ER26-3515-000 · 2026-09-03 · Data Center Coalition
Motion to Intervene and Protest of the Data Center Coalition to PJM Interconnection, L.L.C.’s proposal to establish Interim Resource Adequacy Service and a Large Load Registry
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3515-000
)
MOTION TO INTERVENE
AND PROTEST OF THE DATA CENTER COALITION
Pursuant to Rules 211, 212, and 214 of the Rules of Practice and Procedure of the Federal
Energy Regulatory Commission (“FERC” or the “Commission”)1 and the Commission’s August
13, 2026 Combined Notice of Filings #2,2 the Data Center Coalition (“DCC”) hereby moves to
intervene and submits this protest of PJM Interconnection, L.L.C.’s (“PJM”) proposal to establish
Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry.3
I.
INTRODUCTION
DCC is the membership organization for the U.S. data center industry, representing leading
data center owners and operators that develop, operate, and maintain data center infrastructure and
teams across the country. DCC members operate data centers that constitute significant loads
within the PJM region and DCC has been an active stakeholder in regional efforts to ensure
reliability, enable new generation, and discipline load forecasts.
DCC and its members have been at the forefront of efforts to advance reforms in PJM and
at the state level to accommodate the growth of data centers and other large load customers within
the PJM region while maintaining reliability and protecting existing retail customers. DCC agrees
1 18 C.F.R. §§ 385.211, 385.212, and 385.214.
2 PJM Interconnection, L.L.C., et al., Docket No. ER26-3515-000, et al., Combined Notice of Filings #2
(Aug. 13, 2026).
3 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Proposal of PJM Interconnection, L.L.C. to
Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (Aug. 13,
2026) (“Filing”).
PDF page 2
- 2 -
with PJM that steps must be taken to maintain reliability, protect existing customers from
inappropriate cost shifts, and ensure that data centers and other large load customers take
appropriate responsibility for supporting the development of new generation and infrastructure
necessary to serve their demand.
Indeed, DCC was a leading voice in the PJM Critical Issue Fast Path (“CIFP”) processes
that led to PJM’s Filing in this docket. From the outset of these processes, DCC championed
reforms to enable data centers to bring their own generation capacity to insulate existing customers
from the costs of serving demand from large load customers, as well as legally-durable pathways
to enable states to implement interruptible retail tariffs to support grid-wide reliability and
resilience. Looking beyond the positions DCC took in PJM’s stakeholder process, DCC members
have proudly joined over 200 governors, utilities, electric cooperatives, and data center developers
in support of the White House’s “Ratepayer Protection Pledge,”4 which, through historic levels of
industry investment in long-needed new capacity, is already helping to resolve many of the
fundamental issues PJM aims to address through this proceeding.
DCC also strongly supports state efforts to establish interruptible service tariffs that
facilitate the integration of new large loads while maintaining reliability and protecting existing
customers. In fact, DCC has, alongside the Virginia State Corporation Commission (“VA SCC”),
called for other state regulators to develop model retail interruptible tariffs and emergency load-
reduction programs that would allow large loads to take interruptible service, establish
standardized curtailment obligations and operating rules, and allow state-jurisdictional utilities to
curtail participating large commercial and industrial customers during system emergencies to
4 Ratepayer Protection Pledge, THE WHITE HOUSE, Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4,
2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.
PDF page 3
- 3 -
protect existing customers.5
Notwithstanding DCC’s support for bring-your-own-generation-capacity solutions and the
other initiatives described above, DCC believes that the IRAS proposal is legally defective and
must be rejected. The Federal Power Act (“FPA”) grants states—not PJM or FERC—exclusive
authority over the rates, terms, and conditions of retail service. Yet, PJM asks the Commission to
grant it authorization to impose a new curtailment program that aims to interrupt retail service to
large load customers that PJM determines have failed to comply with new bring your own new
capacity (“BYONC”) requirements prescribed in the PJM tariff (“Eligible New Large Loads”).
Rather than accommodating state efforts to modify retail curtailment policies to account for the
growth of large loads, IRAS instead seeks to compel states within the PJM footprint to conform
their retail curtailment frameworks to PJM tariff requirements. DCC believes that this top-down
approach to addressing the curtailment of retail customers is inconsistent with principles of
cooperative federalism and disregards the carefully calibrated division of authority between FERC
and the states.
DCC acknowledges that successfully addressing the challenges of large load integration in
the region will require collaboration and cooperation among PJM, state regulators, large loads,
electric distribution companies, and other stakeholders. But Congress’s decision to reserve to the
states authority over retail service means that it is the states that must take the lead in developing
the retail service frameworks through which new large loads are integrated into the electric system,
including the rules governing the priority of customer classes, the terms for interrupting service to
retail customers, and the requirements that customers must meet to obtain firm service. While
5 See Exh. A; Letter to Ms. Paula Conboy and Mr. David Mills from VA SCC Chair, Kelsey Bagot and DCC
President & CEO, Josh Levi (June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-
rbp/2026/20260630/20260630-written-comments---va-scc-and-data-center-coalition.pdf.
PDF page 4
- 4 -
PJM has a critical role to play in ensuring that large loads are integrated into the system reliably,
it should not seek to displace the role of the states by imposing a uniform retail curtailment policy
across the PJM region.
This does not mean that PJM and the Commission are powerless to take actions to protect
customers from service interruptions when grid conditions are tight. During the CIFP process,
DCC outlined a framework for a state “opt-in framework” that would couple state-led
implementation of interruptible service with changes to PJM’s operational practices to ensure that
retail curtailments are implemented in a manner that recognizes the respective roles of wholesale
and retail regulators.6 Under that proposal, states would be responsible for establishing
interruptible customer classes for large load customers while PJM would continue to monitor
system conditions and, when conditions warrant, would issue a signal to utilities in participating
states that would trigger curtailments in accordance with state-established tariffs and service
priorities. To provide immediate relief to customers while states work to update their retail tariffs,
DCC also proposed that PJM update its manual load-shed procedures to establish a framework
under which data centers and other large loads would be contacted during emergencies and
provided an opportunity to voluntarily curtail prior to PJM’s implementation of broader load dump
procedures.
DCC’s proposal illustrates that there are approaches that can achieve the same reliability
outcomes as IRAS while respecting the traditional division of responsibility between FERC and
the states. But the benefits of a state-led approach are not limited to merely avoiding the significant
6 See Exh. B; DCC Connect & Manage Alternative: State-Led Implementation with Immediate Residential
Customer Protection (June 30, 2026), available at: https://www.pjm.com/-/media/DotCom/committees-
groups/committees/mc/2026/20260630-special/item-01c---data-center-coalition---cm---executive-summary.pdf. See
also Exh. C; DCC, A Path to Reliable Large-Load Integration: Creating Certainty for Investment, Customers, and the
Grid
(June
10,
2026),
https://www.pjm.com/-/media/DotCom/committees-groups/cifp-
rbp/2026/20260611/20260611-item-03a---data-center-coalition-presentation.pdf.
PDF page 5
- 5 -
legal issues presented by IRAS. Allowing states to take the lead in establishing retail curtailment
priorities avoids one of the other major shortcomings of IRAS: there is no assurance that a PJM-
led framework will be effective or achieve the objectives that PJM seeks. If states are truly free to
establish different curtailment priorities as PJM claims, PJM cannot ensure that the customers it
seeks to target through IRAS will be curtailed, that retail customers that comply with PJM’s
BYONC requirements will avoid service interruptions, or that the proposal will deliver the
reliability benefits PJM claims.
IRAS is also unjust, unreasonable, and unduly discriminatory on its own terms. IRAS
would create a sub-class of Network Integration Transmission Service (“NITS”) customers that
would be defined by the characteristics of the retail customers that they serve. NITS customers
serving Eligible New Large Loads would be required to pay the same transmission and capacity
charges as other NITS customers, but would be curtailed ahead of other NITS customers and firm
point-to-point customers. In fact, while NITS customers serving Eligible New Large Loads still
would be required to pay charges reflecting the cost of capacity committed through PJM’s capacity
market, PJM proposes to curtail these customers prior to deploying Demand Resources that have
been committed to provide capacity to maintain reliability and avoid interruptions to firm
customers. The result would be to force these NITS customers to bear the costs of capacity that
would not be available to meet their needs.
Compounding these problems is the fact that the Filing offers no transition mechanism and
effectively provides New Large Loads a window of less than ten months to procure new capacity
or face curtailment—an interval that PJM’s own documented difficulties in bringing resources
online demonstrates is not realistic. The result is that large loads that have spent billions of dollars
PDF page 6
- 6 -
and entered complex commercial arrangements in reliance on PJM’s longstanding rules will
suddenly face the prospect of being unable to obtain the reliable service their projects depend on.
Rather than implementing measures to degrade the quality of service provided to Eligible
New Large Loads, PJM should be pursuing reforms that eliminate barriers to the development of
the new generation capacity needed to maintain reliability and avoid the curtailment of retail
customers. Yet, PJM proposes to undermine the ability of the capacity market to send price signals
for the development of new capacity by excluding Eligible New Large Loads from the calculation
of the Variable Resource Requirement curve (“VRR Curve”) beginning with the 2029/2030
Delivery Year. Ultimately, the result will be a capacity market that produces prices and results
that are untethered to actual supply and demand conditions within the PJM footprint. A capacity
market that is modeled as if a large and growing increment of demand does not exist cannot send
the price signals needed to attract the supply that PJM says the region lacks.
DCC recognizes that the PJM region must adapt to this high load growth environment in
which new resource entry remains frustrated and is committed to advancing durable solutions that
preserve states’ role in integrating large loads, protect existing customers from inappropriate cost
shifts, and provide data centers and other large loads with timely pathways to power that ultimately
improves reliability throughout the region. Establishing a framework that can accomplish these
objectives is essential to ensuring that America’s industries of the future—data centers,
semiconductors, battery manufacturing, and the automotive, steel, metal, chemical, petrochemical,
and refining industries—remain competitive in the global economy. But PJM’s proposal to impose
a retail curtailment scheme on states that eviscerates the jurisdictional lines drawn by Congress,
requires customers to pay for capacity that they will not benefit from, undermines the settled
PDF page 7
- 7 -
expectations of New Large Loads, and may ultimately prove unworkable is not a viable path
forward.
