ER27-526-000 · 2026-11-16 · Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners
MISO and its transmission owners file large-load review, cost recovery and transmission service revisions under section 205
Back to sections and commentaryPDF page 1
Midcontinent Independent
System Operator, Inc.
317.249-5400
www.misoenergy.org
720 City Center Drive
Carmel, Indiana 46032
2985 Ames Crossing Road
Eagan, Minnesota 55121
1700 Centerview Drive
Little Rock, AR 72211
Michael Kessler
Managing Assistant General Counsel
Direct Dial: 317-753-9434
Email: mkessler@misoenergy.org
November 16, 2026
VIA ELECTRONIC FILING
The Honorable Debbie-Anne Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
Re:
Midcontinent Independent System Operator, Inc.’s
Large Load Review, Cost Recovery and Transmission Services Filing
Docket No. ER27-___-000
Dear Secretary Reese:
The Midcontinent Independent System Operator, Inc. (“MISO”), and the MISO
Transmission Owners1 through this filing,2 submit proposed revisions to its Open Access
Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”),3 concerning the
integration of Large Loads.4 This omnibus filing describes the proposals MISO has already
1
The MISO Transmission Owners for this filing consist of: AEP Indiana Michigan Transmission Company;
Ameren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois
Company d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; Arkansas Electric Cooperative
Corporation; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens Electric
Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland
Power Cooperative; Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric
Cooperative, Inc.; Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New
Orleans, LLC; Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural
Electric Cooperative, Inc.; Indiana Municipal Power Agency; International Transmission Company d/b/a ITC
Transmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric Transmission Company, LLC;
MidAmerican Energy Company; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company LLC;
Prairie Power, Inc.; Republic Transmission, LLC; Southern Illinois Power Cooperative; Southern Indiana Gas &
Electric Company (d/b/a CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency;
Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc.
2
This filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Part 35 of
the regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. § 35.1, et
seq.
3
Unless otherwise indicated by the text or context of this transmittal letter, all terms used herein have the definitions
set forth in Module A of the Tariff.
4
The MISO Transmission Owners join this filing for the purpose of exercising their filing rights and supporting
the filing of the Large Load Cost Recovery Agreement and the Large Load Impacted Transmission Owner Cost
Recovery Agreement. Consistent with the MISO Transmission Owners Agreement, a majority of the MISO
Transmission Owners voted in favor of filing the Large Load Cost Recovery Agreement and the Large Load
PDF page 2
The Honorable Debbie-Anne Reese
November 16, 2026
Page 2
submitted in response to the Federal Energy Regulatory Commission’s (“Commission”) June 18,
2026, Show Cause Order5 and presents additional proposals in response to that order that have
been developed as MISO obtained the information and completed the design work necessary to
bring those components forward.6
MISO’s response has proceeded through a series of related filings addressing different
aspects of Large Load integration.7 The Zero Injection Generator Interconnection Agreement
(“ZGIA”), Interconnection Reliability Requirements for Large Loads (“IRR”), and Large Load
Addition Resource Study (“LARS”) proposals addressed components that were ready for
Commission review while work continued on the application, transmission service, and financial
provisions needed to address the remaining issues. This filing explains how those proposals fit
together with the further revisions described below.8
The additional revisions addressed here9 establish the Large Load Project Review
(“LLPR”) process and provide transmission service options reflecting a Large Load’s intended use
of the Transmission System, including a Firm Service Step Up (“FSSU”) process to evaluate the
availability of Network Integration Transmission Service (“NITS”), and Interim Network
Integration Transmission Service (“Interim NITS”). In addition, and as part of the LLPR process,
MISO and its Transmission Owners propose Tariff revisions and two pro forma cost recovery
agreements (the Large Load Cost Recovery Agreement and Large Load Impacted Transmission
Owner Cost Recovery Agreement), which are designed to mitigate the risk of cost shifting among
Impacted Transmission Owner Cost Recovery Agreement. See Agreement of Transmission Facilities Owners To
Organize The Midcontinent Independent System Operator, Inc., A Delaware Non-Stock Corporation, Rate
Schedule FERC No. 1, Appendix K § II.
5
Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,123 (2026) (“Show Cause Order”) (identifying the issues
concerning large and co-located loads that are the subject of the section 206 proceeding).
6
16 U.S.C. § 824d; 18 C.F.R. §§ 35.3, 35.13 (2026).
7
As proposed in MISO’s IRR filing, a Large Load is defined as “Load with Demand of 50 MW or more associated
with any facility or aggregation of facilities located at a single substation behind one or more Point(s) of
Withdrawal from the Transmission System that is owned, operated, or controlled by: (a) a single entity, or (b) a
group of entities that will coordinate with respect to the profile of the Load. Large Load does not include Load
used exclusively for charging an Electric Storage Resource.”
8
MISO, Transmittal Letter, Zero Injection Generator Interconnection Agreement, Docket No. ER26-3552-000, at
1–2, 5–7 (Aug. 18, 2026) (“ZGIA Transmittal”) (reserving transmission service and electrically proximate load
issues for later proposals); MISO, Transmittal Letter, Interconnection Reliability Requirements for Large Loads,
Docket No. ER26-3650-000, at 1, 4 (Aug. 28, 2026) (“IRR Transmittal”) (identifying additional study, service,
and cost protection work); MISO, Transmittal Letter, Large Load Addition Resource Study, Docket No. ER27-
25-000, at 14–15, 20–21 (Oct. 2, 2026) (“LARS Transmittal”) (anticipating further transmission service and cost
protection provisions).
9
This transmittal letter frequently quotes proposed Tariff revisions to facilitate its explanation. In the event of a
conflict between the Tariff language as discussed in this letter and that reflected in the attached Tariff sheets,
MISO intends that the language in the attached Tariff sheets control.
PDF page 3
The Honorable Debbie-Anne Reese
November 16, 2026
Page 3
Transmission Customers resulting from a Transmission Customer’s taking of Transmission
Service on behalf of a Large Load.10
MISO requests that the Commission accept the proposed revisions effective 90 days from
the date of this filing (i.e., February 14, 2027). MISO recognizes this filing includes significant
Tariff revisions and introduces new processes and cost recovery mechanisms that impact the
broader stakeholder community. In response to OMS and other stakeholder requests for MISO to
support an extended comment period, MISO proposes a 30-day comment period to allow
stakeholders sufficient time to evaluate and comment on the proposals being presented in this
filing. This extended comment period reasonably balances the need for additional time for
stakeholder review while maintaining the urgency presented by the Show Cause Order and works
well within MISO’s requested 90-day effective date request.
I.
EXECUTIVE SUMMARY
MISO to date has been able to successfully manage the integration of large loads leveraging
existing MISO tools and quickly recognized the need for additional frameworks and processes to
support reliable, efficient, and cost-effective integration given projected trends for f faster and
dramatic demand growth across the region. To this end, MISO, its Transmission Owners, state
regulatory authorities, and broad stakeholder community have been working collaboratively to
support the reliable, cost-effective, and efficient integration of large loads. Over the past two years
MISO has been developing new processes and tools to provide additional transparency, efficient
reliability standardization, integrated solutions for generation and new transmission service
offerings with stakeholders to meet the challenge. The MISO Large Load Working Group has
been an effective clearing house for such efforts and is providing a constructive, collaborative
forum to develop these solutions. This group met over thirteen times in the last eight months with
an average of 400 people and a peak of 1000 people participating in each session. This process
included over 100 MISO presentations to stakeholders and over 400 feedback responses from
stakeholders.
MISO recognizes the need for balanced solutions to support the diverse interests of
stakeholders and state policies across the MISO region. While these differing perspectives can
make unanimity- difficult to achieve, they contribute to a robust stakeholder process and better-
informed outcomes that ultimately drive the enormous value that MISO membership brings to
customers in terms of reliability, cost-effectiveness and policy enablement.
The Commission’s Show Cause Order provided important support for MISO’s ongoing
efforts to develop solutions for responsible and reliable integration of large loads. By identifying
specific priorities and encouraging incremental filings as solutions matured, the Commission
established a framework that enabled stakeholders and MISO to advance improvements without
waiting for a single comprehensive package.
10 Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and
Attachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery
Agreement).
PDF page 4
The Honorable Debbie-Anne Reese
November 16, 2026
Page 4
In response, MISO has already filed several proposals responsive to the Show Cause Order
that are currently pending before the Commission, including Zero Injection-GIA, Large Load
Interconnection Reliability Requirements, and the Load Additions Resource Study. Collectively
these filings represent meaningful progress toward more timely, transparent, reliable, and cost-
effective large load integration, which appropriately mitigates cost shifts to other Transmission
Customers.
The additional package of solutions in this filing and the companion filing11 complement
MISO’s pending Large Load filings and directly address the remaining concerns identified in the
Show Cause Order. MISO’s filings, in the aggregate, reflect its compliance with the timelines and
scope of the Show Cause Order. At the same time, MISO recognizes that Large Load integration
will continue to evolve. These filings represent an important milestone, not an endpoint. MISO
remains committed to further enhancing its planning, operational, and market frameworks as
experience is gained and system needs grow. The Large Load Working Group will continue to
serve as the primary stakeholder forum for evaluating, developing and refining additional solutions
to support ongoing integration of Large Loads across the MISO region.
The filings before the Commission are the product of an extremely robust, albeit expedited,
stakeholder process conducted within the timelines established by the Show Cause Order. MISO
advanced solutions that incorporated substantial stakeholder feedback while remaining consistent
with MISO’s filing rights and jurisdictional responsibilities. MISO worked closely with its
Transmission Owners to develop this joint filing and appropriately recognize their respective roles,
rights, and responsibilities. MISO also engaged the Organization of MISO states through regular
discussions throughout the development of this package of filings.
While full alignment was not achieved on every aspect of the proposals, stakeholder and
state regulator input materially informed the resulting framework. MISO is confident that the
collective set of filings before the Commission provides state regulators with additional
transparency, information and tools to help fulfill their responsibilities to retail electricity
customers, consistent with the objectives outlined in the Show Cause Order. The solutions also
preserve flexibility for states to advance their individual policy objectives, including the use of
detailed information and analyses provided through MISO’s planning and operational processes.
The proposals included in the filing provide a robust foundation for integrating Large
Loads in a manner that supports reliability, protects Transmission Customers from cost shifts
related to new Large Loads, and provides additional transmission service options consistent with
the Commission’s objectives for co-located loads, behind the meter generation arrangements and
flexible Large Loads. Specifically, this filing addresses the following elements identified in the
Show Cause Order:
11 MISO is contemporaneously submitting its Grid Responsive Integration Transmission Services (“GRITS”)
proposal as a separate FPA Section 205 filing. The GRITS filing addresses the Show Cause Order requirement
that MISO evaluate the need for both firm and non-firm contract demand transmission service.
PDF page 5
The Honorable Debbie-Anne Reese
November 16, 2026
Page 5
• Large Load Project Review (LLPR) – The LLPR establishes a comprehensive application
and evaluation process to assess the grid impacts associated with Transmission Service
needed to serve proposed Large Loads, including required Network Upgrades and
associated costs. The LLPR also includes deposits, project milestones, and other
safeguards designed to discourage speculative Large Load requests.
• Large Load Transparency Dashboard – The results of the LLPR periodically will be
published to provide transparency into the location and estimated costs associated with
Large Load facilities in the MISO region, while protecting confidential information.
• Cost Shifting Risk Among Transmission Customers – MISO and the MISO Transmission
Owners have developed new Tariff language and pro forma cost recovery agreements
designed to ensure that the costs incurred to provide Transmission Service to Large Load
Transmission Customers, including the costs of Large Load Upgrades (defined herein), are
born by such customers and thereby avoid unfair cost shifts among Transmission
Customers. The agreements leave retail regulatory authorities able to further disaggregate
costs as warranted.
• Additional Transmission Services – The new Transmission Services available to Large
Loads include Firm Service Step Up and Interim Non-Firm NITS service. These offerings
build off existing NITS service and support the timely integration of Large Loads by
aligning Transmission Service with a Transmission Customer’s projected buildout and
operational needs, while providing flexibility in how Transmission Service is obtained
during different stages of development.
MISO appreciates the guidance provided by the Commission in the Show Cause Order and
believes this filing, together with the companion GRITS filing, and MISO’s other pending Large
Load filings fully addresses the concerns identified by the Commission. Taken together, these
proposals represent a significant advancement in framework supporting Large Load integration,
building on processes and tools that MISO has already implemented.
At the same time, MISO recognizes that the rapid growth of Large Loads will continue to
present new challenges and opportunities. As a result, these filings should be viewed as an
important milestone rather than an endpoint. MISO remains committed to working collaboratively
with stakeholders, Transmission Owners, states and the Commission to evaluate and develop
additional tools, processes, and solutions to support the reliable, efficient, transparent and cost-
effective integration and operation of Large Loads in the MISO region.
II.
BACKGROUND
This omnibus filing brings together the history and substance of MISO’s response to the
Commission’s Show Cause Order. MISO has pursued that response through a series of related
filings, submitting individual proposals as the necessary information, stakeholder consideration,
and proposed Tariff provisions became sufficiently developed. The earlier submissions addressed
components that were ready to proceed while work continued on other elements of the response.
This filing explains that progression, describes the relationship among the proposals already
PDF page 6
The Honorable Debbie-Anne Reese
November 16, 2026
Page 6
submitted, and presents the additional provisions that have since been developed. The background
below traces how that coordinated effort led to the present submission.
A. The changing nature of load growth in the MISO region.
The MISO region is experiencing a change in the scale, concentration, and pace of new
electricity demand. Large Load additions, including data centers and advanced manufacturing
facilities, can introduce substantial demand at a single location and seek service on schedules that
are shorter than those traditionally required to develop supporting generation and transmission
infrastructure. These developments require MISO, the Transmission Owners, and the entities
serving those Loads to coordinate planning, investment, and operational requirements early in the
development process to address the unique needs associated with such Large Load additions to the
grid. As MISO explained in its July 20, 2026, Informational Report, conventional forecasting
methods were developed for more gradual and geographically dispersed growth; Large Load
projects present additional uncertainty concerning location, timing, and the demand that ultimately
materializes.12
The resulting challenge extends beyond identifying a physical point of connection. MISO
must assess the transmission facilities needed to serve new demand, understand how the Load will
behave during normal operations and system disturbances, and coordinate the addition of resources
needed to support resource adequacy. At the same time, the uncertainty surrounding Large Load
development makes it necessary to distinguish committed projects from speculative requests and
to address the risk that investments made to serve a particular load may remain unrecovered if that
Load is delayed, reduced, or does not materialize. MISO’s Large Load initiatives were developed
to address these related planning, reliability, and cost recovery concerns.13
MISO has also recognized that certain Large Loads may be willing and able to limit their
withdrawals from the Transmission System. That flexibility can support service before all
facilities needed for full firm service have been completed, or an ongoing arrangement under which
only a portion of the Load receives firm service. Accommodating those different needs requires
clear service rights, enforceable operating limits, and appropriate treatment of the customer’s
planning and financial obligations. The development of additional Transmission Service options
therefore became a component of MISO’s broader Large Load work.
B. MISO’s existing processes and the development of a dedicated stakeholder forum.
MISO’s efforts to address these challenges began before the Commission issued its Show
Cause Order. MISO had improved the Expedited Project Review (“EPR”) process within the
12 MISO, Informational Report, Docket No. EL26-70-000, at 1-2 (July 20, 2026) (“Informational Report”); MISO,
Transmittal Letter, Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650-000, at 2-
3 (Aug. 28, 2026) (“IRR Transmittal”).
13 Informational Report at 1-3; Motion of MISO to Hold Proceeding in Abeyance and Request for Shortened
Comment Period and Expedited Treatment, Docket No. EL26-70-000, at 2-5, 8-9 (Aug. 3, 2026) (“Abeyance
Motion”).
PDF page 7
The Honorable Debbie-Anne Reese
November 16, 2026
Page 7
MISO Transmission Expansion Plan (“MTEP”) to facilitate timely study and approval of
transmission upgrades needed for large load additions.14 On the generation side, MISO developed
the temporary Expedited Resource Addition Study (“ERAS”) process to accelerate the
interconnection of resources addressing identified near-term resource adequacy and reliability
needs.15 These initiatives provided a foundation for additional tools tailored to the pace and
characteristics of large load development.16 Those expedited processes addressed important near-
term needs, but MISO recognized that additional provisions were necessary to address the broader
relationship among load additions, generation development, transmission service, and system
operations.
MISO also began consolidating stakeholder consideration of large load issues. Following
a January 2026 Large Load Additions Workshop, MISO’s Steering Committee approved creation
of the Large Load Working Group (“LLWG”) in March 2026. The LLWG held its first meeting
on April 20, 2026, providing a dedicated forum for issues spanning markets, reliable operations,
planning, and resource adequacy. Its early work included Interconnection Reliability
Requirements, Firm Service Step Up arrangements, and the Zero-Injection Generation
Interconnection proposal. This work brought previously related but separately considered issues
into a coordinated large load work plan.17
C. The Show Cause Order and the opportunity to develop regional solutions.
On June 18, 2026, the Commission instituted a proceeding under section 206 of the Federal
Power Act (“FPA”) to examine whether MISO’s Tariff remained just and reasonable in light of
various concerns related to large and co-located load development. The Commission identified
concerns regarding application and study procedures, operational requirements, network upgrade
cost transparency and recovery, service for flexible and co-located loads, and generation serving
associated Loads. It directed MISO and the Transmission Owners to respond to its preliminary
findings and address potential Tariff changes.18
The Commission’s action reinforced work already underway while identifying additional
matters for stakeholder consideration. The Show Cause Order also contemplated development of
regional solutions through FPA section 205 filings and allowed requests for an abeyance of up to
14 Furnish Testimony at 17-18.
15 MISO, Transmittal Letter, Expedited Resource Addition Study, Docket No. ER25-2454-000 (June 6, 2025)
(“ERAS Transmittal”).
16 Abeyance Motion at 3-4; Informational Report at 6-7; MISO, Transmittal Letter, Zero Injection Generator
Interconnection Agreement, Docket No. ER26-3552-000, at 4-6 (Aug. 18, 2026) (“ZGIA Transmittal”).
17 Abeyance Motion at 3-4 & n.6; MISO, Transmittal Letter, Large Load Addition Resource Study, Docket No.
ER27-25-000, at 49-50 & nn.102-108 (Oct. 2, 2026) (“LARS Transmittal”).
18 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, PP 1-3, 33-39 (2026), errata notice, 196 FERC ¶
61,123 (2026) (“Show Cause Order”); Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,133, P 1 (2026)
(“Abeyance Order”).
PDF page 8
The Honorable Debbie-Anne Reese
November 16, 2026
Page 8
90 days for that purpose. MISO pursued that opportunity to coordinate the existing initiatives with
additional proposals responsive to the Commission’s concerns.19
On July 20, 2026, MISO submitted the Informational Report addressing resource adequacy
and initiatives to accelerate the addition of generation to serve emerging demand. The Report
explained the respective roles of states, load serving entities, and MISO in supporting resource
adequacy and described both existing reforms and additional proposals under development. It
identified a zero injection interconnection process and a parallel study framework for associated
load and generation as complementary approaches to facilitating timely service while accounting
for system needs.20
On August 3, 2026, MISO requested that the proceeding be held in abeyance for 90 days.
