ER27-527-000 · 2026-11-16 · Midcontinent Independent System Operator, Inc.

MISO files the Grid Responsive Integration Transmission Service under section 205

Back to sections and commentary

PDF page 1

Midcontinent Independent 
System Operator, Inc. 
317.249-5400 
www.misoenergy.org 
720 City Center Drive 
Carmel, Indiana 46032 
2985 Ames Crossing Road 
Eagan, Minnesota 55121 
1700 Centerview Drive 
Little Rock, AR 72211 
 
Michael Kessler 
Managing Assistant General Counsel 
Direct Dial:  317-753-9434 
Email:  mkessler@misoenergy.org 
November 16, 2026 
VIA ELECTRONIC FILING 
The Honorable Debbie-Anne Reese  
Secretary 
Federal Energy Regulatory Commission 
888 First Street, NE 
Washington, DC  20426 
Re: 
Midcontinent Independent System Operator, Inc.’s  
Grid Responsive Integration Transmission Service for Large Loads 
Docket No. ER27-___-000 
 
Dear Secretary Reese: 
The Midcontinent Independent System Operator, Inc.  (“MISO”), through this filing,1 
submits proposed revisions to its Open Access Transmission, Energy and Operating Reserve 
Markets Tariff (“Tariff”),2 establishing the Grid Responsive Integration Transmission Service 
(“GRITS”).  GRITS provides a permanent firm and non-firm contract demand-based, 
Transmission Service option for Large Loads willing and able to limit their withdrawals under 
specified price and reliability conditions.   
 
MISO is submitting GRITS as a separate FPA section 205 filing from the Large Load 
Project Review (“LLPR”) process, cost recovery agreements, Firm Service Step Up (“FSSU”), 
and Interim Network Integration Transmission Service (“Interim NITS”).3  These initiatives are 
addressed in MISO’s separate large load omnibus filing submitted concomitantly.  The GRITS 
proposal is a stand-alone proposal and MISO describes the proposals contained in the omnibus 
filing here only as necessary to explain the interfaces with GRITS. 
 
MISO requests that the Commission accept the proposed revisions effective 120-days from 
the date of this filing (i.e., March 16, 2027) in order to facilitate MISO’s development of software 
 
1  
This filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C.  § 824d, and Part 35 of 
the regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R.  § 35.1, 
et seq. 
2  
Unless otherwise indicated by the text or context of this transmittal letter, all terms used herein have the definitions 
set forth in Module A of the Tariff. 
3  
These filings are being submitted contemporaneously in response to the associated concerns set forth in the Show 
Cause Order.

PDF page 2

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 2 
 
 
systems and related process modifications necessary to implement GRITS in early 2029, and to 
continue the development of rates applicable to GRITS in concert with the MISO Transmission 
Owners.  The GRITS proposal responds to the Commission’s concerns regarding the need for an 
ongoing firm and non-firm contract demand service option for flexible Large Loads, including, 
but not limited to, co-located arrangements.  The specific relationship to the proceeding in Docket 
No.  EL26-70-000 is addressed below. 
I. 
EXECUTIVE SUMMARY 
MISO appreciates the collaborative efforts of its stakeholder community and the 
Transmission Owners in developing proposals for the reliable integration of Large Loads on an 
expedited basis, consistent with the urgency created by the timelines established in the Show Cause 
Order. 
 
This filing provides the GRITS framework, which addresses the concerns raised by the 
Commission in the Show Cause Order with respect to the need for a permanent contract demand 
transmission service in the MISO region.  As discussed in more detail below, the earliest MISO 
will be able to implement GRITS is January 1, 2029.  This implementation timeline is driven by 
the need for significant modifications to MISO’s software systems and processes to  facilitate the 
reservation, scheduling, market systems, and billing services for GRITS, which is a new 
transmission service that does not conform with the transmission services offered today under 
MISO’s Tariff.  MISO recognizes the desire for the proposed service as noted by certain 
stakeholders and agrees that GRITS must provide a reliable and workable path for customers that 
elect permanent contract demand-based firm and/or non-firm transmission service and is 
committed to implementation of GRITS consistent with Commission acceptance and on a timeline 
that is technically feasible. 
 
Given the extended timeline for implementing GRITS, MISO and the Transmission 
Owners,  prioritized their efforts on solutions that can be delivered in the near term, including the 
Zero Injection Generator Interconnection Agreement (“ZGIA”) proposal, Interconnection 
Reliability Requirements (“IRR”), Load Addition Resource Study (“LARS”) proposal, Firm 
Service Step Up, Interim NITS and LLPR, including the development of pro forma cost recovery 
agreements to prevent unjust cost shifts related to upgrades identified through the LLPR process.  
This prioritization was necessary given the competing priorities of MISO’s proposals in response 
to the Show Cause Order and the abbreviated time frame during which the multiple issues 
identified in the Show Cause order needed to be addressed.  Moreover, GRITS is a novel and 
complex market-dependent approach to transmission service that was conceived later in the 
abeyance period (i.e., October 2026) and has necessitated greater stakeholder outreach and 
education.  As stated above, considerable work remains including significant modifications to 
MISO’s, and as may be required, the Transmission Owner’s and other Market Participants’, 
software systems and processes to accommodate GRITS.  As such, MISO requests Commission 
acceptance of the proposed GRITS framework to begin software development consistent with the 
Commission’s order and further requests the Commission permit MISO and the Transmission 
Owners to continue to develop a new rate structure applicable to GRITS and work with

PDF page 3

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 3 
 
 
stakeholders to continue to refine the proposal on a timeline that will facilitate GRITS 
implementation in early 2029.   
 
