EL26-67-000 · 2026-07-08 · Global Capacity Alliance

Motion to Intervene and Initial Comments of Global Capacity Alliance in response to FERC's 06/18/2026 Show Cause Order

Global Capacity Alliance moves to intervene and comments on the June 18 show cause orders, proposing Front-of-the-Meter Netting and a Capacity Attribution Contract so flexible large loads can pair with co-located resources while upgrades are built.

Asks FERC to: Grant intervention and direct the RTOs and ISOs, in responding to the show cause orders, to evaluate Front-of-the-Meter Netting frameworks and independent standard-setting pathways.

Answers the order. Comment filed across the show cause dockets; its netting and interim non-firm service concept speaks to the flexible-load service and co-location topics the June orders direct RTOs to address.

E-7 PJM: Service for flexible loads (P 85, p. 56) E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7)

Key points

  1. GCA says a separately metered load and battery at one substation can be curtailed and dispatched at once because dispatch has no link between them.
    A 100 MW data center and a 100 MW BESS sit at the same substation on separate meters. PDF p. 1
  2. FTM-Netting rests on a telemetry shield, a post-operating-day compliance ledger and scarcity yielding in system-wide emergencies.
    Telemetry Shield: Each dispatch interval, the Market Participant (MP) dynamically adjusts the load's consumption floor via market telemetry to match the paired resource's availability PDF p. 2
  3. A private Capacity Attribution Contract bridges non-firm energization and completed network upgrades, then sunsets when the load turns firm.
    its commercial engine is the private Capacity Attribution Contract (CAC), which bridges the gap between initial non-firm energization and completed network upgrades. PDF p. 2
  4. Because the assets are separately metered they stay visible in planning models, unlike behind-the-meter setups.
    they are studied as standard, independent interconnections—fully visible to RTO planning models and subject to existing constraint analyses. PDF p. 2
  5. GCA asks FERC to direct RTO and ISO responses to evaluate FTM-Netting.
    urges the Commission to direct the RTOs and ISOs, in responding to the June 18, 2026, Show Cause Orders, to actively evaluate and incorporate Front-of-the-Meter (FTM) Netting frameworks PDF p. 3

Read topic-matched comments in EL26-67

Topics in the text: Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

FERC-001 Version 1.1 0 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Interconnection of Large Loads to the Interstate Transmission System | Docket No.
Read this passage

I. INTRODUCTION AND MOTION TO INTERVENE

printed heading

Accordingly, the GCA respectfully requests the Commission grant it intervenor party status in these proceedings.
Read this passage

II. FRONT-OF-THE-METER NETTING AND THE ATTRIBUTABILITY GAP

printed heading · Topic match: Reliability and curtailment

Because they are treated independently, the resource’s provided mitigation is socialized to the grid, leaving the load still exposed to curtailment even while the paired resource is offsetting its impact, MW for MW.
Read this passage Filed comments: Reliability and curtailment

III. THE TECHNICAL AND COMMERCIAL CORE OF FTM-NETTING

printed heading · Topic match: Reliability and curtailment

While rare, controlled shedding during system emergencies is possible due to on-site backup generation, but frequent rapid curtailment events are technically and commercially unviable.
Read this passage Filed comments: Reliability and curtailment

IV. TRANSMISSION PLANNING ALIGNMENT AND GRID RELIABILITY

printed heading · Topic match: Reliability and curtailment

Reliability Assurance: The Scarcity Release During system-wide emergency conditions, RTOs may require FTM-Netting participants to execute a Scarcity Release, lowering the telemetry shield so both assets see full market dispatch / curtailment.
Read this passage Filed comments: Reliability and curtailment

V. IMPLEMENTATION AND BENEFITS

printed heading · Topic match: Cost allocation

The Externalities of FTM-Netting: A System-Level Assessment By aligning the commercial imperatives of developers with macro-grid operational needs, FTM-Netting delivers compounding system benefits: • Grid Visibility & Reliability: Halts the "BTM Exodus" by keeping new generation visible to RTOs. •…
Read this passage Filed comments: Cost allocation

VI. CONCLUSION AND REQUEST FOR RELIEF

printed heading · Topic match: Cost allocation

CONCLUSION AND REQUEST FOR RELIEF For the foregoing reasons, the GCA respectfully requests that the Commission grant its Motion to Intervene in these consolidated proceedings and accord it full party status with all attendant rights.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated at Austin, Texas this 8th day of July, 2026. ______________________________ Jesse Gossett Jesse Gossett, Interim Executive Director Global Capacity Alliance