Limited Protest of Bloom Energy Corporation
Bloom Energy files a limited protest of MISO's LARS filing. It supports LARS and a December 2, 2026 effective date but objects to the 200 MW minimum load size and asks FERC to align it with MISO's 50 MW Large Load definition.
Asks FERC to: Accept LARS effective December 2, 2026 and direct a 60-day compliance filing that either aligns eligibility with the 50 MW Large Load definition or supplies evidence for the 200 MW minimum.
Answers the order. Protests one eligibility element of MISO's LARS response to the E-8 show cause order, arguing the 200 MW floor departs from the order's 50 MW large load definition.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- Bloom supports LARS and its December 2 effective date, and protests only the 200 MW minimum.
Bloom protests one element only: the 200 MW minimum load size. PDF p. 1
- Bloom says MISO lowered the threshold from 250 MW to 200 MW without new analysis.
MISO presents no EPR results or other grid impact study for 200 MW, and none for loads below it. PDF p. 2
- The 200 MW floor departs from the 50 MW definition in the show cause order and in MISO's pending IRR filing.
The Show Cause Order identified a reasonable large load definition as a single-site commercial or industrial customer with peak load of 50 MW or greater. PDF p. 2
- Bloom argues paired loads below 200 MW are similarly situated and that the ten-pair cap already focuses each study cycle.
And the ten-pair cap, not a size threshold, already preserves the focus of each study cycle. PDF p. 3
- Bloom says the right screen is connection to the Transmission System, so LARS should cover loads of 50 MW or more.
LARS should therefore apply to loads of 50 MW or more that connect to the Transmission System. PDF p. 4
- If the minimum falls, Bloom asks FERC to conform the 200 MW generation-side minimum in Section 3.12.2.
it should direct a conforming change to Section 3.12.2, which separately requires at least 200 MW of Network Resource Interconnection Service at each Point of Interconnection. PDF p. 5
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation
What the document says
PDF p. 4
Bloom: the 200 MW floor has no impact data behind it; lower it to 50 MW.
LARS should therefore apply to loads of 50 MW or more that connect to the Transmission System. PDF p. 4Filed comments: Connecting load and generation
PDF p. 2
Bloom: the 200 MW floor has no impact data behind it; lower it to 50 MW.
MISO presents no EPR results or other grid impact study for 200 MW, and none for loads below it. PDF p. 2
PDF p. 5
Bloom: accept LARS by December 2, then order a 60-day compliance filing on the threshold.
Bloom does not ask the Commission to delay LARS. PDF p. 5Filed comments: Connecting load and generation
PDF p. 1
Bloom: accept LARS by December 2, then order a 60-day compliance filing on the threshold.
Bloom supports LARS and urges the Commission to accept it by MISO's requested December 2, 2026 effective date. PDF p. 1Filed comments: Connecting load and generation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- MISO defends a higher entry threshold Midcontinent Independent System Operator
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
LARS solves a real problem: today, load and generation studies run on different timelines, so each must wait on the other.Read this passage Filed comments: Connecting load and generation
I. Limited Protest
printed heading · Topic match: Connecting load and generation
MISO's other safeguards already screen out speculative and de minimis requests: the $250,000 non-refundable deposit, the milestone payment, full site control, and the bar on aggregating multiple loads.16 And the pairing agreement, the same LRZ requirement, and the 15-year commitment – not load size…Read this passage Filed comments: Connecting load and generation
II. Conclusion
printed heading
II.Read this passage
Conclusion
printed heading · Topic match: Connecting load and generation
Bloom respectfully requests that the Commission (1) accept LARS effective December 2, 2026; and (2) direct MISO, in a compliance filing within 60 days, either to (a) align LARS eligibility with MISO's Large Load definition, with a corresponding generation-side minimum, or (b) provide record…Read this passage Filed comments: Connecting load and generation
Certificate of Service
printed heading
Dated at Falls Church, VA this 23rd day of October, 2026. /s/ Joel D.Read this passage