PJM proposes a large-load registry, interim service and bring-your-own capacity
PJM files tariff and Reliability Assurance Agreement revisions creating Interim Resource Adequacy Service, a Large Load Registry, definitions of Large Load and New Large Load, and a Variable Resource Requirement curve that excludes new large loads without their own capacity.
Asks FERC to: Accept the Tariff and RAA revisions by October 12, 2026, effective as requested, with PJM's consent to FERC modifying or severing elements under FPA Section 205.
Parallel proceeding. PJM's separate Section 205 filing, ER26-3515, which cites the June 2026 show cause order. IRAS is a curtailable service for new large loads, and the registry defines Large Load, both themes of E-7.
E-7 PJM: Service for flexible loads (P 85, p. 56) E-7 PJM: Application / study process (P 6(a), p. 7) E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- IRAS lets PJM prioritize load reduction in zones where new large loads brought no capacity of their own, and only in real-time shortage conditions.
a service to be implemented by PJM solely during periods when there are insufficient resources to reliably meet demand in real time operations. PDF p. 7
- New large loads avoid IRAS by bringing new capacity, and PJM ties the design to SPP's CHILLS and the June show cause orders.
This principle lays the foundation for the IRAS paradigm in PJM that facilitates large load interconnections in a manner similar to the Southwest Power Pool’s (“SPP”) Conditional High Impact Large Load Service PDF p. 10
- A Large Load is defined as 50 MW or more of cumulative peak load at a single electrical site, with affiliated facilities within one mile combined.
cumulative peak load of 50 megawatts [(“MW”)] or greater at a single electrical site behind one or more points of interconnection PDF p. 11
- PJM would direct each distributor zone to cut load up to the MW tied to eligible new large loads, and states choose which load to reduce.
each Electric Distributor zone/area may be directed by PJM dispatchers to reduce load up to the MW quantity of capacity attributable to Eligible New Large Loads in that zone/area. PDF p. 12
- Compensation for load reduction is capped at 50% of the Non-Performance Charge Rate.
50% of the Non-Performance Charge Rate—as the maximum rate for IRAS performance. PDF p. 108
- From 2029/2030 PJM would exclude new large loads without bring-your-own-capacity arrangements from the demand curve.
exclude from the VRR Curve New Large Loads, to the extent they do not have arrangements with sufficient BYONC, beginning with the 2029/2030 Delivery Year. PDF p. 29
- PJM proposes no end date for IRAS.
not proposing an end date to the IRAS program. PDF p. 78
- PJM requests an October 12, 2026 effective date for the revisions and registry, with IRAS available from June 1, 2027.
make the enclosed proposed Tariff and RAA revisions effective by no later than October 12, 2026 PDF p. 127
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
What the document says
Load forecasting · PDF pp. 30–48
Support for a registry
PJM reported that 82% of 66 poll respondents supported a registration requirement. That was a poll about the registry, not support for every proposed curtailment rule.
82% of the 66 stakeholder respondents agreed that a Large Load registration requirement is necessary PDF p. 36Filed comments: Registry access
Resource adequacy · PDF pp. 49–79
Bring capacity or accept reductions
PJM asked to require a load-serving entity to bring new capacity for an eligible new large customer or face reductions. FERC rejected this part of the proposal in October.
Requirement for New Large Loads to bring capacity or be subject to load reductions PDF p. 55
Curtailment · PDF pp. 80–103
When the operators would call an event
PJM proposed adding reductions of eligible large loads to its emergency sequence. It emphasized that dispatchers still need discretion over the order of actions as conditions change.
the rapidness of system events influences the timing and order of actions necessary to maintain system reliability PDF p. 87
Customer compensation · PDF pp. 104–120
Payment when a large load cuts demand
The August proposal permitted a retail rate from zero to half the non-performance charge rate. This was part of the proposed service; the registry that survived in October does not create that payment.
a retail rate between 50% of the Non-Performance Charge Rate and zero dollars PDF p. 112Filed comments: Retail and wholesale authority
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Aggregate figures or individual projects? Rep. Frank Pallone Jr. (New Jersey)
- Pennsylvania asks to see curtailment data Pennsylvania Public Utility Commission
- States need usable records to set retail rules Organization of PJM States
- Give customers a chance to correct errors Equinix and PJM industrial customers
- Who answers for a supplier’s data? Southern Maryland Electric Cooperative
- A registry cannot tell an operator what just tripped Independent Market Monitor for PJM
- Corporate buyers oppose a uniform retail cutoff Data Center Coalition
- Consumer advocates tie curtailment to an alternative to the backstop Joint Consumer Advocates
- Kentucky, Ohio and Virginia abstained on the IRAS comments Organization of PJM States, recorded member positions
- Google asked FERC to separate the registry from mandatory interim service Google
Source sections
Printed headings where available; page ranges otherwise. Open a heading to read the original passage.
- Opening text
- TABLE OF CONTENTS
- A. The Senior Task Force and Critical Issue Fast Path Stakeholder
- II. THE PROPOSED REFORMS TO THE TARIFF AND THE RAA ARE
- A. Overview of Interim Resource Adequacy Service Framework and
- C. New Large Loads Can Avoid Being Subject to Interim Resource
- E. Compensation for Load Reduction Under Interim Resource
- F. Consistent with the Ratepayer Protection Pledge, PJM Is Proposing
- IV. REQUESTED EFFECTIVE DATE AND CONSENT TO
- I. BACKGROUND
- BACKGROUND
- A. The Senior Task Force and Critical Issue Fast Path Stakeholder
- B. PJM Board Determination
- C. Related PJM Large Load Filings
- II. THE PROPOSED REFORMS TO THE TARIFF AND THE RAA ARE JUST
- A. Overview of Interim Resource Adequacy Service Framework and
- B. The Large Load Registry (RAA, Schedule 11, Section B)
- C. New Large Loads Can Avoid Being Subject to Interim Resource
- D. Load Reduction Under Interim Resource Adequacy Service
- E. Compensation for Load Reduction Under Interim Resource Adequacy
- F. Consistent with the Ratepayer Protection Pledge, PJM Is Proposing to
- III. CORRESPONDENCE
- IV. REQUESTED EFFECTIVE DATE AND CONSENT TO MODIFICATION
- V. DOCUMENTS ENCLOSED
- VI. SERVICE
- VII. CONCLUSION
- CONCLUSION