The Abeyance Motion described a series of anticipated section 205 filings covering Zero-Injection
Interconnection Service, a Large Load definition and Interconnection Reliability Requirements,
coordinated Load and generation studies, Firm Service Step Up arrangements, and additional
service options for flexible Loads. It also identified further work on application and study
procedures and Upgrades cost transparency. MISO explained that the proposals needed to operate
together and fit within MISO’s existing planning, interconnection, and service processes.21
The Commission granted the requested abeyance on August 14, 2026. It found that the
described stakeholder process would provide an opportunity to consider region-specific solutions
and held the proceeding, including the responses and briefing questions, in abeyance for 90 days.22
The Commission established November 16, 2026 as the revised response deadline and explained
that a timely FPA section 205 filing addressing its preliminary findings would suspend the filing
respondents’ obligation to respond and continue the abeyance pending further Commission
direction. The Commission further explained that any issues not addressed by the FPA section
205 filings would remain subject to the FPA section 206 proceeding instituted under the Show
Cause Order and encouraged respondents seeking termination to identify specifically which
proposed revisions resolved which concerns.23
D. The earlier filings and the matters reserved for further development.
During the abeyance period, MISO submitted proposals addressing those elements of its
response that were sufficiently developed for Commission review. Those submissions did not
purport to resolve every issue in a single filing. Instead, they advanced particular components
while expressly identifying related matters for further development and subsequent submission.
The resulting sequence provides important context for this omnibus filing: the present submission
19 Show Cause Order P 37; Abeyance Motion at 4-5, 7-9; Abeyance Order PP 3-5.
20 Informational Report at 1-4, 10-11. The Report responded to the informational reporting requirement in Show
Cause Order P 122.
21 Abeyance Motion at 3-5, 8-13.
22 Abeyance Order at PP 8-9.
23 Id. at PP 8-11. The Order established December 16, 2026, as the deadline for answers to responses. Id. P 9.
PDF page 9
The Honorable Debbie-Anne Reese
November 16, 2026
Page 9
both accounts for the proposals already filed and advances additional portions of the response that
were not ready for submission at those earlier stages.24
First, on August 18, 2026, MISO submitted its Zero Injection Generator Interconnection
Agreement (“ZGIA”) proposal in Docket No. ER26-3552-000. The filing proposed a form of
Generator Interconnection Agreement, a study process, and an agreement for generation serving
Load at the same substation without broader injections onto the Transmission System. MISO had
begun developing the concept before the Show Cause Order and refined it through stakeholder
discussion. MISO limited the initial proposal to same-substation arrangements so that the zero
injection option could proceed while the separate questions presented by generation serving
electrically proximate Load were addressed through further work.25 The ZGIA proposal was
deliberately limited in scope. This distinction is relevant to the present filing because a generator
interconnection pathway alone does not supply the complete Transmission Service and cost
recovery framework for the Load it serves.26
Second, on August 28, 2026, MISO submitted its Interconnection Reliability Requirements
(“IRR”) for Large Loads proposal in Docket No. ER26-3650-000. That proposal included a Tariff
definition of Large Load and requirements addressing data, models, telemetry, forecasting, and
operational visibility, together with phasor measurement, ramp, and ride-through requirements for
Computational Loads. MISO proposed to place the applicable obligations on the Transmission
Customer taking service on behalf of the Large Load, reflecting that customer’s direct relationship
with MISO. The proposal was intended to improve MISO’s ability to assess, observe, and manage
Large Load behavior.27 The IRR filing also distinguished requirements applicable to the
Transmission Customer taking Transmission Service on behalf of the Large Load from the study
procedures used to identify system-level impacts and necessary transmission solutions. MISO
explained that it already performed stability assessments through MTEP and EPR but would
address enhancements to the broader Load addition and Transmission Service study processes in
a later FPA section 205 filing. The IRR proposal thus supplied the proposed operational
requirements to be incorporated into, and assessed through, the developing study framework.28
Third, on October 2, 2026, MISO submitted its Large Load Addition Resource Study
(“LARS”) proposal in Docket No. ER27-25-000. LARS proposed a coordinated process for
studying qualifying Load additions of at least 200 MW and associated new generation. The
proposal built upon experience with expedited load-side planning and coordinated the Load and
generation studies through a common application framework. It complemented ZGIA by
24 ZGIA Transmittal at 1-2, 5-7; IRR Transmittal at 1, 4; LARS Transmittal at 3-4, 15, 20-21.
25 ZGIA Transmittal at 1-2, 6-7. MISO requested an October 18, 2026, effective date. Id. at 2. This paragraph
describes the submitted proposal; it does not state that the Commission accepted the proposal or its requested
effective date.
26 ZGIA Transmittal at 2, 7; LARS Transmittal at 3-4.
27 IRR Transmittal at 1-4. MISO requested a December 4, 2026 effective date. Id. at 2. This paragraph describes
the proposal as submitted.
28 IRR Transmittal at 4.
PDF page 10
The Honorable Debbie-Anne Reese
November 16, 2026
Page 10
addressing qualifying Load and generation arrangements beyond the narrower same-substation,
zero injection configuration.29 LARS also reflected the iterative nature of the stakeholder process.
MISO introduced the coordinated study concept at the July 16, 2026 LLWG meeting and sought
feedback on eligibility, readiness, and protections against speculative requests. The proposal
evolved from an initial 250 MW eligibility concept to the 200 MW threshold submitted to the
Commission. MISO’s LARS transmittal further anticipated a subsequent filing addressing the
Load study process, Transmission Service, and cost recovery provisions needed to complete other
elements of the Large Load framework.30
E. The additional provisions now presented in this omnibus filing.
While the ZGIA, IRR, and LARS proposals proceeded through separate filings, MISO
continued developing the remaining application, study, service, and financial provisions. Those
matters required additional information and coordination concerning how customers would request
service, how the necessary upgrades would be identified, what obligations would support the
resulting investment, and what service could be provided under differing operating conditions.
The present filing brings forward those additional proposals and explains how they relate to the
components previously submitted. The proposed LLPR process builds on the load-specific
functions of EPR to establish a dedicated Tariff framework for a Transmission Customer taking
service on behalf of a Large Load to obtain Transmission Service. The LLPR includes standardized
applications, recurring study cycles, identification of necessary Upgrades, and the integration of
the proposed interconnection reliability requirements.31 While only Transmission Owners were
eligible to submit requests to the EPR process, MISO is proposing that only Large Load
Transmission Customers (in collaboration with the Transmission Owner) may submit an
application to the LLPR process.
The cost recovery and transparency provisions ensure the Large Load Transmission
Customer pays the cost of the Large Load Upgrades required to provide Transmission Service,
including if the expected Load does not arrive as anticipated or remain in service. The proposed
cost recovery agreements, related security, and cost transparency measures are intended to connect
the requested Transmission Service and necessary supporting investment with enforceable
financial obligations. The proposed framework includes Tariff revisions and a pro forma Large
Load Cost Recovery Agreement, and a pro forma Large Load Impacted Transmission Owner Cost
Recovery Agreement, together with a publicly accessible dashboard providing high-level
information about upgrades and estimated costs while protecting confidential information.32
29 LARS Transmittal at 1-6; see also Combined Notice of Filings No. 1, 91 Fed. Reg. 64,362 (Oct. 8, 2026) (Docket
No. ER27-25-000; Oct. 2, 2026 filing; requested Dec. 2, 2026 effective date).
30 LARS Transmittal at 3-4, 15, 20-21, 49-52.
31 Furnish Testimony at 3; see Section D.1.c.ii-iii.
32 Furnish Testimony at 21-23; Abeyance Motion at 12-13. Detailed recovery, security, and accounting provisions
remain subject to confirmation against the final pro forma agreements and supporting testimony.
PDF page 11
The Honorable Debbie-Anne Reese
November 16, 2026
Page 11
The service proposals address the separate question of how a customer may use the
Transmission System once the relevant studies and prerequisites have been satisfied. The
proposed Interim Network Integration Transmission Service (“Interim NITS”) provides a non-firm
Transmission Service option for participation of a Load progressing toward full firm Network
Integration Transmission Service (“NITS”) prior to the completion of required Upgrades. The
proposal also includes an optional Firm Service Step Up for loads progressing toward full firm
service. These alternatives are intended to recognize different operating capabilities and
development schedules while specifying the associated withdrawal limits, curtailment conditions,
and customer obligations.
Accordingly, this omnibus filing should be considered in the context of the full sequence
of MISO’s submissions in response to the Show Cause Order. The earlier filings addressed
components that could be brought forward first; the proposals submitted here reflect the further
development of the application, study, cost recovery, transparency, and service provisions
described above. Together, that history explains both the timing and the scope of the present filing.
The sections that follow identify the relief sought, describe the additional Tariff revisions proposed
here, and explain how this submission and the previously filed proposals comprehensively address
the Commission’s concerns identified in the Show Cause Order.
III.
LARGE LOAD APPLICATION AND STUDY PROCESS
In the Show Cause Order, the Commission directed MISO develop an “application process,
study procedures, and ongoing operational requirements that apply to Eligible Customers seeking
transmission service on behalf of large loads.”33 The Commission recognized that MISO and the
MISO Transmission Owners may have existing Load integration processes that included studies
for Transmission Service to Large Loads but sought documentation of clear and consistent
procedures in MISO’s Tariff that address the characteristics and challenges associated with
interconnecting Large Loads in order to avoid disputes about how studies will be conducted, deter
speculative or duplicative requests for Transmission Service to serve Large Loads, and help avoid
excessive and unnecessary Upgrades.34 MISO has worked with the Transmission Owners,
developers of Large Loads, and other stakeholders to develop the Large Load Project Review
(“LLPR”) process proposed herein. LLPR provides a clear and consistent study process that will
be required for evaluating all requests for Transmission Service to serve Large Loads.35 The LLPR
process addresses the goals of the Show Cause Order by providing a clear and consistent study
process that is tailored to the needs and challenges associated with Large Load integrations and
which provides the necessary framework for implementing the other Large Load reforms sought
by the Show Cause Order.36 The LLPR is also a uniform process that provides increased speed
and certainty to Large Load Transmission Customers in identifying the Network Upgrades needed
33 Show Cause Order at P 3.
34 Id. at PP 49, 55-57.
35 Furnish Testimony at 3-4.
36 Id. at 20-21.
PDF page 12
The Honorable Debbie-Anne Reese
November 16, 2026
Page 12
to provide Transmission Service to Large Load Transmission Customers.37 LLPR also promotes
accountability, deters speculative or duplicative requests for Large Load-driven requests for
Transmission Service, and provides transparency regarding the Large Load-driven Network
Upgrades and their associated costs.
In response to concerns raised by the Commission, MISO and the MISO Transmission Owners
propose Tariff revisions and two pro forma cost recovery agreements that together require the
Transmission Customer seeking to take Transmission Service on behalf of a Large Load (“Large
Load Transmission Customer”) to make a minimum financial contribution toward the revenue
requirement of the Transmission Owners responsible for constructing the Upgrades identified by
MISO in the LLPR, including financial security sufficient to secure such contribution.38 These
proposed Tariff changes and agreements, which are a condition precedent to MTEP approval,
impose cost responsibility and accountability on Large Load Transmission Customers consistent
with the Commission’s direction in the Show Cause Order and provide transparent identification
of the Network Upgrades made necessary by Large Loads, including their estimated costs.39 LLPR
is an expedited process designed to be completed in approximately five months. To simplify the
explanation of the LLPR process, MISO describes the key definitions, the Large Load Application,
and the required steps in the LLPR study process in the sections below.
A. New Definitions for the LLPR Process
MISO includes several new definitions in Attachment FF to its Tariff, which are needed to
provide a working vocabulary for implementing the LLPR process.40 These terms are summarized
below:
• Large Load Network Upgrades are the additions, modifications, and upgrades to
be made to the Transmission System that are located inside the Transmission
Pricing Zone containing the POW for the Large Load that are necessary for MISO
and the Transmission Owner to operate and maintain the Transmission System in a
safe and reliable manner.
• Impacted Transmission Owner Large Load Network Upgrades are the
additions, modifications, and upgrades to be made to the Transmission System that
are located outside the Transmission Pricing Zone containing the POW for the
Large Load that are necessary for MISO and the Transmission Owner to operate
and maintain the Transmission System in a safe and reliable manner.
37 MISO is proposing to add a new definition to Module A to define Large Load Transmission Customer as the
Transmission Customer that is taking Transmission Service on behalf of a Large Load.
38 See Tab E Testimony and Exhibits of Greg M. Gudeman (“Gudeman Testimony) (describing the pro forma cost
recovery agreements).
39 Furnish Testimony at 5.
40 In the transmittal letter, MISO paraphrases the LLPR process definitions, but the full definitions of each of these
terms may be found in Section D.1.c.i of Attachment FF.
PDF page 13
The Honorable Debbie-Anne Reese
November 16, 2026
Page 13
• The Large Load Cost Recover Agreement (“LL-CRA”) is the primary
agreement that establishes the Large Load Transmission Customer’s cost
responsibility for Large Load Network Upgrade(s), which are located in the
Transmission Pricing Zone containing the POW for the Large Load.
• The Large Load Impacted Transmission Owner Cost Recovery Agreement
(“LLITO-CRA”) is the agreement that establishes the Large Load Transmission
Customer’s cost responsibility for the Impacted Transmission Owner Large Load
Network Upgrades, which are located outside of the Transmission Pricing Zone
containing the POW for the Large Load.
The two different kinds of upgrades are distinguished by whether they are located inside
the Transmission Pricing Zone (“TPZ”) or outside of the TPZ containing the POW for the Large
Load.41 Similarly, the LL-CRA and LLITO-CRA establish cost recovery terms based on the
location of the Upgrades, inside or outside the TPZ. As discussed in more detail later, this
agreement framework is necessary for costs to be properly assigned throughout MISO’s
Transmission System.
Together, these terms enable the creation of processes and requirements that recognize the location
on the Transmission System of Large Load Upgrades identified through the LLPR process,
identify their connection to Large Loads, and establish the applicable parties to the proposed
agreements under MISO’s Tariff.42
B. Applicability and Participant Responsibilities.
MISO’s existing study processes require supplementation and enhancement in order to
efficiently and effectively address the growth in Large Load development over the past couple of
years. LLPR builds from and adapts MISO’s existing Expedited Project Review (“EPR”) process
and will be the required core study process for all requests for Transmission Service made on
behalf of or in order to serve Large Loads. Specifically, the LLPR process will apply to all requests
for Transmission Service for Large Loads, as defined in MISO’s Interconnection Reliability
Requirements (“IRR”) filing, including the load components of LARS which is an aligned
transmission and interconnections service requests for very large loads (200 MW or greater) paired
with the generation that will serve it.43
41 To facilitate efficient explanation, MISO uses the term “Large Load Upgrades” to embrace both “Large Load
Network Upgrades” and “Impacted Transmission Owner Large Load Network Upgrades,” reserving use of the
specific defined term for where context requires it.
42 MISO notes that nothing in LLPR interferes with the ability of states and other retail regulators to impose
additional conditions, further allocate cost responsibility and risk among and between retail customers and Load
Serving Entities, or require further agreements involving parties not directly taking service under MISO’s Tariff
(e.g., data centers and other owners of Large Loads).
43 MISO’s LARS proposal, currently pending in Commission Docket ER27-25-000, provides a specialized process
designed to study very large (≥200 MW) Large Loads accompanied by the generation that will serve it on a
coordinated timeline. MISO has committed to updating the load study portion of LARS to Incorporate the LLPR
process and requirements proposed herein once these are accepted.
PDF page 14
The Honorable Debbie-Anne Reese
November 16, 2026
Page 14
MISO envisions different parties playing diverse roles in the LLPR process. First, the
Large Load Transmission Customer, commonly the LSE, plays a key role in the LLPR process as
it is the party that can request Transmission Service through LLPR from MISO. The Transmission
Owner has an integral role in working with the parties on studies. The entity that owns the Large
Load, while usually not directly subject to MISO’s Tariff, will play an essential role in providing
the information needed to support the LLPR Application and working with the Transmission
Customer to determine the type of Transmission Service to request.44 Finally, MISO, as the
Transmission Provider, acts as coordinator, performing the required LLPR studies, administering
the LLPR process and, ultimately, approving transmission projects and granting Transmission
Service.
Transmission Customers seeking to participate in LLPR must submit a Large Load
Application to MISO as well as a non-refundable application fee of $250,000.45 Due to the role
of the Transmission Customer in obtaining Transmission Service for Loads, the Show Cause
Order’s direction that the Transmission Customer seeking Transmission Service to serve a Large
Load bear responsibility for requesting the Transmission Service and executing cost recovery
agreements. The Large Load Transmission Customer is the only party that may request
Transmission Service on behalf of a Large Load from MISO and thus, is the only party that may
submit a Large Load Application.46 MISO’s current processes similarly limit the types of entities
that can submit EPR Requests.47 MISO’s current EPR process similarly only allows Transmission
Owners to submit EPR requests. The Transmission Customer must select from a list of
Transmission Service options which service it is applying for and must identify the amount of
requested firm or non-firm service options.48 LLPR is designed to facilitate several different types
of requests for Transmission Service, including Network Resource Integration Service (“NITS”),
Firm Service Step Up (“FSSU”), Interim (“Interim NITS”), and Transmission Service requested
through LARS.49 Notably, the requested Transmission Service option and the identified MW
amount may not be changed after the Large Load Application is submitted to MISO.50 This,
together with the required application, discourages speculative or unready Large Load
44 A Large Load may assume other responsibilities or obligations pursuant to agreements with the Transmission
Customer or in accordance with rules and regulations adopted by states commissions or other retail regulators.
MISO’s LLPR does not prohibit this.
45 Furnish Testimony at 5.
46 Id.
47 Under current processes, only a Transmission Owner may submit an EPR request into MTEP because they are
the entity that identifies the urgent need on their facilities. Thus, LLPR does not introduce any new restriction
against other types of entities submitting requests for Transmission Service (e.g., Generator Interconnection
Customers, Market Participants). Rather, LLPR simply shifts this role from the Transmission Owner to the Large
Load Transmission Customer to facilitate the accountability goals of the Show Cause Order.
48 Id. at 5-6.
49 Id.
50 Id. at 5. Large Loads may be completed in phases, but the total expected MW load amount must be identified in
the Large Load Application at time of submission. Any additional load amounts must be submitted as a new
request for Transmission Service.
PDF page 15
The Honorable Debbie-Anne Reese
November 16, 2026
Page 15
Applications and provides the needed certainty about what is being studied that is necessary to
perform an accelerated study without creating undue restudy risk.
The specific Transmission Service requested, the size of the Load, and whether the Large
Load has partnered with generation will determine the next steps for the applicant and the load.
For example, if the applicants are looking to co-locate the Load with the generation, then they will
need to ensure that an appropriate Interconnection Agreement e.g. “ZGIA” has already been
executed for the generator.51 If the Large Load is greater than or equal to 200 MW and has formally
partnered with a generator for a minimum of fifteen years, then the applicants will go through the
LARS study process.52 Other Transmission Services or processes such as FSSU and Interim NITS
can be selected at the start of LLPR or after the LLPR study process is completed. Any Large
Load going through the LLPR process will be subject to the Interconnection Reliability
Requirements proposed by MISO in Docket No. ER26-3650-000.53
MISO will complete the LLPR study process three times in each 365-day period based on
any Large Load Applications received by the deadline.54 MISO will post the application deadline
on its website at least 90 calendar days prior to each deadline.55 The Large Load Transmission
Customers may submit Large Load Applications at any time and MISO will maintain a list of all
Applications leading up to each study process.56 Any applications that are submitted after the
deadline will be automatically included in the next LLPR study cycle.57 In order for MISO to
complete these studies in an expedient manner, the applicants must abide by these deadlines and
additional review periods, which will be addressed in the next sections.
C. LLPR Study Cadence, Timing, and Application Requirements—Attachment FF
Sections I.D.1.c.iii.a—I.D.1.c.iii.c.
MISO is proposing to complete the LLPR study process three times in a 365-day period.58 The
timing of this process is reasonable and dictated by how long it is expected for MISO and the other
participants in an LLPR process to complete the required steps. This study cadence is necessary
and appropriate in order to allow the base case of each LLPR study cycle to incorporate the
51 See generally, ZGIA Filing, Docket No. ER26-3552.
52 See LARS Filing, Docket No. ER27-25-000.
53 See IRR Filing, Docket No. ER26-3650-000.
54 Furnish Testimony at 10.
55 Id. As explained in testimony, the first Large Load Application deadline will be on March 1, 2027, and due to the
timing of this filing, MISO will not be able to provide 90-day notice for the first LLPR study cycle.
