ER27-25-000 · 2026-10-23 · ACP and SREA

Protest and Request for Clarification of the American Clean Power Association and Southern Renewable Energy Association

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

What the document says

PDF p. 21

LARS and the queue use different assumptions, so both can claim the same headroom.

LARS projects will therefore be studied as if the only other generation on the system is generation that already holds a GIA. PDF p. 21
Filed comments: Connecting load and generation

PDF p. 21

Queued generators say overallocation raises their upgrade costs and curtails their output.

resulting in more constraints and higher Network Upgrade costs for DPP projects when they are finally studied against a system that LARS projects have already used. PDF p. 21
Filed comments: Cost allocation

PDF p. 6

Utility gatekeeping of LARS applications is undue discrimination against independent generators.

LARS is unduly discriminatory because it makes the LSE the gatekeeper of a Commission-jurisdictional generator interconnection process PDF p. 6
Filed comments: Connecting load and generation

PDF p. 2

LARS is a permanent, uncapped fast lane untethered to any identified resource adequacy need.

It is permanent and uncapped. It is untethered to any identified resource adequacy need. PDF p. 2
Filed comments: Reliability and curtailment

PDF p. 27

Unlike ERAS, LARS has no cap, sunset, independent-producer carve-out, or regulator check.

LARS contains no scoring criteria, no carve-outs, no regulatory verification, no cap, and no sunset. PDF p. 27
Filed comments: Connecting load and generation

PDF p. 14

Same-LRZ pairing is not the two-substation test the Show Cause Order described.

LARS does the opposite: it grants permanent NRIS through a parallel process PDF p. 14
Filed comments: Connecting load and generation

PDF p. 24

Clean energy groups say LARS adds a fifth path onto the grid and breaks planning.

MISO has now twice prioritized separate, one-off expedited processes that not all market participants can feasibly access on a comparable, not unduly discriminatory basis PDF p. 24

PDF p. 29

ACP and SREA: MISO has not met the independent entity variation standard.

MISO cannot satisfy the independent entity variation standard, and LARS does not accomplish the purposes of Order No. 2003 PDF p. 29
Filed comments: Connecting load and generation

PDF p. 30

Protesters ask FERC to reject LARS outright; Clean Energy Advocates offer a deficiency letter instead.

the Clean Energy Trades respectfully request that the Commission reject MISO's LARS proposal. PDF p. 30
Filed comments: Connecting load and generation

PDF p. 30

If FERC accepts LARS, ACP wants the same-LRZ test applied at the point of interconnection.

the relevant location is the applicable POI to the MISO Transmission System rather than the physical location of the Generating Facility PDF p. 30

Responses and related views

MISO says independent generators can negotiate before applying

Midcontinent Independent System Operator · Direct response

MISO said the transmission customer submits an application for an already matched pair. It argued that an independent generator remains free to bring a proposal to that customer before the application, and that the eligibility rules are nondiscretionary.

PDF pp. 20–22

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER27-25-000 (Oct. 7, 2026). 2 members include independent power producers (“IPPs”) that develop generation to serve large loads and that would be directly affected by both the access rules LARS establishes and the effect of LARS on the transmission capacity and Network Upgrade costs available to…
Read this passage Filed comments: Connecting load and generation

I. BACKGROUND

printed heading

I.
Read this passage

BACKGROUND

printed heading

BACKGROUND
Read this passage

A. MISO’s Initial and Revised ERAS Proposals

printed heading · Topic match: Reliability and curtailment

The accepted ERAS process is capped at 68 interconnection requests, with ten reserved for IPPs that have agreements with entities other than LSEs and eight reserved for requests serving retail- choice load; it requires verification by a Relevant Electric Retail Regulatory Authority (“RERRA”) of a…
Read this passage Filed comments: Reliability and curtailment

B. The Show Cause Order

printed heading · Topic match: Connecting load and generation

P 112. 5 obtains Energy Resource Interconnection Service (ERIS) or Network Resource Interconnection Service (NRIS).”15 Separately, the Commission directed MISO to file an informational report on proposals under consideration to address resource adequacy for new large loads.16
Read this passage Filed comments: Connecting load and generation

C. The LARS Proposal

printed heading · Topic match: Connecting load and generation

The LARS Proposal MISO proposes LARS as a new, permanent study process under which a large load of at least 200 megawatts (“MW”) and one or more new Generating Facilities are studied in parallel, with the generator receiving a Large Load Generator Interconnection Agreement (“LLGIA”) for NRIS in…
Read this passage Filed comments: Connecting load and generation

II. PROTEST

printed heading · Topic match: Connecting load and generation

PROTEST Because MISO filed LARS under FPA section 205, MISO bears the burden of demonstrating that its proposal is just and reasonable and not unduly discriminatory or preferential.23 MISO has not carried that burden.
Read this passage Filed comments: Connecting load and generation

A. LARS Would Unduly Discriminate Against Independent Power Producers and

printed heading · Topic match: Connecting load and generation

While it is reasonable for LSEs to initiate and oversee LARS requests on the load side, given state jurisdiction over retail service and LSEs’ obligations to serve load, that logic does not 36 See Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,682; Order No. 2003, 104 FERC ¶ 61,103 at P 827. 37…
Read this passage Filed comments: Connecting load and generation

B. LARS Is Not Just and Reasonable.

printed heading · Topic match: Connecting load and generation

LARS studies “will not include Interconnection Requests currently in the generator interconnection queue that do not have an executed GIA.”84 LARS projects will therefore be studied as if the only other generation on the system is generation that already holds a GIA.
Read this passage Filed comments: Connecting load and generation

C. The Commission’s Orders on MISO’s ERAS Proposals Confirm That LARS Is

printed heading · Topic match: Connecting load and generation

The Commission found that the initial, rejected MISO ERAS proposal did “not sufficiently describe how the ERAS process is sufficiently targeted to study only interconnection requests needed to meet the anticipated shortfall in generating capacity,” and that it was “difficult to determine whether…
Read this passage Filed comments: Connecting load and generation

D. MISO Has Not Demonstrated That LARS Satisfies the Independent Entity

printed heading · Topic match: Connecting load and generation

Operator, Inc., 185 FERC ¶ 61,084, at P 11 (2023)); see also ERAS Acceptance Order, 192 FERC ¶ 61,064 at P 259 (applying standard to ERAS). 114 See pro forma LGIP § 3.1. 115 Tab A, Attachment X, §§ 3.12.1, 3.12.2. 29 the basis of queue position and, following Order No. 2023, in clusters on a…
Read this passage Filed comments: Connecting load and generation

III. REQUEST FOR CLARIFICATION

printed heading · Topic match: Connecting load and generation

Proposed Attachment X, Section 3.12.2 appears to apply the same-LRZ requirement based on the Generating Facility’s POI for an individual LARS Interconnection Customer, providing that “[t]he Point of Interconnection specified in a LARS Application must be located in the same Local Resource Zone as…
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading

IV.
Read this passage

CONCLUSION

printed heading · Topic match: Connecting load and generation

CONCLUSION For the reasons stated above, the Clean Energy Trades respectfully request that the Commission reject MISO’s LARS proposal.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated this 23rd day of October, 2026. /s/ Brett White Brett White Vice President, Markets & Transmission American Clean Power Association 1299 Pennsylvania Ave.