Large Load Interconnection: what this is
What did the grid operators file on Nov 16?
PJM, MISO, CAISO and NYISO each filed large-load tariff rules under section 205 in new dockets, and PJM’s transmission owners filed the cost terms. Each says its filing answers its June order. PJM would study generators and large loads together in one 12-month process. MISO adds a project review with a $250,000 fee. CAISO offers interim service to flexible loads. NYISO offers firm and non-firm withdrawal service. SPP’s response is due Nov 20.
PJM · PJM transmission owners · MISO · CAISO · NYISOQuestions in the filings
- Who can see the registry? PJM would publish totals by distributor area where possible. Site-level filings stay subject to confidentiality rules. Ohio’s consumer advocate wants access under those same protections.
- Who pays if a supplier leaves? PJM proposes that the departing load-serving entity keep its backstop obligation. A later rate filing would set what it owes. The liability can outlast membership.
- What counts as one site? PJM’s 50 MW test uses cumulative peak demand. The clean tariff covers affiliated facilities within one mile under the configurations specified in the agreement.
On October 23, 2025, the Department of Energy invoked its rarely used § 403 authority to direct FERC to open a rulemaking on connecting large loads (data centers, AI, advanced manufacturing) to the interstate grid (Docket RM26-4-000), and asked for final action by April 30, 2026.
Rather than run a multi-year rulemaking, FERC answered on June 18, 2026 with six tailored § 206 show cause orders, one to each RTO/ISO. Each makes a threshold finding that the region’s tariff may be unjust and unreasonable for lack of clear, consistent large-load rules, then puts the market on a 30/60-day clock to defend the status quo or file a fix across the same five reform categories.
The through-line is cost causation made visible: the large load that triggers a network upgrade should bear its cost and spare ordinary ratepayers, with new transparency into how those costs are identified and allocated. The same morning, FERC issued Item E-2 (EL25-49-002), the order on rehearing that finalizes the rates and terms for the three new transmission services its PJM co-location proceeding created, the same services the six orders extend to every other region.
Where it stands on November 17, 2026: five of the six respondents have filed tariffs they say answer their orders, each in a new section 205 docket rather than the show cause docket. ISO-NE filed on Nov 13 in ER27-484-000 (comments due Dec 4). On Nov 16 PJM filed in ER27-531-000 and ER27-522-000, the PJM Transmission Owners in ER27-520-000, MISO in ER27-526-000 and ER27-527-000, CAISO in ER27-506-000 and NYISO in ER27-517-000. Comments on the CAISO, NYISO and PJM Transmission Owners filings are due Dec 7; PJM’s and MISO’s comment dates were not yet read. SPP’s response is due Nov 20. Valley Electric asked on Nov 13 to be dropped from CAISO’s order.
The Timeline tab holds the dated record: the August 3 and August 9 answer periods, the August 14 abeyance orders, the August 17 partial co-location compliance, the August 21 governance comments and backstop protests, and everything since. Each entry cites the document it was read from.
Where things stand
Four proceedings and one context lane run beside each other, each on its own clock. Status as of 2026-11-17.
- The six-market §206 clock (FERC Dockets EL26-67-000 to EL26-72-000). Five of the six respondents have filed. ISO-NE filed Nov 13 in ER27-484 (comments due Dec 4). On Nov 16 PJM filed in ER27-531 and ER27-522, the PJM Transmission Owners in ER27-520, MISO and its transmission owners in ER27-526 and ER27-527, CAISO in ER27-506 (refiled as ER27-532) with fifteen California transmission owners in their own dockets, and NYISO in ER27-517 with the New York Transmission Owners and LS Power Grid New York. Every filing went to a new ER docket. PJM says it “has responded fully to the Large Load Show Cause Order” and asks FERC to close the section 206 side; the others ask much the same. FERC’s first Nov 16 notice sets Dec 7 for comments on the CAISO, NYISO and PJM Transmission Owners’ filings, though NYISO asked for 28 days and CAISO for 30. The notice covering PJM’s and MISO’s filings was not read; PJM asked for 60 days and MISO for 30. SPP’s response is due Nov 20. Valley Electric asked Nov 13 to be dropped from CAISO’s order. NERC petitioned Nov 16 for large-load reliability standards (RD27-3). Next: 2026-11-20, SPP’s show cause response, the last one due.
- PJM co-location: EL25-49 (FERC Docket EL25-49 (Item E-2, order on rehearing)). PJM and the PJM Transmission Owners made their co-location compliance filings on Nov 16, inside their §205 filings. PJM’s ER27-531-000 refiles the compliance changes, including a 50 MW cap on netting retail behind-the-meter generation, and PJM moved the same day to withdraw its Aug 17 partial compliance filing. The transmission owners say ER27-520-000 also complies with the co-location order; its rates for the three new services largely repeat the ones FERC approved. Comments on ER27-520 are due Dec 7; the comment date on ER27-531 was not yet on its sheet on Nov 18. The fight has also moved to court: Vistra Corp. (Oct 22, Case No. 26-3635) and Exelon Corp. and others (Oct 27) petitioned the U.S. Court of Appeals for the Third Circuit for review of four orders in this proceeding, issued Dec 18, 2025, Feb 20, 2026, June 18, 2026 and Aug 20, 2026. That is known from the docket-sheet descriptions; the petitions were not read. No Commission order since the Aug 14 extension. Next: 2026-12-07, Comments due on the PJM Transmission Owners’ filing (ER27-520).
