EL26-70-000 · 2026-08-07 · American Municipal Power, Inc.
Answer of American Municipal Power, Inc. in Response to the Motion to Hold Abeyance filed by Midcontinent Independent System Operator, Inc. et al
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
)
)
Docket No. EL26-70-000
ANSWER OF
AMERICAN MUNICIPAL POWER, INC.
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission (“Commission” or “FERC”)1 and the Commission’s notice,2
American Municipal Power, Inc. (“AMP”) respectfully submits this Answer in response to
the abeyance motion filed by Midcontinent Independent System Operator, Inc. (“MISO”)
and the MISO Transmission Owners on August 3, 2026, in the above-captioned
proceedings (“Motion”). The Motion fails to provide the information required by the
Commission’s June 18 Show Cause Order in the event abeyance is sought,3 and
therefore the Commission has grounds to deny the Motion.
However, in the interest of expediting resolution of this matter, the Commission
should instead direct MISO to present within twenty days to its stakeholders a proposal
for their consideration that addresses in substantial detail the critical cost-transparency
and cost-shifting issues identified in the Show Cause Order, and immediately file that
proposal with the Commission on an informational basis, along with an update describing
MISO’s detailed plan for consideration of its proposal within the stakeholder process, to
demonstrate progress in support of further abeyance. The Commission should also
impose a deadline of November 16, 2026 for MISO and the MISO Transmission Owners
1 18 C.F.R. § 385.213.
2 Notice Establishing Answer Period, Docket No. EL26-70, at 2 (August 4, 2026).
3 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 37 (2026) (“Show Cause Order”).
PDF page 2
2
to file responsive revisions to the MISO Open Access Transmission, Energy and
Operating Reserves Markets Tariff (“Tariff”).
I.
ANSWER
A.
The Show Cause Order identified critical issues for MISO to address
in Tariff revisions to be proposed through a compliance filing that
remains due on August 17, 2026.
The Show Cause Order identified cost transparency and cost-shifting protections
as central deficiencies, among others, in MISO's Tariff. Missing protections include, inter
alia, public disclosure of large-load-driven network upgrades and their costs, cost
recovery agreements, financial security requirements, and protection of existing
transmission customers from stranded costs caused by speculative large-load projects.4
The Show Cause Order discusses each of these problem areas in support of the
Commission’s decision to require submittal of proposed revisions to the Tariff by August
17, in the absence of a demonstration that the existing Tariff is just and reasonable.
B.
The Show Cause Order adopted reasonable standards for evaluating
the abeyance request presented in the Motion.
The Commission anticipated that MISO and the MISO Transmission Owners may
need additional “time while they work through the stakeholder processes to develop FPA
section 205 filings to revise the Tariff to address the issues raised in [the Show Cause
Order].”5 The Show Cause Order indicated “that successful abeyance requests, if any,
will include both (1) a robust description of the content of a potential future filing under
FPA section 205 and (2) a reasoned and specific explanation of when such a filing is
4 See Show Cause Order at PP 3, 23-25, 33, 66, 71-85.
5 Id. P 37.
PDF page 3
3
expected to be made.”6 The Commission expressly stated that it would not grant
abeyances reflexively.7
C.
MISO’s Motion fails to meet the standards for abeyance established in
the Show Cause Order.
MISO's response consists largely of a few lines of text indicating that concepts and
Tariff revisions will be developed in the future through collaboration between MISO and
the MISO Transmission Owners, and eventually presented to MISO’s Large Load
Working Group (“LLWG”), with a potential filing in November anticipated. This falls well
short of the detailed roadmap to compliance that the Commission required to justify
abeyance.8
The Motion only superficially describes a potential future filing under Federal
Power Act (“FPA”) section 205.9 The “anticipated” filing may take place sometime in
November. The only explanation for the vague filing timeline is that MISO will engage with
stakeholders prior to the filing, but no detail is provided regarding that engagement other
than that it will involve presentations, discussions, and feedback:
Finally, MISO and the MISO Transmission Owners are
working together to develop additional solutions, processes,
and services to address the balance of the Commission’s
concerns identified in the Show Cause Order. These include,
among other things, (a) the application process, study
procedures (including evaluating alternative transmission
technologies), and ongoing operational requirements that
apply to Eligible Customers seeking transmission service on
behalf of large loads; and (b) additional transparency
concerning the Network Upgrade costs and cost shift
concerns. MISO will present concepts and proposed Tariff
revisions to the LLWG for discussion and formal stakeholder
6 Id. P 37.
7 Id.
8 See id.
9 16 U.S.C. § 824d.