II. 
BACKGROUND 
The scale and pace of large load development require transmission service options that 
reflect how a Large Load customer intends to use the Transmission System.  Some Large Load 
Transmission Customers may seek full firm service and need an interim arrangement while 
necessary supporting upgrades are completed.  MISO is proposing in its omnibus filing both an 
Interim NITS product and Firm Service Step Up process that will be implemented within its 
existing NITS framework to address these transmission service needs.  Other Large Load 
Transmission Customers may be able to accept continuing interruption of some or all of their 
demand and seek an ongoing allocation between firm and non-firm service on a permanent basis.  
GRITS addresses both of these needs as it provides the Large Load Transmission Customer the 
option to determine the appropriate combination of firm and non-firm contract demand 
transmission services needed to meet its operational needs, but does not require the Large Load 
Transmission Customer to progress toward firm service for any or all of its GRITS Load Limit.4   
 
In the June 18, 2026, Show Cause Order, the Commission examined whether MISO’s 
Tariff adequately addresses large and co-located load development, including service for loads 
willing and able to limit their withdrawals under certain conditions.  The Commission identified a 
permanent contract-demand-like service option, treatment of regulation and black start service, 
and controls needed to enforce withdrawal limits among the matters requiring attention.5   
 
The Commission permitted respondents to develop regional solutions through section 205 
filings and subsequently held the proceeding in abeyance.  MISO has advanced related proposals 
through separate filings, including Zero Injection Generator Interconnection Agreements 
(“ZGIA”), Interconnection Reliability Requirements for Large Loads (“IRR”), and the Large Load 
Addition Resource Study (“LARS”) and the Large Load omnibus filing submitted separately 
pursuant to FPA section 205.  GRITS provides a distinct Transmission Service option that can 
operate with the applicable study, interconnection, and reliability requirements.  Generator 
Interconnection Service does not itself provide the Transmission Service needed for associated 
load.6 
 
 
4  
GRITS Load Limit: The maximum amount of Load specified in the Form of Service Agreement for GRITS by 
the Large Load Transmission Customer taking GRITS that may be scheduled at a Point(s) of Delivery pursuant 
to Module B of this Tariff. 
5  
Midcontinent Indep.  Sys.  Operator, Inc., 195 FERC ¶ 61,212, PP 98–105 (2026), errata notice, 196 FERC ¶ 
61,123 (2026) (“Show Cause Order”). 
6  
Show Cause Order P 37; Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,133, PP 8-11 (2026) 
(“Abeyance Order”); ZGIA Transmittal at 1-2, 6-7.

PDF page 4

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 4 
 
 
III. 
  PROPOSED GRITS SERVICE 
A. 
Eligibility, service quantities, and agreements. 
 
GRITS provides an ongoing service arrangement for a Large Load Transmission Customer 
serving a Large Load that may desire a combination of both firm and non-firm contract demand-
like transmission service and, with respect to any non-firm service, is willing and able to limit its 
withdrawals under specified price and reliability conditions.  For example, a Large Load 
Transmission Customer representing a Large Load of 500 MW may desire to only take 200 MW 
of firm transmission service, allowing the remaining 300 MW to be served on a non-firm basis.  
Under Network Integration Transmission Service this participation model is not available while 
GRITS provides a pathway for such an arrangement. 
    
GRITS will only be made available to a Large Load Transmission Customer, cannot be 
combined with any other NITS transmission service, and is not limited to Large Load being served 
by a co-located generator.  GRITS Service requires that a Large Load Transmission Customer 
establish a GRITS Load Limit and a Firm GRITS quantity that may range from zero to the full 
Load Limit in the pro forma GRITS service agreement (“GRITS Service Agreement”), which 
cannot be exceeded without execution of a new pro forma GRITS Service Agreement.  Non-Firm 
GRITS may be reserved within the difference between those quantities as needed and as available.  
The GRITS Load Limit defines the maximum approved Load in the GRITS Service Agreement; 
it does not guarantee that the entire non-firm quantity will be available in every period. 
 
GRITS contains the firm and non-firm components within one GRITS Service Agreement.  
MISO does not propose combining NITS and GRITS for the same load to create that allocation, 
and a change to the GRITS Load Limit or Firm GRITS quantity requires a new GRITS Service 
Agreement.  Where both firm and non-firm quantities are present, separate Commercial Pricing 
Nodes (“CPNodes”) represent those components.  This representation supports the different 
reservation, interruption, billing, capacity, and Auction Revenue Rights (“ARR”) treatment 
applicable to each GRITS service component. 
 
For example, a 300 MW GRITS Load Limit with 60 MW of Firm GRITS permits a 
maximum non-firm quantity of 240 MW.  At 200 MW of operating demand, the proposed 
allocation assigns the first 60 MW to the CPNode representing the firm component and the 
remaining 140 MW to the CPNode representing the non-firm component.  That allocation is 
subject to an available reservation and the applicable operating limit; the agreement’s 240 MW 
non-firm maximum does not itself establish that 240 MW will be available for every hour. 
 
As noted above, GRITS accommodates both stand-alone Large Loads and qualifying co-
located arrangements.  A Large Load Transmission Customer must request GRITS through the 
applicable LLPR process and will be required to execute a GRITS Service Agreement and a 
GRITS Operating Agreement specifying the quantities, operational limits, communications, and 
control requirements.  Service commences after Network Upgrades, Large Load Network 
Upgrades and/or Impacted Transmission Owner Large Load Network Upgrades identified through

PDF page 5

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 5 
 
 
the LLPR process are complete and the applicable service and operating prerequisites are satisfied.  
As explained by Ms. Xie, Firm Service Step-up, which is proposed in MISO’s Omnibus Filing, 
cannot be combined with GRITS because GRITS establishes its own ongoing allocation of firm 
and non-firm service within the GRITS Service Agreement.   
 