For the foregoing reasons, DCC asks the Commission to issue an order rejecting the Filing
and encouraging PJM to work with stakeholders to develop changes to PJM’s emergency
procedures that accommodate—rather than dictate—the retail curtailment priorities of individual
states. Alternatively, if the Commission finds that the growth of large loads has rendered PJM’s
existing emergency procedures unjust and unreasonable, the Commission should initiate a Section
206 proceeding to develop proposed revisions to these procedures that respect the jurisdictional
boundaries established by the FPA while protecting existing retail customers from service
disruptions and inappropriate cost shifts.
If the Commission does not reject IRAS outright, then it should direct PJM to establish a
meaningful transition mechanism that avoids disrupting existing contractual arrangements and
provides both large load customers and the states a reasonable timeline to take the steps necessary
to adapt to the IRAS framework. Among other things, any transition mechanism should limit the
application of IRAS in a manner that respects existing contracts and investment decisions,
including exempting large load customers that have already entered into contracts for retail service
that pre-date implementation of IRAS. Additionally, the Commission should direct PJM to delay
implementation of IRAS until June 1, 2028 to provide new large loads a reasonable amount of
time to comply with PJM’s BYONC requirements and to provide state authorities with the time
necessary to update their retail policies to account for the IRAS framework.
PDF page 8
- 8 -
II.
PROTEST
A.
IRAS Unlawfully Intrudes On State Authority Over Retail Sales
In drafting the FPA, “Congress meant to draw a bright line easily ascertained, between
state and federal jurisdiction[.]”7 Congress granted FERC jurisdiction over wholesale sales of
electricity and transmission service in interstate commerce.8 At the same time, the FPA “limits
FERC’s regulatory reach, and . . . maintains a zone of exclusive state jurisdiction”9 by reserving
to the states jurisdiction over “any other sale of electric energy” and “over facilities used for the
generation of electric energy” and “facilities used in local distribution[.]”10
Although the “wholesale and retail markets in electricity are inextricably linked,” the mere
fact that the rates, terms, and conditions of retail service may affect wholesale markets is not a
sufficient basis for FERC to assert jurisdiction.11 FERC cannot take an action transgressing the
limits prescribed by Congress “no matter how direct, or dramatic, its impact on wholesale rates.”12
FERC may not approve tariff provisions that directly regulate retail customers, dictate retail
service terms, or prescribe the curtailment priority of retail customers.13 Nor may FERC approve
tariff provisions that “target” those matters left for the states to regulate.14
PJM portrays IRAS as a narrow reliability measure that merely supplements existing
emergency procedures. But the proposal cannot be evaluated based on labels alone. The
7 Federal Power Comm’n v. Southern California Edison Co., 376 U.S. 205 (1964).
8 16 U.S.C. § 824(b)(1).
9 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 266 (2015).
10 16 U.S.C. § 824(b)(1).
11 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 264 (2015).
12 Id. at 280.
13 Northern States Power Co. v. FERC, 176 F.3d 1090 (8th Cir. 1999) (finding that FERC’s “attempt to
regulate the curtailment of electrical transmission on native/retail consumers is unlawful, as it falls outside of the
FPA’s specific grant of authority to FERC.”); Tri-State Generation and Transmission Association, Inc., 193 FERC ¶
61,070, at P 49 (2025) (rejecting large load tariff that “appear[s] to dictate certain terms and conditions for retail
sales[.]”).
14 Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015).
PDF page 9
- 9 -
Commission must examine what IRAS actually does in practice. When PJM’s Filing and proposed
tariff language are considered as a whole, the target of the Filing becomes clear: IRAS is an
unprecedented program that aims to interrupt service to specific retail customers that do not
comply with federally-approved resource procurement requirements prescribed by the PJM tariff
and directs state-regulated distribution utilities to implement PJM’s retail curtailment priorities.
PJM casts IRAS as a new wholesale service that retail customers can provide. But IRAS
is not a novel form of demand response; it is a framework for singling out retail customers for
forced service interruptions during tight grid conditions based on criteria established in a FERC-
jurisdictional tariff. Under IRAS, “end-use customer load” with a peak load of 50 MW or greater
that goes into service15 after PJM prescribed deadlines (i.e., New Large Loads) will be required to
bring capacity meeting PJM’s BYONC criteria or be deemed to be subject to interruption during
emergency conditions. In effect, IRAS:
• seeks to create a new interruptible retail customer class consisting of large load
customers that do not meet PJM’s BYONC requirements;16
• authorizes PJM to issue curtailment instructions during prescribed conditions to
compel Electric Distributors17 to reduce the load of these customers;18
• directs Electric Distributors to provide compensation to Eligible New Large Loads
whose load is curtailed pursuant to these directives equal to 50% of the Non-
Performance Charge Rate set out in the PJM tariff (unless the Eligible New Large
Load agrees to “accept in its retail rates” a lower sum);19 and
15 Filing, Transmittal Letter at 1, n.2 (defining “New Large Load” to include end-use customer load that is
either “a Large Load that goes into service after” the deadline prescribed by the tariff or “incremental load in-service
after [such deadline], that increases the existing end-use customer load at a single electrical site that, prior to such
incremental load, did not previously meet the definition of Large Load.”).
16 Id. at 69.
17 Electric Distributor is defined as a PJM member that owns or leases electric distribution facilities that are
used to provide electric distribution service to load within the PJM region or a cooperative or joint municipal agency
that has a member that owns electric distribution facilities used to provide electric distribution service to load within
the PJM region. PJM, Reliability Assurance Agreement Among Load Serving Entities in the PJM Region, Art. 1
(defining Electric Distributor).
18 Filing, Transmittal Letter at 74-75, 83-84.
19 Id. at 102.
PDF page 10
- 10 -
• directs Electric Distributors to impose charges on other customers to fund these
compensation payments.20
PJM has failed to provide a sufficient basis for the Commission to find that IRAS does not
regulate the terms and conditions of retail service in ways that go beyond the Commission’s
authority. FERC does not have any authority to exercise jurisdiction over the quality of service
that retail customers receive, the terms and conditions that retail customers must meet to avoid
interruption during emergency conditions, or the compensation paid to retail customers whose
service is curtailed. Each of these areas are matters that states have historically regulated pursuant
to their exclusive authority over the rates, terms, and conditions of retail service.
The extent to which IRAS targets matters within the jurisdiction of the states is readily
discernable by even a cursory review of the subject matters addressed by state laws and tariffs
governing retail service. For instance, state laws and tariffs within the PJM region recognize the
authority of state public utility commissions to establish the relative priority of retail customers for
service,21 require state electric utilities to implement curtailments in a manner that complies with
state law and regulation, establish interruptible service classes,22 determine eligibility for
participation in interruptible rate schedules,23 and establish credits and compensation for customers
20 Id., Att. A, Proposed Att. DD-4(X).
21 See, e.g., Va. Code § 56-250 (authorizing Virginia state corporation commission to establish plan
governing curtailment of retail customers during grid emergencies and shortages); 20 VAC5-300-20 (establishing
procedures for Virginia utilities to take during emergencies and establishing relative priority of residential,
commercial, and industrial customers); Ohio Administrative Code 4901:5-19 (recognizing right of Public Utility
Commission of Ohio to implement measures that fulfill “electric requirements for priority use by its consumers” and
reallocate or curtail supplies “among its consumers”).
22 See, e.g., PPL Electric Utilities Corp., General Tariff: Rules and Rate Schedules for Electric Service, Rate
Schedule LP-6 (Large Load Interconnections) (providing large load customers the option to voluntarily elect
“interruptible service . . . instead of firm service”).
23 See, e.g., Pub. Util. Comm’n of Ohio, In the Matter of the Application of Ohio Power Company for
Authority to Establish a Standard Service Offer Pursuant to R.C. 4928.143, In The Form Of An Electric Security Plan,
Opinion and Order, Case No. 23-23-EL-SSO at ¶¶ 105-109, 140-144 (Apr. 3, 2024) (approving interruptible power
tariff for customers that meet notice requirements and establishing demand credits).
PDF page 11
- 11 -
that interrupt their service.24 The service classification of retail customers, the curtailment priority
of different classes, and the consideration paid for these service interruptions are all familiar
components of state-regulated retail service and beyond the bounds of permissible FERC
regulation.
PJM attempts to justify its proposal by stating that it will not curtail specific end-use
customers directly, but will direct Electric Distributors25 to curtail these customers’ demand.26 But
the fact that PJM does not have authority to directly curtail retail customers merely reinforces that
PJM is attempting to exercise control over matters that are outside of its purview and beyond the
boundaries of the Commission’s jurisdiction. And the fact that PJM is attempting to do indirectly
what it cannot do directly is of no legal significance.27 The FPA leaves no room either for FERC
to directly regulate retail sales or approve regulations that would indirectly achieve this result.
PJM argues that IRAS is consistent with the Supreme Court’s determination in EPSA that
Order No. 745’s directive to regional transmission organizations (“RTO”) and independent system
operators (“ISO”) to pay demand response resources participating in the energy market the
locational price for energy did not intrude on the jurisdiction of the states.28 But the reasoning that
the Court employed in sustaining Order No. 745 in EPSA has no application to IRAS.
Importantly, EPSA upheld Order No. 745 based on the Court’s determination that Order
No. 745 merely established a rate for wholesale transactions and was confined solely to the rules
24 See, e.g., id.
25 DCC notes that it is unclear how PJM’s proposal would work in retail choice jurisdictions where
competitive retail suppliers—rather than the Electric Distributor—may be responsible for providing service to retail
customers.
26 Filing, Transmittal Letter at 86.
27 Hughes v. Talen Energy Marketing, LLC, 578 U.S. 150, 163 (2016) (“FPA leaves no room either for direct
state regulation of the prices of interstate wholesales or for regulation that would indirectly achieve the same result.”).
28 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 266 (2015).
PDF page 12
- 12 -
governing the wholesale markets.29 The same cannot be said of IRAS. To the contrary, PJM’s
tariff revisions seek to prescribe the amount paid to retail customers through their retail rates for
service interruptions implemented at PJM’s direction.30 And, in contrast to Order No. 745, the
effectiveness of PJM’s proposed framework depends on electric distributors issuing directives to
their retail customers to reduce demand31 and state regulatory authorities adopting retail tariffs that
align with the curtailment priorities set forth in the PJM tariff.32
The Court also noted that Order No. 745 was carefully crafted to preserve the jurisdiction
of the states by providing state regulators with the option of prohibiting retail customers from
offering demand response into the wholesale markets33 and FERC’s “justifications for regulating
demand response are all about, and only about, improving the wholesale market.”34 IRAS does
not provide state regulators with any such opt out. Regardless of the decisions made by individual
state regulators, PJM will continue to issue directives to electric distributors to curtail New Large
Load customers that do not comply with PJM’s BYONC requirements. And while the
justifications for Order No. 745 were all about the wholesale market, PJM acknowledges that IRAS
is intended to “establish load reduction priorities for retail customers”35 and encourage “states to
29 Id. at 282 (stating that “every aspect of the regulatory plan happens exclusively on the wholesale market
and governs exclusively that market’s rules”).
