ER27-527-000 · 2026-11-16 · Midcontinent Independent System Operator, Inc.
MISO files the Grid Responsive Integration Transmission Service under section 205
Back to sections and commentaryPDF page 1
Midcontinent Independent
System Operator, Inc.
317.249-5400
www.misoenergy.org
720 City Center Drive
Carmel, Indiana 46032
2985 Ames Crossing Road
Eagan, Minnesota 55121
1700 Centerview Drive
Little Rock, AR 72211
Michael Kessler
Managing Assistant General Counsel
Direct Dial: 317-753-9434
Email: mkessler@misoenergy.org
November 16, 2026
VIA ELECTRONIC FILING
The Honorable Debbie-Anne Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
Re:
Midcontinent Independent System Operator, Inc.’s
Grid Responsive Integration Transmission Service for Large Loads
Docket No. ER27-___-000
Dear Secretary Reese:
The Midcontinent Independent System Operator, Inc. (“MISO”), through this filing,1
submits proposed revisions to its Open Access Transmission, Energy and Operating Reserve
Markets Tariff (“Tariff”),2 establishing the Grid Responsive Integration Transmission Service
(“GRITS”). GRITS provides a permanent firm and non-firm contract demand-based,
Transmission Service option for Large Loads willing and able to limit their withdrawals under
specified price and reliability conditions.
MISO is submitting GRITS as a separate FPA section 205 filing from the Large Load
Project Review (“LLPR”) process, cost recovery agreements, Firm Service Step Up (“FSSU”),
and Interim Network Integration Transmission Service (“Interim NITS”).3 These initiatives are
addressed in MISO’s separate large load omnibus filing submitted concomitantly. The GRITS
proposal is a stand-alone proposal and MISO describes the proposals contained in the omnibus
filing here only as necessary to explain the interfaces with GRITS.
MISO requests that the Commission accept the proposed revisions effective 120-days from
the date of this filing (i.e., March 16, 2027) in order to facilitate MISO’s development of software
1
This filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Part 35 of
the regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. § 35.1,
et seq.
2
Unless otherwise indicated by the text or context of this transmittal letter, all terms used herein have the definitions
set forth in Module A of the Tariff.
3
These filings are being submitted contemporaneously in response to the associated concerns set forth in the Show
Cause Order.
PDF page 2
The Honorable Debbie-Anne Reese
November 16, 2026
Page 2
systems and related process modifications necessary to implement GRITS in early 2029, and to
continue the development of rates applicable to GRITS in concert with the MISO Transmission
Owners. The GRITS proposal responds to the Commission’s concerns regarding the need for an
ongoing firm and non-firm contract demand service option for flexible Large Loads, including,
but not limited to, co-located arrangements. The specific relationship to the proceeding in Docket
No. EL26-70-000 is addressed below.
I.
EXECUTIVE SUMMARY
MISO appreciates the collaborative efforts of its stakeholder community and the
Transmission Owners in developing proposals for the reliable integration of Large Loads on an
expedited basis, consistent with the urgency created by the timelines established in the Show Cause
Order.
This filing provides the GRITS framework, which addresses the concerns raised by the
Commission in the Show Cause Order with respect to the need for a permanent contract demand
transmission service in the MISO region. As discussed in more detail below, the earliest MISO
will be able to implement GRITS is January 1, 2029. This implementation timeline is driven by
the need for significant modifications to MISO’s software systems and processes to facilitate the
reservation, scheduling, market systems, and billing services for GRITS, which is a new
transmission service that does not conform with the transmission services offered today under
MISO’s Tariff. MISO recognizes the desire for the proposed service as noted by certain
stakeholders and agrees that GRITS must provide a reliable and workable path for customers that
elect permanent contract demand-based firm and/or non-firm transmission service and is
committed to implementation of GRITS consistent with Commission acceptance and on a timeline
that is technically feasible.
Given the extended timeline for implementing GRITS, MISO and the Transmission
Owners, prioritized their efforts on solutions that can be delivered in the near term, including the
Zero Injection Generator Interconnection Agreement (“ZGIA”) proposal, Interconnection
Reliability Requirements (“IRR”), Load Addition Resource Study (“LARS”) proposal, Firm
Service Step Up, Interim NITS and LLPR, including the development of pro forma cost recovery
agreements to prevent unjust cost shifts related to upgrades identified through the LLPR process.
This prioritization was necessary given the competing priorities of MISO’s proposals in response
to the Show Cause Order and the abbreviated time frame during which the multiple issues
identified in the Show Cause order needed to be addressed. Moreover, GRITS is a novel and
complex market-dependent approach to transmission service that was conceived later in the
abeyance period (i.e., October 2026) and has necessitated greater stakeholder outreach and
education. As stated above, considerable work remains including significant modifications to
MISO’s, and as may be required, the Transmission Owner’s and other Market Participants’,
software systems and processes to accommodate GRITS. As such, MISO requests Commission
acceptance of the proposed GRITS framework to begin software development consistent with the
Commission’s order and further requests the Commission permit MISO and the Transmission
Owners to continue to develop a new rate structure applicable to GRITS and work with
PDF page 3
The Honorable Debbie-Anne Reese
November 16, 2026
Page 3
stakeholders to continue to refine the proposal on a timeline that will facilitate GRITS
implementation in early 2029.
