EL26-67-000 · 2026-06-18 · FERC
PJM show cause order
Back to sections and commentaryPDF page 1
195 FERC ¶ 61,211
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Before Commissioners: Laura V. Swett, Chairman;
David Rosner, Lindsay S. See,
Judy W. Chang, and David LaCerte.
PJM Interconnection, L.L.C.
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated
Appalachian Power Company
Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
Dayton Power and Light Company
Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company
Kentucky Power Company
Keystone Appalachian Transmission Company
Kingsport Power Company
Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC
Monongahela Power Company
Neptune Regional Transmission System, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Ohio Power Company
Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
Docket No. EL26-67-000PDF page 2
Docket No. EL26-67-000
- 2 -
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Silver Run Electric, LLC
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
ORDER INSTITUTING PROCEEDING
UNDER SECTION 206 OF THE FEDERAL POWER ACT
(Issued June 18, 2026)
Paragraph Numbers
I. Background ..................................................................................................................... 6.
A. Growth of Large and Co-Located Loads and ANOPR ............................................. 6.
B. Recent Proceedings Addressing Large and Co-Located Loads .............................. 11.
1. PJM Co-Location Proceedings ............................................................................ 12.
2. SPP High Impact Large Load Process and High Impact Large Load Generation
Assessment Processes .............................................................................................. 15.
3. SPP Conditional High Impact Large Load Service ............................................. 17.
II. PJM’s Existing Processes ............................................................................................ 19.
A. Existing Tariff Processes ......................................................................................... 19.
B. Recent Stakeholder Proceedings in PJM ................................................................. 31.
III. Discussion ................................................................................................................... 35.
A. Transmission Service to Eligible Customers on Behalf of Large Loads ................ 41.
1. Jurisdiction ........................................................................................................... 44.
2. Tariff Provisions .................................................................................................. 50.
B. Cost Shifting Risk Among Transmission Customers .............................................. 66.
1. Jurisdiction ........................................................................................................... 68.
2. Additional Cost Transparency ............................................................................. 71.
3. Cost Recovery Agreements ................................................................................. 77.
C. Extending New Transmission Services to Eligible Customers Taking Service on
Behalf of Flexible Large Loads ................................................................................... 85.
PDF page 3
Docket No. EL26-67-000
- 3 -
D. Interconnection Customers Serving Electrically Proximate Large Load and Co-
Located Load ................................................................................................................ 88.
1. Jurisdiction ........................................................................................................... 92.
2. Definitions ........................................................................................................... 94.
3. Tariff Provisions .................................................................................................. 95.
E. Informational Report ............................................................................................. 102.
IV. Briefing Questions .................................................................................................... 105.
PDF page 4
Docket No. EL26-67-000
- 4 -
Over the past year, the Commission has taken action in numerous dockets1 to
address issues related to (a) unprecedented increases in requests for transmission service
to serve large loads2 and (b) growing interest in the co-location of loads with generating
facilities (co-location arrangements3). Separately, the Secretary of Energy (Secretary)
released an advance notice of proposed rulemaking (ANOPR) in October 2025. The
ANOPR, issued pursuant to section 403 of the Department of Energy Organization Act,4
directed the Commission to consider taking additional actions to address the addition of
large and co-located loads to the transmission system.5 The records in these proceedings
illustrate a host of urgent challenges associated with providing the transmission service
needed to serve the ongoing influx of large loads while maintaining reliability and
affordability. In particular, stakeholders have expressed concerns that large loads are not
efficiently and appropriately integrated onto the transmission system; have identified a
1 See, e.g., PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (PJM Show
Cause Order); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (PJM
Co-Location Order); Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (SPP HILL
Order); Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026) (SPP CHILLS Order); see also,
e.g., Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025); Commonwealth Edison
Co., 194 FERC ¶ 61,181 (2026).
2 As explained below, it appears that it would be reasonable to define a large load
as (1) a new commercial or industrial customer, (2) located at a single site behind one or
more points of interconnection, (3) that has a peak load of 50 MW or greater, (4)
interconnects to the transmission system at a voltage level of greater than 69 kV, and
(5) is not part of a co-location arrangement. See infra P 58.
3 The PJM Co-Location Order defined co-located load as “configuration [that]
refers to end-use customer load that is physically connected to the facilities of an existing
or planned Customer Facility on the Interconnection Customer’s side of the Point of
Interconnection to the PJM Transmission System.” PJM Co-Location Order, 193 FERC
¶ 61,217 at P 164 (alterations in original). The PJM Co-Location Order used the term
co-location arrangement when referring to both the co-located load and the associated
generator. Id. P 3.
4 42 U.S.C. § 7173.
5 See Interconnection of Large Loads to the Interstate Transmission System,
Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 23, 2025)
(ANOPR); see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy, Docket
No. RM26-4-000 (Oct. 23, 2025). The ANOPR uses the term “hybrid facilities,” which it
explains are large loads that “share a point of interconnection with new or existing
generation facilities.” ANOPR at P 12. In this order, we use the term co-located load.
PDF page 5
Docket No. EL26-67-000
- 5 -
number of unique challenges that large load integration poses for the reliable operation of
that system; and have debated how best to ensure that the rates, terms, and conditions of
transmission service remain just and reasonable as more and more large loads are
onboarded onto that system.6 The records in these proceedings likewise present serious
concerns about the lack of clarity and consistency in Regional Transmission Organization
or Independent System Operator (RTO/ISO) tariffs—including with respect to the rates,
terms, and conditions of service that apply to flexible large loads, co-location
arrangements, load with behind the meter generation, and generating facilities with
electrically proximate large load7 or co-located load.
The findings in several recent Commission proceedings establish the foundations
of a just and reasonable framework for addressing these concerns and ensuring the
timely, efficient, and reliable integration of large and co-located loads onto the
transmission system. For example, Southwest Power Pool, Inc. (SPP) has recently taken
a number of innovative and proactive steps to address the challenges of integrating large
loads, co-located loads, and/or generation and electrically proximate large load onto the
transmission system while ensuring that its tariff remains just and reasonable.8 PJM
Interconnection, L.L.C. (PJM), through the Commission’s show cause proceedings, is
also addressing the rates, terms, and conditions of service that apply to co-location
arrangements and establishing new transmission services that reflect the ability of
Eligible Customers9 taking transmission service on behalf of Eligible Load to limit their
6 Throughout this order we rely on comments and answers filed in response to the
ANOPR in Docket No. RM26-4-000 and all referenced comments in this order were filed
in that docket, unless otherwise noted. A full list of commenter names and abbreviations
is attached to this order as an Appendix. Additionally, we have relied on the discussions
held in the Federal and State Current Issues Collaborative in Docket No. AD24-7-000
(NARUC Collaborative). All entities who wish to participate in this docket, regardless of
participation in the ANOPR proceeding or NARUC Collaborative, should file to
intervene in Docket No. EL26-67-000.
7 As explained below, for purposes of this order, an “electrically proximate large
load” is a large load, as defined in this order, that is sufficiently electrically close to the
interconnection customer’s requested point of interconnection, such that the impact on
the transmission system of the combination of the generating facility and the load, with
the exception of the transmission facilities between the two, will be effectively the same
as if they were located at the same substation (e.g., large load that is located no more than
two substations away from the generating facility). See infra P 94.
8 SPP HILL Order, 194 FERC ¶ 61,031; SPP CHILLS Order, 195 FERC ¶ 61,196.
9 PJM’s Tariff defines an Eligible Customer as:
PDF page 6
Docket No. EL26-67-000
- 6 -
withdrawals from the transmission system under certain conditions.10 PJM has also taken
steps attempting to enhance resource adequacy in the region.11 Because the Commission
is addressing its concerns related to co-located load in the separate and ongoing Federal
Power Act (FPA) section 20612 proceeding involving PJM, this order is limited to
addressing the integration of large loads that are not co-located with generation. While
we appreciate the steps PJM has already taken with respect to co-location arrangements,
we note that PJM has not yet proposed tariff revisions to address the challenges
associated with the integration of large loads.
As discussed below, we find that PJM’s existing Open Access Transmission Tariff
(Tariff) appears to be unjust, unreasonable, or unduly discriminatory or preferential. We
(i) Any electric utility (including any Transmission Owner
and any power marketer), Federal power marketing agency,
or any person generating electric energy for sale for resale . . .
(ii) Any retail customer taking unbundled transmission
service pursuant to a state requirement that the Transmission
Provider or a Transmission Owner offer the transmission
service, or pursuant to a voluntary offer of such service by a
Transmission Owner, is an Eligible Customer under the
Tariff. As used in Tariff, Part VIII, Eligible Customer shall
mean only those Eligible Customers that have submitted an
Application and Study Agreement.
PJM Interconnection, L.L.C., Intra-PJM Tariffs, OATT, pt. VIII, § 400
(Definitions E) (2.0.0) (PJM Tariff).
10 PJM Show Cause Order, 190 FERC ¶ 61,115; PJM Co-Location Order,
193 FERC ¶ 61,217, order on reh’g, 195 FERC ¶ 61,209 (2026) (PJM Co-Location
Rehearing Order). In the PJM Co-Location Rehearing Order, the Commission used the
term Eligible Load to refer to co-located load and/or load with Behind the Meter
Generation. PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 91.
11 PJM Interconnection, L.L.C., 195 FERC ¶ 61,197 (2026) (PJM EIT Order);
PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, order on reh’g, 192 FERC ¶ 61,085
(2025); see also PJM Interconnection, L.L.C., Informational Report, Docket
No. EL25-49-000, et al. (filed Jan. 20, 2026); PJM Interconnection, L.L.C., Supplemental
Informational Report, Docket Nos. EL25-49-000, et al. (filed Feb. 23, 2026); PJM
Interconnection, L.L.C., Second Supplemental Informational Report, Docket
No. EL25-49-000, et al. (filed Mar. 9, 2026).
12 16 U.S.C. § 824e.
PDF page 7
Docket No. EL26-67-000
- 7 -
thus institute a show cause proceeding pursuant to section 206 of the FPA, and we direct
PJM and the Transmission Owners,13 within 60 days of the date of this order, to either:
(1) show cause as to why the Tariff remains just and reasonable and not unduly
discriminatory or preferential without provisions addressing:
(a) the application process, study procedures, and ongoing operational
requirements that apply to Eligible Customers seeking transmission service
on behalf of large loads;
(b) additional transparency concerning the Network Upgrade14 costs to
provide transmission service to Eligible Customers on behalf of large loads,
a pro forma cost recovery agreement between PJM, the relevant
transmission owner, and Eligible Customer taking transmission service on
behalf of the large load to mitigate the risk of cost shifting among
transmission customers, and a mechanism to ensure such payments are
appropriately credited toward transmission owners’ transmission revenue
requirements consistent with the Commission’s cost-of-service regulations;
(c) transmission services that reflect Eligible Customers taking transmission
service on behalf of flexible large loads that are willing and able to limit
their use of the transmission system under certain conditions;15 and
13 Transmission Owners refers to the entities listed in the caption of this order. We
recognize that PJM’s transmission owners include entities that are not subject to the
Commission’s jurisdiction because they are not public utilities pursuant to section 201(f)
of the FPA. See 16 U.S.C. § 824(f); Sw. Power Pool, Inc., 180 FERC ¶ 61,022,
at PP 44-45 (2022). Accordingly, the Commission has not included AMP Transmission,
LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public
Power; City of Hamilton, OH; East Kentucky Power Cooperative, Inc.; and Southern
Maryland Electric Cooperative, Inc. here as Transmission Owners that must respond to
this order to show cause. Nonetheless, the Commission retains the authority to review
each entity’s formula rates as a component of PJM’s Tariff in an order to show cause
directed towards PJM, and PJM must respond to this order regarding the non-public
utilities’ PJM Tariff provisions on file with the Commission. See Sw. Power Pool, Inc.,
180 FERC ¶ 61,022 at P 40.
14 Capitalized terms not otherwise defined herein have the meanings ascribed to
them in the Tariff.
15 As explained below, for purpose of this order, “flexible” large loads are a subset
of large loads, as used in this order, that are not co-located with generation, but are
PDF page 8
Docket No. EL26-67-000
- 8 -
(d) the rates, terms, and conditions of service applicable to interconnection
customers serving electrically proximate large load or co-located load; or
(2) explain what changes to the Tariff would remedy the identified concerns if the
Commission were to determine that the Tariff has in fact become unjust and
unreasonable or unduly discriminatory or preferential and, therefore, proceeds to
establish a replacement Tariff.
We are also concerned with PJM’s need to ensure adequate generation to serve
new large loads.16 We therefore direct PJM to submit, within 30 days of the date of
issuance of this order, an informational report on how PJM intends to ensure that
adequate generation will be available to serve existing and new large loads, as detailed
later in this order.
We recognize that large loads, including data centers, are actively working with
transmission owners and other relevant entities to interconnect to, and to take service
from, the transmission system. We appreciate that different large loads are currently at
different stages of that process. We also understand that large loads and Eligible
Customers taking transmission service on behalf of large loads are negotiating, entering
into, and/or have executed various agreements related to interconnecting to the
transmission system and/or the provision of transmission service. This proceeding is not
intended to disrupt existing commercial arrangements, but rather to establish prospective
reforms. Accordingly, any Tariff revisions offered by PJM and/or the Transmission
Owners in response to this proceeding should (a) propose a reasonable implementation
period to ensure minimal disruption to such existing commercial arrangements, and (b)
allow a reasonable amount of time to finalize ongoing agreements that are nearing
completion as of the date such Tariff provisions are filed with the Commission. Such
proposed Tariff revisions should include a reasonable effective date that accommodates
such considerations regarding these existing commercial arrangements.
willing and able to limit their energy withdrawals from the transmission system under
certain conditions. See infra note 178.
16 Cf. PJM Co-Location Order, 193 FERC ¶ 61,217 at PP 237-239 (highlighting
PJM’s ongoing Critical Issue Fast Path stakeholder process to consider proposals to help
integrate large load additions without causing resource inadequacy and directing an
informational report on the status of those proposals).
PDF page 9
Docket No. EL26-67-000
- 9 -
I.
Background
A.
Growth of Large and Co-Located Loads and ANOPR
As the Secretary explained in the ANOPR, electricity demand in the United States
is expected to grow at an extraordinary pace in the near term, largely due to the rapid
growth of large loads.17 The Secretary highlighted findings from the North American
Electric Reliability Corporation (NERC) that show that demand growth is now higher
than at any point in the past two decades, driven in part by increasing quantities of large
commercial and industrial load, most notably data centers, connecting rapidly to the
transmission system.18 The Secretary also highlighted NERC’s conclusion that the size
and speed with which data centers can be connected to the grid present unique challenges
for demand forecasting and system planning. The ANOPR proposed that, in light of the
unprecedented current and expected growth of large loads seeking to interconnect to the
transmission system, the Commission should standardize interconnection procedures and
agreements for large loads, including those that seek to share a point of interconnection
with new or existing generation facilities.19
On April 16, 2026, the Commission issued an order regarding its intent to act with
respect to the ANOPR docket.20 In that order, the Commission explained that it agreed
with the Secretary “that, ‘[i]n light of the unprecedented current and expected growth of
large loads’ such as data centers, there is an urgent need for thoughtful reforms to ensure
that large loads are ‘able to connect to the transmission system in a timely, orderly, and
17 ANOPR at 2 (citing U.S. Dep’t of Energy, Resource Adequacy Report:
Evaluating the Reliability & Security of the United States Electric Grid (July 2025),
www.energy.gov/sites/default/files/2025-
07/DOE%20Final%20EO%20Report%20%28FINAL%20JULY%207%29.pdf).
18 Id. (citing NERC, 2024 Long- Term Reliability Assessment 8 (Dec. 2024,
updated July 2025),
https://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_Long%2
0Term%20Reliability%20Assessment_2024.pdf).
19 Id. P 12. For example, the ANOPR proposed that load and hybrid facilities
should be studied together with generating facilities, observing that “siting a large load
near or at the same point of interconnection as a new generating facility could reduce the
network upgrades needed to interconnect only the load or only the generating facility.”
ANOPR at P 20.
20 Interconnection of Large Loads to the Interstate Transmission Sys., 195 FERC
¶ 61,045 (2026) (Order Regarding Intent to Act).
PDF page 10
Docket No. EL26-67-000
- 10 -
non-discriminatory manner.’”21 After recognizing the Commission’s recent actions in
proceedings involving issues associated with large loads,22 the Commission concluded
that it was clear that additional “action is warranted to support further progress where it is
needed.”23
PJM’s load forecast predicts peak load growth of 32 gigawatts (GW) from 2024 to
2030, 30 GW of which is projected to be from data centers.24 Many commenters in the
ANOPR proceeding highlight the unprecedented load growth in PJM associated with
large loads. For example, AES Ohio currently forecasts over 6.3 GW of new load by
2032, which will nearly triple AES Ohio’s current peak.25 Exelon states that, in
ComEd’s service territory, data center demand has grown at an annual rate of 27%
through June 2025, and ComEd’s most recent large load adjustment request to
PJM included a future expected demand increase of 11 GW by 2040, 6 GW higher than
ComEd’s submission relative to the prior year.26 WATT and Advancing Modern
Powerlines note that PJM is expected to host as much as 70% of future U.S. data center
development and that this concentration of demand, especially in northern Virginia’s
“data center alley,” is creating intense pressure for new greenfield transmission to support
21 Id. P 2.
22 Id. (citing PJM Co-Location Order, 193 FERC ¶ 61,217; SPP HILL Order,
194 FERC ¶ 61,031; Commonwealth Edison Co., 194 FERC ¶ 61,181; Tri-State
Generation & Transmission Ass’n, 193 FERC ¶ 61,070 (2025); Duke Energy Carolinas,
LLC, 193 FERC ¶ 61,237).
23 Id. PP 3-4.
24 Letter from David E. Mills, PJM Board of Managers Chair, PJM,
Interconnection, L.L.C. to PJM Stakeholders (Aug. 8, 2025), https://www.pjm.com/-
/media/DotCom/about-pjm/who-we-are/public-disclosures/2025/20250808-pjm-board-
letter-re-implementation-of-critical-issue-fast-path-process-for-large-load-additions.pdf
(PJM Board Letter). Since the issuance of the PJM Board Letter, PJM has published its
2026 Long-Term Load Forecast Report, which anticipates lower peak demand in the near
term due to forecasting improvements, revising the peak load forecast for 2030
downward by 875 MW, but confirms significant growth in the next 20 years. PJM,
PJM’s Updated 20-Year Forecast Continues to See Significant Long-Term Load Growth
(Jan. 14, 2026), https://insidelines.pjm.com/pjms-updated-20-year-forecast-continues-to-
see-significant-long-term-load-growth/.
25 AES November 21 ANOPR Comments at 4.
26 Exelon November 21 ANOPR Comments at 2.
PDF page 11
Docket No. EL26-67-000
- 11 -
the interconnection of data centers.27 Buckeye states that load growth of approximately
10 GW driven largely by data centers in the Dominion Zone of PJM resulted in
approximately $12 billion in transmission investment across PJM.28
A number of commenters in the ANOPR proceeding assert that large load
additions have caused growing resource adequacy, reliability, and affordability problems
in PJM.29 Commenters also argue that large load interconnection in PJM is experiencing
significant delays.30 In addition, Buckeye and Southeast PIOs express concern that
infrastructure costs driven by data center loads will be borne by all transmission
customers in the corresponding PJM transmission zones and, where applicable, in the
broader PJM region.31 They and other commenters argue that wholesale transmission
customers are at risk of absorbing cost shifts and that retail large load tariffs do not
protect wholesale transmission customers from cost shifting.32 Vistra also raises
concerns that PJM and transmission owners’ processes for determining Network
27 WATT and Advancing Modern Powerlines November 21 ANOPR Comments
at 4.
28 Buckeye November 21 ANOPR Comments at 6.
29 See, e.g., ECA November 21 ANOPR Comments at 8; Geronimo November 21
ANOPR Comments at 7; Illinois AG November 21 ANOPR Comments at 5-6; Joint
Consumer Advocates November 21 ANOPR Comments at 2; OCC November 21
ANOPR Comments at 6-7; PIOs November 21 ANOPR Comments at 3-5, 13-14; PJM
IMM November 25 ANOPR Comments, Attach. A at 3-5.
30 International Energy Credit Association November 21 ANOPR Comments at 6;
Constellation November 21 ANOPR Comments at 2, 49-51.
31 See, e.g., Buckeye November 21 ANOPR Comments at 8; Southeast PIOs
November 21 ANOPR Comments at 10-11 (asserting that there is a significant overlap
between multi-driver projects that may be driven by increased loads, including data
centers, and those transmission projects selected in PJM’s recent RTEP solicitation).
32 See, e.g., APPA November 21 ANOPR Comments at 6 (“Wholesale
transmission customers in particular could be left shouldering massive costs if new large
loads do not ultimately attain or maintain the level of electricity demand that is being
forecasted.”); NRECA November 21 ANOPR Comments at 21 (noting the risk that other
transmission customers could bear stranded upgrade costs caused by large loads that they
cannot absorb); TAPS November 21 ANOPR Comments at 26 (“[A] number of state
commissions are moving forward with retail large load tariffs, which provide for varying
protections, but may not require the revenues and minimum demand levels to be included
in wholesale transmission rates.”).
PDF page 12
Docket No. EL26-67-000
- 12 -
Upgrades are not included in the Tariff and that existing transmission customers may be
disproportionately shouldering the costs for interconnecting large loads.33 OCC requests
that the Commission provide additional transparency regarding large load additions.34
Commenters also support reforms to capture the efficiencies of generation paired with
electrically proximate large load.35
Moreover, many commenters in the ANOPR proceeding filed persuasive
comments documenting, generally, the need for clear and consistent tariff provisions to
ensure regulatory and process certainty, fairness and consistency, and efficiency as large
loads are added to the transmission system in increasing numbers.36 There is also broad
support for rules that help to ensure that other transmission customers are not unfairly
burdened with additional costs or reliability impacts as large loads interconnect to the
transmission system.37 In addition, many ANOPR commenters highlighted the need to
33 Vistra November 21 ANOPR Comments at 22-23.
34 OCC November 21 ANOPR Comments at 3-4.
35 See, e.g., AEP December 5 ANOPR Comments at 10-12; Exelon November 21
ANOPR Comments at 14; Illinois AG November 21 ANOPR Comments at 8.
36 See, e.g., AI Supply Chain Alliance November 21 ANOPR Comments at 2;
Calibrant November 21 ANOPR Comments at 1-3; CEBA November 21 ANOPR
Comments at 9-11; Constellation November 21 ANOPR Comments at 6; DCC
November 21 ANOPR Comments at 3-4; ECA November 21 ANOPR Comments
at 7-11; EPSA November 21 ANOPR Comments at 4-6; Infrastructure Masons
December 5 ANOPR Comments at 4-7; Microsoft November 21 ANOPR Comments
at 9-10; National Grid November 21 ANOPR Comments at 7; ODEC December 5
ANOPR Comments at 2-4; R Street November 21 ANOPR Comments at 3; Switch
December 5 ANOPR Comments at 3; Tract November 21 ANOPR Comments at 5;
Vantage November 21 ANOPR Comments at 5-6; Vistra December 5 ANOPR
Comments at 1-2.
37 See, e.g., APPA November 21 ANOPR Comments at 6; Buckeye November 21
ANOPR Comments at 17; Exelon November 21 ANOPR Comments at 10; Kansas
Commission November 21 ANOPR Comments at 12; NCSL November 21 ANOPR
Comments at 1; NRECA November 21 ANOPR Comments at 8-9; NY UIU
November 21 ANOPR Comments at 3; OCC November 21 ANOPR Comments at 9;
Oklo December 5 ANOPR Comments at 3; Southeast PIOs December 5 ANOPR
Comments 11-15; State Entities November 21 ANOPR Comments at 7-8; Tri-State
November 21 ANOPR Comments at 8; UCS November 21 ANOPR Comments at 9-11;
U.S. Representatives November 21 ANOPR Comments at 1.
PDF page 13
Docket No. EL26-67-000
- 13 -
efficiently integrate large loads, particularly data centers, to support national security
priorities and economic development.38
B.
Recent Proceedings Addressing Large and Co-Located Loads
Over the past year, the Commission has begun to address, both sua sponte and in
response to complaints and FPA section 20539 filings, the growing use of co-location
arrangements.40 The Commission’s orders in those proceedings have addressed the need
for clear and consistent tariff provisions regarding the rates, terms, and conditions of
service that apply to co-location arrangements and for transmission services that reflect
Eligible Customers taking transmission service on behalf of co-located loads and load
with behind the meter generation that are willing and able to limit their energy
withdrawals from the transmission system under certain conditions. Several other
Commission proceedings have addressed the challenges of integrating large loads onto
the transmission system, including the need for clear and consistent tariff provisions
regarding the provision of transmission service to Eligible Customers on behalf of large
loads and for interconnection customers serving electrically proximate large load. As
explained below, these proceedings provide examples that will help to ensure that
jurisdictional transmission service is provided in a manner that is just and reasonable and
maintains reliability as large loads are integrated onto the transmission system and
co-location arrangements become more common. It is in this context, and in recognition
of the steps PJM has taken with respect to co-location arrangements, that the Commission
now considers whether PJM’s Tariff remains just and reasonable.
1.
PJM Co-Location Proceedings
On February 20, 2025, the Commission initiated a show cause proceeding against
PJM and the PJM Transmission Owners regarding the lack of tariff provisions addressing
with sufficient clarity or consistency the rates, terms, and conditions of service that apply
38 See, e.g., AI Supply Chain Alliance November 21 ANOPR Comments at 2;
DCC November 21 ANOPR Comments at 3; ECA November 21 ANOPR Comments
at 6; Geronimo November 21 ANOPR Comments at 1-2; Google November 21 ANOPR
Comments at 2-3; Verrus December 5 ANOPR Comments at 2.
39 16 U.S.C. § 824d.
40 See PJM Show Cause Order, 190 FERC ¶ 61,115; PJM Co-Location Order,
193 FERC ¶ 61,217, order on reh’g, PJM Co-Location Rehearing Order, 195 FERC
¶ 61,209; SPP HILL Order, 194 FERC ¶ 61,031; SPP CHILLS Order, 195 FERC
¶ 61,196.
PDF page 14
Docket No. EL26-67-000
- 14 -
to co-location arrangements.41 The Commission explained when initiating that
proceeding that the absence of such provisions may leave entities unable to determine
what steps they can or must take to effectuate co-location arrangements of various
configurations and how to do so in a manner that is just and reasonable.42 On
December 18, 2025, the Commission found that PJM’s Tariff was indeed unjust and
unreasonable because it does not contain provisions addressing with sufficient clarity or
consistency the rates, terms, and conditions of service that apply to interconnection
customers serving co-located load and Eligible Customers taking transmission service on
behalf of co-located load.43
Specifically, the Commission found that the PJM Tariff was unjust and
unreasonable because there is a lack of sufficient clarity or consistency as to the rates,
terms, and conditions of service that apply to interconnection customers serving
co-located load.44 The Commission also found that PJM’s Tariff was unjust and
unreasonable because it does not include transmission services that reflect Eligible
Customers taking transmission service on behalf of co-located loads that are willing and
able to limit their energy withdrawals from the transmission system under certain
conditions.45 Additionally, the Commission found that PJM’s behind the meter
generation rules were no longer just and reasonable.46 The Commission directed PJM to
file a compliance filing to revise its Tariff: (1) to set forth specific terms and conditions
that an interconnection customer in PJM seeking to serve co-located load must follow in
order to effectuate a co-location arrangement;47 (2) to require that the Eligible Customer
taking transmission service on behalf of co-located load takes one of three transmission
services: (a) network integration transmission service (NITS) or a new interim, non-firm
transmission service while Network Upgrades to provide full NITS service are
41 See PJM Show Cause Order, 190 FERC ¶ 61,115.
42 Id. P 74. The PJM Show Cause Order defined co-located load as a
“configuration [that] refers to end-use customer load that is physically connected to the
facilities of an existing or planned Customer Facility on the Interconnection Customer’s
side of the Point of Interconnection (‘POI’) to the PJM Transmission System.” Id. P 3
n.4.
