← All deployments

Aurora pilot reactor

Oklo's first Aurora powerhouse at Idaho National Laboratory, under DOE's Reactor Pilot Program pathway.

Idaho National Laboratory · Company-reported

Lead company · Oklo →

Program · Reactor Pilot Program

Construction underwayHigh confidence
Deployment stage6 / 8Physical

Deployment trajectory

1Interest
2Preliminary
3Development
4Contractual
5Ready
6Physical
7Operational
8Replication

Latest milestone

Broke ground on the first Aurora powerhouse; DOE's Reactor Pilot Program authorization covers construction, and the separate NRC combined license remains under review.

2025-09 · Oklo groundbreaking release

Open primary source ↗

Next milestone

Complete construction, load fuel, and reach initial criticality; the NRC combined license is a separate track toward commercial operation.

Responsible
Oklo, DOE Idaho Operations, and NRC
Key blocker
Construction completion, fuel readiness, and the separate NRC combined license
GenerationGen IV
ScaleSMR
Reactor familySFR
RoleDemonstration power
Capacity75 MWe maximum (Aurora design)
Reporting basisCompany-reported