30 Filing, Att. A, Proposed Att. DD-4(X)(a) (stating that the rate for the provision of IRAS “shall be 50% of
the Non-Performance Charge Rate . . . unless any Eligible New Large Load elects to (i) accept in its retail rates a sum
less than 50% of the Non-Performance Charge Rate . . . or (ii) waive receipt in its retail rates any compensation for
the provision of” IRAS”) (emphasis added).
31 Id., Transmittal Letter at 26 (“Electric Distributors must execute PJM’s load reduction directives when
PJM issues an Interim Resource Adequacy Alert.”).
32 Id. at 3 (“PJM anticipates participating in efforts to develop standardized regulatory tools and model retail
tariff structures that individual state commissions may consider as they address the integration of new loads and
otherwise decide whether and how to act in response to the evolving federal wholesale landscape, inclusive of the
IRAS filing.”).
33 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 287 (“[T]he Rule allows any State regulator to prohibit
its consumers from making demand response bids in the wholesale market.”).
34 Id. at 282.
35 Filing, Transmittal Letter at 31.
PDF page 13
- 13 -
re-evaluate load reduction plans.”36 The objective of IRAS is clear: to compel state regulators to
modify their regulation of the retail market to conform to PJM policy.
Additionally, Order No. 745 established the rate that demand response providers would be
paid if they voluntarily elected to participate in the wholesale markets. The wholesale demand
response programs at issue in Order No. 745 did not compel retail customers to curtail their loads
involuntarily or state regulators to re-evaluate their retail curtailment programs. IRAS, in contrast,
targets individual retail customers that fail to comply with PJM’s BYONC requirements for
involuntary curtailment and seeks to ensure that states conform their curtailment policies to align
with the priorities established by the PJM tariff.
PJM attempts to avoid these jurisdictional issues by claiming that states retain discretion37
over how to shape their retail policies in response to IRAS and that it will be Electric Distributors
and state regulators that determine which retail customers actually are curtailed. PJM’s reasoning
misses the point. It is the role of the states—not PJM—to establish load reduction priorities for
retail service. Neither PJM nor FERC should be dictating retail curtailment rules, whether directly
or by establishing market rules intended to compel compliance.
Ultimately, IRAS does not offer states a genuine choice. For a state to ignore PJM’s
dictates would be to run the risk that reliability events could result in broader service disruptions
affecting other customers within its jurisdiction rather than a more targeted curtailment of
individual large load customers. Offering states the choice between compliance and indiscriminate
curtailment of retail customers is well past the point at which “pressure turns into compulsion” and
36 Id. at 3.
37 Notwithstanding PJM’s claims about the flexibility afforded to state authorities, a decision by FERC to
assert jurisdiction over, and approve, IRAS would raise serious legal questions about what discretion states have to
deviate from the terms of the filed rate approved by the Commission. See Nantahala Power & Light Co. v. Thornburg,
476 U.S. 953, 966 (1986) (once FERC “sets a rate, a state may not conclude in setting retail rates that the FERC-
approved wholesale rates are unreasonable”).
PDF page 14
- 14 -
undermines the cooperative federalism embodied in the FPA.38
Even if states were given a meaningful choice, PJM’s repeated references to the discretion
of the states as to whether to comply with IRAS highlights a fundamental flaw in PJM’s proposal.
PJM cannot simultaneously maintain that states retain meaningful discretion over the
implementation of retail curtailments and assume that IRAS will operate exactly as PJM describes.
If states are genuinely free to establish different curtailment priorities, PJM cannot guarantee that
the customers it seeks to target through IRAS will actually be curtailed or that the proposal will
achieve its objectives.
Nor can PJM ensure that new large load customers that comply with PJM’s BYONC
requirements will avoid service interruption. For instance, an Eligible New Large Load customer
that procures new capacity to meet its load may still experience service disruptions during
emergency conditions if the relevant state authorities and Electric Distributors do not adopt
curtailment priorities that align with the IRAS framework. The lack of certainty that a customer
that complies with PJM’s BYONC requirements will avoid service interruptions will undermine
one of the primary justifications for the IRAS framework: to provide an incentive for new large
load customers to support the development of new capacity required to meet their needs.
PJM states that IRAS is merely an example of the “federal regime helping to effectuate
state decisions associated with the rates, terms, and conditions of retail service.”39 But it is quite
the opposite. Rather than accommodating state decisions—as the proposal DCC advanced in the
PJM stakeholder process would have—PJM asks the Commission to approve a tariff framework
designed to ensure that retail customers are curtailed in a manner that aligns with PJM’s
38 Nat’l Fed’n of Indep. Bus. v. Sebelius, 567 U.S. 519, 580 (2012) (internal citations and quotations omitted).
39 Filing, Transmittal Letter at 3.
PDF page 15
- 15 -
preferences, priorities, and requirements. If Congress had intended to give FERC the authority to
determine the retail load priorities within 13 states and the District of Columbia then it would have
explicitly provided FERC with this authority in the FPA.40 But it did not. Instead, it explicitly
denied FERC any authority to exercise jurisdiction over the rates, terms, and conditions of retail
service, reserving these matters to the states.
PJM minimizes jurisdictional concerns by noting that the FPA’s drafters could not have
foreseen the resource adequacy impacts of data centers and technological advancements in
artificial intelligence.41 That may be true. But the drafters of the FPA did foresee a different risk:
that federal regulation of the electric industry could encroach upon the authority long enjoyed by
the states. Congress therefore drew a clear jurisdictional boundary, granting FERC authority over
wholesale sales and interstate transmission while reserving regulation of retail service to the states.
Implicit in this structure is the recognition that not all problems require a federal solution. The
novelty of today’s reliability challenges does not permit the Commission to disregard the
boundaries established by Congress.
40 West Virginia v. EPA, 597 U.S. 697, 716 (2022) (explaining that under the major questions doctrine, “courts
‘expect Congress to speak clearly if it wishes to assign to an agency decisions of vast economic and political
significance.’”) (quoting Utility Air Regulatory Group v. EPA, 571 U.S. 302 (2014)).
41 Filing, Transmittal Letter at 91.
PDF page 16
- 16 -
B.
IRAS Is Unjust, Unreasonable, Unduly Discriminatory, And Inconsistent
With Cost Causation Requirements
1.
Curtailing New Large Loads Before Requiring Demand Resources To
Perform Is Unjust And Unreasonable
The purpose of committing capacity through the PJM Reliability Pricing Model (“RPM”)
is to ensure that PJM has sufficient resources available to avoid the risk of supply interruptions.42
In the last two PJM Base Residual Auctions (“BRA”), Demand Resources were paid over a
combined $1.5 billion to reduce their demand when called upon by PJM to maintain reliability.43
Demand Resources are compensated at this level based on “the expectation that such resources
will be available to provide energy and reserves when called upon” just like other Capacity
Resources.44
If IRAS is approved, however, Demand Resources committed through the capacity market
will no longer be available to serve the needs of Eligible New Large Load customers. Specifically,
PJM’s proposed curtailment order following the adoption of IRAS would be as follows:
• PJM dispatches available generation and economic demand response;45
• PJM curtails non-firm export transactions associated with Capacity Resources;46
• PJM curtails new Non-Firm Contract Demand Service and Interim Network
Integrated Transmission Service;47
42 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply,
and Stimulating Investment To Support Durable Reliability at 14 (May 6, 2026), https://www.pjm.com/-
/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-
design.pdf. See also PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 520 (2026) (“Capacity resources are
purchased to meet the needs of transmission customers taking existing firm service, such as NITS.”).
43 See PJM 2028/2029 Base Residual Auction Report at 2-3, 5, 12 (July 14, 2026), available at:
https://www.pjm.com/markets-and-operations/rpm.aspx (showing 7,641 MW of Demand Response clearing at
$333.44 MW-day for 2027/2028 Delivery Year and 7,364 MW of Demand Response clearing at $325.00 MW-day
for 2028/2029 Delivery Year).
44 PJM Interconnection, L.L.C., 151 FERC ¶ 61,208, at P 99 (2015).
45 Filing, Att. C – Aff. of Christopher Pilong on behalf of PJM Interconnection, L.L.C. at ¶ 8. See also Filing,
Transmittal Letter at 78.
46 Id. at ¶ 9. See also Filing, Transmittal Letter at 78.
47 Id. at ¶ 12. See also Filing, Transmittal Letter at 78.
PDF page 17
- 17 -
• PJM curtails Eligible New Large Loads under IRAS;48 and, finally,
• PJM initiates Pre-Emergency Load Management Reduction Actions, including
mandatory reductions for Demand Response.49
In short, under PJM’s proposal New Large Loads that have not satisfied the BYONC requirements
will be curtailed before PJM calls on Demand Resources that have been paid to reduce their load.50
PJM has not demonstrated that it is just and reasonable to direct the curtailment of retail
customers prior to deploying Demand Resources that have been committed precisely to avoid such
service disruptions. The point of Capacity Resources and Demand Resources is that they will
provide capacity when called upon “to avoid periods of involuntarily firm load shed or
blackouts.”51 And the Commission has consistently found that paying resources, including
Demand Resources, for capacity but not expecting them to perform “threaten[s] reliable operation
of the system and forc[es] consumers to pay for capacity without receiving commensurate
reliability benefits” ultimately resulting in unjust and unreasonable rates.52 PJM’s IRAS proposal
reverses that relationship: PJM proposes to involuntarily curtail customers that continue paying
48 Id. at ¶ 13. See also Filing, Transmittal Letter at 78.
49 Id. at ¶ 14; PJM Manual 13: Emergency Operations § 2 (Revision 98; effective June 24, 2026)
(“Applicability: Any site registered in the PJM Demand Response program as a demand resource (a.k.a. DR) type that
needs 30, 60 or 120 minute lead time to make its reductions. These reductions are mandatory when dispatched during
the product availability window.”).
50 The relative curtailment priority of Eligible New Large Loads and Demand Resources also raises questions
about the efficacy of the IRAS framework. Under PJM’s proposal, a New Eligible Large Load would have a strong
incentive to become a Demand Resource, receive capacity revenues, and then be dispatched under PJM’s demand
response rules—after IRAS otherwise would have required it to curtail. In effect, a New Large Load customer could
move from paying for capacity and being curtailed prior to the deployment of demand response to receiving capacity
revenues and receiving a later curtailment priority simply by changing its wholesale market status.
