EL26-67-000 · 2026-07-09 · Individual No Affiliation

Motion to Intervene and Comments of Evan Pierce re the large-load interconnection tariff provisions

New Era Energy & Digital, a data center developer, moves to intervene in EL26-67 and files limited comments asking PJM to address a Maximum Net Withdrawal study framework and fast-track treatment of uprates and reactivated capacity in its adequacy report.

Asks FERC to: Grant intervention and have PJM address Maximum Net Withdrawal for paired load and generation, and expedited uprate and reactivation pathways, in its forthcoming filings.

Answers the order. Limited comments on E-7 asking PJM to address proximate-generation study treatment in its show cause response and uprate fast-tracking in the 30-day adequacy report.

E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8) E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7)

Key points

  1. New Era says PJM should study a load paired with dependable nearby generation by its enforceable maximum net withdrawal rather than full gross demand.
    PJM should evaluate the project based on the facility’s enforceable maximum net withdrawal from the transmission system, rather than assuming the facility will impose its full gross demand PDF p. 4
  2. A net-withdrawal cap would need metering, controls, operator visibility and tariff consequences for exceedance.
    a binding net-withdrawal cap in the relevant service agreement or other tariff- governed arrangement PDF p. 4
  3. PJM should say what transmission service an Eligible Customer takes for a load operated under such a cap.
    PJM should also explain what transmission service the Eligible Customer must take for a large load operated subject to an enforceable Maximum Net Withdrawal. PDF p. 5
  4. The 30-day adequacy report should cover expedited study of low-risk uprates at existing plants.
    PJM should address whether its Tariff provides an adequate pathway for expedited treatment of uprates at existing generating facilities. PDF p. 5
  5. It also asks about expedited reconnection of retired or mothballed capacity without bypassing reliability review.
    The purpose would not be to bypass reliability review, but to avoid subjecting bounded reactivations of existing capacity to procedures designed for wholly new speculative projects. PDF p. 6

Read topic-matched comments in EL26-67

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.
Read this passage

I. MOTION TO INTERVENE

printed heading

MOTION TO INTERVENE New Era Energy & Digital Inc. is a data center developer pursuing data center and energy development in the PJM service area.
Read this passage

III. INTRODUCTION AND RELEVANT BACKGROUND

printed heading

III.
Read this passage

A. The Commission Opened This Section 206 Proceeding in Response to Rapid

printed heading · Topic match: Cost allocation

The Commission Opened This Section 206 Proceeding in Response to Rapid Large-Load Growth and the Need for Tariff-Specific Reforms in PJM.
Read this passage Filed comments: Cost allocation

B. The Commission Identified PJM-Specific Concerns Regarding Large Loads, Co-

printed heading · Topic match: Connecting load and generation

Tariff appears unjust and unreasonable because it lacks transmission services reflecting those operational characteristics.11 Similarly, the Commission preliminarily found that PJM’s Tariff appears to lack generator interconnection study procedures and services that allow interconnection customers…
Read this passage Filed comments: Connecting load and generation

IV. LIMITED COMMENTS

printed heading · Topic match: Connecting load and generation

These comments are directed to the specific issues raised in the Commission’s June 18, 2026 order: the treatment of generation serving electrically proximate or large co-located load, and PJM’s required report on the availability of adequate generation to serve existing and new large loads.15
Read this passage Filed comments: Connecting load and generation

A. PJM Should Address Maximum Net Withdrawal as Part of Any Framework for

printed heading · Topic match: Connecting load and generation

The Commission expressly encouraged PJM to consider what type of transmission service an Eligible Customer will need to take on behalf of electrically proximate large load or large co-located load, noting that generator interconnection service does not itself convey transmission service.19 A…
Read this passage Filed comments: Connecting load and generation

B. PJM’s Resource-Adequacy Report Should Address Fast-Track Treatment for Safe

printed heading · Topic match: Connecting load and generation

Such treatment should be limited to modifications that rely on existing interconnection facilities, do not involve a change in generation technology or fuel type, can be evaluated independently through existing system models or a limited-scope study (a narrower review focused on the incremental…
Read this passage Filed comments: Connecting load and generation

C. Reservation of Rights

printed heading

Reservation of Rights Because the Commission has directed PJM to file a 30-day informational report and a 60-day show-cause response, and has allowed interested entities to respond after those filings, New Era Energy & Digital submits these comments on a limited basis and reserves the right to…
Read this passage

V. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, New Era Energy & Digital respectfully requests that the Commission grant its motion to intervene and consider these limited comments in evaluating PJM’s forthcoming filings in this proceeding. 22 Order, 195 FERC ¶ 61,211, Ordering Paras. (B), (C), (E).
Read this passage