ER26-3650-000 · 2026-10-28 · Central Municipal Power Agency/ServicesMissouri Joint Municipal Electric Utility CommissionWPPI Energy ,Indiana Municipal Power Agency ,
Motion for Leave to Answer and Answer of Central Municipal Power Agency Services, et al. to Midcontinent Independent System Operator, Inc.’s 10/13/2026 Motion for Leave to Answer and Answer
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
Docket No. ER26-3650-000
MOTION FOR LEAVE TO ANSWER AND ANSWER
OF MIDWEST TDUS
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s
(“FERC” or “Commission”) Rules of Practice and Procedure,1 Midwest TDUs2
respectfully move for leave to answer and answer the October 13, 2026, Motion for
Leave to Answer and Answer filed by the Midcontinent Independent System Operator,
Inc. (“MISO”).3 MISO’s Answer responds to Midwest TDUs’ Comments,4 and protests
by numerous other intervenors, of MISO’s original filing5 to revise its Open Access
Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) to implement
Interconnection Reliability Requirements for certain large loads.
Midwest TDUs’ Answer below explains that MISO’s Answer does not resolve the
concerns identified in our original Comments. Specifically:
1 18 C.F.R. §§ 385.212, 385.213.
2 Midwest TDUs consist of Central Municipal Power Agency/Services (“CMPAS”), Indiana Municipal
Power Agency (“IMPA”), Missouri Joint Municipal Electric Utility Commission (“MJMEUC”), and WPPI
Energy (“WPPI”).
3 Motion for Leave to Answer and Answer of the Midcontinent Independent System Operator, Inc. (Oct.
13, 2026), eLibrary No. 20261013-5440 (“MISO Answer”).
4 Motion to Intervene and Comments of Central Municipal Power Agency/Services, Indiana Municipal
Power Agency, Missouri Joint Municipal Electric Utility Commission, and WPPI Energy (Sept. 18, 2026),
eLibrary No. 20260918-5272 (“Midwest TDUs Comments”).
5 MISO, Interconnection Reliability Requirements for Large Loads (Aug. 28, 2026), eLibrary No.
20260828-5278 (“MISO Filing”).
PDF page 2
- 2 -
• Although MISO’s Answer confirms MISO’s intent not to impose its
proposed Interconnection Reliability Requirements on distribution-
connected loads, it fails to show that this critical threshold issue is
unambiguously addressed in the proposed Tariff language.
• MISO’s Answer fails to provide additional clarity as to how it will
effectuate a Transmission Customer’s agreement with a Large Load that
assigns one or more compliance responsibilities to the Large Load.
Midwest TDUs appreciate MISO’s confirmation that Transmission
Customers may rely on such agreements to demonstrate compliance with
the Interconnection Reliability Requirements, but more clarity is needed to
ensure that they can do so in a manner that is efficient and not unduly
burdensome.
The Commission should therefore issue a deficiency letter directing MISO to
address these issues and require revisions to the proposed Tariff language reflecting the
requested clarifications.
I.
MOTION FOR LEAVE TO ANSWER
The Commission’s Rules of Practice and Procedure prohibit answers to answers
unless otherwise authorized by the Commission,6 but the Commission has authority to
waive this prohibition for good cause.7 The Commission has found good cause to waive
the general prohibition on answers to answers where, among other things, the answer
would assist the Commission in its decision-making process.8 Midwest TDUs’ Answer to
MISO’s Answer will aid the Commission’s understanding of the important issues
presented by MISO’s Interconnection Reliability Requirements proposal. Midwest TDUs
respectfully request that the Commission grant leave to submit the following Answer.
6 18 C.F.R. § 385.213(a)(2).
7 Id. § 385.101(e).
8 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, P 24 (2025) (accepting answers to
answers “because they have provided information that assisted us in our decision-making process”).
PDF page 3
- 3 -
II.
ANSWER
A.
Further clarity is needed to ensure that MISO’s proposed
Interconnection Reliability Requirements are limited to
Transmission System-connected Large Loads.
