EL26-70-000 · 2026-09-10 · US HOUSE OF REPRESENTATIVES

Comments of U.S. House of Representatives Victoria Spartz requesting independent federal review of the energy generation, grid resiliency, transmission, water-resource, and consumer-cost implications etc

Rep. Victoria Spartz writes to the Energy and Interior secretaries, copying FERC, asking for an independent federal review of generation, transmission, water and cost allocation for the LEAP district in Lebanon, Indiana, citing FERC's MISO show cause order.

Asks FERC to: Have the Departments of Energy and Interior coordinate with FERC on an independent review of grid reliability, water, infrastructure, cost allocation and transparency for LEAP and other Indiana data center projects.

Background. A congressional letter, copied to FERC and filed in the MISO docket, that applies the E-8 order's cost-shifting findings and cost-recovery directives to a specific Indiana load cluster.

E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Minimum cost recovery / security (P 119, p. 74)

Key points

  1. Spartz says she cannot get clear numbers on energy, water and cost for large Indiana data center projects, partly because of nondisclosure agreements.
    Non-disclosure agreements and confidentiality arrangements have further limited transparency on matters affecting Indiana’s grid, water resources, taxpayers, and utility customers. PDF p. 1
  2. Meta announced a data center campus of more than $10 billion and about 1 GW at LEAP.
    Meta announced plans for a more than $10 billion data-center campus at LEAP, with 10 planned data centers and approximately 1 GW of capacity. PDF p. 1
  3. MISO planning documents put LEAP demand near 1,200 MW, with Wabash Valley Phase 2 transmission at about $345 million and Phase 1 at about $222 million.
    MISO planning documents estimate total LEAP demand at approximately 1,200 MW. PDF p. 2
  4. She summarizes FERC's MISO findings on cost shifting, Network Upgrade transparency, Cost Recovery Agreements and protections against stranded costs.
    FERC directed MISO and its transmission owners to address cost shifting, Network Upgrade transparency, Cost Recovery Agreements, financial protections against stranded infrastructure costs, and alternatives to traditional Network Upgrades PDF p. 3
  5. She requests project-level cost data and the enforceable protections that guard customers if projected loads do not materialize.
    Cost Recovery Agreements, minimum-demand commitments, financial guarantees, collateral, take-or-pay provisions, and other protections against stranded costs if projected loads are delayed, reduced, or never materialize. PDF p. 4

Read topic-matched comments in EL26-70

Topics in the text: Cost allocation · Credit and exit

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Pages 1 to 4

page range · Topic match: Cost allocation

However, development must be economically responsible.
Read this passage Filed comments: Cost allocation

Page 5

page range

The cumulative effects of these loads on generation, transmission, utility rates, water resources, and taxpayers must be evaluated, not merely each project in isolation.
Read this passage