PDF page 4
4
feedback requests as they are developed in anticipation of a
November FPA section 205 filing to address any Commission
directives not addressed in a prior FPA section 205 filing.10
Whereas the Commission has thoughtfully outlined its expectations in terms of cost
transparency and preventing cost shifting, MISO and the MISO Transmission Owners
have scarcely provided a conceptual response to the Commission’s detailed and specific
concerns, much less a reasoned and specific explanation of when a filing will be made or
how it will address those concerns. Yet MISO has vigorously pursued other initiatives with
respect to large loads for months as detailed in the balance of its abeyance request.11
The Motion asserts that there will be six meetings of MISO’s LLWG between now
and November, and that “[a] detailed management plan outlining the specific agenda for
these meetings is located on MISO’s website and will be updated regularly.”12 But the
referenced “plan” merely contains high level bullets listing a few general topics to be
discussed at each meeting. For example, the listing for the August 27, 2026 meeting
states in part: “Introduce New Issue(s) – Cost Transparency . . . .”13
Costs associated with transmission upgrades to serve large loads are likely to be
in the billions of dollars. Solutions to ensure proper cost allocation that will avoid cost
shifting cannot be solely developed by MISO and the MISO Transmission Owners through
proposals that are presented to the rest of the stakeholder community with almost no time
for meaningful input. This is especially true when the Show Cause Order’s directives have
10 Motion at 12-13 (footnotes omitted).
11 See, e.g., Motion at 9-12.
12 Id. at 13 (citing MISO, LLWG Management Plan, (July 31, 2026),
https://cdn.misoenergy.org/20260812%20LLWG%20Item%2001d%20Management%20Plan772569.p
df (“LLWG Management Plan”) (attached hereto as Exhibit A)).
13 LLWG Management Plan.
PDF page 5
5
been in place since mid-June and MISO has not presented any proposals on cost
transparency or cost shifting in the stakeholder process to date.
D.
To expedite resolution of this matter, the Commission should
condition abeyance on a further compliance filing by MISO.
There is a clear gap between the existing broad cost allocation methodologies
applied to transmission projects in MISO generally, and a targeted allocation that is
necessary to protect against cost shifting due to the addition of large loads. Transmission
dependent utilities such as municipalities and cooperatives are not protected by state
utility commissions and retail tariffs because the allocation of costs between individual
load serving entities within MISO transmission pricing zones is performed at the
wholesale level. Transmission service rates are, of course, FERC-jurisdictional and
protections for these wholesale customers (and by implication, their associated retail
customers) cannot be ignored or given short shrift.
Accordingly, the Commission should direct MISO to: (1) bring forward a specific
proposal to meet its obligations under the Show Cause Order to address cost
transparency and cost shifting within the next twenty days in the MISO stakeholder
process and provide the Commission with a detailed report regarding that proposal; (2)
thoroughly vet its proposal with state regulators, consumer advocates, and other
representatives of customers and load serving entities that might bear the costs of
upgrades required to serve large loads; and (3) work collaboratively with these parties to
develop just and reasonable revisions to the MISO Tariff in compliance with the Show
Cause Order, to be submitted for the Commission’s approval by the revised deadline,
which should be no later than the maximum ninety-day abeyance period contemplated in
that order (i.e., no later than November 16, 2026).
PDF page 6
6
II.
CONCLUSION
WHEREFORE, for the foregoing reasons, American Municipal Power, Inc.
respectfully requests that the Commission issue an order containing the three directives
described herein, and that the Commission grant such further relief as the Commission
may deem appropriate.
Respectfully submitted,
/s/ Gerit F. Hull
Lisa G. McAlister
Senior Vice President & General
Counsel
Gerit F. Hull
Deputy General Counsel for
Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
lmcalister@amppartners.org
ghull@amppartners.org
Counsel for American Municipal Power, Inc.
Dated: August 7, 2026
PDF page 7
EXHIBIT A
Midcontinent Independent System Operator, Inc.
Large Load Working Group Management Plan
July 31, 2026
PDF page 8
LLWG Management Plan
Last Update: July 31, 2026
√ Potential Voting Item
^ Feedback Requested
* Verbal Report
Informational / Post Only
Entity: Large Load Working Group (LLWG)
Reports to: Advisory Committee (AC)
Officers:
Chris Plante, Chair
Werner Roth, Vice Chair
Marc Keyser, MISO Liaison
Amanda Jones and Eileen King, Stakeholder Relations
Rationale for Existence:
The objective of the Large Load Working Group (LLWG) is to provide input and policy guidance to MISO Management and the Steering Committee on
processes and policies pertaining to markets, reliable operations, planning, and resource adequacy that facilitate integration and enablement of
large loads in the MISO footprint.
The LLWG will coordinate its efforts with other MISO stakeholder groups, including all entities reporting to the Advisory Committee and any other
related stakeholder forums that are organized during the term of this Working Group.
