duplicative requests for Large Load-driven requests for \nTransmission Service, and provides transparency regarding the Large Load-driven Network \nUpgrades and their associated costs.  \n \nIn response to concerns raised by the Commission, MISO and the MISO Transmission Owners \npropose Tariff revisions and two pro forma cost recovery agreements that together require the \nTransmission Customer seeking to take Transmission Service on behalf of a Large Load (“Large \nLoad Transmission Customer”) to make a minimum financial contribution toward the revenue \nrequirement of the Transmission Owners responsible for constructing the Upgrades identified by \nMISO in the LLPR, including financial security sufficient to secure such contribution.38  These \nproposed Tariff changes and agreements, which are a condition precedent to MTEP approval, \nimpose cost responsibility and accountability on Large Load Transmission Customers consistent \nwith the Commission’s direction in the Show Cause Order and provide transparent identification \nof the Network Upgrades made necessary by Large Loads, including their estimated costs.39  LLPR \nis an expedited process designed to be completed in approximately five months.  To simplify the \nexplanation of the LLPR process, MISO describes the key definitions, the Large Load Application, \nand the required steps in the LLPR study process in the sections below.  \n \nA. New Definitions for the LLPR Process \n \nMISO includes several new definitions in Attachment FF to its Tariff, which are needed to \nprovide a working vocabulary for implementing the LLPR process.40  These terms are summarized \nbelow: \n \n• Large Load Network Upgrades are the additions, modifications, and upgrades to \nbe made to the Transmission System that are located inside the Transmission \nPricing Zone containing the POW for the Large Load that are necessary for MISO \nand the Transmission Owner to operate and maintain the Transmission System in a \nsafe and reliable manner.  \n• Impacted Transmission Owner Large Load Network Upgrades are the \nadditions, modifications, and upgrades to be made to the Transmission System that \nare located outside the Transmission Pricing Zone containing the POW for the \nLarge Load that are necessary for MISO and the Transmission Owner to operate \nand maintain the Transmission System in a safe and reliable manner. \n \n37  MISO is proposing to add a new definition to Module A to define Large Load Transmission Customer as the \nTransmission Customer that is taking Transmission Service on behalf of a Large Load.  \n38  See Tab E Testimony and Exhibits of Greg M. Gudeman (“Gudeman Testimony) (describing the pro forma cost \nrecovery agreements). \n39  Furnish Testimony at 5.  \n40  In the transmittal letter, MISO paraphrases the LLPR process definitions, but the full definitions of each of these \nterms may be found in Section D.1.c.i of Attachment FF."},{"page":13,"startToken":5734,"endToken":6233,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 13 \n \n• The Large Load Cost Recover Agreement (“LL-CRA”) is the primary \nagreement that establishes the Large Load Transmission Customer’s cost \nresponsibility for Large Load Network Upgrade(s), which are located in the \nTransmission Pricing Zone containing the POW for the Large Load. \n• The Large Load Impacted Transmission Owner Cost Recovery Agreement \n(“LLITO-CRA”) is the agreement that establishes the Large Load Transmission \nCustomer’s cost responsibility for the Impacted Transmission Owner Large Load \nNetwork Upgrades, which are located outside of the Transmission Pricing Zone \ncontaining the POW for the Large Load.   \n \nThe two different kinds of upgrades are distinguished by whether they are located inside \nthe Transmission Pricing Zone (“TPZ”) or outside of the TPZ containing the POW for the Large \nLoad.41  Similarly, the LL-CRA and LLITO-CRA establish cost recovery terms based on the \nlocation of the Upgrades, inside or outside the TPZ.  As discussed in more detail later, this \nagreement framework is necessary for costs to be properly assigned throughout MISO’s \nTransmission System.   \n \nTogether, these terms enable the creation of processes and requirements that recognize the location \non the Transmission System of Large Load Upgrades identified through the LLPR process, \nidentify their connection to Large Loads, and establish the applicable parties to the proposed \nagreements under MISO’s Tariff.42 \n \nB. Applicability and Participant Responsibilities. \n \nMISO’s existing study processes require supplementation and enhancement in order to \nefficiently and effectively address the growth in Large Load development over the past couple of \nyears.  LLPR builds from and adapts MISO’s existing Expedited Project Review (“EPR”) process \nand will be the required core study process for all requests for Transmission Service made on \nbehalf of or in order to serve Large Loads.  Specifically, the LLPR process will apply to all requests \nfor Transmission Service for Large Loads, as defined in MISO’s Interconnection Reliability \nRequirements (“IRR”) filing, including the load components of LARS which is an aligned \ntransmission and interconnections service requests for very large loads (200 MW or greater) paired \nwith the generation that will serve it.43   \n \n41  To facilitate efficient explanation, MISO uses the term “Large Load Upgrades” to embrace both “Large Load \nNetwork Upgrades” and “Impacted Transmission Owner Large Load Network Upgrades,” reserving use of the \nspecific defined term for where context requires it.  \n42  MISO notes that nothing in LLPR interferes with the ability of states and other retail regulators to impose \nadditional conditions, further allocate cost responsibility and risk among and between retail customers and Load \nServing Entities, or require further agreements involving parties not directly taking service under MISO’s Tariff \n(e.g., data centers and other owners of Large Loads). \n43  MISO’s LARS proposal, currently pending in Commission Docket ER27-25-000, provides a specialized process \ndesigned to study very large (≥200 MW) Large Loads accompanied by the generation that will serve it on a \ncoordinated timeline.  MISO has committed to updating the load study portion of LARS to Incorporate the LLPR \nprocess and requirements proposed herein once these are accepted."},{"page":14,"startToken":6233,"endToken":6780,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 14 \n \n \nMISO envisions different parties playing diverse roles in the LLPR process.  First, the \nLarge Load Transmission Customer, commonly the LSE, plays a key role in the LLPR process as \nit is the party that can request Transmission Service through LLPR from MISO.  The Transmission \nOwner has an integral role in working with the parties on studies.  The entity that owns the Large \nLoad, while usually not directly subject to MISO’s Tariff, will play an essential role in providing \nthe information needed to support the LLPR Application and working with the Transmission \nCustomer to determine the type of Transmission Service to request.44  Finally, MISO, as the \nTransmission Provider, acts as coordinator, performing the required LLPR studies, administering \nthe LLPR process and, ultimately, approving transmission projects and granting Transmission \nService.   \n \nTransmission Customers seeking to participate in LLPR must submit a Large Load \nApplication to MISO as well as a non-refundable application fee of $250,000.45  Due to the role \nof the Transmission Customer in obtaining Transmission Service for Loads, the Show Cause \nOrder’s direction that the Transmission Customer seeking Transmission Service to serve a Large \nLoad bear responsibility for requesting the Transmission Service and executing cost recovery \nagreements. The Large Load Transmission Customer is the only party that may request \nTransmission Service on behalf of a Large Load from MISO and thus, is the only party that may \nsubmit a Large Load Application.46  MISO’s current processes similarly limit the types of entities \nthat can submit EPR Requests.47  MISO’s current EPR process similarly only allows Transmission \nOwners to submit EPR requests.  The Transmission Customer must select from a list of \nTransmission Service options which service it is applying for and must identify the amount of \nrequested firm or non-firm service options.48  LLPR is designed to facilitate several different types \nof requests for Transmission Service, including Network Resource Integration Service (“NITS”), \nFirm Service Step Up (“FSSU”), Interim (“Interim NITS”), and Transmission Service requested \nthrough LARS.49 Notably, the requested Transmission Service option and the identified MW \namount may not be changed after the Large Load Application is submitted to MISO.50  This, \ntogether with the required application, discourages speculative or unready Large Load \n \n44  A Large Load may assume other responsibilities or obligations pursuant to agreements with the Transmission \nCustomer or in accordance with rules and regulations adopted by states commissions or other retail regulators. \nMISO’s LLPR does not prohibit this.  \n45  Furnish Testimony at 5.  \n46  Id.  \n47  Under current processes, only a Transmission Owner may submit an EPR request into MTEP because they are \nthe entity that identifies the urgent need on their facilities.  Thus, LLPR does not introduce any new restriction \nagainst other types of entities submitting requests for Transmission Service (e.g., Generator Interconnection \nCustomers, Market Participants).  Rather, LLPR simply shifts this role from the Transmission Owner to the Large \nLoad Transmission Customer to facilitate the accountability goals of the Show Cause Order. \n48  Id. at 5-6.  \n49  Id. \n50  Id. at 5. Large Loads may be completed in phases, but the total expected MW load amount must be identified in \nthe Large Load Application at time of submission.  Any additional load amounts must be submitted as a new \nrequest for Transmission Service."},{"page":15,"startToken":6780,"endToken":7306,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 15 \n \nApplications and provides the needed certainty about what is being studied that is necessary to \nperform an accelerated study without creating undue restudy risk.  \n \nThe specific Transmission Service requested, the size of the Load, and whether the Large \nLoad has partnered with generation will determine the next steps for the applicant and the load.  \nFor example, if the applicants are looking to co-locate the Load with the generation, then they will \nneed to ensure that an appropriate Interconnection Agreement e.g. “ZGIA” has already been \nexecuted for the generator.51  If the Large Load is greater than or equal to 200 MW and has formally \npartnered with a generator for a minimum of fifteen years, then the applicants will go through the \nLARS study process.52  Other Transmission Services or processes such as FSSU and Interim NITS \ncan be selected at the start of LLPR or after the LLPR study process is completed.  Any Large \nLoad going through the LLPR process will be subject to the Interconnection Reliability \nRequirements proposed by MISO in Docket No. ER26-3650-000.53  \n \nMISO will complete the LLPR study process three times in each 365-day period based on \nany Large Load Applications received by the deadline.54  MISO will post the application deadline \non its website at least 90 calendar days prior to each deadline.55  The Large Load Transmission \nCustomers may submit Large Load Applications at any time and MISO will maintain a list of all \nApplications leading up to each study process.56  Any applications that are submitted after the \ndeadline will be automatically included in the next LLPR study cycle.57  In order for MISO to \ncomplete these studies in an expedient manner, the applicants must abide by these deadlines and \nadditional review periods, which will be addressed in the next sections.  \n \nC. LLPR Study Cadence, Timing, and Application Requirements—Attachment FF \nSections I.D.1.c.iii.a—I.D.1.c.iii.c. \n \nMISO is proposing to complete the LLPR study process three times in a 365-day period.58  The \ntiming of this process is reasonable and dictated by how long it is expected for MISO and the other \nparticipants in an LLPR process to complete the required steps.  This study cadence is necessary \nand appropriate in order to allow the base case of each LLPR study cycle to incorporate the \n \n51  See generally, ZGIA Filing, Docket No. ER26-3552. \n52  See LARS Filing, Docket No. ER27-25-000.  \n53  See IRR Filing, Docket No. ER26-3650-000. \n54  Furnish Testimony at 10.  \n55  Id. As explained in testimony, the first Large Load Application deadline will be on March 1, 2027, and due to the \ntiming of this filing, MISO will not be able to provide 90-day notice for the first LLPR study cycle.  \n56  Furnish Testimony at 4, 10.  \n57  Id. at 10.  \n58  MISO considers each LLPR study cycle to commence on the date of the Large Load Application deadline and \nends once the project receives MTEP approval, which takes place once the stakeholder process has been \ncompleted and the cost recovery agreements are executed or filed unexecuted with the Commission."},{"page":16,"startToken":7306,"endToken":7819,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 16 \n \nTransmission System changes from the prior LLPR Study cycle.59  To avoid unnecessary restudy \nrisks, it is appropriate to begin each study cycle after the prior one is completed and the applicable \ncost recovery agreements have been executed or submitted to the Commission for acceptance.   \n \nWhile the Large Load Application may only be submitted by the Transmission Customer, \nother parties including the Transmission Owner and the Large Load customer must all provide \nrequired information as part of the application.  The LLPR Applicant must submit the non-\nrefundable application fee of $250,000 and any relevant study deposits at the time of application \nsubmission.60  The parties must also submit a significant amount of information with the \nApplication to ensure that they have completed any necessary pre-planning steps and have reached \nagreement on key portions of the project including the identification of any necessary Large Load \nUpgrades by the Transmission Owner(s).61  \n \nThe required technical information for a completed LLPR Application is set forth in \nproposed Section I.D.1.c.iii.b of Attachment FF.  This information includes the geographic \nlocation and Point of Withdrawal (“POW”) for the Large Load, the MW amount of the Large Load, \nthe type of Transmission Service requested, data regarding the characteristics of the Large Load \nand equipment in order to enable MISO to assess how it will operate, the MTEP and model on \ndemand information for associated load and transmission upgrades, the requested In-Service Date, \nand any requisite contact information.62  \n \nProposed Section I.D.1.c.iii.b.2 requires study files to include various items.  Specifically, \nsuch files should include models, one line diagrams, the Transmission Owner’s Interconnection \nStudy Report, including consideration of Alternative Transmission Technologies (“ATTs”)/Grid-\nEnhancing Technologies (“GETs”), and information about any Large Load Upgrades identified by \nthe applicable Transmission Owner, with specific requirements to provide an estimate of the total \ncosts of the required Large Load Upgrades, the costs that the Large Load Transmission Customer \nwill be obligated to pay, and, if this is less than 100% of the capital costs of the Large Load \nUpgrade, a narrative explaining how their portion of the costs was determined.  This information \nwill enable MISO to verify any analyses performed by the Transmission Owner and provide the \ncost transparency sought by the Show Cause Order.  The Large Load Application is designed to \nbe flexible so that it can be used to initiate the study process for several different types of \nTransmission Service and integrate with other MISO processes.63 \n \n \nProposed Section I.D.1.c.iii.b.3 requires an attestation by the Transmission Customer \nattesting that it acknowledges MISO’s ability to review reliability impacts and additional \n \n59  Furnish Testimony at 12.  \n60  Id. at 5.  \n61  See id. at 6-8.  \n62  See id.  \n63  LARS, for example, will require an Interconnection Request for a Generating Facility and additional information \nabout the commercial relationship and electrical connection between the Interconnection Customer/Generating \nFacility and the LARS Associated Transmission Customer and LARS Associated Large Load."},{"page":17,"startToken":7819,"endToken":8365,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 17 \n \nmitigations through applicable study processes, that the Transmission Customer will comply with \nTariff terms and requirements applicable to Large Loads that are set forth in Module B of the \nTariff, that the Transmission Customer has a commercial agreement with the Large Load providing \nfor it to request Transmission Service in order to serve that Large Load, and that the Transmission \nCustomer does not have other requests pending with MISO for duplicative Transmission Service.  \nThese latter two requirements provide safeguards against unnecessary, speculative, or duplicative \nrequests for Transmission Service by demonstrating that the Transmission Customer submitting \nthe LLPR Application is the correct Transmission Customer that will serve the Large Load and \nthat there are not multiple requests for the same Transmission Service being submitted as \nspeculative alternatives on different parts of the MISO Transmission System.64  If the Large Load \nwas proposed in multiple places then that would artificially inflate the total cost of Large Load \nNetwork Upgrades, jeopardize the finality and commercial certainty of LLPR studies, and create \nrestudy or cost shift risks for other Transmission Customer or participants in other MISO \nprocesses.65 \n \nMISO also proposes to require submission of valid models for electromagnetic transient \n(“EMT”) studies.66  The EMT work must be completed in the pre-application phase in order to \ncapture the complete list of Upgrades and to ensure that the Large Load Transmission Customer \nhas taken into consideration the necessary mitigation to meet the Interconnection Reliability \nRequirements.67  Finally, applicants must submit the LLPR System Impact Study Agreement and \nsign any relevant non-disclosure agreements required by MISO in order to ensure funding for the \nLLPR study and appropriately provide for the handling of confidential information.68  The LLPR \nSystem Impact Study Agreement is based on and largely follows the interconnection study \nagreement required for Generation Interconnection Customers with adjustments to reflect the \ndifferent types of studies that may be performed under LLPR.69  The required CEII NDA to be \nincluded as Attachment FF-10 to the Tariff is substantively identical to the pro forma CEII NDA \nrequired of Generator Interconnection Customers with their Interconnection Requests,70 and the \nrequired Confidential Information NDA is MISO’s pro forma Universal Nondisclosure \nAgreement, which is set forth in Attachment Z to the MISO Tariff.71  \n \n64  Furnish Testimony at 9.  \n65  Id. at 9; MISO has carefully worded the language of Attachment FF Section I.D.1.c.iii.b.3 so as not to prevent the \nsubmission of applications for incremental transmission service needed in addition to that requested in a previous \napplication. This is appropriate because such requests are not speculative alternatives. \n66  MISO is requiring all Large Load Applications to include EMT models, but EMT studies will only be required \nfor specific Large Load projects based on information MISO will provide and the level of detail will be described \nin the BPM.  \n67  Furnish Testimony at 8-9.  \n68  Id. at 26-27.  \n69  See, Attachment X, Appendix 1, Attachment B \n70  See, Attachment X, Attachment C to Appendix 1: Universal Non-Disclosure and Confidentiality Agreement. \n71  The LLPR System Impact Study Agreement is provided in the form of Attachment FF-10 to Attachment FF.  The \nconfidentiality agreements may include MISO’s Universal Non-Disclosure Agreement or non-disclosure \nagreements related to CEII."},{"page":18,"startToken":8365,"endToken":8851,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 18 \n \n \n \nLLPR Applicants are required to submit a $250,000 non-refundable application fee and a \n$100,000 study deposit upon application submission.72  The $250,000 both provides funding for \nLLPR administration and studies while also acting as a deterrent to speculative or uncertain Large \nLoad Applications.73  The $100,000 study deposit provides needed funding for the LLPR System \nImpact Study and any related studies that may be required, such as an FSSU or Interim NITS study.  \nIn the event that a Large Load Transmission Customer chooses to have MISO complete its EMT \nstudy, then an additional $100,000 study deposit must be provided.74  \n \nThe objective of including all these requirements at time of application is to ensure that the \nUpgrades that are needed to reliably serve the Large Load are identified at the outset.75  It is also \ncritical that the parties collaborate prior to submitting the Large Load Application to MISO so that \nMISO may complete the LLPR study process on its accelerated timeline.76  The streamlined \ndeficiency cure period for applicants is another piece of the LLPR proposal.  MISO will review \neach Large Load Application and notify the applicants of any identified deficiencies within fifteen \n(15) business days of receipt. After receiving that deficiency notification from MISO, the \nTransmission Customer will have ten (10) business days to cure the identified deficiencies.77  The \nTransmission Customer will also have five (5) business days to address any errors that may be \nidentified later in the LLPR study process.78  If the Transmission Customer is unable to cure the \ndeficiencies in any of the required timelines, then the Large Load Application will be deemed \nwithdrawn from the LLPR process.79  While the non-refundable application fee will be lost, the \nparties may submit the project in a future LLPR study cycle but must identify what information \nchanged from the previous application.80  There will be only one Application review period and \none cure period for each Large Load Application.81  This is necessary to ensure that the LLPR \nprocess remains streamlined and that MISO is able to complete these studies on an expedited \ntimeline.  MISO’s proposed Tariff language captures all requirements that will be included in the \nLLPR Application. MISO will develop a form of application that captures proposed Tariff \nrequirements, as may be adjusted by any compliance directives received from the Commission, \nand will post this form on MISO’s website prior to the application deadline for the first LLPR \nstudy cycle.  \n \n \n72  Furnish Testimony at 5.  \n73  This is in alignment with the Commission’s Show Cause Order and its concern with speculative transmission \nrequests on behalf of Large Loads. See Show Cause Order PP 68, 73, 80. \n74  Furnish Testimony at 8-9.  \n75  Id.  \n76  Id. at 5, 12.  \n77  Id. at 10-11.  \n78  Id.  \n79  Id.  \n80  Id. at 15-16.  \n81  Furnish Testimony at 10-11."},{"page":19,"startToken":8851,"endToken":9340,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 19 \n \nD. Model Building and Coordination with MTEP and Existing Processes—\nAttachment FF Section I.D.1.c.iii.d \n \nPursuant to proposed Section I.D.1.c.iii.d, MISO will commence developing models for all \nLLPR studies no later than five (5) business days after the conclusion of cure period.82  MISO will \nuse reasonable efforts to complete the model review process within thirty (30) Calendar Days after \nthe conclusion of the Large Load Application cure process.83  MISO will develop models for the \nLLPR studies in the applicable cycle based on the latest MTEP case and reflect all MTEP approvals \nthat have occurred as of the end of the cure period.84  This ensures that LLPR models are based on \nthe latest available information.  The process includes the circulation of draft models to the \napplicable Transmission Owners and Large Load Transmission Customers, subject to the required \nnondisclosure agreements, and provides a five (5) business day window for the applicable \nTransmission Owners and Large Load Transmission Customers to submit comments for MISO’s \nconsideration, after which MISO will finalize the models and circulate the final models to them.85  \nThe model build period ends when the Transmission Provider provides the final models to the \nappliable Transmission Owners and Transmission Customers.86  Taken together, this language \nestablishes a just and reasonable model review process for Large Loads that balances an \nopportunity for participation and comments with a schedule consistent with the expedited nature \nof the LLPR process so as not to disturb or delay subsequent MISO processes that build from the \ncompleted LLPR Study Cycle.  \n \nE. The LLPR System Impact Study—Attachment FF Section I.D.1.c.iii.e. \n \nProposed Sections I.D.1.c.iii.e and I.D.1c.iii.f establish both a LLPR System Impact Study \nprocess by describing the substantive analyses that will be performed as part of LLPR and details \nthe tender and processing of the Final LLPR Study Report. First, proposed Section I.D.1.c.iii.e \nprovides that MISO will commence the LLPR System Impact Study within two business days after \nconclusion of the model review period and explains that the LLPR study will consist of an analysis \nof the impacts of the Large Load on MISO’s Transmission System containing those elements \ndescribed in Attachment FF-10.  The proposed language further provides that the analysis will be \nbased on any applicable planning criteria.87  This language necessarily balances specificity about \nwhat is being studied with sufficient flexibility to accommodate rules currently being developed \nby NERC, Regional Entities, Transmission Owners, and regulators.  While completing the LLPR \nSystem Impact Study, MISO may consider alternative solutions including those suggested by \nstakeholders and the MTEP aggregate system analyses against applicable planning criteria.88  \n \n82  Id. at 13.  \n83  Id.  \n84  Id. at 12-13. \n85  Id. at 13. \n86  Id.   \n87  Furnish Testimony at 13-14.  \n88  Id."},{"page":20,"startToken":9340,"endToken":9752,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 20 \n \nMISO will post all the Large Load Applications that will be included in the upcoming LLPR \nSystem Impact Study to its MTEP webpage on its public website, thus facilitating the transparency \nrequirements identified in the Show Cause Order.89  \n \nIn the event that any Transmission Issues are identified in the LLPR System Impact Study, \nMISO will send the initial Transmission Issues to the applicable Transmission Owner and \ncollaborate with them on the development of possible solutions.90  This will include considering \nATTs/ GETs and selecting the preferred solution to the identified Transmission Issues.91  At this \npoint in the LLPR study process, there are additional strict deadlines that must be followed.  The \nTransmission Owners will have fifteen business days to respond to the identified Transmission \nIssues with possible solutions and, within ten business days after receipt of the proposed solutions, \nMISO will review and test the mitigation.92  If MISO identifies more Transmission Issues, then it \nwill notify the Transmission Owner, who will then have an additional ten business days to develop \nnew possible solutions.93  MISO will then review and test the newly proposed mitigations within \nfive business days.94  If the Transmission Issues are not resolved in the required timeframe, then \nthe Large Load Application will be withdrawn, and the project will be removed from the LLPR \nstudy.95  \n \nOnce the LLPR analysis/mitigation portion of the study is concluded, MISO will provide \na draft LLPR Study Report to the Transmission Customer and each applicable Transmission \nOwner.  The Transmission Customer and Transmission Owner(s) will have five business days to \nreview and provide comments on the study report.96  After reconciling any comments, MISO will \nprovide the final LLPR Study Report and any applicable cost recovery agreements to the \nTransmission Customer and applicable Transmission Owner(s).97  MISO will not process any \nLarge Load Application for MTEP approval until all applicable cost recovery agreements are \nexecuted by all parties or an unexecuted or non-conforming filing is submitted to the \nCommission.98 This is necessary to prevent circumvention of cost recovery agreement obligations \nand is consistent with their place in the LPPR framework as a required pre-condition of MTEP \napproval and obtaining Transmission Service for Large Loads. \n \n \n89  Id.  \n90  Id.  \n91  Id. \n92  Id.; see also, Section I.D.1.c.iii.e-f.  \n93  Furnish Testimony at 14-15. \n94  Id. \n95  Id. \n96  Id. \n97  Id. \n98  See Id. at 15-16."},{"page":21,"startToken":9752,"endToken":10310,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 21 \n \nF. Tender and Processing of the Cost Recovery Agreements—Attachment FF \nSection I.D.1.c.iii.f.99 \n \nWhen MISO shares the final LLPR Study Report with the Large Load Transmission \nCustomer and any applicable Transmission Owners, MISO will also tender the Large Load Cost \nRecovery Agreement and/or the Large Load Impacted Transmission Owner Agreement(s). The \nLarge Load Transmission Customer and Transmission Owner(s) have fifteen business days to \nexecute the cost recovery agreements and return them to MISO, or request that the non-conforming \nor unexecuted cost recovery agreements be filed with the Commission.100  Failure to do so will \nresult in the Large Load Application being withdrawn and the project being removed from the \nLLPR process.101  The Large Load Upgrades associated with these projects will be considered \napproved for MTEP purposes either at the completion of the stakeholder review process, as of the \ndate that the last party executes a conforming cost recovery agreement, or as of the date of filing \nan unexecuted or non-conforming cost recovery agreement with the Commission, whichever is \nlater.102  This approach is structurally consistent with how MISO processes other service \nagreements, such as MISO’s pro forma GIA and preserves the rights of Large Loads Transmission \nCustomers to bring disputes before the Commission through unexecuted filings while maintaining \nthe accelerated LLPR completion timeframe needed to allow subsequent LLPR cycles to \ncommence with models that account for prior LLPR cycles with sufficient certainty.103   \n \n \nTo address stakeholder desires for a date certain when the LLPR Application is deemed \ngranted and the required Large Load Upgrades approved for inclusion in MTEP, MISO’s proposed \nlanguage uses either the date of the completion of the stakeholder review process, the date the last \nparty executes a conforming cost recovery agreement, or the filing date of a non-conforming or \nunexecuted cost recovery agreement, whichever is later, as the point in time at which MTEP \napproval occurs.  This approach is just and reasonable because an executed conforming agreement \nmay be included in MISO’s Electronic Quarterly reports and need not wait for a Commission order \nto be deemed accepted.104  Thus, the certainty that the project will be developed significantly \nincreases at this point.  For nonconforming and/or unexecuted agreements, MISO considered using \nthe date of a Commission order accepting such agreement as the trigger for MTEP inclusion.  \nHowever, MISO ultimately rejected this approach as impractical.  Given the need to build the base \n \n99  Section I.D.1.c.iii.f also addresses the tender of the final LLPR Study Report, but that timing was addressed in \nthe previous section.  \n100  Gudeman Testimony at 5.  \n101  Id.  \n102  Furnish Testimony at 17.  \n103  See, Tariff Attachment X, Section 11.3 (Execution and Filing) (implementing a similar procedure, including a \ndeemed withdrawal for failure to proceed and different timeframes based on the requirements and timing of the \nunderlying process). \n104  Under MISO’s EPR process, projects are deemed approved for inclusion in MTEP once the study is complete and \nMISO adds them to the list of approved projects.  With the introduction of agreements that memorialize \ncommitments associated with the LLPR process, using later of the stakeholder review process completion date, \nthe execution date, or filing date of unexecuted or non-conforming agreements provides an appropriate equivalent \nreference date for approval."},{"page":22,"startToken":10310,"endToken":10891,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 22 \n \nmodels used in subsequent LLPR cycles using a system topography that reflects what was changed \nby prior LLPR cycles in order to accurately study impacts, it would not be possible to wait several \nmonths for a Commission order before building the models used in the next LLPR cycle while \nmaintaining a triannual LLPR study cadence.  MISO proposes the date of filing of an unexecuted \nor nonconforming filing as point where the application should be deemed approved for inclusion \nin MTEP as reasonable compromise between providing certainty in modeling for the next LLPR \nstudy cycle and maintain the accelerated study cadence necessary to accommodate the integration \nschedules of Large Loads.105 \n \nNotably, no Transmission Service shall commence under an unexecuted or non-\nconforming cost recovery agreement until it has been accepted by the Commission.  While it is \nreasonable to include the needed transmission upgrades in models upon submission of an \nunexecuted or nonconforming filing in order to commence subsequent study cycles on schedule, \nallowing Transmission Service to commence prior to Commission acceptance of the cost recovery \nagreements risks decoupling the requirements for the Large Load Transmission Customer \ncontained in the agreements from the Transmission Service granted.  This risk is not needed to \nprevent delays to all other Large Load Transmission Customers and MISO expects that in most \ninstances, a Commission order would likely be issued before the Large Load’s need-by date.106 \n \nMISO’s proposed language is reasonable and necessary to establish the prescribed timeline \nfor executing the cost recovery agreements, enable stakeholder review and feedback, identify when \nLarge Load projects are considered approved for MTEP purposes, and allow model building for \nsubsequent cycles.  These strict timelines are necessary to ensure that the LLPR process can be \ncompleted in a 365-day period and to ensure that MISO has sufficient certainty in the Large Load \nUpgrades completed by applicants in the LLPR process.  These requirements make clear that even \nif a project is withdrawn and removed from the MTEP models, the Large Load Transmission \nCustomer is still responsible for paying for any identified Large Load Upgrade costs. This \napproach avoids reserving system capability for projects that ultimately do not proceed. \n \nG. Resubmission of Withdrawn Applications—Attachment FF Sections I.D.1.c.iii.g \nProposed section I.D.1.c.iii.g provides that any withdrawal of the application will result in \nthe removal of the project from the LLPR study process.  The Large Load Transmission Customer \nmay submit a new Large Load Application to MISO but must identify what information has \n \n105  While this date does not provide as much certainty as the date of Commission acceptance, a project is still more \nlikely to be developed after a service agreement is filed than before that point. In MISO’s experience, most \nunexecuted filings will still result in the agreement being accepted by the Commission, either with or without the \nrequested changes to pro forma agreement terms, and non-conforming agreements are fairly uncommon. MISO \nacknowledges that rejection is possible and projects that have unexecuted agreements can be included in \nsubsequent models only subject to the outcome of the Commission proceeding.  However, the risks of diminished \ncertainty are, on balance, preferable to guaranteed study delays. \n106  This could result in an actual delay only in the highly unlikely scenario where a Large Load is projected to be \nbuilt and require Transmission Service obtained through LLPR in a shorter timeframe than the Commission can \nact on a filing."},{"page":23,"startToken":10891,"endToken":11351,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 23 \n \nchanged since the previous submission.107  This language provides clear withdrawal rules and is \nboth reasonable and needed to allow for the uniform administration of the LLPR process on an \naccelerated timeframe.  \n \nH. Stakeholder Forums—Attachment FF Sections I.D.1.c.iii.h. \n \nConsistent with its current process, MISO will host a stakeholder forum at the end of each \nLLPR study process or as otherwise provided in the Transmission Planning Business Practices \nManual (“TPBPM”) basis to review the identified transmission needs, solutions, and any \nalternatives identified in the completed LLPR studies.108    The purpose of these stakeholder forums \nis to review with stakeholders the transmission needs, solution(s), and any identified alternatives \nidentified in the completed LLPR System Impact Studies.  Following each stakeholder forum, \nstakeholders will have a defined comment period outlined in the TPBPM.109  This stakeholder \nreview process happens in parallel to the tender and execution of any relevant cost recovery \nagreements, thus allowing MISO to schedule stakeholder discussions and comment periods on an \nactionable timeframe.  As explained earlier in this letter, a LLPR Application is considered \napproved by MISO at the completion of the stakeholder review process, execution of a conforming \ncost recovery agreement for such Large Load Upgrade, or upon the filing of an unexecuted or non-\nconforming cost recovery agreement with the Commission, whichever is later.110  For example, if \na cost recovery agreement was executed within two days, MISO would not consider the project \napproved until it completed the stakeholder review process.  This is necessary to allow action on \nstakeholder comments where appropriate.   \n \nThese proposed Tariff additions align with MISO’s commitment to working with \nstakeholders in addressing the integration of Large Loads and providing transparency in the \nprojects studied in the LLPR process.  MISO regularly hosts these stakeholder forums as part of \nthe EPR process and will continue to do so on a regular basis for projects going through the LLPR \nprocess.  \n \nI. Cost Recovery Agreements—Attachment FF Section I.D.1.c.iii.i. \n \nAs part of the proposed LLPR process and to mitigate the risk of cost shifting among \nTransmission Customers, MISO is proposing two cost recovery agreements to ensure that a Large \nLoad Transmission Customer bears the risk and is ultimately responsible for the costs incurred to \nprovide the requested Transmission Service.111  The relevant cost recovery agreements will include \n \n107  Furnish Testimony at 16.  \n108  Id. at 17. Any meetings involving CEII or confidential materials will be handled under Section I.C.23 of \nAttachment FF.  \n109  Id.  \n110  Id. \n111  Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and \nAttachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery \nAgreement)."},{"page":24,"startToken":11351,"endToken":11834,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 24 \n \nan exhibit listing the Large Load Upgrade(s) and/or Impacted Transmission Owner Large Load \nUpgrade(s) that are required for the Large Load Transmission Customer. \n \nThe LLPR process ends with MTEP approval and after the issuance of such approval, the \nTransmission Customer remains responsible for the Large Load Upgrade costs identified through \nthe LLPR.112  Thus, if a project is assigned Large Load Upgrades through the LLPR process and \nthe Large Load is subsequently not built, or its service is terminated, then the Large Load \nTransmission Customer will remain responsible for any associated costs assigned to their project \nunder the proposed cost recovery agreements.  This provides the necessary certainty for later \nprojects studied in the LLPR process and will allow MISO to complete the studies efficiently \nwithout disrupting future LLPR study cycles.113  \n \nThe details and requirements of the proposed cost recovery agreements are further \ndescribed in Section IV of this transmittal letter.  \n \nJ. LLPR Operations Agreement and Confidentiality—Attachment FF Sections \nI.D.1.c.iii.j—I.D.1.c.iii.k. \n \nOnce a Large Load project has received MTEP approval, the Transmission Customer must \nsubmit an updated Large Load forecast along with an operations agreement for the new Large \nLoad.114  This operations agreement, which is Exhibit 2 to Attachment F, is an application for \nNetwork Integration Transmission Service (NITS) in accordance with Module B Section 29.2 of \nthe Tariff prior to the Service Commencement Date.  As part of the operations agreement process, \nthe Transmission Owner will develop a CPNode for each Large Load.  