ER27-25-000 · 2026-10-23 · Entergy and Cleco

Supporting Comments of the Entergy Operating Companies and Cleco Power LLC

The Entergy Operating Companies and Cleco Power file supporting comments on MISO's LARS filing, saying a 120-day parallel study of large loads over 200 MW and their paired generation is just and reasonable and answers the show cause order.

Asks FERC to: Accept MISO's LARS filing as just and reasonable and as a permanent process.

Answers the order. Supports MISO's LARS filing as a direct response to the E-8 show cause order's call for provisions on generation serving electrically proximate large loads.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. Entergy and Cleco support LARS for loads over 200 MW that have identified new generation.
    enable MISO to expeditiously review the interconnection needs of large loads over 200 MW that have identified new generation resources to support their needs. PDF p. 1
  2. They say MISO DPP cycles of four years or longer leave utilities without a timely path to interconnect generation built for new load.
    MISO's DPP cycles have taken four years or longer to reach completion PDF p. 3
  3. They say LARS can reach a reliable outcome in about 120 days, which separate processes cannot.
    produce a reliable outcome in approximately 120 days. PDF p. 4
  4. They argue a permanent LARS gives the certainty needed to site and finance load and generation pairings.
    Making LARS a permanent process is appropriate because it provides needed, long-term regulatory and financial certainty PDF p. 4
  5. They ask FERC to judge LARS under the independent entity variation standard.
    The Commission should evaluate LARS under the PDF p. 4
  6. They list the limits: ten pairs per period, three periods a year, 150 percent ceiling, $250,000 deposit, three-year commercial operation date and same Local Resource Zone.
    only ten generation/load pairs per study period will be evaluated, with three periods per year. PDF p. 5

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation

What the document says

PDF p. 2

LARS studies a 200 MW-plus load and its paired generation together in about 120 days.

LARS offers a coordinated, 120-day parallel study of eligible large loads and their paired generation resources. PDF p. 2
Filed comments: Connecting load and generation

PDF p. 3

Utilities say MISO's generator queue takes years, so paired generation needs a faster lane.

MISO's DPP cycles have taken four years or longer to reach completion, leaving load-serving entities without a timely path to interconnect associated generation PDF p. 3

PDF p. 5

Entry limits cap LARS at ten pairs per study period and three periods a year.

can administratively support the new process, as only ten generation/load pairs per study period will be evaluated, with three periods per year. PDF p. 5

PDF p. 5

Supporters want FERC to accept LARS as filed, citing its entry limits and fuel neutrality.

stringent eligibility requirements to deter speculative interconnection requests and minimize disruption to the DPP PDF p. 5

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER27-25-000 Operator, Inc. ) SUPPORTING COMMENTS OF THE ENTERGY OPERATING COMPANIES AND CLECO POWER LLC Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure1, and the Commission’s October 2, 2026, notice in the above-captioned docket, Entergy Services, LLC, on behalf of the…
Read this passage Filed comments: Connecting load and generation

I. Background

printed heading

I.
Read this passage

Background

printed heading · Topic match: Connecting load and generation

For the Entergy Operating Companies and Cleco Power, the inclusion of LARS as an option to plan for the future needs of its growing customer base is vital.
Read this passage Filed comments: Connecting load and generation

II. The LARS Process is Just and Reasonable

printed heading · Topic match: Connecting load and generation

The LARS Process is Just and Reasonable LARS should be accepted by the Commission because it is just and reasonable and delivers coordinated speed to power without sacrificing study integrity.
Read this passage Filed comments: Connecting load and generation

III. Conclusion

printed heading

III.
Read this passage

Conclusion

printed heading · Topic match: Connecting load and generation

Conclusion LARS is a timely, well-designed, and appropriately limited tool for integrating large loads and the generation built to serve them, and it responds directly to the 9 MISO Transmittal at 9. 10 Id. at 10, 28. 11 Midcontinent Independent System Operator, Inc., 192 FERC ¶ 61,064 at Para. 2…
Read this passage Filed comments: Connecting load and generation