PJM partial compliance filing in response to the June 18, 2026 order on rehearing in EL25-49-002 et al.
PJM files a partial compliance filing under the June 18, 2026 co-location rehearing and paper hearing order, adding Eligible Load, Interim NITS in new Tariff Part XI and Necessary Study rules, while deferring contract demand services and BTMG netting to a later filing.
Asks FERC to: Accept the Tariff revisions effective October 17, 2026, except new Part XI for Interim NITS, which PJM asks to make effective July 1, 2028 with waiver of the 120-day filing limit.
Carries out the order. Carries out the E-2 co-location order's directives on Interim NITS, Eligible Load and BTMG netting, and ties its timing to PJM's larger E-7 large load response due mid-November.
E-2 PJM: Interim NITS (P 2, p. 3) E-2 PJM: One of three new co-location services (P 2, p. 3) E-2 PJM: Retail BTMG netting rewritten (P 4, p. 3)
Key points
- PJM files under FPA section 206 to comply with the June 18 order and plans a full section 205 large load filing by mid-November.
PJM intends to submit that filing by mid-November 2026. PDF p. 1
- PJM sets October 17, 2026 for most revisions and July 1, 2028 for Interim NITS so it can build tools to curtail non-firm service.
PJM proposes an effective date of July 1, 2028, to provide time for operational changes and implementation of additional operational tools PDF p. 2
- PJM adds an Eligible Load definition covering co-located load and load behind BTMG, so both can take Interim NITS.
Eligible Load shall mean Co-Located Load or load connected to Behind the Meter Generation. PDF p. 13
- PJM removes the 50 MW nameplate limit from the Retail BTMG definition, as the June order directed, and works on the 50 MW netting materiality threshold separately.
eliminates the rejected 50 MW nameplate limit and other netting exemptions PDF p. 12
- Customers must pass the Necessary Study process and finish upgrades before serving co-located load, from existing or new generators.
not begin serving Eligible Load until the entire scope of the work under their GIA as amended after the Necessary Study process is complete. PDF p. 11
- Customers with existing service agreements can modify them through the Necessary Study process rather than sign a new GIA.
PJM is proposing changes to allow customers that obtained service agreements pursuant to Parts VI and VII to modify those agreements PDF p. 15
- Interim NITS is energy-only and non-firm, converts to NITS once upgrades are done, and is suspended for up to 120 days after a first dispatch failure.
suspend service for up to 120 days after the first instance and terminate service after the second. PDF p. 18
- PJM defers Firm and Non-Firm Contract Demand services and some BTMG netting to a later compliance filing under a 90-day extension.
PJM sought a 90-day extension of certain directives in the June Order. PDF p. 10
Topics in the text: Connecting load and generation · Filing procedure · Reliability and curtailment
What the document says
PDF p. 2
PJM's August 17 filing proposes Interim NITS in new Part XI, effective July 1, 2028.
PJM proposes an effective date of July 1, 2028, to provide time for operational changes and implementation of additional operational tools that will be needed to curtail non-firm Interim NITS PDF p. 2
PDF p. 23
PJM's August 17 filing proposes Interim NITS in new Part XI, effective July 1, 2028.
PJM Operations personnel will need to implement additional tools and processes before they will be able to monitor and curtail, as needed, the new non-firm Interim NITS product proposed in Tariff, Part XI PDF p. 23
PDF p. 23
PJM wants October 17, 2026 as the effective date for the rest of the compliance changes.
PJM requests an effective date for the compliance changes in Parts I, III, VI, VII, VIII, and IX of the Tariff of October 17, 2026, which is 61 days after the date of this filing. PDF p. 23
PDF p. 10
PJM defers contract demand services and some netting terms to the November 16 filing.
PJM proposed to defer implementation of the new contract demand transmission services and some aspects of the BTMG netting. PDF p. 10
PDF p. 19
PJM defers contract demand services and some netting terms to the November 16 filing.
PJM also omitted language referencing Firm Contract Demand Service and Non-Firm Contract Demand Service, as those services will be implemented in a later compliance filing PDF p. 19
PDF p. 12
PJM is still working with stakeholders on the 50 MW retail behind-the-meter netting language.
PJM is continuing to work with stakeholders to develop Tariff language to implement the 50 MW netting provisions for Retail BTMG. PDF p. 12
PDF p. 2
PJM is still working with stakeholders on the 50 MW retail behind-the-meter netting language.
to eliminate the 50 megawatts (“MW”) nameplate limit for netting PDF p. 2
PDF p. 13
New 'Eligible Load' extends Interim NITS to load with behind-the-meter generation.
PJM is proposing to add the term Eligible Load to the Tariff to encompass both Co-Located Load and Load with BTMG. PDF p. 13
PDF p. 11
Existing generators serving co-located load must give notice and finish Necessary Studies first.
the Tariff would now require that all Interconnection Customers and Generation Project Developers seeking to serve Co-Located Load, whether with existing or new Generating Facilities PDF p. 11
PDF p. 18
Interim NITS operators who ignore dispatch lose service for up to 120 days, then are terminated.