Midwest TDUs appreciate MISO’s apparent confirmation that it intends for the
proposed Interconnection Reliability Requirements to apply only “to Transmission
Customers taking Transmission Service on behalf of Large Loads connected to the MISO
Transmission System.”9 This straightforward statement of the applicability of these
requirements is consistent with testimony that its Answer cites: “This filing proposes
reliability requirements and a reliability-based framework applicable to Transmission
Customers taking Transmission Service on behalf of Large Load interconnected to the
MISO Transmission System.”10 The brief discussion of this critical threshold point in
MISO’s Answer, however, fails to resolve the potential for ambiguity in the proposed
Tariff language.
As noted in our Comments at 6-7, MISO defines a Large Load as one “located at
a single substation behind one or more Point(s) of Withdrawal from the Transmission
System,”11 with “Point(s) of Withdrawal” defined as “[t]he point(s) where a non-
transmission facility that is used to withdraw Energy from the Transmission System to
serve Load connects to the Transmission System.”12 MISO’s definition, unlike the one in
the Commission’s Show Cause Order, does not specify that a Large Load “interconnects
9 MISO Answer at 26 (emphasis added).
10 MISO Filing, Tab C, Prepared Direct Testimony of Beibei Li, Senior Manager of Strategic Assessment,
Testimony at 15(emphasis added), included in testimony pages referenced in MISO’s Answer at 27. See
also Midwest TDUs Comments at 5 (summarizing similar references in MISO’s original filing).
11 MISO Filing, Tab A, Redline Tariff § 1.L (proposed definition of Large Load).
12 Id. § 1.P (proposed definition of Point(s) of Withdrawal).
PDF page 4
- 4 -
to the transmission system.”13 MISO’s Answer does not address the specific sources of
confusion in its proposed Tariff language that Midwest TDUs identified in our
Comments, such as how broadly “behind” the Point of Withdrawal from the
Transmission System could extend without language specifying that a Large Load must
interconnect to the transmission system.14 Instead, MISO states that the references to the
Transmission System in its proposed Tariff language means that “the [Interconnection
Reliability Requirements] Proposal does not create a free-standing MISO reliability
regime for distribution-connected load that is not taking MISO Transmission Service.”15
Unfortunately, MISO’s explanation underscores the need for further specificity in
the proposed Tariff language. The relevant distinction for purposes of MISO’s Large
Load definition is not whether the Transmission Customer is “taking MISO Transmission
Service” on behalf of the load, since an Eligible Customer can take Transmission Service
on behalf of load interconnected to either the MISO Transmission System or a
distribution system.
Rather, MISO’s Tariff language should explicitly define Large Loads as those that
“interconnect[] to the transmission system,”16 which makes clear that the Interconnection
Reliability Requirements do not apply to distribution-connected loads.17 These
13 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, P 58 (2026) (“MISO Show Cause Order”).
14 See Midwest TDUs Comments at 6-7.
15 MISO Answer at 27 (emphasis added).
16 MISO Show Cause Order P 58.
17 The Computational Load registry criteria discussed in Midwest TDUs’ Comments at 9 n.22 (quoting the
proposed criteria which, among other things, require the load to be “connected at a voltage level greater
than or equal to 100 kV from one or more points of connection”) was just filed with this Commission.
Petition of the North American Electric Reliability Corporation for Approval of Revisions to the NERC
Rules of Procedure Regarding Computational Load and Request for Expedited Action, N. Am. Elec.
Reliability Corp., Docket No. RR27-1 (Oct. 21, 2026), eLibrary No. 20261021-5204.
PDF page 5
- 5 -
clarification is also consistent with the Commission’s Show Cause Order and MISO’s
apparent intent not to reach distribution-connected loads with its proposed
Interconnection Reliability Requirements.
B.
There remains uncertainty as to how Transmission Customers
can rely on their agreements with Large Loads to effectuate
compliance.
MISO reiterates that “[t]he proposed Tariff expressly accommodates contractual
arrangements between the Transmission Customer and the Large Load,”18 but its Answer
fails to provide more details as to how those contractual arrangements will be
accommodated in practice. Clarification of these implementation details are important to
ensure that Transmission Customers are not unduly burdened by provisions intended to
address reliability concerns caused by Large Loads. Midwest TDUs do not repeat all of
clarification issues raised in our earlier Comments that should be addressed,19 but we
highlight two specific shortcomings in MISO’s Answer.
