EL26-72-000 · 2026-06-18 · FERC

ISO-NE show cause order

Topics in the text: Connecting load and generation · Cost allocation · Filing procedure

Responses and related views

Eolian wants nearby generation considered for permanent service

Eolian · Direct response

Eolian sought clarification that generation located electrically close to a large load could qualify for permanent limited service if it could constrain grid withdrawals over the long term. FERC dismissed the request because the preliminary order was not final.

Eolian request and FERC discussion (unpaginated)

LaCerte urged timely regional answers

Commissioner David LaCerte · Direct response

LaCerte supported the order as a way to identify gaps in large-load tariffs. He expected a timely response with evidence about the region’s own rules, not a final nationwide tariff imposed in June.

PDF pp. 112–114, LaCerte concurrence

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

195 FERC ¶ 61,215 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on

printed heading

D.
Read this passage

E. Interconnection Customers Serving Electrically Proximate Large Load and Co-

printed heading · Topic match: Connecting load and generation

EL26-72-000 - 3 - Over the past year, the Commission has taken action in numerous dockets1 to address issues related to (a) unprecedented increases in requests for transmission service to serve large loads2 and (b) growing interest in the co-location of loads with generating facilities (co-location…
Read this passage

I. Background

PDF bookmark

I.
Read this passage

Background

printed heading

Background
Read this passage

A. Growth of Large and Co-Located Loads and ANOPR

PDF bookmark · Topic match: Cost allocation

Dep’t of Energy, Resource Adequacy Report: Evaluating the Reliability & Security of the United States Electric Grid (July 2025), www.energy.gov/sites/default/files/2025- 07/DOE%20Final%20EO%20Report%20%28FINAL%20JULY%207%29.pdf). 15 Id. (citing NERC, 2024 Long- Term Reliability Assessment 8 (Dec.…
Read this passage

B. Recent Proceedings Addressing Large and Co-Located Loads

PDF bookmark · Topic match: Filing procedure

Representatives November 21 ANOPR Comments at 1. 41 See, e.g., AI Supply Chain Alliance November 21 ANOPR Comments at 2; DCC November 21 ANOPR Comments at 3; ECA November 21 ANOPR Comments at 6; Geronimo November 21 ANOPR Comments at 1-2; Google November 21 ANOPR Comments at 2-3; Verrus December 5…
Read this passage

1. PJM Co-Location Proceedings

PDF bookmark · Topic match: Connecting load and generation

EL26-72-000 - 14 - Specifically, the Commission found that the PJM tariff was unjust and unreasonable because there is a lack of sufficient clarity or consistency as to the rates, terms, and conditions of service that apply to interconnection customers serving co-located load.47 The Commission also…
Read this passage

2. SPP High Impact Large Load and High Impact Large Load Generation Assessment Processes

PDF bookmark · Topic match: Connecting load and generation

P 32 (explaining that SPP will grant HILLGA customers a new type of interconnection service, load limited resource interconnection service, which grants limited interconnection service solely to serve the associated HILL). 60 Id.
Read this passage

3. SPP Conditional High Impact Large Load Service

PDF bookmark · Topic match: Reliability and curtailment

For the HILL supplemental load connection study, SPP allows the host transmission owner to require a $25,000 study deposit.
Read this passage

II. ISO-NE’s Existing Processes

PDF bookmark

II.
Read this passage

A. Existing Tariff Processes

PDF bookmark · Topic match: Connecting load and generation

EL26-72-000 - 24 - upgrades, distribution upgrades, or system protection facilities.107 In evaluating a request for provisional interconnection service, ISO-NE and the Interconnecting Transmission Owner shall determine, through available studies or additional studies as necessary, whether…
Read this passage

B. Recent Stakeholder Proceedings in ISO-NE

PDF bookmark · Topic match: Connecting load and generation

As such, and as the Commission explained in the April Order Regarding Intent to Act, we find that the Commission must now take further action to ensure that ISO-NE promptly proposes revisions to ensure that its Tariff remains just and reasonable.
Read this passage

III. Discussion

PDF bookmark

III.
Read this passage

Discussion

printed heading · Topic match: Filing procedure

We emphasize that we will not grant such abeyances reflexively, that any abeyance will be limited to 90 days, and that we will look with great disfavor toward requests to extend the abeyance period.
Read this passage

A. Transmission Service to Eligible Customers on Behalf of Large Loads

PDF bookmark · Topic match: Filing procedure

Co., 46 FERC ¶ 61,153, order on reh’g, 47 FERC ¶ 61,275 (1989). 119 As discussed below, our findings here also apply to the study process for unbundled retail transmission service requests by end-use large load customers, as allowed by state law or voluntary utility rules.
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Retail and wholesale authority

Specifically, we find that it is within the Commission’s exclusive authority to ensure that transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers on behalf of large loads interconnecting…
Read this passage

2. Tariff Provisions

PDF bookmark · Topic match: Cost allocation

EL26-72-000 - 36 - study process, wasting time and resources for transmission providers;148 result in inaccurate study results or delays for other Eligible Customers seeking transmission service on behalf of load;149 create a substantial risk of cost shifts if the large load additions do not…
Read this passage

B. Cost Shifting Risk Among Transmission Customers

PDF bookmark · Topic match: Cost allocation

Cost Shifting Risk Among Transmission Customers We next preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for…
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Cost allocation

