Motion for Leave to Answer and Answer of Central Municipal Power Agency Services, et al. to Midcontinent Independent System Operator, Inc.’s 10/13/2026 Motion for Leave to Answer and Answer
The Midwest TDUs answer MISO's October 13 answer, saying it confirms the requirements do not reach distribution-connected loads but does not fix the Tariff language or explain how agreements with Large Loads will show compliance.
Asks FERC to: Issue a deficiency letter directing MISO to address both issues and revise the proposed Tariff language to reflect the clarifications.
Answers the order. Answer in the MISO reliability-requirements docket that relies on the E-8 order's suggested large-load definition (P 58), which refers to interconnection at the transmission system.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- The TDUs say MISO's answer confirms intent to exclude distribution-connected loads but does not show the Tariff language does so.
it fails to show that this critical threshold issue is unambiguously addressed in the proposed Tariff language. PDF p. 2
- They say MISO gave no added clarity on how a Transmission Customer's agreement with a Large Load will assign compliance responsibilities.
MISO’s Answer fails to provide additional clarity as to how it will effectuate a Transmission Customer’s agreement with a Large Load PDF p. 2
- They want the Large Load definition to say it interconnects to the transmission system, as the E-8 order's suggested definition does.
MISO’s Tariff language should explicitly define Large Loads as those that “interconnect[] to the transmission system,” PDF p. 4
- They ask for a deficiency letter and Tariff revisions.
The Commission should therefore issue a deficiency letter directing MISO to address these issues and require revisions to the proposed Tariff language PDF p. 2
Read topic-matched comments in ER26-3650
Topics in the text: Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midcontinent Independent System Operator, Inc.Read this passage
I. MOTION FOR LEAVE TO ANSWER
printed heading
MOTION FOR LEAVE TO ANSWER The Commission’s Rules of Practice and Procedure prohibit answers to answers unless otherwise authorized by the Commission,6 but the Commission has authority to waive this prohibition for good cause.7 The Commission has found good cause to waive the general prohibition on…Read this passage
II. Answer
PDF bookmark
II.Read this passage
A. Further clarity is needed to ensure that MISO’s proposed Interconnection Reliability Requirements are limited to Transmission System-connected Large Loads.
PDF bookmark · Topic match: Registry access
Operator, Inc., 195 FERC ¶ 61,212, P 58 (2026) (“MISO Show Cause Order”). 14 See Midwest TDUs Comments at 6-7. 15 MISO Answer at 27 (emphasis added). 16 MISO Show Cause Order P 58. 17 The Computational Load registry criteria discussed in Midwest TDUs’ Comments at 9 n.22 (quoting the proposed…Read this passage
B. There remains uncertainty as to how Transmission Customers can rely on their agreements with Large Loads to effectuate compliance.
PDF bookmark
MISO states that it “must be able to obtain, through the Transmission Customer, all information and operational access necessary” and that agreements can “establish[] the Transmission Customer’s access to the information needed for 18 MISO Answer at 28. 19 Midwest TDUs Comments at 9-15. 20 MISO…Read this passage
CONCLUSION
printed heading
CONCLUSION For the reasons discussed above, and in Midwest TDUs’ Comments, the Commission should ensure that the issues above are adequately clarified by MISO and order further Tariff revisions to the extent that MISO’s proposed language is not clear on these issues.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated on this 28th day of October, 2026. /s/ Jeffrey M.Read this passage