# Sec. 1205. Judicial review timeline clarity

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/1205)

## Summary

Adds a 150-day statute of limitations for challenges to section 404 permits, general permits, verifications and state program approvals. ([p. 129, line 10 to p. 129, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=129)) Where a draft was published with at least 30 days for comment, a plaintiff must have commented on the issue. ([p. 131, line 12 to p. 131, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131)) Remedies are limited to remand, with vacatur or injunction available only on a finding of imminent and substantial danger to health or the environment. ([p. 132, line 9 to p. 132, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=132)) Remand deadlines are capped at 180 days. ([p. 133, line 4 to p. 133, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=133))

## Key points

- 150-day limit on 404 permit suits ([p. 129, line 21 to p. 129, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=129))
- Permits stay in force on remand absent imminent and substantial danger ([p. 132, line 9 to p. 132, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=132))

## Selected statutory quotes

> the court may not vacate, revoke, enjoin, or otherwise limit the permit unless the court finds that activities authorized under the permit would present an imminent and substantial danger to human health or the environment

[p. 132, line 9 to p. 132, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=132)

A permit stays in force unless the work poses imminent and substantial danger.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

General 6-year APA limit and ordinary equitable remedies.

### EPRA 2024 (reported S. 4753)

EPRA 2024's 150-day rule applied to energy project authorizations generally, not 404 permits specifically.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 128, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=128) (indent level 0)

Section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) is amended—

[p. 128, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=128) (indent level 2)

(1) in subsection (t), by striking “(t) Nothing in this section” and inserting the following:

[p. 128, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=128) (indent level 1)

“(u) SAVINGS PROVISION.—Nothing in this section”; and

[p. 128, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=128) (indent level 2)

(2) by inserting after subsection (s) the following:

[p. 128, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=128) (indent level 1)

“(t) JUDICIAL REVIEW.—

[p. 129, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=129) (indent level 2)

“(1) STATUTE OF LIMITATIONS.—Notwithstanding any applicable provision of law relating to statutes of limitations—

[p. 129, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=129) (indent level 3)

“(A) an action seeking judicial review, under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the ‘Administrative Procedure Act’), or any other applicable provision of law, of the approval by the Administrator of a State permit program pursuant to this section shall be filed not later than the date that is 150 days after the date on which the approval was issued, unless a shorter time period is otherwise provided for by law;

[p. 129, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=129) (indent level 3)

“(B) an action seeking judicial review, under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the ‘Administrative Procedure Act’), or any other applicable provision of law, of an individual permit or general permit issued under this section shall be filed not later than the date that is 150 days after the date on which the permit was issued, unless a shorter time period is otherwise provided for by law; and

[p. 130, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=130) (indent level 3)

“(C) an action seeking judicial review, under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the ‘Administrative Procedure Act’), or any other applicable provision of law, of a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section shall be filed not later than the date that is 150 days after the date on which the verification was issued, unless a shorter time period is otherwise provided for by law.

[p. 130, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=130) (indent level 2)

“(2) LIMITATION ON COMMENCEMENT OF CERTAIN ACTIONS.—

[p. 130, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=130) (indent level 3)

“(A) IN GENERAL.—Notwithstanding any other provision of law but subject to subparagraph (B), no action described in subparagraph (A) or (B) of paragraph (1) may be commenced unless the action—

[p. 130, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=130) (indent level 4)

“(i) is filed by a party that submitted a comment—

[p. 130, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=130) (indent level 5)

“(I) during the public comment period for the administrative proceedings related to the action; and

[p. 131, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131) (indent level 5)

“(II) that is sufficiently detailed to put the Administrator, the Secretary, or the State, as applicable, on notice of the issue on which the party seeks judicial review; and

[p. 131, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131) (indent level 4)

“(ii) is related to that comment.

[p. 131, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131) (indent level 3)

“(B) LIMITATION.—The limitation under subparagraph (A) shall only apply to actions for which—

[p. 131, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131) (indent level 4)

“(i) a draft of the action was published in the Federal Register; and

[p. 131, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131) (indent level 4)

“(ii) the applicable agency provided a public comment period of not less than 30 days.

[p. 131, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=131) (indent level 2)

“(3) REMEDIES FOR ACTIONS RELATING TO PERMITS.—If a court determines that the Secretary or a State, as applicable, did not comply with the requirements of this section in issuing an individual or general permit under this section, or in verifying that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, or otherwise was arbitrary and capricious under subchapter II of chapter 5, and chapter 7, of title 5, United States Code (commonly known as the ‘Administrative Procedure Act’), as applicable—

[p. 132, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=132) (indent level 3)

“(A) the court shall remand the matter to the Secretary or the State, as applicable, for further proceedings consistent with the determination of the court;

[p. 132, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=132) (indent level 3)

“(B) with respect to a determination regarding the issuance of an individual or general permit under this section, the court may not vacate, revoke, enjoin, or otherwise limit the permit unless the court finds that activities authorized under the permit would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law; and

[p. 132, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=132) (indent level 3)

“(C) with respect to a determination regarding a verification that an activity involving a discharge of dredged or fill material is authorized by a general permit issued under this section, the court may not enjoin or otherwise limit the discharge unless the court finds that the activity would present an imminent and substantial danger to human health or the environment for which there is no other equitable remedy available under the law.

[p. 133, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=133) (indent level 2)

“(4) TIMELINE TO ACT ON COURT ORDER.—If a court remands a matter under paragraph (3), the court shall set and enforce a reasonable schedule and deadline, which may not exceed 180 days from the date on which the court remands the matter, except as otherwise required by law, for the Administrator, the Secretary, or the State, as applicable, to take such actions as the court may order.”.