II.
BACKGROUND
The scale and pace of large load development require transmission service options that
reflect how a Large Load customer intends to use the Transmission System. Some Large Load
Transmission Customers may seek full firm service and need an interim arrangement while
necessary supporting upgrades are completed. MISO is proposing in its omnibus filing both an
Interim NITS product and Firm Service Step Up process that will be implemented within its
existing NITS framework to address these transmission service needs. Other Large Load
Transmission Customers may be able to accept continuing interruption of some or all of their
demand and seek an ongoing allocation between firm and non-firm service on a permanent basis.
GRITS addresses both of these needs as it provides the Large Load Transmission Customer the
option to determine the appropriate combination of firm and non-firm contract demand
transmission services needed to meet its operational needs, but does not require the Large Load
Transmission Customer to progress toward firm service for any or all of its GRITS Load Limit.4
In the June 18, 2026, Show Cause Order, the Commission examined whether MISO’s
Tariff adequately addresses large and co-located load development, including service for loads
willing and able to limit their withdrawals under certain conditions. The Commission identified a
permanent contract-demand-like service option, treatment of regulation and black start service,
and controls needed to enforce withdrawal limits among the matters requiring attention.5
The Commission permitted respondents to develop regional solutions through section 205
filings and subsequently held the proceeding in abeyance. MISO has advanced related proposals
through separate filings, including Zero Injection Generator Interconnection Agreements
(“ZGIA”), Interconnection Reliability Requirements for Large Loads (“IRR”), and the Large Load
Addition Resource Study (“LARS”) and the Large Load omnibus filing submitted separately
pursuant to FPA section 205. GRITS provides a distinct Transmission Service option that can
operate with the applicable study, interconnection, and reliability requirements. Generator
Interconnection Service does not itself provide the Transmission Service needed for associated
load.6
4
GRITS Load Limit: The maximum amount of Load specified in the Form of Service Agreement for GRITS by
the Large Load Transmission Customer taking GRITS that may be scheduled at a Point(s) of Delivery pursuant
to Module B of this Tariff.
5
Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, PP 98–105 (2026), errata notice, 196 FERC ¶
61,123 (2026) (“Show Cause Order”).
6
Show Cause Order P 37; Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,133, PP 8-11 (2026)
(“Abeyance Order”); ZGIA Transmittal at 1-2, 6-7.
PDF page 4
The Honorable Debbie-Anne Reese
November 16, 2026
Page 4
III.
PROPOSED GRITS SERVICE
A.
Eligibility, service quantities, and agreements.
GRITS provides an ongoing service arrangement for a Large Load Transmission Customer
serving a Large Load that may desire a combination of both firm and non-firm contract demand-
like transmission service and, with respect to any non-firm service, is willing and able to limit its
withdrawals under specified price and reliability conditions. For example, a Large Load
Transmission Customer representing a Large Load of 500 MW may desire to only take 200 MW
of firm transmission service, allowing the remaining 300 MW to be served on a non-firm basis.
Under Network Integration Transmission Service this participation model is not available while
GRITS provides a pathway for such an arrangement.
GRITS will only be made available to a Large Load Transmission Customer, cannot be
combined with any other NITS transmission service, and is not limited to Large Load being served
by a co-located generator. GRITS Service requires that a Large Load Transmission Customer
establish a GRITS Load Limit and a Firm GRITS quantity that may range from zero to the full
Load Limit in the pro forma GRITS service agreement (“GRITS Service Agreement”), which
cannot be exceeded without execution of a new pro forma GRITS Service Agreement. Non-Firm
GRITS may be reserved within the difference between those quantities as needed and as available.
The GRITS Load Limit defines the maximum approved Load in the GRITS Service Agreement;
it does not guarantee that the entire non-firm quantity will be available in every period.
GRITS contains the firm and non-firm components within one GRITS Service Agreement.
MISO does not propose combining NITS and GRITS for the same load to create that allocation,
and a change to the GRITS Load Limit or Firm GRITS quantity requires a new GRITS Service
Agreement. Where both firm and non-firm quantities are present, separate Commercial Pricing
Nodes (“CPNodes”) represent those components. This representation supports the different
reservation, interruption, billing, capacity, and Auction Revenue Rights (“ARR”) treatment
applicable to each GRITS service component.
For example, a 300 MW GRITS Load Limit with 60 MW of Firm GRITS permits a
maximum non-firm quantity of 240 MW. At 200 MW of operating demand, the proposed
allocation assigns the first 60 MW to the CPNode representing the firm component and the
remaining 140 MW to the CPNode representing the non-firm component. That allocation is
subject to an available reservation and the applicable operating limit; the agreement’s 240 MW
non-firm maximum does not itself establish that 240 MW will be available for every hour.
As noted above, GRITS accommodates both stand-alone Large Loads and qualifying co-
located arrangements. A Large Load Transmission Customer must request GRITS through the
applicable LLPR process and will be required to execute a GRITS Service Agreement and a
GRITS Operating Agreement specifying the quantities, operational limits, communications, and
control requirements. Service commences after Network Upgrades, Large Load Network
Upgrades and/or Impacted Transmission Owner Large Load Network Upgrades identified throughPDF page 5
The Honorable Debbie-Anne Reese
November 16, 2026
Page 5
the LLPR process are complete and the applicable service and operating prerequisites are satisfied.