- PJM governance: AD26-7 (FERC Docket AD26-7-000 (Commission-led technical conference)). The Members Committee votes on Nov 18. Its agenda, posted Nov 11, says “The committee will be asked to approve/endorse the proposed OA, Tariff and RAA revisions as a package at this meeting.” Those revisions turn into governing-document language the term sheet the Members endorsed on Sept 30: §205 rights over the energy-market schedules with a jump-ball rule for competing Member filings, 30 days’ notice of market-design filings, a permanent planning committee and an independence clause. PJM posted the redlines on Oct 13 and walked stakeholders through them on Oct 16. The states opposed the sheet. They wrote the Board on Sept 29 that if it passed they would “forcefully oppose it before the Commission and beyond.” Nothing says yet whether the Board will file the Members’ package, its own, or neither. Commissioner LaCerte told Utility Dive, in an interview published Nov 11, that PJM has “a stakeholder process there that has been proven to be detrimental to improvements in PJM” and that states should have “an appropriate-sized role in governance.” FERC has not acted on the Sept 30 vote. The AD26-7 sheet was read in full on Nov 15, and its newest row is PJM’s Oct 1 informational filing. Next: 2026-11-18, Members Committee vote on the governance revisions as a package.
- The RM26-4 record (FERC Docket RM26-4-000 (the DOE §403 rulemaking)). Open with no dated next step, and nothing new on it since the June 18 orders. FERC answered the directive with the six §206 orders rather than a rule, and its Oct 15 open meeting agenda carried no RM26-4 item. The record's substance now moves through the regional §205 filings the orders invited; the crosswalk on the Comments tab tracks which of the record's issues each order reached.
- Market context. PJM moved on Nov 12 to withdraw its miscoded Oct 29 backstop filing in ER27-330. The same tariff records are pending in ER27-454-000. Comments on that filing and on PJM’s Nov 9 registry filing (ER26-3515-002) are due Nov 30. Two requests on the Oct 9 registry order are pending in ER26-3515-001: Ohio’s Consumers’ Counsel wants access to confidential registry data, and the PJM Industrial Customer Coalition and Steel Producers want limits on who sees it. In Exelon’s capacity-auction complaint (EL27-11), FERC gave PJM until Dec 21 to answer. In MISO’s joint-study docket (ER27-25), six consumer advocates asked on Nov 12 for conditions on acceptance. The backstop paper-hearing briefs are due Jan 11 and Jan 26, 2027. Next: 2026-11-30, Comments on PJM’s registry compliance filing and separate backstop refiling.
The six show cause orders
Each order has its own page below, with the quoted directives, the region-specific findings and the full respondent roster. Every PDF is a committed copy of the ferc.gov original, served with this site so page-precise citations open inline.
- E-7 PJM, Docket EL26-67-000: 195 FERC ¶ 61,211, 114 pp. Co-location rules already in place. Region: Mid-Atlantic / 13 states + DC. PJM is the control case, the one region that does not start from a blank page. FERC built PJM’s co-location rules in the parallel EL25-49 proceeding (finalized the same morning in Item E-2), so E-7 asks PJM to carry those new services (Interim NITS and Firm/Non-Firm Contract Demand) into a general large-load framework. The catch: every request still runs through one ‘first-ready, first-served’ clustered New Services Queue with no large-load-specific study, even though an Eligible Customer already pays ‘100% of the costs of the minimum amount of Network Upgrades’ its request triggers. So the order presses how to add flexible-load service and protect deals nearing completion without breaking that queue.
- E-8 MISO, Docket EL26-70-000: 195 FERC ¶ 61,212, 115 pp. Early-stage large-load rules. Region: 15 states, Midwest + South. MISO is the cost-allocation stress test. Its tariff still studies new load at its maximum demand ‘regardless of the load’s operational capabilities or willingness to be curtailed,’ and the resulting network upgrades are ‘rolled into the relevant transmission owner’s base zonal rates,’ spread across that utility’s wholesale customers. MISO itself told its Large Load Working Group the tariff does ‘not provide a consistent or transparent framework’ for large loads. E-8 presses whether flexible service and a pro forma cost-recovery agreement can keep those upgrade costs on the load that caused them.