51 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply,
and Stimulating Investment To Support Durable Reliability at 14 (May 6, 2026), https://www.pjm.com/-
/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-
design.pdf.
52 ISO New England, Inc., 147 FERC ¶ 61,172, at P 23 (2014).
PDF page 18
- 18 -
capacity charges while leaving Demand Resources that have been committed to provide capacity
undeployed.
The only explanation PJM has provided to justify its proposal is that Demand Resources
are curtailed as part of the Pre-Emergency Load Management Reductions when a North American
Electric Reliability Corporation Energy Emergency Alert Level 1 (“EEA1”) is established.53 And
because Pre-Emergency Load Management Reductions indicate that the “region is approaching a
capacity event,” PJM says that it is “[t]hus, … appropriate for PJM to direct Electric Distributors
to reduce those New Large Loads that have failed to cover their capacity obligations before relying
on Demand Resources, through Pre-Emergency Load Management Reductions Actions, to
maintain reliability.”54
While it is obvious that requiring Eligible New Large Loads to curtail would be helpful to
avoid Pre-Emergency Load Management Reductions Actions, it does not follow that curtailing
retail customers through IRAS is an appropriate mechanism to prevent Demand Response from
being called upon to avoid Pre-Emergency Load Management Reductions Actions. If PJM is
concerned that calling upon Demand Resources will trigger a Pre-Emergency Load Management
Reduction or EEA1 earlier than it believes is warranted, it should revise its curtailment procedures
to allow it to require Demand Response to perform without triggering a Pre-Emergency Load
Management Reduction or EEA1. Indeed, PJM has previously recognized that it needed to revise
its definition of “Emergency Action” to avoid triggering a Performance Assessment Interval
(“PAI”) when it called upon Demand Resources:
[I]nclusion of load management resources, which are generally committed Demand
Resources in the capacity market, in the definition of Emergency Action is not
representative of a capacity emergency. That is because Pre-Emergency Load
53 Filing, Transmittal Letter at 79.
54 Id. (emphasis in original).
PDF page 19
- 19 -
Response Program, like all other committed Capacity Resources, should be able to
support the reliability needs of the PJM Region regardless of whether there is a
capacity emergency. Consequently, deployment of pre-emergency load
management reduction should not, in and of itself, trigger a PAI.55
If PJM is similarly concerned that it cannot call upon Demand Resources before triggering a Pre-
Emergency Load Management Reduction or EEA1, then it should revise its curtailment procedures
so that Demand Resources can be relied upon to perform the capacity function they are paid for.
But PJM should not be permitted to only rely on Demand Resources after it has issued directives
calling for the curtailment of retail load.
2.
Curtailing Load That Pays For Demand Response Before Calling Upon
Demand Response Is Inconsistent With Cost Causation Requirements
The Commission and the courts have recognized that the FPA’s “just and reasonable”
standard incorporates a cost causation principle.56 The cost causation principle requires that “all
approved rates reflect to some degree the costs actually caused by the customer who must pay
them” and prohibits the Commission from approving a rate scheme that will result in one group of
customers being required to subsidize the provision of service to a different group of customers.57
The cost causation principle can be considered “a matter of making sure that burden is matched
with benefit.”58
DCC and its members are committed to paying for the costs associated with integrating
data centers into the grid, including the incremental capacity costs associated with providing them
firm, reliable service. DCC is also a strong proponent of BYONC mechanisms that facilitate
55 PJM Interconnection, L.L.C., Docket No. ER23-1996-000, Proposed Revisions to Prospectively Refine
the Definition of Emergency Action, Request for Shortened Comment Period and Expedited Commission Action at 8
(May 30, 2023).
56 See, e.g., City of Lincoln v. FERC, 89 F.4th 926, 930 (D.C. Cir. 2024).
57 Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1050 (D.C. Cir. 2022) (quoting Black Oak
Energy, LLC v. FERC, 725 F.3d 230 (D.C. Cir. 2013)).
58 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).
PDF page 20
- 20 -
pathways to power for data centers and other large loads while adding capacity to the grid for the
benefit of all customers. But it is nevertheless important that costs imposed on large loads be
consistent with the cost causation principle.
PJM’s IRAS proposal will result in Eligible New Large Load customers incurring the
burden of paying Demand Resources for capacity for which these large loads will not receive a
corresponding benefit. Under PJM’s proposal, NITS customers serving Eligible New Large Loads
will continue to be responsible for paying Locational Reliability Charges reflecting the costs of
capacity procured through the BRA, including Demand Resources—costs that ultimately will be
passed through to Eligible New Large Load customers.59 Yet, these NITS customers and the
Eligible New Large Loads that they serve will no longer benefit from the Demand Resources
committed through the capacity market, as these resources will only be called upon to perform
after PJM issues a directive to these customers to curtail. Requiring NITS customers and their
retail customers to pay the costs of capacity that only will be deployed after their service has been
curtailed is inconsistent with cost causation requirements.
PJM appeared to recognize as much in its stakeholder process. Specifically, in its June 10,
2026 presentation to stakeholders PJM stated that “[l]oads that are subject to Connect and Manage
[now known as IRAS] are not assessed capacity charges” and that it “will adjust EDC RPM Load
Obligations to reflect UCAP associated with new Large Loads assigned Connect & Manage.”60
Yet, PJM’s Filing in this proceeding is devoid of any tariff revisions that would result in Eligible
New Large Loads subject to IRAS being exempt from capacity charges. PJM has not proposed to
59 See PJM Manual 18: PJM Capacity Market § 9.2.1 (Revision 62; effective Dec. 17, 2025) (“Each LSE that
serves load in a PJM Zone or load outside PJM using PJM resources (Non-Zone Network Load) during the Delivery
Year is responsible for paying a Locational Reliability Charge equal to their Daily Unforced Capacity Obligation in a
Zone times the applicable Final Zonal Capacity Price for that Delivery Year.”).
60 PJM CIFP–RBP / Connect and Manage - Stage 3 (June 10, 2026 – Meeting Materials), Connect & Manage
Package Updates at 40 (June 10, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp.
PDF page 21
- 21 -
revise provisions of its tariff addressing the Locational Reliability Charge61 or the determination
of Unforced Capacity Obligations.62 Moreover, PJM’s Filing does not include any mention of
exempting Eligible New Large Loads from a capacity charge other than its cursory statement that
“[t]he net result” of the compensation that may be paid to Eligible New Large Loads subject to
curtailment “is a reduced capacity charge for Eligible New Large Loads.”63 But even if this
compensation was intended to offset the capacity costs Eligible New Large Loads will pay for, it
is only a partial offset. And, as PJM concedes, there is no guarantee that such compensation will
even be awarded to Eligible New Large Loads.”64
The cost causation principle “generally calls for giving the same treatment to new and
continuing customers, [w]here ‘all customers cause the incurrence of the costs . . . , whether by
adding or merely continuing their usage[.]”65 But this principle is founded upon the understanding
that all customers contributing to the costs will be given an equal opportunity to enjoy the
corresponding benefits. It is inconsistent with cost causation to force Eligible New Large Loads
to bear the cost of Demand Resources that will not be used to provide them with service. And if
Eligible New Large Loads are to bear the costs of these capacity resources, then Demand
Resources committed to provide capacity should be deployed prior to interrupting service to
Eligible New Large Loads.
61 PJM, Reliability Assurance Agreement Among Load Serving Entities in the PJM Region § 7.2 (“[E]ach
Party shall pay, as to the loads it serves in each Zone during a Delivery Year, a Locational Reliability Charge for each
such Zone during such Delivery Year. The Locational Reliability Charge shall equal such Party’s Daily Unforced
Capacity Obligation in a Zone, as determined pursuant to RAA, Schedule 8, times the Final Zonal Capacity Price for
such Zone, as determined pursuant to Tariff, Attachment DD.”).
62 PJM, Reliability Assurance Agreement Among Load Serving Entities in the PJM Region, Schedule 8.
63 Filing, Transmittal Letter at 104.
64 Id. at 106 (stating that “how this wholesale rate is used to compensate for IRAS and how it is used to collect
monies for such compensation will be left to the Electric Distributors that directed the specific load reductions to
implement IRAS, consistent with their state-approved program…”).
65 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (2014) (citations omitted).
PDF page 22
- 22 -
To be clear, data centers are committed to paying their fair share of the costs associated
with procuring sufficient capacity to maintain reliability in PJM. Indeed, the DCC and the data
center industry generally have been vocal proponents of proposals that allow data centers to bring
their own capacity to mitigate the potential resource adequacy impact of large load integration.
But where data centers in fact pay for capacity and that capacity is available to be called upon to
preserve reliability, it is unjust and unreasonable for PJM to instead curtail data centers and other
large loads rather than requiring paid-for capacity to perform.
3.
PJM’s Proposal Will Require Customers In Zones With Large Load
Customers To Subsidize The Costs Of Capacity For The PJM Region
PJM’s IRAS proposal also presents a separate and distinct cost causation issue: customers
located in electric distribution service areas where large loads are interconnecting will be required
to subsidize the cost of capacity for the broader PJM region. Under PJM’s proposal, Eligible New
Large Loads will contribute to paying a share of Locational Reliability Charges and, thus, reduce
the capacity costs borne by other customers across the PJM region. PJM then proposes to offset
these capacity costs by requiring Electric Distributors to compensate Eligible New Large Load
customers that are curtailed under IRAS. However, the costs of funding these payments to Eligible
New Large Loads will not be allocated across the region. Instead, PJM’s proposal contemplates
that Electric Distributors will be required to fund these payments by imposing additional charges
on the customers within their service territory. The net result of this framework is that customers
in service territories with large load growth effectively will be required to subsidize rate reductions
for customers in other portions of the PJM footprint.66
PJM’s proposed payment scheme for funding payments to Eligible New Large Loads
66 Filing, Transmittal Letter at 101. Indeed, PJM says that the rate paid to large loads for curtailment under
IRAS by electric distributors is “intended to be conjoined with retail rates.” Filing, Transmittal Letter at 104.
PDF page 23
- 23 -
violates cost causation requirements. As the courts have recognized, the cost causation principle
prohibits the Commission from approving a rate scheme that requires one set of customers to
subsidize the provision of service to others.67 In this case, the capacity-related benefits produced
by Eligible New Large Loads would be shared across the PJM region through lower Locational
Reliability Charges, but the costs of compensating those loads for IRAS curtailments would be
imposed on customers in the host Electric Distributor’s service territory. The result is a mismatch
between costs and benefits: customers in areas experiencing large load growth are required to fund
a regional benefit enjoyed by customers throughout PJM. Cost causation principles do not permit
such cross subsidization.
