ER27-526-000 · 2026-11-16 · Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners

MISO and its transmission owners file large-load review, cost recovery and transmission service revisions under section 205

Back to sections and commentary

PDF page 1

Midcontinent Independent 
System Operator, Inc. 
317.249-5400 
www.misoenergy.org 
720 City Center Drive 
Carmel, Indiana 46032 
2985 Ames Crossing Road 
Eagan, Minnesota 55121 
1700 Centerview Drive 
Little Rock, AR 72211 
 
Michael Kessler 
Managing Assistant General Counsel 
Direct Dial:  317-753-9434 
Email:  mkessler@misoenergy.org 
 
November 16, 2026 
 
VIA ELECTRONIC FILING 
 
The Honorable Debbie-Anne Reese  
Secretary 
Federal Energy Regulatory Commission 
888 First Street, NE 
Washington, DC  20426 
 
Re: 
Midcontinent Independent System Operator, Inc.’s  
Large Load Review, Cost Recovery and Transmission Services Filing 
Docket No. ER27-___-000 
 
Dear Secretary Reese: 
 
The Midcontinent Independent System Operator, Inc. (“MISO”), and the MISO 
Transmission Owners1 through this filing,2 submit proposed revisions to its Open Access 
Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”),3 concerning the 
integration of Large Loads.4  This omnibus filing describes the proposals MISO has already 
 
1  
The MISO Transmission Owners for this filing consist of: AEP Indiana Michigan Transmission Company; 
Ameren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois 
Company d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; Arkansas Electric Cooperative 
Corporation; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens Electric 
Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland 
Power Cooperative; Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric 
Cooperative, Inc.; Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New 
Orleans, LLC; Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural 
Electric Cooperative, Inc.; Indiana Municipal Power Agency; International Transmission Company d/b/a ITC 
Transmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric Transmission Company, LLC; 
MidAmerican Energy Company; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company LLC; 
Prairie Power, Inc.; Republic Transmission, LLC; Southern Illinois Power Cooperative; Southern Indiana Gas & 
Electric Company (d/b/a CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency; 
Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc. 
2  
This filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Part 35 of 
the regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. § 35.1, et 
seq. 
3  
Unless otherwise indicated by the text or context of this transmittal letter, all terms used herein have the definitions 
set forth in Module A of the Tariff. 
4  
The MISO Transmission Owners join this filing for the purpose of exercising their filing rights and supporting 
the filing of the Large Load Cost Recovery Agreement and the Large Load Impacted Transmission Owner Cost 
Recovery Agreement.  Consistent with the MISO Transmission Owners Agreement, a majority of the MISO 
Transmission Owners voted in favor of filing the Large Load Cost Recovery Agreement and the Large Load

PDF page 2

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 2 
 
submitted in response to the Federal Energy Regulatory Commission’s (“Commission”) June 18, 
2026, Show Cause Order5 and presents additional proposals in response to that order that have 
been developed as MISO obtained the information and completed the design work necessary to 
bring those components forward.6 
 
MISO’s response has proceeded through a series of related filings addressing different 
aspects of Large Load integration.7  The Zero Injection Generator Interconnection Agreement 
(“ZGIA”), Interconnection Reliability Requirements for Large Loads (“IRR”), and Large Load 
Addition Resource Study (“LARS”) proposals addressed components that were ready for 
Commission review while work continued on the application, transmission service, and financial 
provisions needed to address the remaining issues.  This filing explains how those proposals fit 
together with the further revisions described below.8 
 
The additional revisions addressed here9 establish the Large Load Project Review 
(“LLPR”) process and provide transmission service options reflecting a Large Load’s intended use 
of the Transmission System, including a Firm Service Step Up (“FSSU”) process to evaluate the 
availability of Network Integration Transmission Service (“NITS”), and Interim Network 
Integration Transmission Service (“Interim NITS”).  In addition, and as part of the LLPR process, 
MISO and its Transmission Owners propose Tariff revisions and two pro forma cost recovery 
agreements (the Large Load Cost Recovery Agreement and Large Load Impacted Transmission 
Owner Cost Recovery Agreement), which are designed to mitigate the risk of cost shifting among 
 
Impacted Transmission Owner Cost Recovery Agreement.  See Agreement of Transmission Facilities Owners To 
Organize The Midcontinent Independent System Operator, Inc., A Delaware Non-Stock Corporation, Rate 
Schedule FERC No. 1, Appendix K § II. 
5  
Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,123 (2026) (“Show Cause Order”) (identifying the issues 
concerning large and co-located loads that are the subject of the section 206 proceeding).   
6  
16 U.S.C. § 824d; 18 C.F.R. §§ 35.3, 35.13 (2026). 
7  
As proposed in MISO’s IRR filing, a Large Load is defined as “Load with Demand of 50 MW or more associated 
with any facility or aggregation of facilities located at a single substation behind one or more Point(s) of 
Withdrawal from the Transmission System that is owned, operated, or controlled by: (a) a single entity, or (b) a 
group of entities that will coordinate with respect to the profile of the Load.  Large Load does not include Load 
used exclusively for charging an Electric Storage Resource.”   
8  
MISO, Transmittal Letter, Zero Injection Generator Interconnection Agreement, Docket No. ER26-3552-000, at 
1–2, 5–7 (Aug. 18, 2026) (“ZGIA Transmittal”) (reserving transmission service and electrically proximate load 
issues for later proposals); MISO, Transmittal Letter, Interconnection Reliability Requirements for Large Loads, 
Docket No. ER26-3650-000, at 1, 4 (Aug. 28, 2026) (“IRR Transmittal”) (identifying additional study, service, 
and cost protection work); MISO, Transmittal Letter, Large Load Addition Resource Study, Docket No. ER27-
25-000, at 14–15, 20–21 (Oct. 2, 2026) (“LARS Transmittal”) (anticipating further transmission service and cost 
protection provisions). 
9  
This transmittal letter frequently quotes proposed Tariff revisions to facilitate its explanation.  In the event of a 
conflict between the Tariff language as discussed in this letter and that reflected in the attached Tariff sheets, 
MISO intends that the language in the attached Tariff sheets control.

PDF page 3

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 3 
 
Transmission Customers  resulting from a Transmission Customer’s taking of Transmission 
Service on behalf of a Large Load.10 
 
MISO requests that the Commission accept the proposed revisions effective 90 days from 
the date of this filing (i.e., February 14, 2027).  MISO recognizes this filing includes significant 
Tariff revisions and introduces new processes and cost recovery mechanisms that impact the 
broader stakeholder community.  In response to OMS and other stakeholder requests for MISO to 
support an extended comment period, MISO proposes a 30-day comment period to allow 
stakeholders sufficient time to evaluate and comment on the proposals being presented in this 
filing.  This extended comment period reasonably balances the need for additional time for 
stakeholder review while maintaining the urgency presented by the Show Cause Order and works 
well within MISO’s requested 90-day effective date request.  
 
I. 
EXECUTIVE SUMMARY 
 
MISO to date has been able to successfully manage the integration of large loads leveraging 
existing MISO tools and quickly recognized the need for additional frameworks and processes to 
support reliable, efficient, and cost-effective integration given projected trends for f faster and 
dramatic demand growth across the region.  To this end, MISO, its Transmission Owners, state 
regulatory authorities, and broad stakeholder community have been working collaboratively to 
support the reliable, cost-effective, and efficient integration of large loads.  Over the past two years 
MISO has been developing new processes and tools to provide additional transparency, efficient 
reliability standardization, integrated solutions for generation and new transmission service 
offerings with stakeholders to meet the challenge.  The MISO Large Load Working Group has 
been an effective clearing house for such efforts and is providing a constructive, collaborative 
forum to develop these solutions.  This group met over thirteen times in the last eight months with 
an average of 400 people and a peak of 1000 people participating in each session.  This process 
included over 100 MISO presentations to stakeholders and over 400 feedback responses from 
stakeholders. 
   
MISO recognizes the need for balanced solutions to support the diverse interests of 
stakeholders and state policies across the MISO region.  While these differing perspectives can 
make unanimity- difficult to achieve, they contribute to a robust stakeholder process and better-
informed outcomes that ultimately drive the enormous value that MISO membership brings to 
customers in terms of reliability, cost-effectiveness and policy enablement. 
  
The Commission’s Show Cause Order provided important support for MISO’s ongoing 
efforts to develop solutions for responsible and reliable integration of large loads.  By identifying 
specific priorities and encouraging incremental filings as solutions matured, the Commission 
established a framework that enabled stakeholders and MISO to advance improvements without 
waiting for a single comprehensive package. 
 
10  Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and 
Attachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery 
Agreement).

PDF page 4

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 4 
 
 
In response, MISO has already filed several proposals responsive to the Show Cause Order 
that are currently pending before the Commission, including Zero Injection-GIA, Large Load 
Interconnection Reliability Requirements, and the Load Additions Resource Study.  Collectively 
these filings represent meaningful progress toward more timely, transparent, reliable, and cost-
effective large load integration, which appropriately mitigates cost shifts to other Transmission 
Customers.   
  
The additional package of solutions in this filing and the companion filing11 complement 
MISO’s pending Large Load filings and directly address the remaining concerns identified in the 
Show Cause Order.  MISO’s filings, in the aggregate, reflect its compliance with the timelines and 
scope of the Show Cause Order.  At the same time, MISO recognizes that Large Load integration 
will continue to evolve.  These filings represent an important milestone, not an endpoint.  MISO 
remains committed to further enhancing its planning, operational, and market frameworks as 
experience is gained and system needs grow.  The Large Load Working Group will continue to 
serve as the primary stakeholder forum for evaluating, developing and refining additional solutions 
to support ongoing integration of Large Loads across the MISO region. 
  
The filings before the Commission are the product of an extremely robust, albeit expedited, 
stakeholder process conducted within the timelines established by the Show Cause Order.  MISO 
advanced solutions that incorporated substantial stakeholder feedback while remaining consistent 
with MISO’s filing rights and jurisdictional responsibilities.  MISO worked closely with its 
Transmission Owners to develop this joint filing and appropriately recognize their respective roles, 
rights, and responsibilities.  MISO also engaged the Organization of MISO states through regular 
discussions throughout the development of this package of filings.  
 
While full alignment was not achieved on every aspect of the proposals, stakeholder and 
state regulator input materially informed the resulting framework.  MISO is confident that the 
collective set of filings before the Commission provides state regulators with additional 
transparency, information and tools to help fulfill their responsibilities to retail electricity 
customers, consistent with the objectives outlined in the Show Cause Order.  The solutions also 
preserve flexibility for states to advance their individual policy objectives, including the use of 
detailed information and analyses provided through MISO’s planning and operational processes. 
 
The proposals included in the filing provide a robust foundation for integrating Large 
Loads in a manner that supports reliability, protects Transmission Customers from cost shifts 
related to new Large Loads, and provides additional transmission service options consistent with 
the Commission’s objectives for co-located loads, behind the meter generation arrangements and 
flexible Large Loads.  Specifically, this filing addresses the following elements identified in the 
Show Cause Order: 
 
 
11  MISO is contemporaneously submitting its Grid Responsive Integration Transmission Services (“GRITS”) 
proposal as a separate FPA Section 205 filing. The GRITS filing addresses the Show Cause Order requirement 
that MISO evaluate the need for both firm and non-firm contract demand transmission service.

PDF page 5

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 5 
 
• Large Load Project Review (LLPR) – The LLPR establishes a comprehensive application 
and evaluation process to assess the grid impacts associated with Transmission Service 
needed to serve proposed Large Loads, including required Network Upgrades and 
associated costs.  The LLPR also includes deposits, project milestones, and other 
safeguards designed to discourage speculative Large Load requests.  
• Large Load Transparency Dashboard – The results of the LLPR periodically will be 
published to provide transparency into the location and estimated costs associated with 
Large Load facilities in the MISO region, while protecting confidential information. 
• Cost Shifting Risk Among Transmission Customers – MISO and the MISO Transmission 
Owners have developed new Tariff language and pro forma cost recovery agreements 
designed to ensure that the costs incurred to provide Transmission Service to Large Load 
Transmission Customers, including the costs of Large Load Upgrades (defined herein), are 
born by such customers and thereby avoid unfair cost shifts among Transmission 
Customers.  The agreements leave retail regulatory authorities able to further disaggregate 
costs as warranted. 
• Additional Transmission Services – The new Transmission Services available to Large 
Loads include Firm Service Step Up and Interim Non-Firm NITS service.  These offerings  
build off existing NITS service and support the timely integration of Large Loads by 
aligning Transmission Service with a Transmission Customer’s projected buildout and 
operational needs, while providing flexibility in how Transmission Service is obtained 
during different stages of development. 
 
MISO appreciates the guidance provided by the Commission in the Show Cause Order and 
believes this filing, together with the companion GRITS filing, and MISO’s other pending Large 
Load filings fully addresses the concerns identified by the Commission.  Taken together, these 
proposals represent a significant advancement in framework supporting Large Load integration, 
building on processes and tools that MISO has already implemented.   
 
At the same time, MISO recognizes that the rapid growth of Large Loads will continue to 
present new challenges and opportunities.  As a result, these filings should be viewed as an 
important milestone rather than an endpoint. MISO remains committed to working collaboratively 
with stakeholders, Transmission Owners, states and the Commission to evaluate and develop 
additional tools, processes, and solutions to support the reliable, efficient, transparent and cost-
effective integration and operation of Large Loads in the MISO region.  
 
II. 
BACKGROUND  
 
This omnibus filing brings together the history and substance of MISO’s response to the 
Commission’s Show Cause Order.  MISO has pursued that response through a series of related 
filings, submitting individual proposals as the necessary information, stakeholder consideration, 
and proposed Tariff provisions became sufficiently developed.  The earlier submissions addressed 
components that were ready to proceed while work continued on other elements of the response.  
This filing explains that progression, describes the relationship among the proposals already

PDF page 6

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 6 
 
submitted, and presents the additional provisions that have since been developed.  The background 
below traces how that coordinated effort led to the present submission. 
 
A. The changing nature of load growth in the MISO region. 
 
The MISO region is experiencing a change in the scale, concentration, and pace of new 
electricity demand.  Large Load additions, including data centers and advanced manufacturing 
facilities, can introduce substantial demand at a single location and seek service on schedules that 
are shorter than those traditionally required to develop supporting generation and transmission 
infrastructure.  These developments require MISO, the Transmission Owners, and the entities 
serving those Loads to coordinate planning, investment, and operational requirements early in the 
development process to address the unique needs associated with such Large Load additions to the 
grid.  As MISO explained in its July 20, 2026, Informational Report, conventional forecasting 
methods were developed for more gradual and geographically dispersed growth; Large Load 
projects present additional uncertainty concerning location, timing, and the demand that ultimately 
materializes.12 
 
The resulting challenge extends beyond identifying a physical point of connection.  MISO 
must assess the transmission facilities needed to serve new demand, understand how the Load will 
behave during normal operations and system disturbances, and coordinate the addition of resources 
needed to support resource adequacy.  At the same time, the uncertainty surrounding Large Load 
development makes it necessary to distinguish committed projects from speculative requests and 
to address the risk that investments made to serve a particular load may remain unrecovered if that 
Load is delayed, reduced, or does not materialize.  MISO’s Large Load initiatives were developed 
to address these related planning, reliability, and cost recovery concerns.13 
 
MISO has also recognized that certain Large Loads may be willing and able to limit their 
withdrawals from the Transmission System.  That flexibility can support service before all 
facilities needed for full firm service have been completed, or an ongoing arrangement under which 
only a portion of the Load receives firm service.  Accommodating those different needs requires 
clear service rights, enforceable operating limits, and appropriate treatment of the customer’s 
planning and financial obligations.  The development of additional Transmission Service options 
therefore became a component of MISO’s broader Large Load work. 
 
B. MISO’s existing processes and the development of a dedicated stakeholder forum. 
 
MISO’s efforts to address these challenges began before the Commission issued its Show 
Cause Order.  MISO had improved the Expedited Project Review (“EPR”) process within the 
 
12  MISO, Informational Report, Docket No. EL26-70-000, at 1-2 (July 20, 2026) (“Informational Report”); MISO, 
Transmittal Letter, Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650-000, at 2-
3 (Aug. 28, 2026) (“IRR Transmittal”). 
13  Informational Report at 1-3; Motion of MISO to Hold Proceeding in Abeyance and Request for Shortened 
Comment Period and Expedited Treatment, Docket No. EL26-70-000, at 2-5, 8-9 (Aug. 3, 2026) (“Abeyance 
Motion”).

PDF page 7

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 7 
 
MISO Transmission Expansion Plan (“MTEP”) to facilitate timely study and approval of 
transmission upgrades needed for large load additions.14  On the generation side, MISO developed 
the temporary Expedited Resource Addition Study (“ERAS”) process to accelerate the 
interconnection of resources addressing identified near-term resource adequacy and reliability 
needs.15  These initiatives provided a foundation for additional tools tailored to the pace and 
characteristics of large load development.16  Those expedited processes addressed important near-
term needs, but MISO recognized that additional provisions were necessary to address the broader 
relationship among load additions, generation development, transmission service, and system 
operations.   
 
MISO also began consolidating stakeholder consideration of large load issues.  Following 
a January 2026 Large Load Additions Workshop, MISO’s Steering Committee approved creation 
of the Large Load Working Group (“LLWG”) in March 2026.  The LLWG held its first meeting 
on April 20, 2026, providing a dedicated forum for issues spanning markets, reliable operations, 
planning, and resource adequacy.  Its early work included Interconnection Reliability 
Requirements, Firm Service Step Up arrangements, and the Zero-Injection Generation 
Interconnection proposal.  This work brought previously related but separately considered issues 
into a coordinated large load work plan.17 
 
C. The Show Cause Order and the opportunity to develop regional solutions. 
 
On June 18, 2026, the Commission instituted a proceeding under section 206 of the Federal 
Power Act (“FPA”) to examine whether MISO’s Tariff remained just and reasonable in light of 
various concerns related to large and co-located load development.  The Commission identified 
concerns regarding application and study procedures, operational requirements, network upgrade 
cost transparency and recovery, service for flexible and co-located loads, and generation serving 
associated Loads.  It directed MISO and the Transmission Owners to respond to its preliminary 
findings and address potential Tariff changes.18 
 
The Commission’s action reinforced work already underway while identifying additional 
matters for stakeholder consideration.  The Show Cause Order also contemplated development of 
regional solutions through FPA section 205 filings and allowed requests for an abeyance of up to 
 
14  Furnish Testimony at 17-18.  
15  MISO, Transmittal Letter, Expedited Resource Addition Study, Docket No. ER25-2454-000 (June 6, 2025) 
(“ERAS Transmittal”).  
16  Abeyance Motion at 3-4; Informational Report at 6-7; MISO, Transmittal Letter, Zero Injection Generator 
Interconnection Agreement, Docket No. ER26-3552-000, at 4-6 (Aug.  18, 2026) (“ZGIA Transmittal”). 
17  Abeyance Motion at 3-4 & n.6; MISO, Transmittal Letter, Large Load Addition Resource Study, Docket No. 
ER27-25-000, at 49-50 & nn.102-108 (Oct.  2, 2026) (“LARS Transmittal”). 
18  Midcontinent Indep.  Sys.  Operator, Inc., 195 FERC ¶ 61,212, PP 1-3, 33-39 (2026), errata notice, 196 FERC ¶ 
61,123 (2026) (“Show Cause Order”); Midcontinent Indep.  Sys.  Operator, Inc., 196 FERC ¶ 61,133, P 1 (2026) 
(“Abeyance Order”).