B. 
Reservations and service priority. 
 
Non-Firm GRITS will be reserved through the Open Access Same-Time Information 
System (“OASIS”) for periods ranging from one Day to one month.  The reservation rules use the 
existing Point-To-Point Transmission Service framework, including priority for longer requested 
service periods within the permitted range and the order of competing equal-duration requests.  A 
new reservation receives its applicable position in that process.  The underlying Form of GRITS 
Service Agreement does not reserve non-firm service indefinitely, and reservation priority of non-
firm service remains distinct from the priority applied when existing service must be curtailed. 
 
Firm GRITS is reserved for at least one year within the ongoing arrangement.  Reservation 
priority determines the order in which requests are evaluated; curtailment priority determines 
which existing service is reduced when the system cannot support scheduled use.  A customer’s 
continuing GRITS agreement does not establish an indefinite reservation of non-firm capability.  
The following depicts the priority of Firm and Non-Firm GRITS: 
 
 
 
C. 
Transmission charges and gross-load billing. 
 
GRITS will use reservation-based Transmission Service charges benchmarked to the rates 
for GRITS service that will be filed in a subsequent FPA section 205 filing.  MISO notes that it

PDF page 6

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 6 
 
 
will continue working with its Transmission Owners specifically,7 and the broader stakeholder 
community, to develop the rates applicable to GRITS transmission services.  MISO and the 
Transmission Owners intend to either submit the proposed GRITS transmission service rates prior 
to the proposed implementation date requested herein (i.e., March 16, 2027) or provide the 
Commission with a status report detailing the progress that has been made to establish such rates 
as well a revised date to propose such rates. 
 
Given the expansive scope of issues that need to be addressed in the Show Cause Order, 
and the relatively limited amount of time to consider and address those issues, there has simply 
not yet been sufficient opportunity for MISO and MISO Transmission Owners to finalize a rate 
design for GRITS.  Notwithstanding the lack of such rates being included in this filing, MISO has 
developed a sufficiently detailed and robust transmission service that both complies with the intent 
of the Show Cause Order and merits Commission acceptance, subject to further compliance.  This 
is particularly the case because GRITS cannot be provided until January 2029.   
 
The GRITS proposal also applies gross-basis treatment to applicable service-related 
charges, including regulation and black start, so that a co-located arrangement does not avoid 
charges for services it receives merely because its net withdrawal is below its gross load.  These 
reservation-based charges and gross-basis billing serve different functions and apply through the 
billing determinants established for the particular service. 
 
A reservation-based charge, such as that used for the existing Point-To-Point Transmission 
Service rates, reflects the amount of Transmission Service reserved, rather than actual 
consumption alone.  The applicable schedules govern any billing adjustment or credit for 
interrupted service.  Co-located generation serving a Large Load receiving GRITS service must 
be registered as a Generation Resource, and the Large Load Transmission Customer must procure 
Transmission Service to receive service from the co-located resource.  Co-location therefore does 
not eliminate the obligation to procure Transmission Service or permit the customer to “net away” 
gross load relevant to regulation and black start billing.   
 
D. 
Price-based interruption. 
 
Non-Firm GRITS will be interrupted when the Locational Marginal Price at its CPNode 
exceeds the GRITS Offer Cap, which is $100/MWh.  Ms. Xie explains that historical data, 
including the 2025 State of the Market Report, indicates that historical data indicates this price 
permits service more than 95% of all Hours.8  To effectuate the GRITS Offer Cap in the Day-
Ahead Energy and Operating Reserve Market, the Market Participant representing the Large Load 
will be required to submit a Price Sensitive Demand Bid for the CPNode representing the non-
 
7  
MISO’s Transmission Owners have filing rights with respect to the rates for transmission service pursuant 
Appendix K to the Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent 
System Operator, Inc., Rate Schedule No. 1 of the Tariff (“Transmission Owners Agreement"). 
8  
2025 STATE OF THE MARKET REPORT FOR THE MISO ELECTRICITY MARKETS available at: 
https://www.potomaceconomics.com/wp-content/uploads/2026/07/2025-MISO-SOM_Appendix_Final.pdf.

PDF page 7

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 7 
 
 
firm portion of the GRITS Load that is no greater than $100/MWh.  The GRITS Offer Cap will be 
effectuated in both the Day-Ahead and Real-Time Energy and Operating Reserve Markets by 
incorporating the Non-Firm GRITS portion of the GRITS Load into the Security Constrained Unit 
Commitment (“SCUC”) and Security Constrained Economic Dispatch (“SCED”) processes.  As 
such, Ms. Xie explains that the Large Load Transmission Customer’s election of Non-Firm GRITS 
therefore includes the ability to comply with both the price condition and the resulting operating 
directive. 
 
