# Sec. 1106. Timely and unified Federal reviews

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/1106)

## Summary

Rewrites NEPA section 107, the core of the review process. ([p. 31, line 11 to p. 31, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31)) Environmental assessments are due in 1 year and environmental impact statements in 2 years, measured from the earlier of the agency's determination or its notice that the application is complete. ([p. 46, line 17 to p. 46, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46)) A record of decision follows a final EIS within 45 days. ([p. 49, line 8 to p. 49, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49)) Agencies in the review must decide all authorizations within 90 days, and agencies outside it within 120 days. ([p. 49, line 21 to p. 49, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49))

Lead agency designation gets a clock, with the CEQ Chairman resolving disputes within 21 days by a final, unreviewable decision. ([p. 35, line 19 to p. 35, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=35)) The Chairman can also order a resolution of interagency disputes, and that order counts as full compliance with any interagency consultation obligation under federal law. ([p. 52, line 14 to p. 52, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52))

The lead agency must drop any alternative that does not meet the purpose and need or the goals of a non-federal sponsor. ([p. 38, line 6 to p. 38, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38)) Agencies need not consider science published after the notice of intent. ([p. 43, line 12 to p. 43, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43)) Public scoping comment periods run 45 to 60 days, or 75 with the sponsor's consent. ([p. 44, line 25 to p. 45, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44))

If an agency defies a Chairman's dispute order and a deadline is missed, then after 30 days its permitting officers and senior executives must spend at least half their workweek on the overdue review. ([p. 54, line 5 to p. 54, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=54)) Once any deadline is 60 days overdue, the agency head may not travel more than 25 miles from the duty station until the document or permit issues. ([p. 54, line 17 to p. 54, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=54)) The Secretary of Defense is exempt. ([p. 55, line 3 to p. 55, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55)) Project sponsors can sue over missed deadlines. ([p. 55, line 18 to p. 55, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55)) The court must rule within 120 days and can order a decision within 60 days. ([p. 58, line 3 to p. 58, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58))

## Key points

- EIS in 2 years, EA in 1 year, with the clock starting at the earlier of the review determination or a complete application ([p. 46, line 17 to p. 46, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46))
- ROD within 45 days of the final EIS; all federal permits within 90 days (120 for non-participating agencies) ([p. 49, line 8 to p. 49, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49))
- No duty to consider scientific research published after the notice of intent ([p. 43, line 12 to p. 43, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43))
- CEQ Chairman's dispute orders are final, unreviewable, and satisfy any interagency consultation requirement ([p. 52, line 11 to p. 52, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52))
- Agency head confined to 25 miles of the duty station once a deadline is 60 days overdue; senior staff spend half the week on the review when the agency has defied a CEQ dispute order ([p. 53, line 13 to p. 53, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53))
- Sponsors get a cause of action with a 120-day court decision clock ([p. 58, line 3 to p. 58, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58))
- Alternatives that do not meet the non-federal sponsor's goals are eliminated ([p. 38, line 11 to p. 38, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38))

## What others say it would do

Outside readings, quoted from their sources. These are claims about effects, not findings of this tracker.

- **King & Spalding** (Lawyers and legal scholars; concerns): Whether agencies can meet the tighter deadlines depends on staffing, so sponsors should expect a rough transition.
  > Whether they can meet the new deadlines will turn on staffing, and sponsors should plan for a bumpy transition.
  [King & Spalding, 2026-10-02](https://www.kslaw.com/Insights/Articles/The-Senate-Permitting-Deal-What-It-Would-Change-and-What-to-Do-Now). On the bill text at [p. 48, line 19 to p. 48, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48).
- **King & Spalding** (Lawyers and legal scholars; explains): Agencies would be freed from considering science published after a review starts, and courts would defer to technical determinations.
  > They would not need to consider research published after review begins, and courts would defer substantially to their technical determinations.
  [King & Spalding, 2026-10-02](https://www.kslaw.com/Insights/Articles/The-Senate-Permitting-Deal-What-It-Would-Change-and-What-to-Do-Now). On the bill text at [p. 43, line 12 to p. 43, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43).
- **Womble Bond Dickinson** (Lawyers and legal scholars; explains): A missed agency deadline gives the sponsor enforcement tools but is not a deemed permit approval.
  > A missed deadline, however, would not itself constitute permit approval.
  [Womble Bond Dickinson, 2026-10-02](https://www.womblebonddickinson.com/us/node/21451). On the bill text at [p. 48, line 19 to p. 48, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48).
- **Columbia University Center on Global Energy Policy** (Think tanks; explains): CGEP's replay of past transmission cases finds the transmission archetype saves 64 months up to the federal decision.
  > The bill reduces the timeline to the federal decision by 64 months in the archetype, compared with 60.7 months in the largest replay (Bordertown to California, a 10-mile, 120 kV line).
  [Columbia University Center on Global Energy Policy, 2026-10-21](https://www.energypolicy.columbia.edu/wp-content/uploads/2026/10/baaja-timelines-v6.html). On the bill text at [p. 48, line 17 to p. 48, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48).
- **Columbia University Center on Global Energy Policy** (Think tanks; mixed): CGEP counts only months saved and cannot count projects BAAJA might enable that current law stops.
  > The estimates count only months saved, not projects that BAAJA might have enabled to proceed but that current law stopped.
  [Columbia University Center on Global Energy Policy, 2026-10-21](https://www.energypolicy.columbia.edu/wp-content/uploads/2026/10/baaja-timelines-v6.html). On the bill text at [p. 48, line 17 to p. 48, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48).
- **Grist** (Reporting; explains): Grist sums up the bill as weakening some environmental laws, speeding agency deadlines and making approved projects harder to cancel.
  > The bill does this by weakening some of the nation’s bedrock environmental laws, speeding up the timeline for government agencies to issue permits, and making it harder to cancel projects that have already gotten federal approval.
  [Grist, 2026-10-08](https://grist.org/politics/permitting-reform-baaja-climate-debate-clean-energy-fossil-fuels/). On the bill text at [p. 159, line 12 to p. 159, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=159).
- **The Revelator** (Lawyers and legal scholars; opposes): Camacho and Glicksman say BAAJA hollows out NEPA, including courts' ability to enforce it.
  > the bill is an out-and-out assault on the National Environmental Policy Act, the bedrock environmental law that has for more than 50 years required the federal government to look before it leaps.
  [The Revelator, 2026-10-23](https://therevelator.org/baaja). On the bill text at [p. 68, line 1 to p. 68, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=68).