PDF page 8

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 8 
 
90 days for that purpose.  MISO pursued that opportunity to coordinate the existing initiatives with 
additional proposals responsive to the Commission’s concerns.19 
 
On July 20, 2026, MISO submitted the Informational Report addressing resource adequacy 
and initiatives to accelerate the addition of generation to serve emerging demand.  The Report 
explained the respective roles of states, load serving entities, and MISO in supporting resource 
adequacy and described both existing reforms and additional proposals under development.  It 
identified a zero injection interconnection process and a parallel study framework for associated 
load and generation as complementary approaches to facilitating timely service while accounting 
for system needs.20 
 
On August 3, 2026, MISO requested that the proceeding be held in abeyance for 90 days.  
The Abeyance Motion described a series of anticipated section 205 filings covering Zero-Injection 
Interconnection Service, a Large Load definition and Interconnection Reliability Requirements, 
coordinated Load and generation studies, Firm Service Step Up arrangements, and additional 
service options for flexible Loads.  It also identified further work on application and study 
procedures and Upgrades cost transparency.  MISO explained that the proposals needed to operate 
together and fit within MISO’s existing planning, interconnection, and service processes.21 
 
The Commission granted the requested abeyance on August 14, 2026.  It found that the 
described stakeholder process would provide an opportunity to consider region-specific solutions 
and held the proceeding, including the responses and briefing questions, in abeyance for 90 days.22  
The Commission established November 16, 2026 as the revised response deadline and explained 
that a timely FPA section 205 filing addressing its preliminary findings would suspend the filing 
respondents’ obligation to respond and continue the abeyance pending further Commission 
direction.  The Commission further explained that any issues not addressed by the FPA section 
205 filings would remain subject to the FPA section 206 proceeding instituted under the Show 
Cause Order and encouraged respondents seeking termination to identify specifically which 
proposed revisions resolved which concerns.23 
 
D. The earlier filings and the matters reserved for further development. 
 
During the abeyance period, MISO submitted proposals addressing those elements of its 
response that were sufficiently developed for Commission review.  Those submissions did not 
purport to resolve every issue in a single filing.  Instead, they advanced particular components 
while expressly identifying related matters for further development and subsequent submission.  
The resulting sequence provides important context for this omnibus filing: the present submission 
 
19  Show Cause Order P 37; Abeyance Motion at 4-5, 7-9; Abeyance Order PP 3-5. 
20  Informational Report at 1-4, 10-11.  The Report responded to the informational reporting requirement in Show 
Cause Order P 122. 
21  Abeyance Motion at 3-5, 8-13. 
22  Abeyance Order at PP 8-9.  
23  Id. at PP 8-11.  The Order established December 16, 2026, as the deadline for answers to responses.  Id.  P 9.

PDF page 9

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 9 
 
both accounts for the proposals already filed and advances additional portions of the response that 
were not ready for submission at those earlier stages.24 
 
First, on August 18, 2026, MISO submitted its Zero Injection Generator Interconnection 
Agreement (“ZGIA”) proposal in Docket No. ER26-3552-000.  The filing proposed a form of 
Generator Interconnection Agreement, a study process, and an agreement for generation serving 
Load at the same substation without broader injections onto the Transmission System.  MISO had 
begun developing the concept before the Show Cause Order and refined it through stakeholder 
discussion.  MISO limited the initial proposal to same-substation arrangements so that the zero 
injection option could proceed while the separate questions presented by generation serving 
electrically proximate Load were addressed through further work.25  The ZGIA proposal was 
deliberately limited in scope.  This distinction is relevant to the present filing because a generator 
interconnection pathway alone does not supply the complete Transmission Service and cost 
recovery framework for the Load it serves.26 
 
Second, on August 28, 2026, MISO submitted its Interconnection Reliability Requirements 
(“IRR”) for Large Loads proposal in Docket No. ER26-3650-000.  That proposal included a Tariff 
definition of Large Load and requirements addressing data, models, telemetry, forecasting, and 
operational visibility, together with phasor measurement, ramp, and ride-through requirements for 
Computational Loads.  MISO proposed to place the applicable obligations on the Transmission 
Customer taking service on behalf of the Large Load, reflecting that customer’s direct relationship 
with MISO.  The proposal was intended to improve MISO’s ability to assess, observe, and manage 
Large Load behavior.27  The IRR filing also distinguished requirements applicable to the 
Transmission Customer taking Transmission Service on behalf of the Large Load from the study 
procedures used to identify system-level impacts and necessary transmission solutions.  MISO 
explained that it already performed stability assessments through MTEP and EPR but would 
address enhancements to the broader Load addition and Transmission Service study processes in 
a later FPA section 205 filing.  The IRR proposal thus supplied the proposed operational 
requirements to be incorporated into, and assessed through, the developing study framework.28 
 
Third, on October 2, 2026, MISO submitted its Large Load Addition Resource Study 
(“LARS”) proposal in Docket No. ER27-25-000.  LARS proposed a coordinated process for 
studying qualifying Load additions of at least 200 MW and associated new generation.  The 
proposal built upon experience with expedited load-side planning and coordinated the Load and 
generation studies through a common application framework.  It complemented ZGIA by 
 
24  ZGIA Transmittal at 1-2, 5-7; IRR Transmittal at 1, 4; LARS Transmittal at 3-4, 15, 20-21. 
25  ZGIA Transmittal at 1-2, 6-7.  MISO requested an October 18, 2026, effective date.  Id.  at 2.  This paragraph 
describes the submitted proposal; it does not state that the Commission accepted the proposal or its requested 
effective date. 
26  ZGIA Transmittal at 2, 7; LARS Transmittal at 3-4. 
27  IRR Transmittal at 1-4.  MISO requested a December 4, 2026 effective date.  Id.  at 2.  This paragraph describes 
the proposal as submitted. 
28  IRR Transmittal at 4.

PDF page 10

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 10 
 
addressing qualifying Load and generation arrangements beyond the narrower same-substation, 
zero injection configuration.29  LARS also reflected the iterative nature of the stakeholder process.  
MISO introduced the coordinated study concept at the July 16, 2026 LLWG meeting and sought 
feedback on eligibility, readiness, and protections against speculative requests.  The proposal 
evolved from an initial 250 MW eligibility concept to the 200 MW threshold submitted to the 
Commission.  MISO’s LARS transmittal further anticipated a subsequent filing addressing the 
Load study process, Transmission Service, and cost recovery provisions needed to complete other 
elements of the Large Load framework.30 
 
E. The additional provisions now presented in this omnibus filing. 
 
While the ZGIA, IRR, and LARS proposals proceeded through separate filings, MISO 
continued developing the remaining application, study, service, and financial provisions.  Those 
matters required additional information and coordination concerning how customers would request 
service, how the necessary upgrades would be identified, what obligations would support the 
resulting investment, and what service could be provided under differing operating conditions.  
The present filing brings forward those additional proposals and explains how they relate to the 
components previously submitted. The proposed LLPR process builds on the load-specific 
functions of EPR to establish a dedicated Tariff framework for a Transmission Customer taking 
service on behalf of a Large Load to obtain Transmission Service. The LLPR includes standardized 
applications, recurring study cycles, identification of necessary Upgrades, and the integration of 
the proposed interconnection reliability requirements.31  While only Transmission Owners were 
eligible to submit requests to the EPR process, MISO is proposing that only Large Load 
Transmission Customers (in collaboration with the Transmission Owner) may submit an 
application to the LLPR process.  
 
The cost recovery and transparency provisions ensure the Large Load Transmission 
Customer pays the cost of the Large Load Upgrades required to provide Transmission Service, 
including if the expected Load does not arrive as anticipated or remain in service.  The proposed 
cost recovery agreements, related security, and cost transparency measures are intended to connect 
the requested Transmission Service and necessary supporting investment with enforceable 
financial obligations.  The proposed framework includes Tariff revisions and a pro forma Large 
Load Cost Recovery Agreement, and a pro forma Large Load Impacted Transmission Owner Cost 
Recovery Agreement, together with a publicly accessible dashboard providing high-level 
information about upgrades and estimated costs while protecting confidential information.32 
 
 
29  LARS Transmittal at 1-6; see also Combined Notice of Filings No. 1, 91 Fed.  Reg.  64,362 (Oct.  8, 2026) (Docket 
No. ER27-25-000; Oct.  2, 2026 filing; requested Dec.  2, 2026 effective date). 
30  LARS Transmittal at 3-4, 15, 20-21, 49-52. 
31  Furnish Testimony at 3; see Section D.1.c.ii-iii. 
32  Furnish Testimony at 21-23; Abeyance Motion at 12-13.  Detailed recovery, security, and accounting provisions 
remain subject to confirmation against the final pro forma agreements and supporting testimony.

PDF page 11

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 11 
 
The service proposals address the separate question of how a customer may use the 
Transmission System once the relevant studies and prerequisites have been satisfied.  The 
proposed Interim Network Integration Transmission Service (“Interim NITS”) provides a non-firm 
Transmission Service option for participation of a Load progressing toward full firm Network 
Integration Transmission Service (“NITS”) prior to the completion of required Upgrades.  The 
proposal also includes an optional Firm Service Step Up for loads progressing toward full firm 
service.  These alternatives are intended to recognize different operating capabilities and 
development schedules while specifying the associated withdrawal limits, curtailment conditions, 
and customer obligations. 
 
Accordingly, this omnibus filing should be considered in the context of the full sequence 
of MISO’s submissions in response to the Show Cause Order.  The earlier filings addressed 
components that could be brought forward first; the proposals submitted here reflect the further 
development of the application, study, cost recovery, transparency, and service provisions 
described above.  Together, that history explains both the timing and the scope of the present filing.  
The sections that follow identify the relief sought, describe the additional Tariff revisions proposed 
here, and explain how this submission and the previously filed proposals comprehensively address 
the Commission’s concerns identified in the Show Cause Order. 
 
III. 
LARGE LOAD APPLICATION AND STUDY PROCESS 
 
In the Show Cause Order, the Commission directed MISO develop an “application process, 
study procedures, and ongoing operational requirements that apply to Eligible Customers seeking 
transmission service on behalf of large loads.”33  The Commission recognized that MISO and the 
MISO Transmission Owners may have existing Load integration processes that included studies 
for Transmission Service to Large Loads but sought documentation of clear and consistent 
procedures in MISO’s Tariff that address the characteristics and challenges associated with 
interconnecting Large Loads in order to avoid disputes about how studies will be conducted, deter 
speculative or duplicative requests for Transmission Service to serve Large Loads, and help avoid 
excessive and unnecessary Upgrades.34 MISO has worked with the Transmission Owners, 
developers of Large Loads, and other stakeholders to develop the Large Load Project Review 
(“LLPR”) process proposed herein.  LLPR provides a clear and consistent study process that will 
be required for evaluating all requests for Transmission Service to serve Large Loads.35  The LLPR 
process addresses the goals of the Show Cause Order by providing a clear and consistent study 
process that is tailored to the needs and challenges associated with Large Load integrations and 
which provides the necessary framework for implementing the other Large Load reforms sought 
by the Show Cause Order.36  The LLPR is also a uniform process that provides increased speed 
and certainty to Large Load Transmission Customers in identifying the Network Upgrades needed 
 
33  Show Cause Order at P 3.  
34  Id. at PP 49, 55-57. 
35  Furnish Testimony at 3-4.  
36  Id. at 20-21.

PDF page 12

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 12 
 
to provide Transmission Service to Large Load Transmission Customers.37  LLPR also promotes 
accountability, deters speculative or duplicative requests for Large Load-driven requests for 
Transmission Service, and provides transparency regarding the Large Load-driven Network 
Upgrades and their associated costs.  
 
In response to concerns raised by the Commission, MISO and the MISO Transmission Owners 
propose Tariff revisions and two pro forma cost recovery agreements that together require the 
Transmission Customer seeking to take Transmission Service on behalf of a Large Load (“Large 
Load Transmission Customer”) to make a minimum financial contribution toward the revenue 
requirement of the Transmission Owners responsible for constructing the Upgrades identified by 
MISO in the LLPR, including financial security sufficient to secure such contribution.38  These 
proposed Tariff changes and agreements, which are a condition precedent to MTEP approval, 
impose cost responsibility and accountability on Large Load Transmission Customers consistent 
with the Commission’s direction in the Show Cause Order and provide transparent identification 
of the Network Upgrades made necessary by Large Loads, including their estimated costs.39  LLPR 
is an expedited process designed to be completed in approximately five months.  To simplify the 
explanation of the LLPR process, MISO describes the key definitions, the Large Load Application, 
and the required steps in the LLPR study process in the sections below.  
 
A. New Definitions for the LLPR Process 
 
MISO includes several new definitions in Attachment FF to its Tariff, which are needed to 
provide a working vocabulary for implementing the LLPR process.40  These terms are summarized 
below: 
 
• Large Load Network Upgrades are the additions, modifications, and upgrades to 
be made to the Transmission System that are located inside the Transmission 
Pricing Zone containing the POW for the Large Load that are necessary for MISO 
and the Transmission Owner to operate and maintain the Transmission System in a 
safe and reliable manner.  
• Impacted Transmission Owner Large Load Network Upgrades are the 
additions, modifications, and upgrades to be made to the Transmission System that 
are located outside the Transmission Pricing Zone containing the POW for the 
Large Load that are necessary for MISO and the Transmission Owner to operate 
and maintain the Transmission System in a safe and reliable manner. 
 
37  MISO is proposing to add a new definition to Module A to define Large Load Transmission Customer as the 
Transmission Customer that is taking Transmission Service on behalf of a Large Load.  
38  See Tab E Testimony and Exhibits of Greg M. Gudeman (“Gudeman Testimony) (describing the pro forma cost 
recovery agreements). 
39  Furnish Testimony at 5.  
40  In the transmittal letter, MISO paraphrases the LLPR process definitions, but the full definitions of each of these 
terms may be found in Section D.1.c.i of Attachment FF.

PDF page 13

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 13 
 
• The Large Load Cost Recover Agreement (“LL-CRA”) is the primary 
agreement that establishes the Large Load Transmission Customer’s cost 
responsibility for Large Load Network Upgrade(s), which are located in the 
Transmission Pricing Zone containing the POW for the Large Load. 
• The Large Load Impacted Transmission Owner Cost Recovery Agreement 
(“LLITO-CRA”) is the agreement that establishes the Large Load Transmission 
Customer’s cost responsibility for the Impacted Transmission Owner Large Load 
Network Upgrades, which are located outside of the Transmission Pricing Zone 
containing the POW for the Large Load.   
 
The two different kinds of upgrades are distinguished by whether they are located inside 
the Transmission Pricing Zone (“TPZ”) or outside of the TPZ containing the POW for the Large 
Load.41  Similarly, the LL-CRA and LLITO-CRA establish cost recovery terms based on the 
location of the Upgrades, inside or outside the TPZ.  As discussed in more detail later, this 
agreement framework is necessary for costs to be properly assigned throughout MISO’s 
Transmission System.   
 
Together, these terms enable the creation of processes and requirements that recognize the location 
on the Transmission System of Large Load Upgrades identified through the LLPR process, 
identify their connection to Large Loads, and establish the applicable parties to the proposed 
agreements under MISO’s Tariff.42 
 
B. Applicability and Participant Responsibilities. 
 
MISO’s existing study processes require supplementation and enhancement in order to 
efficiently and effectively address the growth in Large Load development over the past couple of 
years.  LLPR builds from and adapts MISO’s existing Expedited Project Review (“EPR”) process 
and will be the required core study process for all requests for Transmission Service made on 
behalf of or in order to serve Large Loads.  Specifically, the LLPR process will apply to all requests 
for Transmission Service for Large Loads, as defined in MISO’s Interconnection Reliability 
Requirements (“IRR”) filing, including the load components of LARS which is an aligned 
transmission and interconnections service requests for very large loads (200 MW or greater) paired 
with the generation that will serve it.43   
 
41  To facilitate efficient explanation, MISO uses the term “Large Load Upgrades” to embrace both “Large Load 
Network Upgrades” and “Impacted Transmission Owner Large Load Network Upgrades,” reserving use of the 
specific defined term for where context requires it.  
42  MISO notes that nothing in LLPR interferes with the ability of states and other retail regulators to impose 
additional conditions, further allocate cost responsibility and risk among and between retail customers and Load 
Serving Entities, or require further agreements involving parties not directly taking service under MISO’s Tariff 
(e.g., data centers and other owners of Large Loads). 
43  MISO’s LARS proposal, currently pending in Commission Docket ER27-25-000, provides a specialized process 
designed to study very large (≥200 MW) Large Loads accompanied by the generation that will serve it on a 
coordinated timeline.  MISO has committed to updating the load study portion of LARS to Incorporate the LLPR 
process and requirements proposed herein once these are accepted.

PDF page 14

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 14 
 
 
MISO envisions different parties playing diverse roles in the LLPR process.  First, the 
Large Load Transmission Customer, commonly the LSE, plays a key role in the LLPR process as 
it is the party that can request Transmission Service through LLPR from MISO.  The Transmission 
Owner has an integral role in working with the parties on studies.  The entity that owns the Large 
Load, while usually not directly subject to MISO’s Tariff, will play an essential role in providing 
the information needed to support the LLPR Application and working with the Transmission 
Customer to determine the type of Transmission Service to request.44  Finally, MISO, as the 
Transmission Provider, acts as coordinator, performing the required LLPR studies, administering 
the LLPR process and, ultimately, approving transmission projects and granting Transmission 
Service.   
 
Transmission Customers seeking to participate in LLPR must submit a Large Load 
Application to MISO as well as a non-refundable application fee of $250,000.45  Due to the role 
of the Transmission Customer in obtaining Transmission Service for Loads, the Show Cause 
Order’s direction that the Transmission Customer seeking Transmission Service to serve a Large 
Load bear responsibility for requesting the Transmission Service and executing cost recovery 
agreements. The Large Load Transmission Customer is the only party that may request 
Transmission Service on behalf of a Large Load from MISO and thus, is the only party that may 
submit a Large Load Application.46  MISO’s current processes similarly limit the types of entities 
that can submit EPR Requests.47  MISO’s current EPR process similarly only allows Transmission 
Owners to submit EPR requests.  The Transmission Customer must select from a list of 
Transmission Service options which service it is applying for and must identify the amount of 
requested firm or non-firm service options.48  LLPR is designed to facilitate several different types 
of requests for Transmission Service, including Network Resource Integration Service (“NITS”), 
Firm Service Step Up (“FSSU”), Interim (“Interim NITS”), and Transmission Service requested 
through LARS.49 Notably, the requested Transmission Service option and the identified MW 
amount may not be changed after the Large Load Application is submitted to MISO.50  This, 
together with the required application, discourages speculative or unready Large Load 
 
44  A Large Load may assume other responsibilities or obligations pursuant to agreements with the Transmission 
Customer or in accordance with rules and regulations adopted by states commissions or other retail regulators. 
MISO’s LLPR does not prohibit this.  
45  Furnish Testimony at 5.  
46  Id.  
47  Under current processes, only a Transmission Owner may submit an EPR request into MTEP because they are 
the entity that identifies the urgent need on their facilities.  Thus, LLPR does not introduce any new restriction 
against other types of entities submitting requests for Transmission Service (e.g., Generator Interconnection 
Customers, Market Participants).  Rather, LLPR simply shifts this role from the Transmission Owner to the Large 
Load Transmission Customer to facilitate the accountability goals of the Show Cause Order. 
48  Id. at 5-6.  
49  Id. 
50  Id. at 5. Large Loads may be completed in phases, but the total expected MW load amount must be identified in 
the Large Load Application at time of submission.  Any additional load amounts must be submitted as a new 
request for Transmission Service.

PDF page 15

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 15 
 
Applications and provides the needed certainty about what is being studied that is necessary to 
perform an accelerated study without creating undue restudy risk.  
 
The specific Transmission Service requested, the size of the Load, and whether the Large 
Load has partnered with generation will determine the next steps for the applicant and the load.  
For example, if the applicants are looking to co-locate the Load with the generation, then they will 
need to ensure that an appropriate Interconnection Agreement e.g. “ZGIA” has already been 
executed for the generator.51  If the Large Load is greater than or equal to 200 MW and has formally 
partnered with a generator for a minimum of fifteen years, then the applicants will go through the 
LARS study process.52  Other Transmission Services or processes such as FSSU and Interim NITS 
can be selected at the start of LLPR or after the LLPR study process is completed.  Any Large 
Load going through the LLPR process will be subject to the Interconnection Reliability 
Requirements proposed by MISO in Docket No. ER26-3650-000.53  
 
MISO will complete the LLPR study process three times in each 365-day period based on 
any Large Load Applications received by the deadline.54  MISO will post the application deadline 
on its website at least 90 calendar days prior to each deadline.55  The Large Load Transmission 
Customers may submit Large Load Applications at any time and MISO will maintain a list of all 
Applications leading up to each study process.56  Any applications that are submitted after the 
deadline will be automatically included in the next LLPR study cycle.57  In order for MISO to 
complete these studies in an expedient manner, the applicants must abide by these deadlines and 
additional review periods, which will be addressed in the next sections.  
 
