ER27-25-000 · 2026-10-23 · DTE Electric

Comments of DTE Electric Company

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Reliability and curtailment

What the document says

PDF p. 2

Supporters say studying load and generation together removes duplicative upgrades and lowers costs.

By allowing large loads and associated generation resources to be studied together, the proposal recognizes that jointly planned and electrically proximate resources may produce materially different system impacts PDF p. 2

PDF p. 3

MISO says LARS answers the Show Cause Order and leaves the generator queue untouched.

The LARS filing also preserves an open and non-discriminatory framework by permitting the interconnection customer responsible for the generation component to be any eligible entity. PDF p. 3
Filed comments: Connecting load and generation

PDF p. 3

Supporters want FERC to accept LARS as filed, citing its entry limits and fuel neutrality.

These requirements provide reasonable assurance that participating projects represent durable load-generation relationships and help mitigate potential impacts to the transmission system and other customers. PDF p. 3

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midcontinent Independent System ) Docket No.
Read this passage Filed comments: Connecting load and generation

I. Background

printed heading

I.
Read this passage

Background

printed heading · Topic match: Connecting load and generation

Background In this proceeding, MISO proposes revisions to its Tariff to establish the LARS framework.
Read this passage Filed comments: Connecting load and generation

II. COMMENTS

printed heading · Topic match: Connecting load and generation

COMMENTS DTE Electric supports the LARS filing and respectfully requests that the Commission accept the filing as proposed.
Read this passage Filed comments: Connecting load and generation

A. The LARS filing is a just and reasonable solution to integrate new large loads

printed heading · Topic match: Connecting load and generation

Accordingly, DTE Electric respectfully requests that the Commission approve the LARS Filing as proposed.
Read this passage Filed comments: Connecting load and generation

III. COMMUNICATIONS

printed heading

COMMUNICATIONS DTE Electric requests that all communications, correspondence, documents, and other materials related to this proceeding be addressed to the following persons: 4 Tristin Rojeck Regulatory Affairs DTE Electric Company One Energy Plaza Detroit, Michigan 48226 (313) 235-1041…
Read this passage

IV. CONCLUSION

printed heading

IV.
Read this passage

CONCLUSION

printed heading · Topic match: Connecting load and generation

Accordingly, DTE Electric respectfully requests that the Commission accept the LARS Filing as proposed.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

ER27-25. /s/ Andrea Hayden