ER27-522-000 · 2026-11-16 · PJM Interconnection, L.L.C.

PJM files ride-through and operating requirements for large computational loads under section 205

PJM files tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-522-000. They define Large Computational Load, set a framework for voltage and frequency ride-through and other operating requirements whose details go in PJM's manuals, and add an annual report on the new transmission services.

Asks FERC to: Accept the revisions effective January 16, 2027, severing the ride-through requirements from the rest if needed to act quickly.

Answers the order. Filed under section 205 to answer the E-7 finding that PJM's tariff lacks operating requirements for large loads, and on compliance with the E-2 co-location order's annual reporting directive.

E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Service for flexible loads (P 85, p. 56) E-2 PJM: One of three new co-location services (P 2, p. 3)

Key points

  1. PJM files in answer to FERC's preliminary finding that its tariff lacks operating requirements for large loads.
    that PJM’s Tariff appears to be unjust and unreasonable because it lacks provisions addressing ongoing operational requirements for transmission customers taking transmission service on behalf of large loads. PDF p. 2
  2. The requirements apply to Large Computational Loads, a subset of Large Loads PJM sees as riskier to the grid.
    defining Large Computational Loads, a subset of Large Loads that may pose heightened operational risks in the PJM Region PDF p. 3
  3. The tariff sets the framework; detailed ride-through and other standards go in PJM's manuals.
    which establishes the necessary groundwork for more detailed ride-through standards to be promulgated through revisions to PJM’s Manuals PDF p. 3
  4. PJM cites a July 22, 2026 event in which about 3.9 GW of large load dropped off the system.
    on July 22, 2026, an approximately 3.9 GW large load event caused frequency in the Eastern Interconnection to reach 60.092 Hz PDF p. 6
  5. PJM says it already has about 10 GW of computational load.
    PJM already has approximately 10 GW of computational load in its footprint PDF p. 5
  6. PJM asks for a January 16, 2027 effective date, earlier than its main large-load filing.
    effective January 16, 2027, which is 61 days after the date of this filing PDF p. 4
  7. PJM consents to FERC severing the ride-through requirements so they can take effect first.
    PJM consents to severance of the ride-through requirements from Tariff revisions proposed herein that pertain to other operational requirements PDF p. 4
  8. PJM would post an annual report on demand for and use of the new transmission services, as the co-location order directed.
    PJM proposes to post on its website a report containing information about the demand for and use of PDF p. 5

Topics in the text: Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

In an abundance of caution, PJM requests waiver of any regulation or filing requirements relating to submissions in Docket Nos.
Read this passage

I. BACKGROUND

PDF bookmark

I.
Read this passage

BACKGROUND

printed heading

BACKGROUND
Read this passage

A. PJM Already Faces Risks Arising from Large Load-Transfer Events that Necessitate Ride-Through Requirements

PDF bookmark · Topic match: Connecting load and generation

For example: (1) on July 10, 2024, an approximately 1.5 12 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at PP 579–580 (2026) (“Co-Located Load Order”). 13 Proposed Tariff, Part III, section 28.2; Proposed Tariff, Part XI, section 718.2. 14 PJM’s filing does not further address this proposed…
Read this passage

B. Consultation with Stakeholders in the Development of the Proposed Tariff Language Regarding Large Computational Load and Ride Through Requirements

PDF bookmark

Consultation with Stakeholders in the Development of the Proposed Tariff Language Regarding Large Computational Load and Ride Through Requirements The proposed Tariff language addresses concerns raised by the Commission.
Read this passage

C. Additional Tariff Provisions Setting the Groundwork for Future Development of Other Operational Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads

PDF bookmark · Topic match: Connecting load and generation

Additional Tariff Provisions Setting the Groundwork for Future Development of Other Operational Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads PJM’s submission also proposes Tariff language for other operational components to address…
Read this passage

II. THE PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE

PDF bookmark

THE PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE
Read this passage

A. PJM Proposes to Define Large Computational Loads, the Relevant Subset of Large Loads in PJM for Purposes of the Proposed Operational Requirements

PDF bookmark

Large Computational Load shall include: A) New Large Computational Load.
Read this passage

B. PJM Is Proposing Ride-Through Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads

PDF bookmark

Reese, Secretary November 16, 2026 Page 16 16 reliability-related considerations and shall be applied in a not unduly discriminatory manner to similarly situated Large Computational Load.”41 Finally, it is worth noting that establishing minimum ride-through requirements applicable to Eligible…
Read this passage

C. PJM Is Proposing Tariff Language Authorizing the Development of Other Operational Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads

PDF bookmark

PJM Is Proposing Tariff Language Authorizing the Development of Other Operational Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads The Show Cause Order additionally found the PJM Tariff appeared to be unjust and unreasonable because it…
Read this passage

D. Pro Forma Provisions in Transmission Service Agreements Exist or Will Exist to Memorialize Ongoing Operational Requirements

PDF bookmark

Pro Forma Provisions in Transmission Service Agreements Exist or Will Exist to Memorialize Ongoing Operational Requirements The Commission’s order also notes opportunities for pro forma provisions in a Transmission Service Agreement between PJM and the Eligible Customer taking transmission service…
Read this passage

Attachment F-4, section 4.0.

printed heading

Attachment F-4, section 4.0.
Read this passage

III. STAKEHOLDER ENGAGEMENT

PDF bookmark · Topic match: Connecting load and generation

STAKEHOLDER ENGAGEMENT The proposed Tariff revisions defining Large Computational Load and establishing ride- through requirements follow an expedited stakeholder engagement effort.
Read this passage

IV. PROPOSED EFFECTIVE DATE

PDF bookmark

PROPOSED EFFECTIVE DATE PJM proposes an effective date of January 16, 2027, for the proposed Tariff revisions referenced herein.
Read this passage

V. DESCRIPTION OF SUBMITTAL

PDF bookmark

DESCRIPTION OF SUBMITTAL This filing consists of the following: 1.
Read this passage

VI. CORRESPONDENCE

PDF bookmark

CORRESPONDENCE The following individuals are designated for inclusion on the official service list in this proceeding and for receipt of any communications regarding this filing: Arleigh P.
Read this passage

VII. SERVICE

PDF bookmark

SERVICE PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically.
Read this passage

VIII. CONCLUSION

PDF bookmark

CONCLUSION Based on the foregoing, PJM respectfully requests that the Commission accept proposed revisions to PJM’s Tariff.