PJM show cause order
Read topic-matched comments in EL26-67
Topics in the text: Cost allocation · Connecting load and generation · Filing procedure
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Who pays when a data center brings its own generator? Commissioner David LaCerte
- Pennsylvania’s consumer advocate challenges regional cost sharing Pennsylvania Office of Consumer Advocate
- Four state offices want the full upgrade cost charged to the new load Maryland Office of People’s Counsel, Ohio Consumers’ Counsel, Delaware Division of the Public Advocate and Illinois Attorney General
- An Indiana representative asks for federal review of large-load projects Rep. Victoria Spartz (Indiana’s 5th Congressional District)
- Rosner wants commitments that survive a canceled project Commissioner David Rosner
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
195 FERC ¶ 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.Read this passage Filed comments: Cost allocation
C. Extending New Transmission Services to Eligible Customers Taking Service on
printed heading
C.Read this passage
D. Interconnection Customers Serving Electrically Proximate Large Load and Co-
printed heading · Topic match: Connecting load and generation
EL26-67-000 - 4 - Over the past year, the Commission has taken action in numerous dockets1 to address issues related to (a) unprecedented increases in requests for transmission service to serve large loads2 and (b) growing interest in the co-location of loads with generating facilities (co-location…Read this passage Filed comments: Connecting load and generation
I. Background
PDF bookmark
I.Read this passage
Background
printed heading
BackgroundRead this passage
A. Growth of Large and Co-Located Loads and ANOPR
PDF bookmark · Topic match: Cost allocation
Dep’t of Energy, Resource Adequacy Report: Evaluating the Reliability & Security of the United States Electric Grid (July 2025), www.energy.gov/sites/default/files/2025- 07/DOE%20Final%20EO%20Report%20%28FINAL%20JULY%207%29.pdf). 18 Id. (citing NERC, 2024 Long- Term Reliability Assessment 8 (Dec.…Read this passage Filed comments: Cost allocation
B. Recent Proceedings Addressing Large and Co-Located Loads
PDF bookmark
Recent Proceedings Addressing Large and Co-Located Loads Over the past year, the Commission has begun to address, both sua sponte and in response to complaints and FPA section 20539 filings, the growing use of co-location arrangements.40 The Commission’s orders in those proceedings have addressed…Read this passage
1. PJM Co-Location Proceedings
PDF bookmark · Topic match: Connecting load and generation
EL26-67-000 - 14 - to co-location arrangements.41 The Commission explained when initiating that proceeding that the absence of such provisions may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations and how to do so in…Read this passage Filed comments: Connecting load and generation
2. SPP High Impact Large Load Process and High Impact Large Load Generation Assessment Processes
PDF bookmark · Topic match: Connecting load and generation
P 32 (explaining that SPP will grant HILLGA customers a new type of interconnection service, load limited resource interconnection service, which grants limited interconnection service solely to serve the associated HILL).Read this passage Filed comments: Connecting load and generation
3. SPP Conditional High Impact Large Load Service
PDF bookmark · Topic match: Reliability and curtailment
SPP Conditional High Impact Large Load Service On June 5, 2026, the Commission accepted revisions to SPP’s tariff to add a new type of non-firm transmission service, conditional high impact large load service 57 Id.Read this passage Filed comments: Reliability and curtailment
II. PJM’s Existing Processes
PDF bookmark
II.Read this passage
A. Existing Tariff Processes
PDF bookmark · Topic match: Cost allocation
EL26-67-000 - 22 - Tariff provides that each “Eligible Customer shall be obligated to pay for 100% of the costs of the minimum amount of Network Upgrades necessary to accommodate its New Service Request and that would not have been incurred under the Regional Transmission Expansion Plan [(RTEP)]…Read this passage Filed comments: Cost allocation
Attachment M-3 provides procedures for stakeholder review and comment on
printed heading · Topic match: Cost allocation
The company also proposed implementing an application process and specific requirements for potential customers with a projected load of at least 50 MW.”); id. (“Exelon subsidiary Commonwealth Edison Company (ComEd) has proposed revisions to Rider DE that clarify requirements and procedures for…Read this passage Filed comments: Cost allocation
B. Recent Stakeholder Proceedings in PJM
PDF bookmark · Topic match: Reliability and curtailment
As such, and as the Commission explained in the April Order Regarding Intent to Act, we find that the Commission must now take further action to ensure that PJM promptly proposes revisions to ensure that its Tariff remains just and reasonable.Read this passage Filed comments: Reliability and curtailment
III. Discussion
PDF bookmark
III.Read this passage
Discussion
printed heading · Topic match: Filing procedure
We emphasize that we will not grant such abeyances reflexively, that any abeyance will be limited to 90 days, and that we will look with great disfavor toward requests to extend the abeyance period.Read this passage Filed comments: Cost allocation
A. Transmission Service to Eligible Customers on Behalf of Large Loads
PDF bookmark
It also includes instances where an Eligible Customer requests a new or modified point of remaining directives, we expect a response to this order within the 60-day deadline set forth herein. 112 See, e.g., Idaho Power Co., 145 FERC ¶ 61,122 (2013); Canal Elec.Read this passage
1. Jurisdiction
PDF bookmark · Topic match: Retail and wholesale authority
Specifically, we find that it is within the Commission’s exclusive authority to ensure that transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers on behalf of large loads interconnecting…Read this passage Filed comments: Cost allocation
2. Tariff Provisions
PDF bookmark · Topic match: Cost allocation
Lastly, we are concerned that PJM’s existing Tariff fails to deter speculative or duplicative requests for transmission service by Eligible Customers on behalf of large loads.Read this passage Filed comments: Cost allocation