First, although MISO’s Answer acknowledges that “an Agreement assigning
relevant performance and information duties to the Large Load may be part of a sufficient
compliance showing,”20 it appears to reject the idea that agreements between a Large
Load and the Transmission Customer can enable the Large Load to provide information
directly to MISO. MISO states that it “must be able to obtain, through the Transmission
Customer, all information and operational access necessary” and that agreements can
“establish[] the Transmission Customer’s access to the information needed for
18 MISO Answer at 28.
19 Midwest TDUs Comments at 9-15.
20 MISO Answer at 28 (emphasis added).
PDF page 6
- 6 -
compliance.”21 MISO does not explain why it could not accept relevant information
directly from the Large Load where a Large Load-Transmission Customer agreement
expressly assigns compliance responsibility to the Large Load.
To the extent a Large Load enters into an agreement with the Transmission
Customer to expressly take on identified responsibilities for complying with
Interconnection Reliability Requirements, MISO should not encumber that compliance
by insisting that the Transmission Customer act as a middleman. While MISO says it
“will continue working with Transmission Customers and Large Loads through
implementation to facilitate efficient compliance and provide education regarding the
new requirements,”22 the Commission should not permit MISO’s apparent insistence that
information be needlessly funneled through the Transmission Customer. Where a Large
Load agrees to take on responsibility for compliance with an Interconnection Reliability
Requirement, requiring the Transmission Customer to pass information from the Large
Load to MISO serves as a barrier to implementing agreements that facilitate efficient and
effective compliance.
Second, MISO’s Answer stops short of confirming that the list of potential
consequences in proposed section 37A is the exclusive list of consequences for
noncompliance with the proposed Interconnection Reliability Requirements.23 And while
MISO states that this list is “not an automatic penalty schedule,”24 MISO does not state
21 MISO Answer at 29 (emphasis added).
22 Id.
23 Id.
24 Id. (emphasis added)
PDF page 7
- 7 -
whether, and in what circumstances, it might seek to impose penalties under section 37A
despite none being explicitly identified in that provision. Nor does it clarify (either in its
Answer or with revised proposed Tariff language) the scope of the potentially broad
catchall for “other remediation action(s)” in the provision of section 37A. As explained in
Midwest TDUs’ Comments (at 13), it would be inappropriate to impose punitive
consequences such as financial penalties on the Transmission Customer when an
Interconnection Reliably Requirement is not met by the Large Load assigned compliance
responsibility under an agreement. In these circumstances, the Tariff language in section
37A should be clear that consequences of non-compliance should be tailored to address
and prevent the reliability risks posed by Large Loads.
Requiring additional clarity on these issues does not require MISO to establish
direct relationships with all Large Loads, nor does it alter that the Transmission Customer
is the entity taking Transmission Service of behalf of the Large Load. Rather, Midwest
TDUs’ Comments raised narrow questions about how MISO will effectuate agreements
between a Large Load and the Transmission Customer where the Large Load has agreed
to take on responsibilities for compliance with one or more of the Interconnection
Reliability Requirements. Given that the Large Loads are the source of the reliability
concerns driving the need for the Interconnection Reliability Requirements, it is
appropriate for MISO to engage with those Large Loads that enter into agreements with a
Transmission Customer to take on responsibility for compliance with those
Requirements. Doing so will result in more efficient and effective implementation of
these important reliability requirements, without requiring a direct contractual
PDF page 8
- 8 -
relationship between MISO and the Large Load or relieving the Transmission Customer
from its ultimate obligations under the MISO Tariff.
CONCLUSION
For the reasons discussed above, and in Midwest TDUs’ Comments, the
Commission should ensure that the issues above are adequately clarified by MISO and
order further Tariff revisions to the extent that MISO’s proposed language is not clear on
these issues.
Respectfully submitted,
/s/ Cynthia S. Bogorad
Cynthia S. Bogorad
Jeffrey M. Bayne
Attorneys for Midwest TDUs
Law Offices of:
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
(202) 879-4000
October 28, 2026
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing document to be served
upon each person designated on the official service list compiled by the Secretary in this
proceeding.
Dated on this 28th day of October, 2026.
/s/ Jeffrey M. Bayne
Jeffrey M. Bayne
Law Offices of:
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
(202) 879-4000