ER26-3552: the filed comments
These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.
Connecting load and generation
ER26-3552-000 · 2026-09-11
MISO should clearly specify how such transitions will be sequenced, how queue position and study impacts will be determined, and how transmission capability reserved or relied upon under ZGIA will be treated when the resource seeks broader injection rights. PDF p. 10
Cost allocation
ER26-3552-000 · 2026-09-11
OMS’s support, however, is conditioned on maintaining the fundamental principles of reliability, cost causation, transparency, and equitable treatment of customers and market participants as detailed above. PDF p. 13
Filing procedure
ER26-3552-000 · 2026-09-11
12 Answer in Support of the Motion to Hold Proceeding in Abeyance of MISO and the MISO Transmission Owners of OMS, Docket No. PDF p. 12
Reliability and curtailment
ER26-3552-000 · 2026-09-11
OMS cautiously supports the ZGIA proposal but highlights several critical reliability and resource adequacy concerns for the Commission’s consideration. PDF p. 1
Retail and wholesale authority
ER26-3552-000 · 2026-09-08
Consumers Energy requests, however, that the Commission ensure that any order accepting the MISO Filing expressly preserves state authority over retail loads and does not permit Commission-jurisdictional processes to supersede, preempt, or otherwise displace state regulation of retail electric service. PDF p. 1