This is necessary for MISO \nsettlement, operational visibility, and forecasting purposes.115  These pro forma service agreements \nare executed, reported in the EQR, and posted publicly on MISO’s website.  Service to the Large \nLoad will not commence prior to MISO’s review and execution of the operations agreement. \n \nProposed Section I.D.1.c.iii.k provides for the designation and protection of confidential \nand Critical Energy Infrastructure Information by participants in the LLPR process with access to \nnon-public information subject to MISO’s established Nondisclosure Agreement and CEII rules.  \nAs explained further by Ms. Furnish, the form of non-disclosure agreement will be the universal \nNDA, as accepted by the Commission for inclusion in MISO’s Tariff as Attachment Z.  The CEII \nNDA is directly drawn from the form of nondisclosure agreement included with MISO’s \nInterconnection Request form required for Interconnection Customers, thus promoting rules \nalignment across processes.  Allowing participants in studies to request confidential and/or CEII \ntreatment of appropriate information is a necessary and routine feature of MISO study processes \nand will protect the more sensitive information (e.g., detailed models, diagrams and other sensitive \ntechnical information) required as part of the LLPR process.  MISO notes that these confidentiality \n \n112  Furnish Testimony at 15-16. \n113  Id.  \n114  Furnish Testimony at 16-17.  \n115  Furnish Testimony at 16-17."},{"page":25,"startToken":11834,"endToken":12351,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 25 \n \nsafeguards will not conflict with the transparency requirements proposed in this filing, including \nthe public Large Load dashboard, because the required information is set forth in the Tariff and \nboth MISO’s proposed Tariff language and existing confidentiality rules prohibit designation as \nconfidential of information that a Tariff or other legal requirement specifies be made public.   \n \nAt the conclusion of the LLPR process, the cost recovery agreements associated with Large \nLoad Upgrades will be submitted to the Commission for approval.  Any executed cost recovery \nagreements will be included in MISO’s EQR reports on a quarterly basis and all the agreements \nincluded in those EQR reports are publicly posted on MISO’s public website in accordance with \nthe same procedures applicable to other types of service agreements.  The EQR reports will also \nbe accessible through MISO’s website. 116  Unexecuted or non-conforming cost recovery \nagreements will be filed separately with the Commission and publicly available subject to the \nCommission’s regulations.   \n \nK. The Proposed Tariff Revisions are Just and Reasonable. \n \nUnder section 205 of the Federal Power Act, MISO must show that its proposed Tariff \nrevisions are just and reasonable, and not unduly discriminatory or preferential. “For filings made \nunder FPA section 205, the Commission evaluates whether the proposal in the filing is just and \nreasonable, and not whether alternative proposals are more or less reasonable than the filing party’s \nproposal.”117  In the Show Cause Order, the Commission preliminarily found that MISO’s Tariff \nlacked clear and consistent provisions addressing large load integration.  The Commission noted \nthat MISO’s role in load additions has been largely supplemental and the Transmission Owners’ \nstudy processes are not set in the Tariff and some have used ad hoc, stand-alone study agreements. \nThe proposed LLPR revisions directly address these concerns.  \n \nMISO developed a dedicated framework for Large Loads and proposes to add the LLPR \nprocess to Attachment FF of the Tariff as well as new pro forma Attachments LLL and MMM.  \nWith these additions, every Transmission Customer seeking Transmission Service for a Large \nLoad must submit a Large Load Application and provide the requisite information to MISO.  This \nnot only creates a single path for Large Load Transmission Customers to take when seeking \nTransmission Service, it provides MISO with the ability to expedite the study timelines and, in \nsome cases, optimize the transmission solutions. Each Large Load Application must elect one of \nseveral defined options (LLPR, Interim NITS, LARS, etc.), which replaces the historic and \npotentially inconsistent practices with a single, Tariff-based process that applies equally to all \nLarge Load Transmission Customers.  Together, these provisions create a transparent and \npredictable path for identifying the Large Load Network Upgrades needed to serve Large Load \nTransmission Customers, while balancing speed, reliability, and stakeholder engagement.  \n \nMISO’s proposed Large Load framework provides alternative pathways depending on size \nof the load, which strikes a just and reasonable balance between capturing the larger loads for \n \n116  See MISO, Notifications Overview, Market Settlements, available at: https://www.misoenergy.org/markets-and-\noperations/notifications/.  \n117  See PJM Interconnection, LLC, 197 FERC ¶ 61,019, at P 29 (2026)."},{"page":26,"startToken":12351,"endToken":12917,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 26 \n \nwhich MISO needs visibility to ensure system reliability and directing the smaller loads that do \nnot raise the same reliability concerns into the existing EPR process.118  The Large Load \nApplication is just and reasonable and not unduly discriminatory or preferential because it requires \nthe applicants to provide significant information about the Large Loads, which in turn will provide \nMISO with the information necessary to address the operational impacts of Large Loads looking \nto interconnect to MISO’s Transmission System.   \n \nThe LLPR application process also contains the elements identified by the Commission in \nthe Show Cause Order. The Large Load Applications are accepted on a rolling basis and require a \nnon-refundable application fee of $250,000.  The applications must include detailed information \nabout the Large Load and provide planning models for MISO to utilize when completing its own \nindependent studies.  MISO is also requiring that the Large Load Transmission Customer attest \nthat it has no other pending requests for service to the same Large Load, which will improve load \nforecasting clarity and certainty.  The Commission has noted in other contexts that non-refundable \nfees, study deposits, and readiness requirements deter speculative requests, which is critical for \nMISO to be able to study these loads on an expedited basis.  The proposed Tariff revisions and \npro forma cost recovery agreements also require financial security equal to the Large Load \nNetwork Upgrade capital costs once the LL-CRA is executed, which will further reduce the \npossibility of speculative requests clogging the study processes, distorting load forecasting, or \nfurther risking any kind of cost shifting.  \n \nThe LLPR System Impact Study is just and reasonable because it incorporates enhanced \nstudy requirements to enable MISO independently to analyze the impacts of each Large Load on \nthe Transmission System.  MISO will conduct this analysis based on MTEP models, and in \ncollaboration with the Transmission Owner and Transmission Customer.  Moreover, to participate \nin the LLPR process, MISO requires that EMT studies be completed before the application is \nsubmitted so that the full set of Network Upgrades needed to reliably serve the Large Load can be \nidentified.119  The study also requires the evaluation of alternative transmission technologies and \ngrid-enhancing technologies by the Transmission Owners and MISO will review the consideration \nof any relevant ATTs/GETs, which was another Commission concern.120  \n \nThe LLPR provides the clarity and consistency sought in the Show Cause Order by stating \nthe information required to enter the process, the study sequence, the roles of MISO and the \nTransmission Owners, and the relationship of the results to planning and service.  The readiness \nand attestation requirements address the Commission’s concern with speculative or duplicative \nrequests, while the cumulative assessment and reliability information support consistent treatment \n \n118  See PJM Interconnection, LLC, 197 FERC ¶ 61,019, at P 27 (2026); see also Sw. Power Pool, Inc., 194 FERC ¶ \n61,031, at PP 10, 61 (2026) (accepting a proposed definition of a high impact large load that included a 50 MW \nthreshold for new or increased load at a single site connected to the transmission system at a voltage level greater \nthan 69 kV); Tri-State Generation & Transmission Ass’n, Inc., 196 FERC ¶ 61,127, at P 76 (2026) (Tri-State) \n(accepting a proposal to define a high impact load as load exceeding or forecasted to exceed 45 MW within four \nyears). \n119  Furnish Testimony at 8.  \n120  Id. at 13-14."},{"page":27,"startToken":12917,"endToken":13417,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 27 \n \nof system impacts.  The recurring cycles provide an accelerated path grounded in MISO’s existing \nplanning framework.121  Finally, the proposed revisions were developed through MISO’s Large \nLoad Working Group where the process was presented, reviewed, and discussed by \nstakeholders.122  The Commission recognized and encouraged this effort in the Show Cause Order.  \n \nFor these reasons, the proposed Tariff revisions are just and reasonable, and not unduly \ndiscriminatory or preferential, and the Commission should accept them under section 205 of the \nFederal Power Act.  \n \nL. Separate Proposal to Apply Cost Recovery Agreements to LARS Projects.  \n \nSeparately from all other proposals contained in this filing, MISO proposes to include the \nfollowing language as a separate paragraph in Attachment FF, Section I.D.1.c.iii.f in order to \nfacilitate the use of the LL-CRA and LLITO-CRA as part of the LARS process: \n \nSubject to Commission acceptance of the revisions to Attachment FF of the Tariff \npending before the Commission in Docket No. ER27-25, all LARS Associated \nTransmission Customers that submit LARS Applications for inclusion in a LARS \ncycle with a kickoff date on or after February 14, 2027, shall execute or request the \nunexecuted and/or non-conforming filing of the LL-CRA and/or LLITO-CRA, as \napplicable, for all Network Upgrades identified in a LARS study for which \nAttachment FF I.D.1.b.ii.g. assigns cost responsibility to the LARS Associated \nTransmission Customer.  The LARS Application and Network Upgrades identified \nin a LARS study for which Attachment FF I.D.1.b.ii.g. assigns cost responsibility \nto the LARS Associated Transmission Customer shall be deemed approved for \nMTEP purposes as of the later of: (1) the date the last party executes the applicable \nconforming LL-CRA and, if required, LLITO-CRA(s); (2) the date of filing with \nthe Commission of an unexecuted and/or nonconforming LL-CRA and/or LLITO-\nCRA; or (3) the conclusion of the stakeholder comment period required by Section \nIII.D.1.c.iii.h of this Attachment FF. A LARS Associated Transmission Customer \nshall not commence Transmission Service under an unexecuted or non-conforming \nLL-CRA or LLITO-CRA until such agreement(s) have been accepted by the \nCommission. \n \nIf the Commission ultimately approves MISO’s LARS proposal, all LARS Associated \nTransmission Customers that submit LARS Applications on or after the effective date of this filing \n(February 14, 2027), shall execute or request the unexecuted filing of a cost recovery agreement, \nas applicable, for all Large Load Upgrades identified in a LARS study. The Large Load Upgrades \nassociated with these LARS projects will be considered approved for MTEP purposes as of the \ndate that the last party executes a conforming cost recovery agreement or as of the date of filing \nan unexecuted or non-conforming cost recovery agreement with the Commission.   \n \n121  Show Cause Order at PP 39, 56–65 (identifying concerns regarding timely studies, readiness, operational impacts, \nand clear Tariff provisions); Furnish Testimony at 3.  \n122  See Furnish Testimony at 28-33."},{"page":28,"startToken":13417,"endToken":13991,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 28 \n \n \nIn the LARS Answer, MISO also stated that it would submit another filing to reconcile the \nLARS and LLPR processes to ensure their full alignment.123  Notably though, MISO has proposed \nstandalone Tariff language in this docket to make the proposed cost recovery agreements \napplicable to new LARS studies.  While acceptance of the Tariff language discussed above will \nnot obviate the need to make a subsequent reconciliation filing to harmonize other aspects of the \nLARS and LLPR filings, it will allow for the cost recovery agreements, which are a valuable \ntransparency and accountability mechanism, to apply to LARS studies earlier than would be \npossible if MISO waited until acceptance of the instant filing and a subsequent reconciliation \nfiling, to apply the cost recovery agreements to the LARS process.124  To the extent that the \nCommission accepts the cost recovery agreements in the instant docket, it may then separately \nconsider whether to make them applicable to the next LARS cycle, assuming MISO’s LARS filing \nalso is accepted.   \n \nThus, this proposed Tariff language represents a standalone proposal, which MISO \nincludes in this filing purely for Tariff administration reasons.125  While it builds on the LLPR \nprocess and Cost Recovery Agreements proposed in this filing, it is not a component of any other \nproposal contained in this filing, not a part of any compromise or agreement with stakeholders \nregarding other elements of this filing.  MISO urges acceptance of this language for the reasons \ndescribed above, MISO  \n \nIV. \nCOST RECOVERY AGREEMENT AND COST TRANSPARENCY \n \nThe Show Cause Order preliminarily found that MISO’s Tariff appeared to be unjust and \nunreasonable because it lacked adequate mechanisms to mitigate the risk of cost shifting among \ntransmission customers, which may result in unjust and unreasonable rates for transmission \nservice.126  Specifically, the Commission was concerned about the apparent lack of:  (1) \ntransparency regarding the assignment of network upgrades, and their associated costs, that are \nneeded to provide transmission service to transmission customers on behalf  of large loads; and \n(2) a pro forma cost recovery agreement between MISO, the transmission owner, and the \n \n123  Furnish Testimony at 19; see MISO’s November 9 Answer filed in Docket No. ER27-25-000 (“LARS Answer”) \nat 15.  \n124  This proposed language is severable from LARS because acceptance LARS was designed to work even with \nexisting processes and then be integrated with the reforms contained in this filing once accepted by the \nCommission.. The standalone proposal contained in this filing is an enhancement to LARS, but not necessary for \nits function.  The proposed language is severable from this filing because it is contained in its own paragraph that \nreplicates language proposed elsewhere and its application is limited to LARS. \n125  As explained in the LARS Answer, MISO filed its LARS proposal before LLPR, the LL-CRA and LLITO-CRA \nwere developed given the immediate need for such a process and lead time for implementation. LARS Answer at \n3, 18. In that docket, MISO committed to updating LARS to incorporate the processes changes included in this \nfiling once this filing is accepted. LARS Answer at 15. While MISO could make a separate contemporaneous \nfiling from this one to make the LL-CRA and LLITO-CRA applicable to Large Load Transmission Customers \nparticipating in LARS, this would create version control concerns with pending language built upon pending \nlanguage, as each filing would create a new version of Attachment FF.   \n126  Show Cause Order at P 66."},{"page":29,"startToken":13991,"endToken":14462,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 29 \n \ntransmission customer taking transmission service on behalf of Large Loads that ensures that the \ntransmission customer bears the risk and is ultimately responsible for costs incurred to provide \ntransmission service, including the cost of network upgrades.127  Below is a summary of the \nproposed Tariff revisions that address the Commission’s concerns.   \n \nA. Cost Recovery Agreements \n \nIn the Show Cause Order, the Commission preliminarily found that MISO’s Tariff appeared \nto be unjust and unreasonable because it lacked “adequate mechanisms to mitigate the risk of cost \nshifting among transmission customers, which may result in unjust and unreasonable rates for \ntransmission service.”128  To prevent unjust and unreasonable cost shifting among transmission \ncustomers, the Commission stated that it appeared necessary for MISO, the relevant transmission \nowner, and the transmission customer taking transmission service on behalf of a large load to enter \ninto a cost recovery agreement with a specified minimum financial contribution and financial \nsecurity sufficient to secure such contribution to mitigate cost shifting if the transmission customer \nultimately takes less transmission service than anticipated because the large load does not \nmaterialize as planned or is not developed at all.129   \n \nIn response to concerns raised by the Commission, MISO and the MISO Transmission \nOwners propose Tariff revisions and two pro forma cost recovery agreements that together require \nthe Large Load Transmission Customer to make a minimum contribution toward the revenue \nrequirement of the Transmission Owner(s) responsible for constructing the Large Load Upgrades \nidentified by MISO in the LLPR.130  To ensure the minimum contribution, Large Load \nTransmission Customers are required to provide security to cover the capital cost of the Large \nLoad Upgrades.  As briefly described in the previous section, prior to receiving MTEP approval \nfor any such Large Load Upgrades, Large Load Transmission Customers are required to execute \nthe pro forma LL-CRA and/or LLITO-CRA, as applicable, or request that the cost recovery \nagreements be filed unexecuted or as non-conforming with the Commission within 15 business \ndays of being tendered the agreements by MISO.  Failure to do so by the conclusion of the 15-day \nperiod will result in the Large Load Application being withdrawn, and the project being removed \nfrom the LLPR process.  The customer is required to provide security within 45 days of the \nexecution of the LL-CRA and/or LLITO-CRA.  If the LL-CRA or LLITO-CRA is filed unexecuted \nor as non-conforming, separate terms apply depending on the nature of the dispute and when the \nCommission approves such agreement.  Importantly, a Large Load Transmission Customer cannot \n \n127  Id.  \n128  Show Cause Order at P 78. \n129 Id. at P 82, 84. \n130  Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and \nAttachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery \nAgreement)."},{"page":30,"startToken":14462,"endToken":14930,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 30 \n \ncommence Transmission Service under an unexecuted and/or non-conforming LL-CRA or LLITO-\nCRA until the applicable cost recovery agreements have been approved by the Commission.131   \n \nThe above framework, including the embedded rate mechanisms, which are discussed in \nmore detail below, reflect a balanced approach to mitigating the cost shift concerns identified by \nthe Commission while respecting state laws (in particular state retail ratemaking authority),  \nTransmission Owner diversity, including their varied business models, the reality that \nTransmission Customers are often not the Large Load entities actually interconnecting to the \nTransmission System but merely a pass through, and the region’s economic development \nambitions.  Importantly, nothing in LLPR, including the proposed cost recovery framework \ninterferes, limits the ability of states and other retail regulators to impose additional conditions, \nfurther allocate cost responsibility and risk among and between retail customers and Load Serving \nEntities, or require further agreements involving parties not directly taking service under MISO’s \nTariff (e.g., data centers and other owners of Large Loads).  Although a difficult needle to thread, \nthe proposed framework, consistent with the direction given by the Commission in the Show Cause \nOrder, and in recognition of MISO’s regional differences and state authority, is a just and \nreasonable approach to addressing the risk of cost shifting among Transmission Customers in \nMISO and potentially unjust and unreasonable rates.   \n \nBelow is a summary of each agreement and the rate mechanisms therein. \n \n1. Scope and allocation of responsibilities. \n \nMISO proposes two complementary pro forma cost recovery agreements to establish the \nLarge Load Transmission Customer’s financial responsibility for the Large Load Upgrades \nidentified through the LLPR study process.  The Large Load Cost Recovery Agreement (“LL-\nCRA”) addresses upgrades within the Transmission Pricing Zone containing the Large Load’s \nPoint of Withdrawal.  The Large Load Impacted Transmission Owner Cost Recovery Agreement \n(“LLITO-CRA”) addresses upgrades outside that zone.  MISO, the Large Load Transmission \nCustomer, and the applicable Transmission Owner(s) are required parties to the agreements.  For \npurposes of the agreements, LLPR includes LARS.  The agreements therefore link the LLPR study \nresults to the entities responsible for service, investment, and payment. \n \nIn addition to any Transmission Service charges incurred by the Large Load Transmission \nCustomer under the Tariff, a Large Load Transmission Customer is responsible for the costs of the \nLarge Load Upgrades (“Minimum Contribution”) pursuant to the cost recovery rate mechanisms \nin the LL-CRA and LLITO-CRA.132  This Minimum Contribution is necessary to ensure that the \nLarge Load Transmission Customer is responsible for paying for the costs of transmission driven \nby the Large Load (i.e., the cost incurred to provide the requested Transmission Service, including \nthe costs of any Large Load Network Upgrades).   \n \n \n131  Proposed MISO Tariff, Attachment FF, I.D.1.c.iii.f. \n132  Gudeman Testimony at 7, 22."},{"page":31,"startToken":14930,"endToken":15400,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 31 \n \nTo accommodate the diversity of regulatory approaches and business models among \nTransmission Owners, the pro forma agreements provide the Transmission Owner responsible to \nconstruct a Large Load Upgrade the flexibility to roll into its rates for Transmission Service the \ncapital costs of the Large Load Upgrade or to directly assign the costs of the Large Load Network \nUpgrade(s) to the Large Load Transmission Customer, and such election will be recorded in the \nagreement.133  The MISO Transmission Owners are a diverse group of investor-owned \ntransmission owners, municipal utilities, and cooperatives, including both vertically integrated and \nindependent transmission companies, that own transmission facilities over which MISO provides \nTransmission Service.  For example, some Transmission Owners, in addition to service \nTransmission Customers, serve retail load.  Some do not—they only serve MISO Transmission \nCustomers.  The rate mechanisms in the cost recovery agreements ensure that cost recovery does \nnot unnecessarily conflict with these various Transmission Owner business models in existence \nwithin the MISO footprint.  Importantly, however, as discussed below, whether Large Load \nUpgrade costs are rolled in or directly assigned, the Large Load Transmission Customer is always \nresponsible for the costs of the Large Load Upgrades, thus, mitigating cost shifts to other \nTransmission Customers, consistent with the Show Cause Order.134   \n \n2. Recovery of costs for upgrades within the TPZ. \n \nWhere the capital costs of the Large Load Network Upgrade are rolled in the Transmission \nOwner’s transmission rates, the Large Load Transmission Customer is responsible for its Total \nRequired Revenue Commitment, which amount is set forth in the agreement and payable on a \nyearly basis consistent with the Yearly Required Revenue Commitment.135  If the Transmission \nService revenue attributable to a Large Load Transmission Customer on behalf of the Large Load \nduring a calendar year is less than the customer’s Yearly Required Revenue Commitment, the \ncustomer is required to make a Supplemental Payment to the Transmission Provider.136  The \nformulas for calculating such amounts are set forth in Exhibit C of the LL-CRA.  Below is a more \ndetailed description of these items.   \n \nThe Total Required Revenue Commitment reflects the return on and of the Large Load \nNetwork Upgrade investments over twenty years, including capital cost, return, depreciation, \noperations and maintenance, and taxes.137  The commitment is initially based on the estimated \nupgrade costs and then adjusted as actual capital costs are determined.138   \n \nFollowing each calendar year, the Transmission Owner, in coordination with MISO, will \ndetermine whether the Large Load Transmission Customer has satisfied its Yearly Required \n \n133  Proposed MISO Tariff, Attachment LLL, §§ 3.1–3.4 and signature page; Proposed MISO Tariff, Attachment \nMMM, §§ III–V and signature page. \n134  Gudeman Testimony at 8. \n135  Id. \n136  Id. at 12. \n137  Id. at 8-10. \n138  Proposed MISO Tariff, Attachment LLL, § 3.3.3."},{"page":32,"startToken":15400,"endToken":15925,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 32 \n \nRevenue Commitment or whether a Supplemental Payment is owed.139  If the Transmission \nService revenue attributable to Large Load Transmission Customer during a calendar year is less \nthan the Large Load Transmission Customer’s Yearly Required Revenue Commitment, the Large \nLoad Transmission Customer is required to make a Supplemental Payment to MISO, the formula \nfor which is set forth in Exhibit D to the LL-CRA.  If the attributable revenue equals or exceeds \nthe yearly commitment, no Supplemental Payment is required.  Mr. Gudeman, in his testimony, \ndetails and provides examples for calculating the Total Required Revenue Commitment, the Yearly \nRequired Revenue Commitment and Supplemental Payment.140 \n \nThis annual comparison gives effect to the Large Load Transmission Customer’s actual \ncontribution to transmission revenues while preserving a minimum payment obligation when load \nis below the level needed to mitigate a cost shift.  For example, a $10 million Yearly Required \nRevenue Commitment and $7 million in attributable annual transmission-service revenue would \nnecessitate a $3 million Supplemental Payment; attributable revenue of $10 million or more would \nproduce no Supplemental Payment for that year.  In his testimony, Mr. Gudeman, based on \nassumptions provided in his testimony, provides an illustrative example of how the Supplemental \nPayment is determined.141  If required, MISO will issue the supplemental invoice within ninety \ndays after the end of every calendar year during the term of the cost recovery agreement, with \nbilling and payment governed by Tariff Section 7 and the applicable Business Practice Manuals.142 \n \nMISO will allocate any Supplemental Payments among the Transmission Owners that are \na party to the LL-CRA in proportion to their respective Annual Incremental Revenue Requirement \n(defined in the agreement) included in the Yearly Required Revenue Commitment.143  Any \nSupplemental Payment allocated to a Transmission Owner will be treated as a revenue credit \nagainst the recipient Transmission Owner’s annual transmission revenue requirement, and each \napplicable Transmission Owner must provide a workpaper in its annual informational filing, which \nis generally filed in March of a calendar year, detailing that credit.144  While the need for a \nSupplemental Payment and the amount thereof will not be known until after a calendar year has \nended, there does not necessarily need to be a large lag in reflecting significant Supplemental \nPayments in rates paid by Transmission Customers.  As Mr. Gudeman explains, any lag associated \nwith a Supplemental Payment could be addressed by the Transmission Owner when developing its \nprojected revenue requirement.145  In short, the cost recovery mechanism explained above is \nspecifically designed to offset in rates the costs of the Large Load Network Upgrades so that the \nend result is that those costs are not shifted to other Transmission Customers.146 As shown in \n \n139  Proposed MISO Tariff, Attachment LLL, § 3.3.5. \n140  Gudeman at 8-17; see also Proposed MISO Tariff, Attachment LLL, § 3.3 and Ex. C, D.  \n141  Gudeman Testimony at 12-13; Gudeman Testimony Exhibit MTO-0004 (Calculation of Supplemental Payment). \n142  Proposed MISO Tariff, Attachment LLL, §§ 3.3.5.6 and 3.3.5.7. \n143  Gudeman Testimony at 13. \n144  Gudeman Testimony at 17. \n145  Id. at 13-16. \n146  Id. at 16-17."},{"page":33,"startToken":15925,"endToken":16381,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 33 \n \nExhibit MTO-0006 to Mr. Gudeman’s , with all else being equal assuming no other changes to \nload or revenue requirements, the Large Load Transmission Customer pays at least the incremental \nrevenue requirement for the Large Load Network Upgrades and the zonal rate charged to other \ncustomers will not increase as a result of the Large Load Network Upgrades.147   \n \nWhere the capital costs of the Large Load Network Upgrades are directly assigned to the \nLarge Load Transmission Customer, payments will be due from the customer as specified in a \nseparate agreement between Transmission Owner and Large Load Transmission Customer to be \nfiled with the Commission.148  Under such circumstances, the Transmission Owner agrees that it \nwill not recover the costs of the directly assigned upgrade from other Transmission Customers and \ncommits to providing an annual workpaper showing that treatment.149   \n \nThe LL-CRA continues until the earlier of twenty years after the final Large Load Network \nUpgrade enters service or satisfaction in full of the Total Required Revenue Commitment and the \ndirect-assignment payment obligations, as applicable.150 \n \n3. Recovery of costs for upgrades outside the TPZ. \n \nThe LLITO-CRA establishes a separate rate mechanism for upgrades outside the TPZ.  \nWhere the capital costs of ITO-Large Load Network Upgrades are rolled into a Transmission \nOwner’s rates, the Large Load Transmission Customer is responsible for the ITO Large Load \nNetwork Upgrade(s)’ Monthly Revenue Requirement beginning in the month following the \nTransmission Owner’s notification that the upgrade has entered service.151  The formula to \ncalculate the Monthly Revenue Requirement is set forth in Exhibit II to the LLITO-CRA and is \nidentical to the “Incremental Revenue Requirement for Large Load Network Upgrades \nCalculation” formula in Exhibit C to the LL-CRA.152  As described above, the formula multiplies \nthe capital invested in the ITO-Large Load Network Upgrade(s) by a levelized fixed charge rate \ndetermined from the term of the LLITO-CRA and data from the Transmission Owner’s MISO \nTariff Attachment O Formula Rate, including taxes, interest on long term debt, return on equity, \ndepreciation expense, total operations and maintenance expense, general and common \ndepreciation expense; taxes other than income taxes; and total gross transmission plant.  The \ndefault recovery term is 240 months of payments for each upgrade, unless the parties mutually \nagree to a different term or the applicable obligations are otherwise satisfied.153 \n \n \n147  Id. at 16-17; Gudeman Testimony Exhibit MTO-0006 (Zonal Rate Impact). \n148  Proposed MISO Tariff, Attachment LLL, § 3.4.1. \n149  Proposed MISO Tariff, Attachment LLL, § 3.4.2. \n150  Proposed MISO Tariff, Attachment LLL, §§ 2.2–2.3, 3.3. \n151  Proposed MISO Tariff, Attachment MMM, § IV. \n152  Gudeman Testimony at 24. \n153  Proposed MISO Tariff, Attachment MMM, § II."},{"page":34,"startToken":16381,"endToken":16854,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 34 \n \nThe Transmission Owner recalculates the payment annually using updated inputs from the \nTransmission Owner’s Tariff Attachment O Formula Rate using data from the previous calendar \nyear.154  Any payments from the customer under the LLITO-CRA are treated as revenue credits \nagainst the Transmission Owner’s annual transmission revenue requirement, documented in the \nTransmission Owner’s annual informational filing.155 \n \nIf the impacted Transmission Owner directly assigns ITO-Large Load Network Upgrade \ncosts under proposed Section V of the LLITO-CRA,  payments are due as specified in a separate \nagreement between Transmission Owner and Large Load Transmission Customer to be filed with \nthe Commission.156  As with the LL-CRA, the Transmission Owner may not recover the directly \nassigned costs from other Transmission Customers and must document the foregoing in its annual \ninformational filing.157   \n \n4. Financial security and construction coordination \n \nTo secure the Large Load Transmission Customer’s obligations, the agreements require \nirrevocable security reasonably acceptable to each Transmission Owner (for example, a letter of \ncredit, surety bond, or parent guaranty) in an amount equal to the capital cost of the covered \nupgrades.158  The agreements allow the customer to request a reduction in security, subject to the \nspecified timing, documentation, and floor based on the remaining Minimum Contribution, and \nthe Transmission Owner may not unreasonably deny a request consistent with those provisions.  \nUnder such terms, where the Large Load Transmission Customer and Transmission Owner are the \nsame legal entity, the Transmission Owner is not required to demand security of itself but it is still \nsubject to the requirement to protect against cost shifts.  The security provisions in the agreements \nexist to protect the Transmission Owner from financial risk associated with the capital costs of the \nLarge Load Network Upgrade(s) and Transmission Customers from related cost shifts, and in \nanalogous circumstances, the Commission has found it would be impractical and unnecessary to \nrequire security.159 \n \nThe Large Load Transmission Customer is required to provide security within 45 days of \nthe parties’ execution of the agreements.160  If the agreements are filed unexecuted or as non-\nconforming, however, separate terms apply, depending on when the Commission approves such \nagreement, as well as the nature of the parties’ dispute.  Failure to provide security within the \napplicable period results in immediate withdrawal of the Large Load Application.161 \n \n154  Gudeman Testimony at 24. \n155  Proposed MISO Tariff, Attachment MMM, §§ IV.i—j.  \n156  Gudeman Testimony at 24-25; Proposed MISO Tariff, Attachment MMM, § V. \n157  Gudeman Testimony at 25. \n158  Proposed MISO Tariff, Attachment LLL, § 4.1; Proposed MISO Tariff, Attachment MMM, § VI. \n159  See Midcontinent Indep. Sys. Operator, Inc., 156 FERC ¶ 61,166, at P 12 (2016); Gudeman Testimony at 19, 26. \n160  Gudeman Testimony at 19, 25. \n161  Proposed MISO Tariff, Attachment LLL, § 4.2; Proposed MISO Tariff, Attachment MMM, § VI."},{"page":35,"startToken":16854,"endToken":17337,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 35 \n \n \nUpon the Transmission Owner’s request, the Transmission Owner and Large Load \nTransmission Customer will enter into a separate agreement regarding construction of the covered \nupgrades.162  Such separate agreements do not displace the customer’s obligation to enter into a \ncost recovery agreement.  Where the security’s form, terms, and provider permit, security posted \nunder a cost recovery agreement may satisfy the construction agreement’s security requirement.  \nSimilarly, if the Large Load Transmission Customer provides security under a construction \nagreement prior to providing the required security under the cost recovery agreement, the security \nrequired under the construction agreement may be applied as the required security under the cost \nrecovery agreement if the forms, terms, and provider of the security under the construction \nagreement allow it.  Both pro forma agreements prohibit a lapse between the two arrangements \nand prohibit requiring the customer to concurrently maintain the full security amount under both.  \nThe pro formas also separately preserve applicable Tariff security and collateral requirements for \nTransmission Service.  The coordination provisions therefore address overlapping construction \nsecurity while retaining the payment obligations secured by the cost recovery agreement. \n \nB. MISO Large Load Dashboard—Attachment FF, Section I.D.1.c.iv \n \nTo ensure that MISO addresses the transparency requirements identified in the Show Cause \nOrder, MISO is proposing Tariff language describing its commitment to sharing information \nrelated to large load integration through a public dashboard.  The Commission explained that it \nwas “concerned about the apparent lack of (1) transparency regarding the assignment of Network \nUpgrades, and their associated costs, that are needed to provide transmission service to Eligible \nCustomers on behalf of large loads . . .”163  The proposed Tariff changes address the Commission’s \ngoals for transparency and information sharing.  \n \nMISO’s proposed Large Load dashboard will identify the Large Load Upgrades that are \nneeded and the costs associated with those upgrades.  Transmission Owners must provide MISO \nwith information that may be publicly posted on its website including: 1) the aggregate amount of \nproposed Large Load additions by Large Load Transmission Customers, including in each \nTransmission Pricing Zone; 2) the planned Large Load Upgrades needed to provide the Large Load \nTransmission Customer Transmission Service, identified by type of equipment and Large Load \nUpgrade for each Large Load; and 3) cost estimates for those Large Load Upgrades.164  MISO’s \nproposed Tariff language closely follows the requirements of the Show Cause Order to ensure \nalignment with the Commission’s transparency requirements.165 \n \nIn accordance with the requirements of the Show Cause Order, MISO will provide data \nreceived from its Transmission Owners related to Large Load Upgrades on its public website and \n \n162  Proposed MISO Tariff, Attachment LLL, § 4.2.1; Proposed MISO Tariff, Attachment MMM, § VI.b. \n163  Show Cause Order at P 66.  \n164  Id. at P 77. \n165   Compare Show Cause Order at P 77 with proposed Attachment FF, Section I.D.1.c.iv."},{"page":36,"startToken":17337,"endToken":17827,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 36 \n \nin a format that is searchable and allows users to filter the data.166 These proposed Tariff additions \ndirectly respond to the Commission’s request for “(1) robust, accurate, and systematic provision \nof data on MISO’s website in a single location, and in an easily accessible format that is searchable \nand allows users to filter the data, regarding the cost for Network Upgrades needed to provide \ntransmission service to Eligible Customers on behalf of large loads.”167  As MISO presented to \nstakeholders in the LLWG, it is in the process of developing a Large Load Dashboard, which will \ndepict a map of MISO’s footprint and the location of the Large Loads along with their associated \nLarge Load Upgrades.168  The information displayed in the dashboard will be easily accessible on \nMISO’s website and searchable by users looking to learn more information about large load \ndevelopment in MISO’s footprint. The proposed Tariff requirements obligate Transmission \nOwners to provide MISO with updated information regularly, with the specific timeframes to be \nset forth in MISO’s BPM for Large Load.169 \n \nThe dashboard, along with the cost recovery agreements and associated materials, will \nprovide a fuller picture of the costs associated with integrating Large Load in MISO’s footprint for \nthe public, and will provide a useful input to state and other retail regulatory authorities in \ndeveloping their own Large Load policies, rules, and regulations. \n \nC. Just and Reasonable Treatment.  \n \nMISO and the MISO Transmission Owners submit that the proposed agreements address \nthe concerns identified in the Show Cause Order and support just and reasonable rates by \nconnecting each Large Load Upgrade to an enforceable minimum contribution from the Large \nLoad Transmission Customer.  Put plainly, under the proposed framework, the Large Load \nTransmission Customer is always responsible for the costs of the Large Load Network Upgrade(s), \nthus, mitigating cost shifts to other Transmission Customers, consistent with the Show Cause \nOrder.170 \n \n166  Furnish Testimony at 25-26.  \n167  Show Cause Order at P 67.  \n168  MISO, Cost Shifting Risk Among Transmission Customers (LLWG-2026-8), Sept. 23, 2026, available at:  \n20260923 LLWG Item 05 Cost Shifting Risk Among Transmission Customers (LLWG-2026-8)783359.pdf. \n169  This approach is consistent with the Rule of Reason given that the obligation is to update regularly and the specific \nreporting cadence is an implementation detail best address through BPMs and adjusted based on experience and \nthe requirements of stakeholder. . See, e.g., Midcontinent Indep.  Sys.  