Midcontinent Independent System Operator, Inc.'s Large Load Addition Resource Study Process (transmittal letter; requested effective date December 2, 2026)
MISO files tariff revisions under FPA section 205 to create the Large Load Addition Resource Study, a parallel 120-day study of loads of 200 MW or more and their paired generation, and says the filing responds to the E-8 show cause order.
Asks FERC to: Accept the LARS tariff revisions effective December 2, 2026, with a Commission order by that date so the first LARS study period can start in the first quarter of 2027.
Answers the order. MISO's section 205 answer to the E-8 show cause order on electrically proximate load, tying LARS to the order's resource adequacy request and deferring the cost recovery agreement to a November 16 filing.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Proximate-generation service (P 6(e), p. 7)
Key points
- MISO asks for a December 2, 2026 effective date so it can start the first study period in Q1 2027.
MISO requests that the Tariff revisions submitted herewith be made effective December 2, 2026 PDF p. 2
- MISO says LARS responds to the show cause order finding on study procedures for electrically proximate large loads.
MISO's existing Tariff may be unjust and unreasonable because it does not provide generator interconnection study procedures and services that account for the operational dynamics of serving electrically proximate large loads. PDF p. 3
- MISO moved the load threshold from 250 MW to 200 MW after stakeholder input.
Stakeholders proposed alternative thresholds, including 200 MW, which MISO proposes herein PDF p. 3
- Load and generation studies run together and finish in about 120 days.
The generation and load studies will be completed at the same time and will finish within approximately 120 days. PDF p. 5
- Only the Associated Transmission Customer, often a load-serving entity, can initiate an application, and a $250,000 non-refundable fee applies.
A non-refundable fee of $250,000 must accompany the LARS Application and be paid by the LARS Associated Transmission Customer. PDF p. 8
- MISO takes ten applications per study period and runs three periods a year.
There will be three LARS study periods each year and each study period will be completed in approximately 120 days PDF p. 9
- The generator is capped at 150 percent of the load's peak demand, and the pair must sit in one Local Resource Zone.
limiting the amount of requested Interconnection Service to no more than 150% of the peak demand of the LARS Associated Load PDF p. 10
- MISO says costs from load-side and common violations go to Baseline Reliability or Other projects, and the pro forma cost shifting agreement follows by November 16, 2026.
a pro forma cost shifting agreement will need to be executed and any new terms in transmission services agreements will need to be met. PDF p. 14
- Pairs must stay together for 15 years or the generator's LLGIA ends after a transition of up to one year.
MISO will terminate the LLGIA after a limited operations transition period PDF p. 16
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
What the document says
PDF p. 2
LARS studies a 200 MW-plus load and its paired generation together in about 120 days.
LARS will provide a path for the interconnection of both large loads and supporting generation pairs in a parallel 120-day study process. PDF p. 2Filed comments: Connecting load and generation
PDF p. 15
Supporters say studying load and generation together removes duplicative upgrades and lowers costs.
The goal of LARS is not necessarily to find the lowest cost solution for either the load or generation but to identify the solution that best fits both PDF p. 15Filed comments: Connecting load and generation
PDF p. 18
Utilities say MISO's generator queue takes years, so paired generation needs a faster lane.
LARS meets the urgent need for an accelerated evaluation process that accounts for both load and generation PDF p. 18Filed comments: Connecting load and generation
PDF p. 3
MISO says LARS answers the Show Cause Order and leaves the generator queue untouched.
LARS provides a mechanism for MISO to study a large load and the generation that will serve it at the same time PDF p. 3Filed comments: Connecting load and generation
PDF p. 13
MISO says LARS answers the Show Cause Order and leaves the generator queue untouched.
As a result of the way MISO's study models are structured, LARS projects will not impact existing projects in the DPP process. PDF p. 13Filed comments: Connecting load and generation
PDF p. 9
Entry limits cap LARS at ten pairs per study period and three periods a year.
There will be three LARS study periods each year and each study period will be completed in approximately 120 days PDF p. 9Filed comments: Connecting load and generation
PDF p. 9
Entry limits cap LARS at ten pairs per study period and three periods a year.