56 Furnish Testimony at 4, 10.
57 Id. at 10.
58 MISO considers each LLPR study cycle to commence on the date of the Large Load Application deadline and
ends once the project receives MTEP approval, which takes place once the stakeholder process has been
completed and the cost recovery agreements are executed or filed unexecuted with the Commission.
PDF page 16
The Honorable Debbie-Anne Reese
November 16, 2026
Page 16
Transmission System changes from the prior LLPR Study cycle.59 To avoid unnecessary restudy
risks, it is appropriate to begin each study cycle after the prior one is completed and the applicable
cost recovery agreements have been executed or submitted to the Commission for acceptance.
While the Large Load Application may only be submitted by the Transmission Customer,
other parties including the Transmission Owner and the Large Load customer must all provide
required information as part of the application. The LLPR Applicant must submit the non-
refundable application fee of $250,000 and any relevant study deposits at the time of application
submission.60 The parties must also submit a significant amount of information with the
Application to ensure that they have completed any necessary pre-planning steps and have reached
agreement on key portions of the project including the identification of any necessary Large Load
Upgrades by the Transmission Owner(s).61
The required technical information for a completed LLPR Application is set forth in
proposed Section I.D.1.c.iii.b of Attachment FF. This information includes the geographic
location and Point of Withdrawal (“POW”) for the Large Load, the MW amount of the Large Load,
the type of Transmission Service requested, data regarding the characteristics of the Large Load
and equipment in order to enable MISO to assess how it will operate, the MTEP and model on
demand information for associated load and transmission upgrades, the requested In-Service Date,
and any requisite contact information.62
Proposed Section I.D.1.c.iii.b.2 requires study files to include various items. Specifically,
such files should include models, one line diagrams, the Transmission Owner’s Interconnection
Study Report, including consideration of Alternative Transmission Technologies (“ATTs”)/Grid-
Enhancing Technologies (“GETs”), and information about any Large Load Upgrades identified by
the applicable Transmission Owner, with specific requirements to provide an estimate of the total
costs of the required Large Load Upgrades, the costs that the Large Load Transmission Customer
will be obligated to pay, and, if this is less than 100% of the capital costs of the Large Load
Upgrade, a narrative explaining how their portion of the costs was determined. This information
will enable MISO to verify any analyses performed by the Transmission Owner and provide the
cost transparency sought by the Show Cause Order. The Large Load Application is designed to
be flexible so that it can be used to initiate the study process for several different types of
Transmission Service and integrate with other MISO processes.63
Proposed Section I.D.1.c.iii.b.3 requires an attestation by the Transmission Customer
attesting that it acknowledges MISO’s ability to review reliability impacts and additional
59 Furnish Testimony at 12.
60 Id. at 5.
61 See id. at 6-8.
62 See id.
63 LARS, for example, will require an Interconnection Request for a Generating Facility and additional information
about the commercial relationship and electrical connection between the Interconnection Customer/Generating
Facility and the LARS Associated Transmission Customer and LARS Associated Large Load.
PDF page 17
The Honorable Debbie-Anne Reese
November 16, 2026
Page 17
mitigations through applicable study processes, that the Transmission Customer will comply with
Tariff terms and requirements applicable to Large Loads that are set forth in Module B of the
Tariff, that the Transmission Customer has a commercial agreement with the Large Load providing
for it to request Transmission Service in order to serve that Large Load, and that the Transmission
Customer does not have other requests pending with MISO for duplicative Transmission Service.
These latter two requirements provide safeguards against unnecessary, speculative, or duplicative
requests for Transmission Service by demonstrating that the Transmission Customer submitting
the LLPR Application is the correct Transmission Customer that will serve the Large Load and
that there are not multiple requests for the same Transmission Service being submitted as
speculative alternatives on different parts of the MISO Transmission System.64 If the Large Load
was proposed in multiple places then that would artificially inflate the total cost of Large Load
Network Upgrades, jeopardize the finality and commercial certainty of LLPR studies, and create
restudy or cost shift risks for other Transmission Customer or participants in other MISO
processes.65
MISO also proposes to require submission of valid models for electromagnetic transient
(“EMT”) studies.66 The EMT work must be completed in the pre-application phase in order to
capture the complete list of Upgrades and to ensure that the Large Load Transmission Customer
has taken into consideration the necessary mitigation to meet the Interconnection Reliability
Requirements.67 Finally, applicants must submit the LLPR System Impact Study Agreement and
sign any relevant non-disclosure agreements required by MISO in order to ensure funding for the
LLPR study and appropriately provide for the handling of confidential information.68 The LLPR
System Impact Study Agreement is based on and largely follows the interconnection study
agreement required for Generation Interconnection Customers with adjustments to reflect the
different types of studies that may be performed under LLPR.69 The required CEII NDA to be
included as Attachment FF-10 to the Tariff is substantively identical to the pro forma CEII NDA
required of Generator Interconnection Customers with their Interconnection Requests,70 and the
required Confidential Information NDA is MISO’s pro forma Universal Nondisclosure
Agreement, which is set forth in Attachment Z to the MISO Tariff.71
64 Furnish Testimony at 9.
65 Id. at 9; MISO has carefully worded the language of Attachment FF Section I.D.1.c.iii.b.3 so as not to prevent the
submission of applications for incremental transmission service needed in addition to that requested in a previous
application. This is appropriate because such requests are not speculative alternatives.
66 MISO is requiring all Large Load Applications to include EMT models, but EMT studies will only be required
for specific Large Load projects based on information MISO will provide and the level of detail will be described
in the BPM.
67 Furnish Testimony at 8-9.
68 Id. at 26-27.
69 See, Attachment X, Appendix 1, Attachment B
70 See, Attachment X, Attachment C to Appendix 1: Universal Non-Disclosure and Confidentiality Agreement.
71 The LLPR System Impact Study Agreement is provided in the form of Attachment FF-10 to Attachment FF. The
confidentiality agreements may include MISO’s Universal Non-Disclosure Agreement or non-disclosure
agreements related to CEII.
PDF page 18
The Honorable Debbie-Anne Reese
November 16, 2026
Page 18
LLPR Applicants are required to submit a $250,000 non-refundable application fee and a
$100,000 study deposit upon application submission.72 The $250,000 both provides funding for
LLPR administration and studies while also acting as a deterrent to speculative or uncertain Large
Load Applications.73 The $100,000 study deposit provides needed funding for the LLPR System
Impact Study and any related studies that may be required, such as an FSSU or Interim NITS study.
In the event that a Large Load Transmission Customer chooses to have MISO complete its EMT
study, then an additional $100,000 study deposit must be provided.74
The objective of including all these requirements at time of application is to ensure that the
Upgrades that are needed to reliably serve the Large Load are identified at the outset.75 It is also
critical that the parties collaborate prior to submitting the Large Load Application to MISO so that
MISO may complete the LLPR study process on its accelerated timeline.76 The streamlined
deficiency cure period for applicants is another piece of the LLPR proposal. MISO will review
each Large Load Application and notify the applicants of any identified deficiencies within fifteen
(15) business days of receipt. After receiving that deficiency notification from MISO, the
Transmission Customer will have ten (10) business days to cure the identified deficiencies.77 The
Transmission Customer will also have five (5) business days to address any errors that may be
identified later in the LLPR study process.78 If the Transmission Customer is unable to cure the
deficiencies in any of the required timelines, then the Large Load Application will be deemed
withdrawn from the LLPR process.79 While the non-refundable application fee will be lost, the
parties may submit the project in a future LLPR study cycle but must identify what information
changed from the previous application.80 There will be only one Application review period and
one cure period for each Large Load Application.81 This is necessary to ensure that the LLPR
process remains streamlined and that MISO is able to complete these studies on an expedited
timeline. MISO’s proposed Tariff language captures all requirements that will be included in the
LLPR Application. MISO will develop a form of application that captures proposed Tariff
requirements, as may be adjusted by any compliance directives received from the Commission,
and will post this form on MISO’s website prior to the application deadline for the first LLPR
study cycle.
72 Furnish Testimony at 5.
73 This is in alignment with the Commission’s Show Cause Order and its concern with speculative transmission
requests on behalf of Large Loads. See Show Cause Order PP 68, 73, 80.
74 Furnish Testimony at 8-9.
75 Id.
76 Id. at 5, 12.
77 Id. at 10-11.
78 Id.
79 Id.
80 Id. at 15-16.
81 Furnish Testimony at 10-11.
PDF page 19
The Honorable Debbie-Anne Reese
November 16, 2026
Page 19
D. Model Building and Coordination with MTEP and Existing Processes—
Attachment FF Section I.D.1.c.iii.d
Pursuant to proposed Section I.D.1.c.iii.d, MISO will commence developing models for all
LLPR studies no later than five (5) business days after the conclusion of cure period.82 MISO will
use reasonable efforts to complete the model review process within thirty (30) Calendar Days after
the conclusion of the Large Load Application cure process.83 MISO will develop models for the
LLPR studies in the applicable cycle based on the latest MTEP case and reflect all MTEP approvals
that have occurred as of the end of the cure period.84 This ensures that LLPR models are based on
the latest available information. The process includes the circulation of draft models to the
applicable Transmission Owners and Large Load Transmission Customers, subject to the required
nondisclosure agreements, and provides a five (5) business day window for the applicable
Transmission Owners and Large Load Transmission Customers to submit comments for MISO’s
consideration, after which MISO will finalize the models and circulate the final models to them.85
The model build period ends when the Transmission Provider provides the final models to the
appliable Transmission Owners and Transmission Customers.86 Taken together, this language
establishes a just and reasonable model review process for Large Loads that balances an
opportunity for participation and comments with a schedule consistent with the expedited nature
of the LLPR process so as not to disturb or delay subsequent MISO processes that build from the
completed LLPR Study Cycle.
E. The LLPR System Impact Study—Attachment FF Section I.D.1.c.iii.e.
Proposed Sections I.D.1.c.iii.e and I.D.1c.iii.f establish both a LLPR System Impact Study
process by describing the substantive analyses that will be performed as part of LLPR and details
the tender and processing of the Final LLPR Study Report. First, proposed Section I.D.1.c.iii.e
provides that MISO will commence the LLPR System Impact Study within two business days after
conclusion of the model review period and explains that the LLPR study will consist of an analysis
of the impacts of the Large Load on MISO’s Transmission System containing those elements
described in Attachment FF-10. The proposed language further provides that the analysis will be
based on any applicable planning criteria.87 This language necessarily balances specificity about
what is being studied with sufficient flexibility to accommodate rules currently being developed
by NERC, Regional Entities, Transmission Owners, and regulators. While completing the LLPR
System Impact Study, MISO may consider alternative solutions including those suggested by
stakeholders and the MTEP aggregate system analyses against applicable planning criteria.88
82 Id. at 13.
83 Id.
84 Id. at 12-13.
85 Id. at 13.
86 Id.
87 Furnish Testimony at 13-14.
88 Id.
PDF page 20
The Honorable Debbie-Anne Reese
November 16, 2026
Page 20
MISO will post all the Large Load Applications that will be included in the upcoming LLPR
System Impact Study to its MTEP webpage on its public website, thus facilitating the transparency
requirements identified in the Show Cause Order.89
In the event that any Transmission Issues are identified in the LLPR System Impact Study,
MISO will send the initial Transmission Issues to the applicable Transmission Owner and
collaborate with them on the development of possible solutions.90 This will include considering
ATTs/ GETs and selecting the preferred solution to the identified Transmission Issues.91 At this
point in the LLPR study process, there are additional strict deadlines that must be followed. The
Transmission Owners will have fifteen business days to respond to the identified Transmission
Issues with possible solutions and, within ten business days after receipt of the proposed solutions,
MISO will review and test the mitigation.92 If MISO identifies more Transmission Issues, then it
will notify the Transmission Owner, who will then have an additional ten business days to develop
new possible solutions.93 MISO will then review and test the newly proposed mitigations within
five business days.94 If the Transmission Issues are not resolved in the required timeframe, then
the Large Load Application will be withdrawn, and the project will be removed from the LLPR
study.95
Once the LLPR analysis/mitigation portion of the study is concluded, MISO will provide
a draft LLPR Study Report to the Transmission Customer and each applicable Transmission
Owner. The Transmission Customer and Transmission Owner(s) will have five business days to
review and provide comments on the study report.96 After reconciling any comments, MISO will
provide the final LLPR Study Report and any applicable cost recovery agreements to the
Transmission Customer and applicable Transmission Owner(s).97 MISO will not process any
Large Load Application for MTEP approval until all applicable cost recovery agreements are
executed by all parties or an unexecuted or non-conforming filing is submitted to the
Commission.98 This is necessary to prevent circumvention of cost recovery agreement obligations
and is consistent with their place in the LPPR framework as a required pre-condition of MTEP
approval and obtaining Transmission Service for Large Loads.
89 Id.
90 Id.
91 Id.
92 Id.; see also, Section I.D.1.c.iii.e-f.
93 Furnish Testimony at 14-15.
94 Id.
95 Id.
96 Id.
97 Id.
98 See Id. at 15-16.
PDF page 21
The Honorable Debbie-Anne Reese
November 16, 2026
Page 21
F. Tender and Processing of the Cost Recovery Agreements—Attachment FF
Section I.D.1.c.iii.f.99
When MISO shares the final LLPR Study Report with the Large Load Transmission
Customer and any applicable Transmission Owners, MISO will also tender the Large Load Cost
Recovery Agreement and/or the Large Load Impacted Transmission Owner Agreement(s). The
Large Load Transmission Customer and Transmission Owner(s) have fifteen business days to
execute the cost recovery agreements and return them to MISO, or request that the non-conforming
or unexecuted cost recovery agreements be filed with the Commission.100 Failure to do so will
result in the Large Load Application being withdrawn and the project being removed from the
LLPR process.101 The Large Load Upgrades associated with these projects will be considered
approved for MTEP purposes either at the completion of the stakeholder review process, as of the
date that the last party executes a conforming cost recovery agreement, or as of the date of filing
an unexecuted or non-conforming cost recovery agreement with the Commission, whichever is
later.102 This approach is structurally consistent with how MISO processes other service
agreements, such as MISO’s pro forma GIA and preserves the rights of Large Loads Transmission
Customers to bring disputes before the Commission through unexecuted filings while maintaining
the accelerated LLPR completion timeframe needed to allow subsequent LLPR cycles to
commence with models that account for prior LLPR cycles with sufficient certainty.103
To address stakeholder desires for a date certain when the LLPR Application is deemed
granted and the required Large Load Upgrades approved for inclusion in MTEP, MISO’s proposed
language uses either the date of the completion of the stakeholder review process, the date the last
party executes a conforming cost recovery agreement, or the filing date of a non-conforming or
unexecuted cost recovery agreement, whichever is later, as the point in time at which MTEP
approval occurs. This approach is just and reasonable because an executed conforming agreement
may be included in MISO’s Electronic Quarterly reports and need not wait for a Commission order
to be deemed accepted.104 Thus, the certainty that the project will be developed significantly
increases at this point. For nonconforming and/or unexecuted agreements, MISO considered using
the date of a Commission order accepting such agreement as the trigger for MTEP inclusion.
However, MISO ultimately rejected this approach as impractical. Given the need to build the base
99 Section I.D.1.c.iii.f also addresses the tender of the final LLPR Study Report, but that timing was addressed in
the previous section.
100 Gudeman Testimony at 5.
101 Id.
102 Furnish Testimony at 17.
103 See, Tariff Attachment X, Section 11.3 (Execution and Filing) (implementing a similar procedure, including a
deemed withdrawal for failure to proceed and different timeframes based on the requirements and timing of the
underlying process).
104 Under MISO’s EPR process, projects are deemed approved for inclusion in MTEP once the study is complete and
MISO adds them to the list of approved projects. With the introduction of agreements that memorialize
commitments associated with the LLPR process, using later of the stakeholder review process completion date,
the execution date, or filing date of unexecuted or non-conforming agreements provides an appropriate equivalent
reference date for approval.
PDF page 22
The Honorable Debbie-Anne Reese
November 16, 2026
Page 22
models used in subsequent LLPR cycles using a system topography that reflects what was changed
by prior LLPR cycles in order to accurately study impacts, it would not be possible to wait several
months for a Commission order before building the models used in the next LLPR cycle while
maintaining a triannual LLPR study cadence. MISO proposes the date of filing of an unexecuted
or nonconforming filing as point where the application should be deemed approved for inclusion
in MTEP as reasonable compromise between providing certainty in modeling for the next LLPR
study cycle and maintain the accelerated study cadence necessary to accommodate the integration
schedules of Large Loads.105
Notably, no Transmission Service shall commence under an unexecuted or non-
conforming cost recovery agreement until it has been accepted by the Commission. While it is
reasonable to include the needed transmission upgrades in models upon submission of an
unexecuted or nonconforming filing in order to commence subsequent study cycles on schedule,
allowing Transmission Service to commence prior to Commission acceptance of the cost recovery
agreements risks decoupling the requirements for the Large Load Transmission Customer
contained in the agreements from the Transmission Service granted. This risk is not needed to
prevent delays to all other Large Load Transmission Customers and MISO expects that in most
instances, a Commission order would likely be issued before the Large Load’s need-by date.106
MISO’s proposed language is reasonable and necessary to establish the prescribed timeline
for executing the cost recovery agreements, enable stakeholder review and feedback, identify when
Large Load projects are considered approved for MTEP purposes, and allow model building for
subsequent cycles. These strict timelines are necessary to ensure that the LLPR process can be
completed in a 365-day period and to ensure that MISO has sufficient certainty in the Large Load
Upgrades completed by applicants in the LLPR process. These requirements make clear that even
if a project is withdrawn and removed from the MTEP models, the Large Load Transmission
Customer is still responsible for paying for any identified Large Load Upgrade costs. This
approach avoids reserving system capability for projects that ultimately do not proceed.
G. Resubmission of Withdrawn Applications—Attachment FF Sections I.D.1.c.iii.g
Proposed section I.D.1.c.iii.g provides that any withdrawal of the application will result in
the removal of the project from the LLPR study process. The Large Load Transmission Customer
may submit a new Large Load Application to MISO but must identify what information has
105 While this date does not provide as much certainty as the date of Commission acceptance, a project is still more
likely to be developed after a service agreement is filed than before that point. In MISO’s experience, most
unexecuted filings will still result in the agreement being accepted by the Commission, either with or without the
requested changes to pro forma agreement terms, and non-conforming agreements are fairly uncommon. MISO
acknowledges that rejection is possible and projects that have unexecuted agreements can be included in
subsequent models only subject to the outcome of the Commission proceeding. However, the risks of diminished
certainty are, on balance, preferable to guaranteed study delays.
106 This could result in an actual delay only in the highly unlikely scenario where a Large Load is projected to be
built and require Transmission Service obtained through LLPR in a shorter timeframe than the Commission can
act on a filing.
PDF page 23
The Honorable Debbie-Anne Reese
November 16, 2026
Page 23
changed since the previous submission.107 This language provides clear withdrawal rules and is
both reasonable and needed to allow for the uniform administration of the LLPR process on an
accelerated timeframe.
