PJM reports on resource adequacy and large-load proposals
PJM files its 30-day informational report on resource adequacy for new large loads, describing the backstop procurement and insufficient-adequacy service stakeholder process, load flexibility work, market design reviews and interconnection reforms.
Asks FERC to: Accept the informational report as responsive to the show cause order's directive.
Answers the order. PJM's response to the E-7 30-day directive for an informational report on how it will ensure adequate generation for existing and new large loads.
E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- PJM points to a Critical Issue Fast Path on backstop procurement as its most direct effort on adequacy for new large loads.
this effort is most directly evidenced by the Critical Issue Fast Path (“CIFP”) for the development of a reliability backstop procurement (“RBP”) and a framework for service during periods of insufficient resource adequacy. PDF p. 1
- Stakeholders considered 24 proposals, 11 on service during insufficient adequacy and 13 on the backstop, with a filing expected around July 31, 2026.
In total, 24 proposals were submitted for consideration by PJM, the Independent Market Monitor for PJM, and various stakeholder groups. PDF p. 4
- Large loads that bring too little supply may be required to reduce withdrawals before other load is curtailed.
these large loads may be required to reduce their withdrawals from the transmission system before PJM needs to curtail other load. PDF p. 3
- A large load flexibility initiative would let loads connect before transmission upgrades, using load-reduction allocations and temporary options.
develop options for temporary flexibility to offer loads until transmission upgrades are constructed, such as fully, partially, or storage matched options. PDF p. 6
- PJM's Powering Reliability Through Market Design report sets out three paths, with a filing expected in 2027.
culminating in a filing with the Commission in 2027. PDF p. 8
- PJM reports 829 Cycle 1 applications totaling about 212,000 MW under review.
PJM has received a total of 829 applications under Cycle 1, totaling approximately 212,000 MWs of new capacity currently under review. PDF p. 11
Read topic-matched comments in EL26-67
Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation
What the document says
Cost and curtailment · PDF pp. 2–4
Backstop procurement and shortage service
PJM put the procurement rules and curtailment rules into the same stakeholder process. A large customer without enough new supply could have to cut demand before existing customers.
these large loads may be required to reduce their withdrawals from the transmission system PDF p. 3Filed comments: Reliability and curtailment
Load flexibility · PDF pp. 5–6
Connecting before transmission upgrades
PJM was considering contractual load reductions as a way to connect some customers sooner. The planning question was who could order a reduction and how that obligation would be divided.
would allow certain large load customers to connect to the grid prior to completion of necessary transmission upgrades PDF p. 5
Resource adequacy · PDF pp. 6–8
Three choices for the capacity market
PJM put three paths on the table: long-term procurement, different reliability targets within the region, or greater reliance on energy and reserve revenue. They were alternatives for discussion.
either through mandatory LSE hedging or through centralized long-term procurement PDF p. 7
Market incentives · PDF pp. 8–9
Reserve pricing
PJM wanted reserve prices to reflect the cost of ramping generators when demand or supply turns out differently than forecast.
recalibrate reserve products and update reserve demand curves to better account for ramping and uncertainty PDF p. 8
Interconnection · PDF pp. 9–11
Connecting generation sooner
PJM was studying whether generators in the third phase of its queue could operate before every study finished, subject to safety and reliability.
permitted to safely and reliably begin generating prior to their completion of certain Cycle studies PDF p. 10
Elsewhere in the record
Other parties on the same questions, in their own documents.
- When is an interruption a substitute for capacity? Commissioner David Rosner