As explained by Ms. Xie, Firm Service Step-up, which is proposed in MISO’s Omnibus Filing,
cannot be combined with GRITS because GRITS establishes its own ongoing allocation of firm
and non-firm service within the GRITS Service Agreement.
B.
Reservations and service priority.
Non-Firm GRITS will be reserved through the Open Access Same-Time Information
System (“OASIS”) for periods ranging from one Day to one month. The reservation rules use the
existing Point-To-Point Transmission Service framework, including priority for longer requested
service periods within the permitted range and the order of competing equal-duration requests. A
new reservation receives its applicable position in that process. The underlying Form of GRITS
Service Agreement does not reserve non-firm service indefinitely, and reservation priority of non-
firm service remains distinct from the priority applied when existing service must be curtailed.
Firm GRITS is reserved for at least one year within the ongoing arrangement. Reservation
priority determines the order in which requests are evaluated; curtailment priority determines
which existing service is reduced when the system cannot support scheduled use. A customer’s
continuing GRITS agreement does not establish an indefinite reservation of non-firm capability.
The following depicts the priority of Firm and Non-Firm GRITS:
C.
Transmission charges and gross-load billing.
GRITS will use reservation-based Transmission Service charges benchmarked to the rates
for GRITS service that will be filed in a subsequent FPA section 205 filing. MISO notes that it
PDF page 6
The Honorable Debbie-Anne Reese
November 16, 2026
Page 6
will continue working with its Transmission Owners specifically,7 and the broader stakeholder
community, to develop the rates applicable to GRITS transmission services. MISO and the
Transmission Owners intend to either submit the proposed GRITS transmission service rates prior
to the proposed implementation date requested herein (i.e., March 16, 2027) or provide the
Commission with a status report detailing the progress that has been made to establish such rates
as well a revised date to propose such rates.
Given the expansive scope of issues that need to be addressed in the Show Cause Order,
and the relatively limited amount of time to consider and address those issues, there has simply
not yet been sufficient opportunity for MISO and MISO Transmission Owners to finalize a rate
design for GRITS. Notwithstanding the lack of such rates being included in this filing, MISO has
developed a sufficiently detailed and robust transmission service that both complies with the intent
of the Show Cause Order and merits Commission acceptance, subject to further compliance. This
is particularly the case because GRITS cannot be provided until January 2029.
The GRITS proposal also applies gross-basis treatment to applicable service-related
charges, including regulation and black start, so that a co-located arrangement does not avoid
charges for services it receives merely because its net withdrawal is below its gross load. These
reservation-based charges and gross-basis billing serve different functions and apply through the
billing determinants established for the particular service.
A reservation-based charge, such as that used for the existing Point-To-Point Transmission
Service rates, reflects the amount of Transmission Service reserved, rather than actual
consumption alone. The applicable schedules govern any billing adjustment or credit for
interrupted service. Co-located generation serving a Large Load receiving GRITS service must
be registered as a Generation Resource, and the Large Load Transmission Customer must procure
Transmission Service to receive service from the co-located resource. Co-location therefore does
not eliminate the obligation to procure Transmission Service or permit the customer to “net away”
gross load relevant to regulation and black start billing.
D.
Price-based interruption.
Non-Firm GRITS will be interrupted when the Locational Marginal Price at its CPNode
exceeds the GRITS Offer Cap, which is $100/MWh. Ms. Xie explains that historical data,
including the 2025 State of the Market Report, indicates that historical data indicates this price
permits service more than 95% of all Hours.8 To effectuate the GRITS Offer Cap in the Day-
Ahead Energy and Operating Reserve Market, the Market Participant representing the Large Load
will be required to submit a Price Sensitive Demand Bid for the CPNode representing the non-
7
MISO’s Transmission Owners have filing rights with respect to the rates for transmission service pursuant
Appendix K to the Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent
System Operator, Inc., Rate Schedule No. 1 of the Tariff (“Transmission Owners Agreement").
8
2025 STATE OF THE MARKET REPORT FOR THE MISO ELECTRICITY MARKETS available at:
https://www.potomaceconomics.com/wp-content/uploads/2026/07/2025-MISO-SOM_Appendix_Final.pdf.
PDF page 7
The Honorable Debbie-Anne Reese
November 16, 2026
Page 7
firm portion of the GRITS Load that is no greater than $100/MWh. The GRITS Offer Cap will be
effectuated in both the Day-Ahead and Real-Time Energy and Operating Reserve Markets by
incorporating the Non-Firm GRITS portion of the GRITS Load into the Security Constrained Unit
Commitment (“SCUC”) and Security Constrained Economic Dispatch (“SCED”) processes. As
such, Ms. Xie explains that the Large Load Transmission Customer’s election of Non-Firm GRITS
therefore includes the ability to comply with both the price condition and the resulting operating
directive.