Operator, Inc., 169 FERC ¶ 61,221, at P \n67 2019 (2019) (citing Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 \n(2018)) (describing the rule of reason). \n170  Proposed MISO Tariff, Attachment LLL, §§ 3–5, 7.3; Proposed MISO Tariff, Attachment MMM, §§ III–VII; \nMidcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, PP 78–85 (2026), errata notice, 196 FERC ¶ 61,123 \n(2026) (identifying the cost recovery, security, and revenue-credit concerns)."},{"page":37,"startToken":17827,"endToken":18220,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 37 \n \n \nV. \nTRANSMISSION SERVICE OFFERINGS \n \nA. Overview and service selection. \n \nMISO proposes transmission service options that distinguish a customer seeking temporary \nnon-firm transmission service while progressing toward full NITS from a customer electing an \nongoing permanent firm and non-firm service mix.  Firm Service Step Up (“FSSU”) permits NITS \nservice to increase as the required capability becomes available.  Interim NITS permits \ntransmission service within approved non-firm limits while the remaining upgrades needed for full \nNITS are completed.   \n \nThe transmission service election determines the customer’s rights and obligations.  \nFirmness addresses the availability and priority of Transmission Service; Resource Adequacy \naddresses the capacity needed to support demand.  The proposal treats those questions separately.  \nInterim NITS remains in the capacity construct because it is a transition to full NITS service.  \nNeither election authorizes withdrawals beyond the quantities and operating conditions established \nfor that service. \n \nB. Firm Service Step Up. \n \nThe FSSU process is designed to allow a Transmission Customer to obtain NITS in \nincrements before all upgrades supporting its ultimate NITS requirement have been completed.  \nAs the relevant capability becomes available, a portion of the customer’s Interim NITS, described \nfurther below,  may convert to NITS while the remaining portion continues under the applicable \ninterim restrictions.  The customer therefore can use available firm capability without assuming a \nfirm entitlement to the full quantity before the system can support that service. \n \nThe FSSU process is optional and allows NITS to be combined with Interim NITS.  At \neach step, the applicable firm NITS quantity remains tied to the capability supporting that step; \nany remaining interim quantity continues to be subject to its non-firm, Interim NITS, limits.  This \ndistinction preserves the integrity of the service actually available while accommodating a \ncustomer’s phased development toward full NITS.171 \n \nFSSU provides speed to power because it enables faster integration of incremental amounts \nof Large Load using firm service or Interim NITS.  Ms. Xie explains that an FSSU request may \ninclude a firm service component and Interim NITS component, allowing a portion of the \ncustomer’s non-firm service to convert to firm service before all required Upgrades are complete, \nwith the remaining non-firm service continuing under the applicable Interim NITS operating \nlimits.172  The FSSU proposal thus provides an expeditious option to obtain firm service, at least \nin part.  \n \n \n171  Xie at 21. \n172  Id. at 20."},{"page":38,"startToken":18220,"endToken":18657,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 38 \n \nC. Interim NITS. \n \nThe interim service developed through the Flexible Large-Load Interconnections and \nTransmission Service (“FLITS”) stakeholder work is referred to here as Interim NITS.  It allows \na Transmission Customer taking NITS on behalf of a Large Load to begin receiving an approved \nquantity of non-firm service while the Network Upgrades required for full NITS are completed.  \nThe service is part of the NITS framework and uses the Attachment F NITS Service Agreement \nwith a new exhibit for the Large Load, together with a corresponding Attachment G exhibit setting \nout the additional operating criteria.173 \n \nThe customer remains on a path to full NITS rather than selecting a permanent substitute \nfor NITS.  When the required upgrades are completed and the conditions for full NITS are satisfied, \nfull NITS begins.  Where FSSU is used, the interim agreement continues to govern the portion that \nhas not yet converted to firm service. \n \nCharges for Interim NITS are determined under Schedule 9, and Interim NITS load is \ntreated as Network Load in almost all cases under the proposed design.  An increase in the interim \nload quantity is reflected in the applicable Attachment F exhibit, but updating the exhibit does not \nestablish additional system capability or authorize operation beyond the approved limit.  \nCumulative load growth of at least 25 MW requires the applicable LLPR study.174 \n \nInterim NITS is subject to non-emergency operating restrictions and curtailment when \nrequired by transmission conditions.  During a Transmission Emergency, Interim NITS is curtailed \nafter non-firm Point-to-Point service but before NITS and Firm Point-to-Point Transmission \nService, and Firm GRITS.  Interim NITS is not curtailed solely to mitigate economic congestion.  \nIts non-firm limits are tied to the transmission capability available before completion of the \nUpgrades supporting full NITS.175 \n \nFor Resource Adequacy, Interim NITS remains in the Coincident Peak Demand forecast \nand subject to the existing capacity requirements.  It consequently has the same priority as other \nLoad with Firm Transmission Service during a Capacity Emergency, subject to its separate \ntransmission limitations.  This treatment preserves capacity demand and investment signals for \nload progressing toward NITS and prevents interim non-firm transmission status from operating \nas a capacity exemption.176 \n \nThe non-firm portion does not receive Auction Revenue Rights (“ARR”) Entitlements and is \nexcluded from the applicable Peak Usage calculation.  Firm load under the associated NITS \n \n173  Xie at 7. See also MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service—Interim NITS \nOption, LLWG-2026-5 (Sept. 23, 2026), stakeholder feedback request (identifying the FLITS work as addressing \nthe Interim NITS option). \n174  Xie at 10. \n175  Id. at 19. \n176  Id. at 24."},{"page":39,"startToken":18657,"endToken":19089,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 39 \n \narrangement remains eligible under the existing rules.  Interim NITS may register as a Load \nModifying Resource (“LMR”), subject to the applicable requirements, while its non-firm portions \nare restricted from Demand Response Resource (“DRR”) and Emergency Demand Response \n(“EDR”) participation.  These distinctions preserve the relationship between the service quantity \nand the market and congestion benefits associated with firm service.177 \n \nInterim NITS directly responds to the Commission’s preliminary finding that MISO’s Tariff \nlacks transmission services reflecting Eligible Customers taking service on behalf of flexible Large \nLoads willing and able to limit their use of the transmission system under certain conditions;178 it \naligns the Interim NITS customer’s charges, curtailment priority, Resource Adequacy obligations, \nand market participation rights with its actual, interim non-firm use of the transmission system. In \naddition, Interim NITS protects existing transmission customers from undue cost shifting by \nrequiring Interim NITS Load to be billed under Schedule 9 and to remain subject to existing \nResource Adequacy requirements, and it is time-limited and structurally integrated into the \nexisting NITS framework so that it functions as a genuine bridge to full firm service rather than a \npermanent alternative. Interim NITS is not unduly discriminatory or preferential because it is \navailable on comparable terms. \n \n \nD. Reliability and rate treatment. \n \nThe service options rely on enforceable withdrawal limits.  Metering, telemetry, model \nrepresentation, communications, and operating controls provide the information and capability \nneeded to administer those limits.  The Transmission Owner determines additional control \ntechnologies or protection systems needed for the particular arrangement and for which the Large \nLoad Transmission Customer will be responsible, while MISO establishes the applicable service \nrequirements and communicates directives through the relevant parties.  A commercial agreement \nidentifying a limit does not eliminate the need to make that limit observable and enforceable in \noperations.179 \n \nThe proposed operating framework provides for remote-disconnection procedures, \napplicable unreserved-use consequences, and potential service termination when the customer \ndoes not comply with a required restriction.  Interim NITS participation as an LMR also remains \nsubject to the applicable LMR requirements and penalties.  These provisions support the different \ncurtailment priorities and protect the reliability expectations associated with firm service.  The \ncustomer’s ability to obtain non-firm service depends on accepting the limitations that define that \nservice. \n \nThe resulting differences are grounded in the rights provided.  Interim NITS remains \nassociated with full NITS and its capacity obligation while accepting transmission limits during \nthe transition.  Limiting ARR benefits to firm quantities likewise preserves the existing connection \n \n177  Id. at 25. \n178  See Show Cause Order at PP 102, 104.  \n179  Xie Testimony at 11."},{"page":40,"startToken":19089,"endToken":19558,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 40 \n \nbetween firm Transmission Service and the congestion entitlement associated with it.  MISO \nsubmits that these distinctions support just and reasonable treatment of the different service \narrangements. \n \nVI. \nLEGAL SHOWING AND RESPONSE TO THE SHOW CAUSE ORDER \n \nSection 205 requires jurisdictional rates, charges, and the practices affecting them to be \njust and reasonable and prohibits undue preferences and unreasonable differences in service.  (16 \nU.S.C.  § 824d(a)–(b)).  MISO submits the proposed revisions under that standard.  The proposals \nrespond to the Commission’s preliminary findings through the section 205 pathway expressly \ncontemplated in the Show Cause Order and the Abeyance Order.  That procedural framework \npermits MISO to bring forward developed proposals while the Commission retains authority to \naddress issues that the resulting filings do not resolve.180 \n \nThe application and study concerns are addressed by the combination of LLPR and the \nseparately submitted IRR proposal.  LLPR identifies what the customer must submit and how the \nrequested service is studied.  IRR supplies the proposed Large Load definition and requirements \nconcerning visibility and operating performance.  Their interaction connects the information used \nin planning with the load behavior required after service begins.  The agreement and operating \nprovisions then memorialize the obligations applicable to the resulting service.181 \n \nThe transmission service concerns are addressed by the additional service choices \ndescribed in Section V.  Interim NITS supplies a temporary non-firm path while the upgrades \nneeded for full NITS are completed.  FSSU allows incremental conversion where firm capability \nis available.  The applicable operating limits, capacity treatment, and charges reflect the particular \nrights accepted by the customer.  This approach implements the Commission’s recognition that \nservice can account for a load’s willingness and ability to limit its use of the system.182 \n \nThe initial availability of the new service options is directed to Large Loads within the \nscope of this filing.  MISO’s proposal focuses the service, study, modeling, and operational \nchanges on the category of load identified in the Show Cause Order.  Customers electing the same \nservice are subject to its corresponding requirements.  The focused implementation also permits \nMISO to evaluate the consequences of broader eligibility before proposing that extension.183 \n \nThe generator interconnection and associated load issues are addressed through the \ncomplementary ZGIA and LARS pathways, read with the load’s applicable Transmission Service.  \n \n180  Show Cause Order PP 33–38 (describing the response framework and the opportunity to develop section 205 \nfilings); Abeyance Order PP 8–11 (allowing the staged filings and preserving unresolved issues). \n181  Show Cause Order PP 39, 48–65 (addressing application, study, operational, and agreement provisions); IRR \nTransmittal at 1–4 (describing the proposed definition and operational requirements); Furnish Testimony at 16-\n17, 22-23. \n182  Show Cause Order PP 100–105 (addressing interim NITS, contract-demand service, and flexible load). \n183  Xie Testimony at 21."},{"page":41,"startToken":19558,"endToken":20061,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 41 \n \nZGIA addresses qualifying same-substation zero injection arrangements, while LARS coordinates \nthe study of qualifying load and associated generation.  Neither form of Interconnection Service \neliminates the separate need to identify the transmission and operating obligations of the load.  The \nproposed transmission service arrangements supply that additional part of the framework.184 \n \nThe proposed framework also respects the allocation of responsibilities between federal \nand state regulators.  The filing addresses jurisdictional Transmission Service, generator \ninterconnection, and the associated planning and operating requirements.  It does not displace state \nauthority over retail service or resource procurement and does not authorize retail arrangements \nprohibited by applicable law.  This distinction permits the transmission and interconnection \nprovisions to operate within the existing regional regulatory framework.185 \n \nMISO also submitted the July 20, 2026 Informational Report addressing resource adequacy \nand initiatives to accelerate generation additions.  That report described the roles of the states, load \nserving entities, and MISO and identified both existing reforms and proposals under development.  \nThe current filing complements those efforts by connecting the service election to the applicable \nplanning assumptions and capacity treatment; it does not equate transmission firmness with a \ndetermination that capacity has been procured for the load.186 \n \nMISO requests that the Commission consider this submission together with the related \nfilings in evaluating the response to the Show Cause Order.  The Abeyance Order provides that \ntimely section 205 filings addressing the preliminary findings suspend the filing respondents’ \nobligation to respond and continue the abeyance pending further direction.  It also preserves further \nconsideration of issues not addressed by the filings.187 \n \nA. Existing commercial arrangements and transition. \n \nParagraph 123 of the Show Cause Order asks how implementation should account for \nexisting agreements and agreements nearing execution.  The IRR filing addressed transition for \nthe reliability requirements proposed there. 188  The present application and service provisions \naccount for existing agreements and agreements nearing execution in several ways.  First, the \nLLPR process and requirements apply prospectively, with the first application deadline and LLPR \ncycle targeted for implementation date of Q1 of 2027.  Requests for transmission service to \n \n184  ZGIA Transmittal at 1–2, 6–7 (describing the proposal’s scope and the matters reserved for further work); LARS \nTransmittal at 3–6, 14–15 (describing coordinated load and generation studies and anticipated service provisions). \n185  Show Cause Order PP 42–47, 68–70 (discussing the respective federal and state responsibilities); ZGIA \nTransmittal at 22–23 (explaining that the associated-load provisions respect state restrictions on retail wheeling). \n186  Informational Report at 1–4, 6–11 (responding to the informational requirement and describing resource adequacy \ninitiatives); Show Cause Order P 122 (requiring the report). \n187  Abeyance Order PP 9–11 (describing continued abeyance and the specificity expected for a request to terminate \nthe proceeding in whole or in part). \n188  Show Cause Order P 123 (requesting briefing on implementation and protection of existing commercial \narrangements); See MISO IRR filing, Docket No. ER26-3650, IRR Trans. Ltr. at 1 (identifying transition \nprovisions for the IRR proposal)."},{"page":42,"startToken":20061,"endToken":20518,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 42 \n \naccommodate Large Loads / study the Network Upgrades that have already commenced an EPR \nstudy will remain subject to that process and the proposed Tariff revisions neither require not allow \nprojects that have already been processed through EPR or are in such process to transfer to the \nLLPR process. This respects existing commercial arrangements.  To the extent that a project has \nnot already been studied for its impacts to the Transmission System, the costs of its impacts are \nnot established and requiring such project to proceed through LLPR cannot disrupt established \nexpectations.  Moreover, the LLPR study process is sufficiently similar to the EPR process in terms \nof timing and scope that requiring nascent projects (i.e., those that have not been submitted for \nstudy and costs established) will not introduce significant new delays or unfamiliar study practices.  \nFinally, with respect to the cost recovery agreements required for projects that complete LLPR, \nMISO notes that such agreements, while imposing responsibilities on the Large Load Transmission \nCustomer, do not purport to invalidate or override any agreements that may exist between the \nentity that owns the Large Load and the Large Load Transmission Customer, or prevent more \ngranular assignment of costs by a retail regulator.189 Thus, the process appropriately prevents \ndisruption to existing commercial arrangements and those nearing completion, while still ensuring \nthat Commission goals are met prospectively.  \n \nB. Effects on regional and local planning. \n \nParagraph 124 asks how the new services affect planning, including uncertainty concerning \nthe type, location, and quantity of flexible load.  LLPR evaluates the service requested through \ncumulative models coordinated with MTEP.  Interim NITS remains associated with completion of \nthe facilities needed for full NITS.  These distinctions allow planning to reflect the service \nobligation rather than treat every maximum load quantity as an identical firm delivery \nrequirement.190 \n \nThe separate firm and non-firm representation also makes the operational consequence of \nthe planning assumption identifiable.  A customer receiving non-firm service remains bound by \nits applicable reservation and withdrawal limits; a conversion to firm service depends on the \ncapability and approval supporting that conversion.  The study and operating arrangements \ntherefore give effect to the same service election.  The separate withdrawal review for committed \nload further allows MISO to assess changes in the planning assumptions when a project does not \nproceed.191 \n \n \n \n \n \n189   While MISO’s Tariff would make the Large Load Transmission Customer responsible for costs at the level of \nthe MISO Tariff, it does not purport to prevent a Large Load Transmission Customer from recovering funds \nthrough commercial agreements with the Large Load.  \n  \n190  Show Cause Order P 124 (identifying the planning questions); Furnish Testimony at 4-5, 12-14 (describing \ncumulative models and MTEP coordination). \n191  Furnish Testimony at 15-16."},{"page":43,"startToken":20518,"endToken":20942,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 43 \n \nC. Cost recovery and financial security. \n \nIn response to Show Cause Order’s concern regarding cost shifting among transmission \ncustomers related to large loads, MISO and the MISO Transmission Owners propose the Tariff \nrevisions and pro forma LL-CRA and ITO-CRA described in Section IV.A of this transmittal.  