## Selected statutory quotes

> No Federal agency shall be required to consider any scientific or technical research that becomes publicly available after the date of publication of a notice of intent or decision to prepare an environmental document for a proposed agency action.

[p. 43, line 12 to p. 43, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43)

Research published after the notice of intent need not be considered.

> the head of the relevant key permitting agency shall not travel more than 25 miles from their official duty station for the purposes of official business until the key permitting agency has published or made public the applicable environmental document and issued all outstanding authorizations

[p. 54, line 17 to p. 54, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=54)

The agency head's travel is restricted once a deadline is 60 days overdue.

> shall, for purposes of judicial review of the ultimate agency action and all other Federal law, constitute full compliance with and satisfaction of any requirement for interagency consultation, coordination, concurrence, authorization, or other procedural obligation under Federal law that is the subject of the dispute or delay.

[p. 52, line 14 to p. 52, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52)

A CEQ dispute order satisfies consultation duties under other statutes.

> eliminate from consideration any alternative (except for a no-action alternative) that does not— “(I) fulfill the purpose and need of the proposed agency action; and “(II) meet the goals of an applicable non-Federal project sponsor.

[p. 38, line 6 to p. 38, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38)

Alternatives that miss the sponsor's goals are dropped from the analysis.

> the lead agency shall publish an environmental impact statement, if applicable, not later than the date that is 2 years

[p. 48, line 17 to p. 48, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48)

The two-year deadline for an environmental impact statement.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

The Fiscal Responsibility Act of 2023 set the 2-year EIS and 1-year EA deadlines, page limits of 150 pages for an EIS and 75 for an EA (both kept), and a sponsor's right to petition a court, which can order the agency to act within 90 days.

New here: the clock no longer starts at the notice of intent. A record of decision is due 45 days after the EIS and all permits within 90 or 120 days. Agencies need not consider science published after the notice of intent. The CEQ Chairman settles lead-agency and interagency disputes with final, unreviewable orders, and lead-agency disputes take 21 days, down from 40. Alternatives that miss the sponsor's goals are dropped. Missed deadlines can trigger the staff-time and travel sanctions, and courts must rule on deadline suits within 120 days.

### EPRA 2024 (reported S. 4753)

EPRA 2024 did not rewrite NEPA section 107; its deadlines were project-specific (energy leasing, rights-of-way).

### SPEED Act (House-passed H.R. 4776)

The SPEED Act (sec. 2(c)) kept the 2023 deadlines and added a science cutoff at the earlier of the application or the notice of intent, a requirement that the purpose and need 'meet the goals of the applicant', 21-day clocks for cooperating agencies, and a final agency action within 30 days of the finished document. It had no CEQ dispute orders and no sanctions on agency staff or agency heads.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 31, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 0)

Section 107 of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a) is amended—

[p. 31, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 2)

(1) by striking subsections (a) through (c) and inserting the following:

[p. 31, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 1)

“(a) DETERMINATION OF AGENCY ROLES AND RESPONSIBILITIES.—

[p. 31, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 2)

“(1) LEAD AGENCY.—

[p. 31, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 3)

“(A) DESIGNATION.—

[p. 31, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 4)

“(i) IN GENERAL.—The Federal agency that proposed the proposed agency action shall be the lead agency.

