Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the Comments and Protests re the proposal to establish Interconnection Reliability Requirements for Large Loads
MISO answers the comments and protests on its large-load reliability proposal, defends its definitions, transition provisions and Tariff/BPM split, and asks FERC to accept the proposal unchanged.
Asks FERC to: Accept the answer and accept the IRR Proposal without modification or condition, effective December 4, 2026.
Answers the order. MISO's reply to protests of its first filing after the E-8 order, defending it as a response to the order's findings on large load definition and ongoing operational requirements.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- MISO says the pleadings broadly support the proposal and only one protest asks for rejection with refiling by end of 2027.
only one protest requests the revisions to be rejected and MISO directed to file revised requirements by the end of 2027. PDF p. 2
- MISO says the comments offer alternatives but do not show the proposal fails section 205.
but do not establish that the framework proposed by MISO fails to satisfy the requirements of Section 205 of the Federal Power Act. PDF p. 3
- MISO asks that the proposal be accepted without modification and without expanding the proceeding to other large-load issues.
MISO respectfully requests that the IRR Proposal be accepted without modification and grant the requested effective date of December 4, 2026. PDF p. 3
- MISO ties the proposal to the E-8 findings on a large load definition and ongoing operational requirements.
a definition of large load sufficient to capture loads that present the unique challenges described in the Show Cause Order PDF p. 4
- On scope, MISO says the proposal does not create a regime for distribution-connected load not taking MISO Transmission Service.
the IRR Proposal does not create a free-standing MISO reliability regime for distribution- connected load that is not taking MISO Transmission Service. PDF p. 27
- MISO's conclusion requests acceptance without modification or condition.
MISO respectfully requests that the Commission (i) accept this Answer and (ii) accept the IRR Proposal without modification or condition. PDF p. 34
Read topic-matched comments in ER26-3650
Topics in the text: Registry access · Cost allocation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Municipal utilities seek a clear limit on regulated loads Midwest Transmission Dependent Utilities
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
Several parties expressly support the proposal or its core reliability framework, while other parties seek clarification or additional detail regarding implementation.7 Notably, only one protest requests the revisions to be rejected and MISO directed to file revised requirements by the end of…Read this passage
I. BACKGROUND
printed heading
I.Read this passage
BACKGROUND
printed heading
BACKGROUND The IRR Proposal is an important near-term component of MISO’s broader response to rapidly accelerating Large Load development.Read this passage
II. MOTION FOR LEAVE TO FILE ANSWER
printed heading
MISO therefore respectfully requests waiver of Rule 213(a)(2) and acceptance of this Answer.Read this passage
III. ANSWER
printed heading
III.Read this passage
A. MISO’S LARGE LOAD AND COMPUTATIONAL LOAD DEFINITIONS ARE JUST AND
printed heading · Topic match: Registry access
Within MISO’s 50 MW Large Load applicability threshold, a 25 MW computational component provides an objective quantitative indicator that the facility contains material computational content and is therefore 44 Proposed Tariff § 37A.I; IRR Proposal at 11-12, 22-26. 45 IRR Proposal at 11-12; Li…Read this passage
B. THE TRANSITION PROVISIONS REASONABLY PROTECTS EXISTING COMMERCIAL
printed heading · Topic match: Registry access
The process for making that determination and identifying which requirements must apply will be set forth in the Large Load BPM.71 This targeted reliability backstop preserves commercial certainty while allowing MISO to apply otherwise-exempt requirements where the Tariff’s reliability criterion is…Read this passage Filed comments: Cost allocation
C. THE IRR PROPOSAL PROPERLY PLACES CORE REQUIREMENTS IN THE TARIFF
printed heading
Because Large Loads rely on fast-acting controls, power-electronic interfaces, and increasingly sophisticated uninterruptible power supply systems, the detailed technical parameters that govern telemetry, PMU configuration, forecasting formats, ride-through curves, testing protocols, and ramp-rate…Read this passage
D. MISCELLANEOUS COMMENTS AND PROTESTS.
printed heading
MISO must be able to obtain, through the Transmission Customer, all information and operational access necessary to evaluate, monitor, and verify Large Load behavior under Section 37A, including the facility data, electrical models, telemetry, PMU measurements, and forecasting inputs required to…Read this passage
E. CONCLUDING ARGUMENTS
printed heading
CONCLUDING ARGUMENTS The IRR Proposal should be accepted as filed.Read this passage
IV. NOTICE AND SERVICE
printed heading
NOTICE AND SERVICE MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission…Read this passage
V. CONCLUSION
printed heading
V.Read this passage
CONCLUSION
printed heading
CONCLUSION MISO respectfully requests that the Commission (i) accept this Answer and (ii) accept the IRR Proposal without modification or condition.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 13th day of October 2026, in Carmel, Indiana. /s/ Julie Bunn Julie Bunn Midcontinent Independent System Operator, Inc. 720 City Center Drive Carmel, IN 46032 317-249-5400Read this passage