{"document":{"slug":"pjm-20261106-iti-letter-to-pjm-board","filename":"pjm-20261106-iti-letter-to-pjm-board.pdf","title":"ITI letter to the PJM Board of Managers on large-load integration reforms","url":"https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20261106-information-technology-industry-council-letter-to-the-pjm-board-regarding-large-load.pdf","issued":"2026-11-05","group":"PJM stakeholder record","docket":"PJM stakeholder record","filer":"Information Technology Industry Council","file":"sources/originals/pjm-20261106-iti-letter-to-pjm-board.pdf","kind":"stakeholder document","sha256":"74d5ff4c2d0f31f00d7639879c020f699d1b3e7d9fcaa4b8288b32e86b15c57c","pages":7,"tokens":2652,"emptyPages":[]},"pages":[{"page":1,"startToken":0,"endToken":361,"text":"November 5, 2026 \n \nPaula Conboy \nChair, Board of Managers  \nDavid Mills \nPresident and CEO  \nPJM Interconnection, L.L.C.  \n2750 Monroe Blvd.  \nAudubon, PA 19403 \n \nVia E-mail to: Jennifer Tribulski, Members Committee Secretary \n \nDear Chair Conboy, Mr. Mills, and the PJM Board of Managers, \n \nThe Information Technology Industry Council (ITI) writes to commend PJM on its work to \naddress the Federal Energy Regulatory Commission’s (FERC) Large Load Show Cause Order, \nand to encourage PJM to continue to implement ambitious reforms to ensure timely access to \nelectricity for all customers while protecting existing customers from reliability and affordability \nimpacts from large load demand growth. ITI asks PJM to consider several sensible principles as it \ndeliberates on reforms advanced through its stakeholder process and in its work to address large \nload growth on an ongoing basis, to ensure that its reforms achieve the greatest practical benefit \nfor the region.        \n \nITI is the premier global advocate for technology, representing the world’s most innovative \ncompanies. We promote public policies and industry standards that advance competition and \ninnovation worldwide. Our diverse membership includes a broad spectrum of stakeholders across \nthe U.S. energy ecosystem, including data center developers, owners, operators, end-users, \ntechnology providers, power purchasers, energy distributors, and more. Our members contribute \nto the United States’ continued AI leadership, represent a significant share of the PJM regional \nand national economy, and support innovation that drives economic growth. The technology \nsector represents around 9 percent of the U.S. Gross Domestic Product, directly employs nearly \n10 million Americans, and accounts for roughly 40 percent of the S&P 500’s market \ncapitalization. ITI recognizes that long-term thriving of technological innovation depends on \naffordable, reliable energy infrastructure, and wholeheartedly supports PJM’s efforts to meet \nunprecedented load growth.     \n \nITI seeks to ensure that reforms to address FERC’s Show Cause Order significantly improve \nspeed to power and access to reliable and affordable electricity for existing and computational \nloads alike, while benefiting all customers. The following principles are needed to ensure that \nPJM’s reforms are commercially workable, drive significant new investments, and thereby \nachieve widespread impact on outcomes in the region. Specifically, ITI urges PJM, in finalizing \nand implementing these reforms, to:"},{"page":2,"startToken":361,"endToken":658,"text":"2 \n1. Preserve customer options,  \n2. Maintain technological neutrality,  \n3. Allocate costs transparently, and  \n4. Incentivize the utilization of advanced solutions with proportionate compensation for grid \nservices and avoided infrastructure costs.  \n \nRequirements placed upon customers for interconnection should not be one size fits all but rather \nreflect, to the greatest degree feasible, the service requested, the facility’s operating \ncharacteristics, and its economic development impacts, with fair grandfathering principles for \nprojects already approved for development. \n \nIn addition to these high-level principles, we recommend adoption of reform frameworks that: \n1. Provide clear rules that allow all capable customers to make commercial decisions about \nwhether to make flexibility commitments. \n2. Create voluntary, usable, and defined non-firm service options. \n3. Allow hybrid generation and load studies to provide measurable benefits. \n4. Require meaningful evaluation, standardized inclusion in study processes, and a practical \nroute to deployment of Grid Enhancing Technologies (GETs). \n5. Accommodate proximate generation in addition to other forms of load flexibility as \nsolutions for reducing grid withdrawals. \n6. Provide accreditation certainty for resources serving facility-specific needs. \n \nWe expand on these recommendations in the attachment to our letter. While deliberating on a \npath forward for the region, we emphasize that PJM should carefully consider whether its reforms \nto implement non-firm transmission services provide the clarity, usability, and predictability that \nwill enable significant, voluntary uptake of these services, and the degree to which proposed \nreforms to implement a combined load and generation interconnection process will provide \nmeasurable benefits. \n \nITI appreciates PJM’s work on these important reforms and the opportunity to share the \nperspective