ER26-3380-001 · 2026-10-13 · American Municipal Power

Request for Clarification and Alternative Request for Rehearing of American Municipal Power, Inc.

American Municipal Power asks FERC to clarify its September 29, 2026 order on PJM's Reliability Backstop Procurement so that cost allocation reaches zones with large load growth and the order is read as non-final, and alternatively seeks rehearing.

Asks FERC to: Clarify that the suggested load-difference allocation is unjust if it charges zones without large load growth, and that PJM's as-filed allocation is open in the paper hearing; alternatively grant rehearing.

Parallel proceeding. Seeks clarification of the September 29 order on PJM's Reliability Backstop Procurement in ER26-3380, the separate capacity adequacy track beside the E-7 report on ensuring generation for large loads.

E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)

Key points

  1. PJM's Initial RBP Target is 6,831.3 MW of UCAP, the amount the 2028/2029 auction cleared short.
    PJM set the Initial RBP Target at 6,831.3 MW. PDF p. 2
  2. The September 29 order set paper hearing procedures on cost allocation, Transmission Owner exit rules and LSE collateral.
    The Commission established paper hearing procedures to address three aspects of the PJM Filing – cost allocation, Transmission Owner exit rules, and collateral requirements for Load Serving Entities PDF p. 3
  3. AMP first asks FERC to clarify that its suggested allocation method fails cost causation if it charges zones without large load growth.
    the Commission should clarify that it would not be just and reasonable to apply the Commission’s potential modification to PJM’s cost allocation method if it would result in RBP costs being allocated to Electric Distributor zone/areas that are not experiencing load growth attributable to data centers or other large loads PDF p. 6
  4. AMP second asks FERC to confirm that it made no final ruling on PJM's as-filed allocation method.
    The Commission should clarify that it has not made a final decision regarding the justness and reasonableness of PJM’s as-filed RBP cost allocation approach PDF p. 9
  5. AMP asks that parties may defend PJM's as-filed allocation in the paper hearing.
    The Commission should also clarify that parties may address PJM’s as-filed cost allocation proposal in the paper hearing procedures. PDF p. 9
  6. If clarification is denied, AMP seeks rehearing, calling the rejection arbitrary and capricious.
    The Commission’s rejection of PJM’s proposal was arbitrary and capricious, as it was based on an apparent misunderstanding of PJM’s approach. PDF p. 10
  7. AMP says PJM used Load Adjustments from Table B9b, which count large loads that Table B9 would miss.
    PJM, however, did not rely on the Load Adjustments shown in Table B9 to allocate RBP costs, it proposed to use the Load Adjustments in Table B9b of the Load Forecast. PDF p. 12
  8. AMP says the lack of a MW threshold for Load Adjustments is now fixed with a 50 MW threshold in PJM Manual 19.
    PJM Manual 19 has been updated to specify a 50 MW threshold for future Load Adjustments PDF p. 15

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Filing procedure · Reliability and curtailment

What the document says

PDF p. 15

AMP: PJM's allocation holds, because Table B9b counts the large loads FERC feared missed.

Because the Load Adjustments in Table B9b are intended to count new large load quantities, including those that might have otherwise been embedded in the initial PJM load forecast data, use of Table B9b addresses the Commission’s principal concern PDF p. 15

PDF p. 9

AMP: PJM's allocation holds, because Table B9b counts the large loads FERC feared missed.

The Commission should clarify that it has not made a final decision regarding the justness and reasonableness of PJM’s as-filed RBP cost allocation approach PDF p. 9
Filed comments: Cost allocation

PDF p. 7

AMP: FERC's suggested load-difference method must not charge zones without large-load growth.

implementing its potential modification to RBP cost allocation would likely violate cost causation principles, as it could result in the allocation of RBP costs to zone/areas that have not experienced load growth attributable to data centers or other large loads. PDF p. 7
Filed comments: Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

American Municipal Power, Inc. (“AMP”) hereby requests clarification of certain aspects of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) September 29, 2026 order in the above-captioned docket,1 which addressed the proposal by PJM Interconnection, L.L.C. (“PJM”) to establish a…
Read this passage Filed comments: Cost allocation

I. BACKGROUND

printed heading

I.
Read this passage

BACKGROUND

printed heading · Topic match: Cost allocation

PJM asserted that this allocation framework would be consistent with cost causation principles and the Ratepayer Protection Pledge.11 In the September 29 Order, the Commission preliminarily found that aspects of PJM’s RBP proposal – including cost allocation – may be unjust, unreasonable, unduly…
Read this passage Filed comments: Cost allocation

II. REQUEST FOR CLARIFICATION

printed heading

II.
Read this passage

A. The Commission should clarify that it would not be just and

printed heading · Topic match: Cost allocation

The Commission also found that “PJM’s proposed opt-out for qualifying cooperatives and municipal utilities may be unjust, unreasonable, and unduly discriminatory.” Id. at P 152. 19 Id. at P 155; see also id. at P 154 (agreeing “with concerns in the record that relying on Load Adjustments to measure…
Read this passage Filed comments: Cost allocation

B. The Commission should clarify that it has not made a final decision

printed heading · Topic match: Cost allocation

Granting the requested clarification would be consistent with the general proposition that, when the Commission makes preliminary findings on an issue and establishes further procedures, it has not made a final determination that is subject to rehearing requests.36 The Commission should also…
Read this passage Filed comments: Cost allocation

III. ALTERNATIVE REQUEST FOR REHEARING

printed heading · Topic match: Filing procedure

ALTERNATIVE REQUEST FOR REHEARING If the Commission denies the clarification requested in section II.B above, AMP seeks rehearing of the September 29 Order pursuant to FPA section 31338 and Commission Rule 713.39 The Commission should grant rehearing of its determination that PJM’s proposed RBP…
Read this passage Filed comments: Filing procedure

A. Statement of Issues

printed heading · Topic match: Cost allocation

The Commission’s conclusion that PJM’s proposed RBP cost allocation method was not just and reasonable was arbitrary and capricious.41 2.
Read this passage Filed comments: Cost allocation

B. Request for Rehearing

printed heading · Topic match: Cost allocation

Thus, PJM removes large loads from the underlying forecast data and adds large loads back into the forecast through the Load Adjustments.52 Table B9b is intended to capture the difference between the final forecast and what the final forecast would be without any large load, not just without Load…
Read this passage Filed comments: Cost allocation

IV. CONCLUSION

printed heading

IV.
Read this passage

CONCLUSION

printed heading · Topic match: Filing procedure

In the alternative, AMP requests rehearing of the Commission’s rejection of PJM’s RBP cost allocation methodology.
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 13th day of October, 2026. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.com
Read this passage