C. LLPR Study Cadence, Timing, and Application Requirements—Attachment FF 
Sections I.D.1.c.iii.a—I.D.1.c.iii.c. 
 
MISO is proposing to complete the LLPR study process three times in a 365-day period.58  The 
timing of this process is reasonable and dictated by how long it is expected for MISO and the other 
participants in an LLPR process to complete the required steps.  This study cadence is necessary 
and appropriate in order to allow the base case of each LLPR study cycle to incorporate the 
 
51  See generally, ZGIA Filing, Docket No. ER26-3552. 
52  See LARS Filing, Docket No. ER27-25-000.  
53  See IRR Filing, Docket No. ER26-3650-000. 
54  Furnish Testimony at 10.  
55  Id. As explained in testimony, the first Large Load Application deadline will be on March 1, 2027, and due to the 
timing of this filing, MISO will not be able to provide 90-day notice for the first LLPR study cycle.  
56  Furnish Testimony at 4, 10.  
57  Id. at 10.  
58  MISO considers each LLPR study cycle to commence on the date of the Large Load Application deadline and 
ends once the project receives MTEP approval, which takes place once the stakeholder process has been 
completed and the cost recovery agreements are executed or filed unexecuted with the Commission.

PDF page 16

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 16 
 
Transmission System changes from the prior LLPR Study cycle.59  To avoid unnecessary restudy 
risks, it is appropriate to begin each study cycle after the prior one is completed and the applicable 
cost recovery agreements have been executed or submitted to the Commission for acceptance.   
 
While the Large Load Application may only be submitted by the Transmission Customer, 
other parties including the Transmission Owner and the Large Load customer must all provide 
required information as part of the application.  The LLPR Applicant must submit the non-
refundable application fee of $250,000 and any relevant study deposits at the time of application 
submission.60  The parties must also submit a significant amount of information with the 
Application to ensure that they have completed any necessary pre-planning steps and have reached 
agreement on key portions of the project including the identification of any necessary Large Load 
Upgrades by the Transmission Owner(s).61  
 
The required technical information for a completed LLPR Application is set forth in 
proposed Section I.D.1.c.iii.b of Attachment FF.  This information includes the geographic 
location and Point of Withdrawal (“POW”) for the Large Load, the MW amount of the Large Load, 
the type of Transmission Service requested, data regarding the characteristics of the Large Load 
and equipment in order to enable MISO to assess how it will operate, the MTEP and model on 
demand information for associated load and transmission upgrades, the requested In-Service Date, 
and any requisite contact information.62  
 
Proposed Section I.D.1.c.iii.b.2 requires study files to include various items.  Specifically, 
such files should include models, one line diagrams, the Transmission Owner’s Interconnection 
Study Report, including consideration of Alternative Transmission Technologies (“ATTs”)/Grid-
Enhancing Technologies (“GETs”), and information about any Large Load Upgrades identified by 
the applicable Transmission Owner, with specific requirements to provide an estimate of the total 
costs of the required Large Load Upgrades, the costs that the Large Load Transmission Customer 
will be obligated to pay, and, if this is less than 100% of the capital costs of the Large Load 
Upgrade, a narrative explaining how their portion of the costs was determined.  This information 
will enable MISO to verify any analyses performed by the Transmission Owner and provide the 
cost transparency sought by the Show Cause Order.  The Large Load Application is designed to 
be flexible so that it can be used to initiate the study process for several different types of 
Transmission Service and integrate with other MISO processes.63 
 
 
Proposed Section I.D.1.c.iii.b.3 requires an attestation by the Transmission Customer 
attesting that it acknowledges MISO’s ability to review reliability impacts and additional 
 
59  Furnish Testimony at 12.  
60  Id. at 5.  
61  See id. at 6-8.  
62  See id.  
63  LARS, for example, will require an Interconnection Request for a Generating Facility and additional information 
about the commercial relationship and electrical connection between the Interconnection Customer/Generating 
Facility and the LARS Associated Transmission Customer and LARS Associated Large Load.

PDF page 17

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 17 
 
mitigations through applicable study processes, that the Transmission Customer will comply with 
Tariff terms and requirements applicable to Large Loads that are set forth in Module B of the 
Tariff, that the Transmission Customer has a commercial agreement with the Large Load providing 
for it to request Transmission Service in order to serve that Large Load, and that the Transmission 
Customer does not have other requests pending with MISO for duplicative Transmission Service.  
These latter two requirements provide safeguards against unnecessary, speculative, or duplicative 
requests for Transmission Service by demonstrating that the Transmission Customer submitting 
the LLPR Application is the correct Transmission Customer that will serve the Large Load and 
that there are not multiple requests for the same Transmission Service being submitted as 
speculative alternatives on different parts of the MISO Transmission System.64  If the Large Load 
was proposed in multiple places then that would artificially inflate the total cost of Large Load 
Network Upgrades, jeopardize the finality and commercial certainty of LLPR studies, and create 
restudy or cost shift risks for other Transmission Customer or participants in other MISO 
processes.65 
 
MISO also proposes to require submission of valid models for electromagnetic transient 
(“EMT”) studies.66  The EMT work must be completed in the pre-application phase in order to 
capture the complete list of Upgrades and to ensure that the Large Load Transmission Customer 
has taken into consideration the necessary mitigation to meet the Interconnection Reliability 
Requirements.67  Finally, applicants must submit the LLPR System Impact Study Agreement and 
sign any relevant non-disclosure agreements required by MISO in order to ensure funding for the 
LLPR study and appropriately provide for the handling of confidential information.68  The LLPR 
System Impact Study Agreement is based on and largely follows the interconnection study 
agreement required for Generation Interconnection Customers with adjustments to reflect the 
different types of studies that may be performed under LLPR.69  The required CEII NDA to be 
included as Attachment FF-10 to the Tariff is substantively identical to the pro forma CEII NDA 
required of Generator Interconnection Customers with their Interconnection Requests,70 and the 
required Confidential Information NDA is MISO’s pro forma Universal Nondisclosure 
Agreement, which is set forth in Attachment Z to the MISO Tariff.71  
 
64  Furnish Testimony at 9.  
65  Id. at 9; MISO has carefully worded the language of Attachment FF Section I.D.1.c.iii.b.3 so as not to prevent the 
submission of applications for incremental transmission service needed in addition to that requested in a previous 
application. This is appropriate because such requests are not speculative alternatives. 
66  MISO is requiring all Large Load Applications to include EMT models, but EMT studies will only be required 
for specific Large Load projects based on information MISO will provide and the level of detail will be described 
in the BPM.  
67  Furnish Testimony at 8-9.  
68  Id. at 26-27.  
69  See, Attachment X, Appendix 1, Attachment B 
70  See, Attachment X, Attachment C to Appendix 1: Universal Non-Disclosure and Confidentiality Agreement. 
71  The LLPR System Impact Study Agreement is provided in the form of Attachment FF-10 to Attachment FF.  The 
confidentiality agreements may include MISO’s Universal Non-Disclosure Agreement or non-disclosure 
agreements related to CEII.

PDF page 18

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 18 
 
 
 
LLPR Applicants are required to submit a $250,000 non-refundable application fee and a 
$100,000 study deposit upon application submission.72  The $250,000 both provides funding for 
LLPR administration and studies while also acting as a deterrent to speculative or uncertain Large 
Load Applications.73  The $100,000 study deposit provides needed funding for the LLPR System 
Impact Study and any related studies that may be required, such as an FSSU or Interim NITS study.  
In the event that a Large Load Transmission Customer chooses to have MISO complete its EMT 
study, then an additional $100,000 study deposit must be provided.74  
 
The objective of including all these requirements at time of application is to ensure that the 
Upgrades that are needed to reliably serve the Large Load are identified at the outset.75  It is also 
critical that the parties collaborate prior to submitting the Large Load Application to MISO so that 
MISO may complete the LLPR study process on its accelerated timeline.76  The streamlined 
deficiency cure period for applicants is another piece of the LLPR proposal.  MISO will review 
each Large Load Application and notify the applicants of any identified deficiencies within fifteen 
(15) business days of receipt. After receiving that deficiency notification from MISO, the 
Transmission Customer will have ten (10) business days to cure the identified deficiencies.77  The 
Transmission Customer will also have five (5) business days to address any errors that may be 
identified later in the LLPR study process.78  If the Transmission Customer is unable to cure the 
deficiencies in any of the required timelines, then the Large Load Application will be deemed 
withdrawn from the LLPR process.79  While the non-refundable application fee will be lost, the 
parties may submit the project in a future LLPR study cycle but must identify what information 
changed from the previous application.80  There will be only one Application review period and 
one cure period for each Large Load Application.81  This is necessary to ensure that the LLPR 
process remains streamlined and that MISO is able to complete these studies on an expedited 
timeline.  MISO’s proposed Tariff language captures all requirements that will be included in the 
LLPR Application. MISO will develop a form of application that captures proposed Tariff 
requirements, as may be adjusted by any compliance directives received from the Commission, 
and will post this form on MISO’s website prior to the application deadline for the first LLPR 
study cycle.  
 
 
72  Furnish Testimony at 5.  
73  This is in alignment with the Commission’s Show Cause Order and its concern with speculative transmission 
requests on behalf of Large Loads. See Show Cause Order PP 68, 73, 80. 
74  Furnish Testimony at 8-9.  
75  Id.  
76  Id. at 5, 12.  
77  Id. at 10-11.  
78  Id.  
79  Id.  
80  Id. at 15-16.  
81  Furnish Testimony at 10-11.

PDF page 19

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 19 
 
D. Model Building and Coordination with MTEP and Existing Processes—
Attachment FF Section I.D.1.c.iii.d 
 
Pursuant to proposed Section I.D.1.c.iii.d, MISO will commence developing models for all 
LLPR studies no later than five (5) business days after the conclusion of cure period.82  MISO will 
use reasonable efforts to complete the model review process within thirty (30) Calendar Days after 
the conclusion of the Large Load Application cure process.83  MISO will develop models for the 
LLPR studies in the applicable cycle based on the latest MTEP case and reflect all MTEP approvals 
that have occurred as of the end of the cure period.84  This ensures that LLPR models are based on 
the latest available information.  The process includes the circulation of draft models to the 
applicable Transmission Owners and Large Load Transmission Customers, subject to the required 
nondisclosure agreements, and provides a five (5) business day window for the applicable 
Transmission Owners and Large Load Transmission Customers to submit comments for MISO’s 
consideration, after which MISO will finalize the models and circulate the final models to them.85  
The model build period ends when the Transmission Provider provides the final models to the 
appliable Transmission Owners and Transmission Customers.86  Taken together, this language 
establishes a just and reasonable model review process for Large Loads that balances an 
opportunity for participation and comments with a schedule consistent with the expedited nature 
of the LLPR process so as not to disturb or delay subsequent MISO processes that build from the 
completed LLPR Study Cycle.  
 
E. The LLPR System Impact Study—Attachment FF Section I.D.1.c.iii.e. 
 
Proposed Sections I.D.1.c.iii.e and I.D.1c.iii.f establish both a LLPR System Impact Study 
process by describing the substantive analyses that will be performed as part of LLPR and details 
the tender and processing of the Final LLPR Study Report. First, proposed Section I.D.1.c.iii.e 
provides that MISO will commence the LLPR System Impact Study within two business days after 
conclusion of the model review period and explains that the LLPR study will consist of an analysis 
of the impacts of the Large Load on MISO’s Transmission System containing those elements 
described in Attachment FF-10.  The proposed language further provides that the analysis will be 
based on any applicable planning criteria.87  This language necessarily balances specificity about 
what is being studied with sufficient flexibility to accommodate rules currently being developed 
by NERC, Regional Entities, Transmission Owners, and regulators.  While completing the LLPR 
System Impact Study, MISO may consider alternative solutions including those suggested by 
stakeholders and the MTEP aggregate system analyses against applicable planning criteria.88  
 
82  Id. at 13.  
83  Id.  
84  Id. at 12-13. 
85  Id. at 13. 
86  Id.   
87  Furnish Testimony at 13-14.  
88  Id.

PDF page 20

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 20 
 
MISO will post all the Large Load Applications that will be included in the upcoming LLPR 
System Impact Study to its MTEP webpage on its public website, thus facilitating the transparency 
requirements identified in the Show Cause Order.89  
 
In the event that any Transmission Issues are identified in the LLPR System Impact Study, 
MISO will send the initial Transmission Issues to the applicable Transmission Owner and 
collaborate with them on the development of possible solutions.90  This will include considering 
ATTs/ GETs and selecting the preferred solution to the identified Transmission Issues.91  At this 
point in the LLPR study process, there are additional strict deadlines that must be followed.  The 
Transmission Owners will have fifteen business days to respond to the identified Transmission 
Issues with possible solutions and, within ten business days after receipt of the proposed solutions, 
MISO will review and test the mitigation.92  If MISO identifies more Transmission Issues, then it 
will notify the Transmission Owner, who will then have an additional ten business days to develop 
new possible solutions.93  MISO will then review and test the newly proposed mitigations within 
five business days.94  If the Transmission Issues are not resolved in the required timeframe, then 
the Large Load Application will be withdrawn, and the project will be removed from the LLPR 
study.95  
 
Once the LLPR analysis/mitigation portion of the study is concluded, MISO will provide 
a draft LLPR Study Report to the Transmission Customer and each applicable Transmission 
Owner.  The Transmission Customer and Transmission Owner(s) will have five business days to 
review and provide comments on the study report.96  After reconciling any comments, MISO will 
provide the final LLPR Study Report and any applicable cost recovery agreements to the 
Transmission Customer and applicable Transmission Owner(s).97  MISO will not process any 
Large Load Application for MTEP approval until all applicable cost recovery agreements are 
executed by all parties or an unexecuted or non-conforming filing is submitted to the 
Commission.98 This is necessary to prevent circumvention of cost recovery agreement obligations 
and is consistent with their place in the LPPR framework as a required pre-condition of MTEP 
approval and obtaining Transmission Service for Large Loads. 
 
 
89  Id.  
90  Id.  
91  Id. 
92  Id.; see also, Section I.D.1.c.iii.e-f.  
93  Furnish Testimony at 14-15. 
94  Id. 
95  Id. 
96  Id. 
97  Id. 
98  See Id. at 15-16.

PDF page 21

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 21 
 
F. Tender and Processing of the Cost Recovery Agreements—Attachment FF 
Section I.D.1.c.iii.f.99 
 
When MISO shares the final LLPR Study Report with the Large Load Transmission 
Customer and any applicable Transmission Owners, MISO will also tender the Large Load Cost 
Recovery Agreement and/or the Large Load Impacted Transmission Owner Agreement(s). The 
Large Load Transmission Customer and Transmission Owner(s) have fifteen business days to 
execute the cost recovery agreements and return them to MISO, or request that the non-conforming 
or unexecuted cost recovery agreements be filed with the Commission.100  Failure to do so will 
result in the Large Load Application being withdrawn and the project being removed from the 
LLPR process.101  The Large Load Upgrades associated with these projects will be considered 
approved for MTEP purposes either at the completion of the stakeholder review process, as of the 
date that the last party executes a conforming cost recovery agreement, or as of the date of filing 
an unexecuted or non-conforming cost recovery agreement with the Commission, whichever is 
later.102  This approach is structurally consistent with how MISO processes other service 
agreements, such as MISO’s pro forma GIA and preserves the rights of Large Loads Transmission 
Customers to bring disputes before the Commission through unexecuted filings while maintaining 
the accelerated LLPR completion timeframe needed to allow subsequent LLPR cycles to 
commence with models that account for prior LLPR cycles with sufficient certainty.103   
 
 
To address stakeholder desires for a date certain when the LLPR Application is deemed 
granted and the required Large Load Upgrades approved for inclusion in MTEP, MISO’s proposed 
language uses either the date of the completion of the stakeholder review process, the date the last 
party executes a conforming cost recovery agreement, or the filing date of a non-conforming or 
unexecuted cost recovery agreement, whichever is later, as the point in time at which MTEP 
approval occurs.  This approach is just and reasonable because an executed conforming agreement 
may be included in MISO’s Electronic Quarterly reports and need not wait for a Commission order 
to be deemed accepted.104  Thus, the certainty that the project will be developed significantly 
increases at this point.  For nonconforming and/or unexecuted agreements, MISO considered using 
the date of a Commission order accepting such agreement as the trigger for MTEP inclusion.  
However, MISO ultimately rejected this approach as impractical.  Given the need to build the base 
 
99  Section I.D.1.c.iii.f also addresses the tender of the final LLPR Study Report, but that timing was addressed in 
the previous section.  
100  Gudeman Testimony at 5.  
101  Id.  
102  Furnish Testimony at 17.  
103  See, Tariff Attachment X, Section 11.3 (Execution and Filing) (implementing a similar procedure, including a 
deemed withdrawal for failure to proceed and different timeframes based on the requirements and timing of the 
underlying process). 
104  Under MISO’s EPR process, projects are deemed approved for inclusion in MTEP once the study is complete and 
MISO adds them to the list of approved projects.  With the introduction of agreements that memorialize 
commitments associated with the LLPR process, using later of the stakeholder review process completion date, 
the execution date, or filing date of unexecuted or non-conforming agreements provides an appropriate equivalent 
reference date for approval.

PDF page 22

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 22 
 
models used in subsequent LLPR cycles using a system topography that reflects what was changed 
by prior LLPR cycles in order to accurately study impacts, it would not be possible to wait several 
months for a Commission order before building the models used in the next LLPR cycle while 
maintaining a triannual LLPR study cadence.  MISO proposes the date of filing of an unexecuted 
or nonconforming filing as point where the application should be deemed approved for inclusion 
in MTEP as reasonable compromise between providing certainty in modeling for the next LLPR 
study cycle and maintain the accelerated study cadence necessary to accommodate the integration 
schedules of Large Loads.105 
 
Notably, no Transmission Service shall commence under an unexecuted or non-
conforming cost recovery agreement until it has been accepted by the Commission.  While it is 
reasonable to include the needed transmission upgrades in models upon submission of an 
unexecuted or nonconforming filing in order to commence subsequent study cycles on schedule, 
allowing Transmission Service to commence prior to Commission acceptance of the cost recovery 
agreements risks decoupling the requirements for the Large Load Transmission Customer 
contained in the agreements from the Transmission Service granted.  This risk is not needed to 
prevent delays to all other Large Load Transmission Customers and MISO expects that in most 
instances, a Commission order would likely be issued before the Large Load’s need-by date.106 
 
MISO’s proposed language is reasonable and necessary to establish the prescribed timeline 
for executing the cost recovery agreements, enable stakeholder review and feedback, identify when 
Large Load projects are considered approved for MTEP purposes, and allow model building for 
subsequent cycles.  These strict timelines are necessary to ensure that the LLPR process can be 
completed in a 365-day period and to ensure that MISO has sufficient certainty in the Large Load 
Upgrades completed by applicants in the LLPR process.  These requirements make clear that even 
if a project is withdrawn and removed from the MTEP models, the Large Load Transmission 
Customer is still responsible for paying for any identified Large Load Upgrade costs. This 
approach avoids reserving system capability for projects that ultimately do not proceed. 
 
G. Resubmission of Withdrawn Applications—Attachment FF Sections I.D.1.c.iii.g 
Proposed section I.D.1.c.iii.g provides that any withdrawal of the application will result in 
the removal of the project from the LLPR study process.  The Large Load Transmission Customer 
may submit a new Large Load Application to MISO but must identify what information has 
 
105  While this date does not provide as much certainty as the date of Commission acceptance, a project is still more 
likely to be developed after a service agreement is filed than before that point. In MISO’s experience, most 
unexecuted filings will still result in the agreement being accepted by the Commission, either with or without the 
requested changes to pro forma agreement terms, and non-conforming agreements are fairly uncommon. MISO 
acknowledges that rejection is possible and projects that have unexecuted agreements can be included in 
subsequent models only subject to the outcome of the Commission proceeding.  However, the risks of diminished 
certainty are, on balance, preferable to guaranteed study delays. 
106  This could result in an actual delay only in the highly unlikely scenario where a Large Load is projected to be 
built and require Transmission Service obtained through LLPR in a shorter timeframe than the Commission can 
act on a filing.

