EL26-67-001 · 2026-07-20 · Eolian, L.P.

Eolian, L.P. submits Limited Request for Clarification or, In the Alternative, Rehearing of the 06/18/2026 Order Instituting Proceedings Under Section 206 of the Federal Power Act

Eolian, L.P. supports the June 18 orders and asks FERC to clarify or rehear one limit: permanent load-limited generator interconnection service for electrically proximate front-of-the-meter generation, and the flexibility RTOs have to adopt minimal generator study reforms.

Asks FERC to: Clarify that electrically proximate generation may access permanent load-limited interconnection service, that RTOs are encouraged to offer it, and that minimal generator study reforms do not suffice; otherwise grant rehearing.

Answers the order. Rehearing and clarification request across the PJM, NYISO, MISO, CAISO and ISO-NE show cause orders on generator interconnection service for generation serving electrically proximate large loads.

E-12 NYISO: Proximate-generation service (P 121, p. 72) E-11 ISO-NE: Proximate-generation service (P 7, p. 7) E-7 PJM: Service for flexible loads (P 85, p. 56)

Key points

  1. Eolian says the orders allow permanent load-limited generator service only for co-located generation and make it temporary for electrically proximate generation.
    the Commission appears to categorically limit the availability of permanent generator interconnection services to co-located generation PDF p. 2
  2. It says limited generator service will limit uptake of the new permanent contract demand and Interim NITS services.
    large loads’ ability to make use of the new transmission services will be severely limited if new front-of-the-meter generation projects PDF p. 2
  3. Eolian asks FERC to confirm RTOs may offer permanent load-limited generator interconnection service and to encourage broad availability.
    the Commission strongly encourage RTO/ISOs to make such service broadly available. PDF p. 3
  4. Eolian asks FERC to close language that could let RTOs adopt minimal generator interconnection reforms.
    The Commission must clarify this discussion, so that it does not inadvertently create a loophole that would undermine the critical benefits of its Orders PDF p. 3
  5. Eolian says large loads cannot use the new services widely unless new generation can interconnect without queue cost and timing uncertainty.
    Large loads will not be able to transact with new front-of-the-meter resources if resource developers face significant commercial barriers to interconnection PDF p. 5

Read topic-matched comments in EL26-67

Topics in the text: Connecting load and generation · Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

OF THE COMMISSION’S ORDERS INSTITUTING PROCEEDINGS UNDER SECTION 206 OF THE FEDERAL POWER ACT Pursuant to section 313(a) of the Federal Power Act (“FPA”), 16 U.S.C. § 825l (2024), and Rule 713 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or…
Read this passage Filed comments: Connecting load and generation

I. CONCISE STATEMENT OF ISSUES AND SPECIFICATION OF ERRORS

printed heading · Topic match: Connecting load and generation

CONCISE STATEMENT OF ISSUES AND SPECIFICATION OF ERRORS (1) The Commission’s Orders arbitrarily and capriciously limit RTO/ISOs’ ability to put in place a replacement rate that will ensure just and reasonable and not unduly 4 discriminatory rates by not requiring and/or by limiting their ability to…
Read this passage Filed comments: Connecting load and generation

II. ARGUMENT

printed heading

II.
Read this passage

A. The Commission’s Orders Seek to Address Urgent Problems Due to Large

printed heading · Topic match: Connecting load and generation

The Orders specify that while “it may be reasonable for the generator interconnection service to be permanent” “[t]o the extent that the interconnection customer’s generating facility is serving a large co-located load,” where “the interconnection customer’s generating facility is serving an…
Read this passage Filed comments: Connecting load and generation

B. Absent modification or clarification, the Commission’s Orders unreasonably

printed heading · Topic match: Connecting load and generation

For permanent LLGIS, it asks the same question about locating new generation at Point A (behind the load’s point of interconnection) or at Point B.
Read this passage Filed comments: Connecting load and generation

C. The Orders fail to require broad enough reforms to the generator

printed heading · Topic match: Connecting load and generation

Any flexibility to tailor the generator interconnection reforms to the unique circumstances of the region must be paired with an obligation on the RTO/ISO to show that the set of reforms it proposes will enable a pathway for significant generating capacity to provide load-limited interconnection,…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading

III.
Read this passage

CONCLUSION

printed heading · Topic match: Filing procedure

CONCLUSION For the foregoing reasons, Eolian respectfully requests that the Commission grant the requested clarifications or, in the alternative, grant rehearing.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: July 20, 2026 /s/ Nathan Lobel Nathan Lobel Roselle LLP 300 New Jersey Ave.
Read this passage

ATTACHMENT A

printed heading

ATTACHMENT A UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.
Read this passage

I. QUALIFICATIONS

printed heading

I am a Senior Consultant at The Brattle Group (Brattle). 2 I am an expert on wholesale market design and reliability implications of changes in the power 3 system.
Read this passage

II. ASSIGNMENT

printed heading

ASSIGNMENT 20 I was asked by Eolian, L.P. to assess the five recent Commission Orders on co-located and 21 electrically proximate generation and load pairings, issued June 18, 2026 in the above-captioned 22 dockets.
Read this passage

A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy

printed heading

Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy as part of Docket No.
Read this passage

III. BACKGROUND

printed heading

III.
Read this passage

BACKGROUND

printed heading · Topic match: Connecting load and generation

Five of the regions (all but SPP) addressed an additional tariff reform need: 4) new 11 resource interconnection service for generation serving electrically proximate large load or co- 12 located load.
Read this passage Filed comments: Connecting load and generation

IV. PERMANENT LOAD-LIMITED GENERATOR INTERCONNECTION SERVICE

printed heading · Topic match: Connecting load and generation

Therefore, if the 7 test fails in either case, the generator must go through the standard interconnection queue 8 process.
Read this passage Filed comments: Connecting load and generation