43 PJM Co-Location Order, 193 FERC ¶ 61,217.
44 Id. P 176.
45 Id. P 177.
46 Id. P 179.
47 Id. PP 187-192, 225-230.
PDF page 15
Docket No. EL26-67-000
- 15 -
constructed (interim NITS); (b) a new firm contract demand transmission service; or (c) a
new non-firm contract demand transmission service;48 (3) to revise the behind the meter
generation rules and implement a transition process for existing behind the meter
generation participants;49 and (4) to make several clarifications on how certain aspects of
PJM’s generator interconnection process apply to interconnection customers seeking to
serve co-located load.50
On June 18, 2026, concurrently with the instant order, the Commission issued an
order modifying the discussion in the PJM Co-Location Order and setting aside the order
in part; accepting in part and rejecting in part PJM’s compliance filing, and directing a
further compliance filing; and establishing as just and reasonable certain rates, terms, and
conditions for the new transmission services (i.e., interim NITS, firm contract demand
transmission service, and non-firm contract demand transmission service).51
2.
SPP High Impact Large Load Process and High Impact Large
Load Generation Assessment Processes
On January 14, 2026, the Commission accepted revisions to SPP’s tariff to add a
high impact large load (HILL) study process and High Impact Large Load Generation
Assessment (HILLGA) process.52 SPP’s tariff revisions established HILLs as a new
category of load;53 imposed enhanced study requirements to enable SPP to assess the
48 Id. PP 193-218. The Commission also established a paper hearing to determine
the just and reasonable rates, terms, and conditions for the new transmission services. Id.
PP 219-220.
49 Id. PP 221-224.
50 Id. PP 161, 231-236.
51 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at PP 7-9. PJM’s
compliance filing proposing revisions in response to the Commission’s directives
regarding clarification that certain aspects of PJM’s generator interconnection process
apply to interconnection customers seeking to serve co-located load was accepted in part
on April 16, 2026. PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 (2026).
52 SPP HILL Order, 194 FERC ¶ 61,031 at PP 61, 64.
53 SPP defines a HILL as:
A new commercial or industrial load, or increase in
commercial or industrial load, at a single site connected
through one or more shared Points of Interconnection (POIs)
or delivery points, where such load is either: (1) 10 MW or
PDF page 16
Docket No. EL26-67-000
- 16 -
HILL’s reliability impacts on the transmission system;54 and created additional, ongoing
operational requirements for transmission customers serving HILLs to ensure continued
reliability of the transmission system.55 The tariff revisions also established the HILLGA
process, a new generator interconnection service and related interconnection process to
facilitate the prompt interconnection of generating facilities that are specifically identified
for, and limited to, serving a HILL and are located no more than two substations away
from the HILL.56
more if connected to the Transmission System at a voltage
level less than or equal to 69 [kilovolts (kV)]; or (2) 50 MW
or more if connected to the Transmission System at a voltage
level greater than 69 kV. An Electric Storage Resource is not
considered a HILL.
SPP, Open Access Transmission Tariff, Sixth Revised Vol. No. 1, pt. I, § 1
(Definitions H) (1.0.0).
54 SPP HILL Order, 194 FERC ¶ 61,031 at PP 13-17 (explaining that the HILL
process requires up to three additional studies beyond those required of all transmission
service requests for transmission customers requesting to add or modify a delivery point
associated with a HILL, including a HILL delivery point study, HILL supplemental load
connection study, and potential supplemental Electromagnetic Transient study).
55 Id. P 18 (explaining that market participants registering a HILL must:
(1) follow all nonconforming load requirements (e.g., additional load forecast
requirements); (2) provide load data via telemetry in real time; (3) have remote capability
to disconnect the load from the transmission system made available to the transmission
operator; (4) have an up/down ramp rate not exceeding 20 MW per minute unless
otherwise directed; (5) include additional information with registration; and (6) not have
withdrawals from the transmission system without appropriate transmission service); id.
P 19 (explaining that the transmission owner, at the transmission customer’s expense,
must install a phasor measurement unit or similar equipment); id. PP 20-21 (explaining
that the transmission customer will be required to comply with ride-through requirement
guidelines).
56 Id. P 27 (explaining that, under the HILLGA process, SPP proposes to study
HILLGA requests to determine whether any network upgrades are needed to
accommodate the generating facility’s injection to the local area); id. P 32 (explaining
that SPP will grant HILLGA customers a new type of interconnection service, load
limited resource interconnection service, which grants limited interconnection service
solely to serve the associated HILL).
PDF page 17
Docket No. EL26-67-000
- 17 -
The Commission stated that SPP demonstrated that the “unprecedented growth in
large loads in the SPP region presents significant and unique operational and planning
challenges.”57 The Commission found that SPP demonstrated that its proposed HILL
process was a just and reasonable approach for integrating transmission customers’ new
large loads onto SPP’s transmission system in a reliable manner.58 The Commission
found that it was reasonable to impose additional study requirements and other proposed
requirements given the unique operating characteristics of HILLs. The Commission
further found that the proposed study requirements would ensure the reliable integration
of the transmission customer’s HILLs onto SPP’s transmission system and would provide
SPP with information about their impact on SPP’s transmission system, including the
transmission system’s ability to withstand and control disturbances by the HILL at the
point of interconnection.59 In addition, the Commission found that the proposed study
deposits would discourage speculative HILL study requests.60 Finally, the Commission
concluded that the proposed ongoing reliability requirements would allow SPP to
maintain reliable operation of its transmission system by increasing SPP’s visibility,
providing necessary data, and imposing real-time operational safeguards for HILLs.61 In
accepting HILLGA, the Commission found that “SPP’s HILLGA process reasonably
provides a flexible, expedited, and separate serial interconnection process that will
facilitate the prompt interconnection of generating facilities that are limited to serving a
HILL in the same local area.”62
3.
SPP Conditional High Impact Large Load Service
On June 5, 2026, the Commission accepted revisions to SPP’s tariff to add a new
type of non-firm transmission service, conditional high impact large load service
57 Id. P 60.
58 Id. P 61.
59 Id. P 62.
60 For the HILL delivery point study, SPP required a $10,000 non-refundable
application fee and a $100,000 study deposit, with an additional $200,000 study deposit if
an Electromagnetic Transient study was also required. Id. P 15. For the HILL
supplemental load connection study, SPP allows the host transmission owner to require a
$25,000 study deposit. Id. P 16.
61 Id. P 63.
62 Id. P 64.
PDF page 18
Docket No. EL26-67-000
- 18 -
(CHILLS).63 CHILLS allows transmission customers serving HILLs to reliably receive
transfers of energy until sufficient designated resources and/or network upgrades are in
place to support long-term, firm transmission service.64 CHILLS is an as-available
transmission service that will transfer energy to designated points of delivery to serve the
portion of a HILL eligible to receive CHILLS, subject to curtailment and interruption.65
CHILLS has a maximum term of seven years, which is intended to incentivize
transmission customers seeking CHILLS to obtain the designated resources and/or
complete the network upgrades needed to procure long-term firm transmission service
through existing tariff processes.66
The Commission found that SPP had shown that unprecedented growth in large
loads presents significant and unique operational and planning challenges.67 The
Commission also found that SPP’s ability to add HILLs to its transmission system in a
timely manner may be limited due to delays in obtaining sufficient designated resources
and completing network upgrades needed to provide long-term firm transmission service
to such load.68 The Commission concluded that CHILLS is a just and reasonable and not
unduly discriminatory or preferential approach to addressing the need to expeditiously
interconnect and provide transmission service to new HILLs, while maintaining the
reliable operation of SPP’s transmission system.69
II.
PJM’s Existing Processes
A.
Existing Tariff Processes
PJM’s Tariff sets forth a process by which an Eligible Customer may request
either NITS,70 including modifications to existing service agreements to add new
63 SPP CHILLS Order, 195 FERC ¶ 61,196 at P 1.
64 Id. P 7.
65 Id. PP 9-10.
66 Id. P 9.
67 Id. P 84.
68 Id.
69 Id.
70 NITS is a transmission service that allows Network Customers to use their
Network Resources (as well as other non-designated generation resources) to serve their
PDF page 19
Docket No. EL26-67-000
- 19 -
Network Loads, or Point-to-Point Transmission Service.71 In the PJM Co-Location
Order, the Commission also directed PJM to create three new transmission services that
an Eligible Customer taking transmission service on behalf of co-located load may take:
(1) an interim, non-firm transmission service until all Network Upgrades necessary to
provide the requested NITS are complete, (2) a new Firm Contract Demand transmission
service, and (3) a new Non-Firm Contract Demand transmission service.72
In PJM, new load additions are processed in one of two ways: (1) an Eligible
Customer requesting new transmission service submits a Transmission Service Request
to PJM; or (2) for existing Network Customers adding new Network Loads, the Network
Customer provides PJM with notice of the designation of new Network Load and must
modify its existing service agreement accordingly.73 For NITS and Firm Point-to-Point
Transmission Service Requests, PJM determines whether a Phase I System Impact
Study74 is needed to assess whether the transmission system has sufficient available
capability to provide the requested service and tenders an Application and Studies
Network Load located in the PJM region and designated additional loads. PJM Tariff,
pt. III, § 28.1 (Scope of Service) (1.0.0).
71 Point-to-Point Transmission Service provides for “the reservation and
transmission of capacity and energy on either a firm or non-firm basis from the Point(s)
of Receipt to the Point(s) of Delivery.” Id. pt. I, § 1 (Definitions O-P-Q) (36.0.0)
(definition of Point-to-Point Transmission Service).
72 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 160.
73 PJM Tariff, pt. III, § 31.2 (New Network Loads Connected With the
Transmission Provider) (1.0.0). To the extent that a Network Customer seeks to add a
new Delivery Point or interconnection point between the PJM transmission system and a
Network Load, the Network Customer must provide PJM with as much advance notice as
reasonably practicable. Id. pt. III, § 31.4 (New Interconnection Points) (0.0.0).
74 PJM’s study process for New Service Requests consists of Phase I, II, and III
System Impact Studies.
PDF page 20
Docket No. EL26-67-000
- 20 -
Agreement75 to initiate a New Service Request pursuant to which the Eligible Customer
agrees to reimburse PJM for the required Phase I System Impact Study.76
PJM studies all New Service Requests including generator interconnection
requests, merchant transmission interconnection requests, and long-term firm
transmission service requests77 in a single queue (New Services Queue), which is
governed by the transitional interconnection process in Part VII of the Tariff (for requests
submitted between April 1, 2018 and September 30, 2021, where an Interconnection
Customer does not have an Interconnection Service Agreement as of July 10, 2023), and
the new cycle interconnection process in Part VIII of the Tariff (“new rules” for valid
New Service Requests submitted on or after October 1, 2021).78 PJM’s New Services
75 PJM’s Tariff defines an “Application and Studies Agreement” as the application
that must be submitted by a Project Developer or Eligible Customer that seeks to initiate
a New Service Request. PJM Tariff, pt. VII, § 300 (Definitions A) (3.0.0); id. pt. VIII,
§ 400 (Definitions A) (2.0.0).
76 Id. pt. III, § 32.1 (Notice of Need for Phase I System Impact Study) (2.0.0); id.
pt. II , § 19.1 (Notice of Need for Phase I System Impact Study) (4.0.0). As the RTO,
PJM administers the interconnection of generating facilities and Merchant Transmission
Facilities, requests for transmission service, and upgrades to existing transmission owner
facilities in the PJM transmission system through the New Service Requests process.
PJM Manual 14H: New Service Requests Cycle Process, § 1.1 (Sep. 2025),
https://www.pjm.com/-/media/DotCom/documents/manuals/m14h.ashx (PJM
Manual 14H).
77 Id. pt. VII, subpt. C, § 306(A)(3) (Application Rules) (1.1.0) (includes specific
additional application requirements for Long-Term Firm Transmission Service seeking to
initiate a New Services Request); id. pt. VIII, subpt. B § 403(A)(3) (Application Rules)
(0.1.0); id., pt. VII, § 300 (Definitions N) (2.0.0) (definition of New Service Request); id.
pt. VIII, § 400 (Definitions N) (2.0.0) (definition of New Service Request); see also id.
pt. VII, § 300 (Definitions C) (2.0.0) (definition of Completed Application); id. pt. VII,
§ 300 (Definitions I) (2.0.0) (definition of Interconnection Request); id. pt. VIII, § 400
(Definitions C) (2.0.0) (definition of Completed Application); id. pt. VIII, § 400
(Definitions I) (2.0.0) (definition of Interconnection Request); id. pt. I, § 1
(Definitions A-B) (19.1.1) (definition of Application).
78 See id. pt. VII, § 301 (Transition Introduction) (1.0.0) (“Part VII sets forth the
procedures and other terms governing the Transmission Provider’s administration of the
transition to the new Cycle-process, including procedures and other terms regarding
studies and other processing of New Service Requests within the Transition Cycle”); id.
pt. VIII, § 401 (Applications for Cycle Process Intro) (2.0.0); id. pt. VIII, § 401(A) (New
Cycle Process) (2.0.0) (“Part VIII of the Tariff applies to valid New Service Requests
PDF page 21
Docket No. EL26-67-000
- 21 -
Queue is a first-ready, first-served clustered cycle approach that consists of an application
phase, a three-phase study process, where each phase includes a System Impact Study
and decision point, and a final agreement negotiation phase. For transmission service
requests, once the New Service Request is processed, the transmission customer will
enter into a transmission service agreement, a construction service agreement, and/or a
Network Upgrade cost responsibility agreement. PJM’s Tariff does not have any specific
study provisions or requirements for Eligible Customers requesting transmission service
on behalf of large load additions.
The system impact study is an assessment by PJM of: (1) the adequacy of the
transmission system to accommodate a New Service Request; (2) whether any additional
costs may be incurred in order to provide such transmission service or to accommodate a
New Service Request; and (3) an estimated date that the New Service Requests can be
interconnection with the transmission system and an estimate of the cost responsibility
for the interconnection of the New Service Request.79 The System Impact Studies also
provide “estimates of cost responsibility and construction lead time for new facilities
required to interconnect the project and required system upgrades,”80 including Network
Upgrades. The Tariff describes the phases and studies that determine the cost allocation
of Network Upgrades to New Service Requests, and PJM Manual 14H provides the
implementation details used to govern the interconnection and transmission customers
service request process for new generating facilities seeking to connect to or use the PJM
transmission system through PJM’s cluster-based queue methodology.81 Specifically, the
submitted on or after October 1, 2021, and sets forth the . . . procedures and other terms
regarding studies and other processing of New Service Requests”); id. pt. VIII, § 401(B)
(Applications for Cycle Process) (2.0.0) (“Part VIII of the Tariff applies to (a) Generation
Interconnection Requests; (b) Transmission Interconnection Requests; and (c) Completed
Applications”).
79 Id. pt. VIII, § 400 (Definitions S) (3.0.0) (definition of System Impact Study).
The System Impact Study includes facilities study analysis.
80 Id. pt. VII, subpt. D, § 307 (Introduction) (1.0.0); id. pt. VII, subpt. D,
§ 307(A)(2)(a)(ii) (Overview of System Impact Studies) (1.0.0); id. pt. VIII, subpt. C,
§ 404 (Introduction) (1.0.0); id. pt. VIII, subpt. C, § 404(2)(a)(ii) (Introduction) (1.0.0).
81 See id. pt. VII, subpt. D § 307 (Introduction) (1.0.0) (including a description of
the phases and an overview of the System Impact Studies and cost allocation of Network
Upgrades, noting that the cost allocation will be in accordance with PJM Manuals); id. pt.
VII, subpt. D § 307(A)(5)(c) (Cost Allocation for Network Upgrades) (1.0.0); id. pt. VIII,
subpt. C, § 404 (Introduction) (1.0.0), id. pt. VIII, subpt. C, § 404(A)(5)(c) (Cost
Allocation for Network Upgrades) (1.0.0); see PJM Manual 14H: New Service Requests
PDF page 22
Docket No. EL26-67-000
- 22 -
Tariff provides that each “Eligible Customer shall be obligated to pay for 100% of the
costs of the minimum amount of Network Upgrades necessary to accommodate its New
Service Request and that would not have been incurred under the Regional Transmission
Expansion Plan [(RTEP)] but for such New Service Request, net of benefits resulting
from the construction of the upgrades, such costs not to be less than zero.”82 The Tariff
further specifies that “[a]ll New Service Requests that contribute to the need for a
Network Upgrade will receive cost allocation for that upgrade pursuant to each New
Service Request’s contribution to the reliability violation identified on the transmission
system in accordance with PJM Manuals.”83
As relevant on the generator interconnection side, pursuant to the Tariff, a Project
Developer may request, and PJM may provide, Provisional Interconnection Service for
limited interconnection service at the discretion of PJM based upon an evaluation that
will consider the results of available studies.84 PJM determines, through available studies
or additional studies as necessary, “whether stability, short circuit, thermal, and/or
voltage issues would arise” if the Project Developer interconnects without modifications
to the Generating Facility or the transmission system.85 Under the Tariff, a Project
Developer may also request surplus interconnection service for an unneeded portion of
interconnection service capacity at an existing point of interconnection.86 The surplus
interconnection study consists of reactive power, short circuit/fault duty, stability analysis
and any other appropriate analyses, and steady-state (thermal/voltage) analyses may be
Cycle Process, § 4.2.6 (Sep. 2025), https://www.pjm.com/-
/media/DotCom/documents/manuals/m14h.ashx (PJM Manual 14H).
82 PJM Tariff, pt. VII, subpt. D, § 307(A)(5)(a) (Cost Allocation for Network
Upgrades) (1.0.0); id. pt. VIII, subpt. C, § 404 (A)(5)(a) (Cost Allocation for Network
Upgrades) (1.0.0).
83 Id. pt. VII, subpt. D, § 307(A)(5)(c) (Cost Allocation for Network Upgrades)
(1.0.0); id. pt. VIII, subpt. C, § 404 (A)(5)(c) (Cost Allocation for Network Upgrades)
(1.0.0).
84 Id. pt. IX, subpt. B, app. 2, § 1.4A.2 (Provisional Interconnection Service)
(0.0.0).
85 Id.
86 Id. pt. VIII, subpt. E, § 414(A) (Surplus Interconnection Service Request)
(1.0.0).
PDF page 23
Docket No. EL26-67-000
- 23 -
performed as necessary to ensure that all required reliability conditions are studied under
off-peak conditions.87
In PJM, electric distribution companies and transmission owners administer load
interconnection processes for existing Network Customers, and transmission owners
perform local transmission planning to accommodate load additions.88 PJM, as
transmission provider, conducts additional studies and transmission planning activities to
support load additions. Requests to physically interconnect loads are submitted to
transmission owners, who have their own study processes and requirements. Some
transmission owners have established specific large load interconnection procedures and
requirements.89 New loads taking bundled retail service from a transmission owner or
that are served subject to state-required retail access programs (Native Load) are studied
through transmission owners’ local transmission planning processes. Transmission
owners must designate resources and loads to serve Native Load in the same manner as
any Eligible Customer.90
Network Upgrades identified in transmission owners’ local transmission planning
process as needed to accommodate load additions are designated as Supplemental
Projects under Attachment M-3 of PJM’s Tariff.91 Under Attachment M-3, transmission
owners plan for the local transmission needs of their own transmission systems.
Attachment M-3 provides procedures for stakeholder review and comment on
Supplemental Projects in the Transmission Expansion Advisory Committee (230 kV or
above) and Subregional RTEP Committee (below 230 kV) and as part of a transmission
87 Id. pt. VIII, subpt. E, § 414(B)(1) (Surplus Interconnection Study) (1.0.0).
88 See PJM November 21 ANOPR Comments at 6.
89 See, e.g., EEI March 12 ANOPR Comments at 13 (“In December 2025, Exelon
subsidiary Delmarva Power submitted proposed changes in line with the Commission’s
November 2025 order: a new service class ‘GS-LD’ applicable to large demand
customers with a monthly maximum of 25 MW or greater. The company also proposed
implementing an application process and specific requirements for potential customers
with a projected load of at least 50 MW.”); id. (“Exelon subsidiary Commonwealth
Edison Company (ComEd) has proposed revisions to Rider DE that clarify requirements
and procedures for large load customers' new service requests.”).
90 PJM Tariff, pt. III, § 28.2 (Transmission Provider Responsibilities) (1.0.0).
91 See id. attach. M-3 (Additional Procedures for Planning Supplemental Projects
and Asset Management Projects) (1.0.0).
PDF page 24
Docket No. EL26-67-000
- 24 -
owner’s Local Plan, before the Local Plan is submitted for integration into the RTEP.92
These transmission projects do not qualify for region-wide cost allocation, and PJM
conducts only a “do no harm” test to ensure that local transmission facilities do not
adversely impact the reliability of the broader transmission system before the
Supplemental Projects are added into the RTEP base case.93 Supplemental Project costs
are allocated to the local transmission owner’s zone pursuant to individual transmission
owner cost allocation frameworks.94
Attachment H of the PJM Tariff includes the formula rate for each transmission
owner. The formula rate calculates the annual transmission revenue requirement, and
resulting NITS rate, in the relevant PJM transmission zones. The demand charges for
NITS, which are charged to the relevant Network Customer (i.e., the Eligible Customer),
are determined by multiplying the rate for NITS (based on the NITS rate in Attachment H
of the relevant transmission zone) by the customer’s coincident peak demand.95
In some instances, an aggregation of large loads, coupled with other drivers, could
trigger regional (as opposed to local) transmission system needs, which would be
identified and addressed by a regional transmission project in the RTEP, which is subject
to PJM’s regional cost allocation method. For example, a transmission owner may
identify a local transmission need that may be more efficiently or cost-effectively
addressed by a regional transmission project identified in the RTEP.96
The Tariff includes a hybrid cost allocation method that was accepted as part of
PJM’s compliance with Order No. 1000 for Regional Facilities and Necessary Lower
Voltage Facilities that address a reliability need.97 Under this method, PJM allocates
92 See id. § (c) (Procedures for Review of Attachment M-3 Projects).
93 See PJM Interconnection, L.L.C., Answer, Docket No. EL25-49-000, at 6-7
(filed Mar. 24, 2025); PJM Manual 14B: PJM Regional Transmission Planning Process,
§ 1.1 (Apr. 2026), https://www.pjm.com/-
/media/DotCom/documents/manuals/m14b.pdf#page=14.
94 PJM Interconnection, L.L.C., Answer, Docket No. EL25-49-000, at 7 (filed
Mar. 24, 2025).
95 PJM Tariff, pt. III, § 34.1 (Monthly Demand Charge) (1.0.0).
96 See, e.g., Potomac Edison Co., 190 FERC ¶ 61,074, at PP 5, 22 (2025)
(allowing for recovery of abandoned plant costs where a local transmission project was
superseded by regional transmission development in PJM’s RTEP process).
97 PJM identifies reliability transmission needs and economic constraints that
result from the incorporation of public policy requirements into its sensitivity analyses
PDF page 25
Docket No. EL26-67-000
- 25 -
50% of the costs of Regional Facilities or Necessary Lower Voltage Facilities on a
load-ratio share basis and the other 50% based on the solution-based distribution factor
(DFAX) method. PJM allocates all of the costs of Lower Voltage Facilities using the
solution-based DFAX method. Cost responsibility assignments pursuant to the Order
No. 1000-compliant cost allocation method are included in Schedule 12-Appendix A of
the Tariff.
Schedule 12 of the Tariff provides that cost responsibility for the portion of costs
allocated on a load-ratio share basis will be updated annually using the applicable zonal
loads at the time of each zone’s annual peak load from the 12-month period ending
October 31 of the calendar year preceding the calendar year for which the annual cost
responsibility assignment is determined, consistent with section 34.1 of the Tariff.98
Schedule 12 of the Tariff also provides that, for the portion of cost responsibility
assignments allocated pursuant to the solution-based DFAX method, PJM shall make a
preliminary cost responsibility assignment for each Required Transmission Enhancement
at the time such transmission facility is selected in the RTEP for purposes of cost
allocation. Further, beginning with the calendar year in which a transmission facility is
scheduled to enter service, and thereafter annually at the beginning of each calendar year,
PJM shall update the preliminary cost responsibility assignment for each transmission
facility using the values and inputs used in the base case of the most recent RTEP
approved by the PJM Board prior to the date of the update.99
B.
Recent Stakeholder Proceedings in PJM
PJM has begun considering reforms to address large load additions, including the
development of solutions to ensure large load additions can continue to be integrated
and allocates the costs of the solutions to such transmission needs in accordance with the
type of benefits they provide. PJM Interconnection, L.L.C., 142 FERC ¶ 61,214, at P 441
(2013); see PJM Tariff, Schedule 12 (15.0.0), § (b)(v) (assigning cost responsibility for
Economic Projects that are either accelerations or modifications of Reliability Projects, or
new enhancements or expansions that relieve one or more economic constraints); PJM,
Intra-PJM Tariffs, Operating Agreement, Schedule 6, § 1.5 (Procedure for Development
of the Regional Transmission Expansion Plan) (29.1.0), 1.5.7(c)(iii).
98 PJM Tariff, Schedule 12, § (b)(i)(A)(1) (Designation of Customers Subject to
Transmission Enhancement Charges) (15.0.0).
99 Id. § (b)(iii)(H)(2) (Designation of Customers Subject to Transmission
Enhancement Charges) (15.0.0). The annual update includes any projects that were
included to address any individual transmission owner Form No. 715 local planning
criteria.
PDF page 26
Docket No. EL26-67-000
- 26 -
rapidly and reliably without causing resource inadequacy. On January 16, 2026, the PJM
Board issued a decisional letter on the Critical Issues Fast Path (CIFP) detailing the
initiatives that PJM will move forward to implement, which include: (1) a definition for
large load additions; (2) load forecasting improvements; (3) voluntary “Bring Your Own
New Generation” commensurate with large load additions; (4) an expedited generator
interconnection track to offset large loads; (5) requiring, in specific circumstances, some
new large loads to be subject to curtailment prior to the deployment of pre-emergency
demand response pursuant to a “connect and manage” framework; (6) immediate
initiation of reliability backstop procurement; (7) holistic review of investment incentives
in PJM’s energy, reserve, and capacity markets; and (8) feedback on whether to extend
the price collar for the 2028/2029 and 2029/2030 capacity auctions.100
Additionally, on January 16, 2026, governors from each of the 13 states in PJM
met with the White House National Energy Dominance Council and issued a statement of
principles calling on PJM to: (1) provide 15-year price certainty for new capacity
resources by holding a reliability backstop auction to procure new capacity resources
commencing no later than September 2026; (2) allocate the costs of capacity procured
through the reliability backstop auction to load serving entities with new data centers that
have not self-procured new capacity or agreed to be curtailable; (3) extend the existing
price collar to the next two Base Residual Auctions; (4) refine load forecasting
methodologies by improving large load modeling assumptions; (5) accelerate ongoing
generator interconnection studies; and (6) embark on a stakeholder process to reform the
capacity market to ensure long-term viability.101
In response, PJM has initiated stakeholder processes on several items. The PJM
Board initiated a new CIFP stakeholder process to engage stakeholders in the
100 PJM, Board Decisional Letter on Critical Issue Fast Path - Large Load
Additions (Jan. 16, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-
are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-
large-load-additions.pdf. PJM has since submitted its proposal to extend the price collar
for the 2028/2029 and 2029/2030 delivery years, which the Commission accepted on
April 28, 2026. PJM Interconnection, L.L.C., 195 FERC ¶ 61,076 (2026). PJM has also
since submitted its proposal for a temporary, expedited generator interconnection process
(Expedited Interconnection Track), which the Commission accepted on June 9, 2026.
PJM EIT Order, 195 FERC ¶ 61,197.
101 U.S. Department of Energy, Statement of Principles Regarding PJM (Jan. 16,
2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.
PDF page 27
Docket No. EL26-67-000
- 27 -
development of a reliability backstop procurement mechanism.102 PJM also developed a
Connect and Manage Senior Task Force to consider the “connect and manage”
framework to manage the reliability challenges during the transition period in which new
load additions are outpacing the additions of new capacity in the PJM
system.103 Following initial stakeholder workshops, the PJM Board decided to expand
the scope of the CIFP regarding the reliability backstop procurement mechanism to
include the “connect and manage” framework, given the substantive overlap between the
two proposals.104 PJM expects to develop a comprehensive proposal by the end of June,
which it expects to file with the Commission shortly thereafter, with the goal of procuring
any shortfall resulting from the upcoming Base Residual Auction through a centralized
procurement in September 2026.105 PJM has additionally issued a report examining
market design and investment incentives in light of rising demand, which is driven in part
by the expansion of large loads, and constrained supply.106 PJM has scheduled a series of
workshops through August 2026 to develop recommendations based on the choices
presented in the report.107
While we are encouraged by PJM’s stakeholder efforts, and by its initial attention
to the pressing concerns associated with large and co-located loads,108 and to the
102 PJM, Critical Issue Fast Path – Reliability Backstop Procurement,
https://www.pjm.com/committees-and-groups/cifp-rbp.