[p. 31, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=31) (indent level 4)

“(ii) TWO OR MORE AGENCIES.—If there are 2 or more Federal agencies that are required by law to make a decision relating to an authorization for which an environmental review is required under this Act, those agencies shall determine, by letter or memorandum, which Federal agency shall be the lead agency for that environmental review based on consideration of—

[p. 32, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 5)

“(I) the magnitude of the involvement of the Federal agencies;

[p. 32, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 5)

“(II) the project approval or disapproval authority of those Federal agencies;

[p. 32, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 5)

“(III) the expertise concerning the environmental effects of the proposed agency action;

[p. 32, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 5)

“(IV) the duration of involvement of the Federal agencies with respect to that proposed agency action; and

[p. 32, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 5)

“(V) the sequence of the involvement of the Federal agencies with respect to that proposed agency action.

[p. 32, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 4)

“(iii) JOINT LEAD AGENCIES.—

[p. 32, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=32) (indent level 5)

“(I) IN GENERAL.—In making a determination under clause (ii), the Federal agencies participating in the environmental review may appoint such State, Tribal, or local agencies as joint lead agencies, as those Federal agencies determine to be appropriate.

[p. 33, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=33) (indent level 5)

“(II) RESPONSIBILITIES.—Joint lead agencies appointed under subclause (I) shall jointly fulfill the role described in subparagraph (C).

[p. 33, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=33) (indent level 3)

“(B) DELAY IN DESIGNATION.—

[p. 33, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=33) (indent level 4)

“(i) REQUEST FOR DESIGNATION.—

[p. 33, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=33) (indent level 5)

“(I) IN GENERAL.—Any Federal, State, Tribal, or local agency or project sponsor that is substantially affected by the lack of a designation of a lead agency with respect to a proposed agency action under subparagraph (A) may submit a written request to a Federal agency participating in the environmental review for the designation of a lead agency.

[p. 33, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=33) (indent level 5)

“(II) TRANSMISSION.—A Federal agency that receives a request under subclause (I) shall transmit that request to each Federal agency participating in the environmental review and to the Chairman.

[p. 34, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=34) (indent level 4)

“(ii) CHAIRMAN DESIGNATION.—

[p. 34, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=34) (indent level 5)

“(I) REQUEST.—If the Federal agencies participating in the environmental review are unable to agree on the designation of a lead agency not later than 21 days after the date on which the request was transmitted to a Federal agency participating in the environmental review under clause (i)(II), the Federal, State, Tribal, or local agency or project sponsor that is substantially affected by the lack of a designation of a lead agency may submit to the Chairman a request to designate a lead agency, which request shall consist of—

[p. 34, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=34) (indent level 6)

“(aa) a precise description of the nature and extent of the proposed agency action; and

[p. 34, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=34) (indent level 6)

“(bb) a detailed statement with respect to each Federal agency participating in the environmental review and each factor described in subparagraph (A)(ii) regarding which Federal agency shall serve as lead agency.

[p. 35, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=35) (indent level 5)

“(II) TRANSMISSION.—The Chairman shall transmit a request received under subclause (I) to each Federal agency participating in the environmental review.

[p. 35, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=35) (indent level 5)

“(III) RESPONSE.—A Federal agency participating in an environmental review may, not later than 14 days after the date of the transmission of a request under subclause (II), submit to the Chairman a response to the request for consideration by the Chairman.

[p. 35, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=35) (indent level 5)

“(IV) DESIGNATION.— Not later than 21 days after the date of the transmission of a request under subclause (II), the Chairman shall designate the lead agency with respect to the applicable proposed agency action.

[p. 35, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=35) (indent level 5)

“(V) FINAL AND CONCLUSIVE; NO JUDICIAL REVIEW.—Any action taken by the Chairman to designate a lead agency under this clause—

[p. 36, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 6)

“(aa) shall be final and conclusive; and

[p. 36, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 6)

“(bb) shall not be subject to judicial review.

[p. 36, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 3)

“(C) ROLE OF LEAD AGENCY.—A lead agency shall, with respect to a proposed agency action—

[p. 36, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 4)

“(i) supervise the preparation of an environmental document if, with respect to such proposed agency action, there is more than 1 Federal agency participating in the environmental review;

[p. 36, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 4)

“(ii) request the participation of each cooperating agency at the earliest practicable time;

[p. 36, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 4)

“(iii) in preparing an environmental document, give consideration to any analysis or proposal created, if applicable, by a cooperating agency;

[p. 36, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=36) (indent level 4)

“(iv) develop a schedule, in consultation with each cooperating agency, the project sponsor, and such other entities as the lead agency determines appropriate, for completion of any environmental review or authorization required to carry out the proposed agency action;