H. Stakeholder Forums—Attachment FF Sections I.D.1.c.iii.h.
Consistent with its current process, MISO will host a stakeholder forum at the end of each
LLPR study process or as otherwise provided in the Transmission Planning Business Practices
Manual (“TPBPM”) basis to review the identified transmission needs, solutions, and any
alternatives identified in the completed LLPR studies.108 The purpose of these stakeholder forums
is to review with stakeholders the transmission needs, solution(s), and any identified alternatives
identified in the completed LLPR System Impact Studies. Following each stakeholder forum,
stakeholders will have a defined comment period outlined in the TPBPM.109 This stakeholder
review process happens in parallel to the tender and execution of any relevant cost recovery
agreements, thus allowing MISO to schedule stakeholder discussions and comment periods on an
actionable timeframe. As explained earlier in this letter, a LLPR Application is considered
approved by MISO at the completion of the stakeholder review process, execution of a conforming
cost recovery agreement for such Large Load Upgrade, or upon the filing of an unexecuted or non-
conforming cost recovery agreement with the Commission, whichever is later.110 For example, if
a cost recovery agreement was executed within two days, MISO would not consider the project
approved until it completed the stakeholder review process. This is necessary to allow action on
stakeholder comments where appropriate.
These proposed Tariff additions align with MISO’s commitment to working with
stakeholders in addressing the integration of Large Loads and providing transparency in the
projects studied in the LLPR process. MISO regularly hosts these stakeholder forums as part of
the EPR process and will continue to do so on a regular basis for projects going through the LLPR
process.
I. Cost Recovery Agreements—Attachment FF Section I.D.1.c.iii.i.
As part of the proposed LLPR process and to mitigate the risk of cost shifting among
Transmission Customers, MISO is proposing two cost recovery agreements to ensure that a Large
Load Transmission Customer bears the risk and is ultimately responsible for the costs incurred to
provide the requested Transmission Service.111 The relevant cost recovery agreements will include
107 Furnish Testimony at 16.
108 Id. at 17. Any meetings involving CEII or confidential materials will be handled under Section I.C.23 of
Attachment FF.
109 Id.
110 Id.
111 Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and
Attachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery
Agreement).
PDF page 24
The Honorable Debbie-Anne Reese
November 16, 2026
Page 24
an exhibit listing the Large Load Upgrade(s) and/or Impacted Transmission Owner Large Load
Upgrade(s) that are required for the Large Load Transmission Customer.
The LLPR process ends with MTEP approval and after the issuance of such approval, the
Transmission Customer remains responsible for the Large Load Upgrade costs identified through
the LLPR.112 Thus, if a project is assigned Large Load Upgrades through the LLPR process and
the Large Load is subsequently not built, or its service is terminated, then the Large Load
Transmission Customer will remain responsible for any associated costs assigned to their project
under the proposed cost recovery agreements. This provides the necessary certainty for later
projects studied in the LLPR process and will allow MISO to complete the studies efficiently
without disrupting future LLPR study cycles.113
The details and requirements of the proposed cost recovery agreements are further
described in Section IV of this transmittal letter.
J. LLPR Operations Agreement and Confidentiality—Attachment FF Sections
I.D.1.c.iii.j—I.D.1.c.iii.k.
Once a Large Load project has received MTEP approval, the Transmission Customer must
submit an updated Large Load forecast along with an operations agreement for the new Large
Load.114 This operations agreement, which is Exhibit 2 to Attachment F, is an application for
Network Integration Transmission Service (NITS) in accordance with Module B Section 29.2 of
the Tariff prior to the Service Commencement Date. As part of the operations agreement process,
the Transmission Owner will develop a CPNode for each Large Load. This is necessary for MISO
settlement, operational visibility, and forecasting purposes.115 These pro forma service agreements
are executed, reported in the EQR, and posted publicly on MISO’s website. Service to the Large
Load will not commence prior to MISO’s review and execution of the operations agreement.
Proposed Section I.D.1.c.iii.k provides for the designation and protection of confidential
and Critical Energy Infrastructure Information by participants in the LLPR process with access to
non-public information subject to MISO’s established Nondisclosure Agreement and CEII rules.
As explained further by Ms. Furnish, the form of non-disclosure agreement will be the universal
NDA, as accepted by the Commission for inclusion in MISO’s Tariff as Attachment Z. The CEII
NDA is directly drawn from the form of nondisclosure agreement included with MISO’s
Interconnection Request form required for Interconnection Customers, thus promoting rules
alignment across processes. Allowing participants in studies to request confidential and/or CEII
treatment of appropriate information is a necessary and routine feature of MISO study processes
and will protect the more sensitive information (e.g., detailed models, diagrams and other sensitive
technical information) required as part of the LLPR process. MISO notes that these confidentiality
112 Furnish Testimony at 15-16.
113 Id.
114 Furnish Testimony at 16-17.
115 Furnish Testimony at 16-17.
PDF page 25
The Honorable Debbie-Anne Reese
November 16, 2026
Page 25
safeguards will not conflict with the transparency requirements proposed in this filing, including
the public Large Load dashboard, because the required information is set forth in the Tariff and
both MISO’s proposed Tariff language and existing confidentiality rules prohibit designation as
confidential of information that a Tariff or other legal requirement specifies be made public.
At the conclusion of the LLPR process, the cost recovery agreements associated with Large
Load Upgrades will be submitted to the Commission for approval. Any executed cost recovery
agreements will be included in MISO’s EQR reports on a quarterly basis and all the agreements
included in those EQR reports are publicly posted on MISO’s public website in accordance with
the same procedures applicable to other types of service agreements. The EQR reports will also
be accessible through MISO’s website. 116 Unexecuted or non-conforming cost recovery
agreements will be filed separately with the Commission and publicly available subject to the
Commission’s regulations.
K. The Proposed Tariff Revisions are Just and Reasonable.
Under section 205 of the Federal Power Act, MISO must show that its proposed Tariff
revisions are just and reasonable, and not unduly discriminatory or preferential. “For filings made
under FPA section 205, the Commission evaluates whether the proposal in the filing is just and
reasonable, and not whether alternative proposals are more or less reasonable than the filing party’s
proposal.”117 In the Show Cause Order, the Commission preliminarily found that MISO’s Tariff
lacked clear and consistent provisions addressing large load integration. The Commission noted
that MISO’s role in load additions has been largely supplemental and the Transmission Owners’
study processes are not set in the Tariff and some have used ad hoc, stand-alone study agreements.
The proposed LLPR revisions directly address these concerns.
MISO developed a dedicated framework for Large Loads and proposes to add the LLPR
process to Attachment FF of the Tariff as well as new pro forma Attachments LLL and MMM.
With these additions, every Transmission Customer seeking Transmission Service for a Large
Load must submit a Large Load Application and provide the requisite information to MISO. This
not only creates a single path for Large Load Transmission Customers to take when seeking
Transmission Service, it provides MISO with the ability to expedite the study timelines and, in
some cases, optimize the transmission solutions. Each Large Load Application must elect one of
several defined options (LLPR, Interim NITS, LARS, etc.), which replaces the historic and
potentially inconsistent practices with a single, Tariff-based process that applies equally to all
Large Load Transmission Customers. Together, these provisions create a transparent and
predictable path for identifying the Large Load Network Upgrades needed to serve Large Load
Transmission Customers, while balancing speed, reliability, and stakeholder engagement.
MISO’s proposed Large Load framework provides alternative pathways depending on size
of the load, which strikes a just and reasonable balance between capturing the larger loads for
116 See MISO, Notifications Overview, Market Settlements, available at: https://www.misoenergy.org/markets-and-
operations/notifications/.
117 See PJM Interconnection, LLC, 197 FERC ¶ 61,019, at P 29 (2026).
PDF page 26
The Honorable Debbie-Anne Reese
November 16, 2026
Page 26
which MISO needs visibility to ensure system reliability and directing the smaller loads that do
not raise the same reliability concerns into the existing EPR process.118 The Large Load
Application is just and reasonable and not unduly discriminatory or preferential because it requires
the applicants to provide significant information about the Large Loads, which in turn will provide
MISO with the information necessary to address the operational impacts of Large Loads looking
to interconnect to MISO’s Transmission System.
The LLPR application process also contains the elements identified by the Commission in
the Show Cause Order. The Large Load Applications are accepted on a rolling basis and require a
non-refundable application fee of $250,000. The applications must include detailed information
about the Large Load and provide planning models for MISO to utilize when completing its own
independent studies. MISO is also requiring that the Large Load Transmission Customer attest
that it has no other pending requests for service to the same Large Load, which will improve load
forecasting clarity and certainty. The Commission has noted in other contexts that non-refundable
fees, study deposits, and readiness requirements deter speculative requests, which is critical for
MISO to be able to study these loads on an expedited basis. The proposed Tariff revisions and
pro forma cost recovery agreements also require financial security equal to the Large Load
Network Upgrade capital costs once the LL-CRA is executed, which will further reduce the
possibility of speculative requests clogging the study processes, distorting load forecasting, or
further risking any kind of cost shifting.
The LLPR System Impact Study is just and reasonable because it incorporates enhanced
study requirements to enable MISO independently to analyze the impacts of each Large Load on
the Transmission System. MISO will conduct this analysis based on MTEP models, and in
collaboration with the Transmission Owner and Transmission Customer. Moreover, to participate
in the LLPR process, MISO requires that EMT studies be completed before the application is
submitted so that the full set of Network Upgrades needed to reliably serve the Large Load can be
identified.119 The study also requires the evaluation of alternative transmission technologies and
grid-enhancing technologies by the Transmission Owners and MISO will review the consideration
of any relevant ATTs/GETs, which was another Commission concern.120
The LLPR provides the clarity and consistency sought in the Show Cause Order by stating
the information required to enter the process, the study sequence, the roles of MISO and the
Transmission Owners, and the relationship of the results to planning and service. The readiness
and attestation requirements address the Commission’s concern with speculative or duplicative
requests, while the cumulative assessment and reliability information support consistent treatment
118 See PJM Interconnection, LLC, 197 FERC ¶ 61,019, at P 27 (2026); see also Sw. Power Pool, Inc., 194 FERC ¶
61,031, at PP 10, 61 (2026) (accepting a proposed definition of a high impact large load that included a 50 MW
threshold for new or increased load at a single site connected to the transmission system at a voltage level greater
than 69 kV); Tri-State Generation & Transmission Ass’n, Inc., 196 FERC ¶ 61,127, at P 76 (2026) (Tri-State)
(accepting a proposal to define a high impact load as load exceeding or forecasted to exceed 45 MW within four
years).
119 Furnish Testimony at 8.
120 Id. at 13-14.
PDF page 27
The Honorable Debbie-Anne Reese
November 16, 2026
Page 27
of system impacts. The recurring cycles provide an accelerated path grounded in MISO’s existing
planning framework.121 Finally, the proposed revisions were developed through MISO’s Large
Load Working Group where the process was presented, reviewed, and discussed by
stakeholders.122 The Commission recognized and encouraged this effort in the Show Cause Order.
For these reasons, the proposed Tariff revisions are just and reasonable, and not unduly
discriminatory or preferential, and the Commission should accept them under section 205 of the
Federal Power Act.
L. Separate Proposal to Apply Cost Recovery Agreements to LARS Projects.
Separately from all other proposals contained in this filing, MISO proposes to include the
following language as a separate paragraph in Attachment FF, Section I.D.1.c.iii.f in order to
facilitate the use of the LL-CRA and LLITO-CRA as part of the LARS process:
Subject to Commission acceptance of the revisions to Attachment FF of the Tariff
pending before the Commission in Docket No. ER27-25, all LARS Associated
Transmission Customers that submit LARS Applications for inclusion in a LARS
cycle with a kickoff date on or after February 14, 2027, shall execute or request the
unexecuted and/or non-conforming filing of the LL-CRA and/or LLITO-CRA, as
applicable, for all Network Upgrades identified in a LARS study for which
Attachment FF I.D.1.b.ii.g. assigns cost responsibility to the LARS Associated
Transmission Customer. The LARS Application and Network Upgrades identified
in a LARS study for which Attachment FF I.D.1.b.ii.g. assigns cost responsibility
to the LARS Associated Transmission Customer shall be deemed approved for
MTEP purposes as of the later of: (1) the date the last party executes the applicable
conforming LL-CRA and, if required, LLITO-CRA(s); (2) the date of filing with
the Commission of an unexecuted and/or nonconforming LL-CRA and/or LLITO-
CRA; or (3) the conclusion of the stakeholder comment period required by Section
III.D.1.c.iii.h of this Attachment FF. A LARS Associated Transmission Customer
shall not commence Transmission Service under an unexecuted or non-conforming
LL-CRA or LLITO-CRA until such agreement(s) have been accepted by the
Commission.
If the Commission ultimately approves MISO’s LARS proposal, all LARS Associated
Transmission Customers that submit LARS Applications on or after the effective date of this filing
(February 14, 2027), shall execute or request the unexecuted filing of a cost recovery agreement,
as applicable, for all Large Load Upgrades identified in a LARS study. The Large Load Upgrades
associated with these LARS projects will be considered approved for MTEP purposes as of the
date that the last party executes a conforming cost recovery agreement or as of the date of filing
an unexecuted or non-conforming cost recovery agreement with the Commission.
121 Show Cause Order at PP 39, 56–65 (identifying concerns regarding timely studies, readiness, operational impacts,
and clear Tariff provisions); Furnish Testimony at 3.
122 See Furnish Testimony at 28-33.
PDF page 28
The Honorable Debbie-Anne Reese
November 16, 2026
Page 28
In the LARS Answer, MISO also stated that it would submit another filing to reconcile the
LARS and LLPR processes to ensure their full alignment.123 Notably though, MISO has proposed
standalone Tariff language in this docket to make the proposed cost recovery agreements
applicable to new LARS studies. While acceptance of the Tariff language discussed above will
not obviate the need to make a subsequent reconciliation filing to harmonize other aspects of the
LARS and LLPR filings, it will allow for the cost recovery agreements, which are a valuable
transparency and accountability mechanism, to apply to LARS studies earlier than would be
possible if MISO waited until acceptance of the instant filing and a subsequent reconciliation
filing, to apply the cost recovery agreements to the LARS process.124 To the extent that the
Commission accepts the cost recovery agreements in the instant docket, it may then separately
consider whether to make them applicable to the next LARS cycle, assuming MISO’s LARS filing
also is accepted.
Thus, this proposed Tariff language represents a standalone proposal, which MISO
includes in this filing purely for Tariff administration reasons.125 While it builds on the LLPR
process and Cost Recovery Agreements proposed in this filing, it is not a component of any other
proposal contained in this filing, not a part of any compromise or agreement with stakeholders
regarding other elements of this filing. MISO urges acceptance of this language for the reasons
described above, MISO
IV.
COST RECOVERY AGREEMENT AND COST TRANSPARENCY
The Show Cause Order preliminarily found that MISO’s Tariff appeared to be unjust and
unreasonable because it lacked adequate mechanisms to mitigate the risk of cost shifting among
transmission customers, which may result in unjust and unreasonable rates for transmission
service.126 Specifically, the Commission was concerned about the apparent lack of: (1)
transparency regarding the assignment of network upgrades, and their associated costs, that are
needed to provide transmission service to transmission customers on behalf of large loads; and
(2) a pro forma cost recovery agreement between MISO, the transmission owner, and the
123 Furnish Testimony at 19; see MISO’s November 9 Answer filed in Docket No. ER27-25-000 (“LARS Answer”)
at 15.
124 This proposed language is severable from LARS because acceptance LARS was designed to work even with
existing processes and then be integrated with the reforms contained in this filing once accepted by the
Commission.. The standalone proposal contained in this filing is an enhancement to LARS, but not necessary for
its function. The proposed language is severable from this filing because it is contained in its own paragraph that
replicates language proposed elsewhere and its application is limited to LARS.
125 As explained in the LARS Answer, MISO filed its LARS proposal before LLPR, the LL-CRA and LLITO-CRA
were developed given the immediate need for such a process and lead time for implementation. LARS Answer at
3, 18. In that docket, MISO committed to updating LARS to incorporate the processes changes included in this
filing once this filing is accepted. LARS Answer at 15. While MISO could make a separate contemporaneous
filing from this one to make the LL-CRA and LLITO-CRA applicable to Large Load Transmission Customers
participating in LARS, this would create version control concerns with pending language built upon pending
language, as each filing would create a new version of Attachment FF.
126 Show Cause Order at P 66.
PDF page 29
The Honorable Debbie-Anne Reese
November 16, 2026
Page 29
transmission customer taking transmission service on behalf of Large Loads that ensures that the
transmission customer bears the risk and is ultimately responsible for costs incurred to provide
transmission service, including the cost of network upgrades.127 Below is a summary of the
proposed Tariff revisions that address the Commission’s concerns.
A. Cost Recovery Agreements
In the Show Cause Order, the Commission preliminarily found that MISO’s Tariff appeared
to be unjust and unreasonable because it lacked “adequate mechanisms to mitigate the risk of cost
shifting among transmission customers, which may result in unjust and unreasonable rates for
transmission service.”128 To prevent unjust and unreasonable cost shifting among transmission
customers, the Commission stated that it appeared necessary for MISO, the relevant transmission
owner, and the transmission customer taking transmission service on behalf of a large load to enter
into a cost recovery agreement with a specified minimum financial contribution and financial
security sufficient to secure such contribution to mitigate cost shifting if the transmission customer
ultimately takes less transmission service than anticipated because the large load does not
materialize as planned or is not developed at all.129
In response to concerns raised by the Commission, MISO and the MISO Transmission
Owners propose Tariff revisions and two pro forma cost recovery agreements that together require
the Large Load Transmission Customer to make a minimum contribution toward the revenue
requirement of the Transmission Owner(s) responsible for constructing the Large Load Upgrades
identified by MISO in the LLPR.130 To ensure the minimum contribution, Large Load
Transmission Customers are required to provide security to cover the capital cost of the Large
Load Upgrades. As briefly described in the previous section, prior to receiving MTEP approval
for any such Large Load Upgrades, Large Load Transmission Customers are required to execute
the pro forma LL-CRA and/or LLITO-CRA, as applicable, or request that the cost recovery
agreements be filed unexecuted or as non-conforming with the Commission within 15 business
days of being tendered the agreements by MISO. Failure to do so by the conclusion of the 15-day
period will result in the Large Load Application being withdrawn, and the project being removed
from the LLPR process. The customer is required to provide security within 45 days of the
execution of the LL-CRA and/or LLITO-CRA. If the LL-CRA or LLITO-CRA is filed unexecuted
or as non-conforming, separate terms apply depending on the nature of the dispute and when the
Commission approves such agreement. Importantly, a Large Load Transmission Customer cannot
127 Id.
128 Show Cause Order at P 78.
129 Id. at P 82, 84.
130 Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and
Attachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery
Agreement).
PDF page 30
The Honorable Debbie-Anne Reese
November 16, 2026
Page 30
commence Transmission Service under an unexecuted and/or non-conforming LL-CRA or LLITO-
CRA until the applicable cost recovery agreements have been approved by the Commission.131
The above framework, including the embedded rate mechanisms, which are discussed in
more detail below, reflect a balanced approach to mitigating the cost shift concerns identified by
the Commission while respecting state laws (in particular state retail ratemaking authority),
Transmission Owner diversity, including their varied business models, the reality that
Transmission Customers are often not the Large Load entities actually interconnecting to the
Transmission System but merely a pass through, and the region’s economic development
ambitions. Importantly, nothing in LLPR, including the proposed cost recovery framework
interferes, limits the ability of states and other retail regulators to impose additional conditions,
further allocate cost responsibility and risk among and between retail customers and Load Serving
Entities, or require further agreements involving parties not directly taking service under MISO’s
Tariff (e.g., data centers and other owners of Large Loads). Although a difficult needle to thread,
the proposed framework, consistent with the direction given by the Commission in the Show Cause
Order, and in recognition of MISO’s regional differences and state authority, is a just and
reasonable approach to addressing the risk of cost shifting among Transmission Customers in
MISO and potentially unjust and unreasonable rates.
Below is a summary of each agreement and the rate mechanisms therein.