PDF page 23

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 23 
 
changed since the previous submission.107  This language provides clear withdrawal rules and is 
both reasonable and needed to allow for the uniform administration of the LLPR process on an 
accelerated timeframe.  
 
H. Stakeholder Forums—Attachment FF Sections I.D.1.c.iii.h. 
 
Consistent with its current process, MISO will host a stakeholder forum at the end of each 
LLPR study process or as otherwise provided in the Transmission Planning Business Practices 
Manual (“TPBPM”) basis to review the identified transmission needs, solutions, and any 
alternatives identified in the completed LLPR studies.108    The purpose of these stakeholder forums 
is to review with stakeholders the transmission needs, solution(s), and any identified alternatives 
identified in the completed LLPR System Impact Studies.  Following each stakeholder forum, 
stakeholders will have a defined comment period outlined in the TPBPM.109  This stakeholder 
review process happens in parallel to the tender and execution of any relevant cost recovery 
agreements, thus allowing MISO to schedule stakeholder discussions and comment periods on an 
actionable timeframe.  As explained earlier in this letter, a LLPR Application is considered 
approved by MISO at the completion of the stakeholder review process, execution of a conforming 
cost recovery agreement for such Large Load Upgrade, or upon the filing of an unexecuted or non-
conforming cost recovery agreement with the Commission, whichever is later.110  For example, if 
a cost recovery agreement was executed within two days, MISO would not consider the project 
approved until it completed the stakeholder review process.  This is necessary to allow action on 
stakeholder comments where appropriate.   
 
These proposed Tariff additions align with MISO’s commitment to working with 
stakeholders in addressing the integration of Large Loads and providing transparency in the 
projects studied in the LLPR process.  MISO regularly hosts these stakeholder forums as part of 
the EPR process and will continue to do so on a regular basis for projects going through the LLPR 
process.  
 
I. Cost Recovery Agreements—Attachment FF Section I.D.1.c.iii.i. 
 
As part of the proposed LLPR process and to mitigate the risk of cost shifting among 
Transmission Customers, MISO is proposing two cost recovery agreements to ensure that a Large 
Load Transmission Customer bears the risk and is ultimately responsible for the costs incurred to 
provide the requested Transmission Service.111  The relevant cost recovery agreements will include 
 
107  Furnish Testimony at 16.  
108  Id. at 17. Any meetings involving CEII or confidential materials will be handled under Section I.C.23 of 
Attachment FF.  
109  Id.  
110  Id. 
111  Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and 
Attachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery 
Agreement).

PDF page 24

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 24 
 
an exhibit listing the Large Load Upgrade(s) and/or Impacted Transmission Owner Large Load 
Upgrade(s) that are required for the Large Load Transmission Customer. 
 
The LLPR process ends with MTEP approval and after the issuance of such approval, the 
Transmission Customer remains responsible for the Large Load Upgrade costs identified through 
the LLPR.112  Thus, if a project is assigned Large Load Upgrades through the LLPR process and 
the Large Load is subsequently not built, or its service is terminated, then the Large Load 
Transmission Customer will remain responsible for any associated costs assigned to their project 
under the proposed cost recovery agreements.  This provides the necessary certainty for later 
projects studied in the LLPR process and will allow MISO to complete the studies efficiently 
without disrupting future LLPR study cycles.113  
 
The details and requirements of the proposed cost recovery agreements are further 
described in Section IV of this transmittal letter.  
 
J. LLPR Operations Agreement and Confidentiality—Attachment FF Sections 
I.D.1.c.iii.j—I.D.1.c.iii.k. 
 
Once a Large Load project has received MTEP approval, the Transmission Customer must 
submit an updated Large Load forecast along with an operations agreement for the new Large 
Load.114  This operations agreement, which is Exhibit 2 to Attachment F, is an application for 
Network Integration Transmission Service (NITS) in accordance with Module B Section 29.2 of 
the Tariff prior to the Service Commencement Date.  As part of the operations agreement process, 
the Transmission Owner will develop a CPNode for each Large Load.  This is necessary for MISO 
settlement, operational visibility, and forecasting purposes.115  These pro forma service agreements 
are executed, reported in the EQR, and posted publicly on MISO’s website.  Service to the Large 
Load will not commence prior to MISO’s review and execution of the operations agreement. 
 
Proposed Section I.D.1.c.iii.k provides for the designation and protection of confidential 
and Critical Energy Infrastructure Information by participants in the LLPR process with access to 
non-public information subject to MISO’s established Nondisclosure Agreement and CEII rules.  
As explained further by Ms. Furnish, the form of non-disclosure agreement will be the universal 
NDA, as accepted by the Commission for inclusion in MISO’s Tariff as Attachment Z.  The CEII 
NDA is directly drawn from the form of nondisclosure agreement included with MISO’s 
Interconnection Request form required for Interconnection Customers, thus promoting rules 
alignment across processes.  Allowing participants in studies to request confidential and/or CEII 
treatment of appropriate information is a necessary and routine feature of MISO study processes 
and will protect the more sensitive information (e.g., detailed models, diagrams and other sensitive 
technical information) required as part of the LLPR process.  MISO notes that these confidentiality 
 
112  Furnish Testimony at 15-16. 
113  Id.  
114  Furnish Testimony at 16-17.  
115  Furnish Testimony at 16-17.

PDF page 25

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 25 
 
safeguards will not conflict with the transparency requirements proposed in this filing, including 
the public Large Load dashboard, because the required information is set forth in the Tariff and 
both MISO’s proposed Tariff language and existing confidentiality rules prohibit designation as 
confidential of information that a Tariff or other legal requirement specifies be made public.   
 
At the conclusion of the LLPR process, the cost recovery agreements associated with Large 
Load Upgrades will be submitted to the Commission for approval.  Any executed cost recovery 
agreements will be included in MISO’s EQR reports on a quarterly basis and all the agreements 
included in those EQR reports are publicly posted on MISO’s public website in accordance with 
the same procedures applicable to other types of service agreements.  The EQR reports will also 
be accessible through MISO’s website. 116  Unexecuted or non-conforming cost recovery 
agreements will be filed separately with the Commission and publicly available subject to the 
Commission’s regulations.   
 
K. The Proposed Tariff Revisions are Just and Reasonable. 
 
Under section 205 of the Federal Power Act, MISO must show that its proposed Tariff 
revisions are just and reasonable, and not unduly discriminatory or preferential. “For filings made 
under FPA section 205, the Commission evaluates whether the proposal in the filing is just and 
reasonable, and not whether alternative proposals are more or less reasonable than the filing party’s 
proposal.”117  In the Show Cause Order, the Commission preliminarily found that MISO’s Tariff 
lacked clear and consistent provisions addressing large load integration.  The Commission noted 
that MISO’s role in load additions has been largely supplemental and the Transmission Owners’ 
study processes are not set in the Tariff and some have used ad hoc, stand-alone study agreements. 
The proposed LLPR revisions directly address these concerns.  
 
MISO developed a dedicated framework for Large Loads and proposes to add the LLPR 
process to Attachment FF of the Tariff as well as new pro forma Attachments LLL and MMM.  
With these additions, every Transmission Customer seeking Transmission Service for a Large 
Load must submit a Large Load Application and provide the requisite information to MISO.  This 
not only creates a single path for Large Load Transmission Customers to take when seeking 
Transmission Service, it provides MISO with the ability to expedite the study timelines and, in 
some cases, optimize the transmission solutions. Each Large Load Application must elect one of 
several defined options (LLPR, Interim NITS, LARS, etc.), which replaces the historic and 
potentially inconsistent practices with a single, Tariff-based process that applies equally to all 
Large Load Transmission Customers.  Together, these provisions create a transparent and 
predictable path for identifying the Large Load Network Upgrades needed to serve Large Load 
Transmission Customers, while balancing speed, reliability, and stakeholder engagement.  
 
MISO’s proposed Large Load framework provides alternative pathways depending on size 
of the load, which strikes a just and reasonable balance between capturing the larger loads for 
 
116  See MISO, Notifications Overview, Market Settlements, available at: https://www.misoenergy.org/markets-and-
operations/notifications/.  
117  See PJM Interconnection, LLC, 197 FERC ¶ 61,019, at P 29 (2026).

PDF page 26

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 26 
 
which MISO needs visibility to ensure system reliability and directing the smaller loads that do 
not raise the same reliability concerns into the existing EPR process.118  The Large Load 
Application is just and reasonable and not unduly discriminatory or preferential because it requires 
the applicants to provide significant information about the Large Loads, which in turn will provide 
MISO with the information necessary to address the operational impacts of Large Loads looking 
to interconnect to MISO’s Transmission System.   
 
The LLPR application process also contains the elements identified by the Commission in 
the Show Cause Order. The Large Load Applications are accepted on a rolling basis and require a 
non-refundable application fee of $250,000.  The applications must include detailed information 
about the Large Load and provide planning models for MISO to utilize when completing its own 
independent studies.  MISO is also requiring that the Large Load Transmission Customer attest 
that it has no other pending requests for service to the same Large Load, which will improve load 
forecasting clarity and certainty.  The Commission has noted in other contexts that non-refundable 
fees, study deposits, and readiness requirements deter speculative requests, which is critical for 
MISO to be able to study these loads on an expedited basis.  The proposed Tariff revisions and 
pro forma cost recovery agreements also require financial security equal to the Large Load 
Network Upgrade capital costs once the LL-CRA is executed, which will further reduce the 
possibility of speculative requests clogging the study processes, distorting load forecasting, or 
further risking any kind of cost shifting.  
 
The LLPR System Impact Study is just and reasonable because it incorporates enhanced 
study requirements to enable MISO independently to analyze the impacts of each Large Load on 
the Transmission System.  MISO will conduct this analysis based on MTEP models, and in 
collaboration with the Transmission Owner and Transmission Customer.  Moreover, to participate 
in the LLPR process, MISO requires that EMT studies be completed before the application is 
submitted so that the full set of Network Upgrades needed to reliably serve the Large Load can be 
identified.119  The study also requires the evaluation of alternative transmission technologies and 
grid-enhancing technologies by the Transmission Owners and MISO will review the consideration 
of any relevant ATTs/GETs, which was another Commission concern.120  
 
The LLPR provides the clarity and consistency sought in the Show Cause Order by stating 
the information required to enter the process, the study sequence, the roles of MISO and the 
Transmission Owners, and the relationship of the results to planning and service.  The readiness 
and attestation requirements address the Commission’s concern with speculative or duplicative 
requests, while the cumulative assessment and reliability information support consistent treatment 
 
118  See PJM Interconnection, LLC, 197 FERC ¶ 61,019, at P 27 (2026); see also Sw. Power Pool, Inc., 194 FERC ¶ 
61,031, at PP 10, 61 (2026) (accepting a proposed definition of a high impact large load that included a 50 MW 
threshold for new or increased load at a single site connected to the transmission system at a voltage level greater 
than 69 kV); Tri-State Generation & Transmission Ass’n, Inc., 196 FERC ¶ 61,127, at P 76 (2026) (Tri-State) 
(accepting a proposal to define a high impact load as load exceeding or forecasted to exceed 45 MW within four 
years). 
119  Furnish Testimony at 8.  
120  Id. at 13-14.

PDF page 27

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 27 
 
of system impacts.  The recurring cycles provide an accelerated path grounded in MISO’s existing 
planning framework.121  Finally, the proposed revisions were developed through MISO’s Large 
Load Working Group where the process was presented, reviewed, and discussed by 
stakeholders.122  The Commission recognized and encouraged this effort in the Show Cause Order.  
 
For these reasons, the proposed Tariff revisions are just and reasonable, and not unduly 
discriminatory or preferential, and the Commission should accept them under section 205 of the 
Federal Power Act.  
 
L. Separate Proposal to Apply Cost Recovery Agreements to LARS Projects.  
 
Separately from all other proposals contained in this filing, MISO proposes to include the 
following language as a separate paragraph in Attachment FF, Section I.D.1.c.iii.f in order to 
facilitate the use of the LL-CRA and LLITO-CRA as part of the LARS process: 
 
Subject to Commission acceptance of the revisions to Attachment FF of the Tariff 
pending before the Commission in Docket No. ER27-25, all LARS Associated 
Transmission Customers that submit LARS Applications for inclusion in a LARS 
cycle with a kickoff date on or after February 14, 2027, shall execute or request the 
unexecuted and/or non-conforming filing of the LL-CRA and/or LLITO-CRA, as 
applicable, for all Network Upgrades identified in a LARS study for which 
Attachment FF I.D.1.b.ii.g. assigns cost responsibility to the LARS Associated 
Transmission Customer.  The LARS Application and Network Upgrades identified 
in a LARS study for which Attachment FF I.D.1.b.ii.g. assigns cost responsibility 
to the LARS Associated Transmission Customer shall be deemed approved for 
MTEP purposes as of the later of: (1) the date the last party executes the applicable 
conforming LL-CRA and, if required, LLITO-CRA(s); (2) the date of filing with 
the Commission of an unexecuted and/or nonconforming LL-CRA and/or LLITO-
CRA; or (3) the conclusion of the stakeholder comment period required by Section 
III.D.1.c.iii.h of this Attachment FF. A LARS Associated Transmission Customer 
shall not commence Transmission Service under an unexecuted or non-conforming 
LL-CRA or LLITO-CRA until such agreement(s) have been accepted by the 
Commission. 
 
If the Commission ultimately approves MISO’s LARS proposal, all LARS Associated 
Transmission Customers that submit LARS Applications on or after the effective date of this filing 
(February 14, 2027), shall execute or request the unexecuted filing of a cost recovery agreement, 
as applicable, for all Large Load Upgrades identified in a LARS study. The Large Load Upgrades 
associated with these LARS projects will be considered approved for MTEP purposes as of the 
date that the last party executes a conforming cost recovery agreement or as of the date of filing 
an unexecuted or non-conforming cost recovery agreement with the Commission.   
 
121  Show Cause Order at PP 39, 56–65 (identifying concerns regarding timely studies, readiness, operational impacts, 
and clear Tariff provisions); Furnish Testimony at 3.  
122  See Furnish Testimony at 28-33.

PDF page 28

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 28 
 
 
In the LARS Answer, MISO also stated that it would submit another filing to reconcile the 
LARS and LLPR processes to ensure their full alignment.123  Notably though, MISO has proposed 
standalone Tariff language in this docket to make the proposed cost recovery agreements 
applicable to new LARS studies.  While acceptance of the Tariff language discussed above will 
not obviate the need to make a subsequent reconciliation filing to harmonize other aspects of the 
LARS and LLPR filings, it will allow for the cost recovery agreements, which are a valuable 
transparency and accountability mechanism, to apply to LARS studies earlier than would be 
possible if MISO waited until acceptance of the instant filing and a subsequent reconciliation 
filing, to apply the cost recovery agreements to the LARS process.124  To the extent that the 
Commission accepts the cost recovery agreements in the instant docket, it may then separately 
consider whether to make them applicable to the next LARS cycle, assuming MISO’s LARS filing 
also is accepted.   
 
Thus, this proposed Tariff language represents a standalone proposal, which MISO 
includes in this filing purely for Tariff administration reasons.125  While it builds on the LLPR 
process and Cost Recovery Agreements proposed in this filing, it is not a component of any other 
proposal contained in this filing, not a part of any compromise or agreement with stakeholders 
regarding other elements of this filing.  MISO urges acceptance of this language for the reasons 
described above, MISO  
 
IV. 
COST RECOVERY AGREEMENT AND COST TRANSPARENCY 
 
The Show Cause Order preliminarily found that MISO’s Tariff appeared to be unjust and 
unreasonable because it lacked adequate mechanisms to mitigate the risk of cost shifting among 
transmission customers, which may result in unjust and unreasonable rates for transmission 
service.126  Specifically, the Commission was concerned about the apparent lack of:  (1) 
transparency regarding the assignment of network upgrades, and their associated costs, that are 
needed to provide transmission service to transmission customers on behalf  of large loads; and 
(2) a pro forma cost recovery agreement between MISO, the transmission owner, and the 
 
123  Furnish Testimony at 19; see MISO’s November 9 Answer filed in Docket No. ER27-25-000 (“LARS Answer”) 
at 15.  
124  This proposed language is severable from LARS because acceptance LARS was designed to work even with 
existing processes and then be integrated with the reforms contained in this filing once accepted by the 
Commission.. The standalone proposal contained in this filing is an enhancement to LARS, but not necessary for 
its function.  The proposed language is severable from this filing because it is contained in its own paragraph that 
replicates language proposed elsewhere and its application is limited to LARS. 
125  As explained in the LARS Answer, MISO filed its LARS proposal before LLPR, the LL-CRA and LLITO-CRA 
were developed given the immediate need for such a process and lead time for implementation. LARS Answer at 
3, 18. In that docket, MISO committed to updating LARS to incorporate the processes changes included in this 
filing once this filing is accepted. LARS Answer at 15. While MISO could make a separate contemporaneous 
filing from this one to make the LL-CRA and LLITO-CRA applicable to Large Load Transmission Customers 
participating in LARS, this would create version control concerns with pending language built upon pending 
language, as each filing would create a new version of Attachment FF.   
126  Show Cause Order at P 66.

PDF page 29

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 29 
 
transmission customer taking transmission service on behalf of Large Loads that ensures that the 
transmission customer bears the risk and is ultimately responsible for costs incurred to provide 
transmission service, including the cost of network upgrades.127  Below is a summary of the 
proposed Tariff revisions that address the Commission’s concerns.   
 
A. Cost Recovery Agreements 
 
In the Show Cause Order, the Commission preliminarily found that MISO’s Tariff appeared 
to be unjust and unreasonable because it lacked “adequate mechanisms to mitigate the risk of cost 
shifting among transmission customers, which may result in unjust and unreasonable rates for 
transmission service.”128  To prevent unjust and unreasonable cost shifting among transmission 
customers, the Commission stated that it appeared necessary for MISO, the relevant transmission 
owner, and the transmission customer taking transmission service on behalf of a large load to enter 
into a cost recovery agreement with a specified minimum financial contribution and financial 
security sufficient to secure such contribution to mitigate cost shifting if the transmission customer 
ultimately takes less transmission service than anticipated because the large load does not 
materialize as planned or is not developed at all.129   
 
In response to concerns raised by the Commission, MISO and the MISO Transmission 
Owners propose Tariff revisions and two pro forma cost recovery agreements that together require 
the Large Load Transmission Customer to make a minimum contribution toward the revenue 
requirement of the Transmission Owner(s) responsible for constructing the Large Load Upgrades 
identified by MISO in the LLPR.130  To ensure the minimum contribution, Large Load 
Transmission Customers are required to provide security to cover the capital cost of the Large 
Load Upgrades.  As briefly described in the previous section, prior to receiving MTEP approval 
for any such Large Load Upgrades, Large Load Transmission Customers are required to execute 
the pro forma LL-CRA and/or LLITO-CRA, as applicable, or request that the cost recovery 
agreements be filed unexecuted or as non-conforming with the Commission within 15 business 
days of being tendered the agreements by MISO.  Failure to do so by the conclusion of the 15-day 
period will result in the Large Load Application being withdrawn, and the project being removed 
from the LLPR process.  The customer is required to provide security within 45 days of the 
execution of the LL-CRA and/or LLITO-CRA.  If the LL-CRA or LLITO-CRA is filed unexecuted 
or as non-conforming, separate terms apply depending on the nature of the dispute and when the 
Commission approves such agreement.  Importantly, a Large Load Transmission Customer cannot 
 
127  Id.  
128  Show Cause Order at P 78. 
129 Id. at P 82, 84. 
130  Proposed MISO Tariff, Attachment LLL (Form of Agreement for Large Load Cost Recovery Agreement) and 
Attachment MMM (Form of Agreement for Large Load Impacted Transmission Owner Cost Recovery 
Agreement).