103 PJM, Connect and Manage Senior Task Force,
https://www.pjm.com/committees-and-groups/task-forces/camstf.
104 PJM, Third Supplemental Informational Report, Docket No. EL25-49-000,
et al. (filed May 20, 2026); see also PJM, Critical Issue Fast Path - Reliability Backstop
Procurement / Connect & Manage, https://www.pjm.com/committees-and-groups/cifp-
rbp.
105 PJM, Third Supplemental Informational Report, Docket No. EL25-49-000,
et al. (filed May 20, 2026).
106 PJM, Powering Reliability Through Market Design: Addressing Rising
Demand and Constrained Supply, and Stimulating Investment to Support Durable
Reliability (May 6, 2026), https://www.pjm.com/-/media/DotCom/library/reports-
notices/special-reports/2026/20260506-powering-reliability-through-market-design.pdf.
107 PJM, Powering Reliability Through Market Design Workshops,
https://www.pjm.com/committees-and-groups/workshops/prtmdw.
108 PJM November 21 ANOPR Comments at 12; see also PJM, Large Load
Additions Workshop, at 1 (May 9, 2025), https://www.pjm.com/-
/media/DotCom/committees-groups/workshops/llaw/2025/20250509/20250509-item-02--
PDF page 28
Docket No. EL26-67-000
- 28 -
Secretary’s interest in these issues,109 we are initiating this FPA section 206 proceeding
in order to ensure that PJM’s ongoing processes generate reforms that are sufficiently
timely and comprehensive to address the concerns we today identify. As such, and as the
Commission explained in the April Order Regarding Intent to Act, we find that the
Commission must now take further action to ensure that PJM promptly proposes
revisions to ensure that its Tariff remains just and reasonable.
III.
Discussion
Based on the discussion below, pursuant section 206 of the FPA, we direct PJM
and the Transmission Owners, within 60 days of the date of this order, to either:
(1) show cause as to why the Tariff remains just and reasonable and not unduly
discriminatory or preferential without provisions addressing:
(a) the application process, study procedures, and ongoing operational
requirements that apply to Eligible Customers seeking transmission service
on behalf of large loads;
(b) additional transparency concerning the Network Upgrade costs to
provide transmission service to Eligible Customers on behalf of large loads,
a pro forma cost recovery agreement between PJM, the relevant
transmission owner and Eligible Customer taking transmission service on
behalf of the large load to mitigate the risk of cost shifting among
transmission customers, and a mechanism to ensure such payments are
appropriately credited towards transmission owners’ transmission revenue
requirements consistent with the Commission’s cost-of-service regulations;
(c) transmission services that reflect Eligible Customers taking transmission
service on behalf of flexible large loads that are willing and able to limit
their use of the transmission system under certain conditions; and
(d) the rates, terms, and conditions of service applicable to interconnection
customers serving electrically proximate large load or co-located load; or
-large-load-additions-workshop---presentation.pdf (discussing challenges with reliability
of connecting large loads); PJM IMM, Planning for Large Load Additions (Jan. 7, 2025),
https://www.monitoringanalytics.com/reports/Presentations/2025/IMM_PC_Large_Load
_Additions_20250107.pdf.
109 See supra PP 6-7.
PDF page 29
Docket No. EL26-67-000
- 29 -
(2) explain what changes to the Tariff would remedy the identified concerns if the
Commission were to determine that the Tariff has in fact become unjust and
unreasonable or unduly discriminatory or preferential and, therefore, proceeds to
establish a replacement Tariff.
We also direct PJM to submit, within 30 days of the date of issuance of this order,
an informational report on how PJM intends to ensure that adequate generation will be
available to serve existing and new large loads.
Interested entities may respond within 30 days of PJM’s and the Transmission
Owners’ filings, addressing either or both of: (1) whether the existing Tariff remains just
and reasonable and not unduly discriminatory or preferential; and (2) if not, what changes
to the Tariff should be implemented as replacement rates.
We recognize that PJM and/or the Transmission Owners (to the extent the matters
addressed herein implicate aspects of the Tariff over which they have the filing rights)
may elect to address some or all of the issues discussed in this order by proposing
revisions to the Tariff pursuant to their applicable FPA section 205 filing rights. We
strongly encourage this. Although both the Secretary’s ANOPR and our own Order
Regarding Intent to Act expressly recognized (and indeed encouraged) that possibility,110
no such filings were received from PJM by the Commission prior to the issuance of this
order. Should PJM and/or the Transmission Owners elect to make such filings in
response to this order, those filings should state explicitly that the proposals are being
submitted under FPA section 205. Should PJM and/or the Transmission Owners submit a
filing under FPA section 205, they should also explain which of the Commission’s above
directives their filing addresses and how it resolves them. Additionally, any such filing
should provide a reasoned explanation for how the proposal will avoid disrupting existing
commercial arrangements and clearly identify a reasonable effective date that
accommodates such existing commercial arrangements.
The Commission will consider requests from PJM and/or the Transmission
Owners to hold, for up to 90 days, all or certain aspects of this FPA section 206
proceeding in abeyance, including the deadline to respond to this order. Any such
abeyance, which will begin as of the deadline to respond to this order, would be
considered to provide PJM and the Transmission Owners time while they work through
the stakeholder processes to develop FPA section 205 filings to revise the Tariff to
address the issues raised in this order. Requests for a full or partial abeyance111 should be
110 See ANOPR at P 32; Order Regarding Intent to Act, 195 FERC ¶ 61,045 at P 5.
111 A partial abeyance may be appropriate to the extent PJM is developing FPA
section 205 filings in response to only a subset of the directives in this order. For any
PDF page 30
Docket No. EL26-67-000
- 30 -
submitted prior to the deadline to respond to this order, specifically within 45 days of
issuance of this order, to allow time for the Commission to act on the abeyance request.
We emphasize that we will not grant such abeyances reflexively, that any abeyance will
be limited to 90 days, and that we will look with great disfavor toward requests to extend
the abeyance period. We anticipate that successful abeyance requests, if any, will include
both (1) a robust description of the content of a potential future filing under FPA
section 205 and (2) a reasoned and specific explanation of when such a filing is expected
to be made.
In cases where, as here, the Commission institutes a section 206 investigation on
its own motion, section 206(b) of the FPA requires that the Commission establish a
refund effective date that is no earlier than the date of the publication by the Commission
of notice of its intention to initiate such proceeding nor later than five months after the
publication date. In such cases, in order to give maximum protection to customers, and
consistent with our precedent, we have historically tended to establish the section 206
refund effective date at the earliest date allowed by section 206, and we do so here as
well.112 That date is the date of publication of notice of initiation of this proceeding in
the Federal Register.
A.
Transmission Service to Eligible Customers on Behalf of Large Loads
We today make a preliminary finding that PJM’s Tariff appears to be unjust and
unreasonable because it lacks provisions that address, with sufficient clarity and
consistency, how PJM and/or the Transmission Owners will timely study (i.e., within
60-90 days of receiving the request) the provision of transmission service to Eligible
Customers on behalf of large loads.113
Throughout this order, we use the phrase “the provision of transmission service to
Eligible Customers on behalf of large loads” to encompass the provision of new,
modified, or additional jurisdictional transmission service to Eligible Customers on
behalf of large loads. We note that this phrase is not limited to instances where an
Eligible Customer submits an application to request new transmission service. It also
includes instances where an Eligible Customer requests a new or modified point of
remaining directives, we expect a response to this order within the 60-day deadline set
forth herein.
112 See, e.g., Idaho Power Co., 145 FERC ¶ 61,122 (2013); Canal Elec. Co.,
46 FERC ¶ 61,153, order on reh’g, 47 FERC ¶ 61,275 (1989).
113 As discussed below, our findings here also apply to the study process for
unbundled retail transmission service requests by end-use large load customers, as
allowed by state law or voluntary utility rules.
PDF page 31
Docket No. EL26-67-000
- 31 -
delivery to serve a large load, where a large load seeks a new or modified delivery point
as an unbundled retail transmission service customer, or where large loads are otherwise
included in an Eligible Customer’s reported load growth and that Eligible Customer is
taking NITS.
We direct PJM and the Transmission Owners to the extent the matters addressed
herein implicate aspects of the Tariff over which they have the filing rights, to explain
whether the Tariff remains just and reasonable without an application process, study
procedures, and ongoing operational requirements that address the unique characteristics
and challenges of providing transmission service to Eligible Customers on behalf of large
loads, or to propose appropriate Tariff revisions.
1.
Jurisdiction
At the outset, we clarify the principles relating to the Commission’s jurisdiction
over the matters relevant to the integration of large loads onto the transmission system
and the impacts of large loads on the transmission system. We recognize that rates,
terms, and conditions associated with the addition of and service to large loads implicate
both federal and state interests. We also recognize that resolution of issues related to
large load additions will require the involvement of both federal and state actors,
including the Commission, state public utility commissions, and other state and local
entities. We are encouraged by efforts made at the state level to address issues related to
large load additions that fall within state jurisdiction.114
As discussed below, however, certain aspects of the process for integrating large
loads onto the transmission system fall squarely within the Commission’s exclusive
jurisdiction. Specifically, we find that it is within the Commission’s exclusive authority
to ensure that transmission provider and/or transmission owner tariffs include sufficiently
clear and consistent provisions governing how transmission service to Eligible Customers
on behalf of large loads interconnecting to the transmission system will be studied,
including whether new or upgraded transmission facilities are necessary to provide the
requested transmission service. The Commission has jurisdiction over the study process
for transmission service to both Eligible Customers on behalf of large loads and
unbundled retail transmission service to end-use large load customers where, pursuant to
state law or a public utility’s voluntary offer of such service, the large load is an Eligible
Customer under the transmission provider and/or transmission owner tariffs.115
114 See generally NARUC April 14 ANOPR Comments (highlighting action taken
by state public utility commissions related to large loads).
115 Under the pro forma OATT, Eligible Customers include end-use customers
seeking unbundled retail transmission service, pursuant to state law or public utility’s
PDF page 32
Docket No. EL26-67-000
- 32 -
The Commission is a creature of statute and has jurisdiction over only those
matters that Congress has given it the authority to regulate.116 That authority includes
jurisdiction over the wholesale sale and transmission of electricity in interstate
commerce, including all facilities used for such sale and transmission.117 As relevant
here, the Commission must ensure that the rates, charges, and classifications for such
transmission of electricity—as well as the practices directly affecting such transmission
of electricity—are just and reasonable and not unduly discriminatory or preferential.118
The Supreme Court has held that the Commission’s authority over interstate transmission
is not limited to wholesale transmission service and that the Commission has authority
over unbundled retail transmission service.119 As part of its transmission authority, the
Commission has exercised jurisdiction over the terms of certain interconnections to the
transmission system as an element of transmission service,120 including the
interconnection of wholesale load to the transmission system.121
As applied to large load additions to the transmission system, these principles
mean that the Commission has exclusive jurisdiction over the rates, terms, and conditions
of interstate transmission service to Eligible Customers on behalf of large loads
connecting to the transmission system, and the practices directly affecting the provision
of such interstate transmission of electricity. An essential component of providing such
transmission service is the process by which the transmission provider and/or
voluntary offer of such service. Pro forma OATT, § 1.12 (Definitions – Eligible
Customer); see also PJM Tariff pt. VIII, § 400 (Definitions E) (2.0.0).
116 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002).
117 16 U.S.C. § 824(b)(1).
118 Id. §§ 824d, 824e; see FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278
(2016) (EPSA) (approving “a common-sense construction of the FPA’s language,
limiting FERC’s ‘affecting’ jurisdiction to rules or practices that ‘directly affect the
wholesale rate’” (cleaned up)).
119 New York v. FERC, 535 U.S. 1, 17, 19-20 (2002) (upholding the Commission’s
exercise of jurisdiction over unbundled retail transmission service).
120 Tenn. Power Co., 90 FERC ¶ 61,238, at 61,761 (2000) (Tennessee Power),
order denying reh’g, 91 FERC ¶ 61,271 (2000); Standardization of Generator
Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103, at P 9
(2003); see also Laguna Irrigation Dist., 91 FERC ¶ 61,340, at 62,152 (2000).
121 Pac. Gas & Elec. Co., 109 FERC ¶ 61,392, at P 37 (2004); Pac. Gas & Elec.
Co., 115 FERC ¶ 61,193, at PP 36-38 (2006).
PDF page 33
Docket No. EL26-67-000
- 33 -
transmission owner evaluates (1) whether it can provide the requested transmission
service and (2) the impact that providing such transmission service will have on the
jurisdictional transmission system, including determining whether any new or upgraded
transmission facilities are needed to provide transmission service while maintaining
reliable operation of the transmission system. This transmission service study process
determines what Network Upgrades are needed to provide transmission service to
Eligible Customers on behalf of large loads, the costs of which are included in
transmission rates. As such, this study process directly affects Commission-jurisdictional
transmission rates.122 The Commission has exclusive authority to ensure that the process
to study the provision of transmission service to Eligible Customers is just and reasonable
and not unduly discriminatory or preferential. We therefore find that we have authority
to ensure that tariffs include provisions that clearly and consistently address the study
process for the provision of transmission service to Eligible Customers on behalf of large
loads, including the unique impacts that providing transmission service to Eligible
Customers on behalf of large loads may have on the transmission system.
At the same time, we continue to recognize that the FPA expressly reserves to
states the authority over any other sale of electric energy, including retail sales and
wholesale sales not in interstate commerce (such as wholesale sales within the Electric
Reliability Council of Texas region), as well as facilities used for the generation and
distribution of electricity.123 As such, we recognize that states will continue to regulate:
(1) the specific terms of retail sales to large load;124 (2) which entities may make retail
sales within their borders, including which entities are legally permitted to provide
electricity to retail large load customers;125 and (3) any siting decisions and construction
122 Cf. Transmission Plan. & Cost Allocation by Transmission Owning &
Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051, at P 112 (2011) (“It is
through the transmission planning process that public utility transmission providers
determine which transmission facilities will more efficiently or cost-effectively meet the
needs of the region, the development of which directly impacts the rates, terms and
conditions of jurisdictional service.”).
123 16 U.S.C. § 824(b)(1); see Dayton Power & Light Co. v. FERC, 126 F.4th
1107, 1129 (6th Cir. 2025).
124 See EPSA, 577 U.S. at 279-80 (recognizing state authority over retail electricity
sales); New York v. FERC, 535 U.S. at 28 (same).
125 PJM Show Cause Order, 190 FERC ¶ 61,115 at PP 68-69.
PDF page 34
Docket No. EL26-67-000
- 34 -
associated with the large load project.126 Nothing in this order is intended to intrude upon
state authority over retail service to large loads.
In sum, we today exercise our authority to ensure that the process by which
jurisdictional transmission providers and/or transmission owners will study the provision
of jurisdictional transmission service to Eligible Customers on behalf of large loads
interconnecting to the transmission system, including where, as allowed by state law or a
public utility’s voluntary offer of such service, an end-use large load seeks unbundled
retail transmission service, is just and reasonable and not unduly discriminatory or
preferential. Pursuant to that authority, we find that PJM’s Tariff appears to be unjust
and unreasonable or unduly discriminatory or preferential because it lacks sufficiently
clear and consistent provisions regarding the study process related to the provision of
transmission service to Eligible Customers on behalf of large loads. We need not
comprehensively address the Commission’s jurisdiction over other aspects of the addition
of large loads to the transmission system at this time.
2.
Tariff Provisions
In the following section, we begin by considering PJM’s Tariff as it relates to how
PJM and/or the Transmission Owners will study the provision of transmission service to
Eligible Customers on behalf of large loads and explain our concerns that the lack of
sufficiently clear and consistent provisions regarding the study process for the provision
of transmission service to Eligible Customers on behalf of large loads is unjust and
unreasonable or unduly discriminatory or preferential. We then consider whether the
Tariff is unjust and unreasonable without certain elements. First, we consider whether
the Tariff lacks sufficiently clear and consistent Tariff provisions establishing an
appropriate definition of large load, as a separate category of load. Second, we consider
whether the Tariff lacks sufficiently clear and consistent Tariff provisions establishing an
application process and requirements for Eligible Customers requesting transmission
service on behalf of large loads and a study process that considers the unique operational
challenges of providing transmission service to Eligible Customers on behalf of large
loads. Third, we consider whether the Tariff lacks sufficiently clear and consistent Tariff
provisions establishing ongoing operational requirements necessary to ensure that PJM
can reliably provide transmission service given the unique operational impacts on the
transmission system of providing transmission service to Eligible Customers on behalf of
large loads. Finally, we consider whether the Tariff requires such ongoing operational
126 See, e.g., Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 238 (D.C.
Cir. 2025) (citing 16 U.S.C. § 824(b)(1)) (recognizing state authority over generation
resource mix, including through their siting authority); Order No. 1000, 136 FERC
¶ 61,051 at P 107 (acknowledging state authority over siting, permitting, and construction
of transmission facilities).
PDF page 35
Docket No. EL26-67-000
- 35 -
requirements for Eligible Customers taking transmission service on behalf of large loads
to be memorialized in service agreements.
We preliminarily find that PJM’s Tariff appears to be unjust and unreasonable or
unduly discriminatory or preferential because it does not contain provisions addressing
with sufficient clarity and consistency how PJM and/or the Transmission Owners will
study the provision of transmission service to Eligible Customers on behalf of large
loads. We recognize that PJM and/or the Transmission Owners may have existing load
integration processes, including studies that are performed in evaluating the provision of
transmission service to Eligible Customers on behalf of large loads.127 However, we are
concerned that those processes and any required studies with regard to the provision of
transmission service are not described in the Tariff with the degree of clarity and
specificity necessary to ensure that the transmission provider can mitigate operational
risks of providing transmission service to Eligible Customers on behalf of large loads,
given their impact on the transmission system, avoid disputes regarding how studies are
conducted, deter speculative or duplicative requests for transmission service by Eligible
Customers on behalf of large loads, and help avoid excessive and unnecessary Network
Upgrades. Moreover, we are concerned that the existing Tariff does not contain other
elements akin to those described below, which we preliminarily find may be necessary to
ensure that the rates, terms, and conditions of jurisdictional transmission service are just
and reasonable.
At the outset, we recognize that the Transmission Owners may be primarily
responsible for conducting the studies that (1) evaluate whether a large load may be
interconnected to the transmission system and served by the Eligible Customer, and
(2) determine whether Network Upgrades are necessary to provide transmission service.
We appreciate that this role may stem from how PJM and the Transmission Owners
allocated rights and responsibilities in the governing documents establishing PJM. We
do not seek to alter that allocation of rights and responsibilities.
We are nonetheless concerned that PJM’s Tariff lacks a study process that
addresses the unique operational and reliability challenges that providing transmission
service to Eligible Customers on behalf of large loads presents to the transmission
system. Large loads can be more energy intensive and geographically concentrated than
traditional load, and exhibit different load profiles and operational characteristics.128
127 See supra PP 20-24.
128 See, e.g., SPP HILL Order, 194 FERC ¶ 61,031 at PP 7-8; NERC,
Characteristics and Risks of Emerging Large Loads (July 2025),
https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-
PDF page 36
Docket No. EL26-67-000
- 36 -
PJM itself has recognized that enhanced large load saturation can have a disproportionate
impact on system reliability, including voltage and frequency fluctuations due to their
size and unique characteristics, if mitigating operational steps and other protection
schemas are not developed and implemented.129 The PJM Board has also recognized that
the scale, pace, and characteristics of large load growth present significant operational
and planning challenges.130 As a result, providing transmission service to Eligible
Customers on behalf of large loads may be more complex and could raise greater
reliability concerns for the transmission system, relative to a situation where Eligible
Customers seek transmission service on behalf of traditional load.
Without a clear and consistent process to study the provision of transmission
service to Eligible Customers on behalf of large loads, PJM and/or the Transmission
Owners may not fully capture the transmission system impacts of providing such
transmission service, which could result in significant operational risks for the
transmission system. Furthermore, we are concerned that, without sufficiently clear and
consistent Tariff provisions, PJM will not have the ongoing visibility and operational
control necessary to provide reliable transmission service.
We are also concerned that the absence of sufficiently clear and consistent Tariff
provisions for how PJM and/or the Transmission Owners will study the provision of
transmission service to Eligible Customers on behalf of large loads will lead to disputes
over a variety of issues—e.g., study timelines and delays,131 how the transmission service
needed on behalf of the large load is studied,132 what types of Network Upgrades are
characteristics-and-risks-of-emerging-large-loads.pdf (NERC Characteristics and Risks
of Large Loads).
129 PJM November 21 ANOPR Comments at 12.
130 See PJM Board Letter. PJM TOs further note that many data centers’ initial
loads are significantly lower when they first enter commercial operation, but following
expansion and full potential of operation capacity, their demand increases to much higher
levels. PJM TOs November 21 ANOPR Comments at 9.
131 See, e.g., Institute for Progress November 21 ANOPR Comments at 7-8;
Microsoft November 21 ANOPR Comments at 9; ODEC December 5 ANOPR
Comments at 4; Vistra November 21 ANOPR Comments at 21 (discussing lack of
defined load interconnection process in PJM and lack of detail in PJM Tariff and manuals
regarding load integration study).
132 Commenters raised concern that large loads are not studied with consideration
of their known operating characteristics, including their willingness to be flexible or
curtailable. See, e.g., ClearPath November 21 ANOPR Comments at 5-6; Constellation
November 21 ANOPR Comments at 23-24; Critical Loop November 21 ANOPR
PDF page 37
Docket No. EL26-67-000
- 37 -
considered, and how required Network Upgrades to provide the requested transmission
service are determined.133 Such disputes may arise from the lack of transparency in how
studies are performed and how decisions will be made.134 We are thus concerned that the
lack of clear and consistent provisions in PJM’s Tariff related to the study process for the
provision of transmission service to Eligible Customers on behalf of large loads appears
to be unjust and unreasonable or unduly discriminatory or preferential.
Lastly, we are concerned that PJM’s existing Tariff fails to deter speculative or
duplicative requests for transmission service by Eligible Customers on behalf of large
loads. Many ANOPR comments assert that clear and consistent provisions establishing
study timelines and costs, readiness requirements, and/or penalties will deter speculative
or duplicative requests related to large load additions.135 Commenters explain that
Comments at 3; GridCare December 5 ANOPR Comments at 1-2; L. Lynne Kiesling
November 21 ANOPR Comments at 10.
133 Specifically, commenters raised concern that transmission providers/owners
may only consider traditional transmission infrastructure or that there is a lack of
consideration of alternative transmission solutions. See, e.g., ACORE November 21
ANOPR Comments at 3-4, 6-7; American Terawatt November 21 ANOPR Comments
at 4-5; Calibrant November 21 ANOPR Comments at 1-2, 3; CEBA November 21
ANOPR Comments at 9-10; Chamber of Commerce November 21 ANOPR Comments
at 3; CTC Global Corporation November 21 ANOPR Comments at 1-3; DCC
November 21 ANOPR Comments at 10-11; GridCARE December 5 ANOPR Comments
at 4; Industrial Customers November 21 ANOPR Comments at 27-28; Infrastructure
Masons December 5 ANOPR Comments at 18; Iron Mountain Data Centers, LLC
November 21 ANOPR Comments at 3-4; Land Trust Alliance November 21 ANOPR
Comments at 5-6; PIOs November 21 ANOPR Comments at 22; Southeast PIOs
November 21 ANOPR Comments at 44-45; WATT and Advancing Modern Powerlines
November 21 ANOPR Comments at 5-8.
134 See, e.g., CEBA November 21 ANOPR Comments at 12; ECA December 5
ANOPR Comments at 1-2; Eolian November 21 ANOPR Comments at 17-18; EPSA
November 21 ANOPR Comments at 6; Infrastructure Masons December 5 ANOPR
Comments at 4, 6-7; Southeast PIOs November 21 ANOPR Comments at 39-40; Switch
December 5 ANOPR Comments at 3; Tract November 21 ANOPR Comments at 5;
Vantage November 21 ANOPR Comments at 5-6; Verrus November 21 ANOPR
Comments at 6, 12; Vistra December 5 ANOPR Comments at 27.
135 See, e.g., ACORE November 21 ANOPR Comments at 6; AEU November 21
ANOPR Comments at 17-18; Amazon November 21 ANOPR Comments at 6; Crusoe
December 5 ANOPR Comments at 5-6; EDF Power November 21 ANOPR Comments
at 12-13; EEI November 21 ANOPR Comments at 20; Fervo November 21 ANOPR
PDF page 38
Docket No. EL26-67-000
- 38 -
speculative requests may bog down and delay the study process, wasting time and
resources for transmission providers;136 result in inaccurate study results or delays for
other Eligible Customers seeking transmission service on behalf of load;137 create a
substantial risk of cost shifts if the large load additions do not materialize as planned;138
and distort load forecasts.139 Clear and consistent study procedures that include readiness
requirements (i.e., meaningful milestones and/or financial commitments) can help ensure
that Eligible Customers’ requests for transmission service on behalf of large loads are
more viable and more likely to materialize as planned, given that they must meet specific
milestones and/or pay costs to proceed.
More specifically, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks sufficiently clear and consistent Tariff provisions that
Comments at 3; GridCare December 5 ANOPR Comments at 5; Invenergy November 21
ANOPR Comments at 6; Microsoft November 21 ANOPR Comments at 9; Ohio FEA
November 21 ANOPR Comments at 4.
136 See, e.g., Eolian November 21 ANOPR Comments at 17-18; GridCare
December 5 ANOPR Comments at 5; Illinois AG November 21 ANOPR Comments
at 9-10; Institute for Progress November 21 ANOPR Comments at 9; OCC November 21
ANOPR Comments at 7-8; Ohio FEA November 21 ANOPR Comments at 4; Vistra
November 21 ANOPR Comments at 23.
137 See, e.g., Amazon November 21 ANOPR Comments at 6; CEBA November 21
ANOPR Comments at 8; ClearPath November 21 ANOPR Comments at 4; Geronimo
November 21 ANOPR Comments at 12; TAPS November 21 ANOPR Comments
at 14-15.
138 See, e.g., AES November 21 ANOPR Comments at 10-11; Buckeye
November 21 ANOPR Comments at 1-2; Exelon November 21 ANOPR Comments at 3;
NRECA November 21 ANOPR Comments at 9; OCC November 21 ANOPR Comments
at 9; Southeast PIOs November 21 ANOPR Comments at 20; State Entities November 21
ANOPR Comments at 7-8; TAPS November 21 ANOPR Comments at 15, 22-24;
Tri-State November 21 ANOPR Comments at 6, 8; Vistra November 21 ANOPR
Comments at 23.
139 See, e.g., CEBA November 21 ANOPR Comments at 8; EEI November 21
ANOPR Comments at 20; ELCON November 21 ANOPR Comments at 7; Invenergy
November 21 ANOPR Comments at 6; GridCare December 5 ANOPR Comments at 5;
OCC November 21 ANOPR Comments at 9; PIOs November 21 ANOPR Comments
at 5; Southeast PIOs November 21 ANOPR Comments at 41; Talen November 21
ANOPR Comments at 9.
PDF page 39
Docket No. EL26-67-000
- 39 -
address certain aspects of the process to provide transmission service to Eligible
Customers on behalf of large loads, including:
(1) a definition of large load sufficient to capture loads that present the unique
challenges described herein;
(2) the application process for requesting transmission service to Eligible
Customers on behalf of large loads and the study procedures, including readiness
requirements, for studying the provision of transmission service to Eligible
Customers on behalf of large loads;
(3) ongoing operational requirements for transmission customers140 serving large
loads necessary to ensure reliable operation of the transmission system; and
(4) pro forma provisions in transmission service agreements to memorialize these
terms.
First, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks a definition of large load, as a new category of load. As
PJM acknowledges, integrating large loads poses specific challenges to transmission
system operation given their size, operational behavior, and unique potential to impact
the transmission system.141 An appropriate definition, including a load size and
interconnection voltage threshold, should be based on the characteristics of PJM’s
transmission system. That said, based on the record in the ANOPR proceeding,142 it
appears that it would be reasonable to define a large load as a new, commercial or
140 We note that such ongoing operational requirements should apply to
transmission customers, rather than Eligible Customers, as these requirements apply after
the Eligible Customer has an executed (or a filed unexecuted) service agreement for
transmission service and have become transmission customers under the Tariff.