- E-9 SPP, Docket EL26-68-000: 195 FERC ¶ 61,213, 92 pp. Most mature: HILL / HILLGA. Region: Central U.S., 14+ states. SPP is the benchmark for the other five. E-9 adopts SPP’s own ‘High Impact Large Load’ (HILL) definition, commends its ‘High Impact Large Load Generation Assessment’ (HILLGA) and Conditional HILL Service, and leaves the Attachment Z1/AQ/AX study stack and Highway/Byway cost split intact. Even in this leading framework FERC finds only two real gaps: no requirement to evaluate alternative transmission technologies, and no pro forma terms to ‘memorialize ongoing operational requirements in a transmission service agreement.’ The remaining ask is a mechanism to credit large-load payments back through transmission owners’ revenue requirements.
- E-10 CAISO, Docket EL26-71-000: 195 FERC ¶ 61,214, 118 pp. No Order No. 888 service. Region: California (+ WEIM footprint). CAISO is the translation problem. It ‘does not offer traditional Order No. 888 network and point-to-point transmission services, offers no firm, long-term transmission reservations of capacity,’ and its Participating TOs (not CAISO itself) ‘play the lead role in managing the interconnection of load’ inside California’s state planning and forecasting processes. So E-10 gives CAISO an alternative no other order offers: either build equivalent large-load protections, or explain why its single daily service and Transmission Access Charge (TAC/RAC) framework already solves the same cost and reliability problems.
- E-11 ISO-NE, Docket EL26-72-000: 195 FERC ¶ 61,215, 115 pp. Transmission-constrained grid. Region: Six New England states. ISO-NE is the small-system, big-load case. FERC flags a system peaking at only ‘30,000 MW’ with significant transmission constraints, and a ‘CELT load forecast’ that generally excludes proposed data centers, so a single large customer can move the regional needle. E-11 turns that into concrete planning questions: how Schedule 22/23 cluster studies, Pool Transmission Facilities at ‘69 kV’ and above, and the Monthly Regional Network Load behind-the-meter-netting rules should change, and whether to import PJM’s MW-threshold remedy for that netting.
- E-12 NYISO, Docket EL26-69-000: 195 FERC ¶ 61,216, 119 pp. Largely outside the tariff today. Region: New York State. NYISO is the tariff-gap case. It runs load interconnection for projects over 10 MW at ‘115 kV’ and above largely off-tariff: the study details, deposits, and assumptions sit in non-tariff documents, and its tariff ‘lacks a definition of large load’ as a category. With co-location reforms not expected until ‘2027,’ E-12 converts that off-tariff practice into show-cause issues: a 60-to-90-day study expectation, a new large-load definition with readiness requirements to deter speculation, and the only order’s express path to request a 90-day abeyance.
Decided the same morning: E-2 (Docket EL25-49-002, 195 FERC ¶ 61,209), the PJM co-location order on rehearing that finalises the three new transmission services the six orders extend.
The five reform categories
- Application & study processes (incl. alternative transmission technologies): Developing efficient transmission-service application and study processes, including consideration of alternative transmission technologies.
- Cost-shifting prevention & transmission-cost transparency: Preventing cost shifting and requiring transparency into transmission costs.
- Co-location arrangements & behind-the-meter (BTM) generation: Accommodating co-location agreements and behind-the-meter generation.
- New transmission services for flexible large loads: Providing new transmission services for flexible large loads.
- Studying generation serving electrically proximate / co-located loads: Developing a process to study generating facilities that serve electrically proximate large loads and co-located loads.
The §206 procedural clock
All six §206 orders run one clock from the June 18, 2026 issuance. The periods are stated in each order’s ordering paragraphs; the calendar dates are derived and business-day-adjusted (National Law Review). Status is computed from today’s date and the schedule. It does not show who has filed; the filings table below does.
- 2026-07-09, Motions to intervene (21 days from issuance, Ordering ¶ (D) · Rule 214): Notices of intervention or motions to intervene in the six proceedings are due.
- 2026-07-20, Generation-adequacy report (30 days from issuance, Ordering ¶ (C)): Each RTO/ISO files an informational report on how it will ensure adequate generation to serve existing and new large loads.
- 2026-07-20, Requests for rehearing (30 days from issuance, FPA § 313(a)): Statutory deadline to seek rehearing of the June 18 orders before a court appeal.
- 2026-08-03, Abeyance requests (45 days from issuance, All six orders (e.g., E-12 P 42)): Deadline in each of the six orders to request full or partial abeyance (up to 90 days) of the proceeding. FERC says it will not grant abeyances reflexively and views extension requests with great disfavor.
- 2026-08-17, Show cause or file tariff changes (60 days from issuance, Ordering ¶ (B)): Each RTO/ISO and its Transmission Owners must show cause why the tariff remains just and reasonable, or file remedial tariff changes.
- Not yet dated, Response window opens (filing + 30 days, Ordering ¶ (E)): Interested entities may respond on whether the tariff remains just and reasonable and, if not, what replacement rates to implement. Opens once the show-cause/tariff filing is made.
This is an independent analysis microsite and is not affiliated with FERC or DOE. Order record as of 2026-06-22; commentary 2026-11-12; news and filings swept 2026-11-17. A machine-readable index for agents is at llms.txt.