EL25-49-002 · 2026-08-14 · FERC

Notice of Extension of Time granting PJM and the Indicated PJM Transmission Owners 90 days, to November 16, 2026

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Filing procedure

What the document says

Unpaginated filing

FERC gives PJM and its owners 90 more days, to November 16, on co-location.

The deadline for PJM to comply with certain directives of the Co-Located Load Order, and the deadline for the PJM transmission owners to comply with the directives of the Co-Located Load Order, is extended to and including November 16, 2026. Source text
Filed comments: Connecting load and generation

Unpaginated filing

The extension lines co-location compliance up with PJM's large-load section 205 filing.

to allow PJM to develop the remaining aspects of its compliance filing to comply with the Co-Located Load Order in conjunction with a Federal Power Act section 205 filing being developed in response to the Large Load Show Cause Order Source text
Filed comments: Connecting load and generation

Unpaginated filing

PJM still owed an August 17 partial filing; Constellation wanted full Interim NITS terms.

if its requested relief is granted, it will still make a compliance filing on August 17, 2026 that addresses certain defined terms Source text

Unpaginated filing

PJM still owed an August 17 partial filing; Constellation wanted full Interim NITS terms.

with the clarification that PJM remains obligated to file, on August 17, 2026, a complete set of provisions to facilitate Interim NITS Source text

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

EL25-49-002 EL25-49-000 AD24-11-001 EL25-20-001 (consolidated) ER26-1479-000 NOTICE OF EXTENSION OF TIME (August 14, 2026) On July 28, 2026, PJM filed a motion for a 90-day extension of time to comply with certain directives in the Commission’s June 18, 2026 order in this proceeding,[fn:2] which…
Read this passage Filed comments: Connecting load and generation

Footnotes

Word notes · Topic match: Connecting load and generation

Footnotes [fn:2] See PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (Co-Located Load Order). [fn:3] See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (Large Load Show Cause Order).
Read this passage Filed comments: Connecting load and generation