As \nexplained above, consistent with the concerns identified by the Commission in the Show Cause \nOrder the proposed cost recovery agreements require “a specified minimum financial contribution \nand financial security sufficient to secure such contribution,” thus mitigating cost shifting if the \nLarge Load Transmission Customer ultimately takes less Transmission Service than anticipated \nbecause the Large Load does not materialize as planned or is not developed at all.192  Moreover, \nas explained above and in Mr. Gudeman’s testimony, the Tariff and pro forma agreements ensure \nthat payments made by a Large Load Transmission Customer to the Transmission Provider under \nthe agreements will be appropriately credited toward Transmission Owners’ annual transmission \nrevenue requirements in the event such costs are rolled into the Transmission Owner’s rates \nconsistent with the Commission’s cost-of-service regulations.193  Lastly, the agreements provide \nthat Transmission Owner will provide a workpaper in the annual informational filing detailing how \nany payments made pursuant to a cost recovery agreement are reflected in the Transmission \nOwner’s transmission formula rate, or not recovered from Transmission Customers, as \napplicable.194  \n \nIn response to paragraph 125, MISO proposes the LL-CRA and ITO-CRA described in \nSection IV.A as the contractual structures governing minimum cost contributions for the covered \nupgrades.  For rolled-in in-zone costs, the minimum is the Yearly Required Revenue Commitment \nsupported by the twenty-year incremental revenue calculation, with attributable transmission \nrevenues applied through the annual shortfall comparison.  For rolled-in impacted-owner costs, \nthe minimum is the specified upgrade revenue-requirement payment over the applicable term.  \nEach agreement also permits direct assignment.  The amount follows the upgrades identified for \nthe requested service and the documented customer responsibility, rather than a uniform dollar \ncharge applied to every Large Load. \n \n \nThe financial security provisions initially use upgrade capital cost, permit specified \nadjustments and reductions, and provide draw and replenishment remedies.  The construction-\nsecurity coordination provisions avoid concurrently requiring full security under both a CRA and \nthe corresponding construction agreement when compatible security can serve both.   \n \nThe pro formas do not establish a general substitution right for a retail-level agreement \nwith the end-use Large Load.  Their express coordination provisions address the separate \nconstruction agreement’s security.   \n \n \n \n192  Show Cause Order at P 84. \n193  See id. P 85. \n194  Id."},{"page":44,"startToken":20942,"endToken":21395,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 44 \n \nD. Alternative transmission technologies. \n \nParagraphs 62 and 126 address evaluation of alternative transmission technologies and the \nexplanation furnished when traditional upgrades are selected.  The LLPR application includes the \nTransmission Owner’s evaluation of alternative technologies and grid-enhancing technologies, \nand MISO reviews that information together with any further needs identified in the cumulative \nstudy.  When transmission issues arise, MISO and the Transmission Owners evaluate possible \nsolutions in the mitigation process.  The resulting study report identifies the selected transmission \nsolutions and the basis for the requested service.195 \n \nThe proposed consideration of alternatives is directed to whether a solution will satisfy the \napplicable planning criteria and provide a more efficient means of accommodating the request.   \nMISO has specifically incorporated consideration of alternative transmission technologies \n(“ATTs”) and Grid Enhancing Technologies (“GETs”) as part of the LLPR. Proposed Attachment \nFF Section I.D.1.c.iii.b.2 requires Large Load Transmission Customers to include with their \nLLLPR Application the applicable Transmission Owner’s Interconnection Study Report, \nspecifically identifying what ATTs and GETs were considered and what the outcome of that \ndetermination. Proposed Attachment FF, Section I.D.1.c.iii.e, which establishes the LLPR System \nImpact Study, specifically provides that MISO may consider alternative solutions, including those \nsubmitted by stakeholders.  These solutions will include any ATTs or GETs identified by \nstakeholders. Attachment FF, Section I.D.1.c.iii.e further provides that, in the event MISO \nidentifies any Tranmission Issues during the study, MISO will collaborate with the Transmission \nOwners on the development of solutions, specifically including ATTs and GETS.  \n \nTogether, these proposed Tariff revisions embed a requirement to consider ATTs and \nGETS in the LLPR Study process and provide opportunities for stakeholders to suggest additional \nGETS or ATTs not initially identified in the study. Because this consideration is a part of the LLPR \nstudy, the basis for the proposed solution and alternatives considered will be included in the final \nLLPR Study report.196 Because LLPR will be the required core process for evaluation of all \nrequests for Transmission Service to serve Large Loads, these requirements will apply uniformly \nto new Large Loads.  \n \nMISO’s requested acceptance of those provisions is based on the evaluation and reporting \nrequirements, rather than a customer’s ability to request consideration of an alternative outside the \ndefined study process.197 \n \n \n \n \n \n195  Show Cause Order PP 62, 126; Furnish Testimony at 13-14, 31. \n196   Furnish Testimony at 31 (explaining further that MISO will develop a standardized LLPR Study Report with \nsections that specifically address ATT/GETs considerations). \n197  Show Cause Order P 126 (addressing evaluation without a customer request, appropriate modeling, and the \nexplanation of feasibility, cost, and timing when traditional upgrades are selected)."},{"page":45,"startToken":21395,"endToken":21837,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 45 \n \nE. Generation participation and Resource Adequacy \n \nParagraph 127 addresses market participation and Resource Adequacy treatment of \ngeneration serving co-located or electrically proximate load.  The ZGIA filing proposed \nparticipation as a Generation Resource, Dispatchable Intermittent Resource, Electric Storage \nResource, or Behind the Meter Generation resource, subject to the limitation associated with \nserving the ZG Associated Load.  It also proposed registration and operating-limit provisions that \nprovide visibility into gross load and generation and constrain the resource’s participation to the \napplicable configuration.198 \n \nFor capacity, the ZGIA proposal bases accreditation on participation type and limits it by \nreference to the identified associated load, with the specified adjustment for avoided losses.  It \nprovides for use of ZG Resource credits through a Fixed Resource Adequacy Plan or Reliability \nBased Demand Curve Opt Out and restricts the use of uncleared and self-scheduled credits.  Those \nprovisions reflect the limited reach of ZG Interconnection Service and avoid treating the resource \nas though it could serve unrelated regional load.199 \n \nLARS follows a different interconnection pathway.  The filing requests Network Resource \nInterconnection Service, limits the requested interconnection service to 150 percent of the paired \nload’s peak demand, and requires the load and generation to be located in the same Local Resource \nZone.  MISO explained that these criteria connect the generation to the associated need while \nallowing different fuel types and accreditation outcomes.  The study evaluates the pair’s full \nsystem impacts using the criteria applicable to other NRIS requests.200 \n \nVII. \nDESCRIPTION OF PROPOSED TARIFF REVISIONS \n \nThe proposed revisions implement the application and service framework across the \nrelevant definitions, planning procedures, Transmission Service provisions, and agreements.  \nLLPR establishes the application requirements, study sequence, model review, study report, and \ninterfaces with MTEP and related study processes.  The corresponding defined terms and \nagreement provisions identify the request being studied, the responsible Transmission Customer, \nand the requirements applicable when the resulting service is provided.201 \n \nThe Transmission Service revisions establish the rights and conditions associated with \nInterim NITS and FSSU.  Interim NITS uses the existing Attachment F framework with the \nadditional service exhibit and corresponding Attachment G operating criteria.  The related \n \n198  Show Cause Order P 127(a)–(b) (identifying the generator participation and accreditation questions); ZGIA \nTransmittal at 17–19, 22–23 (describing market registration, operating limits, and the proposed ZG Resource \ndefinition). \n199  ZGIA Transmittal at 18–20 (describing the proposed Module E-1 accreditation, forecast identification, FRAP, Opt \nOut, and credit-use provisions). \n200  LARS Transmittal at 10–11, 13 (describing the service, pairing, and study criteria and their relationship to \nResource Adequacy). \n201  Furnish Testimony at 4, 11 (describing codification of the LLPR process)."},{"page":46,"startToken":21837,"endToken":22103,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 46 \n \nmodeling, Resource Adequacy, and ARR provisions distinguish the firm and non-firm components \nso that the same service election is reflected consistently in planning, operations, and settlements. \n \nThe marked and clean Tariff records submitted as Tab A and B respectively, set out the \nrevisions.  The following table of Tariff revisions is provided for reference and informational \npurposes only.  The language filed in the proposed Tariff revisions shall control in the event of \nany discrepancies between the information provided in this table and the proposed Tariff revisions.  \n \nTariff Section \nTariff Section Title \nBrief Description of Changes \nModule A \n \n \n \n1.B – Definitions - B \nUpdate Baseload Usage to \ninclude Firm Transmission \nService.  Update Behind the \nMeter Generation to add Interim \nNITS as a service. \n \n1.D – Definitions - D \nUpdate Demand Response \nResource, Types I and II, to \ninclude Firm Transmission \nService as an eligibility. \n \n1.F – Definitions - F \nUpdate Firm Service Step Up to \nestablish a process for evaluating \nthe reliability impact of planned \nincremental Load additions \nbefore full integration of a Large \nLoad whose planning study has \nbeen approved through MTEP. \nUpdate Firm Transmission \nService to cover Load served \nunder Firm Point-to-Point \nTransmission Service or NITS \nand exclude Load service on a \nnon-firm basis under Interim \nNITs. \n \n1.I – Definitions - I \nUpdates to Impacted \nTransmission Owner Large Load \nNetwork Upgrade(s) to cover \nupgrades outside the \nTransmission Pricing Zone \ncontaining the Large Load’s \nPoint(s) of Withdrawal that \nMISO identifies through Large \nLoad Project Review as \nnecessary for reliable service.  \nUpdate to Interim NITS to \nprovide for NITS reserved and"},{"page":47,"startToken":22103,"endToken":22321,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 47 \n \nscheduled on an as-available \nbasis and subject to curtailment \nor interruption under Section \n33.5. Updates to Interruptible \nLoad, which now deems the \nportion of a Large Load served \nunder Interim NITS to be \nInterruptible Load. \n \n1.L – Definitions - L \nUpdate to Large Load Network \nUpgrade to cover upgrades \nwithin the Transmission Pricing \nZone containing the Large \nLoad’s Point(s) of Withdrawal \nthat MISO identifies through \nLarge Load Project Review as \nnecessary for reliable service. \nUpdate to Large Load \nTransmission Customer to \ninclude a Transmission Customer \ntaking or requesting \nTransmission Service on behalf \nof a Large Load. Update to Load \nZone to clarify that a Large Load \nreceiving Interim NITS must \nrepresent its firm and non-firm \nportions as separate Load Zones \nand that neither zone may be \ncombined with other Loads.  \n \n1.N – Definitions - N \nUpdate to Network Integration \nTransmission Service to now \ninclude Interim NITS under \nExhibit 4 of Attachment F unless \nthe Tariff expressly provides \notherwise. Update to Network \nLoad to now include all portions \nof a Large Load taking Interim \nNITS under Exhibit 4 of \nAttachment F unless the Tariff \nexpressly provides otherwise. \nUpdate to Non-Firm \nTransmission Service to cover \nLoad served under Non-Firm \nPoint-To-Point Transmission \nService or Interim NITS under \nExhibit 4 of Attachment F."},{"page":48,"startToken":22321,"endToken":22559,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 48 \n \n \n1.P – Definitions - P \nUpdate to Peak Usage to exclude \nthe Interim NITS portion of a \nLarge Load from the forecast \nNITS peak used to calculate Peak \nUsage for ARR allocation. Load \nassociated with a Firm Service \nStep Up request enters the \ncalculation only after all \nassociated upgrades are \ncomplete. \n \n1.T – Definitions - T \nUpdate to Total Forecast Peak \nLoad to excludes Load served \nthrough Interim NITS from the \nforecast NITS peak. It also \nexcludes Load associated with a \nLarge Load’s Firm Service Step \nUp request until all associated \nupgrades are complete. \n \n2.2 – Reservation Priority For Existing \nFirm Transmission Service \nSection 2.2 replaces references to \n“firm service” customers with \nreferences to customers taking \nthe newly defined “Firm \nTransmission Service.” This ties \nrollover priority and the right of \nfirst refusal to qualifying firm \nservice and excludes the non-\nfirm portion of Interim NITS. \nModule B \n \n \n \nI. Introduction \nProvides that a Large Load \nTransmission Customer must \nsubmit an application for LLPR \nreview for Transmission Service \nto serve a Large Load as \ndescribed in Attachment FF. \n \nIII. Network Integration Transmission \nService \nProvides that the rates, terms, \nand conditions governing \nNetwork Integration \nTransmission Service will \ngenerally apply to Interim NITS.  \n \n28.1 – Scope of Service \nProvides that the Large Load \nTransmission Customer taking \nInterim NITS must coordinate \nwith the applicable Transmission \nOwner to establish a Commercial \nPricing Node associated with the"},{"page":49,"startToken":22559,"endToken":22811,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 49 \n \nNITS service and a Commercial \nPricing Node associated with \nInterim NITS service. \n \n28.3 – Network Integration Transmission \nService \nProposes revisions to clarify that \nthe Transmission Provider and, \nas applicable, ITC will provide \nNetwork Integration \nTransmission Service, rather than \nFirm Transmission Service. \n \n29.1 – Condition Precedent for Receiving \nService \nProposes a new framework for a \nLarge Load Transmission \nCustomer to take Interim NITs \nand requiring that customer to \nidentify the Load that will \nqualify for Firm Transmission \nService and the amount of Load \nqualifying for Non-Firm \nTransmission Service. \n \n29.3 – Arrangements to be Completed \nPrior to Service \nProposes revisions to clarify \nwhen Firm Network Integration \nTransmission Service and \nInterim NITS will commence.   \n \n30.8 – Use of Interface Capacity by the \nNetwork Customer \nAdds a provision such that the \nuse of Interface capacity to \nservice the portion of a Network \nCustomer’s Network Load \nserved under Interim NITS shall \nbe on an as-available basis and \nsubject to all limitations, \nCurtailment, and Interruption \nprovisions, and that inclusion of \nsuch Load in the Load-based \nusage limit does not confer a \nright to firm use of Interface \ncapacity to serve that portion of \nLoad. \n \n31.1 – Network Load \nProvides that Network Load will \ninclude all portions of a Large \nLoad served on a non-firm basis, \nunless provided otherwise. \n \n31.5 – Changes in Service Requests \nProvides that a Large Load \nTransmission Customer is \nlimited to one request to defer the \nstart of the Network Integration \nTransmission Service up to a"},{"page":50,"startToken":22811,"endToken":23032,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 50 \n \nperiod of 90 days.  Further \nprovides that, if the Large Load \ndoes not commence operations or \nfails to operate at the approved \nlevel within 90 days of the \nrequested Service \nCommencement Date, the \nTransmission Provider may \nrevoke the approval for the \namount of Network Integration \nTransmission Service that failed \nto begin operation.  Further \nprovides that the Large Load \nTransmission Customer is not \nrelieved of its obligation to pay \nthe costs of the transmission \nfacilities caused to be \nconstructed. \n \n31.7 – Deferral of Service to Large Loads \nNew section proposing the \ndeferral of service to Large \nLoads until the construction of \nnew transmission facilities is \ncompleted.  Provides that the \nLarge Load Transmission \nCustomer may request Interim \nNITS for the portion of any \ndeferred service, which the \nTransmission Provider may defer \nif it determines that providing \nservice would impair existing \nFirm Transmission Service. \n \n31.8 – Excess Withdrawal \nNew section proposing that the \nLarge Load Transmission \nCustomer may not schedule the \ndelivery of Energy to a Large \nLoad in excess of the Firm \nTransmission Service that has \nbeen approved for the Load \nadditions in the intervening step-\nup period, and that any \nwithdrawal in excess of the \napproved limit will be subject to \ncharges and penalties.  Further \nprovides that a Large Load \nTransmission Customer taking"},{"page":51,"startToken":23032,"endToken":23258,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 51 \n \nInterim NITS may not schedule \ndelivery of Energy to a Large \nLoad in excess of the aggregate \nlevel of Firm Transmission \nService and Non-Firm \nTransmission Service. \n \n33.5 – Allocation of Curtailments \nProposes that Interim NITS will \nhave a lower priority than (i) \nFirm Transmission Service and \n(ii) Transmission Service from \nResources other than designated \nNetwork Resources for Network \nCustomers not served under \nInterim NITS.  Among \ntransactions under Interim NITS, \nCurtailments or Interruptions will \nbegin with the Large Load with \nthe most recent Service \nCommencement Date. \n \n33.7 – System Reliability \nProposes that the Transmission \nProvider will be able to curtail \nInterim NITS service for \nreliability reasons and \nimplements penalties if the Large \nLoad Transmission Customers \nfails to cease or reduce service in \nresponse to such a directive.  If \nthe Large Load Customer fails to \ncease or reduce service on two \nseparate occasions within a 365-\nday period, Interim NITS shall be \npermanently terminated.   \nModule C \n \n \n \n38.5 – Load Aggregation \nProvides for limits on Load \naggregation and clarifies each \nLarge Load must be represented \nby a single Commercial Pricing \nNode and may not be aggregated \nor included in a Load Zone with \nother Commercial Pricing Nodes.  \nFurther provides that a Large \nLoad taking both Firm and Non-\nFirm Transmission Service will \nhave separate Commercial \nPricing Nodes for each service,"},{"page":52,"startToken":23258,"endToken":23516,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 52 \n \nwith Actual Energy Withdrawal \nfirst associated with the \nCommercial Pricing Node for \nFirm Transmission Service.  \nFurther provides that the \nTransmission Provider will \nmaintain a list of defined \nElemental Pricing Nodes that \ncomprise a Large Load. \n \n38.6 – Aggregators of Retail Customers \nProvides that ARC registration \nwill require an attestation by the \nARC that no part of the DRR, \nLMR, or EDU is served through \nInterim NITS.  Further provides \nthat for each Large Load \nregistered by an ARC, the Large \nLoad Transmission Customer \nmust certify that the DRR, LMR, \nor EDR is being registered at a \nmaximum Demand that is less \nthan or equal to the total amount \nof Firm Transmission Service \nprovided to the Large Load.  \nProvides that a Large Load being \nregistered by an ARC may not be \nincluded in an aggregation of \nother Loads.  \n \n38.7.2 – Demand Response Resource \nProcedures \nProvides that only the portion of \na Large Load served by Firm \nTransmission Service may \nregister as a Demand Response \nResource, and that the Market \nParticipant must demonstrate that \nthe portion of any Large Load \nbeing registered as a Demand \nResponse Resource has Firm \nTransmission Service. \n \n42.6 – Partial-Year FTR Allocation \nProcess for New ARR Zone(s) \nProposes revisions to exclude the \nportion of a Large Load taking \nInterim NITS from Partial-Year \nFTR Allocation processes.  \n \n43.2.4 – Nomination and Allocation of \nARRs and MTPS ARRs \nProposes revisions throughout \nthe section to exclude the portion \nof a Large Load taking Interim \nNITS from the nomination and"},{"page":53,"startToken":23516,"endToken":23731,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 53 \n \nallocation stages for Network \nIntegration Transmission \nService.  \nAttachments \n \n \nAttachment F \nForm of Service Agreement For Network \nService \nNew Exhibit 2 adds transaction \nspecification sheet for Large \nLoad NITS that records the \nrequested service, start date, and \nrequired upgrades.  