MISO will accept ten LARS Applications per study period and the LARS Applications will be assigned to study periods in order of submission. PDF p. 9Filed comments: Connecting load and generation
PDF p. 8
Applicants must post $250,000, show site control, and sign a five-year pairing contract.
A non-refundable fee of $250,000 must accompany the LARS Application and be paid by the LARS Associated Transmission Customer. PDF p. 8Filed comments: Connecting load and generation
PDF p. 9
Applicants must post $250,000, show site control, and sign a five-year pairing contract.
The agreement must be legally binding and must state a minimum term of five years PDF p. 9
PDF p. 10
Applicants must post $250,000, show site control, and sign a five-year pairing contract.
limiting the amount of requested Interconnection Service to no more than 150% of the peak demand of the LARS Associated Load, and demonstration of 100% site control PDF p. 10Filed comments: Connecting load and generation
PDF p. 7
The load must be 200 MW or more at one point of withdrawal, unaggregated.
must be a large load of at least 200 MW PDF p. 7
PDF p. 11
The load must be 200 MW or more at one point of withdrawal, unaggregated.
While MISO is allowing aggregation for LARS Generating Facilities, MISO is not allowing aggregated load to participate in LARS. PDF p. 11Filed comments: Connecting load and generation
PDF p. 10
Generation must connect in the load's Local Resource Zone, which can span several states.
Another important condition of the LARS process is the requirement that the load and generation pair be located in the same Local Resource Zone PDF p. 10Filed comments: Connecting load and generation
PDF p. 17
The pair must stay together 15 years; if the load leaves, the generator gets a year.
MISO will provide the Generating Facility up to one year after the LARS Associated Load withdraws to continue to operate under the LLGIA PDF p. 17Filed comments: Connecting load and generation
PDF p. 16
The pair must stay together 15 years; if the load leaves, the generator gets a year.
this requirement ensures that the LARS study process accurately reflects the expected impacts of the Generating Facility and LARS Associated Load on the Transmission System for a significant period of time. PDF p. 16Filed comments: Connecting load and generation
PDF p. 12
Upgrades for violations seen in the load study, or in both studies, go to zonal load.
Then any common violations that show up in the generation and load studies are assigned to BRP and Other project types. Only the violations but for the generator are assigned GIP project types. PDF p. 12
PDF p. 13
MISO says double-allocated headroom gets fixed later through MTEP projects, paid by zonal load.
In the event that overallocation does occur, any constraints that are identified as needing mitigation in the MTEP process will be formalized in a future MTEP project. PDF p. 13
PDF p. 13
MISO says double-allocated headroom gets fixed later through MTEP projects, paid by zonal load.
The cost of the MTEP project will be allocated based on existing Tariff rules, which is likely to be the load within the transmission pricing zone where the transmission upgrade is required. PDF p. 13
PDF p. 14
MISO will file its cost-shifting agreement by November 16, 2026; LARS need not wait.
all of which will be submitted to the Commission in a FPA section 205 filing by November 16, 2026. PDF p. 14
PDF p. 14
MISO will file its cost-shifting agreement by November 16, 2026; LARS need not wait.
LARS can be implemented based on the Tariff revisions filed herein and need not await these future filings. PDF p. 14Filed comments: Connecting load and generation
PDF p. 6
MISO says only the transmission customer can buy transmission service, so it must file.
Because only the Transmission Customer can procure Transmission Service under established Tariff processes, LARS requires the LARS Associated Transmission Customer to be the party that initiates the LARS Application PDF p. 6Filed comments: Connecting load and generation
PDF p. 9
MISO says only the transmission customer can buy transmission service, so it must file.