4.
Providing Inferior Service At The Same Price Is Unjust, Unreasonable,
and Contrary To Cost Causation Principles
PJM also has not demonstrated that charging NITS customers serving Eligible New Large
Loads the same transmission rates as other NITS customers is just, reasonable, and not unduly
discriminatory or preferential. The Commission repeatedly has recognized that the transmission
rates imposed on customers must reflect the firmness of the service provided.68 In Order No. 888,
the Commission recognized that “non-firm transmission prices should reflect the interruptibility
of the service and should promote efficient use of the transmission system[.]”69 More recently,
the Commission rejected the PJM Transmission Owner’s proposal to set the rate for Non-Firm
Contract Demand transmission service equal to the rate for Firm Point-to-Point Service because it
67 El Paso Elec. Co. v. FERC, 76 F.4th 352, 363 (5th Cir. 2023).
68 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 406 (2026) (stating that “rates should vary based
on the quality of the transmission service”).
69 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub.
Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036
(1996), clarified, 76 FERC ¶ 61,009 (1996), order on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, at
30272 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82
FERC ¶ 61,046 (1998), aff’d in part and remanded in part sub nom. Transmission Access Policy Study Grp. v. FERC,
225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
PDF page 24
- 24 -
found “the rates should vary based on the quality of the transmission service.”70 Under the IRAS
proposal, NITS customers subject to interruption under IRAS would be required to pay the same
transmission rates as other NITS customers despite receiving inferior service.
PJM cannot have it both ways. If NITS customers serving Eligible New Large Loads pay
the same rates as other NITS customers, then they should receive a comparable level of service
and be curtailed at the same time as other NITS customers. Alternatively, if PJM is going to
subject NITS customers serving Eligible New Large Loads to interruption ahead of other NITS
customers, then the rates for these customers must reflect the lower quality of service being
provided. PJM’s proposal to offer less service at the same price is unjust, unreasonable, and
contrary to cost causation requirements.
5.
Excluding New Large Loads From The VRR Curve Will Undermine
Efforts To Maintain Reliability
At a time when PJM needs additional capacity to meet resource adequacy needs within the
region, PJM’s proposal to exclude New Large Loads that do not meet BYONC requirements from
the VRR Curve beginning with the 2029/2030 Delivery Year is counterproductive and
misguided.71 The VRR Curve is intended to “produce accurate market signals that will encourage
appropriate capacity investment and achieve an adequate level of reliability.”72 But the VRR
Curve and the market as a whole can only send the price signals necessary to attract new
investment if they accurately reflect supply-demand conditions within the PJM region. By
excluding Eligible New Large Loads from consideration in the capacity market, PJM’s proposal
will result in a capacity market construct that will produce market prices and results that are
70 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 406 (2026).
71 Filing, Transmittal Letter at 23.
72 PJM Interconnection, L.L.C., 167 FERC ¶ 61,029, at P 19 (2019).
PDF page 25
- 25 -
untethered from market fundamentals within the PJM region.
The fact that excluding Eligible New Large Loads from the VRR curve will mute
investment signals and undermine reliability has been acknowledged by PJM. In the stakeholder
process, PJM explained that it was important to model loads subject to IRAS in the RPM because
“[i]ncluding Connect and Manage [now known as IRAS] in the RPM Auction continues to provide
price signals for new investment while providing an incentive for New Large Load to BYONC
through new supply or DR/DER.”73 Indeed, there would be no way for the market to send a price
signal that additional supply is needed in the region if the market treats new demand as if it did not
exist. The PJM Board, however, modified the IRAS proposal to remove Eligible New Large Loads
from the VRR Curve on the basis that “[i]ncremental new Large Loads relative to the forecast
utilized for the 2028/2029 BRA will be excluded from the forecast used in future RPM auctions
for the 2029/2030 Delivery Year and beyond unless and until there are new supply resources
offered into an RPM auction in sufficient quantity to cover the new Large Load.”74 The PJM
Board cannot expect new supply resources to appear if the price signals sent by the market do not
reflect—as will be the case under PJM’s IRAS proposal—the actual load that must be served in
the region.
While PJM’s proposal may temporarily suppress capacity prices, it will do so based on an
utterly inaccurate view of the actual demand for capacity in PJM. And if the RPM does not
accurately reflect demand, it is hard to understand how PJM expects the RPM to send price signals
that will ensure the entry of new resources capable of meeting the region’s needs. As the
73 PJM CIFP – RBP / Connect and Manage - Stage 3 (May 27, 2026 – Meeting Materials), Connect and
Manage PJM Package at 29 (May 27, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp.
74 PJM Post CIFP Workshop - Technical Overview, PJM Board - CIFP Framework for Service During
Periods of Insufficient Resource Adequacy - Executive Summary (July 30, 2026), available at:
https://www.pjm.com/committees-and-groups/cifp-rbp.
PDF page 26
- 26 -
Commission observed, a capacity market should “provide price signals that guide the orderly entry
and exit of capacity resources, result in the selection of the least-cost set of resources that possess
the attributes sought by the markets, provide price transparency, shift risk as appropriate from
customers to private capital, and mitigate market power.”75 But a capacity market that does not
send price signals that accurately reflect market fundamentals cannot achieve these objectives.
6.
PJM’s Proposal To Provide Inferior Service To NITS Customers
Serving Eligible New Large Loads Is Unduly Discriminatory
IRAS is not merely a change to PJM’s emergency operating procedures. IRAS degrades
one of the defining characteristics of NITS—its curtailment priority—for a subset of customers.
NITS customers historically have been entitled to receive “firm transmission service over the
Transmission System for the delivery of capacity and energy from its designated Network
Resources to service its Network Loads on a basis that is comparable to each Transmission
Owner’s use of the Transmission System to reliably service its Native Load Customers.”76 When
curtailments are required to maintain reliability, the transmission provider is required to curtail
NITS customers on a non-discriminatory and pro rata basis consistent with the treatment of native
load and firm point-to-point customers.77
This will no longer be the case if IRAS is accepted. In practical terms, IRAS creates a
form of second-class NITS customers. NITS customers serving Eligible New Large Loads will
continue purchasing NITS and paying the same transmission and capacity charges as other firm
customers. Yet, these NITS customers and the Eligible New Large Loads that they serve will be
deprived of one of the principal benefits of NITS: protection from service interruptions and
75 ISO New England Inc., 162 FERC ¶ 61,205, at P 21 (2018).
76 PJM Tariff, Part III § 28.1.
77 PJM Tariff, Part II § 13.6; id., Part III § 33.5.
PDF page 27
- 27 -
curtailment on a basis comparable to other firm uses of the system.78 PJM cannot charge customers
for firm service while reserving the right to treat them as interruptible customers when reliability
conditions deteriorate.
The FPA prohibits public utilities from engaging in any undue discrimination or granting
any undue preference or advantage in providing transmission service.79 Undue discrimination or
preference occurs, as both the courts and the Commission have held, when similarly situated
customers are treated differently “for no good reason.”80 To justify treating customers differently,
the prohibition on undue discrimination requires that the utility proposing disparate treatment
demonstrate that there are “specific factual differences” between the customers that justify the
specific rates, terms, and conditions imposed by the utility.81
PJM does not deny that its proposal is discriminatory. Instead, it attempts to justify the
differences in treatment by pointing to the Commission’s decision to require PJM to revise its tariff
to create a definition for large loads and cites to general statements by the Commission that large
loads are unique and pose specific challenges to the transmission system.82 But PJM cannot justify
the disparate treatment proposed in this case by making general references to the unique challenges
posed by large load integration. The issue is not merely whether there are some differences
between the classes at issue; but whether there are differences that are “material to the inquiry at
hand” that justify the specific differences in treatment that are being proposed.83
78 Filing, Transmittal Letter at 94 (stating that NITS customers serving Eligible New Large Load customers
will “be asked to reduce load prior to other NITS customers in accordance with the Interim Resource Adequacy
Service they may be asked to provide”).
79 16 U.S.C. § 824d(b).
80 Consol. Edison Co. of N.Y., Inc., 45 F.4th 265, 282 (D.C. Cir. 2022); State Corp. Comm’n of Kan. v. FERC,
876 F.3d 322, 335 (D.C. Cir. 2017).
81 See, e.g., Pub. Serv. Co. of Ind. v. FERC, 575 F.2d 1204, 1212 (7th Cir. 1978).
82 Filing, Transmittal Letter at 96.
83 N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018). See Basin Elec. Power Cooperative,
188 FERC ¶ 61,132, at PP 95-96 (2024).
PDF page 28
- 28 -
PJM has failed to meet its burden in this case. As an initial matter, PJM’s suggestion that
FERC has granted transmission providers carte blanche to discriminate against large load
customers because of the characteristics of these customers is simply incorrect. It is true that the
Commission has required PJM to revise its tariff to include a definition of large load. But the
Commission also has sought to create new pathways for large loads to come online while
protecting customers and maintaining reliability, including encouraging PJM and other
transmission providers to revise their tariffs to create new transmission service products that better
align with the characteristics of large load customers, create new interim pathways for the
integration of large load customers and new generation capacity, and provide these customers with
greater flexibility to calibrate their use of the transmission system to meet their needs.84 The notion
that the Commission has found that large load customers inherently are less deserving of firm,
predictable service is incorrect and unsupported by Commission precedent.
Additionally, PJM’s justification fails to account for the fact that IRAS will result in
Electric Distributors serving large load receiving very different treatment based on the timing of
when the load is placed into service. Under IRAS, two Electric Distributors purchasing NITS to
serve loads of comparable size and paying the same rate will receive fundamentally different
services based on when their retail customers were placed into service. For instance, an Electric
Distributor that takes NITS to serve a 100 MW large load customer that is placed into service on
May 31, 2027 will not be interrupted during an emergency until PJM initiates a manual load dump
action after all capacity resources have been exhausted. An Electric Distributor who takes NITS
to serve a 100 MW large load customer that is placed into service one day later, on June 1, 2027,
84 See, e.g., PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (directing changes to the PJM
tariff to better account for the characteristics of large load customers).
PDF page 29
- 29 -
will not be guaranteed this same level of service unless they demonstrate that the retail customer’s
load is supported by new capacity complying with PJM’s BYONC requirements.