Ms. Xie further explains that the GRITS Offer Cap serves two complementary objectives.9
First, by establishing the GRITS Offer Cap, MISO can use the Security Constrained Economic
Commitment (“SCUC”) and Security Constrained Economic Dispatch (“SCED”) processes to
efficiently issue Interruption directives to the Non-Firm GRITS Load without relying upon
administrative Emergency procedures. Requiring Non-Firm GRITS Loads to be included in the
SCUC/SCED processes provides an automated and transparent way of curtailing these Loads as
the system conditions experienced reduced transmission or generation capacity. Second,
establishing the GRITS Offer Cap at the first non-zero step of the Market-Wide Short-Term
Reserve Demand Curve prevents reliability being degraded for all Transmission Customers by
ensuring the Non-Firm GRITS Load is offline before a shortfall of operating reserves occurs. This
limitation reflects the “as-available” nature of Non-Firm GRITS and is consistent with the
reliability rationale underlying the Tariff’s authorization to curtail Non-Firm Point-To-Point
Transmission Service when an Emergency or other unforeseen condition threatens to impair or
degrade Transmission System reliability.
E.
Reliability based Curtailment and enforcement.
Non-Firm GRITS Load is also subject to reliability-based Curtailment directives, including
Curtailment upon the declaration of a Capacity Advisory in the same Local Balancing Authority
(“LBA”). During Transmission Emergencies, Non-Firm GRITS Load is curtailed with the same
priority as Loads served using Non-Firm Point-To-Point Transmission Service of equal service
duration and before Loads served through Interim NITS and Firm Transmission Service. Ms. Xie
explains how Resource Adequacy is maintained if the Non-Firm GRITS Load is excluded from
the Planning Resource Auction because the GRITS Offer Cap will ensure these Loads are curtailed
whenever LMP rises above the GRITS Offer Cap.10 In the event a Capacity Advisory declaration
is made while LMP is below the GRITS Offer Cap, MISO will issue the Curtailment directive for
the entire Non-Firm GRITS Load.11 Accordingly, Resource Adequacy is assured because these
Loads will not be competing with other types of Load at the times when Resource Adequacy is
under pressure. The portion of a Large Load served through Firm GRITS remains in the
Coincident Peak Demand forecast and retains the corresponding capacity responsibility to procure
Zonal Resource Credits.
9
Xie at 9.
10 Xie at 16.
11 Id.
PDF page 8
The Honorable Debbie-Anne Reese
November 16, 2026
Page 8
GRITS depends on observable and enforceable withdrawal limits. Metering, telemetry,
model representation, communications, and operating controls support MISO’s administration of
those limits. The Transmission Owner will determine additional control technologies or protection
systems required for the arrangement. MISO will communicate Interruption and Curtailment
directives through the Market Participant representing the Load in MISO’s Energy and Operating
Reserve Markets, and applicable operating procedures will govern restoration.
Ms. Xie explains that if the Large Load Transmission Customer with Non-Firm GRITS
fails to interrupt when directed, the applicable Transmission Owner has the authority implement
remote disconnect procedures, and the Large Load Transmission Customer will be subject to
unreserved use penalties, additional financial penalties for repeated failure, and possible
termination of Transmission Service.12 These consequences support the operating limitations the
customer accepts in electing GRITS.
F.
Resource Adequacy, ARR Entitlements, and market participation.
Firm GRITS remains subject to the applicable Resource Adequacy and capacity obligations
established in Module E of the Tariff and is eligible to register as a Load Modifying Resource.
Ms. Xie explains, the portion of a Large Load served through Non-Firm GRITS service may be
excluded from the obligation to procure Zonal Resource Credits.13 This means this portion of the
Large Load will not be included in the Coincident Peak Demand forecast and a Market Participant
is not eligible to enroll the Non-Firm GRITS portion of the Large Load as a Load Modifying
Resource. The portion of a Large Load served through Firm GRITS is required to procure Zonal
Resource Credits and is eligible to participate as a Load Modifying Resource.
MISO is not proposing changes to the eligibility requirements for a Load to receive Auction
Revenue Rights (“ARR”). The Tariff changes proposed herein clarify that ARR Entitlements are
limited to Firm GRITS Load only, and the non-firm component of GRITS Load is excluded from
acquiring ARRs and from the Peak Usage determination.
The proposal prohibits Non-Firm GRITS Load from participating as a Demand Response
Resource (“DRR”), Load Modifying Resource (“LMR”), or Emergency Demand Response
(“EDR”) resource. As explained by Ms. Xie, prohibition of Non-Firm GRITS Load from
participating as a DRR is consistent with Order No. 745. Prohibiting enrollment as a Load
Modifying Resource also follows from these Loads not having an obligation to procure Zonal
Resource Credits.14
12 Xie at 20.
13 Xie at 16.
14 Xie at 16.
PDF page 9
The Honorable Debbie-Anne Reese
November 16, 2026
Page 9
G.
Planning and commercial model treatment.
The firm component of GRITS Load is included in ongoing MISO Transmission
Expansion Plan (“MTEP”) planning, while the total GRITS Load remains subject to applicable
Interconnection Reliability Requirements (“IRR”) and stability review. The requirement to
establish separate CPNodes for Firm and Non-Firm GRITS Load respectively, and corresponding
Elemental Pricing Nodes allow the service allocation to be reflected in operations, forecasts,
bidding, billing, and ARR treatment. Actual Energy Withdrawals associated with GRITS service
are assigned first to the firm component, up to the Firm GRITS service quantity, with remaining
withdrawals assigned to the Non-Firm GRITS quantity. This representation does not authorize
withdrawals beyond a valid Transmission Service Reservation or the applicable operating limit.
