Notice of Extension of Time granting PJM and the Indicated PJM Transmission Owners 90 days, to November 16, 2026
FERC grants PJM and the Indicated PJM Transmission Owners a 90-day extension, to November 16, 2026, to comply with certain directives of the June 18 co-located load order, so the compliance can proceed with the large load show cause response.
Changes the schedule. Moves the E-2 co-location compliance deadline to November 16, 2026 to align with PJM's E-7 show cause response, while Interim NITS provisions stay due August 17.
E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-2 PJM: Interim NITS (P 2, p. 3)
Key points
- PJM and the Indicated TOs each moved on July 28, 2026 for 90 more days to comply with the co-location order.
On July 28, 2026, PJM filed a motion for a 90-day extension of time to comply with certain directives in the Commission’s June 18, 2026 order in this proceeding, Source text
- The Indicated TOs say the compliance issues overlap significantly with their show cause order work.
the issues that PJM and Indicated TOs must address on compliance significantly overlap with the issues PJM and Indicated TOs are addressing in response to the Large Load Show Cause Order. Source text
- Constellation supported the motion but said PJM must still file complete Interim NITS provisions on August 17, 2026.
filed an answer supporting PJM’s motion but with the clarification that PJM remains obligated to file, on August 17, 2026, a complete set of provisions to facilitate Interim NITS. Source text
- FERC grants the extension to November 16, 2026 for PJM and the PJM transmission owners.
Upon consideration, notice is hereby given that an extension of 90 days is granted. Source text
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Filing procedure
What the document says
Unpaginated filing
FERC gives PJM and its owners 90 more days, to November 16, on co-location.
The deadline for PJM to comply with certain directives of the Co-Located Load Order, and the deadline for the PJM transmission owners to comply with the directives of the Co-Located Load Order, is extended to and including November 16, 2026. Source textFiled comments: Connecting load and generation
Unpaginated filing
The extension lines co-location compliance up with PJM's large-load section 205 filing.
to allow PJM to develop the remaining aspects of its compliance filing to comply with the Co-Located Load Order in conjunction with a Federal Power Act section 205 filing being developed in response to the Large Load Show Cause Order Source textFiled comments: Connecting load and generation
Unpaginated filing
PJM still owed an August 17 partial filing; Constellation wanted full Interim NITS terms.
if its requested relief is granted, it will still make a compliance filing on August 17, 2026 that addresses certain defined terms Source text
Unpaginated filing
PJM still owed an August 17 partial filing; Constellation wanted full Interim NITS terms.
with the clarification that PJM remains obligated to file, on August 17, 2026, a complete set of provisions to facilitate Interim NITS Source text
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
EL25-49-002 EL25-49-000 AD24-11-001 EL25-20-001 (consolidated) ER26-1479-000 NOTICE OF EXTENSION OF TIME (August 14, 2026) On July 28, 2026, PJM filed a motion for a 90-day extension of time to comply with certain directives in the Commission’s June 18, 2026 order in this proceeding,[fn:2] which…Read this passage Filed comments: Connecting load and generation
Footnotes
Word notes · Topic match: Connecting load and generation
Footnotes [fn:2] See PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (Co-Located Load Order). [fn:3] See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (Large Load Show Cause Order).Read this passage Filed comments: Connecting load and generation