The arbitrary nature of IRAS becomes especially apparent when applied to facilities with
a load ramp. Two otherwise identical MW of the same facility could be subject to different
curtailment priorities solely because one increment of load came online before PJM’s cutoff date
and the other came online after.85 Such vintage-based discrimination does not reflect any
difference material to reliability or resource adequacy and cannot justify the disparate treatment at
issue here.
Nor has PJM demonstrated that the timing of when load has come online is a legitimate
basis for discrimination. Existing resources, like new resources, contribute to the need for
capacity86 and PJM has not explained why existing customers should receive preferential
treatment. IRAS appears premised on the assumption that New Large Load customers solely are
responsible for recent supply shortfalls in the BRA. But there are multiple factors that have
contributed to the supply-demand balance within the PJM region, including the retirement of
existing generation resources, the slow pace of new entry, and load growth within the region.87
PJM offers no evidence that a MW of demand imposes different resource adequacy impacts based
solely on when the demand first takes service. Nor does PJM explain why new customers should
85 As noted above, PJM proposes to define New Large Load as end-use customer load that is either a Large
Load that goes into service after June 1, 2027 or incremental load in-service after this deadline that increases the
existing end-use customer load at a site that did not previously meet the definition of Large Load. Filing, Transmittal
Letter at 1, n.2. Although PJM’s proposed definition of New Large Load is ambiguous, DCC understands that PJM
intends to subject any increment of load placed in service by a large load customer after the deadline to IRAS unless
the increment is supported by capacity meeting PJM’s BYONC requirements. However, DCC believes that the
Commission should require PJM to clarify the scope of its proposal and its application to customers with load ramp
periods that extend beyond the deadlines prescribed in the PJM tariff.
86 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).
87 See PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained
Supply, and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026), https://www.pjm.com/-
/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-
design.pdf.
PDF page 30
- 30 -
bear the reliability impact of generation retirements or a broken interconnection process. PJM’s
proposal to afford less favorable treatment to customers merely because they are “new” is unduly
discriminatory and should be rejected.
In short, PJM’s proposal to afford less favorable treatment to NITS customers serving
Eligible New Large Loads is unduly discriminatory and preferential. NITS customers serving
Eligible New Large Loads are similarly situated to other NITS customers: they have reserved firm
transmission to allow them to meet their supply obligations, pay the same transmission rates as
other NITS customers, and will pay the costs of capacity that has been committed through the
RPM to maintain reliability. Yet, IRAS will result in NITS customers serving Eligible New Large
Loads being afforded less favorable treatment than other NITS customers. And PJM’s vague
references to the unique characteristics of large customers are insufficient to justify the arbitrary
differences in treatment under the IRAS proposal.
C.
IRAS Fails To Account For Existing Contractual Arrangements And Reliance
Interests
Although PJM is permitted to make filings under FPA Section 205 to change its market
rules, in evaluating these changes FERC must be cognizant that existing market rules “may have
‘engendered serious reliance interests that must be taken into account’”88 and “‘assess whether
there were reliance interests’ in the prior rule, determine whether those interests ‘[are] significant,’
and weigh them ‘against competing policy concerns.’”89
PJM’s proposal to curtail a subset of retail customers that do not bring their own capacity
represents a fundamental shift in how PJM’s markets have functioned for the duration of its
existence. For decades new loads in the PJM region were permitted to interconnect and obtain
88 Encino Motorcars, LLC v. Navarro, 579 U.S. 211, 212 (2016).
89 Solar Energy Indus. Ass’n. v. FERC, 80 F.4th 956, 980 (D.C. Cir. 2023) (quoting DHS v. Regents of Univ.
of Cal., 140 S. Ct. 1891, 1914 (2020)); Capital Power Corp. v. FERC, 156 F.4th 644, 653 (D.C. Cir. 2025).
PDF page 31
- 31 -
service based on the same rates, terms, and conditions that were afforded to all other customers.
Service to load in PJM was not conditioned on such load bringing its own new capacity. PJM’s
IRAS proposal drastically alters the ability of certain loads to obtain reliable service in PJM by
limiting New Large Loads to receiving an inferior service until they procure their own new
capacity. PJM proposes these significant structural changes without any transition mechanism or
even acknowledging the potential impact on customers’ investment decisions.
PJM’s proposal will undermine the settled expectations of New Large Loads that have
made investment decisions and entered into contracts based on their ability to receive firm service
consistent with long-standing market rules and retail requirements. As the Commission has
acknowledged, Large Loads have entered into binding contractual obligations and made
significant investments in reliance on the ability to obtain reliable service within the PJM region
based on its longstanding rules.90 These arrangements include entering into energy supply and
transmission service agreements, executing leases with data center tenants, obtaining real property
interests, posting security for the construction of line extensions and other physical infrastructure,
and entering into financing agreements necessary for the construction of their facilities. PJM’s
proposal will undermine the economic assumptions underpinning these arrangements by forcing
New Large Loads to accept less reliable service—which may not align with the contractual
commitments made to their tenants—or incurring significant new costs to ensure that they receive
the same level of firm service that historically has been available.
90 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at P 5 (2026) (“We recognize that large loads, including
data centers, are actively working with transmission owners and other relevant entities to interconnect to, and to take
service from, the transmission system. We appreciate that different large loads are currently at different stages of that
process. We also understand that large loads and Eligible Customers taking transmission service on behalf of large
loads are negotiating, entering into, and/or have executed various agreements related to interconnecting to the
transmission system and/or the provision of transmission service.”).
PDF page 32
- 32 -
The disruption from IRAS will not be limited only to New Large Loads that first place their
facilities into service after June 1, 2027 (or subsequent deadlines established by PJM). IRAS also
appears to extend to incremental load placed in service by an existing customer after this date. In
practice, this means that IRAS will extend to data center customers that have placed their existing
facilities into operation but that have load ramp schedules that extend beyond June 1, 2027. If
IRAS is approved, these customers will now face the prospect that a portion of their loads will be
deemed interruptible unless they comply with PJM’s BYONC requirements.
In some cases, it simply will be too late for large load customers to revisit their investment
decisions or rewrite contracts that were entered into years prior. Even if a data center has some
flexibility to renegotiate existing leases with their tenants, it would have to attempt to renegotiate
these arrangements without certainty regarding how IRAS will be implemented, how relevant state
authorities plan to address IRAS, or when the data center will be able to guarantee firm service for
its tenants. The significant uncertainty that would be created by approval of IRAS has the potential
to create new obstacles to the completion of data center projects that have been under development
for years.
Moreover, IRAS establishes what is effectively a less than 10-month window for New
Large Loads to obtain their own new capacity to avoid curtailment. As the Commission is well
aware91 and as PJM’s own documented struggles with bringing new resources online
91 See, e.g., PJM Interconnection, L.L.C., 190 FERC ¶ 61,084 (2025) (Comm’r Rosner and Phillips,
concurring at P 2) (“PJM’s legacy interconnection process is overwhelmed by the volume of requests to connect new
generation and storage, causing the typical wait time in PJM’s queue to exceed five years. While long overdue, PJM’s
transition away from a legacy serial process includes the unfortunate feature of pausing study of all new
interconnection requests while PJM implements its new, faster process.”).
PDF page 33
- 33 -
demonstrate,92 this timeline does not provide a realistic opportunity for New Large Loads to meet
the BYONC requirements and avoid curtailment. The result will be a significant disruption to
nearly all large load projects with a post-June 1, 2027 in-service date that is likely to threaten the
viability of many projects that are essential for maintaining the nation’s competitive edge in the
global economy.
PJM’s implementation timeline for IRAS and failure to include a transition mechanism is
even more alarming given that many of the regulatory structures PJM acknowledges that states
must adopt to give effect to IRAS have yet to even be proposed.93 While certain state commissions
like the VA SCC may have commenced efforts to establish a regulatory scheme that is consistent
with IRAS,94 such efforts have not been mirrored by most of the PJM state commissions. As a
result, New Large Loads will be forced to scramble to comply with an entirely new service
paradigm in PJM while the rules necessary for implementing IRAS in their relevant states are still
being developed. Undermining the settled expectations of large load customers will alone present
a significant challenge to the ability of large load customers to move forward with their projects,
92 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply,
and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026), https://www.pjm.com/-
/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-
design.pdf. (“Construction timelines have doubled. A decade ago, the market’s three-year forward procurement
horizon was calibrated to the development timeline of the market’s reference technology. Today, a new natural gas
turbine plant – the reference technology for the capacity market – requires at least four years under optimistic
assumptions from financial investment decision to commercial operation, due to supply chain constraints on major
equipment (gas turbines, step-up transformers), extended permitting and interconnection timelines, and larger project
scale.”).
93 Filing, Transmittal Letter at 86-87 (“PJM will not direct specific LSEs and/or specific customers of LSEs—
including specific Large Loads—to reduce their load and/or switch to on-site backup resources. Those decisions
would be worked out through revised state retail tariffs.”) (emphasis in original).
94 Id. at 88 (citing Letter of Chair of Virginia State Corporation Commission, Kelsey Bagot and President
and CEO of Data Center Coalition, Josh Levi to Ms. Paula Conboy, Chair of PJM Board of Managers, and Mr. David
Mills, President and CEO of PJM Interconnection, L.L.C. at 2 (June 30, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-written-comments---va-scc-and-data-center-
coalition.pdf).
PDF page 34
- 34 -
but disrupting their settled expectations and making them plan for a service paradigm in which the
rules are still being developed presents a challenge of a different magnitude.
PJM’s proposal to subject a subset of retail load to mandatory curtailments represents a
stark departure from the historic paradigm in which customers were able to obtain reliable service
on the same rates, terms, and conditions as all other customers. While DCC supports BYONC
requirements, such requirements must be implemented on a timeframe that provides large loads a
reasonable opportunity to comply. The fact that PJM has proposed this departure from its prior
rules without including a transition mechanism as part of its proposal or even considering the
reasonable reliance interests of large loads further warrants rejection of the Filing by the
Commission.
D.
The Commission Should Reject IRAS Or Impose A Meaningful Transition
Mechanism
DCC urges the Commission to issue an order rejecting IRAS while encouraging PJM to
pursue alternative pathways that better align with the jurisdictional divide established by the FPA.
As noted above, DCC believes that the objectives underlying IRAS can be achieved by allowing
states to take the lead in establishing interruptible retail service schedules while PJM modifies its
operational practices to accommodate the choices of states within its footprint. For that reason,
DCC believes that any order in this proceeding rejecting IRAS should encourage PJM to work
with states to pursue a framework that respects the authority reserved to the states under the FPA
while protecting residential customers from service disruptions during emergency conditions.