PDF page 30

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 30 
 
commence Transmission Service under an unexecuted and/or non-conforming LL-CRA or LLITO-
CRA until the applicable cost recovery agreements have been approved by the Commission.131   
 
The above framework, including the embedded rate mechanisms, which are discussed in 
more detail below, reflect a balanced approach to mitigating the cost shift concerns identified by 
the Commission while respecting state laws (in particular state retail ratemaking authority),  
Transmission Owner diversity, including their varied business models, the reality that 
Transmission Customers are often not the Large Load entities actually interconnecting to the 
Transmission System but merely a pass through, and the region’s economic development 
ambitions.  Importantly, nothing in LLPR, including the proposed cost recovery framework 
interferes, limits the ability of states and other retail regulators to impose additional conditions, 
further allocate cost responsibility and risk among and between retail customers and Load Serving 
Entities, or require further agreements involving parties not directly taking service under MISO’s 
Tariff (e.g., data centers and other owners of Large Loads).  Although a difficult needle to thread, 
the proposed framework, consistent with the direction given by the Commission in the Show Cause 
Order, and in recognition of MISO’s regional differences and state authority, is a just and 
reasonable approach to addressing the risk of cost shifting among Transmission Customers in 
MISO and potentially unjust and unreasonable rates.   
 
Below is a summary of each agreement and the rate mechanisms therein. 
 
1. Scope and allocation of responsibilities. 
 
MISO proposes two complementary pro forma cost recovery agreements to establish the 
Large Load Transmission Customer’s financial responsibility for the Large Load Upgrades 
identified through the LLPR study process.  The Large Load Cost Recovery Agreement (“LL-
CRA”) addresses upgrades within the Transmission Pricing Zone containing the Large Load’s 
Point of Withdrawal.  The Large Load Impacted Transmission Owner Cost Recovery Agreement 
(“LLITO-CRA”) addresses upgrades outside that zone.  MISO, the Large Load Transmission 
Customer, and the applicable Transmission Owner(s) are required parties to the agreements.  For 
purposes of the agreements, LLPR includes LARS.  The agreements therefore link the LLPR study 
results to the entities responsible for service, investment, and payment. 
 
In addition to any Transmission Service charges incurred by the Large Load Transmission 
Customer under the Tariff, a Large Load Transmission Customer is responsible for the costs of the 
Large Load Upgrades (“Minimum Contribution”) pursuant to the cost recovery rate mechanisms 
in the LL-CRA and LLITO-CRA.132  This Minimum Contribution is necessary to ensure that the 
Large Load Transmission Customer is responsible for paying for the costs of transmission driven 
by the Large Load (i.e., the cost incurred to provide the requested Transmission Service, including 
the costs of any Large Load Network Upgrades).   
 
 
131  Proposed MISO Tariff, Attachment FF, I.D.1.c.iii.f. 
132  Gudeman Testimony at 7, 22.

PDF page 31

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 31 
 
To accommodate the diversity of regulatory approaches and business models among 
Transmission Owners, the pro forma agreements provide the Transmission Owner responsible to 
construct a Large Load Upgrade the flexibility to roll into its rates for Transmission Service the 
capital costs of the Large Load Upgrade or to directly assign the costs of the Large Load Network 
Upgrade(s) to the Large Load Transmission Customer, and such election will be recorded in the 
agreement.133  The MISO Transmission Owners are a diverse group of investor-owned 
transmission owners, municipal utilities, and cooperatives, including both vertically integrated and 
independent transmission companies, that own transmission facilities over which MISO provides 
Transmission Service.  For example, some Transmission Owners, in addition to service 
Transmission Customers, serve retail load.  Some do not—they only serve MISO Transmission 
Customers.  The rate mechanisms in the cost recovery agreements ensure that cost recovery does 
not unnecessarily conflict with these various Transmission Owner business models in existence 
within the MISO footprint.  Importantly, however, as discussed below, whether Large Load 
Upgrade costs are rolled in or directly assigned, the Large Load Transmission Customer is always 
responsible for the costs of the Large Load Upgrades, thus, mitigating cost shifts to other 
Transmission Customers, consistent with the Show Cause Order.134   
 
2. Recovery of costs for upgrades within the TPZ. 
 
Where the capital costs of the Large Load Network Upgrade are rolled in the Transmission 
Owner’s transmission rates, the Large Load Transmission Customer is responsible for its Total 
Required Revenue Commitment, which amount is set forth in the agreement and payable on a 
yearly basis consistent with the Yearly Required Revenue Commitment.135  If the Transmission 
Service revenue attributable to a Large Load Transmission Customer on behalf of the Large Load 
during a calendar year is less than the customer’s Yearly Required Revenue Commitment, the 
customer is required to make a Supplemental Payment to the Transmission Provider.136  The 
formulas for calculating such amounts are set forth in Exhibit C of the LL-CRA.  Below is a more 
detailed description of these items.   
 
The Total Required Revenue Commitment reflects the return on and of the Large Load 
Network Upgrade investments over twenty years, including capital cost, return, depreciation, 
operations and maintenance, and taxes.137  The commitment is initially based on the estimated 
upgrade costs and then adjusted as actual capital costs are determined.138   
 
Following each calendar year, the Transmission Owner, in coordination with MISO, will 
determine whether the Large Load Transmission Customer has satisfied its Yearly Required 
 
133  Proposed MISO Tariff, Attachment LLL, §§ 3.1–3.4 and signature page; Proposed MISO Tariff, Attachment 
MMM, §§ III–V and signature page. 
134  Gudeman Testimony at 8. 
135  Id. 
136  Id. at 12. 
137  Id. at 8-10. 
138  Proposed MISO Tariff, Attachment LLL, § 3.3.3.

PDF page 32

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 32 
 
Revenue Commitment or whether a Supplemental Payment is owed.139  If the Transmission 
Service revenue attributable to Large Load Transmission Customer during a calendar year is less 
than the Large Load Transmission Customer’s Yearly Required Revenue Commitment, the Large 
Load Transmission Customer is required to make a Supplemental Payment to MISO, the formula 
for which is set forth in Exhibit D to the LL-CRA.  If the attributable revenue equals or exceeds 
the yearly commitment, no Supplemental Payment is required.  Mr. Gudeman, in his testimony, 
details and provides examples for calculating the Total Required Revenue Commitment, the Yearly 
Required Revenue Commitment and Supplemental Payment.140 
 
This annual comparison gives effect to the Large Load Transmission Customer’s actual 
contribution to transmission revenues while preserving a minimum payment obligation when load 
is below the level needed to mitigate a cost shift.  For example, a $10 million Yearly Required 
Revenue Commitment and $7 million in attributable annual transmission-service revenue would 
necessitate a $3 million Supplemental Payment; attributable revenue of $10 million or more would 
produce no Supplemental Payment for that year.  In his testimony, Mr. Gudeman, based on 
assumptions provided in his testimony, provides an illustrative example of how the Supplemental 
Payment is determined.141  If required, MISO will issue the supplemental invoice within ninety 
days after the end of every calendar year during the term of the cost recovery agreement, with 
billing and payment governed by Tariff Section 7 and the applicable Business Practice Manuals.142 
 
MISO will allocate any Supplemental Payments among the Transmission Owners that are 
a party to the LL-CRA in proportion to their respective Annual Incremental Revenue Requirement 
(defined in the agreement) included in the Yearly Required Revenue Commitment.143  Any 
Supplemental Payment allocated to a Transmission Owner will be treated as a revenue credit 
against the recipient Transmission Owner’s annual transmission revenue requirement, and each 
applicable Transmission Owner must provide a workpaper in its annual informational filing, which 
is generally filed in March of a calendar year, detailing that credit.144  While the need for a 
Supplemental Payment and the amount thereof will not be known until after a calendar year has 
ended, there does not necessarily need to be a large lag in reflecting significant Supplemental 
Payments in rates paid by Transmission Customers.  As Mr. Gudeman explains, any lag associated 
with a Supplemental Payment could be addressed by the Transmission Owner when developing its 
projected revenue requirement.145  In short, the cost recovery mechanism explained above is 
specifically designed to offset in rates the costs of the Large Load Network Upgrades so that the 
end result is that those costs are not shifted to other Transmission Customers.146 As shown in 
 
139  Proposed MISO Tariff, Attachment LLL, § 3.3.5. 
140  Gudeman at 8-17; see also Proposed MISO Tariff, Attachment LLL, § 3.3 and Ex. C, D.  
141  Gudeman Testimony at 12-13; Gudeman Testimony Exhibit MTO-0004 (Calculation of Supplemental Payment). 
142  Proposed MISO Tariff, Attachment LLL, §§ 3.3.5.6 and 3.3.5.7. 
143  Gudeman Testimony at 13. 
144  Gudeman Testimony at 17. 
145  Id. at 13-16. 
146  Id. at 16-17.

PDF page 33

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 33 
 
Exhibit MTO-0006 to Mr. Gudeman’s , with all else being equal assuming no other changes to 
load or revenue requirements, the Large Load Transmission Customer pays at least the incremental 
revenue requirement for the Large Load Network Upgrades and the zonal rate charged to other 
customers will not increase as a result of the Large Load Network Upgrades.147   
 
Where the capital costs of the Large Load Network Upgrades are directly assigned to the 
Large Load Transmission Customer, payments will be due from the customer as specified in a 
separate agreement between Transmission Owner and Large Load Transmission Customer to be 
filed with the Commission.148  Under such circumstances, the Transmission Owner agrees that it 
will not recover the costs of the directly assigned upgrade from other Transmission Customers and 
commits to providing an annual workpaper showing that treatment.149   
 
The LL-CRA continues until the earlier of twenty years after the final Large Load Network 
Upgrade enters service or satisfaction in full of the Total Required Revenue Commitment and the 
direct-assignment payment obligations, as applicable.150 
 
3. Recovery of costs for upgrades outside the TPZ. 
 
The LLITO-CRA establishes a separate rate mechanism for upgrades outside the TPZ.  
Where the capital costs of ITO-Large Load Network Upgrades are rolled into a Transmission 
Owner’s rates, the Large Load Transmission Customer is responsible for the ITO Large Load 
Network Upgrade(s)’ Monthly Revenue Requirement beginning in the month following the 
Transmission Owner’s notification that the upgrade has entered service.151  The formula to 
calculate the Monthly Revenue Requirement is set forth in Exhibit II to the LLITO-CRA and is 
identical to the “Incremental Revenue Requirement for Large Load Network Upgrades 
Calculation” formula in Exhibit C to the LL-CRA.152  As described above, the formula multiplies 
the capital invested in the ITO-Large Load Network Upgrade(s) by a levelized fixed charge rate 
determined from the term of the LLITO-CRA and data from the Transmission Owner’s MISO 
Tariff Attachment O Formula Rate, including taxes, interest on long term debt, return on equity, 
depreciation expense, total operations and maintenance expense, general and common 
depreciation expense; taxes other than income taxes; and total gross transmission plant.  The 
default recovery term is 240 months of payments for each upgrade, unless the parties mutually 
agree to a different term or the applicable obligations are otherwise satisfied.153 
 
 
147  Id. at 16-17; Gudeman Testimony Exhibit MTO-0006 (Zonal Rate Impact). 
148  Proposed MISO Tariff, Attachment LLL, § 3.4.1. 
149  Proposed MISO Tariff, Attachment LLL, § 3.4.2. 
150  Proposed MISO Tariff, Attachment LLL, §§ 2.2–2.3, 3.3. 
151  Proposed MISO Tariff, Attachment MMM, § IV. 
152  Gudeman Testimony at 24. 
153  Proposed MISO Tariff, Attachment MMM, § II.

PDF page 34

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 34 
 
The Transmission Owner recalculates the payment annually using updated inputs from the 
Transmission Owner’s Tariff Attachment O Formula Rate using data from the previous calendar 
year.154  Any payments from the customer under the LLITO-CRA are treated as revenue credits 
against the Transmission Owner’s annual transmission revenue requirement, documented in the 
Transmission Owner’s annual informational filing.155 
 
If the impacted Transmission Owner directly assigns ITO-Large Load Network Upgrade 
costs under proposed Section V of the LLITO-CRA,  payments are due as specified in a separate 
agreement between Transmission Owner and Large Load Transmission Customer to be filed with 
the Commission.156  As with the LL-CRA, the Transmission Owner may not recover the directly 
assigned costs from other Transmission Customers and must document the foregoing in its annual 
informational filing.157   
 
4. Financial security and construction coordination 
 
To secure the Large Load Transmission Customer’s obligations, the agreements require 
irrevocable security reasonably acceptable to each Transmission Owner (for example, a letter of 
credit, surety bond, or parent guaranty) in an amount equal to the capital cost of the covered 
upgrades.158  The agreements allow the customer to request a reduction in security, subject to the 
specified timing, documentation, and floor based on the remaining Minimum Contribution, and 
the Transmission Owner may not unreasonably deny a request consistent with those provisions.  
Under such terms, where the Large Load Transmission Customer and Transmission Owner are the 
same legal entity, the Transmission Owner is not required to demand security of itself but it is still 
subject to the requirement to protect against cost shifts.  The security provisions in the agreements 
exist to protect the Transmission Owner from financial risk associated with the capital costs of the 
Large Load Network Upgrade(s) and Transmission Customers from related cost shifts, and in 
analogous circumstances, the Commission has found it would be impractical and unnecessary to 
require security.159 
 
The Large Load Transmission Customer is required to provide security within 45 days of 
the parties’ execution of the agreements.160  If the agreements are filed unexecuted or as non-
conforming, however, separate terms apply, depending on when the Commission approves such 
agreement, as well as the nature of the parties’ dispute.  Failure to provide security within the 
applicable period results in immediate withdrawal of the Large Load Application.161 
 
154  Gudeman Testimony at 24. 
155  Proposed MISO Tariff, Attachment MMM, §§ IV.i—j.  
156  Gudeman Testimony at 24-25; Proposed MISO Tariff, Attachment MMM, § V. 
157  Gudeman Testimony at 25. 
158  Proposed MISO Tariff, Attachment LLL, § 4.1; Proposed MISO Tariff, Attachment MMM, § VI. 
159  See Midcontinent Indep. Sys. Operator, Inc., 156 FERC ¶ 61,166, at P 12 (2016); Gudeman Testimony at 19, 26. 
160  Gudeman Testimony at 19, 25. 
161  Proposed MISO Tariff, Attachment LLL, § 4.2; Proposed MISO Tariff, Attachment MMM, § VI.

PDF page 35

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 35 
 
 
Upon the Transmission Owner’s request, the Transmission Owner and Large Load 
Transmission Customer will enter into a separate agreement regarding construction of the covered 
upgrades.162  Such separate agreements do not displace the customer’s obligation to enter into a 
cost recovery agreement.  Where the security’s form, terms, and provider permit, security posted 
under a cost recovery agreement may satisfy the construction agreement’s security requirement.  
Similarly, if the Large Load Transmission Customer provides security under a construction 
agreement prior to providing the required security under the cost recovery agreement, the security 
required under the construction agreement may be applied as the required security under the cost 
recovery agreement if the forms, terms, and provider of the security under the construction 
agreement allow it.  Both pro forma agreements prohibit a lapse between the two arrangements 
and prohibit requiring the customer to concurrently maintain the full security amount under both.  
The pro formas also separately preserve applicable Tariff security and collateral requirements for 
Transmission Service.  The coordination provisions therefore address overlapping construction 
security while retaining the payment obligations secured by the cost recovery agreement. 
 
B. MISO Large Load Dashboard—Attachment FF, Section I.D.1.c.iv 
 
To ensure that MISO addresses the transparency requirements identified in the Show Cause 
Order, MISO is proposing Tariff language describing its commitment to sharing information 
related to large load integration through a public dashboard.  The Commission explained that it 
was “concerned about the apparent lack of (1) transparency regarding the assignment of Network 
Upgrades, and their associated costs, that are needed to provide transmission service to Eligible 
Customers on behalf of large loads . . .”163  The proposed Tariff changes address the Commission’s 
goals for transparency and information sharing.  
 
MISO’s proposed Large Load dashboard will identify the Large Load Upgrades that are 
needed and the costs associated with those upgrades.  Transmission Owners must provide MISO 
with information that may be publicly posted on its website including: 1) the aggregate amount of 
proposed Large Load additions by Large Load Transmission Customers, including in each 
Transmission Pricing Zone; 2) the planned Large Load Upgrades needed to provide the Large Load 
Transmission Customer Transmission Service, identified by type of equipment and Large Load 
Upgrade for each Large Load; and 3) cost estimates for those Large Load Upgrades.164  MISO’s 
proposed Tariff language closely follows the requirements of the Show Cause Order to ensure 
alignment with the Commission’s transparency requirements.165 
 
In accordance with the requirements of the Show Cause Order, MISO will provide data 
received from its Transmission Owners related to Large Load Upgrades on its public website and 
 
162  Proposed MISO Tariff, Attachment LLL, § 4.2.1; Proposed MISO Tariff, Attachment MMM, § VI.b. 
163  Show Cause Order at P 66.  
164  Id. at P 77. 
165   Compare Show Cause Order at P 77 with proposed Attachment FF, Section I.D.1.c.iv.

PDF page 36

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 36 
 
in a format that is searchable and allows users to filter the data.166 These proposed Tariff additions 
directly respond to the Commission’s request for “(1) robust, accurate, and systematic provision 
of data on MISO’s website in a single location, and in an easily accessible format that is searchable 
and allows users to filter the data, regarding the cost for Network Upgrades needed to provide 
transmission service to Eligible Customers on behalf of large loads.”167  As MISO presented to 
stakeholders in the LLWG, it is in the process of developing a Large Load Dashboard, which will 
depict a map of MISO’s footprint and the location of the Large Loads along with their associated 
Large Load Upgrades.168  The information displayed in the dashboard will be easily accessible on 
MISO’s website and searchable by users looking to learn more information about large load 
development in MISO’s footprint. The proposed Tariff requirements obligate Transmission 
Owners to provide MISO with updated information regularly, with the specific timeframes to be 
set forth in MISO’s BPM for Large Load.169 
 
The dashboard, along with the cost recovery agreements and associated materials, will 
provide a fuller picture of the costs associated with integrating Large Load in MISO’s footprint for 
the public, and will provide a useful input to state and other retail regulatory authorities in 
developing their own Large Load policies, rules, and regulations. 
 
C. Just and Reasonable Treatment.  
 
MISO and the MISO Transmission Owners submit that the proposed agreements address 
the concerns identified in the Show Cause Order and support just and reasonable rates by 
connecting each Large Load Upgrade to an enforceable minimum contribution from the Large 
Load Transmission Customer.  Put plainly, under the proposed framework, the Large Load 
Transmission Customer is always responsible for the costs of the Large Load Network Upgrade(s), 
thus, mitigating cost shifts to other Transmission Customers, consistent with the Show Cause 
Order.170 
 
166  Furnish Testimony at 25-26.  
167  Show Cause Order at P 67.  
168  MISO, Cost Shifting Risk Among Transmission Customers (LLWG-2026-8), Sept. 23, 2026, available at:  
20260923 LLWG Item 05 Cost Shifting Risk Among Transmission Customers (LLWG-2026-8)783359.pdf. 
169  This approach is consistent with the Rule of Reason given that the obligation is to update regularly and the specific 
reporting cadence is an implementation detail best address through BPMs and adjusted based on experience and 
the requirements of stakeholder. . See, e.g., Midcontinent Indep.  Sys.  Operator, Inc., 169 FERC ¶ 61,221, at P 
67 2019 (2019) (citing Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 
(2018)) (describing the rule of reason). 
170  Proposed MISO Tariff, Attachment LLL, §§ 3–5, 7.3; Proposed MISO Tariff, Attachment MMM, §§ III–VII; 
Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, PP 78–85 (2026), errata notice, 196 FERC ¶ 61,123 
(2026) (identifying the cost recovery, security, and revenue-credit concerns).

PDF page 37

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 37 
 
 
V. 
TRANSMISSION SERVICE OFFERINGS 
 
A. Overview and service selection. 
 
MISO proposes transmission service options that distinguish a customer seeking temporary 
non-firm transmission service while progressing toward full NITS from a customer electing an 
ongoing permanent firm and non-firm service mix.  Firm Service Step Up (“FSSU”) permits NITS 
service to increase as the required capability becomes available.  Interim NITS permits 
transmission service within approved non-firm limits while the remaining upgrades needed for full 
NITS are completed.   
 