Ms. Xie further explains that the GRITS Offer Cap serves two complementary objectives.9  
First, by establishing the GRITS Offer Cap, MISO can use the Security Constrained Economic 
Commitment (“SCUC”) and Security Constrained Economic Dispatch (“SCED”) processes to 
efficiently issue Interruption directives to the Non-Firm GRITS Load without relying upon 
administrative Emergency procedures. Requiring Non-Firm GRITS Loads to be included in the 
SCUC/SCED processes provides an automated and transparent way of curtailing these Loads as 
the system conditions experienced reduced transmission or generation capacity.  Second, 
establishing the GRITS Offer Cap at the first non-zero step of the Market-Wide Short-Term 
Reserve Demand Curve prevents reliability being degraded for all Transmission Customers by 
ensuring the Non-Firm GRITS Load is offline before a shortfall of operating reserves occurs.  This 
limitation reflects the “as-available” nature of Non-Firm GRITS and is consistent with the 
reliability rationale underlying the Tariff’s authorization to curtail Non-Firm Point-To-Point 
Transmission Service when an Emergency or other unforeseen condition threatens to impair or 
degrade Transmission System reliability.   
 
E. 
Reliability based Curtailment and enforcement. 
 
Non-Firm GRITS Load is also subject to reliability-based Curtailment directives, including 
Curtailment upon the declaration of a Capacity Advisory in the same Local Balancing Authority 
(“LBA”).  During Transmission Emergencies, Non-Firm GRITS Load is curtailed with the same 
priority as Loads served using Non-Firm Point-To-Point Transmission Service of equal service 
duration and before Loads served through Interim NITS and Firm Transmission Service.  Ms. Xie 
explains how Resource Adequacy is maintained if the Non-Firm GRITS Load is excluded from 
the Planning Resource Auction because the GRITS Offer Cap will ensure these Loads are curtailed 
whenever LMP rises above the GRITS Offer Cap.10  In the event a Capacity Advisory declaration 
is made while LMP is below the GRITS Offer Cap, MISO will issue the Curtailment directive for 
the entire Non-Firm GRITS Load.11  Accordingly, Resource Adequacy is assured because these 
Loads will not be competing with other types of Load at the times when Resource Adequacy is 
under pressure.  The portion of a Large Load served through Firm GRITS remains in the 
Coincident Peak Demand forecast and retains the corresponding capacity responsibility to procure 
Zonal Resource Credits. 
 
9  
Xie at 9. 
10   Xie at 16. 
11   Id.

PDF page 8

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 8 
 
 
 
GRITS depends on observable and enforceable withdrawal limits.  Metering, telemetry, 
model representation, communications, and operating controls support MISO’s administration of 
those limits.  The Transmission Owner will determine additional control technologies or protection 
systems required for the arrangement.  MISO will communicate Interruption and Curtailment 
directives through the Market Participant representing the Load in MISO’s Energy and Operating 
Reserve Markets, and applicable operating procedures will govern restoration.  
 
Ms. Xie explains that if the Large Load Transmission Customer with Non-Firm GRITS 
fails to interrupt when directed, the applicable Transmission Owner has the authority implement 
remote disconnect procedures, and the Large Load Transmission Customer will be subject to 
unreserved use penalties, additional financial penalties for repeated failure, and possible 
termination of Transmission Service.12  These consequences support the operating limitations the 
customer accepts in electing GRITS.   
 
F. 
Resource Adequacy, ARR Entitlements, and market participation. 
 
Firm GRITS remains subject to the applicable Resource Adequacy and capacity obligations 
established in Module E of the Tariff and is eligible to register as a Load Modifying Resource.  
Ms. Xie explains, the portion of a Large Load served through Non-Firm GRITS service may be 
excluded from the obligation to procure Zonal Resource Credits.13  This means this portion of the 
Large Load will not be included in the Coincident Peak Demand forecast and a Market Participant 
is not eligible to enroll the Non-Firm GRITS portion of the Large Load as a Load Modifying 
Resource. The portion of a Large Load served through Firm GRITS is required to procure Zonal 
Resource Credits and is eligible to participate as a Load Modifying Resource.  
 
MISO is not proposing changes to the eligibility requirements for a Load to receive Auction 
Revenue Rights (“ARR”).  The Tariff changes proposed herein clarify that ARR Entitlements are 
limited to Firm GRITS Load only, and the non-firm component of GRITS Load is excluded from 
acquiring ARRs and from the Peak Usage determination.  
 
The proposal prohibits Non-Firm GRITS Load from participating as a Demand Response 
Resource (“DRR”), Load Modifying Resource (“LMR”), or Emergency Demand Response 
(“EDR”) resource.  As explained by Ms. Xie, prohibition of Non-Firm GRITS Load from 
participating as a DRR is consistent with Order No. 745.  Prohibiting enrollment as a Load 
Modifying Resource also follows from these Loads not having an obligation to procure Zonal 
Resource Credits.14  
 
 
12  Xie at 20. 
13  Xie at 16. 
14  Xie at 16.

PDF page 9

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 9 
 
 
G. 
Planning and commercial model treatment. 
 
The firm component of GRITS Load is included in ongoing MISO Transmission 
Expansion Plan (“MTEP”) planning, while the total GRITS Load remains subject to applicable 
Interconnection Reliability Requirements (“IRR”) and stability review.  The requirement to 
establish separate CPNodes for Firm and Non-Firm GRITS Load respectively, and corresponding 
Elemental Pricing Nodes allow the service allocation to be reflected in operations, forecasts, 
bidding, billing, and ARR treatment.  Actual  Energy Withdrawals associated with GRITS service 
are assigned first to the firm component, up to the Firm GRITS service quantity, with remaining 
withdrawals assigned to the Non-Firm GRITS quantity.  This representation does not authorize 
withdrawals beyond a valid Transmission Service Reservation or the applicable operating limit.   
 