1. Scope and allocation of responsibilities.
MISO proposes two complementary pro forma cost recovery agreements to establish the
Large Load Transmission Customer’s financial responsibility for the Large Load Upgrades
identified through the LLPR study process. The Large Load Cost Recovery Agreement (“LL-
CRA”) addresses upgrades within the Transmission Pricing Zone containing the Large Load’s
Point of Withdrawal. The Large Load Impacted Transmission Owner Cost Recovery Agreement
(“LLITO-CRA”) addresses upgrades outside that zone. MISO, the Large Load Transmission
Customer, and the applicable Transmission Owner(s) are required parties to the agreements. For
purposes of the agreements, LLPR includes LARS. The agreements therefore link the LLPR study
results to the entities responsible for service, investment, and payment.
In addition to any Transmission Service charges incurred by the Large Load Transmission
Customer under the Tariff, a Large Load Transmission Customer is responsible for the costs of the
Large Load Upgrades (“Minimum Contribution”) pursuant to the cost recovery rate mechanisms
in the LL-CRA and LLITO-CRA.132 This Minimum Contribution is necessary to ensure that the
Large Load Transmission Customer is responsible for paying for the costs of transmission driven
by the Large Load (i.e., the cost incurred to provide the requested Transmission Service, including
the costs of any Large Load Network Upgrades).
131 Proposed MISO Tariff, Attachment FF, I.D.1.c.iii.f.
132 Gudeman Testimony at 7, 22.
PDF page 31
The Honorable Debbie-Anne Reese
November 16, 2026
Page 31
To accommodate the diversity of regulatory approaches and business models among
Transmission Owners, the pro forma agreements provide the Transmission Owner responsible to
construct a Large Load Upgrade the flexibility to roll into its rates for Transmission Service the
capital costs of the Large Load Upgrade or to directly assign the costs of the Large Load Network
Upgrade(s) to the Large Load Transmission Customer, and such election will be recorded in the
agreement.133 The MISO Transmission Owners are a diverse group of investor-owned
transmission owners, municipal utilities, and cooperatives, including both vertically integrated and
independent transmission companies, that own transmission facilities over which MISO provides
Transmission Service. For example, some Transmission Owners, in addition to service
Transmission Customers, serve retail load. Some do not—they only serve MISO Transmission
Customers. The rate mechanisms in the cost recovery agreements ensure that cost recovery does
not unnecessarily conflict with these various Transmission Owner business models in existence
within the MISO footprint. Importantly, however, as discussed below, whether Large Load
Upgrade costs are rolled in or directly assigned, the Large Load Transmission Customer is always
responsible for the costs of the Large Load Upgrades, thus, mitigating cost shifts to other
Transmission Customers, consistent with the Show Cause Order.134
2. Recovery of costs for upgrades within the TPZ.
Where the capital costs of the Large Load Network Upgrade are rolled in the Transmission
Owner’s transmission rates, the Large Load Transmission Customer is responsible for its Total
Required Revenue Commitment, which amount is set forth in the agreement and payable on a
yearly basis consistent with the Yearly Required Revenue Commitment.135 If the Transmission
Service revenue attributable to a Large Load Transmission Customer on behalf of the Large Load
during a calendar year is less than the customer’s Yearly Required Revenue Commitment, the
customer is required to make a Supplemental Payment to the Transmission Provider.136 The
formulas for calculating such amounts are set forth in Exhibit C of the LL-CRA. Below is a more
detailed description of these items.
The Total Required Revenue Commitment reflects the return on and of the Large Load
Network Upgrade investments over twenty years, including capital cost, return, depreciation,
operations and maintenance, and taxes.137 The commitment is initially based on the estimated
upgrade costs and then adjusted as actual capital costs are determined.138
Following each calendar year, the Transmission Owner, in coordination with MISO, will
determine whether the Large Load Transmission Customer has satisfied its Yearly Required
133 Proposed MISO Tariff, Attachment LLL, §§ 3.1–3.4 and signature page; Proposed MISO Tariff, Attachment
MMM, §§ III–V and signature page.
134 Gudeman Testimony at 8.
135 Id.
136 Id. at 12.
137 Id. at 8-10.
138 Proposed MISO Tariff, Attachment LLL, § 3.3.3.
PDF page 32
The Honorable Debbie-Anne Reese
November 16, 2026
Page 32
Revenue Commitment or whether a Supplemental Payment is owed.139 If the Transmission
Service revenue attributable to Large Load Transmission Customer during a calendar year is less
than the Large Load Transmission Customer’s Yearly Required Revenue Commitment, the Large
Load Transmission Customer is required to make a Supplemental Payment to MISO, the formula
for which is set forth in Exhibit D to the LL-CRA. If the attributable revenue equals or exceeds
the yearly commitment, no Supplemental Payment is required. Mr. Gudeman, in his testimony,
details and provides examples for calculating the Total Required Revenue Commitment, the Yearly
Required Revenue Commitment and Supplemental Payment.140
This annual comparison gives effect to the Large Load Transmission Customer’s actual
contribution to transmission revenues while preserving a minimum payment obligation when load
is below the level needed to mitigate a cost shift. For example, a $10 million Yearly Required
Revenue Commitment and $7 million in attributable annual transmission-service revenue would
necessitate a $3 million Supplemental Payment; attributable revenue of $10 million or more would
produce no Supplemental Payment for that year. In his testimony, Mr. Gudeman, based on
assumptions provided in his testimony, provides an illustrative example of how the Supplemental
Payment is determined.141 If required, MISO will issue the supplemental invoice within ninety
days after the end of every calendar year during the term of the cost recovery agreement, with
billing and payment governed by Tariff Section 7 and the applicable Business Practice Manuals.142
MISO will allocate any Supplemental Payments among the Transmission Owners that are
a party to the LL-CRA in proportion to their respective Annual Incremental Revenue Requirement
(defined in the agreement) included in the Yearly Required Revenue Commitment.143 Any
Supplemental Payment allocated to a Transmission Owner will be treated as a revenue credit
against the recipient Transmission Owner’s annual transmission revenue requirement, and each
applicable Transmission Owner must provide a workpaper in its annual informational filing, which
is generally filed in March of a calendar year, detailing that credit.144 While the need for a
Supplemental Payment and the amount thereof will not be known until after a calendar year has
ended, there does not necessarily need to be a large lag in reflecting significant Supplemental
Payments in rates paid by Transmission Customers. As Mr. Gudeman explains, any lag associated
with a Supplemental Payment could be addressed by the Transmission Owner when developing its
projected revenue requirement.145 In short, the cost recovery mechanism explained above is
specifically designed to offset in rates the costs of the Large Load Network Upgrades so that the
end result is that those costs are not shifted to other Transmission Customers.146 As shown in
139 Proposed MISO Tariff, Attachment LLL, § 3.3.5.
140 Gudeman at 8-17; see also Proposed MISO Tariff, Attachment LLL, § 3.3 and Ex. C, D.
141 Gudeman Testimony at 12-13; Gudeman Testimony Exhibit MTO-0004 (Calculation of Supplemental Payment).
142 Proposed MISO Tariff, Attachment LLL, §§ 3.3.5.6 and 3.3.5.7.
143 Gudeman Testimony at 13.
144 Gudeman Testimony at 17.
145 Id. at 13-16.
146 Id. at 16-17.
PDF page 33
The Honorable Debbie-Anne Reese
November 16, 2026
Page 33
Exhibit MTO-0006 to Mr. Gudeman’s , with all else being equal assuming no other changes to
load or revenue requirements, the Large Load Transmission Customer pays at least the incremental
revenue requirement for the Large Load Network Upgrades and the zonal rate charged to other
customers will not increase as a result of the Large Load Network Upgrades.147
Where the capital costs of the Large Load Network Upgrades are directly assigned to the
Large Load Transmission Customer, payments will be due from the customer as specified in a
separate agreement between Transmission Owner and Large Load Transmission Customer to be
filed with the Commission.148 Under such circumstances, the Transmission Owner agrees that it
will not recover the costs of the directly assigned upgrade from other Transmission Customers and
commits to providing an annual workpaper showing that treatment.149
The LL-CRA continues until the earlier of twenty years after the final Large Load Network
Upgrade enters service or satisfaction in full of the Total Required Revenue Commitment and the
direct-assignment payment obligations, as applicable.150
3. Recovery of costs for upgrades outside the TPZ.
The LLITO-CRA establishes a separate rate mechanism for upgrades outside the TPZ.
Where the capital costs of ITO-Large Load Network Upgrades are rolled into a Transmission
Owner’s rates, the Large Load Transmission Customer is responsible for the ITO Large Load
Network Upgrade(s)’ Monthly Revenue Requirement beginning in the month following the
Transmission Owner’s notification that the upgrade has entered service.151 The formula to
calculate the Monthly Revenue Requirement is set forth in Exhibit II to the LLITO-CRA and is
identical to the “Incremental Revenue Requirement for Large Load Network Upgrades
Calculation” formula in Exhibit C to the LL-CRA.152 As described above, the formula multiplies
the capital invested in the ITO-Large Load Network Upgrade(s) by a levelized fixed charge rate
determined from the term of the LLITO-CRA and data from the Transmission Owner’s MISO
Tariff Attachment O Formula Rate, including taxes, interest on long term debt, return on equity,
depreciation expense, total operations and maintenance expense, general and common
depreciation expense; taxes other than income taxes; and total gross transmission plant. The
default recovery term is 240 months of payments for each upgrade, unless the parties mutually
agree to a different term or the applicable obligations are otherwise satisfied.153
147 Id. at 16-17; Gudeman Testimony Exhibit MTO-0006 (Zonal Rate Impact).
148 Proposed MISO Tariff, Attachment LLL, § 3.4.1.
149 Proposed MISO Tariff, Attachment LLL, § 3.4.2.
150 Proposed MISO Tariff, Attachment LLL, §§ 2.2–2.3, 3.3.
151 Proposed MISO Tariff, Attachment MMM, § IV.
152 Gudeman Testimony at 24.
153 Proposed MISO Tariff, Attachment MMM, § II.
PDF page 34
The Honorable Debbie-Anne Reese
November 16, 2026
Page 34
The Transmission Owner recalculates the payment annually using updated inputs from the
Transmission Owner’s Tariff Attachment O Formula Rate using data from the previous calendar
year.154 Any payments from the customer under the LLITO-CRA are treated as revenue credits
against the Transmission Owner’s annual transmission revenue requirement, documented in the
Transmission Owner’s annual informational filing.155
If the impacted Transmission Owner directly assigns ITO-Large Load Network Upgrade
costs under proposed Section V of the LLITO-CRA, payments are due as specified in a separate
agreement between Transmission Owner and Large Load Transmission Customer to be filed with
the Commission.156 As with the LL-CRA, the Transmission Owner may not recover the directly
assigned costs from other Transmission Customers and must document the foregoing in its annual
informational filing.157
4. Financial security and construction coordination
To secure the Large Load Transmission Customer’s obligations, the agreements require
irrevocable security reasonably acceptable to each Transmission Owner (for example, a letter of
credit, surety bond, or parent guaranty) in an amount equal to the capital cost of the covered
upgrades.158 The agreements allow the customer to request a reduction in security, subject to the
specified timing, documentation, and floor based on the remaining Minimum Contribution, and
the Transmission Owner may not unreasonably deny a request consistent with those provisions.
Under such terms, where the Large Load Transmission Customer and Transmission Owner are the
same legal entity, the Transmission Owner is not required to demand security of itself but it is still
subject to the requirement to protect against cost shifts. The security provisions in the agreements
exist to protect the Transmission Owner from financial risk associated with the capital costs of the
Large Load Network Upgrade(s) and Transmission Customers from related cost shifts, and in
analogous circumstances, the Commission has found it would be impractical and unnecessary to
require security.159
The Large Load Transmission Customer is required to provide security within 45 days of
the parties’ execution of the agreements.160 If the agreements are filed unexecuted or as non-
conforming, however, separate terms apply, depending on when the Commission approves such
agreement, as well as the nature of the parties’ dispute. Failure to provide security within the
applicable period results in immediate withdrawal of the Large Load Application.161
154 Gudeman Testimony at 24.
155 Proposed MISO Tariff, Attachment MMM, §§ IV.i—j.
156 Gudeman Testimony at 24-25; Proposed MISO Tariff, Attachment MMM, § V.
157 Gudeman Testimony at 25.
158 Proposed MISO Tariff, Attachment LLL, § 4.1; Proposed MISO Tariff, Attachment MMM, § VI.
159 See Midcontinent Indep. Sys. Operator, Inc., 156 FERC ¶ 61,166, at P 12 (2016); Gudeman Testimony at 19, 26.
160 Gudeman Testimony at 19, 25.
161 Proposed MISO Tariff, Attachment LLL, § 4.2; Proposed MISO Tariff, Attachment MMM, § VI.
PDF page 35
The Honorable Debbie-Anne Reese
November 16, 2026
Page 35
Upon the Transmission Owner’s request, the Transmission Owner and Large Load
Transmission Customer will enter into a separate agreement regarding construction of the covered
upgrades.162 Such separate agreements do not displace the customer’s obligation to enter into a
cost recovery agreement. Where the security’s form, terms, and provider permit, security posted
under a cost recovery agreement may satisfy the construction agreement’s security requirement.
Similarly, if the Large Load Transmission Customer provides security under a construction
agreement prior to providing the required security under the cost recovery agreement, the security
required under the construction agreement may be applied as the required security under the cost
recovery agreement if the forms, terms, and provider of the security under the construction
agreement allow it. Both pro forma agreements prohibit a lapse between the two arrangements
and prohibit requiring the customer to concurrently maintain the full security amount under both.
The pro formas also separately preserve applicable Tariff security and collateral requirements for
Transmission Service. The coordination provisions therefore address overlapping construction
security while retaining the payment obligations secured by the cost recovery agreement.
B. MISO Large Load Dashboard—Attachment FF, Section I.D.1.c.iv
To ensure that MISO addresses the transparency requirements identified in the Show Cause
Order, MISO is proposing Tariff language describing its commitment to sharing information
related to large load integration through a public dashboard. The Commission explained that it
was “concerned about the apparent lack of (1) transparency regarding the assignment of Network
Upgrades, and their associated costs, that are needed to provide transmission service to Eligible
Customers on behalf of large loads . . .”163 The proposed Tariff changes address the Commission’s
goals for transparency and information sharing.
MISO’s proposed Large Load dashboard will identify the Large Load Upgrades that are
needed and the costs associated with those upgrades. Transmission Owners must provide MISO
with information that may be publicly posted on its website including: 1) the aggregate amount of
proposed Large Load additions by Large Load Transmission Customers, including in each
Transmission Pricing Zone; 2) the planned Large Load Upgrades needed to provide the Large Load
Transmission Customer Transmission Service, identified by type of equipment and Large Load
Upgrade for each Large Load; and 3) cost estimates for those Large Load Upgrades.164 MISO’s
proposed Tariff language closely follows the requirements of the Show Cause Order to ensure
alignment with the Commission’s transparency requirements.165
In accordance with the requirements of the Show Cause Order, MISO will provide data
received from its Transmission Owners related to Large Load Upgrades on its public website and
162 Proposed MISO Tariff, Attachment LLL, § 4.2.1; Proposed MISO Tariff, Attachment MMM, § VI.b.
163 Show Cause Order at P 66.
164 Id. at P 77.
165 Compare Show Cause Order at P 77 with proposed Attachment FF, Section I.D.1.c.iv.
PDF page 36
The Honorable Debbie-Anne Reese
November 16, 2026
Page 36
in a format that is searchable and allows users to filter the data.166 These proposed Tariff additions
directly respond to the Commission’s request for “(1) robust, accurate, and systematic provision
of data on MISO’s website in a single location, and in an easily accessible format that is searchable
and allows users to filter the data, regarding the cost for Network Upgrades needed to provide
transmission service to Eligible Customers on behalf of large loads.”167 As MISO presented to
stakeholders in the LLWG, it is in the process of developing a Large Load Dashboard, which will
depict a map of MISO’s footprint and the location of the Large Loads along with their associated
Large Load Upgrades.168 The information displayed in the dashboard will be easily accessible on
MISO’s website and searchable by users looking to learn more information about large load
development in MISO’s footprint. The proposed Tariff requirements obligate Transmission
Owners to provide MISO with updated information regularly, with the specific timeframes to be
set forth in MISO’s BPM for Large Load.169
The dashboard, along with the cost recovery agreements and associated materials, will
provide a fuller picture of the costs associated with integrating Large Load in MISO’s footprint for
the public, and will provide a useful input to state and other retail regulatory authorities in
developing their own Large Load policies, rules, and regulations.
C. Just and Reasonable Treatment.
MISO and the MISO Transmission Owners submit that the proposed agreements address
the concerns identified in the Show Cause Order and support just and reasonable rates by
connecting each Large Load Upgrade to an enforceable minimum contribution from the Large
Load Transmission Customer. Put plainly, under the proposed framework, the Large Load
Transmission Customer is always responsible for the costs of the Large Load Network Upgrade(s),
thus, mitigating cost shifts to other Transmission Customers, consistent with the Show Cause
Order.170
166 Furnish Testimony at 25-26.
167 Show Cause Order at P 67.
168 MISO, Cost Shifting Risk Among Transmission Customers (LLWG-2026-8), Sept. 23, 2026, available at:
20260923 LLWG Item 05 Cost Shifting Risk Among Transmission Customers (LLWG-2026-8)783359.pdf.
169 This approach is consistent with the Rule of Reason given that the obligation is to update regularly and the specific
reporting cadence is an implementation detail best address through BPMs and adjusted based on experience and
the requirements of stakeholder. . See, e.g., Midcontinent Indep. Sys. Operator, Inc., 169 FERC ¶ 61,221, at P
67 2019 (2019) (citing Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103
(2018)) (describing the rule of reason).
170 Proposed MISO Tariff, Attachment LLL, §§ 3–5, 7.3; Proposed MISO Tariff, Attachment MMM, §§ III–VII;
Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, PP 78–85 (2026), errata notice, 196 FERC ¶ 61,123
(2026) (identifying the cost recovery, security, and revenue-credit concerns).
PDF page 37
The Honorable Debbie-Anne Reese
November 16, 2026
Page 37
V.
TRANSMISSION SERVICE OFFERINGS
A. Overview and service selection.
MISO proposes transmission service options that distinguish a customer seeking temporary
non-firm transmission service while progressing toward full NITS from a customer electing an
ongoing permanent firm and non-firm service mix. Firm Service Step Up (“FSSU”) permits NITS
service to increase as the required capability becomes available. Interim NITS permits
transmission service within approved non-firm limits while the remaining upgrades needed for full
NITS are completed.
The transmission service election determines the customer’s rights and obligations.
Firmness addresses the availability and priority of Transmission Service; Resource Adequacy
addresses the capacity needed to support demand. The proposal treats those questions separately.
Interim NITS remains in the capacity construct because it is a transition to full NITS service.
Neither election authorizes withdrawals beyond the quantities and operating conditions established
for that service.
B. Firm Service Step Up.
The FSSU process is designed to allow a Transmission Customer to obtain NITS in
increments before all upgrades supporting its ultimate NITS requirement have been completed.
As the relevant capability becomes available, a portion of the customer’s Interim NITS, described
further below, may convert to NITS while the remaining portion continues under the applicable
interim restrictions. The customer therefore can use available firm capability without assuming a
firm entitlement to the full quantity before the system can support that service.
The FSSU process is optional and allows NITS to be combined with Interim NITS. At
each step, the applicable firm NITS quantity remains tied to the capability supporting that step;
any remaining interim quantity continues to be subject to its non-firm, Interim NITS, limits. This
distinction preserves the integrity of the service actually available while accommodating a
customer’s phased development toward full NITS.171
FSSU provides speed to power because it enables faster integration of incremental amounts
of Large Load using firm service or Interim NITS. Ms. Xie explains that an FSSU request may
include a firm service component and Interim NITS component, allowing a portion of the
customer’s non-firm service to convert to firm service before all required Upgrades are complete,
with the remaining non-firm service continuing under the applicable Interim NITS operating
limits.172 The FSSU proposal thus provides an expeditious option to obtain firm service, at least
in part.
