EL26-67-001 · 2026-09-21 · FERC

Order dismissing requests for rehearing and clarification of the June 18, 2026 PJM show-cause order

Read topic-matched comments in EL26-67

Topics in the text: Filing procedure · Registry access · Cost allocation

What the document says

PDF p. 11

FERC dismisses the rehearing requests because a show-cause order is not a final order.

We therefore dismiss the requests for rehearing, which concern a Commission action that is not final and that will be succeeded by further Commission action. PDF p. 11

PDF p. 11

FERC will not clarify the show-cause orders while the cases sit in abeyance.

We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance PDF p. 11

PDF p. 5

Eolian sought permanent load-limited interconnection for front-of-meter generation in five of six proceedings.

Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service PDF p. 5
Filed comments: Connecting load and generation

PDF p. 8

Exelon and FirstEnergy argued FERC never showed PJM's existing network service rate is unjust.

Exelon/FirstEnergy argue that the Commission failed to meet its FPA section 206 burden to show that PJM’s existing rate is unjust and unreasonable PDF p. 8

PDF p. 6

PJM's owners want service-specific criteria for large loads beyond the 50 MW definition.

Indicated PJM Transmission Owners contend that it may not be appropriate to offer identical services to all large load customers. PDF p. 6

PDF p. 10

Constellation told FERC to reject any PJM owner definition that disqualifies large loads or slows interconnection.

Constellation further argues that the Commission should clarify that: (1) any eligibility requirements PJM and the Transmission Owners propose in their initial filings must not be so prescriptive as to improperly disqualify large loads PDF p. 10

PDF p. 7

Consumer advocates asked FERC to make owners credit cost-recovery payments to other customers immediately.

Joint Consumer Advocates also request that the Commission clarify that transmission owners must immediately credit revenue received under cost recovery agreements to the other transmission customers in the relevant zone. PDF p. 7

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Virginia Electric and Power Company Wheeling Power Company ORDER DISMISSING REQUESTS FOR REHEARING AND CLARIFICATION (Issued September 21, 2026) On June 18, 2026, the Commission issued an order under section 206 of the Federal Power Act (FPA)1 initiating a show cause proceeding directing PJM…
Read this passage

I. Show Cause Order

PDF bookmark · Topic match: Cost allocation

P 58. 10 The Commission preliminarily found that the PJM Tariff lacks adequate mechanisms to mitigate the risks of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service.
Read this passage Filed comments: Cost allocation

II. Clarification and Rehearing Requests and Answer

PDF bookmark · Topic match: Filing procedure

Clarification and Rehearing Requests and Answer
Read this passage

A. Eolian Request for Clarification or, in the Alternative, Rehearing

PDF bookmark · Topic match: Filing procedure

Eolian Request for Clarification or, in the Alternative, Rehearing Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service where it is equally capable of enabling the large…
Read this passage Filed comments: Connecting load and generation

B. Indicated PJM Transmission Owners Request for Clarification, or in the Alternative, Rehearing

PDF bookmark · Topic match: Filing procedure

Indicated PJM Transmission Owners contend that, as PJM and the Transmission Owners have explained in the PJM co-located load proceeding, there are significant problems with adopting such definitions based on facilities on the customer-side of the point of interconnection, including potentially…
Read this passage Filed comments: Connecting load and generation

C. Joint Consumer Advocates Request for Clarification and Rehearing

PDF bookmark · Topic match: Registry access

Joint Consumer Advocates Request for Clarification and Rehearing Joint Consumer Advocates request that the Commission clarify the standard that the Commission will apply to assess cost recovery agreements.23 Joint Consumer Advocates argue that to be just and reasonable, a cost recovery agreement…
Read this passage Filed comments: Cost allocation

D. PA OCA Request for Clarification or, in the Alternative, Rehearing

PDF bookmark · Topic match: Cost allocation

PA OCA Request for Clarification or, in the Alternative, Rehearing PA OCA requests that the Commission clarify that: (1) the pro forma cost recovery agreements are partial and nonexclusive solutions to the wholesale transmission cost allocation problem;30 (2) existing regional cost allocation…
Read this passage Filed comments: Cost allocation

E. Exelon/FirstEnergy Request for Rehearing

PDF bookmark · Topic match: Cost allocation

Exelon/FirstEnergy Request for Rehearing Exelon/FirstEnergy argue that the Commission failed to meet its FPA section 206 burden to show that PJM’s existing rate is unjust and unreasonable because: (1) there is no evidence in the record that flexible large loads or any other large loads are unable…
Read this passage Filed comments: Cost allocation

F. Constellation Answer

PDF bookmark · Topic match: Credit and exit

ER26-1088-000 and ER26-1479-000.48 Constellation further argues that the Commission should clarify that: (1) any eligibility requirements PJM and the Transmission Owners propose in their initial filings must not be so prescriptive as to improperly disqualify large loads, foreclosing any benefits…
Read this passage

III. Discussion

PDF bookmark

III.
Read this passage

Discussion

printed heading

Discussion
Read this passage

A. Procedural Matters

PDF bookmark

Procedural Matters We accept Constellation’s answer because it is a permissible answer to a request for clarification.50
Read this passage

B. Substantive Matters

PDF bookmark · Topic match: Filing procedure

Substantive Matters Rule 713(b) of the Commission’s Rules of Practice and Procedure permits requests for rehearing “of any final decision or other final order in a proceeding.”51 A final order imposes an obligation, denies a right, or fixes some legal relationship as a consummation of the…
Read this passage