[p. 37, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=37) (indent level 4)

“(v) meet with a cooperating agency that requests such a meeting;

[p. 37, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=37) (indent level 4)

“(vi) define and determine, as appropriate, the purpose and need, the reasonable alternatives, and the reasonably foreseeable environmental effects of the proposed agency action subject to the jurisdiction of the lead agency by law, subject to the condition that the alternatives may include the use of land under the jurisdiction of another Federal agency that has been designated as a cooperating agency;

[p. 37, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=37) (indent level 4)

“(vii) if the lead agency determines that an environmental review or authorization will not be completed in accordance with the schedule developed under clause (iv), submit a notification of any authorization or action by another Federal agency responsible for the possible failure to meet that schedule to the Chairman;

[p. 37, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=37) (indent level 4)

“(viii) presume that the effects of a no-action alternative will be negative for any proposed agency action carried out on, or directly affecting, Tribal trust resources (including lands and minerals) when the action is initiated by the Indian Tribe for which the United States holds the affected Tribal resources in trust; and

[p. 38, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 4)

“(ix) eliminate from consideration any alternative (except for a no-action alternative) that does not—

[p. 38, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 5)

“(I) fulfill the purpose and need of the proposed agency action; and

[p. 38, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 5)

“(II) meet the goals of an applicable non-Federal project sponsor.

[p. 38, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 2)

“(2) COOPERATING AGENCIES.—

[p. 38, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 3)

“(A) DESIGNATION.—

[p. 38, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 4)

“(i) IN GENERAL.—The lead agency may, with respect to a proposed agency action, designate any Federal, State, Tribal, or local agency (including a county, borough, parish, city, and any other political subdivision of a State) that has jurisdiction by law with respect to any environmental effect involved in a proposed agency action to serve as a cooperating agency.

[p. 38, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=38) (indent level 4)

“(ii) REQUIREMENTS.—Not later than 30 days after the date on which the lead agency issues, consistent with section 110, a notice of intent to prepare an environmental impact statement or informs the project sponsor that an environmental assessment is necessary, the lead agency shall—

[p. 39, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=39) (indent level 5)

“(I) identify all Federal and non-Federal agencies and governmental entities likely to require or provide authorization with respect to a proposed agency action; and

[p. 39, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=39) (indent level 5)

“(II) invite each agency identified under subclause (I) to become a cooperating agency.

[p. 39, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=39) (indent level 4)

“(iii) ACCEPTANCE OR DENIAL.—An agency invited under clause (ii)(II) shall accept or deny the invitation not later than 7 days after the date on which the agency receives the invitation.

[p. 39, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=39) (indent level 4)

“(iv) LIMITATIONS.—The designation of a cooperating agency under this subparagraph shall not—

[p. 39, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=39) (indent level 5)

“(I) give such cooperating agency authority or jurisdiction over the proposed agency action; or

[p. 40, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=40) (indent level 5)

“(II) expand any jurisdiction or authority such cooperating agency may have over the proposed agency action.

[p. 40, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=40) (indent level 4)

“(v) UNIDENTIFIED AGENCIES.—In the event that an agency that has jurisdiction by law with respect to any environmental impact involved in a proposed agency action is not identified as a potential cooperating agency under clause (ii)(I), the lead agency shall—

[p. 40, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=40) (indent level 5)

“(I) invite such unidentified agency to become a cooperating agency by not later than 7 days after becoming aware that the agency has jurisdiction by law with respect to the proposed agency action; and

[p. 40, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=40) (indent level 5)

“(II) if such agency accepts the invitation, incorporate such agency into the schedule developed under paragraph (1)(C)(iv) and update such schedule accordingly by not later than 14 days after the date on which such agency accepts the invitation.

[p. 40, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=40) (indent level 3)

“(B) ROLE OF COOPERATING AGENCIES.—

[p. 41, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=41) (indent level 4)

“(i) IN GENERAL.—A cooperating agency may, not later than a date specified in the schedule established by the lead agency under paragraph (1)(C)(iv), submit comments to the lead agency.

[p. 41, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=41) (indent level 4)

“(ii) REQUIREMENTS.—Comments submitted by a cooperating agency under clause (i) shall be limited to matters relating to the jurisdiction by law of the cooperating agency with respect to—

[p. 41, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=41) (indent level 5)

“(I) the reasonably foreseeable environmental effects of the proposed agency action; and

[p. 41, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=41) (indent level 5)

“(II) any applicable authorization required of the cooperating agency.

[p. 41, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=41) (indent level 4)

“(iii) ASSISTANCE.—A cooperating agency may, with the agreement of the lead agency, assist in the preparation of an environmental document.

[p. 41, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=41) (indent level 4)

“(iv) SUFFICIENCY OF ANALYSIS.— For the purpose of compliance with the requirements of this Act, a cooperating agency shall be bound by the purpose and need of the proposed agency action and consider only those alternatives to the proposed agency action that the lead agency has, consistent with paragraph (1)(C), determined are reasonable.