It also \nconfirms that any local \nTransmission Owner operating \nrequirements apply in addition to \nthe applicable Tariff \nrequirements, including Section \n37A. \n \nNew Exhibit 3 adds a transaction \nspecification sheet for Firm \nService Step Up that records the \nfirm service level, start date, and \nrequired upgrades for each \nincrement. Exhibit 4 adds a \nseparate sheet for Interim NITS \nthat records firm and non-firm \nservice levels and the start and \nend dates for each transaction. \nAttachment G \nForm of Network Operating Agreement \nfor Network Service \nSections 3.0–5.0 set separate \ncommencement rules for firm \nNITS and Interim NITS. Firm \nNITS commencement is tied to \ncompletion of the facilities and \nupgrades required for the \napplicable service, while Interim \nNITS requires MISO approval \nunder new Exhibit F. The \nagreement also provides for \nservice to end on a mutually \nagreed date or the transaction \ntermination date. \n \nNew Exhibit F allows non-firm \nLarge Load identified in the Firm \nService Step Up study to operate \nunder Interim NITS before \nrequired upgrades are complete,"},{"page":54,"startToken":23731,"endToken":23931,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 54 \n \nsubject to Section 37A. MISO \nmay curtail that service for \nreliability or operational reasons \nunder Module B. \nAttachment FF \nTransmission Expansion Planning \nProtocol \nSection I.D.1.c establishes the \nLLPR process for new loads of \n50 MW or more and existing \nloads increasing by at least 25 \nMW in the aggregate. It provides \nfor three study cycles per year \nand sets out application \nrequirements, deficiency and \ncure procedures, model \ndevelopment, system impact \nstudies, and stakeholder review. \n \nSection I.D.1.c also establishes \nhow MISO tenders the final \nstudy report and applicable cost \nrecovery agreements under \nAttachments LLL and MMM. It \nspecifies when upgrades are \ndeemed approved for MTEP \npurposes, requires customer \nsecurity for in-zone and out-of-\nzone upgrades, and requires \nMISO to post proposed load \nadditions, planned upgrades, and \nestimated costs in a searchable, \nfilterable format. \n \nSection I.D.3 establishes the \nFirm Service Step Up study \nprocess for incremental service \nbefore full Large Load \nintegration. It limits \ncommencement to one \nincremental block per year and \nsets separate eligibility timing for \nfirm NITS and Interim NITS. \nBoth forms of incremental \nservice end when service for the \nfull Load begins."},{"page":55,"startToken":23931,"endToken":24153,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 55 \n \nAttachments FF-9, FF-10, and \nFF-11 add the Large Load \nTransmission Customer \nattestation, the LLPR System \nImpact Study Agreement, and the \nCritical Energy Infrastructure \nInformation nondisclosure \nagreement, respectively. \n \nI.D.1.c – Large Load Transmission \nService \nProposes a new framework for \nTransmission Service to Large \nLoads including the Large Load \nProject Review (LLPR) process.  \n \nI.D.1.c.i – Definitions \nAdds definitions for Large Load \nNetwork Upgrade(s), Impacted \nTransmission Owner Large Load \nNetwork Upgrade(s), the Large \nLoad Cost Recovery Agreement \n(LL-CRA, Attachment LLL), and \nthe Large Load Impacted \nTransmission Owner Cost \nRecovery Agreement (LLITO-\nCRA, Attachment MMM).  \n \nI.D.1.c.ii – Large Load Project Review \nProcess Scope and Application \nEstablishes a Large Load \nApplication where different \nservice options may be selected \n(LLPR, FSSU, Interim NITS, or \nLARS).  \n \nI.D.1.c.iii – Large Load Project Review  \nProvides for MISO to \nindependently review the \nreliability impacts of Large \nLoads that require upgrades, in \ncollaboration with the \nTransmission Owner(s) and \nLarge Load Transmission \nCustomer, with any system \nmodifications presented through \nMTEP.  \n \nTriannual Studies \nRequires LLPR studies three \ntimes in a 365-day period with \napplication deadlines posted at \nleast 90 calendar days in \nadvance. Late applications will \nbe reviewed in the next cycle.  \n \nRequirements for LLPR Processing \nIdentifies the application \nrequirements including: data,"},{"page":56,"startToken":24153,"endToken":24382,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 56 \n \nstudy files, reports, an attestation, \nnon-refundable application fee,  \nrelevant study deposits, and \nconfidentiality agreements.   \n \nReview and Cure of Application \nDeficiencies \nSets out the period of time that \nMISO has to review and identify \ndeficiencies in the Large Load \nApplication and defines the \nperiod of time the Large Load \nTransmission Customer has to \ncure any deficiencies.  \n \nModel Build Period \nRequires LLPR models to be \nbuilt from the latest MTEP cases, \nwith specific comment windows \nand a target of completing within \n30 calendar days after the cure \nperiod.  \n \nThe LLPR System Impact Study \nDefines the scope of the study, \nthe posting of applications, and \ndeadlines for Transmission \nOwners to propose solutions \n(including ATTs/GETs); \napplications are withdrawn if \nissues remain unresolved. Also \nprovides for the draft and final \nLLPR Study Reports and tender \nof the LL-CRA/LLITO-CRA.  \n \nResubmission of Large Load Applications \nand Removed Projects \nAllows a Large Load \nTransmission Customer whose \napplication was removed to \nresubmit in a future LLPR study \ncycle after identifying what has \nchanged.  \n \nStakeholder Forums \nRequires MISO to host \nstakeholder forums at least three \ntimes per year, followed by \ncomment periods. Projects are \ndeemed approved once the LL-\nCRA and/or LLITO-CRA is \nexecuted or if unexecuted or non-\nconforming, filed with the \nCommission, and the \nTransmission Owner must make \na good faith effort to implement \nthem."},{"page":57,"startToken":24382,"endToken":24617,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 57 \n \n \nPro Forma LL-CRA and LLITO-CRA \nRequires a Large Load \nTransmission Customer to enter \ninto a LL-CRA and/or LLITO-\nCRA listing the required Large \nLoad Network Upgrades, to limit \ncost shifting, and reduce \nspeculative requests. The \ncustomer remains responsible for \nall applicable Transmission \nService charges.  \n \nLarge Load Cost Recovery Agreement \nImposes Minimum Contribution \nfor the Large Load Network \nUpgrades. Also requires security \nequal to the estimated upgrade \ncosts.  \n \nLarge Load Impacted Transmission \nOwner Cost Recovery Agreement  \nRequires a separate LLITO-CRA \nwith each affected Transmission \nOwner, under which the Large \nLoad Transmission Customer is \nresponsible for a Minimum \nContribution for ITO-Large Load \nNetwork Upgrades and security \nto cover those upgrades.  \n \nTender and Execution of the Cost \nAgreement \nGives the parties 15 business \ndays to execute the tendered LL-\nCRA/LLITO-CRA or request an \nunexecuted or non-conforming \nfiling with the Commission; if \nthey do neither, then the Large \nLoad Application is deemed \nwithdrawn and the project is \nremoved from the LLPR process.  \n \nI.D.1.c.iv – Operations Agreement and \nConfidentiality of LLPR Information  \nRequires an updated load \nforecast and a NITS application \nunder Module B, Section 29.2 \nbefore service begins. Also \nrequires the parties to keep non-\npublic LLPR information \nconfidential under MISO’s \nuniversal NDAs.  \nAttachment \nFF-9 \nLarge Load Project Review Attestation \nForm \n New Tariff attachment \nAttachment \nFF-10 \nLLPR System Impact Study Agreement \n New Tariff attachment"},{"page":58,"startToken":24617,"endToken":25029,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 58 \n \nAttachment \nFF-11 \nLLPR Critical Energy Infrastructure \nInformation NDA \n New Tariff attachment \nAttachment \nLLL \nForm of Agreement for Large Load Cost \nRecovery Agreement \n New Tariff attachment \nAttachment \nMMM \nLarge Load Impacted TO Cost Recovery \nAgreement \n New Tariff attachment \n \n \nVIII. \nSTAKEHOLDER ENGAGEMENT \n \nMISO developed the Large Load proposals described herein through an iterative \nstakeholder process that began before issuance of the Show Cause Order.  EPR improvements and \ncoordination of load and generator studies were discussed through the Planning Advisory \nCommittee and Planning Subcommittee during 2024 and 2025.  ZGIA was introduced in \nDecember 2025 and developed through a subsequent planning committee and LLWG discussions.  \nThe LLWG then provided a dedicated forum for the planning, operations, markets, and Resource \nAdequacy questions implicated by Large Load integration.202 \n \nThe process included presentation of concepts, circulation of draft Tariff language, written \nfeedback, and further revisions.  For example, the LARS proposal evolved from an initial 250 MW \nthreshold to the 200 MW threshold filed with the Commission following stakeholder feedback.  \nMISO also revised the proposed treatment of multiple generating facilities and contractual \narrangements and clarified the representation of the load-generation pair.  These changes illustrate \nthe relationship between the stakeholder process and the proposals brought forward in the staged \nfilings.203 \n \nThe LLPR application and transmission service proposals continued and were developed \nthrough that process.  At the September 23, 2026, LLWG meeting, MISO reviewed the LLPR and \nidentified the posted draft Tariff language, inviting feedback on the process and the proposed \nprovisions.  MISO also presented the Interim NITS (initially presented as “FLITS”) option and \nsought feedback on its design.  Stakeholder comments addressed study readiness and timing, \nplanning coordination, service limits, curtailment, and the transition to firm service.  These issues \ninformed the continuing work on the relationship among the application, study, and operating \nprovisions.204 \n \n \n202  ZGIA Transmittal at 45–46 (describing EPR, coordinated study, and ZGIA discussions); LARS Transmittal at 49–\n50 (describing the LLWG’s role and early work plan). \n203  LARS Transmittal at 50–52 (describing the July, August, and September discussions and the resulting changes to \nthe proposal). \n204  MISO, LLWG, Application and Study Process Tariff and Process Design, LLWG-2026-7 (Sept. 23, 2026), \nfeedback request and comments posted Oct. 7–8, 2026 (identifying the draft LLPR review and stakeholder issues); \nMISO, LLWG, Flexible Large-Load Interconnections and Transmission Service—Interim NITS Option, LLWG-\n2026-5 (Sept. 23, 2026), feedback request and comments posted Oct. 2, 2026 (addressing the interim service \ndesign)."},{"page":59,"startToken":25029,"endToken":25301,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 59 \n \nMISO’s development of the present filing also reflects the need to coordinate the proposals \nwith the earlier submissions.  The same load information and reliability assumptions must support \nthe study process, the service election, and the operating agreement.  Stakeholder consideration of \nthose interfaces has therefore proceeded alongside development of the individual service and study \nprovisions.205 \n \nThroughout the stakeholder process, MISO solicited feedback on what approach should be \napplied to developing processes and ensuring stakeholder protections.  MISO proposed, accepted \nfeedback from stakeholders, and significantly modified many aspects of the Large Load effort.  As \ndiscussed below, some of the stakeholder process may be summarized in three categories: (1) cost \ntransparency and recovery; (2) LLPR; and (3) Interim NITS. \n \n \nA. Cost Transparency and Recovery \n \nIn the initial LLWG meeting, MISO identified cost efficiency as one of twelve \nconsiderations governing large-load integration.206  Stakeholder feedback proposed including cost \nallocation within cost efficiency or treating it as an additional consideration.207  MISO agreed to \nwork with stakeholders to define solutions that fit within MISO’s scope. \n \nAs previously discussed, throughout January and May of 2026, stakeholders raised cost \ntransparency concerns while MISO concentrated on reliability requirements and expedited \n \n205  Abeyance Motion at 8–13 (explaining the need to align individual solutions with one another and existing MISO \nprocedures); Abeyance Order P 8 (recognizing the opportunity for region-specific stakeholder solutions). \n206  Available at: \nhttps://cdn.misoenergy.org/20260130%20Large%20Load%20Workshop%20Presentation738349.pdf at 12. \n207  Available at: \nhttps://cdn.misoenergy.org/MISO%20Response%20to%20Large%20Load%20Workshop%20Considerations%2\n0and%20Outcomes%20of%20Large%20Load%20Additions746069.pdf at 4, 13."},{"page":60,"startToken":25301,"endToken":25731,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 60 \n \ninterconnection processes.208  In June, the Show Cause Order identified deficiencies in MISO’s \nTariff concerning cost transparency and protections against cost shifting, but the Show Cause \nOrder was clear that it was not intended to disturb existing regional cost-allocation methods.209 \n \nIn response to early stakeholder feedback and the Show Cause Order, MISO presented \nLLWG-2026-8 during the August 27, 2026 LLWG meeting to address an approach to address \nissues related to cost efficiency, transparency, and allocation.210  The issue covered a mechanism \nto mitigate the risk of cost shifting among transmission customers, Tariff updates to create a public \ndata platform that provides transparency to state and local stakeholders regarding the assignment \nof Network Upgrades and their associated costs. Stakeholder feedback requested more information \nthat estimated project costs.  MISO committed to developing a dashboard and pro forma recovery \nagreement while continuing to work to develop the minimum contribution formula.211 \n \nAt the September 9, 2026, LLWG meeting, MISO previewed the public dashboard intended \nto identify network upgrades associated with large load transmission service.212 Stakeholders \ngenerally supported the dashboard but some suggested additional measures were needed to prevent \ncost shifting.213 \n \nAt the September 23, 2026, LLWG meeting, MISO introduced a conceptual pro forma cost \nrecovery agreement.214  MISO also illustrated how additional large load transmission revenue \ncould offset upgrade costs and how a supplemental payment might protect existing customers if \nrevenue were insufficient.  \n \nAt the October 8, 2026, LLWG meeting, MISO provided additional details regarding the \nproposed pro forma cost recovery agreement, including the calculation of minimum.  MISO also \naddressed the role of financial security and the treatment of payments through Transmission Owner \nannual informational filings.  Stakeholder feedback sought additional clarification regarding the \n \n208  Available at: https://cdn.misoenergy.org/20260420%20LLWG%20Item%2001b%20Agenda750857.pdf; \nhttps://cdn.misoenergy.org/20260514%20LLWG%20Item%2001b%20Agenda756827.pdf. \n209  Show Cause Order at P 82. \n210  Available at : https://cdn.misoenergy.org/New%20Issue%20-\n%20Cost%20Shifting%20Risk%20Among%20Transmission%20Customers776496.pdf. \n211  Available at: \nhttps://cdn.misoenergy.org/LLWG%20Cost%20Transparency%20and%20Cost%20Shifting%20Response%20(\nLLWG-2026-8)%20(20260827)786923.pdf. \n212  Available at: \nhttps://cdn.misoenergy.org/20260909%20LLWG%20Item%2005%20Cost%20Shifting%20Risk%20Among%2\n0Tx%20Customers%20Cost%20Transparency%20(LLWG-2026-8)779833.pdf. \n213  Available at: \nhttps://cdn.misoenergy.org/LLWG%20Cost%20Shifting%20Risk%20Among%20Transmission%20Customers-\nCost%20Transparency%20Response%20(LLWG-2026-8)%20(20260909)789797.pdf. \n214  Available at: \nhttps://cdn.misoenergy.org/20260923%20LLWG%20Item%2005%20Cost%20Shifting%20Risk%20Among%2\n0Transmission%20Customers%20(LLWG-2026-8)783359.pdf at 5-10."},{"page":61,"startToken":25731,"endToken":26141,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 61 \n \ncalculation of the minimum contribution, the treatment of network upgrade costs, financial security \nrequirements, and the interaction between the proposed agreement and existing transmission \nrates.215 \n \nAt the October 29, 2026 LLWG, meeting, specifically, in response to earlier feedback, \nMISO and the Transmission Owners clarified that the Large Load Transmission Customer is \nalways responsible for the costs of the Large Load Upgrade(s) to mitigate the cost shifts to other \nTransmission Customers and changed the amount of financial security to be the capital cost of the \nLarge Load Upgrade(s).  MISO also described how it will provide transparency through a \ncombination of the outputs from the Large Load Project Review, the pro forma cost recovery \nagreement, Transmission Owner annual informational filings, and a transparency dashboard.216  \nMISO revised payments to be prorated for staggered upgrade in service dates and addressed \nseparated agreements for impacted Transmission Owners outside the relevant transmission pricing \nzone.  Additionally, the revised dashboard added Project Description and Cost Shared Status fields.  \nOther updates in response to stakeholder feedback include the financial security holder, security \namounts, security forms, and cost updates.  Feedback is now complete but suggests that the \nrevisions addressed some stakeholder concerns.217 \n \nB. LLPR \n \nAt the August 27, 2026, LLWG meeting, MISO proposed a new Large Load Project \nReview (“LLPR”) process to integrate requirements from the Show Cause Order, incorporate \nenhancements from broader large-load efforts, and preserve the core functions of reliable \nintegration.218  The initial design called for quarterly study cycles, cumulative MTEP studies, and \ncontinued monthly stakeholder meetings.  Stakeholder feedback expressed concerns about \ncommercial confidentiality and premature contract commitments.219 \n \nAt the September 23, 2026, LLWG meeting, MISO proposed a refined approach after \nreceiving stakeholder feedback, including replacing the Electric Service Agreement with an \n \n215  Available at: \nhttps://cdn.misoenergy.org/20261008%20LLWG%20Item%2004%20Cost%20Shifting%20Show%20Cause%20\n%28LLWG-2026-8%29786862.pdf⁠ at 4–8; https://www.misoenergy.org/engage/stakeholder-\nfeedback/2026/llwg-cost-shifting-risk-pro-forma-cost-recovery-agreement-llwg-2026-8-20261008/⁠. \n216  Available at: \nhttps://cdn.misoenergy.org/20261029%20LLWG%20Item%2004%20Cost%20Shifting%20Risk%20Among%2\n0Transmission%20Customers%20(LLWG-2026-8)791917.pdf at 2. \n217  Available at: https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-cost-shifting-risk-among-\ntransmission-customers-llwg-2026-8-20261029/. \n218  Available at: \nhttps://cdn.misoenergy.org/20260827%20LLWG%20Item%2005%20Large%20Load%20Application%20and%\n20Study%20Process%20(LLWG-2026-7)777233.pdf. \n219  Available at: \nhttps://cdn.misoenergy.org/LLWG%20Large%20Load%20Application%20and%20Study%20Process%20Respo\nnse%20(LLWG-2026-7)%20(20260827)786659.pdf."},{"page":62,"startToken":26141,"endToken":26543,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 62 \n \nattestation, tailoring studies to the type of transmission service requested, preserving the EPR for \nother projects, and proposed Tariff language.220   MISO also committed to a standardized report \ncovering assumptions, upgrades, costs, schedules, and Advanced Transmission Technologies and \nGrid-Enhancing Technologies.221  \n \nAt the October 29, 2026, LLWG meeting, MISO presented a final LLPR process with \napplication.  The LLPR included application, study, mitigation, reporting, and approval \nframeworks, as well as three annual study cycles, expanded readiness requirements and draft Tariff \nrevisions.222 \n \nC. Interim NITS \n \nMISO’s development of Firm Service Step-Up (“FSSU”) and Flexible Large-Load Interim \nTransmission Service, which was initially referred to as FLITS but is herein referred to as Interim \nNITS, reflects two related efforts to allow large loads to receive power which can be reliably \ntransmitted before all transmission upgrades needed for full firm service are completed.  The two \nproposals developed separately but became interconnected as MISO responded to stakeholder \nfeedback and the Show Cause Order. \n \nIn April 2026, MISO recommended the Firm Service Step-Up initiative for consideration \nby the LLWG.223  At the April 20, 2026, LLWG meeting, MISO proposed a process to evaluate \nand grant firm service for partial load interconnection.224  The initial proposal was for a phased \nfirm-service.  