PJM revised the operational penalties for failure to follow dispatch instructions or misoperation of control technologies to suspend service for up to 120 days after the first instance and terminate service after the second PDF p. 18
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Constellation challenges the July 2028 date Constellation and PJM
- AMP identifies a missing class of behind-the-meter generation American Municipal Power and PJM
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Consistent with the directives of the June Order, PJM proposes compliance changes to: • Modify the definitions of Co-Located Load, Behind the Meter Generation (“BTMG”), and Necessary Study, as directed;6 • Modify the definition of Retail BTMG to eliminate the 50 megawatts (“MW”) nameplate limit for…Read this passage
INTRODUCTION
printed heading
INTRODUCTIONRead this passage
A. Commission December Order
printed heading · Topic match: Connecting load and generation
Reese August 17, 2026 Page 4 specificity for the rates, terms, and conditions that apply to Co-Located Load and directing PJM to make a number of compliance and informational filings.12 First, the December Order directed PJM to make a compliance filing within 30 days to clarify the rates, terms,…Read this passage
B. PJM Compliance Filings
printed heading · Topic match: Connecting load and generation
ER26- 1088-000 pursuant to the December Order (“Thirty-Day Compliance Filing”).20 The Thirty-Day Compliance Filing proposed to clarify certain aspects of the Tariff for those seeking to serve Co-Located Load with new Generating Facilities.21 Among other changes, the Thirty-Day Compliance Filing…Read this passage
IX. The May 18 Compliance Filing established an effective date of April 16, 2026 in accordance with the
printed heading · Topic match: Connecting load and generation
EL25-49-000 and EL25-49-001 to address the Commission’s finding in the December Order that additional record evidence was needed to set the appropriate replacement rates, terms, and conditions for new transmission services for Eligible Customers serving Co-Located Load, including for Interim NITS,…Read this passage
C. The Commission’s June Order
printed heading · Topic match: Filing procedure
The Commission’s June Order On June 18, 2026, the Commission issued the June Order, addressing the Sixty- Day Compliance Filing, the paper hearing submissions, and requests for rehearing and clarification of the December Order.35 The June Order found that PJM’s Sixty-Day Compliance Filing partially…Read this passage
D. Large Load Order
printed heading · Topic match: Cost allocation
Large Load Order The same day it issued the June Order, the Commission also issued a new show cause order to PJM concerning Large Loads (“Large Load Order”).38 The Large Load Order found that several aspects of PJM’s Tariff appeared unjust and unreasonable due to the lack of specific procedures for…Read this passage
E. Partial Extension
printed heading · Topic match: Filing procedure
Partial Extension On July 28, 2026, PJM filed a motion for extension of time to meet certain compliance requirements in the June Order.46 PJM explained that due to the significant 40 Id. at P 86. 41 Id. at P 77. 42 Id. at ordering paras. (A) & (B). 43 Id. at P 4. 44 Id. at ordering para. (B). 45…Read this passage
A. Prohibition on Serving Co-Located Load from Existing Generators
printed heading · Topic match: Connecting load and generation
Reese August 17, 2026 Page 11 protection systems, and metering are complete and in service.53 This compliance filing proposes to add Necessary Study references and provisions to Parts I, III, VI, and VII, and to direct Generation Project Developers seeking to serve Co-Located Load with an existing…Read this passage
B. Revisions to Retail Behind the Meter Generation Definition
printed heading
However, for purposes of allowing Eligible Customers with load served by Retail BTMG to take Interim NITS,60 PJM is proposing a revised definition of Retail 56 PJM also proposes herein formatting and language changes to the Necessary Study provisions in Part VIII, Subpart A, section 401(H)(3), to…Read this passage
C. Expansion of Service to “Eligible Load” for Load with BTMG
printed heading · Topic match: Connecting load and generation
Reese August 17, 2026 Page 14 Load” with “Eligible Load” and “Co-Located Generator” with “Eligible Generator” and other clarifying changes in Tariff Part I, section 1 (Definitions),67 Part III (Network Integration Transmission Service),68 Part VI (Administration and Study of New Service…Read this passage
D. Elimination of New GIA Requirement
printed heading · Topic match: Connecting load and generation
PJM also proposes to cross-reference Tariff, Part VIII, Subpart L, section 439, Provisional Interconnection Service, added in the Thirty-Day Compliance Filing, in Parts VI and VII to clarify that Provisional Interconnection Service is available to entities that obtained Interconnection Service…Read this passage
E. Interim NITS
printed heading · Topic match: Reliability and curtailment
Second, consistent with the June Order,89 PJM revised the language in section 705.2 to clarify the curtailment priority for Interim NITS relative to Non-Firm Point to Point Service and that it will prioritize customers for curtailment based on duration of service as specified in the PJM Manuals.90…Read this passage
F. Other Commission Ordered Changes
printed heading · Topic match: Connecting load and generation
Reese August 17, 2026 Page 21 June Order Directive PJM Compliance Change Reject increase in cost for Necessary Studies Agreement.112 Removed proposed cost increase from pro forma Necessary Study Agreement.113 Revise the Tariff’s definition of Co- Located Load to use “Point of Interconnection”…Read this passage
G. Effective Date Only
printed heading · Topic match: Connecting load and generation
Reese August 17, 2026 Page 23 • Part III, section 34.3 (Netting of Non-Retail BTMG);128 • Part VII, Subpart A, section 300, Definitions B (BTMG);129 • Part VIII, Subpart A, section 400, Definitions B (BTMG);130 and • Part VIII, Subpart A, section 400, Definitions N (Necessary Study).131 EFFECTIVE…Read this passage
Attachment A:
printed heading
Attachment A: Tariff Redline; and 2.Read this passage
Attachment B:
printed heading
Reese August 17, 2026 Page 25 CORRESPONDENCE AND COMMUNICATIONS Correspondence and communications with respect to this filing should be sent to, and PJM requests the Secretary to include on the official service list, the following:134 Craig Glazer Vice President – Federal Government Policy PJM…Read this passage
CONCLUSION
printed heading
CONCLUSION PJM respectfully requests that the Commission accept this compliance filing as it complies with the requirements of the June Order.Read this passage
CERTIFICATE OF SERVICE
printed heading
Porter Wright & Talisman, P.C. 1200 G Street, N.W., Suite 600 Washington, D.C. 20005 (202) 393-1200 (phone) porter@wrightlaw.comRead this passage