IV.
RESPONSE TO THE SHOW CAUSE ORDER
Section 205 requires jurisdictional rates and practices to be just and reasonable and
prohibits undue preferences and unreasonable differences in service.15 GRITS ties the
Transmission Customer’s rights to the service it requests: firm quantities retain firm treatment and
corresponding capacity obligations, while non-firm quantities receive as-needed and as-available
service, lower priority for reliability interruptions, and a price-based interruption condition.16
Separate reservation requirements and model treatment for Firm and Non-Firm GRITS makes
those distinctions administrable.
The GRITS proposal responds to the ongoing flexible-service concerns in paragraphs 100
through 105 of the Show Cause Order by establishing a defined Load Limit, an elected firm
quantity, separately reserved non-firm service, and enforceable operating conditions.17 The
proposal’s gross-load treatment prohibits netting and addresses the regulation and black start
concerns identified in Paragraphs 98–100 of the Show Cause Order. In addition, the proposal’s
metering and control requirements address the withdrawal-limit concerns in paragraph 102 of the
Show Cause Order. Those features connect the service received with the obligations accepted by
the customer.18
The planning provisions of the GRITS proposal, which require requests for GRITS to be
evaluated through the LLPR process consistent with all other requests for Transmission Service
made by Large Load Transmission Customers, also address the issue identified in Paragraph 124
of the Show Cause Order.19 Through this process requests for Firm GRITS will be subject to the
analysis for ongoing firm service, which reflects the Firm GRITS quantity, while total GRITS
15 16 U.S.C. § 824d(a)–(b).
16 Show Cause Order at PP 100-105; Xie at 6, 20.
17 Xie at 18-21.
18 Show Cause Order at PP 98–105.
19 Xie at 7; Show Cause Order at P 124.
PDF page 10
The Honorable Debbie-Anne Reese
November 16, 2026
Page 10
Load remains subject to reliability and stability assessment.20 The GRITS accreditation provisions
for co-located ZG Resources addresses the portion of paragraph 127 of the Show Cause Order
concerning the relationship between capacity recognition and the associated load’s service.21
These provisions supplement the separately proposed study and generator-interconnection
frameworks.22
Reservation-based charges, gross-load ancillary service billing, price-based interruption,
and firm-only ARR eligibility address different aspects of cost responsibility.23 The separately
proposed cost recovery agreements submitted in the omnibus filing are required for all address
obligations associated with covered Large Load Network Upgrades and Impacted Transmission
Owner Network Upgrades. Because requests for GRITS are required to be evaluated through the
LLPR, all Large Load Transmission Customers granted GRITS will be required to enter into the
Form of Agreement for Large Load Cost Recovery Agreement (proposed Attachment LLL) and
Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery Agreement
(proposed Attachment MMM).24
GRITS service is only available to Large Load Transmission Customers capable of meeting
operational requirements for GRITS and these enforcement mechanisms ensure that the approved
service quantities are not merely contractual limits but are limits that MISO can enforce in real
time.25 Large Load Transmission Customers electing GRITS are subject to the same applicable
service conditions. The distinct treatment of Firm and Non-Firm GRITS quantities reflects the
unique characteristics, firmness, curtailment and interruption obligations of each respective
service.
V.
DESCRIPTION OF PROPOSED TARIFF REVISIONS
As discussed, GRITS is an independent, stand-alone proposal that can be accepted and
implemented separate from MISO’s other FPA section 205 filing submitted in response to the
Show Cause Order. Because MISO’s omnibus filing has been submitted prior to this filing, MISO
has built the GRITS Tariff revisions to include (i.e., on top of) the proposed revisions to the Tariff
submitted in the omnibus filing. MISO has highlighted all Tariff language pending Commission
acceptance in the Tariff records submitted in Tab A hereto.
The proposed Tariff records establish GRITS eligibility and defined quantities; application,
establish a Form of GRITS Service Agreement, and Operating Agreement requirements;
20 Xie at 7, 19-21.
21 Xie at 17-18.
22 Show Cause Order at PP 124, 127.
23 Xie at 15-16, 19-20.
24 Xie at 7.
25 Xie at 20-21.
PDF page 11
The Honorable Debbie-Anne Reese
November 16, 2026
Page 11
reservation duration and priority; price and reliability interruption; control, enforcement, and
restoration requirements; and changes to the Load Limit or firm quantity. Conforming revisions
to Module C of the Tariff implement separate commercial model representation requirements,
establish ARR eligibility only for Firm GRITS, establish Resource Adequacy treatment,
participation restrictions, and the co-located ZG Resource accreditation interface.
A.
Definitions
MISO proposes the following, new definitions for GRITS:
Firm Grid Response Integration Transmission Service (Firm GRITS): The amount of
firm Transmission Service that is reserved and/or scheduled to a specific Point(s) of
Delivery pursuant to the Form of Service Agreement for GRITS. A Large Load
Transmission Customer taking Firm GRITS may reserve and/or schedule between 0 MW
and the GRITS Load Limit.
Grid Response Integration Transmission Service (GRITS): A Transmission Service
provided under Module B of this Tariff that permits a Large Load Transmission Customers
to take Transmission Service. GRITS permits the reservation of Capacity and of Energy
on either a firm or non-firm basis from Network Resources to the Point(s) of Delivery.