[p. 42, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=42) (indent level 1)

“(b) COORDINATION OF AGENCIES PARTICIPATING IN AN ENVIRONMENTAL REVIEW.—

[p. 42, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=42) (indent level 2)

“(1) IN GENERAL.—Not later than 30 days after the date described in clause (iii) of subsection (a)(2)(A) with respect to each agency invited to be a cooperating agency pursuant to clause (ii)(II) of that subsection, the lead agency shall develop the schedule under subsection (a)(1)(C)(iv) for the applicable proposed agency action.

[p. 42, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=42) (indent level 2)

“(2) REQUIREMENTS.—To the maximum extent practicable, if a proposed agency action will require action by more than 1 Federal agency and the lead agency has determined that the proposed agency action requires preparation of an environmental document, the lead agency and cooperating agencies shall—

[p. 42, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=42) (indent level 3)

“(A) evaluate the proposed agency action in a single environmental document;

[p. 42, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=42) (indent level 3)

“(B) carry out the obligations of each respective agency concurrently, and in conjunction with, other environmental reviews and authorizations being conducted by other Federal agencies, unless the agency determines that doing so would impair the ability of the agency to carry out the statutory obligations of the agency; and

[p. 43, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43) (indent level 3)

“(C) formulate and implement administrative, policy, and procedural mechanisms to ensure that the environmental review is coordinated, environmentally responsible, and enables the lead agency to comply with the deadlines described in subsection (g).

[p. 43, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43) (indent level 2)

“(3) CONSIDERATION OF TIMING.—

[p. 43, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43) (indent level 3)

“(A) IN GENERAL.—No Federal agency shall be required to consider any scientific or technical research that becomes publicly available after the date of publication of a notice of intent or decision to prepare an environmental document for a proposed agency action.

[p. 43, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=43) (indent level 3)

“(B) DELAY.—A Federal agency may not delay the issuance of an environmental document or authorization beyond the deadline for the proposed agency action under subsection (g) on the basis of awaiting new scientific or technical research or information that was not available as of the date described in subparagraph (A) for the proposed agency action.

[p. 44, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 3)

“(C) APPLICABILITY TO OTHER LAW.— Nothing in this paragraph affects any review of information required under subchapter II of chapter 5 of title 5, United States Code, with respect to comments received during a public comment period, as applicable.

[p. 44, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 1)

“(c) PUBLIC REVIEW.—

[p. 44, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 2)

“(1) PUBLICATION IN FEDERAL REGISTER.— Each notice of intent to prepare an environmental impact statement under section 102 shall be published in the Federal Register.

[p. 44, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 2)

“(2) PUBLIC COMMENT.—

[p. 44, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 3)

“(A) REQUIREMENTS.—Each notice of intent to prepare an environmental impact statement under section 102 shall include—

[p. 44, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 4)

“(i) a request for public comment on alternatives or impacts and on relevant information, studies, or analyses with respect to the proposed agency action; and

[p. 44, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 4)

“(ii) a concise description of the general location of the proposed agency action and a summary of geospatial information for the proposed agency action, if available.

[p. 44, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=44) (indent level 3)

“(B) COMMENT PERIOD.—The lead agency shall establish a comment period of not less than 45 days and not more than 60 days after the date on which the notice to prepare an environmental impact statement is published in the Federal Register, unless the lead agency and project sponsor agree to a longer deadline, which shall not exceed 75 days.”;

[p. 45, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 2)

(2) in subsection (e), by redesignating paragraphs (1) and (2) as paragraphs (2) and (1), respectively, and moving the paragraphs so as to appear in numerical order;

[p. 45, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 2)

(3) in subsection (f)—

[p. 45, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 3)

(A) in the subsection heading, by inserting “ AND USE OF EXISTING DOCUMENTS” after “PREPARATION”;

[p. 45, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 3)

(B) by striking “A lead agency” and inserting the following:

[p. 45, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 2)

“(1) IN GENERAL.—A lead agency”; and

[p. 45, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 3)

(C) by adding at the end the following:

[p. 45, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=45) (indent level 2)

“(2) EXISTING DOCUMENTS.—On the request of a project sponsor, a lead agency shall consider and, as appropriate, adopt or incorporate by reference, the analysis and documentation prepared for a proposed agency action under the laws and procedures of a State or an Indian Tribe as the documentation, or part of the documentation, required to complete an environmental review, if the analysis and documentation were developed pursuant to laws and procedures of the State or Indian Tribe that serve a similar function as Federal agency compliance with this Act, as determined by the lead agency.”;

[p. 46, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46) (indent level 2)

(4) in subsection (g)—

[p. 46, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46) (indent level 3)

(A) by striking paragraph (1) and inserting the following:

[p. 46, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46) (indent level 2)

“(1) IN GENERAL.—

[p. 46, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46) (indent level 3)

“(A) ENVIRONMENTAL ASSESSMENTS.—

[p. 46, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46) (indent level 4)

“(i) IN GENERAL.—Except as provided in section 106(b)(1)(B) or paragraph (2), with respect to a proposed agency action, a lead agency shall complete and make public the environmental assessment, if applicable, not later than the date that is 1 year after the earlier of, as applicable—

[p. 46, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=46) (indent level 5)

“(I) the date on which the lead agency determines that section 106(b)(1)(A) requires the preparation of an environmental assessment with respect to the proposed agency action; and

[p. 47, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=47) (indent level 5)

“(II) the date on which the lead agency notifies the project sponsor that the application for the proposed agency action is complete.

[p. 47, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=47) (indent level 4)

“(ii) ADDITIONAL REQUIREMENTS.— On completion of an environmental assessment—

[p. 47, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=47) (indent level 5)

“(I)(aa) not later than 7 days after the date on which the lead agency completes and makes public the environmental assessment, the lead agency shall issue a finding of no significant impact;

[p. 47, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=47) (indent level 6)

“(bb) not later than 90 days after the date on which the lead agency completes and makes public the environmental assessment, all Federal agencies participating in the environmental review shall issue and make public a decision on all outstanding authorizations for the proposed agency action; and

[p. 47, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=47) (indent level 6)

“(cc) not later than 120 days after the date on which the lead agency completes and makes public the environmental assessment, all Federal agencies not participating in the environmental review shall issue and make public a decision on all outstanding authorizations for the proposed agency action; or

[p. 48, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48) (indent level 5)

“(II) not later than 7 days after the date on which the lead agency completes the environmental assessment, the lead agency shall publish a notice of intent to prepare an environmental impact statement.

[p. 48, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48) (indent level 3)

“(B) ENVIRONMENTAL IMPACT STATEMENTS.—

[p. 48, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48) (indent level 4)

“(i) IN GENERAL.—Except as provided in paragraph (2), with respect to a proposed agency action, the lead agency shall publish an environmental impact statement, if applicable, not later than the date that is 2 years after the earlier of, as applicable—

[p. 48, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48) (indent level 5)

“(I) the date on which the lead agency determines that section 102(2)(C) requires the issuance of an environmental impact statement with respect to the proposed agency action; and

[p. 49, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49) (indent level 5)

“(II) the date on which the lead agency notifies the project sponsor that the application for the proposed agency action is complete.

[p. 49, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49) (indent level 4)

“(ii) ADDITIONAL REQUIREMENTS.—

[p. 49, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49) (indent level 5)

“(I) RECORD OF DECISION.—Not later than 45 days after the date on which the lead agency publishes an environmental impact statement for a proposed agency action, the lead agency shall issue a record of decision.

[p. 49, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49) (indent level 5)

“(II) ISSUANCE OF AUTHORIZATIONS.—

[p. 49, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=49) (indent level 6)

“(aa) IN GENERAL.—Not later than 90 days after the date on which the lead agency publishes an environmental impact statement for a proposed agency action, all Federal agencies participating in the environmental review shall issue a decision on all outstanding authorizations for the proposed agency action.

[p. 50, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=50) (indent level 6)

“(bb) FEDERAL AGENCIES NOT PARTICIPATING.—Not later than 120 days after the date on which the lead agency publishes an environmental impact statement for a proposed agency action, all Federal agencies not participating in the environmental review shall issue and make public a decision on all outstanding authorizations for the proposed agency action.

[p. 50, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=50) (indent level 4)

“(iii) SAVINGS PROVISION.—Nothing in this subparagraph prohibits an agency from issuing an environmental impact statement and record of decision in a single document.

[p. 50, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=50) (indent level 3)

“(C) DISPUTE RESOLUTION.—

[p. 50, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=50) (indent level 4)

“(i) DEFINITION OF ELIGIBLE DISPUTE OR DELAY.—In this subparagraph, the term ‘eligible dispute or delay’ means a dispute or delay with respect to an environmental review or authorization involving more than 1 Federal agency for which a project sponsor sends a notification to the Chairman under clause (ii).

[p. 51, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=51) (indent level 4)

“(ii) NOTIFICATION OF DISPUTE.— The Chairman, in consultation with each Federal agency participating in the environmental review for a proposed agency action, shall, to the maximum extent practicable to meet the deadlines established under this subsection and the schedule developed under subsection (a)(1)(C)(iv), facilitate resolution of an eligible dispute or delay, including an anticipated delay, between those Federal agencies with respect to an environmental review or authorization not later than 30 days after the date of receipt of a notification from a project sponsor.