Alternatively, if the Commission determines based on the record in this proceeding that
PJM’s emergency procedures must be reformed immediately, then it should initiate a Section 206
proceeding to determine how PJM’s emergency procedures can be modified to mitigate reliability
risks without encroaching on state jurisdiction over the rates, terms, and conditions of retail
PDF page 35
- 35 -
service. While DCC believes that any effort to modify the curtailment priority of retail customers
must be led by the states, a Section 206 proceeding would provide the Commission and other
parties opportunities to further explore what changes can be made to the wholesale market to
further mitigate reliability risks.
Finally, even if the Commission is inclined to approve IRAS, it should direct PJM to
modify its proposal to establish a meaningful transition mechanism that avoids disrupting existing
contractual arrangements and investment decisions, and provides large load customers and the
states a reasonable implementation timeline. Among other things, any transition mechanism
should limit the application of IRAS in a manner that respects existing contracts and investment
decisions (e.g., exempting large load customers that already have entered into contracts for retail
service prior to the implementation date of IRAS). The Commission also should direct PJM to
delay implementation of IRAS until June 1, 2028 to provide new large loads a reasonable amount
of time to procure new capacity before they are subject to IRAS and to provide state authorities
sufficient time to modify their retail policies as necessary to account for the IRAS framework.
III.
MOTION TO INTERVENE
DCC respectfully moves to intervene in this proceeding. DCC is the membership
organization for the U.S. data center industry, representing leading data center owners and
operators that develop, operate, and maintain data center infrastructure and teams across the
country.95 DCC members operate data centers that constitute significant loads within the PJM
95 The DCC is a membership organization of leading data center owners and operators. Public testimony and
written comments submitted by DCC do not necessarily reflect the views of each individual DCC member. A list of
current DCC members is accessible at https://www.datacentercoalition.org/members.
PDF page 36
- 36 -
region and DCC has been an active stakeholder in regional efforts to ensure reliability, enable new
generation, and discipline load forecasts.
DCC’s member companies provide the essential digital infrastructure that underpins the
modern economy and supports critical public services, including cloud computing, artificial
intelligence, emergency response systems, and public safety operations. From 2017 to 2023, the
data center industry contributed $3.5 trillion to U.S. GDP. As the industry unlocks unprecedented
economic opportunities across the country and in the PJM region, supporting affordability is a
foundational priority for DCC members and the communities they serve. DCC advocates for grid
reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate
responsible load growth, support the development of new generation, and enhance grid resilience
system-wide without imposing undue costs on existing ratepayers.
For the above reasons, DCC has a substantial interest in the outcome of this proceeding
that cannot be represented adequately by any other participant to this proceeding. DCC’s
intervention is in the public interest and its motion for leave to intervene in this proceeding should
be granted.
PDF page 37
- 37 -
IV.
CORRESPONDENCE AND COMMUNICATIONS
DCC requests that the following names be placed on the official service list for this
proceeding by the Commission and that all correspondence and communications with respect to
this proceeding be addressed to the following:96
Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, NW
Washington, DC 20005
morgan@datacentercoalition.org
Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C. 20006
Tel: (202) 887-4000
shug@akingump.com
breiter@akingump.com
V.
CONCLUSION
For the reasons set out above, DCC respectfully requests that the Commission issue an
order consistent with this protest.
Respectfully submitted,
/s/ Stephen J. Hug
Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, NW
Washington, DC 20005
morgan@datacentercoalition.org
Data Center Coalition
Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C. 20006
Tel: (202) 887-4000
shug@akingump.com
breiter@akingump.com
Dated: September 3, 2026
Counsel for the Data Center Coalition
96 DCC respectfully requests waiver of Rule 203(b)(3) of the Commission’s regulations, 18 C.F.R. §
385.203(b)(3), in order to permit designation of more than two persons for service in this proceeding.
PDF page 38
Exhibit A
Letter to Ms. Paula Conboy and Mr. David Mills
from VA SCC Chair, Kelsey Bagot and DCC
President & CEO, Josh Levi
PDF page 39
Confidential
June 30, 2026
Ms. Paula Conboy, Chair, PJM Board of Managers
Mr. David Mills, PJM President and CEO
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, Pennsylvania 19403
Dear Ms. Conboy and Mr. Mills:
The Virginia State Corporation Commission (VA SCC), along with its fellow PJM state utility
commissions, is mandated to ensure reliable electric service, just and reasonable retail rates, and to protect
residential and traditional industrial customers from undue cost shifts as the electric system continues to
evolve. The growth of large electric loads presents both significant opportunities for economic
development and important challenges for maintaining affordability and reliability across the PJM region.
The Data Center Coalition (DCC) is the national membership association for the data center industry,
representing leading data center owners and operators who maintain data center infrastructure across the
country and globe, as well as companies that lease large amounts of data center capacity.1 DCC
represents many of the companies driving investment in the PJM region and seeks to ensure that its
members have timely, efficient, and predictable pathways to secure the power necessary for their
operations. DCC members are fully committed to bearing the costs associated with serving their load to
ensure existing customers are protected from any undue cost shifts.
Together, the VA SCC and DCC recognize that the mandate of state utility commissions and serving
emerging large loads are not mutually exclusive. Rather, achieving them will require proactive
collaboration among states, industry, and PJM to develop standardized regulatory tools and model retail
tariff structures that individual state commissions may consider as they address the integration of new
large electric loads. By working collaboratively now, we believe it is possible to facilitate continued
economic investment while preserving reliability and protecting existing customers from inappropriate
cost shifts. Because many of the tools necessary to achieve these objectives fall within state jurisdiction,
the VA SCC and DCC are launching a collaborative effort to develop model retail tariff structures and
regulatory frameworks for consideration by interested state commissions.
State-Level Interruptible Tariffs and Load Reduction Priorities
The VA SCC and DCC will convene a joint working group with other interested states to develop model
state regulatory frameworks that enable states to better integrate large loads while maintaining reliability
1 The Data Center Coalition is a membership organization of leading data center owners and operators.
Public testimony, written comments and letters submitted by DCC do not necessarily reflect the views of
each individual DCC member. A list of current DCC members is accessible at
https://www.datacentercoalition.org/members.
PDF page 40
Confidential
and protecting existing customers. The initiative will focus on two complementary, but distinct,
workstreams.
1. Model State Interruptible Tariffs
The parties will develop model retail interruptible tariff structures that state commissions may consider
adopting to facilitate the integration of new large electric loads while maintaining reliability and
protecting existing customers. These model tariffs would:
● Establish standardized retail tariff provisions under which large customers may receive
interruptible service, whether through voluntary election or pursuant to state regulatory
requirements;
● Define the operational expectations, customer obligations, and utility responsibilities associated
with interruptible service;
● Establish the retail mechanisms through which interruptible customers would respond to requests
for curtailment consistent with applicable state tariffs and regional reliability procedures; and
● Provide model tariff language for consideration by interested state commissions while fully
preserving each state's independent regulatory authority.
The intended completion date for this work is no later than February 1, 2027.
2. Emergency Load Reduction
The VA SCC, DCC, and other interested states will jointly develop model state tariffs establishing
emergency load reduction programs designed to protect residential customers during the most severe
reliability emergencies while preserving reliable system operations. These model tariffs would:
● Establish retail mechanisms authorizing utilities to curtail designated large commercial and
industrial customers, or require the use of available on-site backup generation, once PJM has
exhausted all other available reliability resources, including demand response, but before
implementation of broad manual load shed;
● Define the operational expectations, customer obligations, and utility implementation procedures
associated with those programs; and
● Provide model tariff language for consideration by state utility commissions while preserving
each state's independent regulatory authority.
By targeting reductions from large commercial and industrial customers before implementing widespread
feeder-level outages, this approach can significantly reduce the likelihood that residential customers are
interrupted during the most severe reliability emergencies. It is particularly beneficial for jurisdictions
with little or no large-load development, where residential customers could otherwise be subject to
manual load shed even though targeted reductions of large loads—or deployment of available on-site
backup generation—in other parts of the PJM region would have been sufficient to address the reliability
need.
The intended completion date for this work is no later than February 1, 2027.
PDF page 41
Confidential
Reliability Backstop Cost Allocation
The VA SCC, DCC, and other interested states will also collaborate to develop model state tariff
provisions addressing the retail allocation of costs associated with PJM's Reliability Backstop
Procurement.
The objective is to develop transparent retail mechanisms that appropriately assign reliability backstop
costs to the large load customers whose demand contributes to the need for those procurements, while
protecting existing residential and traditional industrial customers from inappropriate cost shifts.
The intended completion date for this work is no later than January 1, 2028.
Moving Forward
This collaborative effort reflects our shared commitment to finding practical, durable solutions that
balance reliability, affordability, economic development, and regulatory certainty.
Together, the VA SCC and DCC recognize that these objectives are complementary. Achieving them will
require proactive collaboration among states, industry, utilities, and PJM to develop standardized
regulatory tools and model retail tariff structures that state utility commissions may consider as they
address the integration of new large electric loads. We also recognize that meeting the region's growing
electricity demand will require significant investment in new generation and other energy resources. DCC
members are committed to pursuing those investments, and both the VA SCC and DCC recognize that
clear, predictable regulatory frameworks are essential to supporting the investment in new generation and
energy resources needed to reliably serve the region's growing demand while protecting existing
customers.
We appreciate PJM's continued leadership on these matters and look forward to working collaboratively
with PJM, the states, and all stakeholders as these efforts move forward.
Sincerely,
Kelsey Bagot
Chair, Virginia State Corporation Commission
Josh Levi
President & CEO
Data Center Coalition
PDF page 42
Exhibit B
DCC Connect & Manage Alternative: State-Led
Implementation with Immediate Residential
Customer Protection
PDF page 43
DCC Connect & Manage Alternative:
State-Led Implementation with Immediate Residential
Customer Protection
The Data Center Coalition supports PJM’s objective of ensuring that new large loads
contribute to maintaining system reliability and that sufficient capacity is developed to
support continued economic growth. We agree that reliability must be maintained and that
new capacity should accompany significant new load additions. At the same time,
implementation frameworks must provide clear customer treatment, align obligations with
benefits, and protect existing customers.
DCC’s proposal is founded on the principle that large-load integration requires
coordination among PJM, states, electric distribution companies (EDCs), and customers.
Durable solutions must recognize the respective roles of wholesale and retail regulators
while providing certainty regarding reliability obligations, customer protections, and
curtailment treatment.