141 PJM November 21 ANOPR Comments at 12.
142 See, e.g., Constellation November 21 ANOPR Comments at 13 (supporting a
voltage threshold); DTE November 21 ANOPR Comments at 3, 17-19 (recommending a
threshold of an amount between 50 MW to 100 MW); Eolian November 21 ANOPR
Comments at 8-9 (recommending a voltage threshold greater than or equal to an amount
between 60 kV to 100 kV); Illinois AG November 21 ANOPR Comments at 7
(supporting a 20 MW or 50 MW threshold and consideration of other factors, such as
voltage level); ITC November 21 ANOPR Comments at 3 (recommending a threshold of
between 50 MW to 100 MW); Nebraska Board November 21 ANOPR Comments at 4
(proposing a 50 MW threshold); New Mexico Commission November 21 ANOPR
Comments at 5 (proposing a 50 MW threshold).
PDF page 40
Docket No. EL26-67-000
- 40 -
industrial customer, located at a single site behind one or more points of interconnection,
and that has a peak load of 50 MW or greater, interconnects to the transmission system at
a voltage level of greater than 69 kV, and is not part of a co-location arrangement. In its
response to this order, PJM should explain whether the Tariff remains just and reasonable
without such a definition, or propose Tariff revisions establishing its own definition of
large load.
Second, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks sufficiently clear and consistent Tariff provisions
establishing the application process and study procedures that will be used when PJM
and/or the Transmission Owners evaluate the provision of transmission service to
Eligible Customers on behalf of large loads. PJM should explain whether the Tariff
remains just and reasonable, for example, without: (1) an application process that accepts
Eligible Customers’ applications for transmission service on behalf of large loads on a
rolling basis; (2) a non-refundable application fee and sufficient readiness requirements
that escalate at distinct phases of the study process to deter duplicative or speculative
requests for transmission service (e.g., meaningful milestones and/or financial
commitments); and (3) information and data requirements that Eligible Customers must
submit to PJM and/or the Transmission Owners regarding the characteristics of the large
load on behalf of which the Eligible Customer is taking transmission service, including
disclosure to PJM of any substantially similar pending transmission service requests on
behalf of the same large load customer.143 PJM may also elect to propose Tariff revisions
establishing such an application process, fee, and requirements.
Further, PJM’s Tariff appears to lack sufficiently clear and consistent provisions
establishing a study process for evaluating the provision of transmission service to
Eligible Customers on behalf of large loads that considers the unique characteristics and
impacts of large loads on the transmission system. For example, we are concerned that
PJM’s Tariff may not clearly and consistently require PJM or the Transmission Owners
to conduct studies that evaluate the transmission system’s ability to withstand risks
observed from analyzed large load behavior created by the large load at the point of
interconnection, or any other necessary supplemental studies to evaluate the impact of
providing transmission service to Eligible Customers on behalf of large loads.144
143 The Electric Reliability Council of Texas (ERCOT) has proposed a similar
disclosure requirement in its Batch Zero process for large load interconnections. ERCOT
Planning Guide, § 9.7.1(1)(b) (proposed Mar. 4, 2026).
144 See generally NERC, Industry Recommendation: Large Load Interconnection,
Study, Commissioning, and Operations (Sep. 2025),
https://www.nerc.com/globalassets/programs/bpsa/alerts/2025/nerc-alert-level-2--large-
PDF page 41
Docket No. EL26-67-000
- 41 -
Additionally, we preliminarily find that PJM’s Tariff appears unjust and unreasonable
because it lacks appropriate provisions recognizing within the transmission service
request study process the unique operational characteristics of large loads that are willing
and able to limit their energy withdrawals under certain conditions, which may thereby
lessen or potentially avoid the need for certain Network Upgrades. While flexible large
loads can reduce the demand on the transmission system, and therefore potentially reduce
the need for additional transmission capacity, additional informational and study
requirements may be necessary to account for the dynamic nature of these types of loads
while maintaining reliability.145 Additionally, we note that accurate models using
Electromagnetic Transient studies may help to ensure that transmission service needed on
behalf of large loads can be provided without compromising reliability.146
Additionally, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks clear and consistent provisions requiring the evaluation of
alternative transmission technologies147 as potential solutions to accommodate an
Eligible Customer’s request for transmission service on behalf of a large load.
Alternative transmission technologies can add more capacity on existing transmission
loads.pdf (finding that unique operational characteristics of large loads necessitate
enhancements to studies).
145 See, e.g., AEMA November 21 ANOPR Comments at 6; Thermal Battery
Alliance November 21 ANOPR Comments at 7; Verrus November 21 ANOPR
Comments at 10.
146 See, e.g., NERC, Draft Reliability Guideline: Risk Mitigation for Emerging
Large Loads 6-7 (May 2026), https://www.nerc.com/globalassets/who-we-are/standing-
committees/rstc/reliabilityguideline_riskmitigationforemerginglargeloads.pdf; NERC,
Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for
Emerging Large Loads 31 (Mar. 2026), https://www.nerc.com/globalassets/our-
work/guidelines/reliability/white-paper---assessment-of-gaps.pdf; see also SPP HILL
Order, 194 FERC ¶ 61,031 at P 62.
147 For purposes of this order, alternative transmission technologies include static
synchronous compensators, static VAR compensators, advanced power flow control
devices, transmission switching, synchronous condensers, voltage source converters,
advanced conductors, tower lifting, and dynamic line ratings. We note that the
Commission has also referred to these types of technologies as Grid Enhancing
Technologies (GETs).
PDF page 42
Docket No. EL26-67-000
- 42 -
lines quickly, often within one to three years.148 Unlike with traditional load growth,149
large load customers often have development timelines requiring interconnection to the
transmission system faster than traditional Network Upgrades can be built, necessitating a
sufficient evaluation of alternative transmission technologies that can more quickly
accommodate transmission service requests from Eligible Customers on behalf of large
loads.150 The Commission has previously recognized that alternative transmission
technologies have the potential to mitigate or defer the need for traditional Network
Upgrades and often can be deployed both more quickly and at lower cost than traditional
Network Upgrades, and therefore failing to consider whether alternative transmission
technologies can meet transmission needs more efficiently or cost-effectively than
traditional Network Upgrades has the potential to render Commission-jurisdictional rates
148 WATT and Advancing Modern Powerlines November 21 ANOPR Comments
at 5-6.
149 See, e.g., SPP HILL Order, 194 FERC ¶ 61,031 at P 7 (explaining that the
HILL proposal was needed in part due to large load customers frequently requesting
transmission service within months rather than years of their intended commercial
operation, straining legacy regulatory frameworks and planning processes originally
designed for slow, incremental, and predictable load growth); see also Commission Staff,
2025 State of the Market Report 8 (Mar. 2026) (“[D]ata centers have characteristics
unlike more traditional loads [including] size, strong desire for faster interconnection, and
potential flexibility.”).
150 Exec. Off. of the President, Winning the Race: America’s AI Action Plan 1-2,
15 (July 2025), https://www.whitehouse.gov/wp-content/uploads/2025/07/Americas-AI-
Action-Plan.pdf (explaining that accelerated deployment of AI data centers is a critical
matter of national security and international economic competitiveness, and
recommending federal policy action to optimize the existing grid through advanced grid
technologies); WATT and Advancing Modern Powerlines November 21 ANOPR
Comments at 5-8 (“[Alternative transmission technologies’] deployment timelines are
more aligned with the interconnection needs of new large loads, which may only take 1-2
years to construct.”); Industrial Customers November 21 ANOPR Comments at 28
(“Achieving speed-to-power in the near-term, while also protecting customers, will
require the use of GETs, advanced reconductoring, and unlocking all available system
capacity.”); Energy Systems Integration Group, Historical and Modern Large Loads:
Characteristics, Context, and Industry Action to Meet Grid and Customer Needs 4
(Mar. 2026), https://www.esig.energy/wp-content/uploads/2026/03/ESIG-Historical-vs-
Modern-Large-Loads-white-paper-2026.pdf (describing the timing mismatch between
how long it takes to build a new data center and how long it takes to plan, permit, and
build transmission).
PDF page 43
Docket No. EL26-67-000
- 43 -
unjust and unreasonable.151 Further, to the extent Network Upgrade costs to
accommodate an Eligible Customer’s request for transmission service on behalf of a large
load are rolled into a transmission owner’s transmission revenue requirement,
transmission customers other than the Eligible Customer may bear a portion of those
Network Upgrade costs, highlighting the need for clear and consistent provisions
requiring the evaluation of least-cost options like alternative transmission technologies to
mitigate the rate impact on all transmission customers.
PJM should explain whether the Tariff remains just and reasonable without
provisions that: (1) require the evaluation of alternative transmission technologies in
transmission service request studies, using models that are capable of evaluating the
transmission system to accurately account for advanced transmission technologies, in all
instances, without the need for a request from the Eligible Customer seeking transmission
service on behalf of a large load; and (2) if traditional Network Upgrades are selected
instead of alternative transmission technologies, inclusion in the study report to the
Eligible Customer seeking transmission service on behalf of a large load of a sufficiently
clear demonstration of why alternative transmission technologies are not feasible (i.e.,
would not resolve reliability violations identified or meet the relevant planning criteria)
or would not result in lower costs or a faster timeline for accommodating the transmission
service request; or propose Tariff revisions establishing such provisions. This
transparency and informational requirement is warranted for the regulatory scheme we
are establishing for transmission service requests by Eligible Customers on behalf of
large loads given demand from and the expedited development timelines for large load
customers. We underscore that we are not mandating the use of alternative transmission
technologies. To the extent stakeholders believe that specific characteristics of providing
transmission service to Eligible Customers on behalf of large loads warrant requirements
beyond those contemplated here, we seek further briefing.
Finally, based on the record, it appears reasonable that such study processes,
culminating in a report to the Eligible Customer with the results of the studies, including
any Direct Assignment Facilities and Network Upgrades necessary to accommodate the
transmission service request as well as a non-binding good-faith estimate of the cost and
the time to construct such facilities, should take no more than 60-90 days calendar days to
151 Improvements to Generator Interconnection Procs. & Agreements, Order
No. 2023, 184 FERC ¶ 61,054 at P 1583, order on reh’g, 185 FERC ¶ 61,063 (2023),
order on reh’g, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC
¶ 61,134 (2024); see also Bldg. for the Future Through Elec. Reg’l Transmission Plan. &
Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 at P 1201, order on reh’g, Order
No. 1920-A, 189 FERC ¶ 61,126 (2024), order on reh’g, Order No. 1920-B, 191 FERC
¶ 61,026 (2025).
PDF page 44
Docket No. EL26-67-000
- 44 -
complete.152 To the extent PJM or the Transmission Owners already have such
procedures and conduct such studies, but those processes are not included in the Tariff,
PJM and the Transmission Owners should explain their existing processes and consider
whether amendments are necessary to the Tariff to memorialize those processes and also
address the concerns expressed herein. Otherwise, PJM should explain whether the
Tariff remains just and reasonable without: (1) sufficiently clear and consistent
provisions to evaluate the impact of providing the requested transmission service to
Eligible Customers on behalf of large loads, including identifying the Direct Assignment
Facilities and Network Upgrades necessary to provide such service reliably;
(2) provisions to appropriately recognize within the transmission service study process
the unique operational characteristics of large loads; (3) a study deadline of no more than
60-90 calendar days; or propose Tariff revisions establishing them.
Third, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks provisions addressing ongoing operational requirements for
transmission customers taking transmission service on behalf of large loads. We are
concerned that without such requirements the rates, terms, and conditions of transmission
service may be unjust and unreasonable. The unique nature of these large loads creates
challenges for operation of the transmission system and necessitates greater visibility and
operational control when providing transmission service to transmission customers on
behalf of large loads, without which the reliability of the transmission system could be at
risk.153 For example, we are concerned that PJM’s Tariff does not require transmission
customers to provide PJM hourly forecasts, telemetry data, and other data to ensure
sufficient visibility or specify requirements for maintaining communication channels
between PJM and the transmission customer on behalf of the large load. Additionally,
we are concerned that the Tariff does not require transmission owners to install, and
transmission customers to pay for, equipment to enable PJM to monitor large loads for
impacts of, for example, fast-ramping load that may impact the transmission system too
quickly to be captured by conventional data acquisition systems (e.g., the need for phasor
152 Several commenters support a 60-day timeline. See, e.g., Constellation
November 21 ANOPR Comments at 26; Critical Loop December 5 ANOPR Comments
at 8; EDF Power November 21 ANOPR Comments at 16; Tract November 21 ANOPR
Comments at 9. Other commenters note that SPP’s HILL process has a 90-day timeline,
or otherwise support a 90-day timeline. See, e.g., AEMA November 21 ANOPR
Comments at 3; Eolian December 5 ANOPR Comments at 27; Industrial Customers
November 21 ANOPR Comments at 20; PJM November 21 ANOPR Comments at 7;
SPP November 21 ANOPR Comments at 16-17.
153 E.g., ATC November 21 ANOPR Comments at 14; CAISO November 21
ANOPR Comments at 10 (citing NERC Characteristics and Risks of Large Loads); Herb
Schrayshuen November 21 ANOPR Comments at 2-5.
PDF page 45
Docket No. EL26-67-000
- 45 -
measurement units or similar equipment). We are also concerned that the Tariff does not
require the transmission customer to enable PJM to remotely disconnect large loads when
necessary to maintain reliability of the transmission system, with the costs of such
equipment directly assigned to the transmission customer, as well as the terms and
conditions under which PJM may remotely disconnect the large load (e.g., emergency
conditions, so that transmission equipment is not harmed). Further, we are concerned
that the Tariff does not specify ramp rate or ride-through requirements with which the
transmission customer taking transmission service on behalf of the large load must
comply. Lastly, we are concerned that the Tariff does not specify requirements for
necessary control technologies and/or protection systems that may be necessary to limit a
transmission customer’s withdrawals from the transmission system as appropriate.154
PJM should explain whether the Tariff remains just and reasonable without these or other
ongoing operational requirements as part of the rates, terms, and conditions of
transmission service or propose Tariff revisions establishing necessary ongoing
operational requirements.
Fourth, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks pro forma provisions in a transmission service agreement
between PJM and the transmission customer taking transmission service on behalf of a
large load to memorialize the above terms (e.g., equipment requirements, data
requirements, remote disconnect capability). We are concerned that, without such
pro forma provisions in a transmission service agreement between PJM and the
transmission customer, PJM may be unable to enforce ongoing operational requirements
for transmission customers taking transmission service on behalf of large loads. PJM
should explain whether the Tariff remains just and reasonable without such pro forma
provisions in a transmission service agreement, or propose revisions to include pro forma
provisions memorializing the ongoing operational requirements in a transmission service
agreement between PJM and the transmission customer.
B.
Cost Shifting Risk Among Transmission Customers
We next preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting
among transmission customers, which may result in unjust and unreasonable rates for
transmission service. In particular, we are concerned about the apparent lack of:
(1) transparency regarding the assignment of Network Upgrades, and their associated
costs, that are needed to provide transmission service to Eligible Customers on behalf of
large loads; and (2) a pro forma cost recovery agreement between PJM, the relevant
154 Specifically, as discussed below, the Commission has found that such
necessary control technologies and/or protection schemes may be appropriate where
Eligible Customers are taking one of the new transmission services. See infra P 87.
PDF page 46
Docket No. EL26-67-000
- 46 -
transmission owner, and the Eligible Customer taking transmission service on behalf of
large loads that help ensure that Eligible Customers bear the risk and are ultimately
responsible for costs incurred to provide transmission service, including the cost of
Network Upgrades.
We direct PJM and the Transmission Owners, to the extent the matters addressed
herein implicate aspects of the Tariff over which they have the filing rights, to explain
whether the Tariff remains just and reasonable without (1) robust, accurate, and
systematic provision of data on PJM’s website in a single location, and in an easily
accessible format that is searchable and allows users to filter the data, regarding the cost
for Network Upgrades needed to provide transmission service to Eligible Customers on
behalf of large loads; and (2) a pro forma cost recovery agreement between PJM, the
relevant transmission owner, and the Eligible Customer taking transmission service on
behalf of a large load, or to propose Tariff revisions to provide additional transparency
and establish such a pro forma cost recovery agreement. We encourage state regulators
responsible for setting retail rates to provide input to PJM regarding their transparency
needs.
1.
Jurisdiction
The Commission has a duty to address the risk of cost shifting among transmission
customers that may result in unjust and unreasonable transmission rates. As explained
above, the Commission is obligated to ensure that the rates charged for jurisdictional
transmission service—as well as any practice directly affecting such rates—are just and
reasonable and not unduly discriminatory or preferential. With respect to the addition of
large loads to the transmission system, the Commission has exclusive authority to ensure
that transmission rates are just and reasonable. The costs of those upgrades to the
transmission system (i.e., Network Upgrades) necessary to provide transmission service
to Eligible Customers on behalf of large loads are inputs to jurisdictional transmission
rates, and thus directly affect the Commission-jurisdictional rates paid by transmission
customers. To fulfill its responsibility to ensure that transmission rates are just and
reasonable, the Commission must act to address the risk of cost shifting among
transmission customers due to (1) the process transmission providers and/or transmission
owners use to evaluate the facilities needed, and the associated costs, for the provision of
transmission service to Eligible Customers on behalf of large loads and (2) speculative
transmission service requests by Eligible Customers on behalf of large loads that could
result in unjust and unreasonable transmission rates.
In response to the ANOPR, many commenters raise concerns about the impact that
large load additions can have on retail ratepayers, particularly the concern that other retail
ratepayers may be forced to subsidize Network Upgrades needed to add large loads to the
PDF page 47
Docket No. EL26-67-000
- 47 -
transmission system.155 While we appreciate and are similarly concerned about this
issue, the Commission is limited to addressing jurisdictional transmission rates and as
such, we do so herein. As the Commission has explained, states determine how
Commission-approved rates are collected among the relevant retail consumers along with
the rates for state-jurisdictional matters.156 Specifically, states have authority over how
the wholesale costs of providing electricity, including transmission of such electricity, to
those retail customers are recovered through retail rates.157 We are encouraged by efforts
taken by states to reform retail tariffs to address the potential for retail cost shifting as
large loads come online,158 as well as voluntary efforts by transmission owners to protect
retail ratepayers through cost recovery agreements with large loads.159 We are also
encouraged by the execution of the President’s Ratepayer Protection Pledge, through
which data center developers have committed to shield retail ratepayers from increased
electricity prices.160
We expect that the additional cost transparency measures proposed in the
following section will give state public utility commissions and other state regulators the
information necessary to allow them to understand which transmission costs are caused
by which transmission customers, so that they can sub-allocate these costs to the
appropriate retail customers. Indeed, the Commission’s objective in this proceeding is to
respect the cooperative federalism approach established under the FPA. Specifically, one
of the benefits of providing transparency on the costs of Network Upgrades necessary to
provide transmission service to Eligible Customers on behalf of large loads is so that state
regulators can use that information to protect residential and small commercial customers
155 See, e.g., Illinois AG November 21 ANOPR Comments at 11-12; Missouri
Commission November 21 ANOPR Comments at 11; OMS November 21 ANOPR
Comments at 4.
156 PJM Show Cause Order, 190 FERC ¶ 61,115 at P 167.
157 Id. P 68.
158 See, e.g., Pennsylvania Commission November 21 ANOPR Comments at 7-8;
Maryland Commission November 21 ANOPR Comments at 2; Virginia Commission
November 21 ANOPR Comments at 4-5
159 See, e.g., Commonwealth Edison Co. 194 FERC ¶ 61,106; Commonwealth
Edison Co., 194 FERC ¶ 61,109; Commonwealth Edison Co., 194 FERC ¶ 61,110;
Commonwealth Edison Co., 194 FERC ¶ 61,113 (2026); PECO Energy Co., 193 FERC
¶ 61,148; Dayton Power & Light Co., 192 FERC ¶ 61,103; Dayton Power & Light Co.,
189 FERC ¶ 61,220 (2024).
160 Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026).
PDF page 48
Docket No. EL26-67-000
- 48 -
by incorporating those costs into the retail rates as they see fit given their authority to set
rates for different classes of retail customers. We encourage state public utility
commissions, state regulators, and state consumer advocates to submit comments
explaining whether this information is sufficient and granular enough or to submit
comments explaining precisely which additional information on transmission cost
allocation may be needed to inform proper state-jurisdictional cost allocation.
2.
Additional Cost Transparency
We preliminarily find that PJM’s Tariff appears to be unjust and unreasonable or
unduly discriminatory or preferential because it does not contain provisions requiring the
provision of data on PJM’s website in a single location, and in an easily accessible format
that is searchable and allows users to filter the data, on transmission service requested by
Eligible Customers on behalf of large loads, for Network Upgrades evaluated in the local
transmission planning process that are needed to provide transmission service to Eligible
Customers on behalf of those large loads, and the costs for those Network Upgrades. We
preliminarily find that cost transparency measures are needed to provide stakeholders
with sufficient information and visibility regarding the Network Upgrades, and their
associated costs, needed to provide transmission service to Eligible Customers on behalf
of large loads.
As discussed above, Network Upgrades needed to accommodate a new
transmission service request or designation of new network load may be designated as
local transmission facilities (i.e., Supplemental Projects) or contribute to regional
transmission system needs and be addressed by a Required Transmission Enhancement in
the RTEP. PJM’s Tariff Schedule 12 Appendix and Appendix A include the cost
responsibility assignments for regional transmission projects selected through the RTEP
process. In addition, Attachment M-3 of PJM’s Tariff provides procedures for
stakeholder review and comment on Supplemental Projects identified through
transmission owners’ local transmission planning process in the Transmission Expansion
Advisory Committee (230 kV or above) and Subregional RTEP Committee (below
230 kV) and as part of a transmission owner’s Local Plan, before the Local Plan is
submitted for integration into the RTEP.161 PJM’s website also includes a list of
Required Transmission Enhancements and Supplemental Projects with their project
status, cost, and cost allocation.162
161 See PJM Tariff, attach. M-3, § (c) (Procedures for Review of Attachment M-3
Projects) (1.0.0).
162 PJM, Project Status & Cost Allocation,
https://www.pjm.com/planning/m/project-construction.
PDF page 49
Docket No. EL26-67-000
- 49 -
However, PJM’s Tariff does not appear to require that information identifying the
Network Upgrades needed to provide transmission service to Eligible Customers on
behalf of large loads and the costs of those Network Upgrades determined through local
transmission planning processes be readily available on PJM’s website in a single
location, and in an easily accessible format that is searchable and allows users to filter the
data. We acknowledge that PJM’s website provides information concerning certain
transmission projects, including Supplemental Projects, such as project status, cost, cost
allocation, and the type of equipment and upgrade, and includes the primary driver for
each transmission project (i.e., load growth), but these postings do not appear to be
specific to transmission projects needed to provide transmission service to Eligible
Customers on behalf of large loads. The speed and scale with which Eligible Customers
are seeking transmission service on behalf of large loads makes it difficult for interested
parties, including transmission customers and state regulators, to accurately assess which
transmission costs are driven by requests for transmission service by Eligible Customers
to serve large loads. Further, as PJM acknowledges, it forecasts significant peak load
growth, but there is a large cone of uncertainty around the trajectory and amplitude of
future demand growth.163 We are concerned that the potentially speculative nature of
requests for transmission service by Eligible Customers on behalf of large loads,164 the
speed and scale with which large loads are seeking to be added to the transmission
system, the projected need for significant Network Upgrades to provide transmission
service to Eligible Customers on behalf of large loads, and the lack of centralized
information on the associated transmission costs in PJM hamper the ability of the
Commission and stakeholders (including transmission customers and state regulators165)
to understand and accurately assess the relationship between the addition of large loads to
the transmission system and wholesale transmission costs.
163 See PJM Board Letter at 1.
164 See supra P 56.
165 See Transcript, NARUC Collaborative, Docket No. AD24-7-000, at 16-17
(Feb. 11, 2026) (Chair Bagot, Virginia) (asserting that additional transparency at the RTO
level would help the states get the information they need to “identify . . . that bucket of
costs” related to large load-driven transmission costs), 19 (Commissioner Chattopadhyay,
New Hampshire) (noting the need for “all parties to be able to see things transparently”
with respect to wholesale transmission costs), 35-37 (Chair Martz, Iowa) (raising concern
that currently RTOs/ISOs do not have to clearly explain when a “bucket of costs is
specifically for this large load” and noting that “if we, at the state level, can’t see the
driver [of transmission costs], we can’t assign the cost to the causer[,] [a]nd so we need
that clarity”), 69-70 (Chair Myers, Arizona) (“[B]eing able to allocate the large load costs
to the correct bucket when it gets to the states is kind of a top priority.”).
PDF page 50
Docket No. EL26-67-000
- 50 -
We are concerned that without sufficient transparency regarding the Network
Upgrades, and their associated costs, needed to provide transmission service to Eligible
Customers on behalf of large loads, stakeholders may lack information and visibility
regarding the costs driven by large load additions. We preliminarily find that, for
Network Upgrades evaluated in the local transmission planning process166 that are
needed to provide transmission service to Eligible Customers on behalf of large loads,
PJM must provide clear, timely, and detailed information regarding the extent to which
requests for transmission service by Eligible Customers on behalf of large loads
necessitate Network Upgrades to accommodate the transmission service to Eligible
Customers on behalf of large loads, as well as the costs of those Network Upgrades.
We note that centralized information regarding Network Upgrades needed to
accommodate requests for transmission service by Eligible Customers on behalf of large
loads would also help inform stakeholders at the state and local level to address
affordability and other challenges posed by the integration of large loads. Indeed,
commenters state that the opaque nature of requests for transmission service by Eligible
Customers on behalf of large loads, and the associated Network Upgrades required to
provide that transmission service, prevent wholesale and retail customers, states, and
other stakeholders from understanding such costs.167
166 Our concern with transparency regarding Network Upgrades needed to provide
transmission service to Eligible Customers on behalf of large loads, as well as the costs of
such upgrades, is limited to Network Upgrades planned through the local transmission
planning process. While we acknowledge that in Order No. 890, the Commission
adopted requirements for RTOs/ISOs, as well as for transmission owners to the extent
that they perform transmission planning within an RTO/ISO, to have open and
transparent transmission planning processes, there are additional requirements that apply
to regional transmission planning processes (that do not apply to local transmission
facilities) and thus is relevant to the distinction here. Specifically, under Order No. 1000,
public utility transmission providers, including RTOs/ISOs, must evaluate as part of their
regional transmission planning process whether there are transmission facilities that more
efficiently or cost-effectively meet the transmission planning region’s identified
transmission needs. See Order No. 1000, 136 FERC ¶ 61,051 at P 11.
167 See OCC November 21 ANOPR Comments at 3 (“Consumers, state advocates
and state regulatory commissions have a right to know which entities are seeking
large-load interconnections, the nature of the requested service, and how related costs
could flow through to transmission and distribution rates.”); U.S. House of
Representatives Committee on Energy and Commerce Ranking Members November 21
ANOPR Comments at 2 (urging the Commission to “require sufficient transparency from
grid operators so it can determine which specific large load facilities are responsible for
grid upgrade needs”); see also CPUC November 21 ANOPR Comments at 16-17
PDF page 51
Docket No. EL26-67-000
- 51 -
Accordingly, we preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it does not require the provision of data on PJM’s website in a
single location, and in an easily accessible format that is searchable and allows users to
filter the data, that identifies the Network Upgrades that are needed to accommodate
requests for transmission service by Eligible Customers on behalf of large loads, and the
costs of those Network Upgrades. PJM should explain whether the Tariff remains just
and reasonable without provisions that would require PJM and the Transmission Owners
to publicly post and regularly update data that details: (1) the aggregate amounts of
proposed large load additions in PJM’s footprint, including the aggregate amounts in
each transmission pricing zone; (2) the planned Network Upgrades needed to provide
transmission service to Eligible Customers on behalf of large loads, identified by type of
equipment and Network Upgrade (e.g., new substation, reconductoring, a new
high-voltage transmission line) for each transmission service request; and (3) cost
estimates for those Network Upgrades; or propose such Tariff revisions. PJM and the
Transmission Owners should also consider what other data related to transmission costs
resulting from the provision of transmission service to Eligible Customers on behalf of
large loads would be useful to include on PJM’s website. To the extent there are
concerns about data confidentiality, PJM and the Transmission Owners should consider
whether there are ways to mitigate those concerns while still providing the necessary
transparency.
3.