[p. 51, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=51) (indent level 4)

“(iii) DETERMINATION OF RESOLUTION.— If an eligible dispute or delay, including an anticipated delay, described in clause (ii) remains unresolved by the date that is 30 days after the date on which a notification is received under that clause, the Chairman, not later than 14 days after that date, shall determine a resolution and order the relevant agencies to the eligible dispute or delay, including an anticipated delay, to act in accordance with that determination as soon as practicable.

[p. 52, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52) (indent level 4)

“(iv) FINAL RESOLUTION.—Notwithstanding any other provision of law, any order given or action taken by the Chairman in resolution of an eligible dispute or delay, including an anticipated delay, under clause (iii)—

[p. 52, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52) (indent level 5)

“(I) shall be final and conclusive;

[p. 52, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52) (indent level 5)

“(II) shall not be subject to judicial review; and

[p. 52, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52) (indent level 5)

“(III) shall, for purposes of judicial review of the ultimate agency action and all other Federal law, constitute full compliance with and satisfaction of any requirement for interagency consultation, coordination, concurrence, authorization, or other procedural obligation under Federal law that is the subject of the dispute or delay.”;

[p. 52, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=52) (indent level 3)

(B) in paragraph (2)—

[p. 53, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53) (indent level 4)

(i) by inserting “applicable” before “deadline described in paragraph (1)”;

[p. 53, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53) (indent level 4)

(ii) by striking “in consultation with the applicant” and inserting “with the approval of the project sponsor”; and

[p. 53, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53) (indent level 4)

(iii) by striking “such environmental impact statement or environmental assessment” and inserting “the applicable environmental document”; and

[p. 53, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53) (indent level 3)

(C) by striking paragraph (3) and inserting the following:

[p. 53, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53) (indent level 2)

“(3) FAILURE TO ACT.—

[p. 53, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=53) (indent level 3)

“(A) IN GENERAL.—If, after 30 days have passed from the date on which the Chairman determines that a key permitting agency has not acted in accordance with a determination under subparagraph (C)(iii) of paragraph (1) and causes a failure to comply with a deadline in accordance with that paragraph or an extended deadline in accordance with paragraph (2), each relevant agency CERPO of the key permitting agency and each career employee of the key permitting agency within the Senior Executive Service (as defined in section 2101a of title 5, United States Code) that has supervisory authority over personnel in the key permitting agency and that has a substantive role or responsibility in reviewing the applicable environmental document or authorization that remains unpublished or unissued, shall spend not less than 50 percent of the workweek, as determined pursuant to title 5, United States Code, or other applicable law, to remedy the failure.

[p. 54, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=54) (indent level 3)

“(B) NO TRAVEL OUTSIDE DUTY STATION.— If, after 60 days have passed from the date on which a deadline described in paragraph (1) or (2) was failed to be met and the key permitting agency has not published or made public the applicable environmental document and has not issued all outstanding authorizations, as described in those paragraphs, with respect to a proposed agency action, the head of the relevant key permitting agency shall not travel more than 25 miles from their official duty station for the purposes of official business until the key permitting agency has published or made public the applicable environmental document and issued all outstanding authorizations related to the proposed agency action that are not in compliance with the requirements of this subsection.

[p. 55, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 3)

“(C) EXCEPTION.—This paragraph shall not apply to the Secretary of Defense.

[p. 55, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 2)

“(4) CAUSES OF ACTION.—

[p. 55, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 3)

“(A) DEFINITION OF COURT OF COMPETENT JURISDICTION.—In this paragraph, the term ‘court of competent jurisdiction’ means—

[p. 55, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 4)

“(i) if a court has jurisdiction over an applicable proposed agency action pursuant to any other provision of Federal law other than this Act, such court; or

[p. 55, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 4)

“(ii) if no such court exists under clause (i), the district court of the United States for the district in which a substantial part of the applicable proposed agency action is situated.

[p. 55, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 3)

“(B) RIGHT TO PETITION.—A project sponsor may obtain judicial review of the compliance by a Federal agency with the relevant deadline established under paragraph (1) or (2) by filing a written petition in a court of competent jurisdiction.

[p. 55, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=55) (indent level 3)

“(C) EXCEPTIONS.—The failure of a Federal agency to publish in the Federal Register or make public an environmental document or issue a decision on all necessary authorizations shall not be considered failure to comply with the deadlines established under paragraph (1) or (2) if the Federal agency proves by clear and convincing evidence that the failure was caused by—

[p. 56, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=56) (indent level 4)

“(i) a natural disaster, act of God, or act of war that reasonably impaired the ability of the Federal agency to comply with the relevant deadline established under paragraph (1) or (2);

[p. 56, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=56) (indent level 4)

“(ii) a national emergency for which the only available response is to delay the publication or making public the environmental document or withhold decisions on the relevant authorizations by the relevant deadline established under paragraph (1) or (2);

[p. 56, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=56) (indent level 4)

“(iii) the publication or making public of the environmental document or issuance of the authorization violating the statutory obligations of the Federal agency;

[p. 56, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=56) (indent level 4)

“(iv) the completed application of the project sponsor under section 110 being based on fraud or material misrepresentations of fact;

[p. 57, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=57) (indent level 4)

“(v) the project sponsor withholding information necessary to the ability of the Federal agency to comply with its statutory obligations in publishing or making public an environmental document or issuing a decision on all necessary authorizations, after the Federal agency has made a reasonable and timely request for such information; or

[p. 57, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=57) (indent level 4)

“(vi) a lapse in appropriations of more than 2 weeks affecting 1 or more of the relevant agencies involved in the preparation of the environmental documents or authorizations.

