Eolian, L.P. submits Limited Request for Clarification or, In the Alternative, Rehearing of the 06/18/2026 Order Instituting Proceedings Under Section 206 of the Federal Power Act
Eolian, L.P. supports the June 18 orders and asks FERC to clarify or rehear one limit: permanent load-limited generator interconnection service for electrically proximate front-of-the-meter generation, and the flexibility RTOs have to adopt minimal generator study reforms.
Asks FERC to: Clarify that electrically proximate generation may access permanent load-limited interconnection service, that RTOs are encouraged to offer it, and that minimal generator study reforms do not suffice; otherwise grant rehearing.
Answers the order. Rehearing and clarification request across the PJM, NYISO, MISO, CAISO and ISO-NE show cause orders on generator interconnection service for generation serving electrically proximate large loads.
E-12 NYISO: Proximate-generation service (P 121, p. 72) E-11 ISO-NE: Proximate-generation service (P 7, p. 7) E-7 PJM: Service for flexible loads (P 85, p. 56)
Key points
- Eolian says the orders allow permanent load-limited generator service only for co-located generation and make it temporary for electrically proximate generation.
the Commission appears to categorically limit the availability of permanent generator interconnection services to co-located generation PDF p. 2
- It says limited generator service will limit uptake of the new permanent contract demand and Interim NITS services.
large loads’ ability to make use of the new transmission services will be severely limited if new front-of-the-meter generation projects PDF p. 2
- Eolian asks FERC to confirm RTOs may offer permanent load-limited generator interconnection service and to encourage broad availability.
the Commission strongly encourage RTO/ISOs to make such service broadly available. PDF p. 3
- Eolian asks FERC to close language that could let RTOs adopt minimal generator interconnection reforms.
The Commission must clarify this discussion, so that it does not inadvertently create a loophole that would undermine the critical benefits of its Orders PDF p. 3
- Eolian says large loads cannot use the new services widely unless new generation can interconnect without queue cost and timing uncertainty.
Large loads will not be able to transact with new front-of-the-meter resources if resource developers face significant commercial barriers to interconnection PDF p. 5
Read topic-matched comments in EL26-67
Topics in the text: Connecting load and generation · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
OF THE COMMISSION’S ORDERS INSTITUTING PROCEEDINGS UNDER SECTION 206 OF THE FEDERAL POWER ACT Pursuant to section 313(a) of the Federal Power Act (“FPA”), 16 U.S.C. § 825l (2024), and Rule 713 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or…Read this passage Filed comments: Connecting load and generation
I. CONCISE STATEMENT OF ISSUES AND SPECIFICATION OF ERRORS
printed heading · Topic match: Connecting load and generation
CONCISE STATEMENT OF ISSUES AND SPECIFICATION OF ERRORS (1) The Commission’s Orders arbitrarily and capriciously limit RTO/ISOs’ ability to put in place a replacement rate that will ensure just and reasonable and not unduly 4 discriminatory rates by not requiring and/or by limiting their ability to…Read this passage Filed comments: Connecting load and generation
II. ARGUMENT
printed heading
II.Read this passage
A. The Commission’s Orders Seek to Address Urgent Problems Due to Large
printed heading · Topic match: Connecting load and generation
The Orders specify that while “it may be reasonable for the generator interconnection service to be permanent” “[t]o the extent that the interconnection customer’s generating facility is serving a large co-located load,” where “the interconnection customer’s generating facility is serving an…Read this passage Filed comments: Connecting load and generation
B. Absent modification or clarification, the Commission’s Orders unreasonably
printed heading · Topic match: Connecting load and generation
For permanent LLGIS, it asks the same question about locating new generation at Point A (behind the load’s point of interconnection) or at Point B.Read this passage Filed comments: Connecting load and generation
C. The Orders fail to require broad enough reforms to the generator
printed heading · Topic match: Connecting load and generation
Any flexibility to tailor the generator interconnection reforms to the unique circumstances of the region must be paired with an obligation on the RTO/ISO to show that the set of reforms it proposes will enable a pathway for significant generating capacity to provide load-limited interconnection,…Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
III.Read this passage
CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the foregoing reasons, Eolian respectfully requests that the Commission grant the requested clarifications or, in the alternative, grant rehearing.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated: July 20, 2026 /s/ Nathan Lobel Nathan Lobel Roselle LLP 300 New Jersey Ave.Read this passage
ATTACHMENT A
printed heading
ATTACHMENT A UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.Read this passage
I. QUALIFICATIONS
printed heading
I am a Senior Consultant at The Brattle Group (Brattle). 2 I am an expert on wholesale market design and reliability implications of changes in the power 3 system.Read this passage
II. ASSIGNMENT
printed heading
ASSIGNMENT 20 I was asked by Eolian, L.P. to assess the five recent Commission Orders on co-located and 21 electrically proximate generation and load pairings, issued June 18, 2026 in the above-captioned 22 dockets.Read this passage
A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy
printed heading
Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No.Read this passage
III. BACKGROUND
printed heading
III.Read this passage
BACKGROUND
printed heading · Topic match: Connecting load and generation
Five of the regions (all but SPP) addressed an additional tariff reform need: 4) new 11 resource interconnection service for generation serving electrically proximate large load or co- 12 located load.Read this passage Filed comments: Connecting load and generation
IV. PERMANENT LOAD-LIMITED GENERATOR INTERCONNECTION SERVICE
printed heading · Topic match: Connecting load and generation
Therefore, if the 7 test fails in either case, the generator must go through the standard interconnection queue 8 process.Read this passage Filed comments: Connecting load and generation