ER26-3515-002 · 2026-11-09 · PJM

Thirty-Day Compliance Filing on PJM’s Large Load Definition and Large Load Registry

PJM files the tariff and Reliability Assurance Agreement text that keeps the 50 MW Large Load definition and the Large Load Registry FERC accepted on October 9, with the fields tied to its rejected capacity proposal removed.

Asks FERC to: Accept the compliance filing with an October 12, 2026 effective date.

Parallel proceeding. Defines which PJM loads count as large and how PJM learns about them, the threshold question the E-7 order leaves to PJM's show cause response.

E-7 PJM: Application / study process (P 6(a), p. 7) E-12 NYISO: Define ‘large load’ (P 64, p. 41)

Key points

  1. PJM drops the two registry fields tied to its rejected capacity proposal.
    the amount of BYONC brought by a particular Large Load and the allocated RBP UCAP MW quantity PDF p. 2
  2. A Large Load is 50 MW of cumulative peak at one electrical site.
    a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection PDF p. 109
  3. Loads in service before June 1, 2027 must be reported by March 1, 2027.
    prior to June 1, 2027, shall provide the information required by RAA, Schedule 11.B.1 to the Office of the Interconnection by March 1, 2027. PDF p. 124
  4. Later loads must be reported before they enter service.
    before the in-service date of the Large Load. PDF p. 125

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Connecting load and generation · Reliability and curtailment

What the document says

Registry scope · PDF pp. 1–2

Transmittal: what survived the October order

PJM asks for an October 12 effective date for the definition and registry. It strips out the two fields that would have recorded a customer's new capacity and allocated backstop megawatts. The filing does not revive the rejected curtailment service.

the amount of BYONC brought by a particular Large Load and the allocated RBP UCAP MW quantity PDF p. 2
Filed comments: Registry access

Filing record · PDF pp. 2–5

I–III. What PJM submitted and served

PJM submits the same tariff and reliability agreement changes in marked and clean copies. The service section says PJM notified its members and state utility commissions. The conclusion asks for acceptance; it does not establish that FERC accepted this filing.

PJM respectfully requests that the Commission accept this compliance filing PDF p. 4

Registry scope · PDF pp. 6–65

Attachment A: how to read the marked text

The redlines show where PJM placed the surviving definition and reporting rules. Use the clean copy starting on PDF page 66 to read the resulting language; the reproduced definitions surrounding the edits are not all new rules.

all affiliated load facilities within a one-mile radius will be considered a single electrical site PDF p. 49

Registry scope · PDF pp. 66–86

Attachment B: tariff definition

The clean Open Access Transmission Tariff points to the Reliability Assurance Agreement for the definition. Page 109 gives the threshold and the test for grouping affiliated facilities.

“Large Load” shall have the meaning provided in the Reliability Assurance Agreement. PDF p. 68

Registry reporting · PDF pp. 87–90

Attachment DD-4: who keeps the registry

PJM maintains the registry under Schedule 11. Electric distributors coordinate with PJM and supply information they consider appropriate, including applicable retail tariffs and contracts. Section I is reserved.

any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry PDF p. 89
Filed comments: Registry access

Registry scope · PDF pp. 91–122

RAA Article 1: what counts as one site

The threshold is 50 MW of cumulative peak demand at one electrical site, even behind several interconnection points. Affiliated load facilities within a one-mile radius count as one site under the stated configurations.

a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection PDF p. 109

Registry reporting · PDF pp. 123–124

Schedule 11.B.1(a): what must be reported

Entities bound by the Operating Agreement must submit, or arrange submission of, data about each large load they serve. Fields include location, dates for each load increment, peak MW and ramp schedule, telemetry, and backup generation with fuel and permit limits.

Backup generation (MW), including fuel type and relevant permitting limitations PDF p. 124

Registry access · PDF p. 124

Schedule 11.B.1(b)–(d): validation and access

PJM may check the data with the distributor, transmission owner or customer. The text names regulators, system participants and the market monitor as possible recipients under safeguards. It does not explicitly list state consumer advocate offices.

Information maintained in the Large Load registry may be available to Authorized Commissions PDF p. 124
Filed comments: Registry access

Registry access · PDF p. 124

Schedule 11.B.1(e): what the public can see

PJM would post aggregate data by distributor zone or area where possible. Confidentiality protections still apply; this is not a public list of individual sites and contracts.

aggregated by Electric Distributor zone/area, where possible PDF p. 124

Registry reporting · PDF pp. 124–125

Schedule 11.B.2: deadlines and changes of supplier

For loads in service before June 1, 2027, the serving or contracted entity must report by March 1, 2027. For loads entering service on or after June 1, it must report before startup. It must promptly report later changes, including transfer of the right to serve the load.

before the in-service date of the Large Load PDF p. 125