Feedback indicated that stakeholders generally supported a process to assess and \ngrant firm service to facilitate the timely interconnection in large loads, but some pointed to a need \nfor flexibility in how service level was granted.225  Other feedback opposed annual only studies, \nand some raised the possibility of non-firm service for a facility that might want some flexible load \nindefinitely.  The feedback established a need for multiple incremental steps and more flexible \n \n220  Available at: \nhttps://cdn.misoenergy.org/20260923%20LLWG%20Item%2004%20Tariff%20Defined%20Application%20an\nd%20Study%20Process%20(LLWG-2026-7)782743.pdf. \n221  Available at: \nhttps://cdn.misoenergy.org/LLWG%20Application%20and%20Study%20Process%20Tariff%20and%20Process\n%20Design%20Response%20(LLWG-2026-7)%20(20260923)791576.pdf. \n222   Available at: \nhttps://cdn.misoenergy.org/20261029%20LLWG%20Item%2006%20Large%20Load%20Application%20and%\n20Study%20Process%20(LLWG-2026-7)791445.pdf. \n223  Available at: https://www.misoenergy.org/engage/MISO-Dashboard/firm-service-step-up-for-large-load-\ninterconnections/. \n224  Available at: \nhttps://cdn.misoenergy.org/20260420%20LLWG%20Item%2008%20Firm%20Service%20Step%20Up%20Ove\nrview751418.pdf. \n225  Available at: \nhttps://cdn.misoenergy.org/MISO%20Feedback%20Response%20Firm%20Service%20Step%20Up%20(LLWG\n-2026-1)%20(20260420)760062.pdf."},{"page":63,"startToken":26543,"endToken":26988,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 63 \n \nservice timing, and MISO committed to developing further details in the process to provide clarity \nat the June LLWG. \n \nAt the June 10, 2026, LLWG meeting MISO presented further details on the Firm Service \nStep Up process.226  MISO proposed quarterly study opportunities to identify how much firm load \ncould be served reliability before all necessary upgrades were complete.227 MISO’s proposed \nprocess was more defined.  It now allowed requests through Transmission Owner and Load \nServing Entity coordination following MTEP approval, the ability to request several incremental \nload blocks, and a 36-month horizon.  Feedback also indicated that MISO had largely responded \nto the need for more frequent studies and multiple steps but was adapting the proposal for \nupcoming stakeholder meetings.  Some stakeholders expressed concern whether requested in-\nservice dates could distort priority. \n \nAt the July 16, 2026, LLWG meeting, MISO presented a refined FSSU process and initial \nTariff language.228  A Bridge Interim Transmission Service Proposal was also presented by a \nstakeholder.229  MISO proposed to update the FSSU process and proposed to clarify terminology, \ndefine the step-up period, and adopt additional requirements.  The proposed Tariff language \nrestricted requested load blocks to a minimum 25 MW step, limited to the number of network \nupgrade projects associated with the original full load integration study.  MISO proposed a 36-\nmonth request horizon, and limits on additional upgrades and restudies.  Stakeholder feedback \nfocused on provisions to correct terminology, a timing requirement for transmission service \nrequests, and limiting incremental load blocks on an annual basis. \n \nAt the August 12, 2026, LLWG meeting, MISO reviewed the initial proposal for a \nframework for Non-Firm Transmission Service for Large Loads called Flexible Large-load \nInterconnection and Transmission Service (FLITS).230  FLITS was proposed as a non-firm \ntransmission service option for large loads, usable either temporarily while upgrades were \ncompleted or on a more permanent basis.  The proposal contemplated separate interim and \npermanent non-firm transmission service and worked alongside existing NITS and FSSU \narrangements. MISO received a variety of feedback, though most stakeholders desired to see non-\n \n226  Available at: \nhttps://cdn.misoenergy.org/20260610%20LLWG%20Item%2007%20Firm%20Service%20Step%20Up%20Stud\ny%20Process763098.pdf. \n227  Available at: \nhttps://cdn.misoenergy.org/LLWG%20Large%20Load%20Firm%20Service%20Step%20Up%20Approach%20\nResponse%20(LLWG-2026-1)%20(20260610)769664.pdf. \n228  Available at: \nhttps://cdn.misoenergy.org/20260716%20LLWG%20Item%2008%20Firm%20Service%20Step%20Up%20Stud\ny%20Process768776.pdf. \n229  Available at: \nhttps://cdn.misoenergy.org/20260716%20LLWG%20Item%2007c%20BITS%20Proposal_Alliant%20Energy76\n8542.pdf. \n230  Available at: https://cdn.misoenergy.org/20260812%20LLWG%20Item%2006%20Conditional%20Non-\nFirm%20Transmission%20Service%20(LLWG-2026-5)774185.pdf."},{"page":64,"startToken":26988,"endToken":27393,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 64 \n \nfirm large load included in the Coincident Peak Demand forecast.  Others raised concerns over \ncongestion prices, cost shifting, curtailment priority and other issues. \n \nAt the August 27, 2026, LLWG meeting, MISO proposed revised Tariff language for the \nFSSU process.  In response to stakeholder feedback, MISO included terminology corrections, \nclarifications of requirements, limiting number of steps on an annual basis, and new requirements \nfor submitting transmission service and load forecasts.  \n \nOn September 9, 2026, LLWG meeting, MISO posted a summary of stakeholder feedback \ntaken into consideration to improve the design for non-firm Transmission Service.231  MISO \nreported that 12 respondents, including the OMS, supported including non-firm load in capacity-\ndemand forecasts, compared with two favoring exclusion and four requesting further discussion. \nMISO also corrected an error in its August presentation regarding settlement modeling.  MISO \nreported receiving 23 submissions and made several other identifiable changes.  \n \nIncorporating this feedback, MISO also presented at the September 9, 2026, LLWG \nmeeting, where MISO proposed changes to FLITS in response to stakeholder feedback.232  In \nresponse to feedback, MISO split the concept into interim FLITS and permanent Contract Demand, \nincluded all load in the Coincident Peak Demand forecast, removed the fixed ramp rate and \nrequired curtailment in a time specified by MISO. \n \nAt the September 23, 2026, LLWG meeting, MISO presented changes to the FLITS \nproposal.233  MISO revised ARR entitlements to no longer be granted to the non-firm portion of \nthe load and did not propose special rules for large loads in the Resource Adequacy construct.  \nMISO also announced that it continued to develop a permanent non-firm Transmission Service \noption. \n \nMISO responded to stakeholder feedback by revising Attachment FF provisions for clarity, \ncorrecting redundant sections, and reorganizing provisions related to transmission service.234 \nMISO also stated that BPM language was being developed to describe the study process and \ncriteria details at the implementation level.  \n \n \n231  Available at: https://cdn.misoenergy.org/Flexible%20Large-\nLoad%20Interconnection%20and%20Transmission%20Service%20(FLITS)%20Response%20(LLWG-2026-\n5)780398.pdf. \n232   Available at: \nhttps://cdn.misoenergy.org/20260909%20LLWG%20Item%2006%20Non%20Firm%20Large%20Load%20(LL\nWG-2026-5)780125.pdf. \n233  Available at: https://cdn.misoenergy.org/20260923%20LLWG%20Item%2007%20Conditional%20Non-\nFirm%20Transmission%20Service%20(LLWG-2026-5)783425.pdf. \n234  Available at: \nhttps://cdn.misoenergy.org/LLWG%20Firm%20Service%20Step%20Up%20for%20Large%20Load%20Interco\nnnections%20Tariff%20Response%20(LLWG-2026-1)%20(20260923)792368.pdf."},{"page":65,"startToken":27393,"endToken":27788,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 65 \n \nAt the October 29, 2026, LLWG meeting, MISO presented proposed revisions to BPM-\n020 addressing the FSSU study process, including study parameters, evaluation criteria, Interim \nNetwork Integration Transmission Service, and Qualified Changes.  MISO also presented \nrevisions to the LLPR framework, including application requirements, study timelines, reliability \nassessments, identification of Network Upgrades, and coordination with Transmission Owners. \nMISO requested additional stakeholder feedback on both proposals to further refine the \nprocesses and implementation procedures.  \n \nIX. \nDOCUMENTS SUBMITTED IN THIS FILING \n \nIn addition to this Transmittal Letter, this submission includes the following materials, with \nthe final tab and exhibit designations identified in the filing index: \n \nTab A – Redline Tariff235 \n \nTab B – Clean Tariff \n \nTab C – Testimony of Jeanna Furnish \n \nTab D – Testimony of Zhaoxia Xie \n \nTab E – Testimony and Exhibits of Greg M. Gudeman  \n \nTab F – Show Cause Order Briefing Questions and Answers \n \n \nX. \nEFFECTIVE DATE AND REQUEST FOR WAIVER \n   \nMISO requests that the proposed revisions become effective 90-days from the date of filing \n(i.e., February 14, 2027). \n \nMISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. § \n35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable \nrequirement of 18 C.F.R. Part 35 for which waiver is not specifically requested, if necessary, in \norder to permit Commission acceptance of this filing. \n \n235  Language currently pending before the Commission in the following, unrelated dockets is highlighted in yellow: \nER26-3552-000; ER26-3650-000; and ER27-25-000.  MISO requests that the Commission treat such highlighted \nlanguage as subject to the outcome of those pending proceedings.  If needed, MISO commits to file any revisions \nto this highlighted language as necessary to comply with any Commission orders in the proceeding. \nIn addition, MISO has not included language that has future effective dates of 6/1/2027, 9/1/2027, and 6/1/2029, \nunder Docket Nos. ER26-1882-001, ER25-1886-000, and ER22-1640-003;-006, respectively. MISO has also \nremoved language that has a future effective date of 6/12/2028 and is pending in Docket No. ER26-2825-000. If \nneeded, MISO commits to file any revisions to comply with any Commission orders in these proceedings and \nMISO commits to make subsequent filings with the Commission to reflect the most up-to-date version of the \nthen-current Tariff provisions prior to the effective dates of the language."},{"page":66,"startToken":27788,"endToken":28085,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 66 \n \n \nXI. \nCOMMUNICATIONS \n \nMISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of \nPractice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the \ndesignation of more than two persons for service on behalf of MISO in this proceeding and requests \nall communications related to this filing be directed to: \n \nFor MISO: \n \n \n \n \n \nFor MISO: \n \nMichael Kessler  \nManaging Assistant General Counsel \nChristopher D. Supino \nManaging Senior Corporate Counsel \nMidcontinent \nIndependent \nSystem \nOperator, Inc. \n720 City Center Drive  \nCarmel, Indiana 46032  \nTelephone: (317) 249-5400 \nmkessler@misoenergy.org \ncsupino@misoenergy.org  \nJames C.  Holsclaw \nLauren A. Stenger \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-4266 \njholsclaw@calfee.com  \nlastenger@calfee.com \n \nFor MISO Transmission Owners: \n \nWendy N. Reed \nAnna Fernandez \nWright & Talisman, P.C. \n1200 G Street, N.W \nSuite 600 \nWashington, D.C. 20005 \nTelephone: (202) 393-1200 \nreed@wrightlaw.com \nfernandez@wrightlaw.com \n \nXII. \nNOTICE AND SERVICE \n \nMISO has served a copy of this filing electronically, including attachments, upon all Tariff \ncustomers, MISO Members, Member representatives of Transmission Owners and non-\nTransmission Owners, as well as all state commissions within the MISO Region and the \nOrganization of MISO States. The filing has been posted electronically on MISO’s website at \nhttps://www.misoenergy.org/legal/ferc-filings/ for other parties interested in this matter.    \n \nMISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. § \n35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable \nrequirement of 18 C.F.R. Part 35 for which waiver is not specifically requested, if necessary, in \norder to permit Commission acceptance of this filing."},{"page":67,"startToken":28085,"endToken":28241,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 67 \n \nXIII. \nCONCLUSION \n \nFor all of the foregoing reasons, MISO respectfully requests that the Commission accept \nthis filing and grant waiver of any Commission regulations the Commission deems in order for the \nCommission to accept it as proposed. \nRespectfully submitted, \n \n/s/ Michael Kessler \nMichael Kessler  \nManaging Assistant General Counsel \nChristopher D. Supino \nManaging Senior Corporate Counsel \nMidcontinent Independent System  \nOperator, Inc. \n720 City Center Drive  \nCarmel, Indiana 46032  \nTelephone: (317) 249-5400 \nmkessler@misoenergy.org \ncsupino@misoenergy.org \n \nJames C.  Holsclaw \nLauren A. Stenger \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-4266 \njholsclaw@calfee.com  \nlastenger@calfee.com  \n \nAttorneys for the Midcontinent Independent \nSystem Operator, Inc. \n \nWendy N. Reed \nAnna Fernandez \nWright & Talisman, P.C. \n1200 G Street, N.W \nSuite 600 \nWashington, D.C. 20005 \nTelephone: (202) 393-1200 \nreed@wrightlaw.com \nfernandez@wrightlaw.com \n \nAttorneys for the MISO Transmission Owners"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":997,"startToken":0,"endToken":1151},{"p":3,"at":997,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":3,"endAt":1001,"startToken":1151,"endToken":1152},{"p":3,"at":1001,"title":"EXECUTIVE SUMMARY","method":"printed heading","endPage":5,"endAt":2736,"startToken":1152,"endToken":2334},{"p":5,"at":2736,"title":"II. BACKGROUND","method":"printed heading","endPage":5,"endAt":2741,"startToken":2334,"endToken":2335},{"p":5,"at":2741,"title":"BACKGROUND","method":"printed heading","endPage":6,"endAt":236,"startToken":2335,"endToken":2445},{"p":6,"at":236,"title":"A. The changing nature of load growth in the MISO region.","method":"printed heading","endPage":6,"endAt":2670,"startToken":2445,"endToken":2785},{"p":6,"at":2670,"title":"B. MISO’s existing processes and the development of a dedicated stakeholder forum.","method":"printed heading","endPage":7,"endAt":1513,"startToken":2785,"endToken":3090},{"p":7,"at":1513,"title":"C. The Show Cause Order and the opportunity to develop regional solutions.","method":"printed heading","endPage":8,"endAt":2385,"startToken":3090,"endToken":3668},{"p":8,"at":2385,"title":"D. The earlier filings and the matters reserved for further development.","method":"printed heading","endPage":10,"endAt":775,"startToken":3668,"endToken":4423},{"p":10,"at":775,"title":"E. The additional provisions now presented in this omnibus filing.","method":"printed heading","endPage":11,"endAt":1581,"startToken":4423,"endToken":5009},{"p":11,"at":1581,"title":"III. LARGE LOAD APPLICATION AND STUDY PROCESS","method":"printed heading","endPage":12,"endAt":1592,"startToken":5009,"endToken":5496},{"p":12,"at":1592,"title":"A. New Definitions for the LLPR Process","method":"printed heading","endPage":13,"endAt":1494,"startToken":5496,"endToken":5951},{"p":13,"at":1494,"title":"B. Applicability and Participant Responsibilities.","method":"printed heading","endPage":15,"endAt":1900,"startToken":5951,"endToken":7088},{"p":15,"at":1900,"title":"C. LLPR Study Cadence, Timing, and Application Requirements—Attachment FF","method":"printed heading","endPage":19,"endAt":63,"startToken":7088,"endToken":8860},{"p":19,"at":63,"title":"D. Model Building and Coordination with MTEP and Existing Processes—","method":"printed heading","endPage":19,"endAt":1728,"startToken":8860,"endToken":9124},{"p":19,"at":1728,"title":"E. The LLPR System Impact Study—Attachment FF Section I.D.1.c.iii.e.","method":"printed heading","endPage":21,"endAt":63,"startToken":9124,"endToken":9761},{"p":21,"at":63,"title":"F. Tender and Processing of the Cost Recovery Agreements—Attachment FF","method":"printed heading","endPage":22,"endAt":2433,"startToken":9761,"endToken":10676},{"p":22,"at":2433,"title":"G. Resubmission of Withdrawn Applications—Attachment FF Sections I.D.1.c.iii.g","method":"printed heading","endPage":23,"endAt":281,"startToken":10676,"endToken":10932},{"p":23,"at":281,"title":"H. Stakeholder Forums—Attachment FF Sections I.D.1.c.iii.h.","method":"printed heading","endPage":23,"endAt":2195,"startToken":10932,"endToken":11219},{"p":23,"at":2195,"title":"I. Cost Recovery Agreements—Attachment FF Section I.D.1.c.iii.i.","method":"printed heading","endPage":28,"endAt":1620,"startToken":11219,"endToken":13669},{"p":28,"at":1620,"title":"IV. COST RECOVERY AGREEMENT AND COST TRANSPARENCY","method":"printed heading","endPage":29,"endAt":423,"startToken":13669,"endToken":14051},{"p":29,"at":423,"title":"A. Cost Recovery Agreements","method":"printed heading","endPage":35,"endAt":1397,"startToken":14051,"endToken":17044},{"p":35,"at":1397,"title":"B. MISO Large Load Dashboard—Attachment FF, Section I.D.1.c.iv","method":"printed heading","endPage":36,"endAt":1529,"startToken":17044,"endToken":17575},{"p":36,"at":1529,"title":"C. Just and Reasonable Treatment.","method":"printed heading","endPage":37,"endAt":65,"startToken":17575,"endToken":17836},{"p":37,"at":65,"title":"V. TRANSMISSION SERVICE OFFERINGS","method":"printed heading","endPage":37,"endAt":103,"startToken":17836,"endToken":17840},{"p":37,"at":103,"title":"A. Overview and service selection.","method":"printed heading","endPage":37,"endAt":1130,"startToken":17840,"endToken":17975},{"p":37,"at":1130,"title":"B. Firm Service Step Up.","method":"printed heading","endPage":38,"endAt":63,"startToken":17975,"endToken":18229},{"p":38,"at":63,"title":"C. Interim NITS.","method":"printed heading","endPage":39,"endAt":1518,"startToken":18229,"endToken":18868},{"p":39,"at":1518,"title":"D. Reliability and rate treatment.","method":"printed heading","endPage":40,"endAt":268,"startToken":18868,"endToken":19124},{"p":40,"at":268,"title":"VI. LEGAL SHOWING AND RESPONSE TO THE SHOW CAUSE ORDER","method":"printed heading","endPage":41,"endAt":2001,"startToken":19124,"endToken":19824},{"p":41,"at":2001,"title":"A. Existing commercial arrangements and transition.","method":"printed heading","endPage":42,"endAt":1571,"startToken":19824,"endToken":20295},{"p":42,"at":1571,"title":"B. Effects on regional and local planning.","method":"printed heading","endPage":43,"endAt":63,"startToken":20295,"endToken":20527},{"p":43,"at":63,"title":"C. Cost recovery and financial security.","method":"printed heading","endPage":44,"endAt":63,"startToken":20527,"endToken":20951},{"p":44,"at":63,"title":"D. Alternative transmission technologies.","method":"printed heading","endPage":45,"endAt":63,"startToken":20951,"endToken":21404},{"p":45,"at":63,"title":"E. Generation participation and Resource Adequacy","method":"printed heading","endPage":45,"endAt":1802,"startToken":21404,"endToken":21644},{"p":45,"at":1802,"title":"VII. DESCRIPTION OF PROPOSED TARIFF REVISIONS","method":"printed heading","endPage":48,"endAt":1015,"startToken":21644,"endToken":22476},{"p":48,"at":1015,"title":"I. Introduction","method":"printed heading","endPage":48,"endAt":1210,"startToken":22476,"endToken":22505},{"p":48,"at":1210,"title":"III. Network Integration Transmission","method":"printed heading","endPage":53,"endAt":148,"startToken":22505,"endToken":23533},{"p":53,"at":148,"title":"Attachment F","method":"printed heading","endPage":53,"endAt":844,"startToken":23533,"endToken":23636},{"p":53,"at":844,"title":"Attachment G","method":"printed heading","endPage":58,"endAt":354,"startToken":23636,"endToken":24663},{"p":58,"at":354,"title":"VIII. STAKEHOLDER ENGAGEMENT","method":"printed heading","endPage":59,"endAt":919,"startToken":24663,"endToken":25154},{"p":59,"at":919,"title":"A. Cost Transparency and Recovery","method":"printed heading","endPage":61,"endAt":1453,"startToken":25154,"endToken":25937},{"p":61,"at":1453,"title":"B. LLPR","method":"printed heading","endPage":62,"endAt":679,"startToken":25937,"endToken":26231},{"p":62,"at":679,"title":"C. Interim NITS","method":"printed heading","endPage":65,"endAt":653,"startToken":26231,"endToken":27474},{"p":65,"at":653,"title":"IX. DOCUMENTS SUBMITTED IN THIS FILING","method":"printed heading","endPage":65,"endAt":1109,"startToken":27474,"endToken":27542},{"p":65,"at":1109,"title":"X. EFFECTIVE DATE AND REQUEST FOR WAIVER","method":"printed heading","endPage":66,"endAt":65,"startToken":27542,"endToken":27797},{"p":66,"at":65,"title":"XI. COMMUNICATIONS","method":"printed heading","endPage":66,"endAt":1185,"startToken":27797,"endToken":27957},{"p":66,"at":1185,"title":"XII. NOTICE AND SERVICE","method":"printed heading","endPage":67,"endAt":63,"startToken":27957,"endToken":28094},{"p":67,"at":63,"title":"XIII. CONCLUSION","method":"printed heading","endPage":67,"endAt":70,"startToken":28094,"endToken":28095},{"p":67,"at":70,"title":"CONCLUSION","method":"printed heading","endPage":67,"endAt":1159,"startToken":28095,"endToken":28241}]}