Cost Recovery Agreements
We next preliminarily find that PJM’s Tariff appears to be unjust and
unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting
among transmission customers, which may result in unjust and unreasonable rates for
transmission service. In particular, we are concerned about the apparent lack of a
pro forma cost recovery agreement between PJM, the relevant transmission owner, and
the Eligible Customer taking transmission service on behalf of large loads that help
ensure that Eligible Customers bear the risk and are ultimately responsible for costs
incurred to provide transmission service, including the cost of Network Upgrades.
Several commenters discuss the risk of cost shifting among transmission
customers that could result from transmission service requests by Eligible Customers on
behalf of large loads.168 Commenters also argue that retail-level large load tariffs do not
(asserting that the public posting of large load cost responsibility determinations would
improve transparency, to the benefit of businesses and ratepayers).
168 See, e.g., Buckeye November 21 ANOPR Comments at 8-13; APPA
November 21 ANOPR Comments at 6 (“Wholesale transmission customers in particular
could be left shouldering massive costs if new large loads do not ultimately attain or
maintain the level of electricity demand that is being forecasted.”); NRECA
PDF page 52
Docket No. EL26-67-000
- 52 -
protect wholesale transmission customers from cost shifting.169 Specifically, commenters
in the record contend that, while a retail-level large load tariff protects the load serving
entity taking wholesale transmission service and its retail customers, it fails “to provide
any mechanism to protect other wholesale transmission customers” from stranded
transmission costs.170 The Kansas Commission states that while its Large Load Power
Services rate plan that requires large loads to make minimum payments toward
transmission costs protects retail ratepayers from large-load driven transmission costs, it
cannot protect against cost shifting associated with regional transmission buildout where
“the large loads that formed the basis for the [regional] transmission plans do not
materialize, leaving only existing customers to pay for generational expansions of the
transmission grid.”171 TAPS contends, moreover, that it is not sufficient for the
Commission to rely on transmission owners to voluntarily file cost recovery agreements
to protect transmission customers from cost shifting for Network Upgrades.172
We are likewise concerned that there may be speculative transmission service
requests by Eligible Customers on behalf of large loads that could result in cost shifting
among transmission customers, which may lead to unjust and unreasonable increases in
jurisdictional transmission rates. When a transmission owner constructs Network
Upgrades to accommodate an Eligible Customer’s request for transmission service on
behalf of a large load, those transmission costs will be included in the transmission
owner’s transmission revenue requirement. If, however, the Eligible Customer takes less
transmission service than anticipated because the large load operates at a lower demand
November 21 ANOPR Comments at 21 (noting the risk that other transmission customers
could bear stranded upgrade costs caused by large loads that they cannot absorb); TAPS
November 21 ANOPR Comments at 22-24; California DWR November 21 ANOPR
Comments at 8.
169 TAPS November 21 ANOPR Comments at 26 (“[A] number of state
commissions are moving forward with retail large load tariffs, which provide for varying
protections, but may not require the revenues and minimum demand levels to be included
in wholesale transmission rates.”); Buckeye November 21 ANOPR Comments at 14-16;
Kansas Commission November 21 ANOPR Comments at 15-16.
170 Buckeye November 21 ANOPR Comments at 14-15; see TAPS November 21
ANOPR Comments at 26-27 & nn.50-51.
171 Kansas Commission November 21 ANOPR Comments at 11-12.
172 TAPS November 21 ANOPR Comments at 25-26 (noting that AES Ohio
“committed to reflecting the payments it received from the data center in its
Commission-jurisdictional transmission revenue requirement so that other customers are
protected,” in a Construction Service Agreement with Amazon).
PDF page 53
Docket No. EL26-67-000
- 53 -
than anticipated or fails to materialize at all, other transmission customers may see an
increase in transmission rates. In such a situation, those other transmission customers
may have to pay for potentially unnecessary Network Upgrades that they neither caused
the need for nor benefit commensurately from. In other words, this introduces the risk
that costs may be unfairly shifted to other transmission customers, which may result in
those costs then being passed through to residential customers, among others.
PJM’s Tariff does not require cost recovery agreements between PJM, the relevant
transmission owner, and the Eligible Customer taking transmission service on behalf of a
large load. Such agreements would help ensure that the Eligible Customer makes a
minimum contribution to the transmission owner’s transmission revenue requirement
commensurate with the costs incurred to provide the requested transmission service,
including the costs of any needed Network Upgrades. Absent such cost recovery
agreements, we are concerned that there is no mechanism to help ensure that Eligible
Customers taking transmission service on behalf of large loads (as opposed to other
transmission customers) bear the risk of, and are ultimately responsible for, the costs
incurred to provide them with the requested transmission service, including the costs of
any needed Network Upgrades.
Accordingly, we preliminarily find that, in order to prevent unjust and
unreasonable cost shifting among transmission customers, it appears necessary for PJM,
the relevant transmission owner, and the Eligible Customer taking transmission service
on behalf of a large load to enter into a cost recovery agreement that requires the Eligible
Customer to make a minimum contribution toward the transmission owner’s transmission
revenue requirement, if the Eligible Customer ultimately takes less transmission service
than anticipated because the large load does not materialize as planned or is not
developed at all. We preliminarily find that such cost recovery agreements are necessary
to help ensure that the Eligible Customer is responsible for timely paying the costs of
large load-driven transmission (i.e., the costs incurred to provide them with the requested
transmission service, including the costs of any needed Network Upgrades), rather than
having those costs paid by other transmission customers that neither caused the need for
nor benefit commensurately from those Network Upgrades.173 Our preliminary finding is
not intended to alter or call into question existing regional cost allocation methods for
Network Upgrades, but instead is focused on helping to prevent cost shifting among
transmission customers.
We note that several transmission owners and large load customers have filed cost
recovery agreements (Transmission Security Agreements or Construction Service
Agreements) with the Commission that guarantee minimum contributions from a large
173 See, e.g., Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368
(D.C. Cir. 2004); Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009).
PDF page 54
Docket No. EL26-67-000
- 54 -
load customer (rather than from the Eligible Customer taking transmission service on
behalf of the large load customer) to the transmission owner’s transmission revenue
requirement.174 Although we decline to preliminarily find that cost recovery agreements
between the transmission owner and the large load customer (rather than the Eligible
Customer) are necessary to ensure just and reasonable transmission rates, we continue to
find that such agreements directly affect Commission-jurisdictional transmission rates.
Therefore, to the extent a transmission owner and a large load customer enter into a cost
recovery agreement (whether voluntarily or pursuant to state law) through which the
large load customer guarantees contributions to the transmission owner’s
Commission-jurisdictional transmission revenue requirement, we find that such an
agreement should be filed with the Commission.175 To reduce duplicative credit
requirements and transaction costs, we direct further briefing on whether it would be
appropriate for such an agreement to substitute for the requirement on the Eligible
Customer to enter into a cost recovery agreement with the transmission owner, if the
agreement with the large load customer provided comparable or greater protection
against cost shifting among transmission customers than an agreement between the
transmission owner and the Eligible Customer would.
In addition to our preliminary finding that PJM’s Tariff is unjust and unreasonable
because it lacks a pro forma cost recovery agreement of this type, we also preliminarily
find that the minimum contribution required pursuant to such an agreement should be
based on the level of jurisdictional transmission service (in MW) requested by the
Eligible Customer on behalf of the large load. That figure is in turn tied to how PJM
and/or Transmission Owners will study the requested transmission service and determine
any necessary Network Upgrades that must be developed to provide the requested
transmission service. We note, however, that there may be other just and reasonable
methods for determining this minimum contribution, including methods that account for
potential timing differences between when costs are incurred to develop needed Network
Upgrades and the pace at which the large load ramps toward energizing at its full level of
requested service. We further preliminarily find that the cost recovery agreement should
include a credit support (or other financial security) requirement sufficient to secure the
obligations of the Eligible Customer taking transmission service on behalf of a large load
to pay the amounts owed pursuant to the cost recovery agreement. We find that a cost
recovery agreement with a specified minimum financial contribution and financial
security sufficient to secure such contribution is necessary to mitigate cost shifting if the
174 See supra note 159.
175 We emphasize that this finding is in no way intended to preempt or interfere
with the ability of states to implement ratepayer protection measures designed to mitigate
cost shifting among retail customers, such as through state-jurisdictional large load
tariffs.
PDF page 55
Docket No. EL26-67-000
- 55 -
Eligible Customer ultimately takes less transmission service than anticipated because the
large load does not materialize as planned or is not developed at all. We preliminarily
find that an Eligible Customer may include a credit support or other financial security
posted by a large load as part of a retail agreement to avoid creating duplicative credit
support requirements. PJM should explain why such a pro forma cost recovery
agreement is not necessary to ensure just and reasonable rates, or propose such a
pro forma cost recovery agreement. To the extent that stakeholders believe that other
mechanisms could address our cost shifting concerns, we seek further briefing as
discussed below.176
Lastly, we expect that any payments made by an Eligible Customer to a
transmission owner pursuant to such a cost recovery agreement (or by a large load to a
transmission owner pursuant to other voluntary agreement) will be appropriately credited
toward transmission owners’ transmission revenue requirements consistent with the
Commission’s cost-of-service regulations.177 We preliminarily find that it appears
reasonable for filers of formula rates to provide a separate workpaper in the annual
informational filing describing how any payments made pursuant to a cost recovery
agreement are reflected in the transmission owner’s transmission formula rate.
C.
Extending New Transmission Services to Eligible Customers Taking
Service on Behalf of Flexible Large Loads
In response to the ANOPR, a number of commenters argue that certain large loads
are able to limit their withdrawals from the transmission system under certain conditions.
Namely, commenters observe that flexible large loads178 can quickly and verifiably adjust
their consumption in response to system conditions or price signals.179 Commenters in
the ANOPR also observe that, where load studies and system planning consider the
flexible nature of large loads, flexible large loads can potentially defer or reduce the need
176 See infra P 107.
177 See 18 C.F.R. pt. 101 (2025).
178 For purposes of this order, “flexible” large loads are a subset of large loads, as
used in this order, that are not co-located with generation, but are willing and able to limit
their energy withdrawals from the transmission system under certain conditions.
179 See, e.g., AEMA November 21 ANOPR Comments at 1-2; Land Trust Alliance
November 21 ANOPR Comments at 10; California DWR November 21 ANOPR
Comments at 5; CEBA November 21 ANOPR Comments at 14-15; ClearPath
November 21 ANOPR Comments at 2-4; Digital Energy Council November 21 ANOPR
Comments at 1; EDF Power November 21 ANOPR Comments at 4; Emerald
November 21 ANOPR Comments at 2; Verrus November 21 ANOPR Comments at 4.
PDF page 56
Docket No. EL26-67-000
- 56 -
for Network Upgrades, among other potential benefits.180 In recognition of this
flexibility, many commenters support new transmission services that reflect the
operational capabilities of flexible large loads, including interim NITS while Network
Upgrades are constructed, and non-firm transmission service.181
We preliminarily find that PJM’s Tariff appears to be unjust and unreasonable
because it does not include transmission services that reflect Eligible Customers taking
transmission service on behalf of flexible large loads that are willing and able to limit
their use of the transmission system under certain conditions. The transmission services
available to Eligible Customers, including on behalf of flexible large loads, in PJM are
NITS and firm and non-firm Point-to-Point Transmission Service.182 While these remain
just and reasonable options for an Eligible Customer to take on behalf of a flexible large
load, based on the record before us, we preliminarily find that new transmission services
should be available to reflect the operational reality that large loads may use the
transmission system to differing extents and certain large loads are willing and able to
limit their use of the transmission system under certain conditions.183 The Commission
found that Eligible Customers taking transmission service on behalf of Eligible Load
should be allowed to choose a transmission service that aligns with their use of the
transmission system and therefore aligns the charges for service with the benefits
received.184 As the record suggests, Eligible Customers taking transmission service on
behalf of flexible large load also may be willing and able to limit their use of the
transmission system under certain conditions. As recognized in the ANOPR record, load
180 See, e.g., AEMA November 21 ANOPR Comments at 5; ELCON
November 21 ANOPR Comments at 9; Emerald November 21 ANOPR Comments
at 6-7; Institute for Progress November 21 ANOPR Comments at 11; Land Trust Alliance
November 21 ANOPR Comments at 10; LS Power November 21 ANOPR Comments
at 5; Microsoft November 21 ANOPR Comments at 10-11; National Grid November 21
ANOPR Comments at 19-20; OMS November 21 ANOPR Comments at 13-14;
Southeast PIOs November 21 ANOPR Comments at 50.
181 See, e.g., Constellation November 21 ANOPR Comments at 24-25; Calibrant
November 21 ANOPR Comments at 2-4; Critical Loop November 21 ANOPR
Comments at 2; Digital Power Network November 21 ANOPR Comments at 3; PIOs
November 21 ANOPR Comments at 27-28; Splight November 21 ANOPR Comments
at 3-4.
182 See supra P 19 (describing existing transmission services in PJM).
183 See supra P 85.
184 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 199; PJM Co-Location
Rehearing Order, 195 FERC ¶ 61,209 at P 103.
PDF page 57
Docket No. EL26-67-000
- 57 -
flexibility can avoid inefficient and costly transmission system build-out.185 In addition,
transmission services that reflect that flexible large loads are willing and able to limit
their withdrawals from the transmission system under certain conditions could help
timely interconnect flexible large loads.186 Entities in the PJM footprint acknowledge the
importance of facilitating load flexibility.187
Therefore, we are concerned that PJM’s Tariff does not include transmission
services that reflect the use of the transmission system by Eligible Customers on behalf of
flexible large load, on both an interim and permanent basis. PJM should explain whether
the Tariff remains just and reasonable without the transmission services described by the
Commission in the PJM Co-Location Order being available to Eligible Customers taking
transmission service on behalf of flexible large loads, or propose appropriate Tariff
revisions. Specifically, PJM should explain whether the Tariff remains just and
reasonable without (1) an interim non-firm network transmission service while Network
Upgrades are being constructed (i.e., interim NITS) and (2) permanent firm and non-firm
contract demand transmission services (transmission service up to a specified MW
quantity, i.e., the contract level, on a firm or non-firm basis).188 Finally, we note that the
Commission has found it just and reasonable that, in order for an Eligible Customer to
185 See supra P 85; see also PJM Co-Location Order, 193 FERC ¶ 61,217
at PP 160, 177, 199 (finding that new transmission service options reflect a co-located
load’s ability to limit withdrawals from the transmission system and potentially avoid
costly and inefficient transmission system buildout that may not be necessary).
186 See supra P 85; see also PJM Co-Location Order, 193 FERC ¶ 61,217
at PP 201 (finding that the interim, non-firm transmission service will facilitate the
“timely” provision of transmission service and that “[t]his willingness to curtail would
potentially allow them to obtain service more quickly”), 205 (recognizing that parties
argue that co-located loads may be able to receive transmission service faster with use of
a new, limited transmission service product than they would if they selected NITS, to the
extent that providing NITS would require Network Upgrades that the limited
transmission service would not).
187 See, e.g., Constellation November 21 ANOPR Comments at 23-24; Load
Flexibility Parties November 21 ANOPR Comments at 2-5; State Entities November 21
ANOPR Comments at 4.
188 In an order also issued today, the Commission established as just and
reasonable certain rates, terms, and conditions for the new transmission services directed
in the PJM Co-Location Order, which include portions of PJM’s and the Transmission
Owners’ proposals submitted in the briefs, and directed further compliance filings. See
generally PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209.
PDF page 58
Docket No. EL26-67-000
- 58 -
take interim NITS, firm contract demand transmission service, and non-firm contract
demand transmission service, an Eligible Customer must have necessary control
technologies and/or protection systems, which may include a special protection scheme,
to limit its energy withdrawals to its approved level.189
D.
Interconnection Customers Serving Electrically Proximate Large Load
and Co-Located Load
In response to the ANOPR, a number of commenters agree that the ability to study
new load and new generation together, when physically or electrically proximate,
presents system benefits and can help address the challenges posed by large load
additions.190 Commenters argue that studies that consider large load and generation
together present a more complete picture of the grid and can enable the identification of
more accurate, efficient, and cost-effective transmission solutions by minimizing system
impacts.191 As a result, this can speed up the interconnection process for both large loads
and generation, and shorten energization timelines,192 which commenters contend
reduces uncertainty for both parties193 and “is necessary to match the pace of AI
innovation in the United States.”194 CEBA also highlights that cost and timeline factors
drive developers to submit multiple requests for price and timing discovery, which
189 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 480.
190 See e.g., DCC November 21 ANOPR Comments at 5-6; DTE November 21
ANOPR Comments at 11; Google November 21 ANOPR Comments at 7; International
Energy Credit Association November 21 ANOPR Comments at 10; Terraflux
November 21 ANOPR Comments at 1.
191 AEU November 21 ANOPR Comments at 13; ClearPath November 21
ANOPR Comments at 4; DCC November 21 ANOPR Comments at 5; DTE
November 21 ANOPR Comments at 8-11; ENGIE November 21 ANOPR Comments
at 6; Entergy November 21 ANOPR Comments at 5; Geronimo November 21 ANOPR
Comments at 17-18; Information Technology Industry Council November 21 ANOPR
Comments at 2.
192 DCC November 21 ANOPR Comments at 5; DTE November 21 ANOPR
Comments at 8-11; Information Technology Industry Council November 21 ANOPR
Comments at 2; Microsoft November 21 ANOPR Comments at 8-9; Verrus December 5
ANOPR Comments at 9.
193 ClearPath November 21 ANOPR Comments at 4; CEBA November 21
ANOPR Comments at 8.
194 Microsoft November 21 ANOPR Comments at 8-9.
PDF page 59
Docket No. EL26-67-000
- 59 -
inflates queue volumes, distorts demand and supply forecasts, and causes significant
delays when projects withdraw late after finding costs or energization timelines
uneconomic.195 Other benefits to a joint study identified by commenters include
improving load forecasting and siting decisions196 and reducing the need for critical
supply chain components.197
Commenters contend that current generator interconnection study processes may
not adequately capture generation and load, including by failing to model known
electrically proximate large load in base case assumptions, which may result in inaccurate
studies and inefficient system build-out.198 For example, Eolian states that in its
experience developing a project in PJM, the failure of the generator interconnection study
process to reflect reasonably expected load conditions on the grid models triggered overly
costly Network Upgrades and caused the cancellation of generation project that could
have reliably served adjacent load growth.199
Commenters in the ANOPR proceeding argue that the current state of the
generator interconnection queue is not meeting the expeditious time frame needed to
match the pace of large load additions and ensure the safe and reliable interconnection of
these loads.200 For example, Oracle states that one of the most significant and
widespread delays it encounters when siting data centers in the U.S. is access to sufficient
energy.201 Similarly, Helion contends that more than half of U.S. developers now
identify interconnection delays as the single biggest barrier to adding new generation
195 CEBA November 21 ANOPR Comments at 8.
196 ELCON November 21 ANOPR Comments at 5; Maryland Commission
November 21 ANOPR Comments at 6-7.
197 AEU November 21 ANOPR Comments at 13.
198 Base Power November 21 ANOPR Comments at 7; Eolian November 21
ANOPR Comments at 18-19; Eolian May 19 ANOPR Comments at 2; Longroad
November 21 ANOPR Comments at 8.
199 Eolian May 19 ANOPR Comments at 10.
200 See, e.g., AEP December 5 ANOPR Comments at 1; DCC November 21
ANOPR Comments at 8; esVolta November 21 ANOPR Comments at 11-12; Oracle
May 1 ANOPR Comments at 4.
201 Oracle November 21 ANOPR Comments at 1.
PDF page 60
Docket No. EL26-67-000
- 60 -
capacity.202 Commenters contend that if large load interconnection proceeds more
quickly than new generation can come online, the result could be price increases for
consumers.203
A number of commenters support expedited interconnection studies for new
generation paired with load.204 Some commenters argue that one solution to generator
interconnection delays may be the creation of time-limited or conditional interconnection
service for generators serving large loads, which could require less time for initial
generator interconnection studies and improve speed to power.205 For example, several
commenters express support for SPP’s HILLGA proposal as a model and urge the
Commission to establish nationwide rules similar to that approach.206 Other commenters
suggest reforms to expedite studies for new generation paired with large loads at existing
points of interconnection that have already been studied, arguing it is unjust and
unreasonable not to fully utilize existing infrastructure and proven reliability paths while
new load waits for service.207
1.
Jurisdiction
The Commission’s statutory authority includes jurisdiction over the wholesale sale
and transmission of electricity in interstate commerce, including the facilities used for
202 Helion November 21 ANOPR Comments at 1 (citing Third Way, Picking Up
the PACE: A Comprehensive Analysis of Available Pathways to Accelerating Clean
Energy (PACE) (Nov. 2025)).
203 AEP December 5 ANOPR Comments at 1-2; OPSI November 21 ANOPR
Comments at 6-7, 11.
204 See, e.g., DTE November 21 ANOPR Comments at 8; ENGIE November 21
ANOPR Comments at 4; International Energy Credit Association November 21 ANOPR
Comments at 8; Meta November 21 ANOPR Comments at 5-6; Ohio FEA November 21
ANOPR Comments at 5.
205 AEP December 5 ANOPR Comments at 12; AEU November 21 ANOPR
Comments at 13; Google December 5 ANOPR Comments at 15; see also Duke
November 21 ANOPR Comments at 21-22.
206 AEP December 5 ANOPR Comments at 4; Crusoe December 5 ANOPR
Comments at 7; Enchanted Rock November 21 ANOPR Comments at 4; Google
November 21 ANOPR Comments at 7; GridStor November 21 ANOPR Comments at 5;
Verrus November 21 ANOPR Comments at 9.
207 Constellation June 5 ANOPR Comments at 8-9.
PDF page 61
Docket No. EL26-67-000
- 61 -
such sale and transmission.208 The Commission also has exclusive jurisdiction to
regulate the procedures and agreements applicable to generating facilities seeking to
interconnect to a Commission-jurisdictional distribution facility or transmission
facility.209 In the PJM Co-Location Order, the Commission observed that a generator’s
interconnection to the interstate transmission system “does not fall outside of the
Commission’s jurisdiction merely because there is [c]o-[l]ocated [l]oad behind the
generator’s point of interconnection.”210 By the same token, the Commission retains
jurisdiction over a generator’s interconnection even where the generator plans to serve an
electrically proximate large load.
We recognize that states have exclusive authority over resource planning and the
generation mix within their boundaries.211 Nothing about our preliminary finding here,
however, intrudes or is intended to intrude on that exclusive authority. Rather, we
preliminarily find that it is necessary and appropriate to exercise our exclusive
jurisdiction over generator interconnection to ensure the availability of generator
interconnection processes specifically tailored to the unique operational characteristics of
generating facilities dedicated to serving electrically proximate large loads and co-located
loads, as defined below. The Commission has exercised this jurisdiction previously in
requiring generator interconnection services that allow certain generating facilities to
interconnect more quickly through the use of provisional interconnection service and
surplus interconnection service,212 and has approved interconnection processes that allow
208 16 U.S.C. § 824(b)(1).
209 Id.; Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d at 1280-82
(affirming Order No. 2003 and observing that “interconnections appear to be
relationships between parties with respect to electricity flowing over facilities. . . By
establishing standard agreements [the Commission] has exercised its jurisdiction over
the terms of those relationships.”); see Pac. Gas & Elec. Co., 115 FERC ¶ 61,193 at P 36
(“[I]interconnection is part and parcel of transmission of electric energy in interstate
commerce, and thus interconnection service is part and parcel of jurisdictional
transmission service.”).
210 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 171.
211 See, e.g., Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th at 238 (citing
16 U.S.C. § 824(b)(1)).
212 Reform of Generator Interconnection Procs. & Agreements, Order No. 845,
163 FERC ¶ 61,043, at PP 438, 467 (2018), order on reh’g & clarification, Order
No. 845-A, 166 FERC ¶ 61,137, order on reh’g & clarification, Order No. 845-B,
168 FERC ¶ 61,092 (2019); Order No. 2023, 184 FERC ¶ 61,054 at P 1436; PJM
Interconnection, L.L.C., 190 FERC ¶ 61,083 (2025).
PDF page 62
Docket No. EL26-67-000
- 62 -
certain generating facilities to interconnect more quickly by replacing a retiring existing
generating facility.213
2.
Definitions
For purposes of this order, it appears to be reasonable to use the term “electrically
proximate large load” to mean a large load, as defined in this order,214 that is sufficiently
electrically close to the interconnection customer’s requested point of interconnection,
such that the impact on the transmission system of the combination of the generating
facility and the load, with the exception of the transmission facilities between the two,
will be effectively the same as if they were located at the same substation (e.g., large load
that is located no more than two substations away from the generating facility). We will
consider proposed revisions to this definition that ensure it is appropriately tailored to
PJM’s transmission system.
3.
Tariff Provisions
We preliminarily find that PJM’s Tariff appears to be unjust and unreasonable
because it does not contain provisions allowing an interconnection customer to seek the
generator interconnection service(s) that reflects the operational dynamics of serving
either: (1) an electrically proximate large load; or (2) a co-located load, as defined in the
PJM Co-Location Order,215 that has a high peak load (i.e., large co-located loads that are
50 MW or greater).216 Specifically, we preliminarily find that PJM’s Tariff appears to be
unjust and unreasonable because it lacks a generator interconnection study process and/or
generator interconnection service to reflect an interconnection customer’s commitment in
an interconnection agreement to limit the generating facility’s output to minimize the
impact on the transmission system while serving an electrically proximate large load or
large co-located load. We are concerned that PJM’s Tariff lacks, for example, generator
interconnection study procedures and generator interconnection services that reflect (a)
an interconnection customer’s commitment in an interconnection agreement to limit a
generating facility’s output to match the hourly forecast of an electrically proximate large
load or large co-located load; and/or (b) a generating facility with necessary control
technologies and/or protection systems, which may include a special protection
213 See, e.g., PJM Interconnection, L.L.C., 194 FERC ¶ 61,079 (2026);
Midcontinent Indep. Sys. Operator Inc., 167 FERC ¶ 61,146 (2019).
214 See supra P 58.
215 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 164.
216 We note that generator interconnection service in and of itself does not convey
transmission service.
PDF page 63
Docket No. EL26-67-000
- 63 -
scheme,217 that ensure that the injection does not exceed the limit in the existing or new
interconnection agreement. Where a generating facility’s output is matched to the
demand of the electrically proximate large load or large co-located load or if the
generating facility’s output is limited to ensure no new injection, the impacts to the
transmission system of interconnecting the generating facility to serve that electrically
proximate large load or large co-located load may be limited,218 thereby potentially
reducing the need for Network Upgrades, which can accelerate the generator
interconnection process.219 In the absence of Tariff provisions accounting for these
operational dynamics when an interconnection customer’s generating facility is serving
electrically proximate large loads or large co-located loads, new shovel-ready generating
facilities may face unnecessary delays in reaching commercial operation under current
generator interconnection processes and will be unable to serve the immediate demand of
new large loads or large co-located loads.220
217 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 480.
218 In other words, because the generating facility and load are located so closely
on the transmission system, if the generating facility’s output matches the load’s demand,
then the transmission provider would need to study only the local impacts because the
impact on the transmission system of the combination of the generating facility and the
load, with the exception of the transmission facilities between the two, will be effectively
the same as if they were located at the same substation.
219 See, e.g., AEU November 21 ANOPR Comments at 13 (“To the extent that a
new large load and new generation or storage resource are geographically and electrically
proximate, studying them together would reduce network upgrades, lower costs, and
reduce the need for critical supply chain components.”); DTE November 21 ANOPR
Comments at 10 (integrating the study of load and its supporting generation “reduces the
need for network upgrades, optimizes the use of existing infrastructure, and accelerates
the timeline for bringing both load and generation online”); Eolian November 21 ANOPR
Comments at 18 (“It is obvious from basic engineering principles that generation located
near load requires less transmission infrastructure to serve that load than generation
located distant from load.”); GridStor November 21 ANOPR Comments at 5 (“Siting a
large load near or at the same point of interconnection as a new generating facility could
reduce the network upgrades needed to interconnect only the load or only the generating
facility.”).
