ER26-3380-000 · 2026-08-21 · Organization of PJM States, Inc.

Comments of the Organization of PJM States, Inc. in support of PJM Interconnection, L.L.C.’s 07/31/2026 filing

The Organization of PJM States, supported by 13 of its member commissions, files comments backing PJM's July 31 Reliability Backstop Procurement proposal and urging quick FERC action, while noting that retail cost allocation stays with state regulators.

Asks FERC to: Accept PJM's Tariff and RAA revisions and let PJM implement the Reliability Backstop Procurement without disrupting later capacity auctions.

Parallel proceeding. Comments in PJM's separate backstop procurement docket ER26-3380, the capacity-adequacy track that runs beside the E-7 order's 30-day report on how PJM will ensure generation for large loads.

E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)

Key points

  1. OPSI supports the filing and asks FERC to act fast so later capacity auctions keep their schedule.
    OPSI encourages the Commission to act expeditiously so that PJM can implement the RBP without disrupting the schedule for subsequent capacity auctions. PDF p. 1
  2. OPSI backs a supplemental procurement equal to the 2028/2029 auction shortfall.
    OPSI supports PJM's proposal to implement a supplemental procurement of new capacity equal to the shortfall observed in the BRA for the 2028/2029 Delivery Year to serve large loads. PDF p. 2
  3. OPSI says allocating backstop costs to retail customers remains with state regulators.
    Under the Federal Power Act, the allocation of RBP costs to retail customers remains within the jurisdiction of retail regulators. PDF p. 2
  4. OPSI supports the new-capacity eligibility test so offsets add capacity.
    helps ensure that bilateral offsets and RBP procurements result in a genuine increase in regional capacity PDF p. 3
  5. OPSI strongly supports the voluntary bilateral matching process that lets large loads procure capacity and lower the procurement target.
    OPSI strongly supports the ongoing voluntary, iterative bilateral matching process through which new large loads may procure new capacity directly PDF p. 3
  6. OPSI recommends PJM revise the target and load forecast if load drops out before the procurement ends.
    should an electric distribution company ("EDC") / load serving entity ("LSE") confirm before completion of the RBP that a specific amount of load in the relevant load forecast is no longer expected to materialize, PJM would revise its RBP target and load forecast. PDF p. 3

Read topic-matched comments in ER26-3380

Topics in the text: Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.
Read this passage Filed comments: Reliability and curtailment

I. COMMENTS

printed heading · Topic match: Reliability and curtailment

Under the Federal Power Act, the allocation of RBP costs to retail customers remains within the jurisdiction of retail regulators.6 Accordingly, several states have already begun implementing or considering retail ratemaking reforms designed to more closely align the costs associated with new…
Read this passage Filed comments: Reliability and curtailment

II. CONCLUSION

printed heading

II.
Read this passage

CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, OPSI respectfully encourages the Commission to accept PJM’s proposed Tariff and RAA revisions and permit PJM to implement the RBP while continuing to pursue related reforms necessary to address the challenges posed by large-load growth.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Sloan Executive Director Organization of PJM States, Inc. 700 Barksdale Road, Suite 1 Newark, DE 19711 Tel: 601-214-8481 Dated at Newark, Delaware this August 21, 2026.
Read this passage