IV. 
RESPONSE TO THE SHOW CAUSE ORDER 
 
Section 205 requires jurisdictional rates and practices to be just and reasonable and 
prohibits undue preferences and unreasonable differences in service.15  GRITS ties the 
Transmission Customer’s rights to the service it requests: firm quantities retain firm treatment and 
corresponding capacity obligations, while non-firm quantities receive as-needed and as-available 
service, lower priority for reliability interruptions, and a price-based interruption condition.16  
Separate reservation requirements and model treatment for Firm and Non-Firm GRITS makes 
those distinctions administrable. 
 
The GRITS proposal responds to the ongoing flexible-service concerns in paragraphs 100 
through 105 of the Show Cause Order by establishing a defined Load Limit, an elected firm 
quantity, separately reserved non-firm service, and enforceable operating conditions.17  The 
proposal’s gross-load treatment prohibits netting and addresses the regulation and black start 
concerns identified in Paragraphs 98–100 of the Show Cause Order.  In addition, the proposal’s 
metering and control requirements address the withdrawal-limit concerns in paragraph 102 of the 
Show Cause Order.  Those features connect the service received with the obligations accepted by 
the customer.18   
 
The planning provisions of the GRITS proposal, which require requests for GRITS to be 
evaluated through the LLPR process consistent with all other requests for Transmission Service 
made by Large Load Transmission Customers, also address the issue identified in Paragraph 124 
of the Show Cause Order.19  Through this process requests for Firm GRITS will be subject to the 
analysis for ongoing firm service, which reflects the Firm GRITS quantity, while total GRITS 
 
15  16 U.S.C. § 824d(a)–(b). 
16  Show Cause Order at PP 100-105; Xie at 6, 20. 
17  Xie at 18-21. 
18  Show Cause Order at PP 98–105. 
19  Xie at 7; Show Cause Order at P 124.

PDF page 10

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 10 
 
 
Load remains subject to reliability and stability assessment.20  The GRITS accreditation provisions 
for co-located ZG Resources addresses the portion of paragraph 127 of the Show Cause Order 
concerning the relationship between capacity recognition and the associated load’s service.21  
These provisions supplement the separately proposed study and generator-interconnection 
frameworks.22   
 
Reservation-based charges, gross-load ancillary service billing, price-based interruption, 
and firm-only ARR eligibility address different aspects of cost responsibility.23  The separately 
proposed cost recovery agreements submitted in the omnibus filing are required for all address 
obligations associated with covered Large Load Network Upgrades and Impacted Transmission 
Owner Network Upgrades.  Because requests for GRITS are required to be evaluated through the 
LLPR, all Large Load Transmission Customers granted GRITS will be required to enter into the 
Form of Agreement for Large Load Cost Recovery Agreement (proposed Attachment LLL) and 
Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery Agreement 
(proposed Attachment MMM).24 
 
GRITS service is only available to Large Load Transmission Customers capable of meeting 
operational requirements for GRITS and these enforcement mechanisms ensure that the approved 
service quantities are not merely contractual limits but are limits that MISO can enforce in real 
time.25  Large Load Transmission Customers electing GRITS are subject to the same applicable 
service conditions.  The distinct treatment of Firm and Non-Firm GRITS quantities reflects the 
unique characteristics, firmness, curtailment and interruption obligations of each respective 
service.   
 
V. 
DESCRIPTION OF PROPOSED TARIFF REVISIONS 
 
As discussed, GRITS is an independent, stand-alone proposal that can be accepted and 
implemented separate from MISO’s other FPA section 205 filing submitted in response to the 
Show Cause Order.  Because MISO’s omnibus filing has been submitted prior to this filing, MISO 
has built the GRITS Tariff revisions to include (i.e., on top of) the proposed revisions to the Tariff 
submitted in the omnibus filing.  MISO has highlighted all Tariff language pending Commission 
acceptance in the Tariff records submitted in Tab A hereto.   
 
The proposed Tariff records establish GRITS eligibility and defined quantities; application, 
establish a Form of GRITS Service Agreement, and Operating Agreement requirements; 
 
20  Xie at 7, 19-21. 
21  Xie at 17-18. 
22  Show Cause Order at PP 124, 127. 
23  Xie at 15-16, 19-20. 
24  Xie at 7. 
25  Xie at 20-21.

PDF page 11

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 11 
 
 
reservation duration and priority; price and reliability interruption; control, enforcement, and 
restoration requirements; and changes to the Load Limit or firm quantity.  Conforming revisions 
to Module C of the Tariff implement separate commercial model representation requirements, 
establish ARR eligibility only for Firm GRITS, establish Resource Adequacy treatment, 
participation restrictions, and the co-located ZG Resource accreditation interface.   
 
A. 
Definitions 
 
 
MISO proposes the following, new definitions for GRITS: 
 
Firm Grid Response Integration Transmission Service (Firm GRITS):  The amount of 
firm Transmission Service that is reserved and/or scheduled to a specific Point(s) of 
Delivery pursuant to the Form of Service Agreement for GRITS.  A Large Load 
Transmission Customer taking Firm GRITS may reserve and/or schedule between 0 MW 
and the GRITS Load Limit. 
 
Grid Response Integration Transmission Service (GRITS):  A Transmission Service 
provided under Module B of this Tariff that permits a Large Load Transmission Customers 
to take Transmission Service.  GRITS permits the reservation of Capacity and of Energy 
on either a firm or non-firm basis from Network Resources to the Point(s) of Delivery.  
GRITS is comprised of three components; GRITS Load Limit, Firm GRITS, and Non-Firm 
GRITS.  A Transmission Customer may not change the GRITS Load Limit or the amount 
of Firm GRITS without a new Form of Service Agreement for GRITS. 
 