GRITS is comprised of three components; GRITS Load Limit, Firm GRITS, and Non-Firm
GRITS. A Transmission Customer may not change the GRITS Load Limit or the amount
of Firm GRITS without a new Form of Service Agreement for GRITS.
GRITS Load Limit: The maximum amount of Load specified in the Form of Service
Agreement for GRITS by the Large Load Transmission Customer taking GRITS that may
be scheduled at a Point(s) of Delivery pursuant to Module B of this Tariff.
GRITS Offer Cap: The maximum Locational Marginal Price at the Commercial Pricing
Node associated with a Large Load taking Non-Firm GRITS service that a Market
Participant may submit in a Bid. Non-Firm GRITS may be Interrupted if the Locational
Marginal Price rises above the GRITS Offer Cap.
Non-Firm GRITS: The amount of Non-Firm Transmission Service that is reserved and
scheduled on an as-available basis and is subject to Curtailment or Interruption as set forth
in Section 37B of this Tariff. Non-Firm GRITS is available only to Large Load
Transmission Customers for periods ranging from one (1) Day to one (1) Month. A Large
Load Transmission Customer taking Grid Responsive Integration Transmission Service
may reserve and/or schedule between 0 MW and the difference of GRITS Load Limit and
Firm GRITS.
PDF page 12
The Honorable Debbie-Anne Reese
November 16, 2026
Page 12
B.
Module B
MISO has revised the introduction of Module B of the Tariff to establish GRITS as a
service available only to Large Load Transmission Customers. In addition, MISO has established
Section 37B of the Tariff to include the terms and conditions of GRITS. The following table
provides a brief overview of the proposed GRITS Tariff revisions in addition to the definitions.
The marked and clean Tariff records submitted as Tab A and B respectively, set out the
revisions. The following table of Tariff revisions is provided for reference and informational
purposes only. The language filed in the proposed Tariff revisions shall control in the event of any
discrepancies between the information provided in this table and the proposed Tariff revisions.
Tariff Section
Tariff Section Title
Brief Description of changes
Module B
37B.1
GRITS Term
Establishes the minimum service
terms for Firm GRITS and Non-Firm
Grits
37B.2
GRITS Reservation Priority
Establishes the reservation priority for
Firm GRITS and Non-Firm GRITS
relative to other Transmission
Services under the Tariff
37B.3
GRITS Service Agreement
Establishes the requirement that a
Large Loat Transmission Customer
taking GRITS must execute a Form of
Service Agreement for GRITS.
37B.4
GRITS Change in Service Request
Establishes the requirement that a
Large| Loat Transmission Customer
seeking to change the amount of
GRITS must submit a new application
for GRITS.
37B.5
GRITS Transmission Provider
Responsibilities
Establishes MISO’s responsibilities
for revising GRITS requests.
37B.6
Secondary Service to Firm GRITS
Establishes the treatment of Firm
GRITS from non-Designated Network
Resources and the associated priority
of the service.
37B.7
GRITS Restrictions on Use of
Service
Requires any Large Load
Transmission Customer to use Point-
to-Point Transmission Service for
third-party sales outside of the MISO
Region.
37B.8
GRITS Application Procedures
Establishes the application and
procedures for requesting GRITS, and
PDF page 13
The Honorable Debbie-Anne Reese
November 16, 2026
Page 13
provides detail regarding the
evaluation of a GRITS request.
37B.9
GRITS Arrangement to be
Completed Prior to Service
Establishes the requirement to
complete installation of all equipment
specified under the GRITS Operating
Agreement prior to service.
37B.10
GRITS Transmission Customer
Facilities
Establishes responsibility for
construction, maintenance and
operation of facilities used to provide
GRITS.
37B.11
GRITS Study Procedures
Establishes the study procedures for
requests for Non-Firm GRITS.
37B.12
GRITS Procedures
Requires that procedures for Load
Shedding, Curtailment and
Interruption be established by MISO,
the Transmission Owner and Large
Load Transmission Customer prior to
commencement of GRITS.
37B.13
GRITS Transmission Constraints
States that MISO will take actions
necessary to maintain Transmission
System reliability if necessary to
address a transmission constraint.
37B.14
GRITS Cost Responsibility for
Relieving Transmission Constraint
Establishes that curtailment of
scheduled deliveries may occur in
accordance with the applicable
GRITS Operating Agreement or
NERC / NAESB TLR procedures.
37B.15
GRITS Curtailment of Scheduled
Deliveries
Establishes the procedure for
curtailing Firm GRITS.
37B.16
GRITS Load Shedding
Established the procedures for Load
Shedding relative to Firm GRITS.
37B.17
GRITS System Reliability
Establishes the provisions for
curtailment of Firm and Non-Firm
Grits, and the costs associated with a
Large Load Transmission Customer’s
failure to respond to MISO’s
curtailment directives.
37B.18
Classification of Firm GRITS
Limits the use of FIRM GRITS to the
levels specific in the applicable
GRITS Service Agreement.
