EL26-71-000 · 2026-08-03 · Southern California Edison CompanySan Diego Gas & Electric CompanyPacific Gas & Electric Company ,SunZia Transmission, LLC ,Citizens Sunrise Transmission LLC ,Citizens Sycamore-Penasquitos Transmission LLC ,Citizens S-Line Transmission LLC ,LS Power Grid California, LLC ,DesertLink, LLC ,Horizon West Transmission, LLC ,GridLiance West LLC ,Trans Bay Cable, LLC ,Viridon Path 15 LLC ,Valley Electric Association, Inc. ,Startrans IO, L.L.C. ,

Request for Abeyance of Southern California Edison Company, et al. in response to the Order issued on 06/18/2026

Fifteen CAISO transmission owners (the Joint PTOs) ask FERC to hold the 60-day show cause response deadline in abeyance for 90 days, to November 16, 2026, so each can prepare section 205 TO Tariff filings coordinated with CAISO.

Asks FERC to: Hold the deadline to respond to the show cause order and briefing questions in abeyance until November 16, 2026.

Changes the schedule. Requests the up-to-90-day abeyance option in the E-10 CAISO show cause order and previews TO Tariff filings on the study process and the pro forma cost recovery agreement. FERC granted it August 14, 2026.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25)

Key points

  1. The Joint PTOs seek a 90-day full abeyance of the 60-day response deadline to prepare section 205 TO Tariff filings.
    The Joint PTOs seek a 90-day full abeyance of the current 60-day deadline to respond to all issues raised in the OSC PDF p. 2
  2. Tariff changes will vary by PTO because some serve load and others do not.
    some PTOs serve load while others do not, for example PDF p. 3
  3. Filing on August 17 would likely conflict with CAISO's design, so the Joint PTOs want a coordinated set of filings.
    Filing tariff revisions on August 17 would require the Joint PTOs to submit tariff provisions that would likely conflict with the CAISO’s design PDF p. 4
  4. The Joint PTOs read the co-location, flexible service and proximate generation findings as aimed at the CAISO Tariff.
    the third, fourth, and fifth issues – co-located load, flexible services, and proximate load – are primarily directed at the CAISO Tariff PDF p. 5
  5. CAISO's Board acts October 28, so CAISO Tariff revisions are unlikely to be final until near November 16.
    The CAISO does not currently plan to seek Board approval until October 28, just over two and a half weeks before a 90-day extended filing deadline PDF p. 6
  6. The expected filings cover study, application and operational procedures plus transparency, cost recovery, financial security and rate treatment.
    present revisions to the TO Tariffs to include study, application, and operational procedures for the interconnection of large loads PDF p. 7
  7. The Joint PTOs also ask that the briefing question deadline be tolled for 90 days.
    The Joint PTOs also request to toll the deadline to respond to the briefing questions for 90 days PDF p. 7

Topics in the text: Filing procedure · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

EL26-71-000 2 REQUEST FOR ABEYANCE OF SOUTHERN CALIFORNIA EDISON COMPANY; PACIFIC GAS AND ELECTRIC COMPANY; SAN DIEGO GAS & ELECTRIC COMPANY; CITIZENS SUNRISE TRANSMISSION LLC; CITIZENS SYCAMORE-PENASQUITOS TRANSMISSION LLC; CITIZENS S-LINE TRANSMISSION LLC; SUNZIA TRANSMISSION, LLC; LS POWER GRID…
Read this passage

I. INTRODUCTION

PDF bookmark

I.
Read this passage

INTRODUCTION

printed heading · Topic match: Filing procedure

The Joint PTOs acknowledge that there are significant differences among the California PTOs (some PTOs serve load while others do not, for example) such that the appropriate TO Tariff changes to implement the OSC will also likely vary from PTO to PTO such that each PTO must develop its proposed…
Read this passage

II. ARGUMENT

PDF bookmark · Topic match: Filing procedure

ARGUMENT In the OSC, the Commission states that it will consider requests for abeyances of up to 90 days, which should include both (1) a robust description of the content of a potential future filing under FPA section 205 and (2) a reasoned and specific explanation of when such a filing is…
Read this passage

A. Proposed TO Tariff Revisions

PDF bookmark · Topic match: Filing procedure

The Joint PTOs have already been meeting with the CAISO weekly, and have coordinated in developing their respective requests for abeyance, including by conferring regarding the issues expected to be addressed, the contemplated process for implementing appropriate FPA section 205 revisions, and the…
Read this passage

B. Briefing Questions

PDF bookmark · Topic match: Filing procedure

Briefing Questions The Commission also identifies several issues for further briefing.12 The Joint PTOs also request to toll the deadline to respond to the briefing questions for 90 days, consistent with the OSC’s explanation of the effect of an abeyance.13 The Joint PTOs believe an abeyance is…
Read this passage

III. Conclusion

PDF bookmark

III.
Read this passage

CONCLUSION

printed heading · Topic match: Filing procedure

Kenney Attorneys for SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770 Telephone: (626) 302-9519 E-mail: Ellen.Kenney@sce.com Jonathan J.
Read this passage

CERTIFICATE OF SERVICE

printed heading · Topic match: Filing procedure

Dated at Rosemead, California, this 3rd day of August 2026. /s/ Karen Abarca Karen Abarca Senior Legal Administrative Assistant SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770
Read this passage