GRITS Load Limit:  The maximum amount of Load specified in the Form of Service 
Agreement for GRITS by the Large Load Transmission Customer taking GRITS that may 
be scheduled at a Point(s) of Delivery pursuant to Module B of this Tariff. 
 
GRITS Offer Cap:  The maximum Locational Marginal Price at the Commercial Pricing 
Node associated with a Large Load taking Non-Firm GRITS service that a Market 
Participant may submit in a Bid.  Non-Firm GRITS may be Interrupted if the Locational 
Marginal Price rises above the GRITS Offer Cap. 
 
Non-Firm GRITS:  The amount of Non-Firm Transmission Service that is reserved and 
scheduled on an as-available basis and is subject to Curtailment or Interruption as set forth 
in Section 37B of this Tariff.  Non-Firm GRITS is available only to Large Load 
Transmission Customers for periods ranging from one (1) Day to one (1) Month.  A Large 
Load Transmission Customer taking Grid Responsive Integration Transmission Service 
may reserve and/or schedule between 0 MW and the difference of GRITS Load Limit and 
Firm GRITS.

PDF page 12

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 12 
 
 
 
B. 
Module B 
 
 
MISO has revised the introduction of Module B of the Tariff to establish GRITS as a 
service available only to Large Load Transmission Customers.  In addition, MISO has established 
Section 37B of the Tariff to include the terms and conditions of GRITS.  The following table 
provides a brief overview of the proposed GRITS Tariff revisions in addition to the definitions. 
 
 
The marked and clean Tariff records submitted as Tab A and B respectively, set out the 
revisions.  The following table of Tariff revisions is provided for reference and informational 
purposes only.  The language filed in the proposed Tariff revisions shall control in the event of any 
discrepancies between the information provided in this table and the proposed Tariff revisions.  
 
Tariff Section 
Tariff Section Title 
Brief Description of changes 
Module B 
 
 
37B.1 
GRITS Term 
Establishes the minimum service 
terms for Firm GRITS and Non-Firm 
Grits 
37B.2 
GRITS Reservation Priority 
Establishes the reservation priority for 
Firm GRITS and Non-Firm GRITS 
relative to other Transmission 
Services under the Tariff 
37B.3 
GRITS Service Agreement 
Establishes the requirement that a 
Large Loat Transmission Customer 
taking GRITS must execute a Form of 
Service Agreement for GRITS. 
37B.4 
GRITS Change in Service Request 
Establishes the requirement that a 
Large| Loat Transmission Customer 
seeking to change the amount of 
GRITS must submit a new application 
for GRITS. 
37B.5 
GRITS Transmission Provider 
Responsibilities 
Establishes MISO’s responsibilities 
for revising GRITS requests. 
37B.6 
Secondary Service to Firm GRITS 
Establishes the treatment of Firm 
GRITS from non-Designated Network 
Resources and the associated priority 
of the service. 
37B.7 
GRITS Restrictions on Use of 
Service 
Requires any Large Load 
Transmission Customer to use Point-
to-Point Transmission Service for 
third-party sales outside of the MISO 
Region. 
37B.8 
GRITS Application Procedures 
Establishes the application and 
procedures for requesting GRITS, and

PDF page 13

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 13 
 
 
provides detail regarding the 
evaluation of a GRITS request. 
37B.9 
GRITS Arrangement to be 
Completed Prior to Service 
Establishes the requirement to 
complete installation of all equipment 
specified under the GRITS Operating 
Agreement prior to service. 
37B.10 
GRITS Transmission Customer 
Facilities 
Establishes responsibility for 
construction, maintenance and 
operation of facilities used to provide 
GRITS. 
37B.11 
GRITS Study Procedures 
Establishes the study procedures for 
requests for Non-Firm GRITS. 
37B.12 
GRITS Procedures 
Requires that procedures for Load 
Shedding, Curtailment and 
Interruption be established by MISO, 
the Transmission Owner and Large 
Load Transmission Customer prior to 
commencement of GRITS. 
37B.13 
GRITS Transmission Constraints 
States that MISO will take actions 
necessary to maintain Transmission 
System reliability if necessary to 
address a transmission constraint. 
37B.14 
GRITS Cost Responsibility for 
Relieving Transmission Constraint 
Establishes that curtailment of 
scheduled deliveries may occur in 
accordance with the applicable 
GRITS Operating Agreement or 
NERC / NAESB TLR procedures. 
37B.15 
GRITS Curtailment of Scheduled 
Deliveries 
Establishes the procedure for 
curtailing Firm GRITS. 
37B.16 
GRITS Load Shedding 
Established the procedures for Load 
Shedding relative to Firm GRITS. 
37B.17 
GRITS System Reliability 
Establishes the provisions for 
curtailment of Firm and Non-Firm 
Grits, and the costs associated with a 
Large Load Transmission Customer’s 
failure to respond to MISO’s 
curtailment directives. 
37B.18 
Classification of Firm GRITS 
Limits the use of FIRM GRITS to the 
levels specific in the applicable 
GRITS Service Agreement. 
37B.19 
Classification of Non-Firm GRITS 
Establishes unreserved use penalties 
for Non-Firm GRITS 
37B.20  
Scheduling of Non-Firm GRITS 
Requires Non-Firm GRITS schedules 
to be submitted consistent with the

PDF page 14

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 14 
 
 
requirements of Attachment J to the 
Tariff. 
37B.21 
Non-Firm GRITS Curtailment or 
Interruption of Service 
Establishes the rules for curtailment or 
interruption of Non-Firm GRITS and 
the priority of Non-Firm GRITS in 
relation to other Transmission 
Services. 
37B.22 
GRITS Offer Cap 
Establishes the GRITS Offer Cap of 
$100/MWh. 
37B.23 
GRITS Operating Agreement 
Establishes the components of the 
GRITS Operating Agreement. 
Module C 
 