171 Xie at 21.
172 Id. at 20.
PDF page 38
The Honorable Debbie-Anne Reese
November 16, 2026
Page 38
C. Interim NITS.
The interim service developed through the Flexible Large-Load Interconnections and
Transmission Service (“FLITS”) stakeholder work is referred to here as Interim NITS. It allows
a Transmission Customer taking NITS on behalf of a Large Load to begin receiving an approved
quantity of non-firm service while the Network Upgrades required for full NITS are completed.
The service is part of the NITS framework and uses the Attachment F NITS Service Agreement
with a new exhibit for the Large Load, together with a corresponding Attachment G exhibit setting
out the additional operating criteria.173
The customer remains on a path to full NITS rather than selecting a permanent substitute
for NITS. When the required upgrades are completed and the conditions for full NITS are satisfied,
full NITS begins. Where FSSU is used, the interim agreement continues to govern the portion that
has not yet converted to firm service.
Charges for Interim NITS are determined under Schedule 9, and Interim NITS load is
treated as Network Load in almost all cases under the proposed design. An increase in the interim
load quantity is reflected in the applicable Attachment F exhibit, but updating the exhibit does not
establish additional system capability or authorize operation beyond the approved limit.
Cumulative load growth of at least 25 MW requires the applicable LLPR study.174
Interim NITS is subject to non-emergency operating restrictions and curtailment when
required by transmission conditions. During a Transmission Emergency, Interim NITS is curtailed
after non-firm Point-to-Point service but before NITS and Firm Point-to-Point Transmission
Service, and Firm GRITS. Interim NITS is not curtailed solely to mitigate economic congestion.
Its non-firm limits are tied to the transmission capability available before completion of the
Upgrades supporting full NITS.175
For Resource Adequacy, Interim NITS remains in the Coincident Peak Demand forecast
and subject to the existing capacity requirements. It consequently has the same priority as other
Load with Firm Transmission Service during a Capacity Emergency, subject to its separate
transmission limitations. This treatment preserves capacity demand and investment signals for
load progressing toward NITS and prevents interim non-firm transmission status from operating
as a capacity exemption.176
The non-firm portion does not receive Auction Revenue Rights (“ARR”) Entitlements and is
excluded from the applicable Peak Usage calculation. Firm load under the associated NITS
173 Xie at 7. See also MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service—Interim NITS
Option, LLWG-2026-5 (Sept. 23, 2026), stakeholder feedback request (identifying the FLITS work as addressing
the Interim NITS option).
174 Xie at 10.
175 Id. at 19.
176 Id. at 24.
PDF page 39
The Honorable Debbie-Anne Reese
November 16, 2026
Page 39
arrangement remains eligible under the existing rules. Interim NITS may register as a Load
Modifying Resource (“LMR”), subject to the applicable requirements, while its non-firm portions
are restricted from Demand Response Resource (“DRR”) and Emergency Demand Response
(“EDR”) participation. These distinctions preserve the relationship between the service quantity
and the market and congestion benefits associated with firm service.177
Interim NITS directly responds to the Commission’s preliminary finding that MISO’s Tariff
lacks transmission services reflecting Eligible Customers taking service on behalf of flexible Large
Loads willing and able to limit their use of the transmission system under certain conditions;178 it
aligns the Interim NITS customer’s charges, curtailment priority, Resource Adequacy obligations,
and market participation rights with its actual, interim non-firm use of the transmission system. In
addition, Interim NITS protects existing transmission customers from undue cost shifting by
requiring Interim NITS Load to be billed under Schedule 9 and to remain subject to existing
Resource Adequacy requirements, and it is time-limited and structurally integrated into the
existing NITS framework so that it functions as a genuine bridge to full firm service rather than a
permanent alternative. Interim NITS is not unduly discriminatory or preferential because it is
available on comparable terms.
D. Reliability and rate treatment.
The service options rely on enforceable withdrawal limits. Metering, telemetry, model
representation, communications, and operating controls provide the information and capability
needed to administer those limits. The Transmission Owner determines additional control
technologies or protection systems needed for the particular arrangement and for which the Large
Load Transmission Customer will be responsible, while MISO establishes the applicable service
requirements and communicates directives through the relevant parties. A commercial agreement
identifying a limit does not eliminate the need to make that limit observable and enforceable in
operations.179
The proposed operating framework provides for remote-disconnection procedures,
applicable unreserved-use consequences, and potential service termination when the customer
does not comply with a required restriction. Interim NITS participation as an LMR also remains
subject to the applicable LMR requirements and penalties. These provisions support the different
curtailment priorities and protect the reliability expectations associated with firm service. The
customer’s ability to obtain non-firm service depends on accepting the limitations that define that
service.
The resulting differences are grounded in the rights provided. Interim NITS remains
associated with full NITS and its capacity obligation while accepting transmission limits during
the transition. Limiting ARR benefits to firm quantities likewise preserves the existing connection
177 Id. at 25.
178 See Show Cause Order at PP 102, 104.
179 Xie Testimony at 11.
PDF page 40
The Honorable Debbie-Anne Reese
November 16, 2026
Page 40
between firm Transmission Service and the congestion entitlement associated with it. MISO
submits that these distinctions support just and reasonable treatment of the different service
arrangements.
VI.
LEGAL SHOWING AND RESPONSE TO THE SHOW CAUSE ORDER
Section 205 requires jurisdictional rates, charges, and the practices affecting them to be
just and reasonable and prohibits undue preferences and unreasonable differences in service. (16
U.S.C. § 824d(a)–(b)). MISO submits the proposed revisions under that standard. The proposals
respond to the Commission’s preliminary findings through the section 205 pathway expressly
contemplated in the Show Cause Order and the Abeyance Order. That procedural framework
permits MISO to bring forward developed proposals while the Commission retains authority to
address issues that the resulting filings do not resolve.180
The application and study concerns are addressed by the combination of LLPR and the
separately submitted IRR proposal. LLPR identifies what the customer must submit and how the
requested service is studied. IRR supplies the proposed Large Load definition and requirements
concerning visibility and operating performance. Their interaction connects the information used
in planning with the load behavior required after service begins. The agreement and operating
provisions then memorialize the obligations applicable to the resulting service.181
The transmission service concerns are addressed by the additional service choices
described in Section V. Interim NITS supplies a temporary non-firm path while the upgrades
needed for full NITS are completed. FSSU allows incremental conversion where firm capability
is available. The applicable operating limits, capacity treatment, and charges reflect the particular
rights accepted by the customer. This approach implements the Commission’s recognition that
service can account for a load’s willingness and ability to limit its use of the system.182
The initial availability of the new service options is directed to Large Loads within the
scope of this filing. MISO’s proposal focuses the service, study, modeling, and operational
changes on the category of load identified in the Show Cause Order. Customers electing the same
service are subject to its corresponding requirements. The focused implementation also permits
MISO to evaluate the consequences of broader eligibility before proposing that extension.183
The generator interconnection and associated load issues are addressed through the
complementary ZGIA and LARS pathways, read with the load’s applicable Transmission Service.
180 Show Cause Order PP 33–38 (describing the response framework and the opportunity to develop section 205
filings); Abeyance Order PP 8–11 (allowing the staged filings and preserving unresolved issues).
181 Show Cause Order PP 39, 48–65 (addressing application, study, operational, and agreement provisions); IRR
Transmittal at 1–4 (describing the proposed definition and operational requirements); Furnish Testimony at 16-
17, 22-23.
182 Show Cause Order PP 100–105 (addressing interim NITS, contract-demand service, and flexible load).
183 Xie Testimony at 21.
PDF page 41
The Honorable Debbie-Anne Reese
November 16, 2026
Page 41
ZGIA addresses qualifying same-substation zero injection arrangements, while LARS coordinates
the study of qualifying load and associated generation. Neither form of Interconnection Service
eliminates the separate need to identify the transmission and operating obligations of the load. The
proposed transmission service arrangements supply that additional part of the framework.184
The proposed framework also respects the allocation of responsibilities between federal
and state regulators. The filing addresses jurisdictional Transmission Service, generator
interconnection, and the associated planning and operating requirements. It does not displace state
authority over retail service or resource procurement and does not authorize retail arrangements
prohibited by applicable law. This distinction permits the transmission and interconnection
provisions to operate within the existing regional regulatory framework.185
MISO also submitted the July 20, 2026 Informational Report addressing resource adequacy
and initiatives to accelerate generation additions. That report described the roles of the states, load
serving entities, and MISO and identified both existing reforms and proposals under development.
The current filing complements those efforts by connecting the service election to the applicable
planning assumptions and capacity treatment; it does not equate transmission firmness with a
determination that capacity has been procured for the load.186
MISO requests that the Commission consider this submission together with the related
filings in evaluating the response to the Show Cause Order. The Abeyance Order provides that
timely section 205 filings addressing the preliminary findings suspend the filing respondents’
obligation to respond and continue the abeyance pending further direction. It also preserves further
consideration of issues not addressed by the filings.187
A. Existing commercial arrangements and transition.
Paragraph 123 of the Show Cause Order asks how implementation should account for
existing agreements and agreements nearing execution. The IRR filing addressed transition for
the reliability requirements proposed there. 188 The present application and service provisions
account for existing agreements and agreements nearing execution in several ways. First, the
LLPR process and requirements apply prospectively, with the first application deadline and LLPR
cycle targeted for implementation date of Q1 of 2027. Requests for transmission service to
184 ZGIA Transmittal at 1–2, 6–7 (describing the proposal’s scope and the matters reserved for further work); LARS
Transmittal at 3–6, 14–15 (describing coordinated load and generation studies and anticipated service provisions).
185 Show Cause Order PP 42–47, 68–70 (discussing the respective federal and state responsibilities); ZGIA
Transmittal at 22–23 (explaining that the associated-load provisions respect state restrictions on retail wheeling).
186 Informational Report at 1–4, 6–11 (responding to the informational requirement and describing resource adequacy
initiatives); Show Cause Order P 122 (requiring the report).
187 Abeyance Order PP 9–11 (describing continued abeyance and the specificity expected for a request to terminate
the proceeding in whole or in part).
188 Show Cause Order P 123 (requesting briefing on implementation and protection of existing commercial
arrangements); See MISO IRR filing, Docket No. ER26-3650, IRR Trans. Ltr. at 1 (identifying transition
provisions for the IRR proposal).
PDF page 42
The Honorable Debbie-Anne Reese
November 16, 2026
Page 42
accommodate Large Loads / study the Network Upgrades that have already commenced an EPR
study will remain subject to that process and the proposed Tariff revisions neither require not allow
projects that have already been processed through EPR or are in such process to transfer to the
LLPR process. This respects existing commercial arrangements. To the extent that a project has
not already been studied for its impacts to the Transmission System, the costs of its impacts are
not established and requiring such project to proceed through LLPR cannot disrupt established
expectations. Moreover, the LLPR study process is sufficiently similar to the EPR process in terms
of timing and scope that requiring nascent projects (i.e., those that have not been submitted for
study and costs established) will not introduce significant new delays or unfamiliar study practices.
Finally, with respect to the cost recovery agreements required for projects that complete LLPR,
MISO notes that such agreements, while imposing responsibilities on the Large Load Transmission
Customer, do not purport to invalidate or override any agreements that may exist between the
entity that owns the Large Load and the Large Load Transmission Customer, or prevent more
granular assignment of costs by a retail regulator.189 Thus, the process appropriately prevents
disruption to existing commercial arrangements and those nearing completion, while still ensuring
that Commission goals are met prospectively.
B. Effects on regional and local planning.
Paragraph 124 asks how the new services affect planning, including uncertainty concerning
the type, location, and quantity of flexible load. LLPR evaluates the service requested through
cumulative models coordinated with MTEP. Interim NITS remains associated with completion of
the facilities needed for full NITS. These distinctions allow planning to reflect the service
obligation rather than treat every maximum load quantity as an identical firm delivery
requirement.190
The separate firm and non-firm representation also makes the operational consequence of
the planning assumption identifiable. A customer receiving non-firm service remains bound by
its applicable reservation and withdrawal limits; a conversion to firm service depends on the
capability and approval supporting that conversion. The study and operating arrangements
therefore give effect to the same service election. The separate withdrawal review for committed
load further allows MISO to assess changes in the planning assumptions when a project does not
proceed.191
189 While MISO’s Tariff would make the Large Load Transmission Customer responsible for costs at the level of
the MISO Tariff, it does not purport to prevent a Large Load Transmission Customer from recovering funds
through commercial agreements with the Large Load.
190 Show Cause Order P 124 (identifying the planning questions); Furnish Testimony at 4-5, 12-14 (describing
cumulative models and MTEP coordination).
191 Furnish Testimony at 15-16.
PDF page 43
The Honorable Debbie-Anne Reese
November 16, 2026
Page 43
C. Cost recovery and financial security.
In response to Show Cause Order’s concern regarding cost shifting among transmission
customers related to large loads, MISO and the MISO Transmission Owners propose the Tariff
revisions and pro forma LL-CRA and ITO-CRA described in Section IV.A of this transmittal. As
explained above, consistent with the concerns identified by the Commission in the Show Cause
Order the proposed cost recovery agreements require “a specified minimum financial contribution
and financial security sufficient to secure such contribution,” thus mitigating cost shifting if the
Large Load Transmission Customer ultimately takes less Transmission Service than anticipated
because the Large Load does not materialize as planned or is not developed at all.192 Moreover,
as explained above and in Mr. Gudeman’s testimony, the Tariff and pro forma agreements ensure
that payments made by a Large Load Transmission Customer to the Transmission Provider under
the agreements will be appropriately credited toward Transmission Owners’ annual transmission
revenue requirements in the event such costs are rolled into the Transmission Owner’s rates
consistent with the Commission’s cost-of-service regulations.193 Lastly, the agreements provide
that Transmission Owner will provide a workpaper in the annual informational filing detailing how
any payments made pursuant to a cost recovery agreement are reflected in the Transmission
Owner’s transmission formula rate, or not recovered from Transmission Customers, as
applicable.194
In response to paragraph 125, MISO proposes the LL-CRA and ITO-CRA described in
Section IV.A as the contractual structures governing minimum cost contributions for the covered
upgrades. For rolled-in in-zone costs, the minimum is the Yearly Required Revenue Commitment
supported by the twenty-year incremental revenue calculation, with attributable transmission
revenues applied through the annual shortfall comparison. For rolled-in impacted-owner costs,
the minimum is the specified upgrade revenue-requirement payment over the applicable term.
Each agreement also permits direct assignment. The amount follows the upgrades identified for
the requested service and the documented customer responsibility, rather than a uniform dollar
charge applied to every Large Load.
The financial security provisions initially use upgrade capital cost, permit specified
adjustments and reductions, and provide draw and replenishment remedies. The construction-
security coordination provisions avoid concurrently requiring full security under both a CRA and
the corresponding construction agreement when compatible security can serve both.
The pro formas do not establish a general substitution right for a retail-level agreement
with the end-use Large Load. Their express coordination provisions address the separate
construction agreement’s security.
192 Show Cause Order at P 84.
193 See id. P 85.
194 Id.
PDF page 44
The Honorable Debbie-Anne Reese
November 16, 2026
Page 44
D. Alternative transmission technologies.
Paragraphs 62 and 126 address evaluation of alternative transmission technologies and the
explanation furnished when traditional upgrades are selected. The LLPR application includes the
Transmission Owner’s evaluation of alternative technologies and grid-enhancing technologies,
and MISO reviews that information together with any further needs identified in the cumulative
study. When transmission issues arise, MISO and the Transmission Owners evaluate possible
solutions in the mitigation process. The resulting study report identifies the selected transmission
solutions and the basis for the requested service.195
The proposed consideration of alternatives is directed to whether a solution will satisfy the
applicable planning criteria and provide a more efficient means of accommodating the request.
MISO has specifically incorporated consideration of alternative transmission technologies
(“ATTs”) and Grid Enhancing Technologies (“GETs”) as part of the LLPR. Proposed Attachment
FF Section I.D.1.c.iii.b.2 requires Large Load Transmission Customers to include with their
LLLPR Application the applicable Transmission Owner’s Interconnection Study Report,
specifically identifying what ATTs and GETs were considered and what the outcome of that
determination. Proposed Attachment FF, Section I.D.1.c.iii.e, which establishes the LLPR System
Impact Study, specifically provides that MISO may consider alternative solutions, including those
submitted by stakeholders. These solutions will include any ATTs or GETs identified by
stakeholders. Attachment FF, Section I.D.1.c.iii.e further provides that, in the event MISO
identifies any Tranmission Issues during the study, MISO will collaborate with the Transmission
Owners on the development of solutions, specifically including ATTs and GETS.
Together, these proposed Tariff revisions embed a requirement to consider ATTs and
GETS in the LLPR Study process and provide opportunities for stakeholders to suggest additional
GETS or ATTs not initially identified in the study. Because this consideration is a part of the LLPR
study, the basis for the proposed solution and alternatives considered will be included in the final
LLPR Study report.196 Because LLPR will be the required core process for evaluation of all
requests for Transmission Service to serve Large Loads, these requirements will apply uniformly
to new Large Loads.
MISO’s requested acceptance of those provisions is based on the evaluation and reporting
requirements, rather than a customer’s ability to request consideration of an alternative outside the
defined study process.197
195 Show Cause Order PP 62, 126; Furnish Testimony at 13-14, 31.
196 Furnish Testimony at 31 (explaining further that MISO will develop a standardized LLPR Study Report with
sections that specifically address ATT/GETs considerations).
197 Show Cause Order P 126 (addressing evaluation without a customer request, appropriate modeling, and the
explanation of feasibility, cost, and timing when traditional upgrades are selected).
PDF page 45
The Honorable Debbie-Anne Reese
November 16, 2026
Page 45
E. Generation participation and Resource Adequacy
Paragraph 127 addresses market participation and Resource Adequacy treatment of
generation serving co-located or electrically proximate load. The ZGIA filing proposed
participation as a Generation Resource, Dispatchable Intermittent Resource, Electric Storage
Resource, or Behind the Meter Generation resource, subject to the limitation associated with
serving the ZG Associated Load. It also proposed registration and operating-limit provisions that
provide visibility into gross load and generation and constrain the resource’s participation to the
applicable configuration.198
For capacity, the ZGIA proposal bases accreditation on participation type and limits it by
reference to the identified associated load, with the specified adjustment for avoided losses. It
provides for use of ZG Resource credits through a Fixed Resource Adequacy Plan or Reliability
Based Demand Curve Opt Out and restricts the use of uncleared and self-scheduled credits. Those
provisions reflect the limited reach of ZG Interconnection Service and avoid treating the resource
as though it could serve unrelated regional load.199
LARS follows a different interconnection pathway. The filing requests Network Resource
Interconnection Service, limits the requested interconnection service to 150 percent of the paired
load’s peak demand, and requires the load and generation to be located in the same Local Resource
Zone. MISO explained that these criteria connect the generation to the associated need while
allowing different fuel types and accreditation outcomes. The study evaluates the pair’s full
system impacts using the criteria applicable to other NRIS requests.200
VII.
DESCRIPTION OF PROPOSED TARIFF REVISIONS
The proposed revisions implement the application and service framework across the
relevant definitions, planning procedures, Transmission Service provisions, and agreements.
LLPR establishes the application requirements, study sequence, model review, study report, and
interfaces with MTEP and related study processes. The corresponding defined terms and
agreement provisions identify the request being studied, the responsible Transmission Customer,
and the requirements applicable when the resulting service is provided.201
The Transmission Service revisions establish the rights and conditions associated with
Interim NITS and FSSU. Interim NITS uses the existing Attachment F framework with the
additional service exhibit and corresponding Attachment G operating criteria. The related
198 Show Cause Order P 127(a)–(b) (identifying the generator participation and accreditation questions); ZGIA
Transmittal at 17–19, 22–23 (describing market registration, operating limits, and the proposed ZG Resource
definition).
199 ZGIA Transmittal at 18–20 (describing the proposed Module E-1 accreditation, forecast identification, FRAP, Opt
Out, and credit-use provisions).
