# Sec. 1109. Applications for authorizations

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/1109)

## Summary

Sets an application clock: within 60 days, an agency must say whether an application is complete. ([p. 64, line 22 to p. 64, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64)) Within another 60 days, the agency must tell the sponsor whether the action is excluded from NEPA. ([p. 65, line 14 to p. 65, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65)) The agency must also say whether the action needs an environmental assessment or gets a notice of intent for an EIS. ([p. 66, line 3 to p. 66, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66)) Applicants must submit a list of all known permits, a record of stakeholder engagement, and a statement of purpose and need. ([p. 66, line 23 to p. 66, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66))

## Key points

- 60 days to declare an application complete; 60 more to pick the level of review ([p. 65, line 14 to p. 65, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65))
- Applicants file a record of stakeholder engagement with the application ([p. 67, line 1 to p. 67, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=67))

## What others say it would do

Outside readings, quoted from their sources. These are claims about effects, not findings of this tracker.

- **Eno Center for Transportation** (Think tanks; mixed): Fixed completeness-determination timing improves predictability, but less room to iteratively request information could extend reviews.
  > they'll have less flexibility to iteratively identify new information needs, which can improve review accuracy but also extend review times.
  [Eno Center for Transportation, 2026-10-02](https://enotrans.org/article/senate-proposes-major-changes-to-permit-and-review-processes/). On the bill text at [p. 64, line 22 to p. 64, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64).

## Selected statutory quotes

> not later than 60 days after the date on which the project sponsor submits the application, the Federal agency shall— “(A) document receipt of the application; and “(B)(i) notify the project sponsor that the application is complete

[p. 64, line 22 to p. 65, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64)

The 60-day completeness check.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

New. The current section 110 ordered CEQ to study a permitting portal; that study is replaced by the eNEPA mandate in section 1121.

### EPRA 2024 (reported S. 4753)

Not in EPRA 2024.

### SPEED Act (House-passed H.R. 4776)

The SPEED Act (sec. 2(c)(4)) had the same 60-day completeness check and 60-day level-of-review decision. The required list of permits, record of stakeholder engagement and purpose-and-need description are Senate additions.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 64, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64) (indent level 0)

Section 110 of the National Environmental Policy Act of 1969 (42 U.S.C. 4336d) is amended to read as follows:

[p. 64, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64) (indent level 0)

“SEC. 110. APPLICATIONS FOR AUTHORIZATIONS.

[p. 64, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64) (indent level 1)

“(a) APPLICATION SUFFICIENCY.—

[p. 64, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=64) (indent level 2)

“(1) NOTIFICATION OF COMPLETE OR INCOMPLETE APPLICATION.—Unless a shorter deadline is specified by law, in connection with a proposed agency action for which a project sponsor submitted an application for an authorization to a Federal agency, not later than 60 days after the date on which the project sponsor submits the application, the Federal agency shall—

[p. 65, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 3)

“(A) document receipt of the application; and

[p. 65, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 3)

“(B)(i) notify the project sponsor that the application is complete; or

[p. 65, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 4)

“(ii) notify the project sponsor that the application is incomplete and request, in writing, any additional information that the Federal agency needs to determine that the application is complete.

[p. 65, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 2)

“(2) AGENCY DETERMINATION.—

[p. 65, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 3)

“(A) COMPLETE DETERMINATION.—If a Federal agency determines that an application is complete under paragraph (1)(B)(i), the Federal agency shall, not later than 60 days after the date on which the Federal agency makes that determination, unless a shorter period is provided for by law—

[p. 65, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 4)

“(i) notify the project sponsor that the Federal agency has determined that—

[p. 65, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 5)

“(I) the proposed agency action—

[p. 65, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 6)

“(aa) is excluded pursuant to a categorical exclusion; or

[p. 65, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=65) (indent level 6)

“(bb) is not a major Federal action; or

[p. 66, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66) (indent level 5)

“(II) no further agency action is required;

[p. 66, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66) (indent level 4)

“(ii) notify the project sponsor that the agency has determined that preparation of an environmental assessment is necessary; or

[p. 66, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66) (indent level 4)

“(iii) issue a notice of intent to prepare an environmental impact statement for the proposed agency action.

[p. 66, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66) (indent level 3)

“(B) INCOMPLETE DETERMINATION.—If a Federal agency requests additional information under paragraph (1)(B)(ii), the deadline described in subparagraph (A) shall be based on the date on which the Federal agency receives the additional information instead of the date on which the determination is made.

[p. 66, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66) (indent level 1)

“(b) ADDITIONAL APPLICATION INFORMATION.—Unless otherwise required by law, in addition to any information required by a Federal agency for an application for authorization for a proposed agency action requiring an environmental review, a project sponsor shall submit to the applicable Federal agency—

[p. 66, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=66) (indent level 2)

“(1) a list of each known Federal, State, Tribal, or local authorization required to complete the proposed agency action;

[p. 67, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=67) (indent level 2)

“(2) a record of stakeholder engagement for the proposed agency action as of the date of the application; and

[p. 67, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=67) (indent level 2)

“(3) a brief description of a statement of purpose and need for the proposed agency action, including, to the extent practicable, the location of the project and any known alternatives.”.