  
38.6 
Aggregators of Retail Customers 
Requires an ARC to attest that no part 
of a DRR, LMR, or EDR is being 
served by Non-Firm GRITS. 
39.2.2 
Demand Bid Rules in the Day-
Ahead Energy and Operating 
Reserve Markets 
Limits the amount of Price Sensitive 
Demand Bid from Large Load taking 
Non-Firm GRITS to the GRITS Offer 
Cap. 
40.2.15.s 
Real-Time Energy and Operating 
Reserve Market Process 
Establishes that Non-Firm GRITS is 
subject to Interruption when the Real-
Time Ex Ante LMP exceeds the 
GRITS Offer Cap. 
40.2.20 
Capacity Shortage Conditions in 
the Real-Time Energy and 
Operating Reserve Market 
Establishes Step Zero in the priority 
of Interruption for Capacity Shortage 
Conditions in the Real Time market. 
42.6 
Partial-Year FTR Allocation 
Process for New ARR Zones 
Includes Firm GRITS as an eligible 
service for nominations. 
43.2.4 
Nomination and Allocation of 
ARRs and MTPS ARRs 
Includes Firm GRITS as an eligible 
service for nominations. 
69A.1.1 
Forecasted Demand Identification 
Excludes Non-Firm GRITS from 
Coincident Peak Demand forecast. 
69A.1.2 
Daily Assignment of Coincident 
Peak Demand Obligations 
Excludes Demand from a Large Load 
taking Non-Firm GRITS from an 
LSE’s portion of such Demand. 
69A.3.1.G 
Determination of Deliverability 
Makes explicit deliverability of a ZG 
Resource to a ZG Associated Load 
requires Firm Transmission Service or 
Interim NITS Transmission Service. 
69A.3.3 
Load Modifying Resources 
Non-Firm GRITS cannot participate 
as a Load Modifying Resource 
Attachments

PDF page 15

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 15 
 
 
Attachment F-1 
Form of Service Agreement for 
Grid Responsive Integration 
Transmission Service 
Form of Service Agreement for 
GRITS and related exhibits including 
specification sheets. 
Attachment G-1 
Form of GRITS Operating 
Agreement for Grid Responsive 
Integration Transmission Service 
Form Operating Agreement for 
GRITS service. 
   
VI. 
STAKEHOLDER ENGAGEMENT 
 
MISO developed the GRITS proposal through successive discussions with the Large Load 
Working Group (“LLWG”).  At the August 12, 2026 LLWG meeting, MISO presented its Flexible 
Large-Load Interconnections and Transmission Service (“FLITS”) concept, which contemplated 
both interim and permanent non-firm service.  MISO requested written feedback by August 19, 
2026, with particular emphasis on resource adequacy.  Stakeholders addressed curtailment, 
capacity obligations, and the implications of offering permanent non-firm service.  The 
environmental sector recommended developing separate interim and permanent products given 
their different purposes and operating requirements.26 
 
At the September 9, 2026 LLWG meeting, MISO presented interim FLITS and a separate 
permanent Contract Demand service and requested written comments by September 16. 
Stakeholders addressed how the proposed services would differ in rates, curtailment priority, 
resource adequacy treatment, and ARR eligibility.  At the September 23, 2026  LLWG meeting, 
MISO focused its presentation on Interim NITS and confirmed during the discussion that it 
continued to develop the permanent service and would return with an update on October 8, 2026.  
The September 23, 2026 feedback request set an October 2, 2026 deadline for comments on the 
Interim NITS design and an October 16 deadline for comments on the anticipated Interim NITS 
Tariff redlines.27 
 
At the October 8, 2026 LLWG meeting, MISO presented the permanent service as GRITS 
and requested written feedback by October 16, 2026.  The proposal allowed customers to combine 
a firm service quantity with short-term, as-available non-firm reservations.  MISO also proposed 
excluding the non-firm portion from the Coincident Peak Demand forecast and requiring 
interruption under specified reliability and price conditions.  Stakeholders commented on the 
proposed price trigger, coordination and enforcement of curtailment, capacity forecasting and 
modeling, and the treatment of co-located resources.  They also asked how a customer could 
increase its firm service quantity after service began.  
 
26   MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service (FLITS) Proposal, LLWG-2026-
5 (Aug. 12, 2026) (feedback request and submitted comments, including Environmental Sector comments). 
(misoenergy.org, misoenergy.org). 
 
27  MISO, LLWG, Non-Firm Large Load, Item 6 (Sept. 9, 2026), and associated feedback request and comments, 
LLWG-2026-5. See also MISO, LLWG, Conditional Non-Firm Transmission Service, Item 7, slide 2 (Sept. 23, 
2026), and associated Interim NITS feedback request, LLWG-2026-5. (misoenergy.org, cdn.misoenergy.org, 
misoenergy.org).