To fulfill its responsibility to ensure that transmission rates are just and reasonable, the Commission must act to address the risk of cost shifting among transmission customers due to (1) the process transmission providers and/or transmission owners use to evaluate the facilities needed, and the…
Read this passage

2. Additional Cost Transparency

PDF bookmark · Topic match: Cost allocation

The speed and scale with which Eligible Customers are seeking transmission service on behalf of large loads makes it difficult for interested parties, including transmission customers and state regulators, to accurately assess which transmission costs are driven by requests for transmission service…
Read this passage

3. Cost Recovery Agreements

PDF bookmark · Topic match: Cost allocation

EL26-72-000 - 50 - in the record contend that, while a retail-level large load tariff protects the load serving entity taking wholesale transmission service and its retail customers, it fails “to provide any mechanism to protect other wholesale transmission customers” from stranded transmission…
Read this passage

C. Co-Location Arrangements and Load with Behind the Meter Generation

PDF bookmark · Topic match: Connecting load and generation

We direct ISO-NE and the Participating Transmission Owners, to the extent the matters addressed herein implicate aspects of the Tariff over which they have the filing rights, to explain whether the Tariff remains just and reasonable without provisions addressing the rates, terms and conditions that…
Read this passage

1. Definition

PDF bookmark · Topic match: Connecting load and generation

See infra P 88. 193 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 2; PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at PP 91-102. 194 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 164 (alterations in original). 195 Id.
Read this passage

2. Jurisdiction

PDF bookmark · Topic match: Connecting load and generation

As we explained in the PJM Co- Location Order, states retain exclusive authority over the specific terms of retail sales and retail rate design, including retail cost allocation to the co-located load; which entities are legally permitted to provide electricity to retail customers in co-location…
Read this passage

3. Tariff Provisions

PDF bookmark · Topic match: Connecting load and generation

Additionally, in the PJM Co-Location Order, the Commission found that it was necessary to clarify that interconnection customers seeking to use new generating facilities to serve co-located load may (1) request interconnection service at a level below the generating facility’s maximum facility…
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads

PDF bookmark · Topic match: Filing procedure

Finally, we note that the Commission has found it just and reasonable that, in order for an Eligible Customer to take interim NITS, firm contract demand transmission service, and non-firm contract demand transmission service, an Eligible Customer must have necessary control technologies and/or…
Read this passage

E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load

PDF bookmark · Topic match: Connecting load and generation

EL26-72-000 - 64 - together present a more complete picture of the grid and can enable the identification of more accurate, efficient, and cost-effective transmission solutions by minimizing system impacts.233 As a result, this can speed up the interconnection process for both large loads and…
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Connecting load and generation

The Commission has exercised this jurisdiction previously in requiring generator interconnection services that allow certain generating facilities to interconnect more quickly through the use of provisional interconnection service and surplus interconnection service,254 and has approved…
Read this passage

2. Definitions

PDF bookmark

Definitions For purposes of this order, it appears to be reasonable to use the term “electrically proximate large load” to mean a large load, as defined in this order,256 that is sufficiently electrically close to the interconnection customer’s requested point of interconnection, such that the…
Read this passage

3. Tariff Provisions

PDF bookmark · Topic match: Connecting load and generation

EL26-72-000 - 73 - electrically proximate large load or large co-located load.273 We note that, in the PJM Co-Location Order, the Commission found that the Eligible Customer must take transmission service on behalf of co-located load that will not withdraw energy from the transmission system, even…
Read this passage

F. Informational Report

PDF bookmark · Topic match: Reliability and curtailment

The informational report must include a detailed schedule of key milestones, such as stakeholder or ISO-NE Board votes, that includes the estimated date on which ISO-NE expects to file any such proposals with the Commission.
Read this passage

IV. Briefing Questions

PDF bookmark · Topic match: Cost allocation

We find that there may be a variety of possible approaches to protect customers from significant cost shifts associated with network upgrades triggered by large loads.
Read this passage

I. Overview of Today’s Orders

PDF bookmark · Topic match: Cost allocation

Overview of Today’s Orders In each of today’s orders to show cause, the Commission identifies a series of issues raised by the ongoing growth of large loads, directs briefing on whether existing tariffs remain just and reasonable in light of those developments, and describes possible solutions to…
Read this passage

II. The Commission Needs Good Records to Ensure Reasoned Decision-Making

PDF bookmark

The Commission Needs Good Records to Ensure Reasoned Decision-Making I first want to emphasize that the Commission needs active participation from interested stakeholders to develop thorough records in each region.
Read this passage

III. The Commission Needs to Pursue Meaningful Customer Protection

PDF bookmark · Topic match: Cost allocation

As we develop the new infrastructure, many have raised concerns about whether these costs are being fairly assigned to new and existing customers, whose benefits must be commensurate with the costs they pay.
Read this passage

IV. The Commission Needs to Understand the Implications of Extending New Transmission Services to Additional Loads and Regions

PDF bookmark · Topic match: Cost allocation

While it is important to identify innovative solutions that can adapt to the needs of the system, the Commission and grid operators must also be careful not to implement changes that create unforeseen reliability risks.
Read this passage

V. The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies

PDF bookmark

The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies Lastly, today we preliminarily find that each RTO/ISO’s tariff is unjust and unreasonable because the tariff lacks clear and consistent provisions requiring the evaluation of alternative transmission technologies…
Read this passage

VI. Conclusion

PDF bookmark

VI.
Read this passage

Conclusion

printed heading · Topic match: Cost allocation