This does not supersede the role of the LARS Associated Transmission Customer to determine whether to submit a LARS Application PDF p. 9Filed comments: Connecting load and generation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Two state commissions back the parallel study Mississippi and Louisiana Public Service Commissions
- Arkansas signs on to the Southern regulators’ case Arkansas Public Service Commission
- Consumer offices question the treatment of existing load Iowa Office of Consumer Advocate, Illinois and Michigan attorneys general, Minnesota Department of Commerce and co-protesters
- Google backs co-study but wants safeguards for independent bids Google
- Bloom proposes 50 MW without delaying the filing Bloom Energy
- Who gets first claim on spare grid capacity? American Clean Power Association and Southern Renewable Energy Association
- Solar developers challenge a utility veto Solar Energy Industries Association and Advanced Energy United
- A parallel queue can promise the same grid capacity twice Clean Energy Advocates
- Utilities say deposits and commitments screen speculative requests Alliant Energy and Consumers Energy
- Entergy and Cleco contrast 120 days with years in the regular queue Entergy and Cleco
- DTE sees a binding match as evidence of readiness DTE Electric
- State organization asks for protection of existing queue positions Organization of MISO States, quoted by Utility Dive
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
This is done to avoid confusion because that definition remains pending before the Commission and because, given the 200 MW threshold for entry into LARS, not all “Large Loads” will be eligible to be a “LARS Associated Load.” The Honorable Debbie-Anne Reese October 2, 2026 Page 2 MISO requests that…Read this passage Filed comments: Connecting load and generation
I. Executive Summary
PDF bookmark
I.Read this passage
EXECUTIVE SUMMARY
printed heading · Topic match: Connecting load and generation
In addition, the Commission requested a detailed informational report on any proposals under consideration to address the issue of resource adequacy to serve new large loads, strongly encouraging new proposals to the extent necessary to address these concerns.10 The LARS process responds to this…Read this passage Filed comments: Connecting load and generation
II. Overview of the LARS Process
PDF bookmark · Topic match: Connecting load and generation
OVERVIEW OF THE LARS PROCESSRead this passage Filed comments: Connecting load and generation
A. BACKGROUND
printed heading
A.Read this passage
BACKGROUND
printed heading · Topic match: Reliability and curtailment
Significant new demand must be accompanied by sufficient resources to maintain reliability and resource adequacy.Read this passage Filed comments: Reliability and curtailment
B. STRUCTURE OF LARS AND PARTIES
printed heading · Topic match: Connecting load and generation
The Honorable Debbie-Anne Reese October 2, 2026 Page 7 for the LARS Associated Load and has the responsibility to construct Network Upgrades (subject to applicable Tariff rules that are not changed by this filing).27 The fourth key participant is the entity that owns or controls the LARS Associated…Read this passage Filed comments: Connecting load and generation
C. THE LARS APPLICATION
printed heading · Topic match: Connecting load and generation
A non-refundable fee of $250,000 must accompany the LARS Application and be paid by the LARS Associated Transmission Customer.32 Notably, MISO is establishing a “pre-submission coordination process” that LARS applicants must participate in prior to submitting a LARS Application.33 This coordination…Read this passage Filed comments: Connecting load and generation
D. THE LARS STUDY PROCESS
printed heading · Topic match: Connecting load and generation
Drake explained, “LARS studies will not include Interconnection Requests currently in the generator interconnection queue that do not have an executed GIA.”56 MISO has designed the LARS study this way to reduce the number of speculative projects in the modeling process.Read this passage Filed comments: Connecting load and generation
E. COORDINATED LARS STUDY PROCESS
printed heading · Topic match: Connecting load and generation
Drake explains, the LARS process enables MISO to optimize solutions for the transmission grid to reduce costs overall while also maintaining reliability.69 The LARS Application must identify a Commercial Operation Date for the Generating Facility and a Load In-Service Date for the LARS Associated…Read this passage Filed comments: Connecting load and generation
III. The Proposed Revisions Are Just and Reasonable
PDF bookmark · Topic match: Connecting load and generation
LARS provides a valuable tool to enable the study of LARS Associated Loads that are brought to MISO with a paired generation solution.Read this passage Filed comments: Connecting load and generation
A. LARS COMPLEMENTS OTHER COMPONENTS OF MISO’S LARGE LOAD
printed heading · Topic match: Connecting load and generation
Stakeholders have raised questions regarding how LARS generation will interact with generation already progressing through the ordinary Generator Interconnection Queue and the protections necessary to avoid adversely affecting existing Interconnection Customers.85 The transmission capacity headroom…Read this passage Filed comments: Connecting load and generation
B. ADDRESSING FERC’S SHOW CAUSE ORDER: ELECTRICALLY PROXIMATE
printed heading · Topic match: Connecting load and generation
Drake explained in her testimony, “[u]ltimately, limiting the generation and LARS Associated Load to locations within the same LRZ ensures deliverability of the generation to the LARS Associated Load because it avoids potential capacity import / capacity export limitations for the individual LRZ…Read this passage Filed comments: Connecting load and generation
IV. Description of Proposed Tariff Revisions
PDF bookmark · Topic match: Connecting load and generation
DESCRIPTION OF PROPOSED TARIFF REVISIONS To implement the LARS process proposed herein, MISO is requesting approval of new Tariff provisions, as well as revisions to several existing provisions.94Read this passage Filed comments: Connecting load and generation