PDF page 16

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 16 
 
 
 
At the October 29, 2026 LLWG meeting, MISO presented GRITS alongside Interim NITS 
and reviewed the differences in reservation terms, service priority, billing, and resource adequacy 
treatment.  After receiving stakeholder feedback on the October 8, 2026 proposal, MISO reported 
that it was evaluating whether to use a GRITS Offer Cap as a price-based interruption trigger and, 
if so, where to set it.  Stakeholders submitted additional written comments on November 4 
addressing, among other matters, non-firm transmission charges, the proposed price trigger, and 
resource adequacy treatment.28 
 
VII. 
DOCUMENTS SUBMITTED IN THIS FILING 
 
In addition to this Transmittal Letter, this submission includes the following materials, with 
the final tab and exhibit designations identified in the filing index: 
 
Tab A – Redline Tariff29 
 
Tab B – Clean Tariff 
 
Tab C – Testimony of Zhaoxia Xie 
 
VIII. 
EFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE 
   
MISO requests an effective date 120-days from the date of this filing (i.e., March 16, 2027), 
with implementation of GRITS to begin January 1, 2029.  Acceptance of the GRITS proposal by 
the requested effective date is necessary to facilitate the planned implementation timeline because 
such implementation requires significant modifications to MISO’s existing software systems and 
processes, coordinated service agreements, models, market registration, billing arrangements, 
operating controls, and communications. 
 
 
28  MISO, LLWG, Interim NITS and Grid Responsive Integration Transmission Service, Item 5, slides 2, 8, 20–24 
(Oct. 29, 2026). Antora Energy comments (Nov. 4, 2026, posted Nov. 9, 2026). (cdn.misoenergy.org, 
cdn.misoenergy.org, misoenergy.org, misoenergy.org). 
29  Language currently pending before the Commission in the following, unrelated dockets is highlighted in yellow: 
ER26-3552-000 and ER26-3650-000.  Also highlighted is pending language filed in MISO’s Large Load Omnibus 
filing being submitted contemporaneously.  MISO requests that the Commission treat such highlighted language 
as subject to the outcome of those pending proceedings.  If needed, MISO commits to file any revisions to this 
highlighted language as necessary to comply with any Commission orders in the proceeding. 
In addition, MISO has not included language that has future effective dates of 6/1/2027, 9/1/2027, 6/12/2028, 
6/1/2029, under Docket Nos. ER22-1640-007, ER22-1640-006, and ER22-1640-003, respectively. MISO has also 
removed language that has a future effective date of 9/1/2027 and is pending in Docket No. ER25-1886-000. If 
needed, MISO commits to file any revisions to comply with any Commission orders in these proceedings and 
MISO commits to make subsequent filings with the Commission to reflect the most up-to-date version of the 
then-current Tariff provisions prior to the effective dates of the language.

PDF page 17

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 17 
 
 
MISO also moves to extend the existing abeyance period under Rule 212 of the 
Commission’s Rules of Practice and Procedure.30  As the Abeyance Order explained, the 
Commission encouraged MISO, the Transmission Owners, and stakeholder to continue to 
collaborate in order to develop one or more FPA section 205 proposals to address the requirements 
of the Show Cause Order.31  The GRITS proposal is one output from this ongoing stakeholder 
process.  As stated, MISO cannot implement GRITS until January 1, 2029, subject to the 
Commission accepting a rate, which as explained above will be submitted in for Commission 
review in a future filing.  MISO, therefore, moves to extend the abeyance period until the 
Commission accepts the GRITS proposal and applicable rate for Firm and Non-Firm GRITS.  
MISO respectfully submits that this extension to the abeyance is necessary to avoid a lapse in the 
existing abeyance period while the GRITS rate is determined.  Moreover, granting the continued 
abeyance is reasonable, especially in light of the limited scope of request as compared to the 
significant proposals filed in response to the Show Cause Order. 
 
IX. 
COMMUNICATIONS 
MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of 
Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the 
designation of more than two persons for service on behalf of MISO in this proceeding and requests 
all communications related to this filing be directed to: 
Michael Kessler  
Managing Assistant General Counsel 
Midcontinent Independent System   
Operator, Inc. 
720 City Center Drive  
Carmel, Indiana 46032  
Telephone: (317) 753-9434 
mkessler@misoenergy.org 
 
 
James C. Holsclaw 
Lauren A. Stenger 
Calfee, Halter & Griswold LLP 
3900 Salesforce Tower 
111 Monument Circle 
Indianapolis, Indiana 46204 
Telephone: (317) 308-4266 
jholsclaw@calfee.com 
lastenger@calfee.com  
 
X. 
NOTICE AND SERVICE 
MISO has served a copy of this filing electronically, including attachments, upon all Tariff 
customers, MISO Members, Member representatives of Transmission Owners and non-
Transmission Owners, as well as all state commissions within the MISO Region and the 
Organization of MISO States.  The filing has been posted electronically on MISO’s website at 
https://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter. 
 
 
30  See 18 C.F.R.  § 385.212 (2026).   
31  Midcontinent Indep.  Sys.  Operator, Inc., 196 FERC P 61,133, at PP 8-9 (2026) (“Abeyance Order”).

PDF page 18

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 18 
 
 
XI. 
CONCLUSION 
For all of the foregoing reasons, MISO respectfully requests that the Commission accept 
this filing and grant waiver of any Commission regulations the Commission deems in order for the 
Commission to accept it as proposed. 
Respectfully submitted, 
 
/s/ Michael Kessler 
Michael Kessler  
Managing Assistant General Counsel 
Midcontinent Independent System   
Operator, Inc. 
720 City Center Drive  
Carmel, Indiana 46032  
Telephone: (317) 753-9434 
mkessler@misoenergy.org 
 
James C. Holsclaw 
Lauren A. Stenger 
Calfee, Halter & Griswold LLP 
3900 Salesforce Tower 
111 Monument Circle 
Indianapolis, Indiana 46204 
Telephone: (317) 308-4266 
jholsclaw@calfee.com   
lastenger@calfee.com 
 
Attorneys for the Midcontinent Independent 
System Operator, Inc. 
Attachments