Protest of the Solar Energy Industries Association and Advanced Energy United
The Solar Energy Industries Association and Advanced Energy United protest MISO's LARS filing as unduly discriminatory because only the Associated Transmission Customer, often a vertically integrated utility, can submit an application. They also object to generator stranding risk and LARS and DPP coordination.
Asks FERC to: Reject LARS with guidance to let any qualified participant apply directly; alternatively accept it and clarify that the application role must be administered without discrimination.
Answers the order. Protests MISO's LARS filing, offered as its answer to the E-8 show cause order on electrically proximate load, as discriminatory in who may apply and uncertain for generators and queued projects.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- Only the LARS Associated Transmission Customer, often a load-serving entity, can start an application.
The LARS Associated Transmission Customer is the only party that may initiate the LARS Application. PDF p. 3
- They say independent producers can join only if the utility competitor lets them, with no duty to submit.
Yes, independent power producers can participate in the LARS process PDF p. 5
- They ask FERC to reject LARS and direct a refiling that lets any qualified market participant apply directly to MISO.
reject the LARS proposal, on the grounds that the proposal is unduly discriminatory PDF p. 2
- A generator whose paired load leaves in the first fifteen years can lose its LLGIA and must re-enter the DPP.
the generator's LLGIA ultimately will be terminated and the generator must obtain new Interconnection Service through the Definitive Planning Process (DPP) to continue operating. PDF p. 7
- MISO offers only a transition period of up to one year, which they contrast with SPP's five-year HILLGA approach.
MISO proposes only a temporary transition period of up to one year PDF p. 8
- They say LARS studies leave out queued DPP projects without executed GIAs, so the two processes use different assumptions.
MISO specifically states that LARS studies will not include interconnection requests currently in the generator interconnection queue that have not executed GIAs. PDF p. 10
- In the alternative, they ask FERC to clarify that the Associated Transmission Customer must apply the same standards and timelines it uses for its own projects.
the Commission expects the LARS Associated Transmission Customer to apply the same submission standards and timelines it applies to its own similarly situated projects. PDF p. 13
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Cost allocation
What the document says
PDF p. 10
LARS and the queue use different assumptions, so both can claim the same headroom.
Under the proposal, LARS and DPP requests will be studied separately and using different assumptions. PDF p. 10Filed comments: Connecting load and generation
PDF p. 11
Queued generators say overallocation raises their upgrade costs and curtails their output.
The filing does not adequately explain how MISO will coordinate transmission-capability assumptions across parallel interconnection processes. PDF p. 11
PDF p. 1
Utility gatekeeping of LARS applications is undue discrimination against independent generators.
MISO proposes to effectively grant the Transmission Customer, which has an incentive to discriminate against competitive generation, the ability to discriminate against competitive generation. PDF p. 1
PDF p. 2
SEIA and United: reject LARS and let any qualified party file; or require nondiscriminatory handling.
reject the LARS proposal, on the grounds that the proposal is unduly discriminatory, and provide guidance to MISO to refile the proposal with a mechanism that would allow any qualified market participant PDF p. 2Filed comments: Connecting load and generation
PDF p. 13
SEIA and United: reject LARS and let any qualified party file; or require nondiscriminatory handling.
the Commission should clarify that once an applicant meets all applicable LARS eligibility, readiness, financial security, and application requirements, the Commission expects the LARS Associated Transmission Customer to apply the same submission standards PDF p. 13Filed comments: Connecting load and generation
PDF p. 8
If the paired load leaves, the generator faces a one-year bridge into a backlogged queue.
The proposed transition mechanism is woefully inadequate to address this stranded asset risk. PDF p. 8
Elsewhere in the record
Other parties on the same questions, in their own documents.
- MISO says independent generators can negotiate before applying Midcontinent Independent System Operator
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
ER27-25-000 PROTEST OF THE SOLAR ENERGY INDUSTRIES ASSOCIATION AND ADVANCED ENERGY UNITED Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure,1 the Solar Energy Industries Association (SEIA)2 and Advanced Energy United (United)3 submit…Read this passage Filed comments: Connecting load and generation
I. Protest
PDF bookmark
I.Read this passage
A. The LARS Proposal is unduly discriminatory because it allows LSEs to decide if their competitors may participate in the LARS process.
PDF bookmark · Topic match: Connecting load and generation
MISO’s filing is part of its efforts to comply with the Commission’s June 18, 2026, Show Cause Order.7 As relevant here, the Show Cause Order found that MISO’s tariff may be unjust and unreasonable because it does not contain provisions allowing an interconnection customer to seek interconnection…Read this passage Filed comments: Connecting load and generation
B. The LARS proposal is unjust and unreasonable because it conditions
printed heading · Topic match: Cost allocation
The LARS proposal is unjust and unreasonable because it conditions generators’ interconnection rights on specific large loads while risking double- counted transmission headroom, harm to earlier-queued projects, and improper cost shifts.Read this passage Filed comments: Cost allocation
i. LARS makes a generator’s rights depend on a specific large load, exposing viable projects to operational and financial uncertainty if that load departs.
PDF bookmark · Topic match: Connecting load and generation
Under the LARS Proposal, a generator’s eligibility for LARS Interconnection Service is tied to the continued existence of a specific associated large load for a substantial portion of the generator’s operating life.28 LARS provides off-ramps when an associated load departs.29 If the LARS Associated…Read this passage Filed comments: Connecting load and generation
ii. MISO has not demonstrated how transmission capability will be transparently managed across parallel LARS and DPP study processes to protect earlier-queued projects from double-counted headroom, cost shifts, and diminished available capability.
PDF bookmark · Topic match: Connecting load and generation
While MISO states that protecting the DPP process was an express consideration during development of the proposal,39 there is limited detail regarding how transmission capability assumptions will be coordinated between LARS and DPP studies or how potential conflicts will be identified and resolved…Read this passage Filed comments: Connecting load and generation
III. Alternative Recommendation
PDF bookmark
III.Read this passage
A. Alternatively, the Commission should clarify that the LARS application process must be administered on a nondiscriminatory basis.
PDF bookmark · Topic match: Connecting load and generation
Alternatively, the Commission should clarify that the LARS application process must be administered on a nondiscriminatory basis.Read this passage Filed comments: Connecting load and generation
IV. Conclusion
PDF bookmark
IV.Read this passage
CONCLUSION
printed heading · Topic match: Connecting load and generation
In a region such as MISO’s where many utilities are vertically integrated, that role grants these initiated by the LARS Associated Transmission Customer, the Interconnection Customer, Transmission Owner, and LARS Associated Transmission Customer must all complete the required information as part of…Read this passage Filed comments: Connecting load and generation