200 LARS Transmittal at 10–11, 13 (describing the service, pairing, and study criteria and their relationship to
Resource Adequacy).
201 Furnish Testimony at 4, 11 (describing codification of the LLPR process).
PDF page 46
The Honorable Debbie-Anne Reese
November 16, 2026
Page 46
modeling, Resource Adequacy, and ARR provisions distinguish the firm and non-firm components
so that the same service election is reflected consistently in planning, operations, and settlements.
The marked and clean Tariff records submitted as Tab A and B respectively, set out the
revisions. The following table of Tariff revisions is provided for reference and informational
purposes only. The language filed in the proposed Tariff revisions shall control in the event of
any discrepancies between the information provided in this table and the proposed Tariff revisions.
Tariff Section
Tariff Section Title
Brief Description of Changes
Module A
1.B – Definitions - B
Update Baseload Usage to
include Firm Transmission
Service. Update Behind the
Meter Generation to add Interim
NITS as a service.
1.D – Definitions - D
Update Demand Response
Resource, Types I and II, to
include Firm Transmission
Service as an eligibility.
1.F – Definitions - F
Update Firm Service Step Up to
establish a process for evaluating
the reliability impact of planned
incremental Load additions
before full integration of a Large
Load whose planning study has
been approved through MTEP.
Update Firm Transmission
Service to cover Load served
under Firm Point-to-Point
Transmission Service or NITS
and exclude Load service on a
non-firm basis under Interim
NITs.
1.I – Definitions - I
Updates to Impacted
Transmission Owner Large Load
Network Upgrade(s) to cover
upgrades outside the
Transmission Pricing Zone
containing the Large Load’s
Point(s) of Withdrawal that
MISO identifies through Large
Load Project Review as
necessary for reliable service.
Update to Interim NITS to
provide for NITS reserved and
PDF page 47
The Honorable Debbie-Anne Reese
November 16, 2026
Page 47
scheduled on an as-available
basis and subject to curtailment
or interruption under Section
33.5. Updates to Interruptible
Load, which now deems the
portion of a Large Load served
under Interim NITS to be
Interruptible Load.
1.L – Definitions - L
Update to Large Load Network
Upgrade to cover upgrades
within the Transmission Pricing
Zone containing the Large
Load’s Point(s) of Withdrawal
that MISO identifies through
Large Load Project Review as
necessary for reliable service.
Update to Large Load
Transmission Customer to
include a Transmission Customer
taking or requesting
Transmission Service on behalf
of a Large Load. Update to Load
Zone to clarify that a Large Load
receiving Interim NITS must
represent its firm and non-firm
portions as separate Load Zones
and that neither zone may be
combined with other Loads.
1.N – Definitions - N
Update to Network Integration
Transmission Service to now
include Interim NITS under
Exhibit 4 of Attachment F unless
the Tariff expressly provides
otherwise. Update to Network
Load to now include all portions
of a Large Load taking Interim
NITS under Exhibit 4 of
Attachment F unless the Tariff
expressly provides otherwise.
Update to Non-Firm
Transmission Service to cover
Load served under Non-Firm
Point-To-Point Transmission
Service or Interim NITS under
Exhibit 4 of Attachment F.
PDF page 48
The Honorable Debbie-Anne Reese
November 16, 2026
Page 48
1.P – Definitions - P
Update to Peak Usage to exclude
the Interim NITS portion of a
Large Load from the forecast
NITS peak used to calculate Peak
Usage for ARR allocation. Load
associated with a Firm Service
Step Up request enters the
calculation only after all
associated upgrades are
complete.
1.T – Definitions - T
Update to Total Forecast Peak
Load to excludes Load served
through Interim NITS from the
forecast NITS peak. It also
excludes Load associated with a
Large Load’s Firm Service Step
Up request until all associated
upgrades are complete.
2.2 – Reservation Priority For Existing
Firm Transmission Service
Section 2.2 replaces references to
“firm service” customers with
references to customers taking
the newly defined “Firm
Transmission Service.” This ties
rollover priority and the right of
first refusal to qualifying firm
service and excludes the non-
firm portion of Interim NITS.
Module B
I. Introduction
Provides that a Large Load
Transmission Customer must
submit an application for LLPR
review for Transmission Service
to serve a Large Load as
described in Attachment FF.
III. Network Integration Transmission
Service
Provides that the rates, terms,
and conditions governing
Network Integration
Transmission Service will
generally apply to Interim NITS.
28.1 – Scope of Service
Provides that the Large Load
Transmission Customer taking
Interim NITS must coordinate
with the applicable Transmission
Owner to establish a Commercial
Pricing Node associated with the
PDF page 49
The Honorable Debbie-Anne Reese
November 16, 2026
Page 49
NITS service and a Commercial
Pricing Node associated with
Interim NITS service.
28.3 – Network Integration Transmission
Service
Proposes revisions to clarify that
the Transmission Provider and,
as applicable, ITC will provide
Network Integration
Transmission Service, rather than
Firm Transmission Service.
29.1 – Condition Precedent for Receiving
Service
Proposes a new framework for a
Large Load Transmission
Customer to take Interim NITs
and requiring that customer to
identify the Load that will
qualify for Firm Transmission
Service and the amount of Load
qualifying for Non-Firm
Transmission Service.
29.3 – Arrangements to be Completed
Prior to Service
Proposes revisions to clarify
when Firm Network Integration
Transmission Service and
Interim NITS will commence.
30.8 – Use of Interface Capacity by the
Network Customer
Adds a provision such that the
use of Interface capacity to
service the portion of a Network
Customer’s Network Load
served under Interim NITS shall
be on an as-available basis and
subject to all limitations,
Curtailment, and Interruption
provisions, and that inclusion of
such Load in the Load-based
usage limit does not confer a
right to firm use of Interface
capacity to serve that portion of
Load.
31.1 – Network Load
Provides that Network Load will
include all portions of a Large
Load served on a non-firm basis,
unless provided otherwise.
31.5 – Changes in Service Requests
Provides that a Large Load
Transmission Customer is
limited to one request to defer the
start of the Network Integration
Transmission Service up to a
PDF page 50
The Honorable Debbie-Anne Reese
November 16, 2026
Page 50
period of 90 days. Further
provides that, if the Large Load
does not commence operations or
fails to operate at the approved
level within 90 days of the
requested Service
Commencement Date, the
Transmission Provider may
revoke the approval for the
amount of Network Integration
Transmission Service that failed
to begin operation. Further
provides that the Large Load
Transmission Customer is not
relieved of its obligation to pay
the costs of the transmission
facilities caused to be
constructed.
31.7 – Deferral of Service to Large Loads
New section proposing the
deferral of service to Large
Loads until the construction of
new transmission facilities is
completed. Provides that the
Large Load Transmission
Customer may request Interim
NITS for the portion of any
deferred service, which the
Transmission Provider may defer
if it determines that providing
service would impair existing
Firm Transmission Service.
31.8 – Excess Withdrawal
New section proposing that the
Large Load Transmission
Customer may not schedule the
delivery of Energy to a Large
Load in excess of the Firm
Transmission Service that has
been approved for the Load
additions in the intervening step-
up period, and that any
withdrawal in excess of the
approved limit will be subject to
charges and penalties. Further
provides that a Large Load
Transmission Customer taking
PDF page 51
The Honorable Debbie-Anne Reese
November 16, 2026
Page 51
Interim NITS may not schedule
delivery of Energy to a Large
Load in excess of the aggregate
level of Firm Transmission
Service and Non-Firm
Transmission Service.
33.5 – Allocation of Curtailments
Proposes that Interim NITS will
have a lower priority than (i)
Firm Transmission Service and
(ii) Transmission Service from
Resources other than designated
Network Resources for Network
Customers not served under
Interim NITS. Among
transactions under Interim NITS,
Curtailments or Interruptions will
begin with the Large Load with
the most recent Service
Commencement Date.
33.7 – System Reliability
Proposes that the Transmission
Provider will be able to curtail
Interim NITS service for
reliability reasons and
implements penalties if the Large
Load Transmission Customers
fails to cease or reduce service in
response to such a directive. If
the Large Load Customer fails to
cease or reduce service on two
separate occasions within a 365-
day period, Interim NITS shall be
permanently terminated.
Module C
38.5 – Load Aggregation
Provides for limits on Load
aggregation and clarifies each
Large Load must be represented
by a single Commercial Pricing
Node and may not be aggregated
or included in a Load Zone with
other Commercial Pricing Nodes.
Further provides that a Large
Load taking both Firm and Non-
Firm Transmission Service will
have separate Commercial
Pricing Nodes for each service,
PDF page 52
The Honorable Debbie-Anne Reese
November 16, 2026
Page 52
with Actual Energy Withdrawal
first associated with the
Commercial Pricing Node for
Firm Transmission Service.
Further provides that the
Transmission Provider will
maintain a list of defined
Elemental Pricing Nodes that
comprise a Large Load.
38.6 – Aggregators of Retail Customers
Provides that ARC registration
will require an attestation by the
ARC that no part of the DRR,
LMR, or EDU is served through
Interim NITS. Further provides
that for each Large Load
registered by an ARC, the Large
Load Transmission Customer
must certify that the DRR, LMR,
or EDR is being registered at a
maximum Demand that is less
than or equal to the total amount
of Firm Transmission Service
provided to the Large Load.
Provides that a Large Load being
registered by an ARC may not be
included in an aggregation of
other Loads.
38.7.2 – Demand Response Resource
Procedures
Provides that only the portion of
a Large Load served by Firm
Transmission Service may
register as a Demand Response
Resource, and that the Market
Participant must demonstrate that
the portion of any Large Load
being registered as a Demand
Response Resource has Firm
Transmission Service.
42.6 – Partial-Year FTR Allocation
Process for New ARR Zone(s)
Proposes revisions to exclude the
portion of a Large Load taking
Interim NITS from Partial-Year
FTR Allocation processes.
43.2.4 – Nomination and Allocation of
ARRs and MTPS ARRs
Proposes revisions throughout
the section to exclude the portion
of a Large Load taking Interim
NITS from the nomination and
PDF page 53
The Honorable Debbie-Anne Reese
November 16, 2026
Page 53
allocation stages for Network
Integration Transmission
Service.
Attachments
Attachment F
Form of Service Agreement For Network
Service
New Exhibit 2 adds transaction
specification sheet for Large
Load NITS that records the
requested service, start date, and
required upgrades. It also
confirms that any local
Transmission Owner operating
requirements apply in addition to
the applicable Tariff
requirements, including Section
37A.
New Exhibit 3 adds a transaction
specification sheet for Firm
Service Step Up that records the
firm service level, start date, and
required upgrades for each
increment. Exhibit 4 adds a
separate sheet for Interim NITS
that records firm and non-firm
service levels and the start and
end dates for each transaction.
Attachment G
Form of Network Operating Agreement
for Network Service
Sections 3.0–5.0 set separate
commencement rules for firm
NITS and Interim NITS. Firm
NITS commencement is tied to
completion of the facilities and
upgrades required for the
applicable service, while Interim
NITS requires MISO approval
under new Exhibit F. The
agreement also provides for
service to end on a mutually
agreed date or the transaction
termination date.
New Exhibit F allows non-firm
Large Load identified in the Firm
Service Step Up study to operate
under Interim NITS before
required upgrades are complete,
PDF page 54
The Honorable Debbie-Anne Reese
November 16, 2026
Page 54
subject to Section 37A. MISO
may curtail that service for
reliability or operational reasons
under Module B.
Attachment FF
Transmission Expansion Planning
Protocol
Section I.D.1.c establishes the
LLPR process for new loads of
50 MW or more and existing
loads increasing by at least 25
MW in the aggregate. It provides
for three study cycles per year
and sets out application
requirements, deficiency and
cure procedures, model
development, system impact
studies, and stakeholder review.
Section I.D.1.c also establishes
how MISO tenders the final
study report and applicable cost
recovery agreements under
Attachments LLL and MMM. It
specifies when upgrades are
deemed approved for MTEP
purposes, requires customer
security for in-zone and out-of-
zone upgrades, and requires
MISO to post proposed load
additions, planned upgrades, and
estimated costs in a searchable,
filterable format.
Section I.D.3 establishes the
Firm Service Step Up study
process for incremental service
before full Large Load
integration. It limits
commencement to one
incremental block per year and
sets separate eligibility timing for
firm NITS and Interim NITS.
Both forms of incremental
service end when service for the
full Load begins.
PDF page 55
The Honorable Debbie-Anne Reese
November 16, 2026
Page 55
Attachments FF-9, FF-10, and
FF-11 add the Large Load
Transmission Customer
attestation, the LLPR System
Impact Study Agreement, and the
Critical Energy Infrastructure
Information nondisclosure
agreement, respectively.
I.D.1.c – Large Load Transmission
Service
Proposes a new framework for
Transmission Service to Large
Loads including the Large Load
Project Review (LLPR) process.
I.D.1.c.i – Definitions
Adds definitions for Large Load
Network Upgrade(s), Impacted
Transmission Owner Large Load
Network Upgrade(s), the Large
Load Cost Recovery Agreement
(LL-CRA, Attachment LLL), and
the Large Load Impacted
Transmission Owner Cost
Recovery Agreement (LLITO-
CRA, Attachment MMM).
I.D.1.c.ii – Large Load Project Review
Process Scope and Application
Establishes a Large Load
Application where different
service options may be selected
(LLPR, FSSU, Interim NITS, or
LARS).
I.D.1.c.iii – Large Load Project Review
Provides for MISO to
independently review the
reliability impacts of Large
Loads that require upgrades, in
collaboration with the
Transmission Owner(s) and
Large Load Transmission
Customer, with any system
modifications presented through
MTEP.
Triannual Studies
Requires LLPR studies three
times in a 365-day period with
application deadlines posted at
least 90 calendar days in
advance. Late applications will
be reviewed in the next cycle.
Requirements for LLPR Processing
Identifies the application
requirements including: data,
PDF page 56
The Honorable Debbie-Anne Reese
November 16, 2026
Page 56
study files, reports, an attestation,
non-refundable application fee,
relevant study deposits, and
confidentiality agreements.
Review and Cure of Application
Deficiencies
Sets out the period of time that
MISO has to review and identify
deficiencies in the Large Load
Application and defines the
period of time the Large Load
Transmission Customer has to
cure any deficiencies.
Model Build Period
Requires LLPR models to be
built from the latest MTEP cases,
with specific comment windows
and a target of completing within
30 calendar days after the cure
period.
The LLPR System Impact Study
Defines the scope of the study,
the posting of applications, and
deadlines for Transmission
Owners to propose solutions
(including ATTs/GETs);
applications are withdrawn if
issues remain unresolved. Also
provides for the draft and final
LLPR Study Reports and tender
of the LL-CRA/LLITO-CRA.
Resubmission of Large Load Applications
and Removed Projects
Allows a Large Load
Transmission Customer whose
application was removed to
resubmit in a future LLPR study
cycle after identifying what has
changed.
Stakeholder Forums
Requires MISO to host
stakeholder forums at least three
times per year, followed by
comment periods. Projects are
deemed approved once the LL-
CRA and/or LLITO-CRA is
executed or if unexecuted or non-
conforming, filed with the
Commission, and the
Transmission Owner must make
a good faith effort to implement
them.
PDF page 57
The Honorable Debbie-Anne Reese
November 16, 2026
Page 57
Pro Forma LL-CRA and LLITO-CRA
Requires a Large Load
Transmission Customer to enter
into a LL-CRA and/or LLITO-
CRA listing the required Large
Load Network Upgrades, to limit
cost shifting, and reduce
speculative requests. The
customer remains responsible for
all applicable Transmission
Service charges.
Large Load Cost Recovery Agreement
Imposes Minimum Contribution
for the Large Load Network
Upgrades. Also requires security
equal to the estimated upgrade
costs.
Large Load Impacted Transmission
Owner Cost Recovery Agreement
Requires a separate LLITO-CRA
with each affected Transmission
Owner, under which the Large
Load Transmission Customer is
responsible for a Minimum
Contribution for ITO-Large Load
Network Upgrades and security
to cover those upgrades.
Tender and Execution of the Cost
Agreement
Gives the parties 15 business
days to execute the tendered LL-
CRA/LLITO-CRA or request an
unexecuted or non-conforming
filing with the Commission; if
they do neither, then the Large
Load Application is deemed
withdrawn and the project is
removed from the LLPR process.
I.D.1.c.iv – Operations Agreement and
Confidentiality of LLPR Information
Requires an updated load
forecast and a NITS application
under Module B, Section 29.2
before service begins. Also
requires the parties to keep non-
public LLPR information
confidential under MISO’s
universal NDAs.
Attachment
FF-9
Large Load Project Review Attestation
Form
New Tariff attachment
Attachment
FF-10
LLPR System Impact Study Agreement
New Tariff attachment
PDF page 58
The Honorable Debbie-Anne Reese
November 16, 2026
Page 58
Attachment
FF-11
LLPR Critical Energy Infrastructure
Information NDA
New Tariff attachment
Attachment
LLL
Form of Agreement for Large Load Cost
Recovery Agreement
New Tariff attachment
Attachment
MMM
Large Load Impacted TO Cost Recovery
Agreement
New Tariff attachment
VIII.
STAKEHOLDER ENGAGEMENT
MISO developed the Large Load proposals described herein through an iterative
stakeholder process that began before issuance of the Show Cause Order. EPR improvements and
coordination of load and generator studies were discussed through the Planning Advisory
Committee and Planning Subcommittee during 2024 and 2025. ZGIA was introduced in
December 2025 and developed through a subsequent planning committee and LLWG discussions.
The LLWG then provided a dedicated forum for the planning, operations, markets, and Resource
Adequacy questions implicated by Large Load integration.202
The process included presentation of concepts, circulation of draft Tariff language, written
feedback, and further revisions. For example, the LARS proposal evolved from an initial 250 MW
threshold to the 200 MW threshold filed with the Commission following stakeholder feedback.
MISO also revised the proposed treatment of multiple generating facilities and contractual
arrangements and clarified the representation of the load-generation pair. These changes illustrate
the relationship between the stakeholder process and the proposals brought forward in the staged
filings.203
The LLPR application and transmission service proposals continued and were developed
through that process. At the September 23, 2026, LLWG meeting, MISO reviewed the LLPR and
identified the posted draft Tariff language, inviting feedback on the process and the proposed
provisions. MISO also presented the Interim NITS (initially presented as “FLITS”) option and
sought feedback on its design. Stakeholder comments addressed study readiness and timing,
planning coordination, service limits, curtailment, and the transition to firm service. These issues
informed the continuing work on the relationship among the application, study, and operating
provisions.204
202 ZGIA Transmittal at 45–46 (describing EPR, coordinated study, and ZGIA discussions); LARS Transmittal at 49–
50 (describing the LLWG’s role and early work plan).
203 LARS Transmittal at 50–52 (describing the July, August, and September discussions and the resulting changes to
the proposal).
204 MISO, LLWG, Application and Study Process Tariff and Process Design, LLWG-2026-7 (Sept. 23, 2026),
feedback request and comments posted Oct. 7–8, 2026 (identifying the draft LLPR review and stakeholder issues);
MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service—Interim NITS Option, LLWG-
2026-5 (Sept. 23, 2026), feedback request and comments posted Oct. 2, 2026 (addressing the interim service
design).
PDF page 59
The Honorable Debbie-Anne Reese
November 16, 2026
Page 59
MISO’s development of the present filing also reflects the need to coordinate the proposals
with the earlier submissions. The same load information and reliability assumptions must support
the study process, the service election, and the operating agreement. Stakeholder consideration of
those interfaces has therefore proceeded alongside development of the individual service and study
provisions.205
Throughout the stakeholder process, MISO solicited feedback on what approach should be
applied to developing processes and ensuring stakeholder protections. MISO proposed, accepted
feedback from stakeholders, and significantly modified many aspects of the Large Load effort. As
discussed below, some of the stakeholder process may be summarized in three categories: (1) cost
transparency and recovery; (2) LLPR; and (3) Interim NITS.