37B.19
Classification of Non-Firm GRITS
Establishes unreserved use penalties
for Non-Firm GRITS
37B.20
Scheduling of Non-Firm GRITS
Requires Non-Firm GRITS schedules
to be submitted consistent with the
PDF page 14
The Honorable Debbie-Anne Reese
November 16, 2026
Page 14
requirements of Attachment J to the
Tariff.
37B.21
Non-Firm GRITS Curtailment or
Interruption of Service
Establishes the rules for curtailment or
interruption of Non-Firm GRITS and
the priority of Non-Firm GRITS in
relation to other Transmission
Services.
37B.22
GRITS Offer Cap
Establishes the GRITS Offer Cap of
$100/MWh.
37B.23
GRITS Operating Agreement
Establishes the components of the
GRITS Operating Agreement.
Module C
38.6
Aggregators of Retail Customers
Requires an ARC to attest that no part
of a DRR, LMR, or EDR is being
served by Non-Firm GRITS.
39.2.2
Demand Bid Rules in the Day-
Ahead Energy and Operating
Reserve Markets
Limits the amount of Price Sensitive
Demand Bid from Large Load taking
Non-Firm GRITS to the GRITS Offer
Cap.
40.2.15.s
Real-Time Energy and Operating
Reserve Market Process
Establishes that Non-Firm GRITS is
subject to Interruption when the Real-
Time Ex Ante LMP exceeds the
GRITS Offer Cap.
40.2.20
Capacity Shortage Conditions in
the Real-Time Energy and
Operating Reserve Market
Establishes Step Zero in the priority
of Interruption for Capacity Shortage
Conditions in the Real Time market.
42.6
Partial-Year FTR Allocation
Process for New ARR Zones
Includes Firm GRITS as an eligible
service for nominations.
43.2.4
Nomination and Allocation of
ARRs and MTPS ARRs
Includes Firm GRITS as an eligible
service for nominations.
69A.1.1
Forecasted Demand Identification
Excludes Non-Firm GRITS from
Coincident Peak Demand forecast.
69A.1.2
Daily Assignment of Coincident
Peak Demand Obligations
Excludes Demand from a Large Load
taking Non-Firm GRITS from an
LSE’s portion of such Demand.
69A.3.1.G
Determination of Deliverability
Makes explicit deliverability of a ZG
Resource to a ZG Associated Load
requires Firm Transmission Service or
Interim NITS Transmission Service.
69A.3.3
Load Modifying Resources
Non-Firm GRITS cannot participate
as a Load Modifying Resource
Attachments
PDF page 15
The Honorable Debbie-Anne Reese
November 16, 2026
Page 15
Attachment F-1
Form of Service Agreement for
Grid Responsive Integration
Transmission Service
Form of Service Agreement for
GRITS and related exhibits including
specification sheets.
Attachment G-1
Form of GRITS Operating
Agreement for Grid Responsive
Integration Transmission Service
Form Operating Agreement for
GRITS service.
VI.
STAKEHOLDER ENGAGEMENT
MISO developed the GRITS proposal through successive discussions with the Large Load
Working Group (“LLWG”). At the August 12, 2026 LLWG meeting, MISO presented its Flexible
Large-Load Interconnections and Transmission Service (“FLITS”) concept, which contemplated
both interim and permanent non-firm service. MISO requested written feedback by August 19,
2026, with particular emphasis on resource adequacy. Stakeholders addressed curtailment,
capacity obligations, and the implications of offering permanent non-firm service. The
environmental sector recommended developing separate interim and permanent products given
their different purposes and operating requirements.26
At the September 9, 2026 LLWG meeting, MISO presented interim FLITS and a separate
permanent Contract Demand service and requested written comments by September 16.
Stakeholders addressed how the proposed services would differ in rates, curtailment priority,
resource adequacy treatment, and ARR eligibility. At the September 23, 2026 LLWG meeting,
MISO focused its presentation on Interim NITS and confirmed during the discussion that it
continued to develop the permanent service and would return with an update on October 8, 2026.
The September 23, 2026 feedback request set an October 2, 2026 deadline for comments on the
Interim NITS design and an October 16 deadline for comments on the anticipated Interim NITS
Tariff redlines.27
At the October 8, 2026 LLWG meeting, MISO presented the permanent service as GRITS
and requested written feedback by October 16, 2026. The proposal allowed customers to combine
a firm service quantity with short-term, as-available non-firm reservations. MISO also proposed
excluding the non-firm portion from the Coincident Peak Demand forecast and requiring
interruption under specified reliability and price conditions. Stakeholders commented on the
proposed price trigger, coordination and enforcement of curtailment, capacity forecasting and
modeling, and the treatment of co-located resources. They also asked how a customer could
increase its firm service quantity after service began.
26 MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service (FLITS) Proposal, LLWG-2026-
5 (Aug. 12, 2026) (feedback request and submitted comments, including Environmental Sector comments).
(misoenergy.org, misoenergy.org).
27 MISO, LLWG, Non-Firm Large Load, Item 6 (Sept. 9, 2026), and associated feedback request and comments,
LLWG-2026-5. See also MISO, LLWG, Conditional Non-Firm Transmission Service, Item 7, slide 2 (Sept. 23,
2026), and associated Interim NITS feedback request, LLWG-2026-5. (misoenergy.org, cdn.misoenergy.org,
misoenergy.org).