220 See AEP December 5 ANOPR Comments at 1; Base Power November 21
ANOPR Comments at 7; CEBA November 21 ANOPR Comments at 8; DCC
November 21 ANOPR Comments at 6 (asserting that a clear framework to study large
loads paired with generation would resolve development bottlenecks); Eolian
November 21 ANOPR Comments at 18-19; Eolian May 19 ANOPR Comments at 2;
PDF page 64
Docket No. EL26-67-000
- 64 -
As commenters in the ANOPR proceeding have recognized, the status quo may
result in inefficient and unnecessary development of infrastructure, which leads to
unnecessarily higher Network Upgrade costs that may result in unjust and unreasonable
rates.221 The Commission has already determined in the PJM Co-Location Order that
without the new transmission services that reflect the operational dynamics of co-location
arrangements, there could be unnecessary, costly, and inefficient Network Upgrades,
increasing Network Upgrade costs.222 The same result may occur in the absence of new
generator interconnection study procedures and generator interconnection services
tailored to a new generating facility coming online for the express purpose of serving an
electrically proximate large load or large co-located load.223
SPP recognized this problem and submitted an FPA section 205 filing to
implement a new, interim, generator interconnection service and related generator
interconnection process, HILLGA, to facilitate the prompt interconnection of generating
facilities that are specifically identified for and limited to serving a HILL, which the
Commission accepted.224 The Commission found that HILLGA “reasonably provides a
flexible, expedited, and separate serial interconnection process that will facilitate the
prompt interconnection of generating facilities that are limited to serving a HILL in the
Google November 21 ANOPR Comments at 7 (calling for nationwide rules enabling
proximate load-generation interconnection to “accelerate the pace at which new
generation comes online”); Longroad November 21 ANOPR Comments at 8.
221 See, e.g., AEU November 21 ANOPR Comments at 13, AEP December 5
ANOPR Comments at 1-2; Longroad November 21 ANOPR Comments at 8; OPSI
November 21 ANOPR Comments at 11.
222 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 177 (“[F]or Eligible
Customers taking service on behalf of Co-Located Loads that do not reserve
transmission . . . requiring such Eligible Customers to take NITS on behalf of these
Co-Located Loads may in some circumstances result in costly and inefficient
transmission system buildout that may not be necessary if such Eligible Customers are
willing and able to take a transmission service that requires fewer Network Upgrades to
provide, and therefore may result in lower Network Upgrade costs, than would NITS.”).
223 See AEP December 5 ANOPR Comments at 1-2 (stating that current processes
produce insufficient/inefficient infrastructure and “potentially unsustainable price
increases”); Eolian May 19 ANOPR Comments at 2, 10 (contending that a lack of
coordinated study leads to unjust and unreasonable outcomes).
224 SPP HILL Order, 194 FERC ¶ 61,031.
PDF page 65
Docket No. EL26-67-000
- 65 -
same local area.”225 We do not expect or propose that PJM adopt an identical process to
SPP’s HILLGA process, nor do we preliminarily find that the absence of Tariff
provisions specifically mirroring SPP’s Tariff renders PJM’s Tariff unjust and
unreasonable. Nevertheless, we remain concerned that the Tariff may be unjust and
unreasonable without any uniquely tailored interconnection study process and/or
generator interconnection service to recognize the reduced transmission system impacts
that may result from the interconnection of a generating facility where the
interconnection customer has committed, in an interconnection agreement, to limit the
generating facility’s output to match the hourly forecast of an electrically proximate large
load or large co-located load.226 To the extent that the interconnection customer’s
generating facility is serving an electrically proximate large load, we believe that the
generator interconnection service should be of an interim nature until the interconnection
customer obtains Energy Resource Interconnection Service (ERIS) or Network Resource
Interconnection Service (NRIS). To the extent that the interconnection customer’s
generating facility is serving a large co-located load, it may be reasonable for the
generator interconnection service to be permanent because there will be no injections
onto the transmission system and therefore it does not present operational or planning
risks for reliability.
Another potentially reasonable approach to address our concerns could be to
develop a generator interconnection study process that would allow the use of existing
ERIS or NRIS of an existing generator to connect a new generating facility and a new
large load behind the same point of interconnection of the existing generator with
necessary control technologies and/or protection systems, which may include a special
protection scheme, that ensure that the net injection does not exceed the amount in the
existing generator interconnection agreement.227 Such an approach could expedite the
interconnection study process for a generator planning to serve an electrically proximate
225 Id. P 64.
226 While, as discussed above, we view such a process that permits generation to
serve electrically proximate loads no more than two substations away from the generators
to be reasonable, we understand the unique features of PJM’s transmission system may
warrant consideration of a more limited definition of electrically proximate. See Duke
November 21 ANOPR Comments at 21-22; DTE November 21 ANOPR Comments
at 8-11 (asserting that studying large loads with electrically proximate generation
streamlines interconnection and reduces upgrades); AEU November 21 ANOPR
Comments at 13-15.
227 See Constellation June 5 ANOPR Comments at 1-2, 10-13.
PDF page 66
Docket No. EL26-67-000
- 66 -
(in this case at the same point of interconnection) large load.228 An additional potentially
reasonable approach could be a new load-limited generator interconnection service that
allows a new generating facility and new large co-located load seeking to interconnect
behind the same new point of interconnection, with necessary control technologies and/or
protection systems, which may include a special protection scheme, to ensure that there is
no injection to the transmission system.229 It may be reasonable for such a load-limited
generator interconnection service to be or not to be of an interim nature. We invite PJM
and/or Transmission Owners, in responding to this order or in an FPA section 205 filing,
to submit original proposals designed to address the concerns expressed herein and
tailored to their unique circumstances.
We are concerned that the absence of generator interconnection study procedures
and generator interconnection services facilitating the interconnection of a new
generating facility that is being brought onto the transmission system in order to serve an
electrically proximate large load or large co-located load will result in PJM’s current
generator interconnection process failing to keep pace with the new large loads seeking to
be integrated onto PJM’s transmission system.230 We preliminarily find that this
outcome may be unjust and unreasonable because reliance on PJM’s current generator
interconnection processes for generating facilities serving electrically proximate large
loads or large co-located loads could result in unnecessary interconnection delays,
unnecessary Network Upgrades, and an otherwise inefficient expansion of the
transmission system, imposing unnecessary delays and costs on transmission customers.
PJM should explain whether the Tariff remains just and reasonable without, for
example, provisions that establish: (1) a new generator interconnection study process and
new interim generator interconnection service that reflect an interconnection customer’s
228 See id. at 5 (explaining that when new generation load pairings “are sited at an
existing generator’s Point of Interconnection and fall within the same study parameters
reflected by that existing generator’s interconnection, they benefit from studies and
upgrades already completed for that existing generator and can come on more rapidly
without jeopardizing reliability”).
229 See MISO November 21 ANOPR Comments at 13; see also MISO TOs April 3
ANOPR Comments at 13-14.
230 See Helion November 21 ANOPR Comments at 1 (noting interconnection
delays are the biggest barrier to adding new generation); Oracle November 21 ANOPR
Comments at 1 (noting significant delays in access to sufficient energy for data centers);
OPSI November 21 ANOPR Comments at 11 (explaining that expedited study
encourages loads to bring their own generation); Enchanted Rock November 21 ANOPR
Comments at 4; Microsoft November 21 ANOPR Comments at 8-9.
PDF page 67
Docket No. EL26-67-000
- 67 -
commitment, in a generator interconnection agreement, to limit a generating facility’s
output to match the hourly forecast of an electrically proximate large load or large
co-located load; or (2) a generator interconnection study process that allows the use of the
existing ERIS or NRIS of an existing generator to connect a new generating facility and a
new large load behind the same point of interconnection of the existing generator with
necessary control technologies and/or protection systems, which may include a special
protection scheme, that ensures that the net injection does not exceed the amount in the
existing generator interconnection agreement; or (3) a new generator interconnection
service that allows a new generating facility and new large co-located load seeking to
interconnect behind the same new point of interconnection with necessary control
technologies and/or protection systems, which may include a special protection scheme,
to ensure that there is no injection to the transmission system. We note that, with respect
to numbers (2) or (3), these approaches could be either interim or permanent. These
approaches may not be mutually exclusive.
Given that generator interconnection service in and of itself does not convey
transmission service, we encourage PJM to consider, in responding to these concerns,
what type of transmission service an Eligible Customer will need to take on behalf of the
electrically proximate large load or large co-located load.231 We note that, in the PJM
Co-Location Order, the Commission found that the Eligible Customer must take
transmission service on behalf of co-located load that will not withdraw energy from the
transmission system, even if it is 0 MW.232
E.
Informational Report
The rapid addition and proliferation of large loads without commensurate
additions of supply or demand-side resources presents resource adequacy concerns. As
discussed above and highlighted in the ANOPR, the growth of demand, and the speed of
such growth, is driven in large part by the interconnection of large loads. While not
expressly contemplated in the ANOPR, commenters highlight the strain rapid demand
growth is putting on resource adequacy in many regions.233 Indeed, the relative speed
and concentration at which large loads are seeking to interconnect appears to be
outpacing the addition of new generation, which in turn heightens reliability risks and
231 See SPP HILL Order, 194 FERC ¶ 61,031 at P 34.
232 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 206.
233 See, e.g., Entergy November 21 ANOPR Comments at 29-30; Eolian
November 21 ANOPR Comments at 16-17; Industrial Customers November 21 ANOPR
Comments at 24-26; R Street November 21 ANOPR Comments at 1; South Dakota
Commission November 13 ANOPR Comments at 5; Talen December 5 ANOPR
Comments at 7.
PDF page 68
Docket No. EL26-67-000
- 68 -
drives up costs to ratepayers.234 We are concerned that PJM and load serving entities are
unable to plan adequate generation to serve all load at the pace such load seeks to
connect.
We recognize that RTOs/ISOs are engaging in efforts to more rapidly interconnect
generation that is needed to serve this unprecedented growth in load. In particular, PJM’s
Reliability Resource Initiative and Expedited Interconnection Track have provided
pathways for expedited interconnection for generation.235 Further, as detailed above and
in informational reports submitted by PJM,236 PJM has ongoing stakeholder processes to
address resource adequacy issues related to large load additions, including a voluntary
“Bring Your Own New Generation” pathway for large loads, a “connect-and-manage”
framework applicable to new large loads that do not bring commensurate new generating
capacity, and a reliability backstop procurement.237 While we are encouraged by the
implementation of such processes to ensure resource adequacy and faster interconnection
and ongoing stakeholder discussions, we remain concerned that these efforts may fall
short in light of generator retirements and tightening supply conditions.
Accordingly, we direct PJM to submit in Docket No. EL26-67-000, within 30 days
of the date of issuance of this order, a detailed informational report on the current status
of proposals under consideration in its stakeholder process to address the issue of
resource adequacy to serve new large loads. We also strongly encourage new proposals
to the extent necessary to address these concerns. The informational report must include
a detailed schedule of key milestones, such as stakeholder or PJM Board votes, that
includes the estimated date on which PJM expects to file any such proposals with the
Commission. Additionally, as part of this informational report, we direct PJM to identify
any problem statements, issue charges, or other ongoing stakeholder processes that aim to
increase the pace of adding generating capacity in the PJM region. The informational
234 See, e.g., Eolian November 21 ANOPR Comments at 16-17; David Gardiner &
Associates November 21 ANOPR Comments at 1-2; Joint Consumer Advocates
December 5 ANOPR Comments at 2; PSEG November 21 ANOPR Comments at 8;
Southern California Edison December 5 ANOPR Comments at 3.
235 PJM Interconnection, L.L.C., 190 FERC ¶ 61,084; order on reh’g, 192 FERC
¶ 61,085 (2025); PJM EIT Order, 195 FERC ¶ 61,197.
236 PJM Interconnection, L.L.C., Informational Report, Docket No. EL25-49-000,
et al. (filed Jan. 20, 2026); PJM Interconnection, L.L.C., Supplemental Informational
Report, Docket No. EL25-49-000, et al. (filed Feb. 23, 2026); PJM Interconnection,
L.L.C., Second Supplemental Informational Report, Docket No. EL25-49-000, et al.
(filed Mar. 9, 2026).
237 See supra P 33.
PDF page 69
Docket No. EL26-67-000
- 69 -
report must include a detailed schedule of such initiatives, including timing of the
stakeholder process and dates of any anticipated filings with the Commission.
IV.
Briefing Questions
We note that large loads, including data centers, are actively working with
transmission owners and other relevant entities to interconnect to, and to take
interconnection and/or transmission service from, the transmission system and may be at
varying stages of that process. We appreciate that different large loads are currently at
different stages of that process. We also understand that large loads and Eligible
Customers taking transmission service on behalf of large loads are negotiating, entering
into, and/or have executed various agreements related to interconnecting to the
transmission system and/or the provision of transmission service. We direct further
briefing regarding how PJM and the Transmission Owners, in responding to the order to
show cause, should protect existing commercial arrangements including: (1) what would
be a reasonable implementation period to ensure minimal disruption to such existing
commercial arrangements, and (2) how to allow a reasonable amount of time to finalize
ongoing agreements that are nearing completion as of the date such Tariff provisions are
filed with the Commission.
Today’s order proposes, as part of a potential replacement rate, to establish new
transmission services that recognize flexible large loads’ ability and willingness to limit
their use of the transmission system under certain conditions. As we assess this proposal,
we also consider how these new transmission services might affect other parts of PJM’s
Tariff and/or processes. Specifically, what, if any, potential impacts on regional and
local transmission planning would arise from the introduction of the new transmission
services discussed herein? For example, when planning for load growth, how would
transmission providers and planners account for flexible large loads’ potential preference
to take the new transmission services, including potential uncertainties around the type,
location, and quantity of such expected loads?
Today’s order preliminarily finds that PJM’s Tariff appears to be unjust and
unreasonable without the inclusion of cost shifting protections. We find that there may
be a variety of possible approaches to protect customers from significant cost shifts
associated with Network Upgrades triggered by large loads. To that end, we direct
respondents to include information regarding potential structures for agreements between
the transmission owner/provider and an Eligible Customer to prevent unjust and
unreasonable cost shifts among transmission customers related to Network Upgrade costs
required for large loads. Further, please include information on what an appropriate
minimum level of cost recovery and financial security from an Eligible Customer would
be under any such agreements.
PDF page 70
Docket No. EL26-67-000
- 70 -
Today’s order preliminarily finds that PJM’s Tariff appears to be unjust and
unreasonable because it lacks clear and consistent provisions requiring the evaluation of
alternative transmission technologies. The order directs PJM to explain whether the
Tariff remains just and reasonable without provisions that: (1) require the evaluation of
alternative transmission technologies in transmission service request studies, using
models that are capable of evaluating the transmission system to accurately account for
advanced transmission technologies, in all instances, without the need for a request from
the Eligible Customer seeking transmission service on behalf of large load; and (2) if
traditional Network Upgrades are selected instead of alternative transmission
technologies, inclusion in the study report to the Eligible Customer seeking transmission
service on behalf of large load of a sufficiently clear demonstration of why alternative
transmission technologies are not feasible (i.e., would not resolve reliability violations
identified or meet the relevant planning criteria) or would not result in lower costs or a
faster timeline for accommodating the transmission service request. As noted above, to
the extent stakeholders believe that specific characteristics of providing transmission
service to Eligible Customers on behalf of large loads warrant requirements beyond those
contemplated here, we seek further briefing.
Today’s order preliminarily finds that PJM’s Tariff appears to be unjust and
unreasonable because it does not contain provisions allowing an interconnection
customer serving electrically proximate large load or large co-located load to seek
generator interconnection service(s) that reflects the operational dynamics of serving such
loads. Any filings or tariff changes submitted in response to this order should address the
following questions:
a. To what extent would PJM allow an interconnection customer’s generating
facility serving electrically proximate large load or large co-located load to
participate in PJM’s energy and ancillary services market, and if PJM were
to allow them to participate, what restrictions or mitigation would PJM
apply?
b. To the extent that PJM plans for the electrically proximate large load or
large co-located load associated with an interconnection customer’s
generating facility for resource adequacy purposes, would PJM account for
the generating facilities serving electrically proximate large load or large
co-located load in the resource adequacy construct? If applicable, would
PJM allow the generating facilities serving electrically proximate large load
or large co-located load to participate in PJM’s capacity market? If so,
would PJM accredit these generating facilities using the same method as
other PJM generating facilities?
The Commission orders:
PDF page 71
Docket No. EL26-67-000
- 71 -
(A)
Pursuant to the authority contained in and subject to the jurisdiction
conferred upon the Federal Energy Regulatory Commission by section 402(a) of the
Department of Energy Organization Act and by the FPA, particularly section 206 thereof,
and pursuant to the Commission’s Rules of Practice and Procedure and the regulations
under the FPA (18 C.F.R. Chapter I), the Commission hereby institutes a proceeding in
Docket No. EL26-67-000 as discussed in the body of this order.
(B)
PJM and the Transmission Owners are hereby directed, within 60 days of
the date of the order, either: (1) to show cause as to why the Tariff remains just and
reasonable and not unduly discriminatory or preferential; or (2) to explain what changes
to the Tariff they believe would remedy the identified concerns if the Commission were
to determine that the Tariff has in fact become unjust and unreasonable or unduly
discriminatory or preferential and, therefore, proceeds to establish a replacement Tariff.
(C)
PJM is directed to submit an informational report within 30 days of the date
of issuance of this order, as discussed in the body of this order.
(D)
Any interested person desiring to be heard in Docket No. EL26-67-000
must file a notice of intervention or motion to intervene, as appropriate, with the
Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426,
in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure,
18 C.F.R. § 385.214 (2025), within 21 days of the date of issuance of this order. The
Commission encourages electronic submission of interventions in lieu of paper using the
“eFiling” link at http://www.ferc.gov. Persons unable to file electronically may file by
U.S. mail addressed to Federal Energy Regulatory Commission, Secretary of the
Commission, 888 First Street, N.E., Washington, DC 20426, or by hand (including
courier) delivery to Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, MD 20852.
(E)
Interested entities may respond within 30 days of PJM’s and the
Transmission Owners’ filing, addressing either or both of: (1) whether the Tariff remains
just and reasonable and not unduly discriminatory or preferential; and (2) if not, what
changes to the Tariff should be implemented as a replacement rate.
(F)
The Secretary shall promptly publish in the Federal Register a notice of the
Commission’s initiation of the proceeding under section 206 of the FPA in Docket
No. EL26-67-000.
(G)
The refund effective date in Docket No. EL26-67-000 pursuant to
section 206 of the FPA shall be the date of publication in the Federal Register of the
notice discussed in Ordering Paragraph (F) above.
By the Commission. Chairman Swett is concurring with a separate statement attached.
Commissioner Rosner is concurring with a separate statement
PDF page 72
Docket No. EL26-67-000
- 72 -
attached.
Commissioner See is concurring with a separate statement attached.
Commissioner Chang is concurring with a separate statement
attached.
Commissioner LaCerte is concurring with a separate statement
attached.
( S E A L )
Debbie-Anne A. Reese,
Secretary.
PDF page 73
Docket No. EL26-67-000
- 73 -
Appendix - Commenters in Docket No. RM26-4-000
Advanced Energy Management Alliance (AEMA)
Advanced Energy United (AEU)
Advancing Modern Powerlines Coalition (together with Working for Advanced
Transmission Technologies Coalition, WATT and Advancing Modern Powerlines)
Advocates for Consumer Regulated Electricity
AES Corporation (AES)
AI Supply Chain Alliance
Alexandre Figueras, on behalf of Monza Tech
Alliance for Tribal Clean Energy
Alliant Energy Corporate Services, Inc.
Amazon Energy LLC (Amazon)
America’s Power
American Chemistry Council
American Clean Power Association
American Conservation Coalition
American Council on Renewable Energy (ACORE)
American Electric Power Service Corporation238
American Public Gas Association
American Public Power Association (APPA)
American Terawatt, Inc. (American Terawatt)
American Transmission Company LLC239
Americans for a Clean Energy Grid
Antora Energy, Inc.
Arevia Power
Arizona Public Service Company
Arkansas Public Service Commission
Attorney General of the State of Oklahoma
238 American Electric Power Service Corporation submitted comments on behalf
of its affiliates Appalachian Power Company, Indiana Michigan Power Company,
Kentucky Power Company, Kingsport Power Company, Ohio Power Company,
Wheeling Power Company, Public Service Company of Oklahoma, Southwestern
Electric Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana
Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc.,
AEP Ohio Transmission Company, Inc., AEP West Virginia Transmission Company,
Inc., AEP Oklahoma Transmission Company, Inc., and AEP Southwestern Transmission
Company, Inc.
239 American Transmission Company LLC submitted comments on behalf of itself
and its corporate manager ATC Management Inc.
PDF page 74
Docket No. EL26-67-000
- 74 -
Base Power Company, Inc (Base Power).
Bloom Energy Corporation
Buckeye Power, Inc. (Buckeye)
Calibrant Energy Holdings, LLC (Calibrant)
California Department of Water Resources State Water Project (California DWR)
California Independent System Operator Corporation
California Public Utilities Commission (CPUC)
Center for Biological Diversity
Chevron U.S.A., Inc.
Clean Energy Buyers Association (CEBA)
ClearPath, Inc. (ClearPath)
Confederated Tribes and Bands of the Yakama Nation
Constellation Energy Generation, LLC (Constellation)
Consumer Energy Alliance
Consumers Energy Company
Critical Loop, Inc. (Critical Loop)
Crusoe Energy Systems, Inc. (Crusoe)
CTC Global Corporation
Data Center Coalition (DCC)
David Gardiner & Associates
Delaware Division of the Public Advocate (together with Pennsylvania Office of
Consumer Advocate, Joint Consumer Advocates)240
Digital Energy Council
Digital Power Network
Distributed Capacity Parties241
Dr. Elisa Nelson
DTE Electric Company (DTE)
Duke Energy Corporation (Duke)
EDF Power Solutions, Inc. (EDF Power)
Edison Electric Institute (EEI)
Electricity Consumers Resource Council (ELCON)
Electricity Customers Alliance (ECA)
Electric Power Supply Association (EPSA)
Emerald AI (Emerald)
Enchanted Rock, LLC
Energy New England, LLC
240 The Illinois Attorney General joined the Joint Consumer Advocates in filing
reply comments.
241 Distributed Capacity Parties include: Cloverleaf Infrastructure; Spark
Community Investment d/b/a Sparkfund; and Voltus, Inc.
PDF page 75
Docket No. EL26-67-000
- 75 -
Energy Trading Institute
ENGIE North America, Inc. (ENGIE)
Entergy Services, LLC (Entergy)242
Environmental Law & Policy Center
Eolian L.P. (Eolian)
Equinix, Inc.
esVolta, LP
ETX Upstream, LLC
Eversource Energy243
Exelon Corporation (Exelon)244
Fervo Energy Company (Fervo)
FirstEnergy Service Company245
Fluence
Front Door Technologies LLC
FuelCell Energy, Inc.
Georgia Public Service Commission
Geronimo Power, LLC (Geronimo)
Google LLC (Google)
Governors Josh Shapiro and Glenn Youngkin
GridCARE
GridStor LLC (GridStor)
Harvard Electricity Law Initiative
242 Entergy submitted comments on behalf of the Entergy Operating Companies,
which include Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi,
LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.
243 Eversource Energy submitted comments on behalf of its affiliates The
Connecticut Light and Power Company, NSTAR Electric Company, and Public Service
Company of New Hampshire, and through its agent Eversource Energy Service
Company.
244 Exelon submitted comments on behalf of itself and its affiliates Atlantic City
Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison
Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light
Company, PECO Energy Company, and Potomac Electric Power Company.
245 FirstEnergy Service Company submitted comments on behalf of itself and its
affiliates American Transmission Systems, Inc., Jersey Central Power & Light Company,
Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission
Company, The Potomac Edison Company, Monongahela Power Company, and
Trans-Allegheny Interstate Line Company.
PDF page 76
Docket No. EL26-67-000
- 76 -
Helion Energy (Helion)
Herbert Schrayschuen
Heron Power Electronics Company
Indiana Energy Association
Indicated PJM Transmission Owners (PJM TOs)246
Industrial Customer Organizations (Industrial Customers)247
Information Technology Industry Council
Infrastructure Masons, Inc. (Infrastructure Masons)
Institute for Progress
International Energy Credit Association
Invenergy248
Iron Mountain Data Centers, LLC
246 PJM TOs include: AEP on behalf of Appalachian Power Company, Indiana
Michigan Power Company, Kentucky Power Company, Kingsport Power Company,
Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission
Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky
Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West
Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland,
Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton,
OH; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company
d/b/a Dominion Energy Virginia; Duke Energy Corporation on behalf of its affiliates
Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business
Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon
Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric
Company, Commonwealth Edison Company, Commonwealth Edison Company of
Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac
Electric Power Company; FirstEnergy Service Company, as agent for its affiliates
American Transmission Systems, Incorporated, Jersey Central Power & Light Company,
Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission
Company, The Potomac Edison Company, Monongahela Power Company and Trans-
Allegheny Interstate Line Company; Old Dominion Electric Cooperative; PPL Electric
Utilities Corporation; Rockland Electric Company; Southern Maryland Electric
Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.
247 Industrial Customers include: the Industrial Energy Consumers of America,
the American Forest & Paper Association, the PJM Industrial Customer Coalition, and
the Coalition of MISO Transmission Customers
248 Invenergy includes: Invenergy Wind Development North America LLC,
Invenergy Solar Development North America LLC, and Invenergy Thermal Development
Holdings LLC.
PDF page 77
Docket No. EL26-67-000
- 77 -
ISO New England, Inc.
ITC Holdings Corp. (ITC)
Jason Miller, on behalf of VEIR Inc.
Kansas Corporation Commission (Kansas Commission)
L. Lynne Kiesling
L.M. Marlowe
Land Trust Alliance
Large Public Power Council
Lauren Hopkins
LEAN Energy US
Load Flexibility Parties249
Long Island Power Authority
Longroad Energy Holdings, LLC (Longroad)
Louisiana Public Service Commission
LS Power Development, LLC (LS Power)
Maine Office of the Public Advocate
Maryland Energy Administration
Maryland Public Service Commission (Maryland Commission)
Maven Solutions
MCC Economics and Finance
Meta Platforms, Inc.
Michigan Attorney General Dana Nessel
Microsoft, Inc. (Microsoft)
Midcontinent Independent System Operator, Inc.
MISO Transmission Owners (MISO TOs)250
249 Load Flexibility Parties include: Enerwise Global Technologies, LLC d/b/a
CPower, Enel North America, Inc., and Voltus, Inc.
250 MISO TOs include: Ameren Services Company, as agent for Union Electric
Company d/b/a Ameren Missouri, Ameren Illinois Company d/b/a Ameren Illinois and
Ameren Transmission Company of Illinois; American Transmission Company LLC; Big
Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens
Electric Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC;
Cooperative Energy; Dairyland Power Cooperative; Duke Energy Business Services,
LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative; Entergy Arkansas,
LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New Orleans, LLC;
Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy
Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power
& Light Company d/b/a AES Indiana; Lafayette Utilities System; MidAmerican Energy
Company; Minnesota Power (and its subsidiary Superior Water, L&P); Montana-Dakota
Utilities Co.; Northern Indiana Public Service Company LLC; Northern States Power
Company, a Minnesota corporation, and Northern States Power Company, a Wisconsin
PDF page 78
Docket No. EL26-67-000
- 78 -
Mississippi Public Service Commission
Missouri Public Service Commission (Missouri Commission)
Monitoring Analytics, LLC, acting in its capacity as the Independent Market Monitor for
PJM (PJM IMM)
Nathan Peterson
National Association of Regulatory Utility Commissioners
National Association of State Utility Consumer Advocates
National Conference of State Legislatures (NCSL)
National Congress of American Indians
National Grid PLC (National Grid)251
National Rural Electric Cooperative Association (NRECA)
Nebraska Power Review Board (Nebraska Board)
New England States Committee on Electricity
New England Conference of Public Utility Commissioners
New England Consumer-Owned Systems252
corporation, subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric
Company; Otter Tail Power Company; Prairie Power, Inc.; Republic Transmission, LLC;
Southern Illinois Power Cooperative; Southern Indiana Gas & Electric Company (d/b/a
CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency;
Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc
251 National Grid submitted comments behalf of its affiliates: Niagara Mohawk
Power Corporation; New England Power Company; New England Electric Transmission
Corporation; New England Hydro-Transmission Corporation; New England
Hydro-Transmission Electric Company, Inc.; and Massachusetts Electric Company.
252 New England Consumer-Owned Systems include: Belmont Municipal Light
Department, Block Island Utility District, Braintree Electric Light Department, Concord
Municipal Light Plant, Danvers Electric Division, Georgetown Municipal Light
Department, Groveland Electric Light Department, Hingham Municipal Lighting Plant,
Hudson Light & Power Department, Littleton Electric Light & Water Department,
Merrimac Municipal Light Department, Middleborough Gas & Electric Department,
Middleton Electric Light Department, North Attleborough Electric Department, Norwood
Municipal Light Department, Clear River Electric & Water District, Rowley Municipal
Lighting Plant, Stowe Electric Department, Taunton Municipal Lighting Plant, Town of
Wallingford, Connecticut Department of Public Utilities Electric Division, Westfield Gas
and Electric Light Department, and Mid-Coast Regional Redevelopment Authority.