State Opt-In Framework
DCC proposes a State Opt-In model that allows states and EDCs to establish interruptible
service classifications and customer treatment rules while PJM continues to administer
wholesale reliability requirements. Under this approach:
• States establish interruptible customer classes and associated tariff provisions for large-
load customers.
• PJM monitors system conditions and, when reliability conditions warrant, issues a
wholesale reliability signal for interruption of interruptible load.
• The PJM signal activates the applicable state interruptible tariff.
• The EDC implements curtailments in accordance with state-established customer
classifications, priorities, and protections.
• PJM maintains responsibility for bulk-system reliability, while states retain authority over
retail customer classifications and curtailment treatment.
• This approach achieves the desired reliability outcome while preserving the traditional
division of state and federal responsibilities and avoiding the jurisdictional concerns
associated with PJM directly imposing mandatory curtailment obligations on retail
customers.
PDF page 44
• The framework also preserves incentives for customers to support the development of
new capacity resources.
The proposal acknowledges a practical reality: regardless of the wholesale framework
adopted, states and EDCs ultimately determine how customers are treated during
emergency conditions. By explicitly incorporating state implementation into the
framework, the proposal creates a more transparent and durable path for integrating large-
load growth while maintaining reliability.
The state-led approach is also necessary to avoid significant jurisdictional concerns. Any
framework that requires PJM to impose mandatory curtailment obligations based on the
characteristics of specific retail customers risks blurring the longstanding division between
wholesale and retail regulation. By relying on states and EDCs to establish customer
classifications, interruptible service arrangements, and curtailment priorities, the proposal
preserves the traditional regulatory compact while allowing PJM to maintain reliability
through wholesale market signals.
Immediate Reliability Action to Protect Residential Customers
While states develop long-term large-load tariffs and customer classifications, PJM, states,
and EDCs should take immediate action to strengthen emergency load-shed procedures
and better protect residential customers.
DCC proposes a phased manual load-shed approach under which large commercial and
industrial customers are contacted and provided an opportunity to curtail load before
residential customers are interrupted during emergency reliability events. States and zones
without significant large-load customers available for curtailment would not be expected
to participate in the initial phase. Instead, the first phase would focus on areas where large
commercial and industrial load reductions can be achieved. Residential customers and
critical services would remain a last-resort option after practical large-customer
curtailment opportunities within the affected area have been exhausted.
This recommendation is significant because it can be implemented immediately and does
not require states to first complete lengthy tariff, rulemaking, or customer-classification
proceedings. It provides a practical bridge between today’s reliability challenges and the
longer-term frameworks currently under development across the PJM region.
The approach offers several benefits:
• Provides immediate protection for residential customers.
• Reduces the likelihood that residential and critical-service customers are interrupted.
PDF page 45
• Preserves state authority over retail customer classifications and curtailment priorities.
• Improves reliability outcomes during emergency conditions using existing operational
tools and processes.
• Creates time for states, EDCs, customers, and PJM to develop durable long-term
solutions without delaying meaningful residential customer protections.
Conclusion
DCC’s proposal advances PJM’s reliability objectives while providing a practical
implementation pathway that aligns responsibilities among PJM, states, EDCs, and
customers. The State Opt-In framework recognizes the realities of retail implementation,
preserves incentives for new capacity development, and provides greater clarity regarding
customer obligations and protections. Combined with immediate actions to better protect
residential customers during reliability emergencies, the proposal offers both a near-term
and long-term path for maintaining reliability while supporting continued economic growth
throughout the PJM region.
PDF page 46
Exhibit C
DCC – A Path to Reliable Large-Load
Integration: Creating Certainty for Investment,
Customers, and the Grid
PDF page 47
June 10, 2026
A Path to Reliable Large-Load Integration
Creating Certainty for Investment, Customers, and the Grid
PDF page 48
New Load Should Fund New Capacity
Industry practice has already shifted toward customer-funded capacity to
protect existing ratepayers.
2
PDF page 49
Predictable Pathway to Firm Service
Large load needs regulatory certainty to confidently invest in new capacity.
Key Takeaway:
Data Centers are
committed to invest in
new capacity once the
path to firm service
without paying twice is
assured.
3
PDF page 50
PJM Cannot Provide the Needed Answers
PJM lacks the authority to answer critical questions that customers need
before investing billions to bring new supply to PJM.
Key Takeaway: PJM’s proposal depends on customer action
that PJM lacks authority to define, enforce, or guarantee.
4
PDF page 51
Large-load integration requires new
capacity and customer accountability.
Lasting solutions require states and PJM
to each perform their proper role.
5
PDF page 52
Connect & Manage:
Challenges
PDF page 53
Jurisdiction: Core Issue
C&M relies on retail customer characteristics to determine wholesale
obligations creating a jurisdictional vulnerability.
Curtailment obligations depend on retail customer
characteristics.
Large-load size and interconnection date/ load ramp
drives outcomes
Retail customer attributes become wholesale triggers
Appears targeted at retail transactions
Raises Federal Power Act concerns
7
PDF page 54
C&M Is Not Really About Load Growth
Example
SCENARIO A
SCENARIO B
New Load
200 MW
100 MW
Customer Type
Many small loads
One large load
C&M Obligation
No
Yes
The outcome depends on customer type –
not the amount of load growth
8
PDF page 55
Undue Discrimination Risk
The proposal is not truly prospective – loads face different treatment based on
ramp duration, not when they were put in service or contract terms.
The difference is based on ramp timing. Proposed rules do not permit or
contemplate evaluating contracts in place. Cost causation rationale is weak.
9
PDF page 56
Arbitrary Outcomes Created by Vintage
Cutoff dates create arbitrary results that are not based on load magnitude or
system impact.
10
PDF page 57
Protection is Not Assured
The Claimed Benefit of BYONC Is Outside PJM’s Control
Protection Must Be Real
• PJM cannot dictate retail curtailment decisions
• States and EDCs determine actual load-shed priorities
• Meeting PJM requirements may not guarantee protection
• Customers may still face curtailment despite meeting PJM’s
BYONC requirements
• Benefits and obligations may not align
Customers need certainty regarding the benefit they receive for
bringing new capacity.
11
PDF page 58
What Service Is Being Purchased?
• C&M load remains subject to interruption
• Customers continue paying for firm transmission (NITS)
• The proposal does not clearly establish what reliability rights
accompany C&M treatment
• Undue discrimination relative to DR and disruption of DR contracts
• Benefits and obligations may not align
• Customers need certainty regarding the service they are purchasing
Service Classification Mismatch
If customers are subject to interruption, the associated service rights
and classifications should be clearly defined.
12
PDF page 59
• States may require locational or “in state” resources
• States may impose policy priorities on the resource
type, e.g., threshold % for clean resources
• States may impose additional conditions on workforce
or other requirements
• Pennsylvania illustrates this trend
• BYONC to PJM ≠ BYONC to State
State Policy Preferences Will Differ
Retail implementation will remain state-specific
13
PDF page 60
Operational, Policy, and Litigation Risks
Defining new load, implementing across states and EDCs, and allocating costs create
significant operational, policy and legal risks without assured customer benefit
14
PDF page 61
So Where Does This Leave Us?
We Agree on the Objective
• Reliability must be maintained
• New capacity should accompany new large load
The Missing Piece
• States, EDCs, and PJM lack a coordinated framework for customer
curtailment and protection
The Path Forward
✓ Respect and coordinate with state jurisdiction
✓ Create clear customer treatment rules
✓ Align obligations with benefits
✓ Preserve incentives for new capacity
15
PDF page 62
A Better Path Forward: State Opt-In Model
16
PDF page 63
Immediate Reliability Action
Manual Load Dump: Curtail Large C&I Before Residential Load
While states develop interruptible-load tariffs and customer classifications, States, EDCs,
and PJM should immediately improve emergency load-shed procedures.
17
PDF page 64
• Large-load integration requires action from PJM, states, EDCs, and
customers
• Initial feedback on the opt-in framework focused on what happens if
states do not act - that risk exists under any C&M framework
• PJM cannot establish retail curtailment rules through assumption
• State implementation is a dependency whether acknowledged or not
• PJM's proposal assumes states will take actions that the tariff itself
cannot require
• Our proposal explicitly recognizes the respective roles of PJM and the
states.
State Action is Necessary and Unavoidable
Restoring the Regulatory Compact
Ignoring the need for state action does not eliminate the
dependency, it only obscures it.
18
PDF page 65
Reliability Backstop
Mechanism
PDF page 66
We Support a Limited, Targeted Backstop
• Bilateral procurement remains the preferred path for securing new
capacity
• DCC supported PJM's proposal for an extended bilateral procurement
window before any backstop procurement
• We recognize PJM's need to move forward on a September timeline
We Will Not Oppose a September Backstop Auction
• The backstop should supplement – not replace – bilateral
procurement
The Backstop Must Remain Limited
• Procurement should be limited to demonstrated capacity shortfall
that will not be addressed through bilateral arrangements.
Reliability Backstop: DCC Position
20
PDF page 67
Procure Only for Load That Will Not Bilateral
• Backstop MWs should be limited to demonstrated reliability shortfalls
• Capacity should not be procured for customers actively pursuing
bilateral solutions – particularly for load on the 2030+ timeframe
• Avoid duplicative procurement for the same future load
• The objective is to fill remaining gaps, not substitute for
private contracting
Procurement: Limited to Residual Needs
21
PDF page 68
Cost Responsibility Established Up Front
Transparency and Accountability Matter
• Cost responsibility should be determined before procurement
commitments are made
• Customers expected to fund procurement should be identified
whenever feasible
• States and EDCs should provide notice before acting on behalf
of specific customers
• Broad socialization should not replace targeted cost
responsibility
Capacity procurement and cost allocation should be determined together
—not sequentially.
22
PDF page 69
Meaningful Market Power Mitigation
Mean + 2 Standard Deviations is Not a Market Power Screen
• The benchmark is calculated from market offers
• Market offers may already reflect concentrated supply conditions
• Excluding statistical outliers does not establish that remaining offers are
competitive
• The benchmark may continue to embed market power
• Consumer protections should be grounded in resource economics
• Consider a cap based on Net CONE (require support for costs > Net CONE)
Mitigation Should Not Depend on Potentially Exercised Market Power
A statistical filter is not a substitute for economic mitigation
23
PDF page 70
Pamela Quinlan
Principal, GQS
PQuinlan@GQSenergy.com
PDF page 71
CERTIFICATE OF SERVICE
I hereby certify that I have this day served a copy of the foregoing document on the persons
designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 3rd day of September 2026.
/s/ Stephen J. Hug
Stephen Hug