How many meetings were held in 2025? N/A
What was the average number of total participants in 2025? N/A
Recurring Tasks
Annual Administrative Tasks
Status Reports from Subordinate Entities
•
New issues assigned by Steering
Committee (as needed) or FERC (e.g.,
Rulemaking, NOPR)
•
Leadership nominations (April)
•
Leadership elections (May)
•
Next year meeting schedule (Q3/Q4)
•
Annual charter and management plan
review and approval (Q1)
N/A
A-1PDF page 9
LLWG Management Plan
Last Update: July 31, 2026
√ Potential Voting Item
^ Feedback Requested
* Verbal Report
Informational / Post Only
Q3 2026
•
Operational Reliability
Requirements Issues
(TBD)
Stakeholder Panel:
Perspective and
Experience with Large
Loads
•
BPM Updates:
o
Large Load BPM-
032
o
Large Load Firm
Service Step Up
(LLWG-2026-1)
•o ZGIA (PAC-
2024-4) ZGIA
BPM (PAC-2024-
4)
July 16
•
Large Load Firm Service Step Up (LLWG-2026-1) ^
•
Creation of Large Load BPM 032/ Other BPM Updates
•
Alliant Large Load Non-Firm Transmission Service (BITS) Proposal
•
Discuss FERC June Large Load Action
•
New Issue/Discussion: Conditional/Non-firm Transmission Service √
•
New Issue/Discussion: Load Addition Resource Study √
•
July 27
•
Interconnection Reliability Requirements (LLWG-2026-3)
August 12
Review Conditional Non-firm Transmission Service (LLWG-2026-5)
•
Large Load Show Cause Abeyance Request/Filing Plans
•
Interconnection Reliability Requirements (LLWG-2026-3)
•
Conditional Non-firm Transmission Service (LLWG-2026-5) ^
August 27
•
Large Load Firm Service Step Up (RASC-2026-1) Final Tariff Redlines
•
Large Load Reserve Product Enhancements (LLWG-2026-2) Evaluation results and initial
recommendation(s)
•
Creation of Large Load BPM 032/ Other BPM Updates
•
Large Load Filing Plans (August)
•
Interconnection Reliability Requirements: Stability Assessment Requirements
•
Load Addition Resource Study (LLWG-2026-6) Draft Tariff Redlines
Large Load Reserve Product Enhancements (LLWG-2026-2) initial evaluation results, cost
allocation recommendation
•
Introduce New Issue(s) – Cost Transparency, Tariff Defined Application Process, Large Load Study
Process√
•
Large Load BPM 032/ Other BPM Updates
•
September 23no meeting
Load Addition Resource Study (LLWG-2026 6)
BPM Updates:
LL BPM-032
A-2PDF page 10
LLWG Management Plan
Last Update: July 31, 2026
√ Potential Voting Item
^ Feedback Requested
* Verbal Report
Informational / Post Only
Large Load Firm Service Step Up (LLWG-2026-1)
ZGIA (PAC-2024-4)
•
Interconnection Reliability Requirements: (LLWG-2026-3) Stability Assessment Requirements
•
Conditional Non-firm Transmission Service (LLWG-2026-5)
•
Load Addition Resource Study (LLWG-2026-6)
•
Cost Transparency/Allocation (LLWG-2026-TBD)
•
Tariff Defined Application Process (LLWG-2026-TBD)
•
Large Load Study Process (LLWG-2026-TBD)
•
New Issue/Discussion: Large Load Remote Disconnect √
•
Large Load Remote Disconnect Proposal (LLWG-2026-TBD)^
•
BPM Updates
Q4 2026
•
Operational Reliability
Requirements Issues
(TBD)
•
Large Load Reserve
Product Enhancements
(LLWG-2026-2) reserve
enhancement
recommendation and
evaluation summary
•
BPM Updates:
o
Large Load BPM-
032
o
Large Load Firm
Service Step Up
(LLWG-2026-1)
o
Conditional Non-
firm Transmission
Service (LLWG-
2026-5)
October 8
•
Tariff for Conditional/Non-firm Transmission Service (LLWG-2026-5) Draft Tariff Redlines ^
October 29
•
Large Load Firm Service Step Up (LLWG-2026-1) BPM
•
Tariff for Conditional/Non-firm Transmission Service (LLWG-2026-5) Final Tariff Redlines
Firm Step Up BPM (add issue #)
•
Large Load Remote Disconnect (LLWG-2026-TBD) Tariff Redlines ^
November 16 (afternoon tentative to change)
•
Review response to Large Load show cause order
A-3PDF page 11
LLWG Management Plan
Last Update: July 31, 2026
√ Potential Voting Item
^ Feedback Requested
* Verbal Report
Informational / Post Only
o
Load Addition
Resource Study
(LLWG-2026-6)
•
Creation of Large Load
BPM 032/ Other BPM
Updates
Load Addition Resource
Study
•
Cost
Transparency/Allocation
(LLWG-2026-TBD)
•
Tariff Defined Application
Process (LLWG-2026-
TBD)
•
Large Load Study Process
(LLWG-2026-TBD)
December 15
Q1 2027
•
Leadership Nominations
and Election √
•
Administrative Items
Annual Review √
Meeting TBD
Meeting TBD
Q2 2027
•
Leadership Nominations
and Election √
•
Meeting TBD
A-4PDF page 12
LLWG Management Plan
Last Update: July 31, 2026
√ Potential Voting Item
^ Feedback Requested
* Verbal Report
Informational / Post Only
Meeting TBD
Q3 2027
•
Meeting TBD
Meeting TBD
A-5PDF page 13
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each
person designated on the official service list compiled by the Secretary in this proceeding.
/s/ Gerit F. Hull
Gerit F. Hull
Deputy General Counsel for
Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
Dated at Columbus, Ohio, this 7th day of August, 2026.