The transmission service election determines the customer’s rights and obligations.  
Firmness addresses the availability and priority of Transmission Service; Resource Adequacy 
addresses the capacity needed to support demand.  The proposal treats those questions separately.  
Interim NITS remains in the capacity construct because it is a transition to full NITS service.  
Neither election authorizes withdrawals beyond the quantities and operating conditions established 
for that service. 
 
B. Firm Service Step Up. 
 
The FSSU process is designed to allow a Transmission Customer to obtain NITS in 
increments before all upgrades supporting its ultimate NITS requirement have been completed.  
As the relevant capability becomes available, a portion of the customer’s Interim NITS, described 
further below,  may convert to NITS while the remaining portion continues under the applicable 
interim restrictions.  The customer therefore can use available firm capability without assuming a 
firm entitlement to the full quantity before the system can support that service. 
 
The FSSU process is optional and allows NITS to be combined with Interim NITS.  At 
each step, the applicable firm NITS quantity remains tied to the capability supporting that step; 
any remaining interim quantity continues to be subject to its non-firm, Interim NITS, limits.  This 
distinction preserves the integrity of the service actually available while accommodating a 
customer’s phased development toward full NITS.171 
 
FSSU provides speed to power because it enables faster integration of incremental amounts 
of Large Load using firm service or Interim NITS.  Ms. Xie explains that an FSSU request may 
include a firm service component and Interim NITS component, allowing a portion of the 
customer’s non-firm service to convert to firm service before all required Upgrades are complete, 
with the remaining non-firm service continuing under the applicable Interim NITS operating 
limits.172  The FSSU proposal thus provides an expeditious option to obtain firm service, at least 
in part.  
 
 
171  Xie at 21. 
172  Id. at 20.

PDF page 38

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 38 
 
C. Interim NITS. 
 
The interim service developed through the Flexible Large-Load Interconnections and 
Transmission Service (“FLITS”) stakeholder work is referred to here as Interim NITS.  It allows 
a Transmission Customer taking NITS on behalf of a Large Load to begin receiving an approved 
quantity of non-firm service while the Network Upgrades required for full NITS are completed.  
The service is part of the NITS framework and uses the Attachment F NITS Service Agreement 
with a new exhibit for the Large Load, together with a corresponding Attachment G exhibit setting 
out the additional operating criteria.173 
 
The customer remains on a path to full NITS rather than selecting a permanent substitute 
for NITS.  When the required upgrades are completed and the conditions for full NITS are satisfied, 
full NITS begins.  Where FSSU is used, the interim agreement continues to govern the portion that 
has not yet converted to firm service. 
 
Charges for Interim NITS are determined under Schedule 9, and Interim NITS load is 
treated as Network Load in almost all cases under the proposed design.  An increase in the interim 
load quantity is reflected in the applicable Attachment F exhibit, but updating the exhibit does not 
establish additional system capability or authorize operation beyond the approved limit.  
Cumulative load growth of at least 25 MW requires the applicable LLPR study.174 
 
Interim NITS is subject to non-emergency operating restrictions and curtailment when 
required by transmission conditions.  During a Transmission Emergency, Interim NITS is curtailed 
after non-firm Point-to-Point service but before NITS and Firm Point-to-Point Transmission 
Service, and Firm GRITS.  Interim NITS is not curtailed solely to mitigate economic congestion.  
Its non-firm limits are tied to the transmission capability available before completion of the 
Upgrades supporting full NITS.175 
 
For Resource Adequacy, Interim NITS remains in the Coincident Peak Demand forecast 
and subject to the existing capacity requirements.  It consequently has the same priority as other 
Load with Firm Transmission Service during a Capacity Emergency, subject to its separate 
transmission limitations.  This treatment preserves capacity demand and investment signals for 
load progressing toward NITS and prevents interim non-firm transmission status from operating 
as a capacity exemption.176 
 
The non-firm portion does not receive Auction Revenue Rights (“ARR”) Entitlements and is 
excluded from the applicable Peak Usage calculation.  Firm load under the associated NITS 
 
173  Xie at 7. See also MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service—Interim NITS 
Option, LLWG-2026-5 (Sept. 23, 2026), stakeholder feedback request (identifying the FLITS work as addressing 
the Interim NITS option). 
174  Xie at 10. 
175  Id. at 19. 
176  Id. at 24.

PDF page 39

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 39 
 
arrangement remains eligible under the existing rules.  Interim NITS may register as a Load 
Modifying Resource (“LMR”), subject to the applicable requirements, while its non-firm portions 
are restricted from Demand Response Resource (“DRR”) and Emergency Demand Response 
(“EDR”) participation.  These distinctions preserve the relationship between the service quantity 
and the market and congestion benefits associated with firm service.177 
 
Interim NITS directly responds to the Commission’s preliminary finding that MISO’s Tariff 
lacks transmission services reflecting Eligible Customers taking service on behalf of flexible Large 
Loads willing and able to limit their use of the transmission system under certain conditions;178 it 
aligns the Interim NITS customer’s charges, curtailment priority, Resource Adequacy obligations, 
and market participation rights with its actual, interim non-firm use of the transmission system. In 
addition, Interim NITS protects existing transmission customers from undue cost shifting by 
requiring Interim NITS Load to be billed under Schedule 9 and to remain subject to existing 
Resource Adequacy requirements, and it is time-limited and structurally integrated into the 
existing NITS framework so that it functions as a genuine bridge to full firm service rather than a 
permanent alternative. Interim NITS is not unduly discriminatory or preferential because it is 
available on comparable terms. 
 
 
D. Reliability and rate treatment. 
 
The service options rely on enforceable withdrawal limits.  Metering, telemetry, model 
representation, communications, and operating controls provide the information and capability 
needed to administer those limits.  The Transmission Owner determines additional control 
technologies or protection systems needed for the particular arrangement and for which the Large 
Load Transmission Customer will be responsible, while MISO establishes the applicable service 
requirements and communicates directives through the relevant parties.  A commercial agreement 
identifying a limit does not eliminate the need to make that limit observable and enforceable in 
operations.179 
 
The proposed operating framework provides for remote-disconnection procedures, 
applicable unreserved-use consequences, and potential service termination when the customer 
does not comply with a required restriction.  Interim NITS participation as an LMR also remains 
subject to the applicable LMR requirements and penalties.  These provisions support the different 
curtailment priorities and protect the reliability expectations associated with firm service.  The 
customer’s ability to obtain non-firm service depends on accepting the limitations that define that 
service. 
 
The resulting differences are grounded in the rights provided.  Interim NITS remains 
associated with full NITS and its capacity obligation while accepting transmission limits during 
the transition.  Limiting ARR benefits to firm quantities likewise preserves the existing connection 
 
177  Id. at 25. 
178  See Show Cause Order at PP 102, 104.  
179  Xie Testimony at 11.

PDF page 40

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 40 
 
between firm Transmission Service and the congestion entitlement associated with it.  MISO 
submits that these distinctions support just and reasonable treatment of the different service 
arrangements. 
 
VI. 
LEGAL SHOWING AND RESPONSE TO THE SHOW CAUSE ORDER 
 
Section 205 requires jurisdictional rates, charges, and the practices affecting them to be 
just and reasonable and prohibits undue preferences and unreasonable differences in service.  (16 
U.S.C.  § 824d(a)–(b)).  MISO submits the proposed revisions under that standard.  The proposals 
respond to the Commission’s preliminary findings through the section 205 pathway expressly 
contemplated in the Show Cause Order and the Abeyance Order.  That procedural framework 
permits MISO to bring forward developed proposals while the Commission retains authority to 
address issues that the resulting filings do not resolve.180 
 
The application and study concerns are addressed by the combination of LLPR and the 
separately submitted IRR proposal.  LLPR identifies what the customer must submit and how the 
requested service is studied.  IRR supplies the proposed Large Load definition and requirements 
concerning visibility and operating performance.  Their interaction connects the information used 
in planning with the load behavior required after service begins.  The agreement and operating 
provisions then memorialize the obligations applicable to the resulting service.181 
 
The transmission service concerns are addressed by the additional service choices 
described in Section V.  Interim NITS supplies a temporary non-firm path while the upgrades 
needed for full NITS are completed.  FSSU allows incremental conversion where firm capability 
is available.  The applicable operating limits, capacity treatment, and charges reflect the particular 
rights accepted by the customer.  This approach implements the Commission’s recognition that 
service can account for a load’s willingness and ability to limit its use of the system.182 
 
The initial availability of the new service options is directed to Large Loads within the 
scope of this filing.  MISO’s proposal focuses the service, study, modeling, and operational 
changes on the category of load identified in the Show Cause Order.  Customers electing the same 
service are subject to its corresponding requirements.  The focused implementation also permits 
MISO to evaluate the consequences of broader eligibility before proposing that extension.183 
 
The generator interconnection and associated load issues are addressed through the 
complementary ZGIA and LARS pathways, read with the load’s applicable Transmission Service.  
 
180  Show Cause Order PP 33–38 (describing the response framework and the opportunity to develop section 205 
filings); Abeyance Order PP 8–11 (allowing the staged filings and preserving unresolved issues). 
181  Show Cause Order PP 39, 48–65 (addressing application, study, operational, and agreement provisions); IRR 
Transmittal at 1–4 (describing the proposed definition and operational requirements); Furnish Testimony at 16-
17, 22-23. 
182  Show Cause Order PP 100–105 (addressing interim NITS, contract-demand service, and flexible load). 
183  Xie Testimony at 21.

PDF page 41

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 41 
 
ZGIA addresses qualifying same-substation zero injection arrangements, while LARS coordinates 
the study of qualifying load and associated generation.  Neither form of Interconnection Service 
eliminates the separate need to identify the transmission and operating obligations of the load.  The 
proposed transmission service arrangements supply that additional part of the framework.184 
 
The proposed framework also respects the allocation of responsibilities between federal 
and state regulators.  The filing addresses jurisdictional Transmission Service, generator 
interconnection, and the associated planning and operating requirements.  It does not displace state 
authority over retail service or resource procurement and does not authorize retail arrangements 
prohibited by applicable law.  This distinction permits the transmission and interconnection 
provisions to operate within the existing regional regulatory framework.185 
 
MISO also submitted the July 20, 2026 Informational Report addressing resource adequacy 
and initiatives to accelerate generation additions.  That report described the roles of the states, load 
serving entities, and MISO and identified both existing reforms and proposals under development.  
The current filing complements those efforts by connecting the service election to the applicable 
planning assumptions and capacity treatment; it does not equate transmission firmness with a 
determination that capacity has been procured for the load.186 
 
MISO requests that the Commission consider this submission together with the related 
filings in evaluating the response to the Show Cause Order.  The Abeyance Order provides that 
timely section 205 filings addressing the preliminary findings suspend the filing respondents’ 
obligation to respond and continue the abeyance pending further direction.  It also preserves further 
consideration of issues not addressed by the filings.187 
 
A. Existing commercial arrangements and transition. 
 
Paragraph 123 of the Show Cause Order asks how implementation should account for 
existing agreements and agreements nearing execution.  The IRR filing addressed transition for 
the reliability requirements proposed there. 188  The present application and service provisions 
account for existing agreements and agreements nearing execution in several ways.  First, the 
LLPR process and requirements apply prospectively, with the first application deadline and LLPR 
cycle targeted for implementation date of Q1 of 2027.  Requests for transmission service to 
 
184  ZGIA Transmittal at 1–2, 6–7 (describing the proposal’s scope and the matters reserved for further work); LARS 
Transmittal at 3–6, 14–15 (describing coordinated load and generation studies and anticipated service provisions). 
185  Show Cause Order PP 42–47, 68–70 (discussing the respective federal and state responsibilities); ZGIA 
Transmittal at 22–23 (explaining that the associated-load provisions respect state restrictions on retail wheeling). 
186  Informational Report at 1–4, 6–11 (responding to the informational requirement and describing resource adequacy 
initiatives); Show Cause Order P 122 (requiring the report). 
187  Abeyance Order PP 9–11 (describing continued abeyance and the specificity expected for a request to terminate 
the proceeding in whole or in part). 
188  Show Cause Order P 123 (requesting briefing on implementation and protection of existing commercial 
arrangements); See MISO IRR filing, Docket No. ER26-3650, IRR Trans. Ltr. at 1 (identifying transition 
provisions for the IRR proposal).

PDF page 42

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 42 
 
accommodate Large Loads / study the Network Upgrades that have already commenced an EPR 
study will remain subject to that process and the proposed Tariff revisions neither require not allow 
projects that have already been processed through EPR or are in such process to transfer to the 
LLPR process. This respects existing commercial arrangements.  To the extent that a project has 
not already been studied for its impacts to the Transmission System, the costs of its impacts are 
not established and requiring such project to proceed through LLPR cannot disrupt established 
expectations.  Moreover, the LLPR study process is sufficiently similar to the EPR process in terms 
of timing and scope that requiring nascent projects (i.e., those that have not been submitted for 
study and costs established) will not introduce significant new delays or unfamiliar study practices.  
Finally, with respect to the cost recovery agreements required for projects that complete LLPR, 
MISO notes that such agreements, while imposing responsibilities on the Large Load Transmission 
Customer, do not purport to invalidate or override any agreements that may exist between the 
entity that owns the Large Load and the Large Load Transmission Customer, or prevent more 
granular assignment of costs by a retail regulator.189 Thus, the process appropriately prevents 
disruption to existing commercial arrangements and those nearing completion, while still ensuring 
that Commission goals are met prospectively.  
 
B. Effects on regional and local planning. 
 
Paragraph 124 asks how the new services affect planning, including uncertainty concerning 
the type, location, and quantity of flexible load.  LLPR evaluates the service requested through 
cumulative models coordinated with MTEP.  Interim NITS remains associated with completion of 
the facilities needed for full NITS.  These distinctions allow planning to reflect the service 
obligation rather than treat every maximum load quantity as an identical firm delivery 
requirement.190 
 
The separate firm and non-firm representation also makes the operational consequence of 
the planning assumption identifiable.  A customer receiving non-firm service remains bound by 
its applicable reservation and withdrawal limits; a conversion to firm service depends on the 
capability and approval supporting that conversion.  The study and operating arrangements 
therefore give effect to the same service election.  The separate withdrawal review for committed 
load further allows MISO to assess changes in the planning assumptions when a project does not 
proceed.191 
 
 
 
 
 
189   While MISO’s Tariff would make the Large Load Transmission Customer responsible for costs at the level of 
the MISO Tariff, it does not purport to prevent a Large Load Transmission Customer from recovering funds 
through commercial agreements with the Large Load.  
  
190  Show Cause Order P 124 (identifying the planning questions); Furnish Testimony at 4-5, 12-14 (describing 
cumulative models and MTEP coordination). 
191  Furnish Testimony at 15-16.

PDF page 43

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 43 
 
C. Cost recovery and financial security. 
 
In response to Show Cause Order’s concern regarding cost shifting among transmission 
customers related to large loads, MISO and the MISO Transmission Owners propose the Tariff 
revisions and pro forma LL-CRA and ITO-CRA described in Section IV.A of this transmittal.  As 
explained above, consistent with the concerns identified by the Commission in the Show Cause 
Order the proposed cost recovery agreements require “a specified minimum financial contribution 
and financial security sufficient to secure such contribution,” thus mitigating cost shifting if the 
Large Load Transmission Customer ultimately takes less Transmission Service than anticipated 
because the Large Load does not materialize as planned or is not developed at all.192  Moreover, 
as explained above and in Mr. Gudeman’s testimony, the Tariff and pro forma agreements ensure 
that payments made by a Large Load Transmission Customer to the Transmission Provider under 
the agreements will be appropriately credited toward Transmission Owners’ annual transmission 
revenue requirements in the event such costs are rolled into the Transmission Owner’s rates 
consistent with the Commission’s cost-of-service regulations.193  Lastly, the agreements provide 
that Transmission Owner will provide a workpaper in the annual informational filing detailing how 
any payments made pursuant to a cost recovery agreement are reflected in the Transmission 
Owner’s transmission formula rate, or not recovered from Transmission Customers, as 
applicable.194  
 
In response to paragraph 125, MISO proposes the LL-CRA and ITO-CRA described in 
Section IV.A as the contractual structures governing minimum cost contributions for the covered 
upgrades.  For rolled-in in-zone costs, the minimum is the Yearly Required Revenue Commitment 
supported by the twenty-year incremental revenue calculation, with attributable transmission 
revenues applied through the annual shortfall comparison.  For rolled-in impacted-owner costs, 
the minimum is the specified upgrade revenue-requirement payment over the applicable term.  
Each agreement also permits direct assignment.  The amount follows the upgrades identified for 
the requested service and the documented customer responsibility, rather than a uniform dollar 
charge applied to every Large Load. 
 
 
The financial security provisions initially use upgrade capital cost, permit specified 
adjustments and reductions, and provide draw and replenishment remedies.  The construction-
security coordination provisions avoid concurrently requiring full security under both a CRA and 
the corresponding construction agreement when compatible security can serve both.   
 
The pro formas do not establish a general substitution right for a retail-level agreement 
with the end-use Large Load.  Their express coordination provisions address the separate 
construction agreement’s security.   
 
 
 
192  Show Cause Order at P 84. 
193  See id. P 85. 
194  Id.

PDF page 44

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 44 
 
D. Alternative transmission technologies. 
 
Paragraphs 62 and 126 address evaluation of alternative transmission technologies and the 
explanation furnished when traditional upgrades are selected.  The LLPR application includes the 
Transmission Owner’s evaluation of alternative technologies and grid-enhancing technologies, 
and MISO reviews that information together with any further needs identified in the cumulative 
study.  When transmission issues arise, MISO and the Transmission Owners evaluate possible 
solutions in the mitigation process.  The resulting study report identifies the selected transmission 
solutions and the basis for the requested service.195 
 
The proposed consideration of alternatives is directed to whether a solution will satisfy the 
applicable planning criteria and provide a more efficient means of accommodating the request.   
MISO has specifically incorporated consideration of alternative transmission technologies 
(“ATTs”) and Grid Enhancing Technologies (“GETs”) as part of the LLPR. Proposed Attachment 
FF Section I.D.1.c.iii.b.2 requires Large Load Transmission Customers to include with their 
LLLPR Application the applicable Transmission Owner’s Interconnection Study Report, 
specifically identifying what ATTs and GETs were considered and what the outcome of that 
determination. Proposed Attachment FF, Section I.D.1.c.iii.e, which establishes the LLPR System 
Impact Study, specifically provides that MISO may consider alternative solutions, including those 
submitted by stakeholders.  These solutions will include any ATTs or GETs identified by 
stakeholders. Attachment FF, Section I.D.1.c.iii.e further provides that, in the event MISO 
identifies any Tranmission Issues during the study, MISO will collaborate with the Transmission 
Owners on the development of solutions, specifically including ATTs and GETS.  
 
Together, these proposed Tariff revisions embed a requirement to consider ATTs and 
GETS in the LLPR Study process and provide opportunities for stakeholders to suggest additional 
GETS or ATTs not initially identified in the study. Because this consideration is a part of the LLPR 
study, the basis for the proposed solution and alternatives considered will be included in the final 
LLPR Study report.196 Because LLPR will be the required core process for evaluation of all 
requests for Transmission Service to serve Large Loads, these requirements will apply uniformly 
to new Large Loads.  
 
MISO’s requested acceptance of those provisions is based on the evaluation and reporting 
requirements, rather than a customer’s ability to request consideration of an alternative outside the 
defined study process.197 
 
 
 
 
 
195  Show Cause Order PP 62, 126; Furnish Testimony at 13-14, 31. 
196   Furnish Testimony at 31 (explaining further that MISO will develop a standardized LLPR Study Report with 
sections that specifically address ATT/GETs considerations). 
197  Show Cause Order P 126 (addressing evaluation without a customer request, appropriate modeling, and the 
explanation of feasibility, cost, and timing when traditional upgrades are selected).

