MISO reports on resource adequacy and large-load proposals
MISO files the 30-day informational report the E-8 order required. It describes the state-led resource adequacy framework, near-term surpluses, ERAS and JTIQ results, and two new processes (ZGIA and a parallel load and generation study) for large-load speed to power.
Asks FERC to: Accept the report as compliance with the 30-day informational report requirement of the Show Cause Order, and grant any needed waiver.
Answers the order. MISO's filing under E-8 paragraph 122, the 30-day informational report on proposals to ensure resource adequacy for new large loads, with schedules of stakeholder initiatives that speed generation additions.
E-8 MISO: 30-day report on serving large loads with adequate generation (p. 7)
Key points
- MISO says its current framework suits traditional load growth but new large loads bring challenges that need new tools.
The unique nature of certain new large loads and the need to help ensure speed to power, however, brings new challenges that require MISO to continue to work with its states PDF p. 1
- MISO says LSEs should not build local transmission or generation for speculative loads.
It is not prudent for load serving entities to build local transmission, or generation, for speculative loads. PDF p. 2
- MISO plans a Zero Injection Generator Interconnection Agreement for generation serving load at the same substation.
facilitate faster interconnection of generation resources that serve only Load connected to the same substation and will not inject energy further onto the Transmission System. PDF p. 2
- MISO will develop a Large Load Parallel Study Process and file it under section 205.
intends to submit a Section 205 filing to the Commission codifying the Large Load Parallel Study Process in the Tariff PDF p. 3
- MISO says states are primarily responsible for resource adequacy.
States are primarily responsible for resource adequacy, which involves overseeing Load Serving Entities (“LSEs”) and ensuring LSEs plan for and secure enough power PDF p. 3
- The 2026 OMS-MISO Survey projects sufficient capacity for five years while LSE load growth runs 3.1% to 5.1% a year.
Compound Annual Growth Rate (“CAGR”) projected between 3.1% and 5.1% over five years. PDF p. 4
- ERAS has moved 40 projects and 19 GW through accelerated interconnection.
To date, 40 projects and 19 GWs of generation have completed the accelerated ERAS process PDF p. 7
- MISO says JTIQ upgrades unlock more than 28 GW of interconnection capability on the MISO-SPP seam.
unlock more than 28 GW of new interconnection capability along the MISO‑SPP seam PDF p. 9
Read topic-matched comments in EL26-70
Topics in the text: Reliability and curtailment · Connecting load and generation · Retail and wholesale authority
What the document says
State authority · PDF pp. 2–7
Who plans for the next five years?
MISO combines forecasts from load-serving entities with an annual survey of resource owners; state and retail regulators retain responsibility for determining required adequacy.
LSEs are the entities responsible for providing demand forecasts PDF p. 4
Interconnection · PDF pp. 7–9
Studying projects across grid boundaries
MISO reports that a delayed neighboring-system study need not stop a generator’s application from advancing.
allowing Interconnection Customers to move forward even where an affected system study is delayed PDF p. 9
Co-location · PDF pp. 9–14
Generation that serves only the adjacent load
The proposed zero-injection agreement would give paired generation and load a study path without granting delivery rights on the wider system. MISO later filed the agreement in ER26-3552.
will be co-located with load and will not inject energy further onto the Transmission System PDF p. 10
Elsewhere in the record
Other parties on the same questions, in their own documents.
- What MISO’s regional report leaves out Organization of MISO States
Source sections
Printed headings where available; page ranges otherwise. Open a heading to read the original passage.
- Opening text
- I. Executive Summary
- Executive Summary
- II. BACKGROUND
- BACKGROUND
- III. INFORMATIONAL FILING
- A. The MISO Region Is Resource Adequate.
- B. MISO’s Efforts to Support Resource Adequacy
- C. MISO’s Future Efforts to Bring Resources Online Faster
- IV. COMMUNICATIONS
- V. NOTICE AND SERVICE
- VI. CONCLUSION
- CONCLUSION
- ATTACHMENT A