of our members. ITI looks forward to continuing to engage with PJM and its \nstakeholders as these reforms are finalized and implemented, and we would welcome the \nopportunity to discuss these recommendations further. \n \nSincerely, \n \n \n \nJason Oxman \nPresident & CEO, ITI"},{"page":3,"startToken":658,"endToken":1045,"text":"ITI Recommendations to Support Timely, Affordable, and Reliable \nLarge Load Integration \n \n1. Provide clear rules that allow all capable customers to make commercial decisions \nabout whether to make flexibility commitments. \n \nWhile not all loads can operate flexibly, load flexibility can provide significant value to the grid. \nTo provide for robust non-firm service enrollment, with attendant grid benefits, PJM’s non-firm \nservice paradigm should define flexibility broadly and in a technologically neutral fashion, \nprovide requisite specificity to inform decisionmaking, and compensate flexibility for the grid \nservices it provides.  \n \nITI supports FERC’s directives to define non-firm service eligibility with reference to \nperformance capability—i.e., ability to reduce withdrawals during grid peaks, whether achieved \nthrough on-site or proximate storage, on-site or proximate generation, compute shifting, workload \nmanagement, cooling and building controls, investing in distributed energy resources off site, or \nother innovative solutions—rather than a single technology or operating model. FERC’s direction \nto allow loads to take a mix of firm and non-firm contract demand service will also maximize \nflexibility commitments by allowing loads to maintain firm service for a portion of their critical \noperations. PJM should implement these directives faithfully. \n \nIn addition, PJM should: \n• \nCompensate and account for the value that flexibility provides to the grid. Voluntary \nflexibility commitments should translate into identifiable customer benefits, driven by \nearlier interconnection, avoided need for network upgrades, cheaper service, and \nproportionately reduced financial security requirements. Without such recognition of the \nvalue provided by flexibility commitments, loads will under-enroll, and load flexibility \nmay not translate to savings for other customers by avoiding unneeded infrastructure \nbuildout. These conditional-service benefits should be distinguished from compensation \nfor eligible demand response, energy, ancillary services, or other market products \nprovided by loads taking firm service or their eligible proximate or behind-the-meter \nresources. PJM should preserve opportunities for such compensated participation while \ndistinguishing incremental services from curtailment already required as a condition of \nfaster energization or non-firm service and avoiding double counting. \n• \nEstablish clear, practical rules to guide commercial decisions. Telemetry, verification, \ntesting, cybersecurity, and communications requirements should be proportionate to the \nflexibility commitment, thus scaling with complexity of the site’s configuration. Rules \nshould address recovery and reconnection so that simultaneous restoration of curtailed \nloads does not create another reliability problem. Rules should be clear to facilitate \ncommercial decisionmaking and not more burdensome than needed to ensure system \nreliability."},{"page":4,"startToken":1045,"endToken":1481,"text":"2 \n \nMoreover, flexible loads can provide value to the grid through mechanisms beyond taking non-\nfirm service. PJM should consider the interactions of various flexibility value streams, including \nvia demand response, peak shaving programs, and transmission service netting, to maximize the \ngrid services that load flexibility can provide to the extent operationally possible. \n \n2. Create voluntary, usable, and defined non-firm service options. \n \nIn addition to clearly defining the contours of non-firm service eligibility, PJM should establish \nnon-firm service terms and conditions that are manageable for loads and therefore facilitate \nparticipation.  \n \nAs an initial matter, ITI supports FERC’s directive to provide both interim and permanent non-\nfirm service options. Customers should have options to select interruptible service as a bridge \nwhile infrastructure upgrades are completed or as a longer-term arrangement based on their \noperational needs. Permanent service options are needed to allow loads willing and able to make \nlong-term flexibility commitments to reduce the need for new infrastructure to serve them. \n \nITI supports further efforts by PJM to establish these services in a manner that provides for \nimproved visibility about grid conditions to help inform flexible load management and limits that \nloads need to make flexibility commitments.  \n• \nDefine non-firm service with sufficient certainty to support investment decisions. \nTariffs and agreements should establish the firm and interruptible megawatt (MW) \nquantities, curtailment triggers and priority, notice and response requirements, restoration \nprocedures, and consequences of non-performance. Where reliably supportable, the \nservices should also cap the hours of discrete service interruptions to reduce uncertainty \nand enable load participation, while separately specifying emergency authority and the \ntreatment of service once a cap is reached.  \n• \nUnbundle bases for non-firm service interruptions. Service agreements should \nseparate service that is interruptible based on transmission constraints from service \ninterruptible for capacity constraints to give customers more options to enroll in the \nservice that makes the most sense for them—and thereby increase participation. SPP’s \nCHILLS framework offers a useful example: its study pathways distinguish sufficient \ndesignated resources with pending transmission upgrades from planned or other \nqualifying resource support, and its operating rules separately identify curtailment when \nsupporting-resource capacity falls below the conditional load. Both configurations retain \nbroader reliability and emergency restrictions. PJM should similarly identify the binding \nconstraint, affected MW, supporting resources, and conditions for lifting each restriction \nthroughout applications, studies, and agreements. Resource adequacy (RA) sufficiency \nassessments should also account for applicable state rules governing what counts toward \nRA and transparently reconcile those rules with PJM qualification and accreditation \nrequirements, without conflating resource qualification with transmission deliverability. \n• \nAccount for flexibility commitments in transmission planning and interconnection \nstudies. Permanent non-firm service commitments should reduce the infrastructure"},{"page":5,"startToken":1481,"endToken":1913,"text":"3 \nneeded to serve those customers where studies demonstrate that the commitments relieve \nthe relevant constraints. To the extent that PJM establishes rules for integrating load-\ngeneration interconnection studies, those studies should allow non-firm service \ncommitments to avoid the need for network upgrades and expedite interconnection. In \naddition, Cost Recovery Agreements for large loads must account for non-firm service \ncustomers’ lesser system impacts, including through lower minimum contributions and \nfinancial security to the extent supported by demonstrated avoided costs and obligations. \nThe framework should transparently identify costs that remain necessary to serve that \ncustomer reliably. \n• \nAlign capacity charges with non-firm service. PJM should not procure capacity for, or \nallocate associated capacity procurement charges to load serving entities for, large-load \nMW accepting non-firm RA service and the corresponding enforceable curtailment \nobligations during emergency conditions. Consistent with PJM’s stated approach, those \nMW should be excluded from capacity obligations and billing determinants. For mixed-\nservice sites, the exclusion should apply to the non-firm portion. PJM should separately \nexplain the treatment of any elected RA coverage retained alongside transmission-related \nconditional access. \n• \nProvide a clear transition to firm service. Interim customers must understand the \nmilestones, additional studies, costs, and timing implicated in the transition from non-firm \nto firm service, separately identifying the transmission upgrades and resource-support \nrequirements needed to remove each restriction. Taking non-firm service should not \nimpact the processing of a customer’s interconnection request or require unnecessary \nrestudies or other delays. \n \n3. Allow hybrid generation and load studies to provide measurable benefits. \n \nLarge loads that pair with on-site or nearby generation and storage may be able to reduce their \nimpact on the grid and accelerate their own timelines for interconnection. Study processes that \nevaluate associated generation, storage, and load together can recognize those reduced impacts. \nITI therefore supports FERC’s directive to provide a coordinated study process for electrically \nproximate generation, storage, and load. PJM’s proposed combined study and Fast Energization \nprocess should implement these principles with clear timelines and configuration-specific results. \n \nTo that end, ITI recommends that PJM:  \n• \nProvide for coordinated studies for associated generation, storage, and load. Study \nprocesses should evaluate the combined effects of a load and associated resources and \nidentify opportunities to reduce redundant analysis and avoid unnecessary upgrades. \n• \nAllow customers to realize practical advantages from hybrid pairings. Customers \nwill only use these pathways if they offer measurable benefits. Integrated studies should \nprovide for earlier energization, reduced upgrade requirements, clearer project timelines, \nlower costs, or reduced financial security requirements. \n• \nUse digital modeling to improve study speed and accuracy. PJM should continue to \nenhance its modeling processes, adopt digital innovation, and establish clear data"},{"page":6,"startToken":1913,"endToken":2321,"text":"4 \nrequirements for interconnection customers, which should allow PJM to reuse study \ninputs and reduce avoidable resubmissions. \n• \nCoordinate resulting approvals and agreements. PJM should provide for \ninterconnection customers to receive transparent information about the impact of \nintegrated generation and load interconnection, non-firm service commitments, and other \noperational requirements on the network upgrades assigned to an integrated load-\ngeneration pair.  \n \n4. Require meaningful evaluation, standardized inclusion in study processes, and a \npractical route to deployment of GETs. \n \nBetter utilization of existing infrastructure is essential to improving speed to power and reducing \ncustomer costs. GETs and other alternative transmission technologies can increase the capability \nof the existing system and, in appropriate cases, may resolve constraints faster or at lower cost \nthan conventional upgrades. Realizing those benefits requires that these technologies be evaluated \nconsistently within the study process, and that there is a clear path to deploy them where the \nanalysis shows they offer a better outcome. ITI therefore supports FERC’s directive to require \nevaluation of GETs in transmission service studies and demonstration of cost-efficacy when \nnetwork upgrades are selected over GETs to address transmission constraints. \n \nIn implementing this requirement, ITI recommends that PJM:  \n• \nStandardize how solutions are evaluated. PJM should adopt and apply common, \npublished methods for modeling and evaluating GETs alongside conventional upgrades. \nThat includes consistent assumptions for capability, availability, and performance \nverification, including the ability of several GETs in combination to resolve constraints. \nCustomers should not have to request assessments on a case-by-case basis. Identifying \nGETs opportunities requires robust, auditable modeling that evaluates diverse solutions to \nidentified constraints, individually and in combination. PJM should commit in its Tariff to \nusing these study processes and verifying their consistent application, including \ndocumented assumptions, alternatives, and results, rather than leaving their selection, use, \nor verification solely to electric distribution companies. \n• \nCompare cost, timing, and reliable capability. Study results should explain the \nalternatives considered, expected deployment dates, lifecycle costs, operating \nrequirements, and capacity benefits. As required by FERC’s order, decisions to require \nconventional network upgrades should explain why GETs are not sufficient or cost-\neffective to address the relevant constraint. \n• \nSupport deployment where the analysis demonstrates value. Reforms should convey \nclear responsibility for GETs procurement, installation, operation, maintenance, and cost \nrecovery. Evaluation requirements will have limited effect if there are not clear \naccountability structures for implementing a selected solution.   \n• \nInclude the digital infrastructure needed to deliver the benefit. Monitoring, \ncommunications, analytics, cybersecurity, and control systems should be treated as \nintegral implementation needs."},{"page":7,"startToken":2321,"endToken":2652,"text":"5 \n• \nMeasure results. PJM should report appropriate aggregate metrics on technologies \nevaluated and deployed, capacity enabled, time saved, and costs avoided. These results \ncan inform improvements to future studies and planning. \n  \n5. Accommodate proximate generation in addition to other forms of load flexibility as \nsolutions for reducing grid withdrawals. \n \nLinking a new large load with supporting generation nearby can be an effective approach to \nenable quick access to grid power and is another valuable arrangement that may allow loads to \nlimit net withdrawals from the broader transmission network. Examples include a co-located \n“energy park” facility at a single site or loads sited separately with generation proximate in \nnearby substations. Such arrangements serve the dual purpose of (1) meeting the large load’s RA \nneeds (without relying on existing generation capacity on the grid) and (2) accelerating \ntransmission connection by utilizing existing transmission, reducing or eliminating the need to \nrely on slow and potentially costly transmission upgrades. PJM should give equal consideration \nto proximate generation as to other forms of load flexibility, such as co-location of generation and \nload curtailment, particularly in both load and generator interconnection studies. \n \n6. Provide accreditation certainty for resources serving facility-specific needs. \n \nOutside of the show cause context, large load customers may seek to mitigate procurement price \nimpacts for other customers by bringing their own new capacity to the market. These customers \nneed confidence, however, that the value of those investments will not unpredictably erode \nthereafter. Stable, transparent accreditation and market treatment will encourage these \ninvestments, which can in turn support reliability and reduce the need for infrastructure paid for \nby other customers. Accordingly, ITI supports reforms to provide for more stability in resource \naccreditations to the greatest extent possible without harming reliability, including potentially \nholding values in place for defined periods so that changes in methodology do not undermine \ninvestment cases after the fact. PJM could also include reforms to grandfather resources already \nunder development to serve a facility when new rules or valuation methods are adopted."}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 4","method":"page range","endPage":5,"endAt":0,"startToken":0,"endToken":1481},{"p":5,"at":0,"title":"Pages 5 to 7","method":"page range","endPage":7,"endAt":2340,"startToken":1481,"endToken":2652}]}