PDF page 45

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 45 
 
E. Generation participation and Resource Adequacy 
 
Paragraph 127 addresses market participation and Resource Adequacy treatment of 
generation serving co-located or electrically proximate load.  The ZGIA filing proposed 
participation as a Generation Resource, Dispatchable Intermittent Resource, Electric Storage 
Resource, or Behind the Meter Generation resource, subject to the limitation associated with 
serving the ZG Associated Load.  It also proposed registration and operating-limit provisions that 
provide visibility into gross load and generation and constrain the resource’s participation to the 
applicable configuration.198 
 
For capacity, the ZGIA proposal bases accreditation on participation type and limits it by 
reference to the identified associated load, with the specified adjustment for avoided losses.  It 
provides for use of ZG Resource credits through a Fixed Resource Adequacy Plan or Reliability 
Based Demand Curve Opt Out and restricts the use of uncleared and self-scheduled credits.  Those 
provisions reflect the limited reach of ZG Interconnection Service and avoid treating the resource 
as though it could serve unrelated regional load.199 
 
LARS follows a different interconnection pathway.  The filing requests Network Resource 
Interconnection Service, limits the requested interconnection service to 150 percent of the paired 
load’s peak demand, and requires the load and generation to be located in the same Local Resource 
Zone.  MISO explained that these criteria connect the generation to the associated need while 
allowing different fuel types and accreditation outcomes.  The study evaluates the pair’s full 
system impacts using the criteria applicable to other NRIS requests.200 
 
VII. 
DESCRIPTION OF PROPOSED TARIFF REVISIONS 
 
The proposed revisions implement the application and service framework across the 
relevant definitions, planning procedures, Transmission Service provisions, and agreements.  
LLPR establishes the application requirements, study sequence, model review, study report, and 
interfaces with MTEP and related study processes.  The corresponding defined terms and 
agreement provisions identify the request being studied, the responsible Transmission Customer, 
and the requirements applicable when the resulting service is provided.201 
 
The Transmission Service revisions establish the rights and conditions associated with 
Interim NITS and FSSU.  Interim NITS uses the existing Attachment F framework with the 
additional service exhibit and corresponding Attachment G operating criteria.  The related 
 
198  Show Cause Order P 127(a)–(b) (identifying the generator participation and accreditation questions); ZGIA 
Transmittal at 17–19, 22–23 (describing market registration, operating limits, and the proposed ZG Resource 
definition). 
199  ZGIA Transmittal at 18–20 (describing the proposed Module E-1 accreditation, forecast identification, FRAP, Opt 
Out, and credit-use provisions). 
200  LARS Transmittal at 10–11, 13 (describing the service, pairing, and study criteria and their relationship to 
Resource Adequacy). 
201  Furnish Testimony at 4, 11 (describing codification of the LLPR process).

PDF page 46

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 46 
 
modeling, Resource Adequacy, and ARR provisions distinguish the firm and non-firm components 
so that the same service election is reflected consistently in planning, operations, and settlements. 
 
The marked and clean Tariff records submitted as Tab A and B respectively, set out the 
revisions.  The following table of Tariff revisions is provided for reference and informational 
purposes only.  The language filed in the proposed Tariff revisions shall control in the event of 
any discrepancies between the information provided in this table and the proposed Tariff revisions.  
 
Tariff Section 
Tariff Section Title 
Brief Description of Changes 
Module A 
 
 
 
1.B – Definitions - B 
Update Baseload Usage to 
include Firm Transmission 
Service.  Update Behind the 
Meter Generation to add Interim 
NITS as a service. 
 
1.D – Definitions - D 
Update Demand Response 
Resource, Types I and II, to 
include Firm Transmission 
Service as an eligibility. 
 
1.F – Definitions - F 
Update Firm Service Step Up to 
establish a process for evaluating 
the reliability impact of planned 
incremental Load additions 
before full integration of a Large 
Load whose planning study has 
been approved through MTEP. 
Update Firm Transmission 
Service to cover Load served 
under Firm Point-to-Point 
Transmission Service or NITS 
and exclude Load service on a 
non-firm basis under Interim 
NITs. 
 
1.I – Definitions - I 
Updates to Impacted 
Transmission Owner Large Load 
Network Upgrade(s) to cover 
upgrades outside the 
Transmission Pricing Zone 
containing the Large Load’s 
Point(s) of Withdrawal that 
MISO identifies through Large 
Load Project Review as 
necessary for reliable service.  
Update to Interim NITS to 
provide for NITS reserved and

PDF page 47

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 47 
 
scheduled on an as-available 
basis and subject to curtailment 
or interruption under Section 
33.5. Updates to Interruptible 
Load, which now deems the 
portion of a Large Load served 
under Interim NITS to be 
Interruptible Load. 
 
1.L – Definitions - L 
Update to Large Load Network 
Upgrade to cover upgrades 
within the Transmission Pricing 
Zone containing the Large 
Load’s Point(s) of Withdrawal 
that MISO identifies through 
Large Load Project Review as 
necessary for reliable service. 
Update to Large Load 
Transmission Customer to 
include a Transmission Customer 
taking or requesting 
Transmission Service on behalf 
of a Large Load. Update to Load 
Zone to clarify that a Large Load 
receiving Interim NITS must 
represent its firm and non-firm 
portions as separate Load Zones 
and that neither zone may be 
combined with other Loads.  
 
1.N – Definitions - N 
Update to Network Integration 
Transmission Service to now 
include Interim NITS under 
Exhibit 4 of Attachment F unless 
the Tariff expressly provides 
otherwise. Update to Network 
Load to now include all portions 
of a Large Load taking Interim 
NITS under Exhibit 4 of 
Attachment F unless the Tariff 
expressly provides otherwise. 
Update to Non-Firm 
Transmission Service to cover 
Load served under Non-Firm 
Point-To-Point Transmission 
Service or Interim NITS under 
Exhibit 4 of Attachment F.

PDF page 48

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 48 
 
 
1.P – Definitions - P 
Update to Peak Usage to exclude 
the Interim NITS portion of a 
Large Load from the forecast 
NITS peak used to calculate Peak 
Usage for ARR allocation. Load 
associated with a Firm Service 
Step Up request enters the 
calculation only after all 
associated upgrades are 
complete. 
 
1.T – Definitions - T 
Update to Total Forecast Peak 
Load to excludes Load served 
through Interim NITS from the 
forecast NITS peak. It also 
excludes Load associated with a 
Large Load’s Firm Service Step 
Up request until all associated 
upgrades are complete. 
 
2.2 – Reservation Priority For Existing 
Firm Transmission Service 
Section 2.2 replaces references to 
“firm service” customers with 
references to customers taking 
the newly defined “Firm 
Transmission Service.” This ties 
rollover priority and the right of 
first refusal to qualifying firm 
service and excludes the non-
firm portion of Interim NITS. 
Module B 
 
 
 
I. Introduction 
Provides that a Large Load 
Transmission Customer must 
submit an application for LLPR 
review for Transmission Service 
to serve a Large Load as 
described in Attachment FF. 
 
III. Network Integration Transmission 
Service 
Provides that the rates, terms, 
and conditions governing 
Network Integration 
Transmission Service will 
generally apply to Interim NITS.  
 
28.1 – Scope of Service 
Provides that the Large Load 
Transmission Customer taking 
Interim NITS must coordinate 
with the applicable Transmission 
Owner to establish a Commercial 
Pricing Node associated with the

PDF page 49

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 49 
 
NITS service and a Commercial 
Pricing Node associated with 
Interim NITS service. 
 
28.3 – Network Integration Transmission 
Service 
Proposes revisions to clarify that 
the Transmission Provider and, 
as applicable, ITC will provide 
Network Integration 
Transmission Service, rather than 
Firm Transmission Service. 
 
29.1 – Condition Precedent for Receiving 
Service 
Proposes a new framework for a 
Large Load Transmission 
Customer to take Interim NITs 
and requiring that customer to 
identify the Load that will 
qualify for Firm Transmission 
Service and the amount of Load 
qualifying for Non-Firm 
Transmission Service. 
 
29.3 – Arrangements to be Completed 
Prior to Service 
Proposes revisions to clarify 
when Firm Network Integration 
Transmission Service and 
Interim NITS will commence.   
 
30.8 – Use of Interface Capacity by the 
Network Customer 
Adds a provision such that the 
use of Interface capacity to 
service the portion of a Network 
Customer’s Network Load 
served under Interim NITS shall 
be on an as-available basis and 
subject to all limitations, 
Curtailment, and Interruption 
provisions, and that inclusion of 
such Load in the Load-based 
usage limit does not confer a 
right to firm use of Interface 
capacity to serve that portion of 
Load. 
 
31.1 – Network Load 
Provides that Network Load will 
include all portions of a Large 
Load served on a non-firm basis, 
unless provided otherwise. 
 
31.5 – Changes in Service Requests 
Provides that a Large Load 
Transmission Customer is 
limited to one request to defer the 
start of the Network Integration 
Transmission Service up to a

PDF page 50

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 50 
 
period of 90 days.  Further 
provides that, if the Large Load 
does not commence operations or 
fails to operate at the approved 
level within 90 days of the 
requested Service 
Commencement Date, the 
Transmission Provider may 
revoke the approval for the 
amount of Network Integration 
Transmission Service that failed 
to begin operation.  Further 
provides that the Large Load 
Transmission Customer is not 
relieved of its obligation to pay 
the costs of the transmission 
facilities caused to be 
constructed. 
 
31.7 – Deferral of Service to Large Loads 
New section proposing the 
deferral of service to Large 
Loads until the construction of 
new transmission facilities is 
completed.  Provides that the 
Large Load Transmission 
Customer may request Interim 
NITS for the portion of any 
deferred service, which the 
Transmission Provider may defer 
if it determines that providing 
service would impair existing 
Firm Transmission Service. 
 
31.8 – Excess Withdrawal 
New section proposing that the 
Large Load Transmission 
Customer may not schedule the 
delivery of Energy to a Large 
Load in excess of the Firm 
Transmission Service that has 
been approved for the Load 
additions in the intervening step-
up period, and that any 
withdrawal in excess of the 
approved limit will be subject to 
charges and penalties.  Further 
provides that a Large Load 
Transmission Customer taking

PDF page 51

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 51 
 
Interim NITS may not schedule 
delivery of Energy to a Large 
Load in excess of the aggregate 
level of Firm Transmission 
Service and Non-Firm 
Transmission Service. 
 
33.5 – Allocation of Curtailments 
Proposes that Interim NITS will 
have a lower priority than (i) 
Firm Transmission Service and 
(ii) Transmission Service from 
Resources other than designated 
Network Resources for Network 
Customers not served under 
Interim NITS.  Among 
transactions under Interim NITS, 
Curtailments or Interruptions will 
begin with the Large Load with 
the most recent Service 
Commencement Date. 
 
33.7 – System Reliability 
Proposes that the Transmission 
Provider will be able to curtail 
Interim NITS service for 
reliability reasons and 
implements penalties if the Large 
Load Transmission Customers 
fails to cease or reduce service in 
response to such a directive.  If 
the Large Load Customer fails to 
cease or reduce service on two 
separate occasions within a 365-
day period, Interim NITS shall be 
permanently terminated.   
Module C 
 
 
 
38.5 – Load Aggregation 
Provides for limits on Load 
aggregation and clarifies each 
Large Load must be represented 
by a single Commercial Pricing 
Node and may not be aggregated 
or included in a Load Zone with 
other Commercial Pricing Nodes.  
Further provides that a Large 
Load taking both Firm and Non-
Firm Transmission Service will 
have separate Commercial 
Pricing Nodes for each service,

PDF page 52

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 52 
 
with Actual Energy Withdrawal 
first associated with the 
Commercial Pricing Node for 
Firm Transmission Service.  
Further provides that the 
Transmission Provider will 
maintain a list of defined 
Elemental Pricing Nodes that 
comprise a Large Load. 
 
38.6 – Aggregators of Retail Customers 
Provides that ARC registration 
will require an attestation by the 
ARC that no part of the DRR, 
LMR, or EDU is served through 
Interim NITS.  Further provides 
that for each Large Load 
registered by an ARC, the Large 
Load Transmission Customer 
must certify that the DRR, LMR, 
or EDR is being registered at a 
maximum Demand that is less 
than or equal to the total amount 
of Firm Transmission Service 
provided to the Large Load.  
Provides that a Large Load being 
registered by an ARC may not be 
included in an aggregation of 
other Loads.  
 
38.7.2 – Demand Response Resource 
Procedures 
Provides that only the portion of 
a Large Load served by Firm 
Transmission Service may 
register as a Demand Response 
Resource, and that the Market 
Participant must demonstrate that 
the portion of any Large Load 
being registered as a Demand 
Response Resource has Firm 
Transmission Service. 
 
42.6 – Partial-Year FTR Allocation 
Process for New ARR Zone(s) 
Proposes revisions to exclude the 
portion of a Large Load taking 
Interim NITS from Partial-Year 
FTR Allocation processes.  
 
43.2.4 – Nomination and Allocation of 
ARRs and MTPS ARRs 
Proposes revisions throughout 
the section to exclude the portion 
of a Large Load taking Interim 
NITS from the nomination and

PDF page 53

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 53 
 
allocation stages for Network 
Integration Transmission 
Service.  
Attachments 
 
 
Attachment F 
Form of Service Agreement For Network 
Service 
New Exhibit 2 adds transaction 
specification sheet for Large 
Load NITS that records the 
requested service, start date, and 
required upgrades.  It also 
confirms that any local 
Transmission Owner operating 
requirements apply in addition to 
the applicable Tariff 
requirements, including Section 
37A. 
 
New Exhibit 3 adds a transaction 
specification sheet for Firm 
Service Step Up that records the 
firm service level, start date, and 
required upgrades for each 
increment. Exhibit 4 adds a 
separate sheet for Interim NITS 
that records firm and non-firm 
service levels and the start and 
end dates for each transaction. 
Attachment G 
Form of Network Operating Agreement 
for Network Service 
Sections 3.0–5.0 set separate 
commencement rules for firm 
NITS and Interim NITS. Firm 
NITS commencement is tied to 
completion of the facilities and 
upgrades required for the 
applicable service, while Interim 
NITS requires MISO approval 
under new Exhibit F. The 
agreement also provides for 
service to end on a mutually 
agreed date or the transaction 
termination date. 
 
New Exhibit F allows non-firm 
Large Load identified in the Firm 
Service Step Up study to operate 
under Interim NITS before 
required upgrades are complete,

PDF page 54

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 54 
 
subject to Section 37A. MISO 
may curtail that service for 
reliability or operational reasons 
under Module B. 
Attachment FF 
Transmission Expansion Planning 
Protocol 
Section I.D.1.c establishes the 
LLPR process for new loads of 
50 MW or more and existing 
loads increasing by at least 25 
MW in the aggregate. It provides 
for three study cycles per year 
and sets out application 
requirements, deficiency and 
cure procedures, model 
development, system impact 
studies, and stakeholder review. 
 
Section I.D.1.c also establishes 
how MISO tenders the final 
study report and applicable cost 
recovery agreements under 
Attachments LLL and MMM. It 
specifies when upgrades are 
deemed approved for MTEP 
purposes, requires customer 
security for in-zone and out-of-
zone upgrades, and requires 
MISO to post proposed load 
additions, planned upgrades, and 
estimated costs in a searchable, 
filterable format. 
 
Section I.D.3 establishes the 
Firm Service Step Up study 
process for incremental service 
before full Large Load 
integration. It limits 
commencement to one 
incremental block per year and 
sets separate eligibility timing for 
firm NITS and Interim NITS. 
Both forms of incremental 
service end when service for the 
full Load begins.

PDF page 55

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 55 
 
Attachments FF-9, FF-10, and 
FF-11 add the Large Load 
Transmission Customer 
attestation, the LLPR System 
Impact Study Agreement, and the 
Critical Energy Infrastructure 
Information nondisclosure 
agreement, respectively. 
 
I.D.1.c – Large Load Transmission 
Service 
Proposes a new framework for 
Transmission Service to Large 
Loads including the Large Load 
Project Review (LLPR) process.  
 
I.D.1.c.i – Definitions 
Adds definitions for Large Load 
Network Upgrade(s), Impacted 
Transmission Owner Large Load 
Network Upgrade(s), the Large 
Load Cost Recovery Agreement 
(LL-CRA, Attachment LLL), and 
the Large Load Impacted 
Transmission Owner Cost 
Recovery Agreement (LLITO-
CRA, Attachment MMM).  
 
I.D.1.c.ii – Large Load Project Review 
Process Scope and Application 
Establishes a Large Load 
Application where different 
service options may be selected 
(LLPR, FSSU, Interim NITS, or 
LARS).  
 
I.D.1.c.iii – Large Load Project Review  
Provides for MISO to 
independently review the 
reliability impacts of Large 
Loads that require upgrades, in 
collaboration with the 
Transmission Owner(s) and 
Large Load Transmission 
Customer, with any system 
modifications presented through 
MTEP.  
 
Triannual Studies 
Requires LLPR studies three 
times in a 365-day period with 
application deadlines posted at 
least 90 calendar days in 
advance. Late applications will 
be reviewed in the next cycle.  
 
Requirements for LLPR Processing 
Identifies the application 
requirements including: data,

PDF page 56

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 56 
 
study files, reports, an attestation, 
non-refundable application fee,  
relevant study deposits, and 
confidentiality agreements.   
 
Review and Cure of Application 
Deficiencies 
Sets out the period of time that 
MISO has to review and identify 
deficiencies in the Large Load 
Application and defines the 
period of time the Large Load 
Transmission Customer has to 
cure any deficiencies.  
 
Model Build Period 
Requires LLPR models to be 
built from the latest MTEP cases, 
with specific comment windows 
and a target of completing within 
30 calendar days after the cure 
period.  
 
The LLPR System Impact Study 
Defines the scope of the study, 
the posting of applications, and 
deadlines for Transmission 
Owners to propose solutions 
(including ATTs/GETs); 
applications are withdrawn if 
issues remain unresolved. Also 
provides for the draft and final 
LLPR Study Reports and tender 
of the LL-CRA/LLITO-CRA.  
 
Resubmission of Large Load Applications 
and Removed Projects 
Allows a Large Load 
Transmission Customer whose 
application was removed to 
resubmit in a future LLPR study 
cycle after identifying what has 
changed.  
 
Stakeholder Forums 
Requires MISO to host 
stakeholder forums at least three 
times per year, followed by 
comment periods. Projects are 
deemed approved once the LL-
CRA and/or LLITO-CRA is 
executed or if unexecuted or non-
conforming, filed with the 
Commission, and the 
Transmission Owner must make 
a good faith effort to implement 
them.

PDF page 57

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 57 
 
 
Pro Forma LL-CRA and LLITO-CRA 
Requires a Large Load 
Transmission Customer to enter 
into a LL-CRA and/or LLITO-
CRA listing the required Large 
Load Network Upgrades, to limit 
cost shifting, and reduce 
speculative requests. The 
customer remains responsible for 
all applicable Transmission 
Service charges.  
 
Large Load Cost Recovery Agreement 
Imposes Minimum Contribution 
for the Large Load Network 
Upgrades. Also requires security 
equal to the estimated upgrade 
costs.  
 
Large Load Impacted Transmission 
Owner Cost Recovery Agreement  
Requires a separate LLITO-CRA 
with each affected Transmission 
Owner, under which the Large 
Load Transmission Customer is 
responsible for a Minimum 
Contribution for ITO-Large Load 
Network Upgrades and security 
to cover those upgrades.  
 
Tender and Execution of the Cost 
Agreement 
Gives the parties 15 business 
days to execute the tendered LL-
CRA/LLITO-CRA or request an 
unexecuted or non-conforming 
filing with the Commission; if 
they do neither, then the Large 
Load Application is deemed 
withdrawn and the project is 
removed from the LLPR process.  
 