B. Cost Shifting Risk Among Transmission Customers
PDF bookmark · Topic match: Cost allocation
Cost Shifting Risk Among Transmission Customers We next preliminarily find that PJM’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for…Read this passage Filed comments: Cost allocation
1. Jurisdiction
PDF bookmark · Topic match: Cost allocation
To fulfill its responsibility to ensure that transmission rates are just and reasonable, the Commission must act to address the risk of cost shifting among transmission customers due to (1) the process transmission providers and/or transmission owners use to evaluate the facilities needed, and the…Read this passage Filed comments: Cost allocation
2. Additional Cost Transparency
PDF bookmark · Topic match: Cost allocation
The speed and scale with which Eligible Customers are seeking transmission service on behalf of large loads makes it difficult for interested parties, including transmission customers and state regulators, to accurately assess which transmission costs are driven by requests for transmission service…Read this passage Filed comments: Cost allocation
3. Cost Recovery Agreements
PDF bookmark · Topic match: Cost allocation
EL26-67-000 - 52 - protect wholesale transmission customers from cost shifting.169 Specifically, commenters in the record contend that, while a retail-level large load tariff protects the load serving entity taking wholesale transmission service and its retail customers, it fails “to provide any…Read this passage Filed comments: Cost allocation
C. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads
PDF bookmark · Topic match: Filing procedure
EL26-67-000 - 58 - take interim NITS, firm contract demand transmission service, and non-firm contract demand transmission service, an Eligible Customer must have necessary control technologies and/or protection systems, which may include a special protection scheme, to limit its energy withdrawals…Read this passage
D. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load
PDF bookmark · Topic match: Connecting load and generation
Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load In response to the ANOPR, a number of commenters agree that the ability to study new load and new generation together, when physically or electrically proximate, presents system benefits and can help address the…Read this passage Filed comments: Connecting load and generation
1. Jurisdiction
PDF bookmark · Topic match: Connecting load and generation
The Commission has exercised this jurisdiction previously in requiring generator interconnection services that allow certain generating facilities to interconnect more quickly through the use of provisional interconnection service and surplus interconnection service,212 and has approved…Read this passage Filed comments: Connecting load and generation
2. Definitions
PDF bookmark
Definitions For purposes of this order, it appears to be reasonable to use the term “electrically proximate large load” to mean a large load, as defined in this order,214 that is sufficiently electrically close to the interconnection customer’s requested point of interconnection, such that the…Read this passage
3. Tariff Provisions
PDF bookmark · Topic match: Connecting load and generation
Given that generator interconnection service in and of itself does not convey transmission service, we encourage PJM to consider, in responding to these concerns, what type of transmission service an Eligible Customer will need to take on behalf of the electrically proximate large load or large…Read this passage Filed comments: Connecting load and generation
E. Informational Report
PDF bookmark · Topic match: Reliability and curtailment
The informational report must include a detailed schedule of key milestones, such as stakeholder or PJM Board votes, that includes the estimated date on which PJM expects to file any such proposals with the Commission.Read this passage Filed comments: Reliability and curtailment
IV. Briefing Questions
PDF bookmark · Topic match: Cost allocation
We find that there may be a variety of possible approaches to protect customers from significant cost shifts associated with Network Upgrades triggered by large loads.Read this passage Filed comments: Cost allocation
I. Overview of Today’s Orders
PDF bookmark · Topic match: Cost allocation
Overview of Today’s Orders In each of today’s orders to show cause, the Commission identifies a series of issues raised by the ongoing growth of large loads, directs briefing on whether existing tariffs remain just and reasonable in light of those developments, and describes possible solutions to…Read this passage Filed comments: Cost allocation
II. The Commission Needs Good Records to Ensure Reasoned Decision-Making
PDF bookmark
The Commission Needs Good Records to Ensure Reasoned Decision-Making I first want to emphasize that the Commission needs active participation from interested stakeholders to develop thorough records in each region.Read this passage
III. The Commission Needs to Pursue Meaningful Customer Protection
PDF bookmark · Topic match: Cost allocation
As we develop the new infrastructure, many have raised concerns about whether these costs are being fairly assigned to new and existing customers, whose benefits must be commensurate with the costs they pay.Read this passage Filed comments: Cost allocation
IV. The Commission Needs to Understand the Implications of Extending New Transmission Services to Additional Loads and Regions
PDF bookmark · Topic match: Cost allocation
While it is important to identify innovative solutions that can adapt to the needs of the system, the Commission and grid operators must also be careful not to implement changes that create unforeseen reliability risks.Read this passage Filed comments: Cost allocation
V. The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies
PDF bookmark
The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies Lastly, today we preliminarily find that each RTO/ISO’s tariff is unjust and unreasonable because the tariff lacks clear and consistent provisions requiring the evaluation of alternative transmission technologies…Read this passage
VI. Conclusion
PDF bookmark
VI.Read this passage
Conclusion
printed heading · Topic match: Cost allocation
While this is a long journey, even so, we must continue to move at breakneck pace to win the AI race.Read this passage Filed comments: Cost allocation