PDF page 79
Docket No. EL26-67-000
- 79 -
New England Public Systems253
New Mexico Public Regulation Commission (New Mexico Commission)
New York Independent System Operator, Inc.
New York State Department of State Utility Intervention Unit (NY UIU)
New York Public Service Commission
New York State Reliability Council
New York Transmission Owners254
North American Electric Reliability Corporation
North Carolina Utilities Commission
North Carolina Utilities Commission Public Staff
North Dakota Public Service Commission
Northeastern Rural Electric Membership Corporation
NRG Energy, Inc.
Office of the Illinois Attorney General (Illinois AG)
Office of the Ohio Consumers’ Counsel (OCC)
Oklahoma Corporation Commission
Oklo Inc. (Oklo)
Old Dominion Electric Cooperative (ODEC)
Oncor Electric Delivery Company LLC
ON Energy Storage, Inc.
OpenAI Inc.
Oracle America, Inc. (Oracle)
Organization of MISO States, Inc. (OMS)
Organization of PJM States, Inc. (OPSI)
Paces AI Inc.
Pacific Gas & Electric Company
Paige Lambermont, on behalf of Competitive Enterprise Institute
Paul Statchen
Pennsylvania Office of Consumer Advocate
Pennsylvania Public Utility Commission (Pennsylvania Commission)
Pew Charitable Trusts Energy Modernization Project
PJM Interconnection, LLC (PJM)
253 New England Public Systems include: Connecticut Municipal Electric
Cooperative, Massachusetts Municipal Wholesale Electric Company, and Vermont
Public Power Supply Authority.
254 New York Transmission Owners include: Central Hudson Gas & Electric
Corporation, Consolidated Edison Company of New York, Inc., New York Power
Authority, New York State Electric & Gas Corporation, Niagara Mohawk Power Corp.
(d/b/a National Grid), Orange and Rockland Utilities, Inc., Long Island Power Authority,
and Rochester Gas and Electric Corporation.
PDF page 80
Docket No. EL26-67-000
- 80 -
Power for Tomorrow
PPL Corporation255
Prime Mover Institute
PSEG Companies (PSEG)256
Public Citizen, Inc.
Public Interest Organizations (PIOs)257
Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate (Ohio
FEA)
R Street Institute (R Street)
Rewiring America
MCC Economics Ltd.
RWE Clean Energy, LLC
Sarah McKinley
Shell Energy North America (US), L.P.
Sierra Club
SMA Solar Technology AG
Solar Energy Industries Association
South Carolina Office of Regulatory Staff
South Dakota Public Utilities Commission (South Dakota Commission)
Southeast Public Interest Organizations (Southeast PIOs)258
Southern California Edison Company (Southern California Edison)
Southern Companies259
255 PPL Corporation submitted comments on behalf of the PPL Companies, which
include PPL Electric Utilities Corporation, Louisville Gas & Electric Company and
Kentucky Utilities, and The Narragansett Electric Company d/b/a Rhode Island Energy.
256 PSEG Companies include: Public Service and Gas Company, PSEG Power
LLC, and PSEG Energy Resources & Trade LLC, which are each wholly-owned, direct
or indirect subsidiaries of Public Service Enterprise Group Incorporated.
257 PIOs include: Clean Air Task Force, Inc., Coalition for Affordable Utility
Services and Energy Efficiency in Pennsylvania, Earthjustice, Environmental Defense
Fund, Montana Environmental Information Center, Natural Resources Defense Council,
Sustainable FERC Project, Sierra Club, and Southern Environmental Law Center.
258 Southeast PIOs include: Southern Environmental Law Center, Appalachian
Voices, North Carolina Sustainable Energy Association, South Carolina Coastal
Conservation League, and Southern Alliance for Clean Energy.
259 Southern Companies include: Georgia Power Company, Alabama Power
Company, and Mississippi Power Company.
PDF page 81
Docket No. EL26-67-000
- 81 -
Southern Maryland Electric Cooperative, Inc.
Southwest Power Pool, Inc.
Southwest Power Pool Transmission Owner Group260
Splight Inc. (Splight)
State Entities261
Steel Manufacturers Association
Switch, Ltd. (Switch)
Talen Energy Corporation (Talen)
Terraflux LLC (Terraflux)
Tesla, Inc.
Texas Blockchain Council
Thermal Battery Alliance
Tract Holding Company I, LLC (Tract)
Transmission Access Policy Study Group (TAPS)
Tri-State Generation and Transmission Association, Inc. (Tri-State)
Travis Fisher, on behalf of Cato Institute
U.S. Chamber of Commerce (Chamber of Commerce)
U.S. Energy Storage Coalition
U.S. House of Representatives Committee on Energy and Commerce Ranking
Members262
U.S. Representatives263
U.S. Senate Committee on Energy and Natural Resources
260 Southwest Power Pool Transmission Owner Group includes: American
Electric Power Service Corporation, Evergy Kansas Central, Inc., Evergy Metro, Inc.,
Evergy Missouri West, Inc., Oklahoma Gas and Electric Company, and Xcel Energy
Services Inc., on behalf of Southwestern Public Service Company.
261 State Entities include: Massachusetts Attorney General’s Office, the Arizona
Attorney General’s Office, the Colorado Attorney General’s Office, the Connecticut
Office of Consumer Counsel, the Maryland Office of People’s Counsel, the Minnesota
Attorney General’s Office, the Office of the Nevada Attorney General, Bureau of
Consumer Protection, the New Hampshire Office of the Consumer Advocate, the Oregon
Attorney General, and the Rhode Island Division of Public Utilities and Carriers.
262 Submitted by Frank Pallone, Jr. (Ranking Member) and Kathy Castor (Ranking
Member, Subcommittee on Energy).
263 The U.S. Representatives that submitted comments include: Suhas
Subramanyam, John W. Mannion, Mike Quigley, and Donald S. Beyer Jr.
PDF page 82
Docket No. EL26-67-000
- 82 -
U.S. Senators264
U.S. Senator Jon Ossoff
Union of Concerned Scientists (UCS)
Vantage Data Centers (Vantage)
Verrus
Virginia State Corporation Commission (Virginia Commission)
Vistra Corp. (Vistra)
Washington Utilities and Transportation Commission
WIRES
Wisconsin Electric Company
Wisconsin Public Service Corporation
264 The U.S. Senators that submitted comments include: Edward J. Markey, Chris
Van Hollen, Elizabeth Warren, Peter Welch, Raphael Warnock, Richard Blumenthal, and
Adam B. Schiff.
PDF page 83
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated
Appalachian Power Company
Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
Dayton Power and Light Company
Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company
Kentucky Power Company
Keystone Appalachian Transmission Company
Kingsport Power Company
Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC
Monongahela Power Company
Neptune Regional Transmission System, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Ohio Power Company
Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Docket No. EL26-67-000
PDF page 84
Docket No. EL26-67-000
- 2 -
Silver Run Electric, LLC
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
(Issued June 18, 2026)
SWETT, Chairman, concurring:
Today, we take historic action to push our country’s electric markets and economy
into the future—a future of fair cost allocation, unprecedented transparency for the
American ratepayer, respect for states’ rights, efficient markets and speed to power. Last
October, Secretary Wright articulated the monumental, generational and “urgent”
challenge FERC must solve for our country when he directed us to develop “reforms to
ensure the timely and orderly interconnection of large loads to the transmission system.”1
I strongly agree. And now, through this suite of six orders, we deliver.
Simply put, the show cause orders the Commission issues today to each of the six
electric markets subject to its jurisdiction find that the status quo across much of the
country is not good enough.2 Nowhere close. The record prompted by the Secretary’s
ANOPR leaves no doubt that most of the markets (and their existing rules) are inherently
slow and prohibitive of the dexterity necessary to adapt to and power societal evolution—
whether brought about by technological innovation or sustaining the great industrial
economy that anchors America.
I wholeheartedly, fully concur with these orders, which we carefully crafted to
execute upon the problems the Secretary identified in a manner that is quick, efficient,
1 Advance notice of proposed rulemaking (ANOPR) Interconnection of Large
Loads to the Interstate Transmission System, Advance Notice of Proposed Rulemaking
(Oct. 23, 2025) (ANOPR); see Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy
(Oct. 23, 2025) (Secretary’s Letter).
2 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (CAISO); ISO New
Eng. Inc., 195 FERC ¶ 61,215 (2026) (ISO-NE); Midcontinent Indep. Sys. Operator, Inc.,
195 FERC ¶ 61,212 (2026) (MISO); N.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216
(2026) (NYISO); PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (PJM); Sw.
Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (SPP) (collectively, Orders to Show
Cause).
PDF page 85
Docket No. EL26-67-000
- 3 -
and legally durable. I write separately to highlight certain considerations underlying the
Commission’s procedural approach to delivering on the ANOPR and to today’s orders.
Based on my analysis of the extensive record and numerous ongoing substantive
stakeholder interactions, I have determined that the most productive way to “build upon
the[] principles”3 in the ANOPR and “work expeditiously”4 towards a solution is to issue
individualized orders to show cause to each market.5 That is so for two main reasons.
First, the record the Commission collected in response to the challenges identified
in the ANOPR and subsequent resulting developments indicate that an approach that
honors the ANOPR principles but accounts for widening regional variation may now be
more efficient than a one-size-fits-all rule.6 The world has changed a great deal since last
October. The ANOPR itself, including the articulated principles, appears to have shifted
the playing field and prompted great progress across several electric markets. This
change (and the Commission’s alignment with the Secretary) is well illustrated by a
number of landmark orders approving several market new constructs that we issued since
October, which together operationalize the Secretary’s principles and laid groundwork
for meaningful reform and today’s actions.7 While working to develop those orders, the
3 Secretary’s Letter at 2.
4 Id.
5 See SEC v. Chenery Corp., 332 U.S. 194, 202-03 (1947) (“[A]n administrative
agency must be equipped to act either by general rule or individual order. To insist upon
one form of action to the exclusion of the other is to exalt form over necessity. . . . [T]he
choice made between proceeding by general rule or by individual, ad hoc litigation is one
that lies primarily in the informed discretion of the administrative agency.”); Wis. Gas
Co. v. FERC, 770 F.2d 1144, 1166 (D.C. Cir. 1985) (“It is a well-settled principle of
administrative law that the decision whether to proceed by rulemaking or adjudication
lies within the broad discretion of the agency.”).
6 “[T]he Commission may rely on ‘generic’ or ‘general’ findings of a systemic
problem to support imposition of an industry-wide solution.” Interstate Nat. Gas Ass’n
of Am. v. FERC, 285 F.3d 18, 37 (D.C. Cir. 2002) (internal citations omitted). However,
the Commission “has long allowed different regional transmission organizations to
follow different rules, in recognition of regional variations including potential differences
in ‘geographic size and location.’” Cent. Hudson Gas & Elec. Corp. v. FERC, 138 F.4th
531, 539 (D.C. Cir. 2025) (internal citations omitted).
7 See id. P 2 & nn.6-11.
PDF page 86
Docket No. EL26-67-000
- 4 -
Commission has simultaneously devoted significant attention to evaluating the various
procedural paths through which we might comprehensively deliver.
Individual show cause proceedings will allow the Commission to ensure that
solutions to the problems the Secretary identified are tailored to the specific, varied
circumstances and market constructs of each region. Indeed, a careful review of today’s
six orders reveals the many ways in which those orders are customized for each market’s
unique circumstances and progress (or lack thereof) towards serving large load. To name
just a few examples, the orders recognize ongoing stakeholder processes in various
regions and are adapted to existing tariff provisions concerning large and co-located
loads; account for regional variances in allocating rights and responsibilities among
RTOs/ISOs and the transmission owners; leave room for each market to tailor operational
requirements for large loads that are particular to their region; and otherwise account for
incumbent regional differences on topics such as cost allocation and cost transparency,
study processes, and network upgrade procedures.
Proceeding via show cause proceedings will also allow the markets (and their
respective transmission owners) to explain, in the first instance, how to address the
Commission’s concerns. These entities have the deepest understanding of their
respective regions and are best positioned to implement solutions we identified, in the
most expeditious manner. The Commission will promptly evaluate their responses to
today’s orders, and, with input from stakeholders, swiftly establish appropriate reforms.
Second, proceeding via individual show cause orders will allow the Commission
to act more quickly than through traditional rulemaking. Notice-and-comment
rulemaking may not capitalize upon individual market progress prompted since October
and would be unduly time-consuming,8 as it also inevitably would require the additional
steps of accommodating the regional variations of the approach we take today.
Rulemaking efforts can be particularly inefficient when, as here, they risk incubating
uncertainty after progress has begun, and diverting scarce stakeholder resources away
from other endeavors, such as the development of market-specific reforms submitted to
the Commission under section 205 of the Federal Power Act (FPA). (To be clear, we
very much encourage 205 submissions encapsulating the principles we articulate in the
206s, and with all due deliberate haste.)
Furthermore, rulemaking requires a lengthy series of steps before the proposed
reforms would actually take effect—e.g., a NOPR, then a final rule, then potential orders
on rehearing, and then a “compliance” process in which affected parties make filings (or,
more likely, multiple rounds of filings) explaining how they intend to implement the rule.
8 See, e.g., Comments of Talen Energy Corporation, Docket No. RM26-4, at 5-6
(filed Nov. 21, 2025).
PDF page 87
Docket No. EL26-67-000
- 5 -
By their nature, these procedures take time. For example, the compliance process for the
Commission’s Order No. 20239 (which matured out of an ANOPR issued in July 2021
and a NOPR issued in June 2022) still is not fully complete as of June 2026. The
compliance process for Order No. 222210 (NOPR issued in November 2016) could be
considered completed in May 2026; however, even with that timing, not all of the
RTOs/ISOs have yet fully implemented their Commission-accepted market rules. I
provide these examples not to suggest that the completion of a rulemaking process on the
interconnection of large loads would take this long,11 but rather to make clear the scope
of the years-long delays in implementation that might be expected if the Commission
elected to proceed via a NOPR. By contrast, we expect that individual show cause
proceedings for each of the RTO/ISOs will enable the Commission to spearhead lasting
reform much more expeditiously.
The six markets together cover nearly two-thirds of load subject to Commission-
jurisdictional rates, and therefore focusing initially on those regions is a prudent first step.
But I am under no illusion that the challenges discussed in today’s orders are somehow
unique to the RTO/ISO regions. Our actions today do not foreclose the possibility of a
future rulemaking, and nor do they prevent us from acting on filings made under sections
205 and 206 of the FPA. I encourage transmission providers and other stakeholders
outside RTO/ISO regions to make individual filings to address the issues we discuss
today.
FERC is no longer the sleepy, responsive agency of the past—our country cannot
afford for it to be. This is a time for the best thinkers we have to collaborate on solving
our biggest problems, and thus it is my great honor to deliver a solution that honors the
Secretary’s goals.
9 Improvements to Generator Interconnection Procs. & Agreements, Order No.
2023, 184 FERC ¶ 61,054, order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g,
Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134 (2024).
10 Participation of Distributed Energy Res. Aggregations in Mkts. Operated by
Reg’l Transmission Orgs. & Indep. Sys. Operators, Order No. 2222, 172 FERC ¶ 61,247
(2020), order on reh’g, Order No. 2222-A, 174 FERC ¶ 61,197, order on reh’g, Order
No. 2222-B, 175 FERC ¶ 61,227 (2021).
11 I do not mean to suggest that the public utilities subject to compliance under
these rulemakings—or the Commission itself—have been derelict. The time-consuming
nature of the compliance process is a natural consequence of complex, nuanced efforts
toward tariff reform. As Chairman, I will continue to evaluate Commission directives to
ensure that obligations on regulated entities are not unduly burdensome and to make
certain that Commission action during the compliance process is as timely as possible.
PDF page 88
Docket No. EL26-67-000
- 6 -
For these reasons, I respectfully concur.
______________________
Laura V. Swett
Chairman
PDF page 89
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated
Appalachian Power Company
Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
Dayton Power and Light Company
Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company
Kentucky Power Company
Keystone Appalachian Transmission Company
Kingsport Power Company
Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC
Monongahela Power Company
Neptune Regional Transmission System, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Ohio Power Company
Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Docket No. EL26-67-000
PDF page 90
Docket No. EL26-67-000
- 2 -
Silver Run Electric, LLC
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
(Issued June 18, 2026)
ROSNER, Commissioner, concurring:
The electric industry is in the midst of changes not seen in a generation.
Compared to more traditional load growth, the large loads seeking to connect to the grid
today are larger, sometimes by orders of magnitude, and more concentrated. They also
exhibit different operational characteristics, such as the ability to quickly change their
energy consumption, sometimes in seconds. Often, these large loads seek to connect to
the grid as quickly as possible. And because of these dynamics, large loads are rapidly
driving the need for new transmission infrastructure and energy supply. This creates new
challenges that, if unaddressed, could jeopardize the reliability and affordability of the
grid on which we all depend.
Today, we are taking an important step toward addressing these challenges. We
are opening a dialogue with each of the six RTO/ISOs on a series of reforms that are
tailored to address the unique reliability and affordability challenges posed by large load
growth and the infrastructure buildout needed to serve dramatically growing demand.
Informed by the record developed in response to the Secretary of Energy’s October 2025
ANOPR,1 and by innovative proposals that stakeholders have filed with the Commission
under FPA section 205, today’s orders are aimed at ensuring that the grid remains reliable
and affordable for all customers, especially residential customers. It is also crucial that
we unlock the immense economic opportunity that once-in-a-generation growth
represents. While each order’s specific focus varies according to the progress that each
RTO/ISO has made, our actions today fit broadly into four key pillars that, taken
together, provide a foundation for durable reform. Today, we are: (1) Protecting
Consumers, (2) Safeguarding Reliability, (3) Enhancing Transparency, and (4) Fostering
Innovation (see Figure 1). I write separately to explain how.
1 U.S. Dep’t of Energy, Secretary of Energy Chris Wright, Direction that the
Commission Initiate Rulemaking Procedures and Proposal Regarding the Interconnection
of Large Loads Pursuant to the Secretary’s Authority Under Section 403 of the
Department of Energy Organization Act (Oct. 23, 2025).
PDF page 91
Docket No. EL26-67-000
- 3 -
*****
Protecting Consumers: Today’s orders include key protections that promote
affordability. First, today’s orders require “Cost Recovery Agreements”, which are
designed to ensure that large loads pay their fair share of the costs incurred to serve them,
regardless of whether the large load comes online as planned. Thus, if new infrastructure
is built to accommodate a data center, and that data center doesn’t show up, residential
customers are not left on the hook to pay the costs. Cost Recovery Agreements prevent
those costs from being shifted to residential customers. Depending on how they are
structured, Cost Recovery Agreements can also address the potentially uneven pacing of
new infrastructure costs, where grid upgrade costs may hit customer bills before the large
load is fully online and energized. Data centers have committed to paying their own
way.2 Today, with “Cost Recovery Agreements,” we are taking steps to ensure that those
commitments are honored. I note, however, that the door remains open to other creative,
regionally-specific ideas to protect consumers. If there are other ways to accomplish that
goal, I welcome those proposals.
Another win for consumers is requiring RTO/ISOs to consider grid enhancing
technologies (GETs), including dynamic line ratings, when adding new large loads to the
grid. GETs are technologies that squeeze more juice out of the existing grid, reducing the
need for expensive upgrades and speeding up the time connect. Ensuring that RTO/ISOs
consider GETs in the planning process—and if GETs are not used, explain why—not
only helps new large loads get connected more quickly, but is also a commonsense step
towards saving all consumers money. Put differently, today’s orders will help us
understand if we are leaving efficiencies on the table, an outcome we cannot afford.
Safeguarding Reliability: Today’s orders safeguard reliability. They help ensure
that RTO/ISOs use study procedures and operational requirements that reflect large
loads’ unique characteristics and the reliability impacts of connecting them to the grid.
Those novel characteristics and reliability impacts are well-documented, and it is not
clear if existing study procedures or operational requirements account for them. Clear,
comprehensive, and specifically tailored study procedures and operational requirements
are needed, such as enhanced data reporting and telemetry to increase visibility into how
these loads interact with the grid, and today’s orders represent progress towards this goal.
Finally, although not part of today’s orders, I want to highlight NERC’s ongoing
efforts to establish registration criteria for large computational loads and to develop
reliability standards.3 NERC’s goal is to finish the first phase of this critical work this
2 See Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026).
3 NERC, Large Loads Action Plan Q1 2026 Update (Apr. 2026),
https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/llap-quarterly-
PDF page 92
Docket No. EL26-67-000
- 4 -
year. It is essential that NERC meet this deadline. I encourage all stakeholders to
participate in NERC’s process.
Enhancing Transparency: Today’s orders provide regulators—the Commission
and, critically, our state partners—and customers with data on how connecting large
loads to the grid affects bills. Today’s orders embody a commonsense approach: if a
Network Upgrade is built to connect a large load to the grid, consumers should know who
that upgrade was built for and what it cost.
Transparency is important because “who pays?” has been and continues to be a
fraught and contentious question for large load interconnection. Stakeholders, including
state regulators and the ratepayers that they represent, must know the costs, for whom
they are being incurred, and how they are being allocated, to know that everyone is
paying their fair share. Today’s orders ensure that this information is public, accessible,
and clear. State regulators in more than half of the country have enacted large load
tariffs.4 Our action today helps them as they continue their critically important work.
The Commission’s action today also addresses speculative load interconnection
requests, which clog up load interconnection queues, divert resources, and distort
forecasts. Under current rules, data centers can (and are incentivized to) “shop around”
their prospective projects with different utilities to identify the fastest and cheapest
location to connect. This wastes time and resources studying projects that are not real.
Worse yet, it can inflate expected load growth by modeling projects that do not
materialize, leading to double counting, inaccurate market signals, and unnecessarily high
prices for consumers. Today, we target speculative projects by establishing escalating
readiness requirements for distinct phases of the study process to deter duplicative or
speculative requests for transmission service. I strongly encourage RTO/ISOs to pursue
other improvements to load forecasts, such as using objective screening criteria like
physical site control, to ensure that the data used to plan the grid is as accurate as
possible.5
update-q1-2026.pdf.
4 See, e.g., National Association of Regulatory Utility Commissioners
Supplemental Comments at 2-6; Edison Electric Institute Supplemental Comments at
App. 9-13.
5 See Comm’r David Rosner, Letter to the RTOs/ISOs on Large Load Forecasting
(Sept. 18, 2025), https://www.ferc.gov/news-events/news/chairman-rosners-letter-
rtosisos-large-load-forecasting.
PDF page 93
Docket No. EL26-67-000
- 5 -
Fostering Innovation: As I have said, to meet the moment, “a business-as-usual
approach . . . will not suffice.”6 Building new infrastructure is difficult and costly, which
delays efforts to connect large loads to the grid quickly, reliably, and cost effectively.
This is doubly true when generation and load are planned and studied separately.
Today’s orders push beyond this status quo.
First, today’s orders promote flexible transmission services—that is, non-firm
service to a co-located load that is willing and able to limit withdrawals from the grid—in
every RTO/ISO (see Figure 2). As we explained when we first created these
transmission services in PJM for co-located loads, customers willing to embrace
flexibility can reduce the need for Network Upgrades and generating capacity to serve a
co-located load, which speeds up connecting to the grid and reduces costs for the co-
located load as well as other retail customers.
Second, today’s orders recognize that extending these same transmission services
to large loads that are not co-located but that may also be willing to limit their
withdrawals from the grid can unlock even more efficiency. Just as for co-located loads,
legalizing flexible transmission service options for more large load customers can speed
interconnection, avoid constructing unnecessary transmission upgrades, reduce strain on
the grid, and make power bills cheaper for everyone.
Finally, today’s orders embrace yet another innovation. Load and generation need
not be co-located to reduce the number of Network Upgrades; in other words, literal co-
location is not the only way to facilitate faster, more efficient, and more cost-effective
connections to the grid. Rather, where a large load and an associated generator are
electrically proximate (i.e., close together) and studied together, the reliability impacts on
the grid may be more limited than if the load and generator are studied separately. Just
like with co-location, more limited impacts on the grid mean, all else equal, fewer
Network Upgrades, which makes connecting to the grid faster, more efficient, and
cheaper for both the large load and the associated generator. That last point is key. To
add new supply to the grid, we must create incentives for “Bring Your Own New
Generation.” Today’s orders make BYONG faster and more efficient.
SPP has been a leader in showing how to push beyond the status quo. With its
innovative HILLGA proposal, approved by the Commission in January,7 SPP leveraged
the opportunity for speed and efficiency by studying load and generation together, and by
creating a limited, expedited interconnection service to connect faster. By matching the
generator’s output to the electrically proximate large load’s demand, the impacts to the
6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2026), (Rosner, Comm’r,
concurring) at P 3.
7 See Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026).
PDF page 94
Docket No. EL26-67-000
- 6 -
grid are less than they otherwise would be, minimizing the need for time-consuming and
costly Network Upgrades needed to connect. HILLGA is one solution that works for
SPP, but today’s orders direct other regions to follow SPP’s lead in ways that work for
them. Today’s orders add a key tool by ensuring that all RTO/ISOs can study load and
generation together.
*****
The Commission’s action today is an important step forward, but the Commission
cannot accomplish this work alone. States are essential partners in this work. The
Commission’s actions here respect the long-standing jurisdictional line between federal
and state authority provided by Congress and repeatedly affirmed by the Supreme Court.
States retain exclusive jurisdiction to allocate the costs of FERC-jurisdictional
transmission charges among their retail ratepayers, including co-located loads. States
also hold the keys to energy infrastructure permits, so we rely on their decisions to ensure
that needed transmission and generation get built. At a time when some large loads are
retail customers that can consume as much energy as a small city, it is imperative that we
work within our respective jurisdictions, but that we collaborate. I look forward to
continued collaboration.
Today’s orders begin an important dialogue with RTO/ISOs. As a potential next
step, today’s orders invite RTO/ISOs to respond by submitting proposals under FPA
section 205. I cannot encourage this enough. I also encourage public utilities outside of
RTO/ISOs across the country to do the same. The electric industry is rapidly evolving
with regions experiencing and addressing these challenges in different ways. Many of
the examples on which the actions in today’s orders are based on stakeholders thinking
creatively to develop solutions, and I welcome other new, innovative, and regionally
tailored proposals that build on the four key pillars set forth today: (1) Protecting
Consumers, (2) Safeguarding Reliability, (3) Enhancing Transparency, and (4) Fostering
Innovation. Only by working together can we rise to the occasion and meet this once-in-
a-generation moment to deliver the reliable and affordable energy on which we all
depend. It will not be easy, but I remain optimistic and look forward to the path ahead.
For these reasons, I respectfully concur.
________________________
David Rosner
Commissioner
PDF page 97
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated
Appalachian Power Company
Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
Dayton Power and Light Company
Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company
Kentucky Power Company
Keystone Appalachian Transmission Company
Kingsport Power Company
Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC
Monongahela Power Company
Neptune Regional Transmission System, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Ohio Power Company
Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Docket No. EL26-67-000
PDF page 98
Docket No. EL26-67-000
- 2 -
Silver Run Electric, LLC
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
(Issued June 18, 2026)
SEE, Commissioner, concurring:
Growing electricity demand underscores America’s economic strength and the
opportunities that come with it. And with new opportunities come new challenges. The
pace and scale of emerging large loads create new circumstances that require us to adapt
in how we build and manage the grid. Large and flexible loads can materially change
system operations, for instance, as well as near-term planning needs, upgrade
requirements, and how we allocate costs. Most existing systems were not designed to
accommodate those changes—especially not at the pace needed to support AI growth and
advanced manufacturing that are central to America’s economic competitiveness. As a
result, uncertainty over the operative rules and delays in interconnecting large loads can
undermine reliability and investment and add unacceptable and avoidable costs.
Today, the Commission takes strong action within our jurisdictional sweep to
address these and other challenges that large load growth poses to the interstate
transmission system. Today’s orders support both just and reasonable rates and speed to
(reliable) power. I’m deeply grateful for the many commenters who shared their insight
and ideas in this action. They let us build a record that highlights the need for clearer
processes, better information, and faster analysis while our country moves new large load
additions online. As we press forward in these dockets, I will be looking to continue
building on the momentum already underway across the country to craft more practical,
region-specific solutions that support timely action while protecting consumers. Our
continued ability to deliver reliable and affordable electricity requires nothing less.