A. Cost Transparency and Recovery
In the initial LLWG meeting, MISO identified cost efficiency as one of twelve
considerations governing large-load integration.206 Stakeholder feedback proposed including cost
allocation within cost efficiency or treating it as an additional consideration.207 MISO agreed to
work with stakeholders to define solutions that fit within MISO’s scope.
As previously discussed, throughout January and May of 2026, stakeholders raised cost
transparency concerns while MISO concentrated on reliability requirements and expedited
205 Abeyance Motion at 8–13 (explaining the need to align individual solutions with one another and existing MISO
procedures); Abeyance Order P 8 (recognizing the opportunity for region-specific stakeholder solutions).
206 Available at:
https://cdn.misoenergy.org/20260130%20Large%20Load%20Workshop%20Presentation738349.pdf at 12.
207 Available at:
https://cdn.misoenergy.org/MISO%20Response%20to%20Large%20Load%20Workshop%20Considerations%2
0and%20Outcomes%20of%20Large%20Load%20Additions746069.pdf at 4, 13.
PDF page 60
The Honorable Debbie-Anne Reese
November 16, 2026
Page 60
interconnection processes.208 In June, the Show Cause Order identified deficiencies in MISO’s
Tariff concerning cost transparency and protections against cost shifting, but the Show Cause
Order was clear that it was not intended to disturb existing regional cost-allocation methods.209
In response to early stakeholder feedback and the Show Cause Order, MISO presented
LLWG-2026-8 during the August 27, 2026 LLWG meeting to address an approach to address
issues related to cost efficiency, transparency, and allocation.210 The issue covered a mechanism
to mitigate the risk of cost shifting among transmission customers, Tariff updates to create a public
data platform that provides transparency to state and local stakeholders regarding the assignment
of Network Upgrades and their associated costs. Stakeholder feedback requested more information
that estimated project costs. MISO committed to developing a dashboard and pro forma recovery
agreement while continuing to work to develop the minimum contribution formula.211
At the September 9, 2026, LLWG meeting, MISO previewed the public dashboard intended
to identify network upgrades associated with large load transmission service.212 Stakeholders
generally supported the dashboard but some suggested additional measures were needed to prevent
cost shifting.213
At the September 23, 2026, LLWG meeting, MISO introduced a conceptual pro forma cost
recovery agreement.214 MISO also illustrated how additional large load transmission revenue
could offset upgrade costs and how a supplemental payment might protect existing customers if
revenue were insufficient.
At the October 8, 2026, LLWG meeting, MISO provided additional details regarding the
proposed pro forma cost recovery agreement, including the calculation of minimum. MISO also
addressed the role of financial security and the treatment of payments through Transmission Owner
annual informational filings. Stakeholder feedback sought additional clarification regarding the
208 Available at: https://cdn.misoenergy.org/20260420%20LLWG%20Item%2001b%20Agenda750857.pdf;
https://cdn.misoenergy.org/20260514%20LLWG%20Item%2001b%20Agenda756827.pdf.
209 Show Cause Order at P 82.
210 Available at : https://cdn.misoenergy.org/New%20Issue%20-
%20Cost%20Shifting%20Risk%20Among%20Transmission%20Customers776496.pdf.
211 Available at:
https://cdn.misoenergy.org/LLWG%20Cost%20Transparency%20and%20Cost%20Shifting%20Response%20(
LLWG-2026-8)%20(20260827)786923.pdf.
212 Available at:
https://cdn.misoenergy.org/20260909%20LLWG%20Item%2005%20Cost%20Shifting%20Risk%20Among%2
0Tx%20Customers%20Cost%20Transparency%20(LLWG-2026-8)779833.pdf.
213 Available at:
https://cdn.misoenergy.org/LLWG%20Cost%20Shifting%20Risk%20Among%20Transmission%20Customers-
Cost%20Transparency%20Response%20(LLWG-2026-8)%20(20260909)789797.pdf.
214 Available at:
https://cdn.misoenergy.org/20260923%20LLWG%20Item%2005%20Cost%20Shifting%20Risk%20Among%2
0Transmission%20Customers%20(LLWG-2026-8)783359.pdf at 5-10.
PDF page 61
The Honorable Debbie-Anne Reese
November 16, 2026
Page 61
calculation of the minimum contribution, the treatment of network upgrade costs, financial security
requirements, and the interaction between the proposed agreement and existing transmission
rates.215
At the October 29, 2026 LLWG, meeting, specifically, in response to earlier feedback,
MISO and the Transmission Owners clarified that the Large Load Transmission Customer is
always responsible for the costs of the Large Load Upgrade(s) to mitigate the cost shifts to other
Transmission Customers and changed the amount of financial security to be the capital cost of the
Large Load Upgrade(s). MISO also described how it will provide transparency through a
combination of the outputs from the Large Load Project Review, the pro forma cost recovery
agreement, Transmission Owner annual informational filings, and a transparency dashboard.216
MISO revised payments to be prorated for staggered upgrade in service dates and addressed
separated agreements for impacted Transmission Owners outside the relevant transmission pricing
zone. Additionally, the revised dashboard added Project Description and Cost Shared Status fields.
Other updates in response to stakeholder feedback include the financial security holder, security
amounts, security forms, and cost updates. Feedback is now complete but suggests that the
revisions addressed some stakeholder concerns.217
B. LLPR
At the August 27, 2026, LLWG meeting, MISO proposed a new Large Load Project
Review (“LLPR”) process to integrate requirements from the Show Cause Order, incorporate
enhancements from broader large-load efforts, and preserve the core functions of reliable
integration.218 The initial design called for quarterly study cycles, cumulative MTEP studies, and
continued monthly stakeholder meetings. Stakeholder feedback expressed concerns about
commercial confidentiality and premature contract commitments.219
At the September 23, 2026, LLWG meeting, MISO proposed a refined approach after
receiving stakeholder feedback, including replacing the Electric Service Agreement with an
215 Available at:
https://cdn.misoenergy.org/20261008%20LLWG%20Item%2004%20Cost%20Shifting%20Show%20Cause%20
%28LLWG-2026-8%29786862.pdf at 4–8; https://www.misoenergy.org/engage/stakeholder-
feedback/2026/llwg-cost-shifting-risk-pro-forma-cost-recovery-agreement-llwg-2026-8-20261008/.
216 Available at:
https://cdn.misoenergy.org/20261029%20LLWG%20Item%2004%20Cost%20Shifting%20Risk%20Among%2
0Transmission%20Customers%20(LLWG-2026-8)791917.pdf at 2.
217 Available at: https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-cost-shifting-risk-among-
transmission-customers-llwg-2026-8-20261029/.
218 Available at:
https://cdn.misoenergy.org/20260827%20LLWG%20Item%2005%20Large%20Load%20Application%20and%
20Study%20Process%20(LLWG-2026-7)777233.pdf.
219 Available at:
https://cdn.misoenergy.org/LLWG%20Large%20Load%20Application%20and%20Study%20Process%20Respo
nse%20(LLWG-2026-7)%20(20260827)786659.pdf.
PDF page 62
The Honorable Debbie-Anne Reese
November 16, 2026
Page 62
attestation, tailoring studies to the type of transmission service requested, preserving the EPR for
other projects, and proposed Tariff language.220 MISO also committed to a standardized report
covering assumptions, upgrades, costs, schedules, and Advanced Transmission Technologies and
Grid-Enhancing Technologies.221
At the October 29, 2026, LLWG meeting, MISO presented a final LLPR process with
application. The LLPR included application, study, mitigation, reporting, and approval
frameworks, as well as three annual study cycles, expanded readiness requirements and draft Tariff
revisions.222
C. Interim NITS
MISO’s development of Firm Service Step-Up (“FSSU”) and Flexible Large-Load Interim
Transmission Service, which was initially referred to as FLITS but is herein referred to as Interim
NITS, reflects two related efforts to allow large loads to receive power which can be reliably
transmitted before all transmission upgrades needed for full firm service are completed. The two
proposals developed separately but became interconnected as MISO responded to stakeholder
feedback and the Show Cause Order.
In April 2026, MISO recommended the Firm Service Step-Up initiative for consideration
by the LLWG.223 At the April 20, 2026, LLWG meeting, MISO proposed a process to evaluate
and grant firm service for partial load interconnection.224 The initial proposal was for a phased
firm-service. Feedback indicated that stakeholders generally supported a process to assess and
grant firm service to facilitate the timely interconnection in large loads, but some pointed to a need
for flexibility in how service level was granted.225 Other feedback opposed annual only studies,
and some raised the possibility of non-firm service for a facility that might want some flexible load
indefinitely. The feedback established a need for multiple incremental steps and more flexible
220 Available at:
https://cdn.misoenergy.org/20260923%20LLWG%20Item%2004%20Tariff%20Defined%20Application%20an
d%20Study%20Process%20(LLWG-2026-7)782743.pdf.
221 Available at:
https://cdn.misoenergy.org/LLWG%20Application%20and%20Study%20Process%20Tariff%20and%20Process
%20Design%20Response%20(LLWG-2026-7)%20(20260923)791576.pdf.
222 Available at:
https://cdn.misoenergy.org/20261029%20LLWG%20Item%2006%20Large%20Load%20Application%20and%
20Study%20Process%20(LLWG-2026-7)791445.pdf.
223 Available at: https://www.misoenergy.org/engage/MISO-Dashboard/firm-service-step-up-for-large-load-
interconnections/.
224 Available at:
https://cdn.misoenergy.org/20260420%20LLWG%20Item%2008%20Firm%20Service%20Step%20Up%20Ove
rview751418.pdf.
225 Available at:
https://cdn.misoenergy.org/MISO%20Feedback%20Response%20Firm%20Service%20Step%20Up%20(LLWG
-2026-1)%20(20260420)760062.pdf.
PDF page 63
The Honorable Debbie-Anne Reese
November 16, 2026
Page 63
service timing, and MISO committed to developing further details in the process to provide clarity
at the June LLWG.
At the June 10, 2026, LLWG meeting MISO presented further details on the Firm Service
Step Up process.226 MISO proposed quarterly study opportunities to identify how much firm load
could be served reliability before all necessary upgrades were complete.227 MISO’s proposed
process was more defined. It now allowed requests through Transmission Owner and Load
Serving Entity coordination following MTEP approval, the ability to request several incremental
load blocks, and a 36-month horizon. Feedback also indicated that MISO had largely responded
to the need for more frequent studies and multiple steps but was adapting the proposal for
upcoming stakeholder meetings. Some stakeholders expressed concern whether requested in-
service dates could distort priority.
At the July 16, 2026, LLWG meeting, MISO presented a refined FSSU process and initial
Tariff language.228 A Bridge Interim Transmission Service Proposal was also presented by a
stakeholder.229 MISO proposed to update the FSSU process and proposed to clarify terminology,
define the step-up period, and adopt additional requirements. The proposed Tariff language
restricted requested load blocks to a minimum 25 MW step, limited to the number of network
upgrade projects associated with the original full load integration study. MISO proposed a 36-
month request horizon, and limits on additional upgrades and restudies. Stakeholder feedback
focused on provisions to correct terminology, a timing requirement for transmission service
requests, and limiting incremental load blocks on an annual basis.
At the August 12, 2026, LLWG meeting, MISO reviewed the initial proposal for a
framework for Non-Firm Transmission Service for Large Loads called Flexible Large-load
Interconnection and Transmission Service (FLITS).230 FLITS was proposed as a non-firm
transmission service option for large loads, usable either temporarily while upgrades were
completed or on a more permanent basis. The proposal contemplated separate interim and
permanent non-firm transmission service and worked alongside existing NITS and FSSU
arrangements. MISO received a variety of feedback, though most stakeholders desired to see non-
226 Available at:
https://cdn.misoenergy.org/20260610%20LLWG%20Item%2007%20Firm%20Service%20Step%20Up%20Stud
y%20Process763098.pdf.
227 Available at:
https://cdn.misoenergy.org/LLWG%20Large%20Load%20Firm%20Service%20Step%20Up%20Approach%20
Response%20(LLWG-2026-1)%20(20260610)769664.pdf.
228 Available at:
https://cdn.misoenergy.org/20260716%20LLWG%20Item%2008%20Firm%20Service%20Step%20Up%20Stud
y%20Process768776.pdf.
229 Available at:
https://cdn.misoenergy.org/20260716%20LLWG%20Item%2007c%20BITS%20Proposal_Alliant%20Energy76
8542.pdf.
230 Available at: https://cdn.misoenergy.org/20260812%20LLWG%20Item%2006%20Conditional%20Non-
Firm%20Transmission%20Service%20(LLWG-2026-5)774185.pdf.
PDF page 64
The Honorable Debbie-Anne Reese
November 16, 2026
Page 64
firm large load included in the Coincident Peak Demand forecast. Others raised concerns over
congestion prices, cost shifting, curtailment priority and other issues.
At the August 27, 2026, LLWG meeting, MISO proposed revised Tariff language for the
FSSU process. In response to stakeholder feedback, MISO included terminology corrections,
clarifications of requirements, limiting number of steps on an annual basis, and new requirements
for submitting transmission service and load forecasts.
On September 9, 2026, LLWG meeting, MISO posted a summary of stakeholder feedback
taken into consideration to improve the design for non-firm Transmission Service.231 MISO
reported that 12 respondents, including the OMS, supported including non-firm load in capacity-
demand forecasts, compared with two favoring exclusion and four requesting further discussion.
MISO also corrected an error in its August presentation regarding settlement modeling. MISO
reported receiving 23 submissions and made several other identifiable changes.
Incorporating this feedback, MISO also presented at the September 9, 2026, LLWG
meeting, where MISO proposed changes to FLITS in response to stakeholder feedback.232 In
response to feedback, MISO split the concept into interim FLITS and permanent Contract Demand,
included all load in the Coincident Peak Demand forecast, removed the fixed ramp rate and
required curtailment in a time specified by MISO.
At the September 23, 2026, LLWG meeting, MISO presented changes to the FLITS
proposal.233 MISO revised ARR entitlements to no longer be granted to the non-firm portion of
the load and did not propose special rules for large loads in the Resource Adequacy construct.
MISO also announced that it continued to develop a permanent non-firm Transmission Service
option.
MISO responded to stakeholder feedback by revising Attachment FF provisions for clarity,
correcting redundant sections, and reorganizing provisions related to transmission service.234
MISO also stated that BPM language was being developed to describe the study process and
criteria details at the implementation level.
231 Available at: https://cdn.misoenergy.org/Flexible%20Large-
Load%20Interconnection%20and%20Transmission%20Service%20(FLITS)%20Response%20(LLWG-2026-
5)780398.pdf.
232 Available at:
https://cdn.misoenergy.org/20260909%20LLWG%20Item%2006%20Non%20Firm%20Large%20Load%20(LL
WG-2026-5)780125.pdf.
233 Available at: https://cdn.misoenergy.org/20260923%20LLWG%20Item%2007%20Conditional%20Non-
Firm%20Transmission%20Service%20(LLWG-2026-5)783425.pdf.
234 Available at:
https://cdn.misoenergy.org/LLWG%20Firm%20Service%20Step%20Up%20for%20Large%20Load%20Interco
nnections%20Tariff%20Response%20(LLWG-2026-1)%20(20260923)792368.pdf.
PDF page 65
The Honorable Debbie-Anne Reese
November 16, 2026
Page 65
At the October 29, 2026, LLWG meeting, MISO presented proposed revisions to BPM-
020 addressing the FSSU study process, including study parameters, evaluation criteria, Interim
Network Integration Transmission Service, and Qualified Changes. MISO also presented
revisions to the LLPR framework, including application requirements, study timelines, reliability
assessments, identification of Network Upgrades, and coordination with Transmission Owners.
MISO requested additional stakeholder feedback on both proposals to further refine the
processes and implementation procedures.
IX.
DOCUMENTS SUBMITTED IN THIS FILING
In addition to this Transmittal Letter, this submission includes the following materials, with
the final tab and exhibit designations identified in the filing index:
Tab A – Redline Tariff235
Tab B – Clean Tariff
Tab C – Testimony of Jeanna Furnish
Tab D – Testimony of Zhaoxia Xie
Tab E – Testimony and Exhibits of Greg M. Gudeman
Tab F – Show Cause Order Briefing Questions and Answers
X.
EFFECTIVE DATE AND REQUEST FOR WAIVER
MISO requests that the proposed revisions become effective 90-days from the date of filing
(i.e., February 14, 2027).
MISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. §
35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable
requirement of 18 C.F.R. Part 35 for which waiver is not specifically requested, if necessary, in
order to permit Commission acceptance of this filing.
235 Language currently pending before the Commission in the following, unrelated dockets is highlighted in yellow:
ER26-3552-000; ER26-3650-000; and ER27-25-000. MISO requests that the Commission treat such highlighted
language as subject to the outcome of those pending proceedings. If needed, MISO commits to file any revisions
to this highlighted language as necessary to comply with any Commission orders in the proceeding.
In addition, MISO has not included language that has future effective dates of 6/1/2027, 9/1/2027, and 6/1/2029,
under Docket Nos. ER26-1882-001, ER25-1886-000, and ER22-1640-003;-006, respectively. MISO has also
removed language that has a future effective date of 6/12/2028 and is pending in Docket No. ER26-2825-000. If
needed, MISO commits to file any revisions to comply with any Commission orders in these proceedings and
MISO commits to make subsequent filings with the Commission to reflect the most up-to-date version of the
then-current Tariff provisions prior to the effective dates of the language.
PDF page 66
The Honorable Debbie-Anne Reese
November 16, 2026
Page 66
XI.
COMMUNICATIONS
MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of
Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the
designation of more than two persons for service on behalf of MISO in this proceeding and requests
all communications related to this filing be directed to:
For MISO:
For MISO:
Michael Kessler
Managing Assistant General Counsel
Christopher D. Supino
Managing Senior Corporate Counsel
Midcontinent
Independent
System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400
mkessler@misoenergy.org
csupino@misoenergy.org
James C. Holsclaw
Lauren A. Stenger
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com
lastenger@calfee.com
For MISO Transmission Owners:
Wendy N. Reed
Anna Fernandez
Wright & Talisman, P.C.
1200 G Street, N.W
Suite 600
Washington, D.C. 20005
Telephone: (202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
XII.
NOTICE AND SERVICE
MISO has served a copy of this filing electronically, including attachments, upon all Tariff
customers, MISO Members, Member representatives of Transmission Owners and non-
Transmission Owners, as well as all state commissions within the MISO Region and the
Organization of MISO States. The filing has been posted electronically on MISO’s website at
https://www.misoenergy.org/legal/ferc-filings/ for other parties interested in this matter.
MISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. §
35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable
requirement of 18 C.F.R. Part 35 for which waiver is not specifically requested, if necessary, in
order to permit Commission acceptance of this filing.
PDF page 67
The Honorable Debbie-Anne Reese
November 16, 2026
Page 67
XIII.
CONCLUSION
For all of the foregoing reasons, MISO respectfully requests that the Commission accept
this filing and grant waiver of any Commission regulations the Commission deems in order for the
Commission to accept it as proposed.
Respectfully submitted,
/s/ Michael Kessler
Michael Kessler
Managing Assistant General Counsel
Christopher D. Supino
Managing Senior Corporate Counsel
Midcontinent Independent System
Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400
mkessler@misoenergy.org
csupino@misoenergy.org
James C. Holsclaw
Lauren A. Stenger
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-4266
jholsclaw@calfee.com
lastenger@calfee.com
Attorneys for the Midcontinent Independent
System Operator, Inc.
Wendy N. Reed
Anna Fernandez
Wright & Talisman, P.C.
1200 G Street, N.W
Suite 600
Washington, D.C. 20005
Telephone: (202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
Attorneys for the MISO Transmission Owners