EL26-70: the filed comments

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Cost allocation

Individual No Affiliation

EL26-70-000 · 2026-06-24

As a local concerned citizen regarding the Viridon WISE project in Wisconsin, I formally asked ATC to evaluate upgrading their existing infrastructure (such as reconductoring) as a cheaper, ratepayer-protective alternative to Viridon's $350 million greenfield transmission line. PDF p. 1

US HOUSE OF REPRESENTATIVES

EL26-70-000 · 2026-09-10

Request for Independent Review and Concrete Data: I respectfully request that the Departments coordinate with FERC and other appropriate federal agencies to conduct an independent review addressing interstate grid reliability, water resources, infrastructure, cost allocation, and transparency. PDF p. 4

Reliability and curtailment

Organization of MISO States, Inc.

EL26-70-000 · 2026-08-14

state and local regulators play a central role in ensuring reliable, affordable electric service and should remain active participants in discussions regarding resource adequacy. PDF p. 2

Retail and wholesale authority

Organization of MISO States, Inc.

EL26-70-000 · 2026-08-14

OMS remains committed to working constructively with MISO and stakeholders to strengthen the existing framework while preserving state authority over resource adequacy and ensuring that reforms continue to support reliable service, efficient markets, and reasonable customer costs. PDF p. 2