Today’s orders speak for themselves. I write separately to briefly highlight two
principles baked throughout them and that I believe must remain central as the
Commission evaluates further steps.
First, these issues extend beyond the Commission. Creating efficient, predictable
large load interconnection processes is a joint and overlapping task for us, other federal
agencies, the States, and the RTOs/ISOs and utilities. My animating principle here is that
we must use FERC’s statutory authority to bring clarity to the parts of this national issue
we own, and to complement and aid others as they tackle theirs. The very procedure the
PDF page 99
Docket No. EL26-67-000
- 3 -
Commission deploys today reflects that goal: Recognizing the value in region-specific
approaches, we are directing individual action in each of the RTO/ISO regions and
encouraging—strongly—proposals under section 205 of the Federal Power Act from
transmission providers or other entities that are molded to their unique system needs.
Most critically, exercising our authority fully without hamstringing our regulatory
and industry partners means respecting the States. States make many of the key decisions
that affect how we manage large loads. States bring indispensable expertise over local
conditions, siting needs, retail structures, and the resource decisions within their borders.
And they have been hard at work pursuing the retail implications and other State-specific
concerns that large load interconnection presents.1 All this effort flows from the States’
statutorily preserved role in regulating the power system. Today’s order understands that
limit—our power “extend[s] only to those matters which are not subject to regulation by
the States.”2 It also embraces the value in a statutory lens that views large load issues as
an area of shared federal-State responsibility. As we require clear study and operational
parameters for large load interconnection, we should remember that the nation’s energy
landscape is not monolithic. State and regional diversity is a strength, and today’s orders
know that the best solutions reflect differing system characteristics. Our action today is
designed to support further State efforts in this urgent and fast-moving space, not
override them.
Second, affordability must be at the forefront as we protect consumers from
unnecessary costs in a time of rising demand. True, the Commission lacks authority over
all the factors that drive electricity costs at the retail level. Today’s orders recognize that.
In response, the orders strive to aid the States in their front-line affordability duties by
getting into their hands all relevant information about Commission-jurisdictional costs.
As these matters move forward, I am particularly interested in continued feedback from
the States on what information they most need to assess cost implications as new loads
come online. Are the cost transparency measures we identify today sufficient, or are
additional or more granular data needed for States to appropriately suballocate
transmission costs among retail customers? Tools like alternative cost allocation
structures, greater clarity in transmission service agreements, accounting for States’
large-load-specific tariffs, and direct assignment in appropriate cases may help States
ensure that retail consumers do not bear costs incommensurate with the benefits they
receive.
1 See EEI Supplemental Comments at Appendix 9 – 13 (listing pending and
approved State large load tariffs).
2 16 U.S.C. § 824(a).
PDF page 100
Docket No. EL26-67-000
- 4 -
Moving to areas where the Commission has a more direct role in ensuring cost
responsibility, we need to pull all the levers we have to keep rates fair and transparent.
Today we reaffirm our responsibility to assign jurisdictional costs to the customers who
drive or benefit from grid upgrades, not shift them onto families and small businesses.
For instance, today’s orders seek to reduce large-load driven network upgrade costs
through alternative transmission technologies, or ATTs (also commonly called Grid
Enhancing Technologies). In determining how best to meet the needs of this historic
large load growth, technologies that can improve system capability faster than traditional
upgrades and at lower costs deserve a hard look. ATTs may not be the best tool in every
circumstance, but where they are they can support timely interconnections and avoid
potentially tens or hundreds of millions of dollars in unnecessary network upgrade costs
that would otherwise flow into transmission customers’ bills.
So our approach today supports continuing the Commission’s policy to roll most
network upgrade costs—including those in the large load space—into the embedded-cost
rate most transmission customers pay. But it includes an asterisk that this policy works
for ratepayers only so long as we remain committed to pursuing technological
innovations that keep those costs at a responsible and accountable level. Today’s order
thus calls for transmission providers to sufficiently evaluate ATTs to assess if and how
they can meet large loads’ interconnection needs. The answer may be yes or no in a
given case. But if the transmission provider opts for traditional network upgrades, they
must demonstrate why ATTs are not feasible or would not result in lower costs or a faster
timeline for the large load interconnection customer. In short, the goal is to respect
transmission providers’ engineering judgments while protecting against upgrade costs
when ATTs could solve transmission needs faster and with a lower bill.
I am also sensitive to novel questions about cost shifting that interconnecting large
load may present. Today’s findings on cost recovery agreements between transmission
owners and Eligible Customers are an important step in mitigating the risks of stranded
assets if large loads prove speculative. We are also reducing unnecessary redundancy by
allowing an Eligible Customer to meet its financial security requirements by relying on
credit support or other financial security a large load customer may have posted under a
retail agreement. As we gain more experience studying transmission service requests on
behalf of large loads, it may become appropriate to further streamline financial security
arrangements. Perhaps, for instance, cost -recovery agreements between a transmission
owner and a large load customer itself could satisfy an Eligible Customer’s financial
security requirements. As we move forward, I’ll be looking to ensure cost-recovery
agreements contain fair and transparent measures to ensure the right costs get on the right
bills. (Relatedly, the discussion about the full nature of transmission-related charges in
our concurrent PJM Order on Rehearing, Clarification, Compliance, and Paper Hearing 3
3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026).
PDF page 101
Docket No. EL26-67-000
- 5 -
may prove relevant here: Real-world experience with new transmission services for co-
located load may clarify if future action becomes needed to address potential cost shifts
as Eligible Customers take new transmission services on behalf of large loads.4)
More generally, as we gain more experience as an industry and a country in
getting large loads connected to the grid, I welcome bold proposals to keep affordability
central. Large load growth presents a real opportunity to build a stronger, more capable,
and more reliable electric system that can benefit all ratepayers. Meeting that opportunity
at the pace we need and at an acceptable cost requires innovative thinking and fast action.
I commend the States in their continued work in these areas. I urge the RTOs and ISOs
to continue their good work as they respond quickly to today’s orders. I also remain
committed to moving forward within the Commission’s statutory zone with clarity and
decisiveness. I am proud to support the Commission’s important steps today. And we all
have more work ahead.
For these reasons, I respectfully concur.
______________________________
Lindsay S. See
Commissioner
4 See id. P 456.
PDF page 102
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated
Appalachian Power Company
Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
Dayton Power and Light Company
Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company
Kentucky Power Company
Keystone Appalachian Transmission Company
Kingsport Power Company
Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC
Monongahela Power Company
Neptune Regional Transmission System, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Ohio Power Company
Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Docket Nos. EL26-67-000
PDF page 103
Docket No. EL26-67-000
- 2 -
Silver Run Electric, LLC
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
(Issued June 18, 2026)
CHANG, Commissioner, concurring:
In a series of orders today, the Commission initiates separate proceedings under
Federal Power Act (FPA) section 206 to explore the impact of the increasing growth of
large loads in Regional Transmission Organization (RTO) and Independent System
Operator (ISO) regions. The preliminary findings in these orders, and the associated
proposed reforms to RTO/ISO and transmission owner tariffs, could significantly change
how loads procure, use, and pay for transmission service, with ramifications for
RTO/ISO operations, planning, and markets. I write separately to emphasize the
importance of building actionable records in these proceedings, particularly with respect
to our consideration of customer protection, transmission service, and alternative
transmission technology reforms.
I.
Overview of Today’s Orders
In each of today’s orders to show cause, the Commission identifies a series of
issues raised by the ongoing growth of large loads, directs briefing on whether existing
tariffs remain just and reasonable in light of those developments, and describes possible
solutions to those issues if the Commission ultimately concludes that the relevant tariffs
are unjust and unreasonable. Each order is directed to a specific RTO/ISO and relevant
transmission owners that play a role in interconnecting large loads to the Commission-
jurisdictional transmission system. The Commission does not pursue the broad assertion
of jurisdictional authority contemplated in the Advanced Notice of Proposed
Rulemaking, which I hope assuages concerns raised by our state colleagues that the
Commission ought not encroach upon matters properly left to their jurisdiction.1
1 I will do my part to ensure that the Commission continues to be a collaborative
partner to our state counterparts, other federal agencies, and the industry as we seek to
address this wide-ranging challenge. Accordingly, I welcome feedback from our state
colleagues and others if they believe the Commission’s preliminary findings raise
jurisdictional concerns.
PDF page 104
Docket No. EL26-67-000
- 3 -
Broadly summarized, each order seeks regional input on a specific list of issues:
(1) the clarity and consistency of existing rules governing how each RTO/ISO and its
relevant transmission owners analyze the impact of providing transmission service to
Eligible Customers on behalf of large loads; (2) whether each RTO/ISO tariff requires
reforms to mitigate the risk of cost shifting among wholesale transmission customers; (3)
whether each RTO/ISO tariff (other than PJM) requires additional clarity regarding the
provisions addressing co-located generation and load arrangements; (4) the potential
extension of new firm and non-firm transmission services to co-located load, load with
behind the meter generation, and other flexible loads; and (5) the need for reforms,
modeled on Southwest Power Pool, Inc.’s High Impact Large Load Generation
Assessment concept, to facilitate a process through which a generator may temporarily
serve a co-located or electrically proximate load until interconnection and transmission
service is available. The Commission also invites each region to submit FPA section 205
filings that can address each issue identified in the orders, thereby resolving the
Commission’s concerns.
II.
The Commission Needs Good Records to Ensure Reasoned Decision-Making
I first want to emphasize that the Commission needs active participation from
interested stakeholders to develop thorough records in each region. The Commission
cannot make reasoned decisions about whether reforms might be needed without an
accurate understanding of the existing processes, which differ by region. Because the
Commission is acting via FPA section 206 rather than generically through a rulemaking,
the issues addressed by these orders will be subject to ex parte restrictions across the
RTOs/ISO regions, including with our state colleagues whose regulation can and will
directly affect the individual transmission owners that need to comply with the orders
issued today. This will limit the Commission’s ability to engage in informal fact-finding
and discussions with regional stakeholders, and thus, it is even more essential that the
record in each region fully reflects the views of all interested parties.
Second, I highlight three issues below that will be especially important to the
success of this effort, and I hope that interested parties will take particular care in helping
the Commission address those issues. Importantly, I recognize that the record established
in each RTO/ISO region will (and should) differ, which will allow the Commission to
ensure any required changes to an RTO/ISO’s tariff are appropriately tailored to that
region’s needs.
III.
The Commission Needs to Pursue Meaningful Customer Protection
The FPA is fundamentally a customer protection statute,2 and the Commission has
an obligation to ensure that the rates that wholesale and transmission customers pay are
2 See, e.g., Mun. Light Bds. Of Reading and Wakefield v. FPC, 450 F.2d 1341,
PDF page 105
Docket No. EL26-67-000
- 4 -
just and reasonable. Rapid large load growth has strained planning and resource
procurement processes around the country, as transmission owners, load serving entities,
and generators accelerate the building of new infrastructure needed to serve these new
loads. As we develop the new infrastructure, many have raised concerns about whether
these costs are being fairly assigned to new and existing customers, whose benefits must
be commensurate with the costs they pay. While individual states have been exploring or
using various approaches to protect retail customers against unjustified cost shifts, the
Commission to date has not initiated any proactive exploration of how to protect
wholesale customers against unjustified cost shifts. I am laser-focused on this issue
because we should not create unjustified costs for consumers in our efforts to connect and
serve large loads.
In today’s orders, the Commission launches an inquiry into whether existing
RTO/ISO tariffs include adequate mechanisms to mitigate the risk of undue cost shifting
among transmission customers. To address this risk, the Commission preliminarily
identifies a two-part solution: (1) that each RTO/ISO post public information about the
amount of new large loads seeking to connect to the RTO’s/ISO’s transmission system,
any Network Upgrades identified in the local transmission planning process to serve
those loads, and the costs of those Network Upgrades; and (2) that each RTO/ISO adopt a
pro forma cost recovery agreement to help ensure that Eligible Customers serving large
loads bear the risk and are ultimately responsible for costs incurred to provide
transmission service. I strongly support this effort to provide additional transparency
regarding jurisdictional transmission service requests and the costs associated with
providing transmission service to the requesting parties, as the Commission cannot
effectively execute its statutory responsibilities without sufficient understanding of the
costs that feed into jurisdictional rates.
Exploring how agreements between transmission owners and Eligible Customers
can protect wholesale customers against cost shifts is important. However, as I have
previously explained, bilateral agreements that simply provide transmission revenue
contributions untethered from any assessment of the actual cost of providing transmission
service induced by individual large loads may be insufficient to adequately protect other
customers against unjustified cost shifts.3 It is therefore important that the resulting
regulatory and rate design are not limited to a pre-defined solution set, and that parties
provide the Commission with comprehensive records outlining various and innovative
1348 (D.C. Cir. 1971) (stating that the FPA’s “primary aim is the protection of
consumers from excessive rates and charges”).
3 E.g., PECO Energy Co., 193 FERC ¶ 61,148 (2025) (Comm’r
Chang, concurring); Commonwealth Edison Co., 194 FERC ¶ 61,109 (2026) (Comm’r
Chang, concurring).
PDF page 106
Docket No. EL26-67-000
- 5 -
approaches to protect customers. I am encouraged by the continued development of the
ANOPR record on this subject,4 innovative solutions being developed at the state level,5
and a growing body of thoughtful analyses and proposed approaches to provide customer
protection for costs driven by large load growth.6 Without prejudging any particular
proposed solution, the Commission needs a robust record in each docket and each region
to ensure we establish the right cost shift protections for wholesale customers, including
but not limited to the commitments outlined in the Ratepayer Protection Pledge.7
I support initiating our own review of customer protection approaches, rather than
simply relying on voluntary commitments that may fall short of optimal protection,
because the Commission has the opportunity and obligation to get this issue right. I
therefore encourage interested parties to assist the Commission in that effort by clearly
and comprehensively explaining the benefits and tradeoffs of alternative customer
protection approaches. How power infrastructure costs will be assigned across Eligible
Customers that serve large loads and other customers is at the core of the efforts we
initiate today.
IV.
The Commission Needs to Understand the Implications of Extending New
Transmission Services to Additional Loads and Regions
The orders also preliminarily find that the Commission should extend the
transmission services developed in the PJM co-location proceeding – Interim NITS, Firm
Contract Demand, and Non-Firm Contract Demand – to new types of load and new
4 E.g., Interconnection of Large Loads to the Interstate Trans. Sys., Supplemental
Comments of FirstEnergy Svc. Co., Docket No. RM26-4-000 (filed June 5, 2026); id.,
Comment of the Harvard Electricity Law Initiative, Docket No. RM26-4-000 (Apr. 15,
2026); id., Supplemental Comments of WIRES, Docket No. RM26-4-000 (Mar. 30,
2026).
5 E.g., Utility Dive, Microsoft seeks Nevada tariff to shield ratepayers from data
center costs (June 8, 2026), available at https://www.utilitydive.com/news/microsoft-
seeks-nevada-tariff-to-shield-ratepayers-from-data-center-costs/822250/.
6 E.g., Travis Kavulla, How Will Data Centers Pay for Power?, American Affairs
(may 2026), available at https://americanaffairsjournal.org/2026/05/how-will-data-
centers-pay-for-power/ ; Electricity Customer Alliance, A Customer-Centric Agenda for
the Federal Energy Reg. Comm’n (Jan. 2026), available at https://lnkd.in/em-apfuQ;
Grid Strategies, Federal Transmission Pricing Vol. 2, Options for Ensuring Affordability
in an Era of High Load Growth (June 2026), available at
https://gridstrategiesllc.com/project/federal-transmission-pricing.
7 Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026).
PDF page 107
Docket No. EL26-67-000
- 6 -
regions. These new transmission services represent a fundamental paradigm shift from
the traditional network service and point-to-point transmission service models established
in Order No. 888 that have been used across the country for the last three decades. While
these services have the potential to facilitate more efficient use and build out of the
transmission system, they also contemplate running the system “tighter” than we have
done in the past, potentially with more loads on the system served by co-located or
behind-the-meter generation, and potentially more use of batteries, load control systems,
and backup resources to manage demand during system peaks or other stressed
conditions. While it is important to identify innovative solutions that can adapt to the
needs of the system, the Commission and grid operators must also be careful not to
implement changes that create unforeseen reliability risks. Ultimately, we must find the
proper balance (and I would argue we are exploring a new balance) between costs of
investments versus reliability.
The Commission’s experience in the PJM co-location proceeding highlights the
complexities and challenges of introducing these new transmission services, which have
significant ramifications for system operations, transmission planning, grid reliability,
market dispatch, resource adequacy, and cost allocation. As the Commission considers
whether to expand these transmission services to new types of load and new regions, I
encourage commenters to address what impacts the introduction of new firm and non-
firm transmission products would have in their regions, as well as any relevant
characteristics that might distinguish their regions from the Commission’s findings in the
PJM co-location docket. Ultimately, this topic will have direct long-term impacts on how
future transmission systems will be planned and configured, how efficiently future power
markets will operate, and how customers will respond to prices and system needs.
Therefore, I am specifically interested in understanding how extending the new
transmission services might affect individual suppliers or customers, as well as how
existing systems or processes might be affected by these new services. I am open to
understanding how these services might be helpful to a region or that they may create
problems not yet anticipated.
V.
The Orders Recognize the Importance of Evaluating Advanced Transmission
Technologies
Lastly, today we preliminarily find that each RTO/ISO’s tariff is unjust and
unreasonable because the tariff lacks clear and consistent provisions requiring the
evaluation of alternative transmission technologies as potential solutions to accommodate
an Eligible Customer’s request for transmission service on behalf of a large load.
Specifically, it is important for RTO/ISOs and transmission owners to evaluate whether
alternative transmission technologies are feasible in reducing the cost of transmission
system upgrades or allow for a faster timeline for accommodating the transmission
service request. As many transmission owners have explored various alternative
PDF page 108
Docket No. EL26-67-000
- 7 -
technologies in pilot projects,8 it is time to roll out all available technologies to reduce
risks and costs for customers, as well as help the industry continue to develop new
technologies that can increase the robustness of our transmission system while protecting
customers from higher costs.
VI.
Conclusion
Today’s orders address some of the most consequential issues currently in the
industry and before the Commission. I hope that these proceedings provide vehicles
through which the Commission can provide much-needed clarity and direction, and it is
imperative that we build strong and comprehensive records on each issue in each region
to inform our decision-making. I therefore encourage all interested parties to fully
engage and help the Commission navigate these complex, multi-faceted challenges. Our
success will ultimately be measured by our shared ability to deliver reliable and
affordable power to all customers, to ensure new loads can interconnect in a timely
fashion while paying their fair share of system costs, and to protect existing customers
against adverse reliability or economic impacts.
8 See, e.g., Increasing Mkt. and Planning Efficiency Through Improved Software,
Effective Congestion Mitigation with Transmission Topology Optimization at Alliant
Energy and ATC, Docket No. AD10-12-016, available at
https://www.ferc.gov/media/effective-congestion-mitigation-transmission-topology-
optimization-alliant-energy-and-atc (Alliant and ATC were able to save customers
approximately $24 million over a 12-month period through the use of topology
optimization); Pablo Ruiz and Derek Brown, “Reliable and Efficient Congestion
Mitigation Using Transmission Reconfigurations,” NewGrid and Evergy presentation
(Oct. 2022)¸ available at https://www.spp.org/Documents/67968/SAG%20Meeting%20
Materials%2020221007.zip (identifying reconfigurations, had they been implemented,
which could eliminate 98% of overloads and reduce congestion costs by 85% for
congestion patterns associated with 10 significant constraints on Evergy’s system);
Pacific Gas & Electric Press Release, PG&E and Smart Wires Enhance Grid Reliability,
Capacity for Data Centers in San Jose (May 28, 2025), available at
https://investor.pgecorp.com/news-events/press-releases/press-release-details/2025/PGE-
and-Smart-Wires-Enhance-Grid-Reliability-Capacity-for-Data-Centers-in-San-
Jose/default.aspx (describing PG&E’s deployment of advanced power flow control
devices were able to mitigate thermal overloads by up to 34%, enabling an additional 100
MW of firm power delivery over existing lines at a congested substation).
PDF page 109
Docket No. EL26-67-000
- 8 -
For these reasons, I respectfully concur.
________________________
Judy W. Chang
Commissioner
PDF page 110
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated
Appalachian Power Company
Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
Dayton Power and Light Company
Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company
Kentucky Power Company
Keystone Appalachian Transmission Company
Kingsport Power Company
Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC
Monongahela Power Company
Neptune Regional Transmission System, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Ohio Power Company
Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Silver Run Electric, LLC
Docket No. EL26-67-000
PDF page 111
Docket No. EL26-67-000
- 2 -
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
(Issued June 18, 2026)
LACERTE, Commissioner, concurring:
I support today’s fleet of show cause orders. We are at an inflection point in the
history of American energy infrastructure. The extraordinary and rapid growth of large
loads in RTOs and ISOs is faster than the current system can handle. This order charts a
course for addressing the potential gaps and shortcomings in PJM’s Tariff that need to be
resolved to appropriately respond to this growth, as informed by careful review of the
thousands of pages of comments received in response to the advance notice of proposed
rulemaking (ANOPR).1 I write separately to underscore my expectation for RTOs and
ISOs, including PJM, to timely submit their robust, thoughtful, and region-specific
proposals to address the concerns that we have preliminarily identified in their respective
tariffs and agreements. By harnessing your region-specific expertise and creativity to
bring tailored solutions to the table, together we can efficiently, reliably, and affordably
integrate large load, co-located load and generation and/or storage, as well as electrically
proximate large load onto the transmission system. I also support the use of alternative
transmission technologies to unlock every megawatt of existing capacity from our current
transmission system. We have the technology. We should use it now to enable faster
interconnection of large loads, lower costs to customers, and help prevent cost shifting.
To that end, and in light of our action in today’s orders, I also ask the state public
utility commissions—whether they have already approved large load retail tariffs, are in
the process of crafting large load retail tariffs, or have yet to embark on this essential
tariff design process—to take a hard look and ensure their large load retail tariff
provisions insulate ratepayers from the negative impacts of data center growth.
Additionally, I expect PJM to design proposals in response to this show cause order that
dovetail with the efforts on the retail side to implement the Ratepayer Protection Pledge,
1 Interconnection of Large Loads to the Interstate Transmission System, Advance
Notice of Proposed Rulemaking, Docket No. RM26-4-000, (Oct. 23, 2025) (ANOPR);
see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy (Oct. 23, 2025)
(Secretary’s Letter).
PDF page 112
Docket No. EL26-67-000
- 3 -
protect customers, and ensure that large loads cover the costs they incur to integrate with
the grid.
The stakes here could not be higher and every gambler knows that the secret to
surviving is knowing what to throw away and knowing what to keep.2 Today’s orders do
exactly that—adopting thoughtful proposals that position our nation for success, driving
meaningful change, and rejecting the gridlock, half-measures, and failure to plan that
have gone on for far too long. The data center odyssey that we embarked upon first with
PJM, then SPP, we now aggressively extend to all the RTO/ISO regions.3 Enabling the
swift and efficient interconnection of large loads to the transmission system while
maintaining affordability, reliability, commitment to open access, competitive principles
and cooperative federalism, will only be achieved through consistent, coordinated action
and persistence. But without that first step,4 there is no direction, no forward momentum,
no journey, and no way to arrive at our future destination. In the show cause orders we
issue today, the Commission takes a series of long strides towards our ultimate large load
interconnection destination: we make preliminary findings that the RTO/ISO tariffs,
including PJM may be unjust and unreasonable and/or unduly discriminatory or
preferential because they lack features necessary to timely, reliably, and safely
interconnect and serve new large loads in a way that produces just and reasonable rates.
I commend each commentor for their robust and ongoing responses to the
concerns that Secretary Wright and the Commission raised in the ANOPR proceeding.
The comments helped us identify the common issues, common solutions, and individual
differences among the RTOs/ISOs. We heard a plea for broad flexibility and regionally
tailored solutions. And we will strive to work towards those solutions, not through top-
down, one-size-fits-all mandates, but through consideration of region-specific proposals.
And we endeavor to support an appeal for federal policies that build upon rather than
disrupt current and planned developments, reflecting state and local processes and
stakeholder efforts. Through these individually tailored and region-specific show cause
orders, we are delivering to ensure that our transmission system can accommodate new
large loads in a timely, safe, and reliable manner. And, importantly, in a manner that
2 Kenny Rogers, The Gambler (United Artists Records 1978).
3 Interconnection of Large Loads to the Interstate Transmission System, 195
FERC ¶ 61,045 at P 2 (2026) (Order Regarding Intent to Act) (citing PJM Co-Location
Order, 193 FERC ¶ 61,217; SPP HILL Order, 194 FERC ¶ 61,031; Commonwealth
Edison Co., 194 FERC ¶ 61,181 (2026); Tri-State Generation and Transmission Ass’n,
193 FERC ¶ 61,070 (2025); Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025)).
4 Admittedly, we are further down the road in some regions as compared with
others.
PDF page 113
Docket No. EL26-67-000
- 4 -
ensures benefits and protection for all customers. Affordability remains a top concern as
we proceed forward.
The collective voices in the ANOPR comments have shaped our decision to issue
six separate individually tailored and region-specific show cause orders, rather than a
proposed final rule at this time. But the success of the next phase of this journey rests
with you, PJM, and your stakeholders. We are directing you to expeditiously bring
forward for our consideration your novel, region-specific solution(s). Time is of the
essence. By inviting you to proceed under FPA section 205, we are giving you
significant perks: the benefits of first wielder of the pen and the relatively capacious
standard under FPA section 205 that allows us to accept a potentially broad range of
proposals provided they are shown to be just and reasonable and not unduly
discriminatory or preferential.5 We are even giving you flexibility to propose the
implementation date for your innovative proposals. But such freedom comes with great
and concomitant responsibility.
This is not a time to be cavalier and dodge the urgent need to meet the moment.
While this is a long journey, even so, we must continue to move at breakneck pace to win
the AI race. So let me be direct. If you choose not to submit timely, reasonable, non-
discriminatory or preferential, comprehensive, and substantiated proposal(s), as directed
and as required under our applicable statutes, your deficient response will not go
unnoticed. I am prepared to play jurisdictional hardball, if needed.6 This Commission
has appropriately exercised considerable restraint in asserting the full scope of our
jurisdiction in these orders. However, the Commission has very broad jurisdiction over
transmission that we will not hesitate to utilize as necessary to ensure that we meet our
objectives in all show cause proceedings, including this PJM proceeding we initiate here.
If we find your Tariff is in fact unjust and unreasonable and unduly discriminatory or
5 See, e.g., NRG Power Mktg, LLC v. FERC, 862 FERC 108, 105 (D.C. Cir. 2017)
(FERC may not employ a rate design that follows “a completely different strategy” than,
or is “methodologically distinct” from, a proposed rate) (internal quotations omitted);
Oxy USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) (stating that a proposal under
FPA section 205 “need not be the only reasonable methodology, or even the most
accurate”); City of Winnfield v. FERC, 744 F.2d 871, at 874-875 (D.C. Cir. 1984)
(comparing the respective authorities of the Commission and public utilities under
sections 205 and 206).
6 16 U.S.C. § 824(b); New York v. FERC, 535 U.S. 17 (2002) (“There is no
language in the statute limiting FERC’s transmission jurisdiction to the wholesale
market[.]”)) (emphasis in original); id. at 20 (stating that “the FPA authorizes FERC's
jurisdiction over interstate transmissions, without regard to whether the transmissions are
sold to a reseller or directly to a consumer[.]”).
PDF page 114
Docket No. EL26-67-000
- 5 -
preferential, any failure on your end to provide a sufficient FPA filing or filings to
address the large-load-related concerns that we have identified will result in the
Commission dictating the solutions for you. I say this not as a threat, but as a statement
of duty. While you may not like our remedies—I have often said that the federal
government generally does not come up with the best solutions—this is an outcome we
are prepared to pursue given the gravity of the moment and our statutory obligation.
Notwithstanding our readiness to step in, it greatly benefits everyone for you to come up
with an approach tailored to your region.
I will end my concurrence where I began: We have heard your concerns, and, let
me underscore, now is the time for you to heed ours. This is an extraordinarily
consequential proceeding. The stakes for reliability, for affordability, and for the
American ratepayer could not be higher. We owe it to the public to get this right. I look
forward to reviewing and acting as expeditiously as possible on your responses to this
show cause order, which I expect will include an FPA section 205 proposal or proposals.
For these reasons, I respectfully concur.
______________________________
David LaCerte
Commissioner