PDF page 16
The Honorable Debbie-Anne Reese
November 16, 2026
Page 16
At the October 29, 2026 LLWG meeting, MISO presented GRITS alongside Interim NITS
and reviewed the differences in reservation terms, service priority, billing, and resource adequacy
treatment. After receiving stakeholder feedback on the October 8, 2026 proposal, MISO reported
that it was evaluating whether to use a GRITS Offer Cap as a price-based interruption trigger and,
if so, where to set it. Stakeholders submitted additional written comments on November 4
addressing, among other matters, non-firm transmission charges, the proposed price trigger, and
resource adequacy treatment.28
VII.
DOCUMENTS SUBMITTED IN THIS FILING
In addition to this Transmittal Letter, this submission includes the following materials, with
the final tab and exhibit designations identified in the filing index:
Tab A – Redline Tariff29
Tab B – Clean Tariff
Tab C – Testimony of Zhaoxia Xie
VIII.
EFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE
MISO requests an effective date 120-days from the date of this filing (i.e., March 16, 2027),
with implementation of GRITS to begin January 1, 2029. Acceptance of the GRITS proposal by
the requested effective date is necessary to facilitate the planned implementation timeline because
such implementation requires significant modifications to MISO’s existing software systems and
processes, coordinated service agreements, models, market registration, billing arrangements,
operating controls, and communications.
28 MISO, LLWG, Interim NITS and Grid Responsive Integration Transmission Service, Item 5, slides 2, 8, 20–24
(Oct. 29, 2026). Antora Energy comments (Nov. 4, 2026, posted Nov. 9, 2026). (cdn.misoenergy.org,
cdn.misoenergy.org, misoenergy.org, misoenergy.org).
29 Language currently pending before the Commission in the following, unrelated dockets is highlighted in yellow:
ER26-3552-000 and ER26-3650-000. Also highlighted is pending language filed in MISO’s Large Load Omnibus
filing being submitted contemporaneously. MISO requests that the Commission treat such highlighted language
as subject to the outcome of those pending proceedings. If needed, MISO commits to file any revisions to this
highlighted language as necessary to comply with any Commission orders in the proceeding.
In addition, MISO has not included language that has future effective dates of 6/1/2027, 9/1/2027, 6/12/2028,
6/1/2029, under Docket Nos. ER22-1640-007, ER22-1640-006, and ER22-1640-003, respectively. MISO has also
removed language that has a future effective date of 9/1/2027 and is pending in Docket No. ER25-1886-000. If
needed, MISO commits to file any revisions to comply with any Commission orders in these proceedings and
MISO commits to make subsequent filings with the Commission to reflect the most up-to-date version of the
then-current Tariff provisions prior to the effective dates of the language.
PDF page 17
The Honorable Debbie-Anne Reese
November 16, 2026
Page 17
MISO also moves to extend the existing abeyance period under Rule 212 of the
Commission’s Rules of Practice and Procedure.30 As the Abeyance Order explained, the
Commission encouraged MISO, the Transmission Owners, and stakeholder to continue to
collaborate in order to develop one or more FPA section 205 proposals to address the requirements
of the Show Cause Order.31 The GRITS proposal is one output from this ongoing stakeholder
process. As stated, MISO cannot implement GRITS until January 1, 2029, subject to the
Commission accepting a rate, which as explained above will be submitted in for Commission
review in a future filing. MISO, therefore, moves to extend the abeyance period until the
Commission accepts the GRITS proposal and applicable rate for Firm and Non-Firm GRITS.
MISO respectfully submits that this extension to the abeyance is necessary to avoid a lapse in the
existing abeyance period while the GRITS rate is determined. Moreover, granting the continued
abeyance is reasonable, especially in light of the limited scope of request as compared to the
significant proposals filed in response to the Show Cause Order.
IX.
COMMUNICATIONS
MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of
Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the
designation of more than two persons for service on behalf of MISO in this proceeding and requests
all communications related to this filing be directed to:
Michael Kessler
Managing Assistant General Counsel
Midcontinent Independent System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 753-9434
mkessler@misoenergy.org
James C. Holsclaw
Lauren A. Stenger
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com
lastenger@calfee.com
X.
NOTICE AND SERVICE
MISO has served a copy of this filing electronically, including attachments, upon all Tariff
customers, MISO Members, Member representatives of Transmission Owners and non-
Transmission Owners, as well as all state commissions within the MISO Region and the
Organization of MISO States. The filing has been posted electronically on MISO’s website at
https://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter.
30 See 18 C.F.R. § 385.212 (2026).
31 Midcontinent Indep. Sys. Operator, Inc., 196 FERC P 61,133, at PP 8-9 (2026) (“Abeyance Order”).
PDF page 18
The Honorable Debbie-Anne Reese
November 16, 2026
Page 18
XI.
CONCLUSION
For all of the foregoing reasons, MISO respectfully requests that the Commission accept
this filing and grant waiver of any Commission regulations the Commission deems in order for the
Commission to accept it as proposed.
Respectfully submitted,
/s/ Michael Kessler
Michael Kessler
Managing Assistant General Counsel
Midcontinent Independent System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 753-9434
mkessler@misoenergy.org
James C. Holsclaw
Lauren A. Stenger
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com
lastenger@calfee.com
Attorneys for the Midcontinent Independent
System Operator, Inc.
Attachments