[p. 57, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=57) (indent level 3)

“(D) REMEDY.—If a court of competent jurisdiction finds that a Federal agency has failed to act in accordance with this subsection, the court shall provide injunctive relief, as appropriate, to give effect to this section and retain jurisdiction to ensure compliance with any such relief.

[p. 57, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=57) (indent level 3)

“(E) EXPEDITED PROCEDURES; TIME TO DECIDE.—The reviewing court shall—

[p. 58, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 4)

“(i) establish an expedited schedule for briefing and disposition;

[p. 58, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 4)

“(ii) issue a decision as expeditiously as practicable, but not later than 120 days after the date on which the petition is filed, absent extraordinary circumstances; and

[p. 58, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 4)

“(iii) if the petition for relief is granted, issue an order requiring a decision on the covered application not later than 60 days after the date on which the order is issued.”; and

[p. 58, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 2)

(5) in subsection (h)—

[p. 58, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 3)

(A) in paragraph (1)—

[p. 58, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 4)

(i) in the matter preceding subparagraph (A), by striking “the Committee on Natural Resources of the House of Representatives and the Committee on Environment and Public Works of the Senate” and inserting “the Chairman, not later than April 15 of each year,”; and

[p. 58, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 4)

(ii) by striking subparagraphs (A) and (B) and inserting the following:

[p. 58, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=58) (indent level 3)

“(A) identifies each environmental document that was not completed by each lead agency by the deadline described in subsection (g) and provides an explanation for the failure to meet the deadline;

[p. 59, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=59) (indent level 3)

“(B) identifies each environmental document the preparation of which commenced before the date of enactment of the Fiscal Responsibility Act of 2023 (Public Law 118–5; 137 Stat. 10) and is not yet complete at the time of the report and provides an explanation for the failure to complete the environmental document;

[p. 59, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=59) (indent level 3)

“(C) details the on-time completion rate of each key permitting agency in adhering to applicable deadlines described in subsection (g); and

[p. 59, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=59) (indent level 3)

“(D) details the progress of each key permitting agency in adhering to those deadlines as compared to the completion rate during the preceding year.”; and

[p. 59, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=59) (indent level 3)

(B) in paragraph (2)—

[p. 59, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=59) (indent level 4)

(i) in subparagraph (A), by striking “such environmental assessment and environmental impact statement” and inserting “applicable environmental document”;

[p. 60, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 4)

(ii) by striking subparagraph (B) and inserting the following:

[p. 60, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 3)

“(B) the earlier of—

[p. 60, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 4)

“(i) with respect to an environmental assessment, as applicable—

[p. 60, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 5)

“(I) the date on which the lead agency determines that section 106(b)(1)(A) requires the preparation of an environmental assessment with respect to the proposed agency action; and

[p. 60, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 5)

“(II) the date on which the lead agency notifies the project sponsor that the application for the proposed agency action is complete; and

[p. 60, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 4)

“(ii) with respect to an environmental impact statement, as applicable—

[p. 60, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 5)

“(I) the date on which the lead agency determines that section 102(2)(C) requires the issuance of an environmental impact statement with respect to the proposed agency action; and

[p. 60, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=60) (indent level 5)

“(II) the date on which the lead agency notifies the project sponsor that the application for the proposed agency action is complete; and”; and

[p. 61, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=61) (indent level 4)

(iii) in subparagraph (C), by striking “environmental assessment and environmental impact statement” and inserting “environmental document”; and

[p. 61, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=61) (indent level 3)

(C) by adding at the end the following:

[p. 61, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=61) (indent level 2)

“(3) COMPILATION.—The Chairman shall—

[p. 61, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=61) (indent level 3)

“(A) compile the reports received by the heads of lead agencies under paragraph (1) each year;

[p. 61, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=61) (indent level 3)

“(B) provide recommendations on how to improve the performance of Federal agencies in adhering to the deadlines described in subsection (g); and

[p. 61, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=61) (indent level 3)

“(C) submit that compilation of those reports and those recommendations to the Committee on Environment and Public Works of the Senate and Committee on Natural Resources of the House of Representatives by not later than June 15 of the applicable year.”.