A. Attachment X (Generator Interconnection Procedures).
printed heading · Topic match: Connecting load and generation
The proposed revisions are as follows: No changes shall be made to the LARS Application after submission and prior to the execution or the unexecuted filing of the LLGIA and MTEP approval for the LARS Associated Load except that a LARS Application that is deferred to the next available LARS Study…Read this passage Filed comments: Connecting load and generation
B. Attachment X – Appendix 1 (Interconnection Request for a Generating
printed heading
B.Read this passage
Attachment X – Appendix 1 (Interconnection Request for a Generating
printed heading · Topic match: Connecting load and generation
These revisions include adding new options for interconnection requests and interconnection service to accommodate LARS, confirm that the amount of Interconnection Service cannot exceed 150% of the total amount of its LARS Associated Load, to describe the requirements for LARS Associated Load and…Read this passage Filed comments: Connecting load and generation
D. Attachment X – Appendix 6 (Generator Interconnection Agreement)
printed heading
D.Read this passage
Attachment X – Appendix 6 (Generator Interconnection Agreement)
printed heading · Topic match: Connecting load and generation
The proposed revisions are as follows: This LLGIA shall be terminated by Transmission Provider after giving Interconnection Customer ninety (90) Calendar Days advance written notice if: (1) the LARS Associated Load or a portion of the LARS Associated Load fails to achieve a Service Commencement…Read this passage Filed comments: Connecting load and generation
E. Attachment FF (Transmission Expansion Planning Protocol)
printed heading · Topic match: Connecting load and generation
Both the Transmission Owner supporting the LARS Application and requesting to join LARS shall submit the required Large Load information to the MTEP Portal and an Interconnection Customer supporting the LARS Application and requesting to join LARS shall submit their Interconnection Request with the…Read this passage Filed comments: Connecting load and generation
V. The LARS Stakeholder Process
PDF bookmark · Topic match: Connecting load and generation
MISO also clarified several of the requirements of the LARS process including addressing the concerns on representation of the LARS generator/load pair within the parallel study processes.117 The stakeholder process also addressed the relationship between the load and generation, project-readiness…Read this passage Filed comments: Connecting load and generation
VI. Documents Submitted in this Filing
PDF bookmark
MISO requests that the Commission treat such highlighted language as subject to the outcome of this pending proceeding.Read this passage
VII. Effective Date
PDF bookmark · Topic match: Connecting load and generation
Acceptance of LARS by the requested effective date is necessary to allow LARS to begin on this timeframe because the proposed rules require pre-submission coordination and for MISO to develop software to support the LARS Application prior to opening the first LARS Study Period.Read this passage Filed comments: Connecting load and generation
VIII. Communications
PDF bookmark
COMMUNICATIONS MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all…Read this passage
IX. Notice and Service
PDF bookmark
NOTICE AND SERVICE MISO has served a copy of this filing electronically upon all parties listed on the Commission’s eService list, and upon all Tariff customers, MISO Members, Member representatives of Transmission Owners and non-Transmission Owners, as well as all state commissions within the MISO…Read this passage
X. Conclusion
PDF bookmark
X.Read this passage
CONCLUSION
printed heading
CONCLUSION For all of the foregoing reasons, MISO respectfully requests that the Commission accept this filing and grant waiver of any Commission regulations the Commission deems applicable, but not specifically addressed above in order for the Commission to accept it as proposed.Read this passage