I.D.1.c.iv – Operations Agreement and 
Confidentiality of LLPR Information  
Requires an updated load 
forecast and a NITS application 
under Module B, Section 29.2 
before service begins. Also 
requires the parties to keep non-
public LLPR information 
confidential under MISO’s 
universal NDAs.  
Attachment 
FF-9 
Large Load Project Review Attestation 
Form 
 New Tariff attachment 
Attachment 
FF-10 
LLPR System Impact Study Agreement 
 New Tariff attachment

PDF page 58

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 58 
 
Attachment 
FF-11 
LLPR Critical Energy Infrastructure 
Information NDA 
 New Tariff attachment 
Attachment 
LLL 
Form of Agreement for Large Load Cost 
Recovery Agreement 
 New Tariff attachment 
Attachment 
MMM 
Large Load Impacted TO Cost Recovery 
Agreement 
 New Tariff attachment 
 
 
VIII. 
STAKEHOLDER ENGAGEMENT 
 
MISO developed the Large Load proposals described herein through an iterative 
stakeholder process that began before issuance of the Show Cause Order.  EPR improvements and 
coordination of load and generator studies were discussed through the Planning Advisory 
Committee and Planning Subcommittee during 2024 and 2025.  ZGIA was introduced in 
December 2025 and developed through a subsequent planning committee and LLWG discussions.  
The LLWG then provided a dedicated forum for the planning, operations, markets, and Resource 
Adequacy questions implicated by Large Load integration.202 
 
The process included presentation of concepts, circulation of draft Tariff language, written 
feedback, and further revisions.  For example, the LARS proposal evolved from an initial 250 MW 
threshold to the 200 MW threshold filed with the Commission following stakeholder feedback.  
MISO also revised the proposed treatment of multiple generating facilities and contractual 
arrangements and clarified the representation of the load-generation pair.  These changes illustrate 
the relationship between the stakeholder process and the proposals brought forward in the staged 
filings.203 
 
The LLPR application and transmission service proposals continued and were developed 
through that process.  At the September 23, 2026, LLWG meeting, MISO reviewed the LLPR and 
identified the posted draft Tariff language, inviting feedback on the process and the proposed 
provisions.  MISO also presented the Interim NITS (initially presented as “FLITS”) option and 
sought feedback on its design.  Stakeholder comments addressed study readiness and timing, 
planning coordination, service limits, curtailment, and the transition to firm service.  These issues 
informed the continuing work on the relationship among the application, study, and operating 
provisions.204 
 
 
202  ZGIA Transmittal at 45–46 (describing EPR, coordinated study, and ZGIA discussions); LARS Transmittal at 49–
50 (describing the LLWG’s role and early work plan). 
203  LARS Transmittal at 50–52 (describing the July, August, and September discussions and the resulting changes to 
the proposal). 
204  MISO, LLWG, Application and Study Process Tariff and Process Design, LLWG-2026-7 (Sept. 23, 2026), 
feedback request and comments posted Oct. 7–8, 2026 (identifying the draft LLPR review and stakeholder issues); 
MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service—Interim NITS Option, LLWG-
2026-5 (Sept. 23, 2026), feedback request and comments posted Oct. 2, 2026 (addressing the interim service 
design).

PDF page 59

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 59 
 
MISO’s development of the present filing also reflects the need to coordinate the proposals 
with the earlier submissions.  The same load information and reliability assumptions must support 
the study process, the service election, and the operating agreement.  Stakeholder consideration of 
those interfaces has therefore proceeded alongside development of the individual service and study 
provisions.205 
 
Throughout the stakeholder process, MISO solicited feedback on what approach should be 
applied to developing processes and ensuring stakeholder protections.  MISO proposed, accepted 
feedback from stakeholders, and significantly modified many aspects of the Large Load effort.  As 
discussed below, some of the stakeholder process may be summarized in three categories: (1) cost 
transparency and recovery; (2) LLPR; and (3) Interim NITS. 
 
 
A. Cost Transparency and Recovery 
 
In the initial LLWG meeting, MISO identified cost efficiency as one of twelve 
considerations governing large-load integration.206  Stakeholder feedback proposed including cost 
allocation within cost efficiency or treating it as an additional consideration.207  MISO agreed to 
work with stakeholders to define solutions that fit within MISO’s scope. 
 
As previously discussed, throughout January and May of 2026, stakeholders raised cost 
transparency concerns while MISO concentrated on reliability requirements and expedited 
 
205  Abeyance Motion at 8–13 (explaining the need to align individual solutions with one another and existing MISO 
procedures); Abeyance Order P 8 (recognizing the opportunity for region-specific stakeholder solutions). 
206  Available at: 
https://cdn.misoenergy.org/20260130%20Large%20Load%20Workshop%20Presentation738349.pdf at 12. 
207  Available at: 
https://cdn.misoenergy.org/MISO%20Response%20to%20Large%20Load%20Workshop%20Considerations%2
0and%20Outcomes%20of%20Large%20Load%20Additions746069.pdf at 4, 13.

PDF page 60

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 60 
 
interconnection processes.208  In June, the Show Cause Order identified deficiencies in MISO’s 
Tariff concerning cost transparency and protections against cost shifting, but the Show Cause 
Order was clear that it was not intended to disturb existing regional cost-allocation methods.209 
 
In response to early stakeholder feedback and the Show Cause Order, MISO presented 
LLWG-2026-8 during the August 27, 2026 LLWG meeting to address an approach to address 
issues related to cost efficiency, transparency, and allocation.210  The issue covered a mechanism 
to mitigate the risk of cost shifting among transmission customers, Tariff updates to create a public 
data platform that provides transparency to state and local stakeholders regarding the assignment 
of Network Upgrades and their associated costs. Stakeholder feedback requested more information 
that estimated project costs.  MISO committed to developing a dashboard and pro forma recovery 
agreement while continuing to work to develop the minimum contribution formula.211 
 
At the September 9, 2026, LLWG meeting, MISO previewed the public dashboard intended 
to identify network upgrades associated with large load transmission service.212 Stakeholders 
generally supported the dashboard but some suggested additional measures were needed to prevent 
cost shifting.213 
 
At the September 23, 2026, LLWG meeting, MISO introduced a conceptual pro forma cost 
recovery agreement.214  MISO also illustrated how additional large load transmission revenue 
could offset upgrade costs and how a supplemental payment might protect existing customers if 
revenue were insufficient.  
 
At the October 8, 2026, LLWG meeting, MISO provided additional details regarding the 
proposed pro forma cost recovery agreement, including the calculation of minimum.  MISO also 
addressed the role of financial security and the treatment of payments through Transmission Owner 
annual informational filings.  Stakeholder feedback sought additional clarification regarding the 
 
208  Available at: https://cdn.misoenergy.org/20260420%20LLWG%20Item%2001b%20Agenda750857.pdf; 
https://cdn.misoenergy.org/20260514%20LLWG%20Item%2001b%20Agenda756827.pdf. 
209  Show Cause Order at P 82. 
210  Available at : https://cdn.misoenergy.org/New%20Issue%20-
%20Cost%20Shifting%20Risk%20Among%20Transmission%20Customers776496.pdf. 
211  Available at: 
https://cdn.misoenergy.org/LLWG%20Cost%20Transparency%20and%20Cost%20Shifting%20Response%20(
LLWG-2026-8)%20(20260827)786923.pdf. 
212  Available at: 
https://cdn.misoenergy.org/20260909%20LLWG%20Item%2005%20Cost%20Shifting%20Risk%20Among%2
0Tx%20Customers%20Cost%20Transparency%20(LLWG-2026-8)779833.pdf. 
213  Available at: 
https://cdn.misoenergy.org/LLWG%20Cost%20Shifting%20Risk%20Among%20Transmission%20Customers-
Cost%20Transparency%20Response%20(LLWG-2026-8)%20(20260909)789797.pdf. 
214  Available at: 
https://cdn.misoenergy.org/20260923%20LLWG%20Item%2005%20Cost%20Shifting%20Risk%20Among%2
0Transmission%20Customers%20(LLWG-2026-8)783359.pdf at 5-10.

PDF page 61

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 61 
 
calculation of the minimum contribution, the treatment of network upgrade costs, financial security 
requirements, and the interaction between the proposed agreement and existing transmission 
rates.215 
 
At the October 29, 2026 LLWG, meeting, specifically, in response to earlier feedback, 
MISO and the Transmission Owners clarified that the Large Load Transmission Customer is 
always responsible for the costs of the Large Load Upgrade(s) to mitigate the cost shifts to other 
Transmission Customers and changed the amount of financial security to be the capital cost of the 
Large Load Upgrade(s).  MISO also described how it will provide transparency through a 
combination of the outputs from the Large Load Project Review, the pro forma cost recovery 
agreement, Transmission Owner annual informational filings, and a transparency dashboard.216  
MISO revised payments to be prorated for staggered upgrade in service dates and addressed 
separated agreements for impacted Transmission Owners outside the relevant transmission pricing 
zone.  Additionally, the revised dashboard added Project Description and Cost Shared Status fields.  
Other updates in response to stakeholder feedback include the financial security holder, security 
amounts, security forms, and cost updates.  Feedback is now complete but suggests that the 
revisions addressed some stakeholder concerns.217 
 
B. LLPR 
 
At the August 27, 2026, LLWG meeting, MISO proposed a new Large Load Project 
Review (“LLPR”) process to integrate requirements from the Show Cause Order, incorporate 
enhancements from broader large-load efforts, and preserve the core functions of reliable 
integration.218  The initial design called for quarterly study cycles, cumulative MTEP studies, and 
continued monthly stakeholder meetings.  Stakeholder feedback expressed concerns about 
commercial confidentiality and premature contract commitments.219 
 
At the September 23, 2026, LLWG meeting, MISO proposed a refined approach after 
receiving stakeholder feedback, including replacing the Electric Service Agreement with an 
 
215  Available at: 
https://cdn.misoenergy.org/20261008%20LLWG%20Item%2004%20Cost%20Shifting%20Show%20Cause%20
%28LLWG-2026-8%29786862.pdf⁠ at 4–8; https://www.misoenergy.org/engage/stakeholder-
feedback/2026/llwg-cost-shifting-risk-pro-forma-cost-recovery-agreement-llwg-2026-8-20261008/⁠. 
216  Available at: 
https://cdn.misoenergy.org/20261029%20LLWG%20Item%2004%20Cost%20Shifting%20Risk%20Among%2
0Transmission%20Customers%20(LLWG-2026-8)791917.pdf at 2. 
217  Available at: https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-cost-shifting-risk-among-
transmission-customers-llwg-2026-8-20261029/. 
218  Available at: 
https://cdn.misoenergy.org/20260827%20LLWG%20Item%2005%20Large%20Load%20Application%20and%
20Study%20Process%20(LLWG-2026-7)777233.pdf. 
219  Available at: 
https://cdn.misoenergy.org/LLWG%20Large%20Load%20Application%20and%20Study%20Process%20Respo
nse%20(LLWG-2026-7)%20(20260827)786659.pdf.

PDF page 62

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 62 
 
attestation, tailoring studies to the type of transmission service requested, preserving the EPR for 
other projects, and proposed Tariff language.220   MISO also committed to a standardized report 
covering assumptions, upgrades, costs, schedules, and Advanced Transmission Technologies and 
Grid-Enhancing Technologies.221  
 
At the October 29, 2026, LLWG meeting, MISO presented a final LLPR process with 
application.  The LLPR included application, study, mitigation, reporting, and approval 
frameworks, as well as three annual study cycles, expanded readiness requirements and draft Tariff 
revisions.222 
 
C. Interim NITS 
 
MISO’s development of Firm Service Step-Up (“FSSU”) and Flexible Large-Load Interim 
Transmission Service, which was initially referred to as FLITS but is herein referred to as Interim 
NITS, reflects two related efforts to allow large loads to receive power which can be reliably 
transmitted before all transmission upgrades needed for full firm service are completed.  The two 
proposals developed separately but became interconnected as MISO responded to stakeholder 
feedback and the Show Cause Order. 
 
In April 2026, MISO recommended the Firm Service Step-Up initiative for consideration 
by the LLWG.223  At the April 20, 2026, LLWG meeting, MISO proposed a process to evaluate 
and grant firm service for partial load interconnection.224  The initial proposal was for a phased 
firm-service.  Feedback indicated that stakeholders generally supported a process to assess and 
grant firm service to facilitate the timely interconnection in large loads, but some pointed to a need 
for flexibility in how service level was granted.225  Other feedback opposed annual only studies, 
and some raised the possibility of non-firm service for a facility that might want some flexible load 
indefinitely.  The feedback established a need for multiple incremental steps and more flexible 
 
220  Available at: 
https://cdn.misoenergy.org/20260923%20LLWG%20Item%2004%20Tariff%20Defined%20Application%20an
d%20Study%20Process%20(LLWG-2026-7)782743.pdf. 
221  Available at: 
https://cdn.misoenergy.org/LLWG%20Application%20and%20Study%20Process%20Tariff%20and%20Process
%20Design%20Response%20(LLWG-2026-7)%20(20260923)791576.pdf. 
222   Available at: 
https://cdn.misoenergy.org/20261029%20LLWG%20Item%2006%20Large%20Load%20Application%20and%
20Study%20Process%20(LLWG-2026-7)791445.pdf. 
223  Available at: https://www.misoenergy.org/engage/MISO-Dashboard/firm-service-step-up-for-large-load-
interconnections/. 
224  Available at: 
https://cdn.misoenergy.org/20260420%20LLWG%20Item%2008%20Firm%20Service%20Step%20Up%20Ove
rview751418.pdf. 
225  Available at: 
https://cdn.misoenergy.org/MISO%20Feedback%20Response%20Firm%20Service%20Step%20Up%20(LLWG
-2026-1)%20(20260420)760062.pdf.

PDF page 63

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 63 
 
service timing, and MISO committed to developing further details in the process to provide clarity 
at the June LLWG. 
 
At the June 10, 2026, LLWG meeting MISO presented further details on the Firm Service 
Step Up process.226  MISO proposed quarterly study opportunities to identify how much firm load 
could be served reliability before all necessary upgrades were complete.227 MISO’s proposed 
process was more defined.  It now allowed requests through Transmission Owner and Load 
Serving Entity coordination following MTEP approval, the ability to request several incremental 
load blocks, and a 36-month horizon.  Feedback also indicated that MISO had largely responded 
to the need for more frequent studies and multiple steps but was adapting the proposal for 
upcoming stakeholder meetings.  Some stakeholders expressed concern whether requested in-
service dates could distort priority. 
 
At the July 16, 2026, LLWG meeting, MISO presented a refined FSSU process and initial 
Tariff language.228  A Bridge Interim Transmission Service Proposal was also presented by a 
stakeholder.229  MISO proposed to update the FSSU process and proposed to clarify terminology, 
define the step-up period, and adopt additional requirements.  The proposed Tariff language 
restricted requested load blocks to a minimum 25 MW step, limited to the number of network 
upgrade projects associated with the original full load integration study.  MISO proposed a 36-
month request horizon, and limits on additional upgrades and restudies.  Stakeholder feedback 
focused on provisions to correct terminology, a timing requirement for transmission service 
requests, and limiting incremental load blocks on an annual basis. 
 
At the August 12, 2026, LLWG meeting, MISO reviewed the initial proposal for a 
framework for Non-Firm Transmission Service for Large Loads called Flexible Large-load 
Interconnection and Transmission Service (FLITS).230  FLITS was proposed as a non-firm 
transmission service option for large loads, usable either temporarily while upgrades were 
completed or on a more permanent basis.  The proposal contemplated separate interim and 
permanent non-firm transmission service and worked alongside existing NITS and FSSU 
arrangements. MISO received a variety of feedback, though most stakeholders desired to see non-
 
226  Available at: 
https://cdn.misoenergy.org/20260610%20LLWG%20Item%2007%20Firm%20Service%20Step%20Up%20Stud
y%20Process763098.pdf. 
227  Available at: 
https://cdn.misoenergy.org/LLWG%20Large%20Load%20Firm%20Service%20Step%20Up%20Approach%20
Response%20(LLWG-2026-1)%20(20260610)769664.pdf. 
228  Available at: 
https://cdn.misoenergy.org/20260716%20LLWG%20Item%2008%20Firm%20Service%20Step%20Up%20Stud
y%20Process768776.pdf. 
229  Available at: 
https://cdn.misoenergy.org/20260716%20LLWG%20Item%2007c%20BITS%20Proposal_Alliant%20Energy76
8542.pdf. 
230  Available at: https://cdn.misoenergy.org/20260812%20LLWG%20Item%2006%20Conditional%20Non-
Firm%20Transmission%20Service%20(LLWG-2026-5)774185.pdf.

PDF page 64

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 64 
 
firm large load included in the Coincident Peak Demand forecast.  Others raised concerns over 
congestion prices, cost shifting, curtailment priority and other issues. 
 
At the August 27, 2026, LLWG meeting, MISO proposed revised Tariff language for the 
FSSU process.  In response to stakeholder feedback, MISO included terminology corrections, 
clarifications of requirements, limiting number of steps on an annual basis, and new requirements 
for submitting transmission service and load forecasts.  
 
On September 9, 2026, LLWG meeting, MISO posted a summary of stakeholder feedback 
taken into consideration to improve the design for non-firm Transmission Service.231  MISO 
reported that 12 respondents, including the OMS, supported including non-firm load in capacity-
demand forecasts, compared with two favoring exclusion and four requesting further discussion. 
MISO also corrected an error in its August presentation regarding settlement modeling.  MISO 
reported receiving 23 submissions and made several other identifiable changes.  
 
Incorporating this feedback, MISO also presented at the September 9, 2026, LLWG 
meeting, where MISO proposed changes to FLITS in response to stakeholder feedback.232  In 
response to feedback, MISO split the concept into interim FLITS and permanent Contract Demand, 
included all load in the Coincident Peak Demand forecast, removed the fixed ramp rate and 
required curtailment in a time specified by MISO. 
 
At the September 23, 2026, LLWG meeting, MISO presented changes to the FLITS 
proposal.233  MISO revised ARR entitlements to no longer be granted to the non-firm portion of 
the load and did not propose special rules for large loads in the Resource Adequacy construct.  
MISO also announced that it continued to develop a permanent non-firm Transmission Service 
option. 
 
MISO responded to stakeholder feedback by revising Attachment FF provisions for clarity, 
correcting redundant sections, and reorganizing provisions related to transmission service.234 
MISO also stated that BPM language was being developed to describe the study process and 
criteria details at the implementation level.  
 
 
231  Available at: https://cdn.misoenergy.org/Flexible%20Large-
Load%20Interconnection%20and%20Transmission%20Service%20(FLITS)%20Response%20(LLWG-2026-
5)780398.pdf. 
232   Available at: 
https://cdn.misoenergy.org/20260909%20LLWG%20Item%2006%20Non%20Firm%20Large%20Load%20(LL
WG-2026-5)780125.pdf. 
233  Available at: https://cdn.misoenergy.org/20260923%20LLWG%20Item%2007%20Conditional%20Non-
Firm%20Transmission%20Service%20(LLWG-2026-5)783425.pdf. 
234  Available at: 
https://cdn.misoenergy.org/LLWG%20Firm%20Service%20Step%20Up%20for%20Large%20Load%20Interco
nnections%20Tariff%20Response%20(LLWG-2026-1)%20(20260923)792368.pdf.

PDF page 65

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 65 
 
At the October 29, 2026, LLWG meeting, MISO presented proposed revisions to BPM-
020 addressing the FSSU study process, including study parameters, evaluation criteria, Interim 
Network Integration Transmission Service, and Qualified Changes.  MISO also presented 
revisions to the LLPR framework, including application requirements, study timelines, reliability 
assessments, identification of Network Upgrades, and coordination with Transmission Owners. 
MISO requested additional stakeholder feedback on both proposals to further refine the 
processes and implementation procedures.  
 
IX. 
DOCUMENTS SUBMITTED IN THIS FILING 
 
In addition to this Transmittal Letter, this submission includes the following materials, with 
the final tab and exhibit designations identified in the filing index: 
 
Tab A – Redline Tariff235 
 
Tab B – Clean Tariff 
 
Tab C – Testimony of Jeanna Furnish 
 
Tab D – Testimony of Zhaoxia Xie 
 
Tab E – Testimony and Exhibits of Greg M. Gudeman  
 
Tab F – Show Cause Order Briefing Questions and Answers 
 
 
X. 
EFFECTIVE DATE AND REQUEST FOR WAIVER 
   
MISO requests that the proposed revisions become effective 90-days from the date of filing 
(i.e., February 14, 2027). 
 
MISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. § 
35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable 
requirement of 18 C.F.R. Part 35 for which waiver is not specifically requested, if necessary, in 
order to permit Commission acceptance of this filing. 
 
235  Language currently pending before the Commission in the following, unrelated dockets is highlighted in yellow: 
ER26-3552-000; ER26-3650-000; and ER27-25-000.  MISO requests that the Commission treat such highlighted 
language as subject to the outcome of those pending proceedings.  If needed, MISO commits to file any revisions 
to this highlighted language as necessary to comply with any Commission orders in the proceeding. 
In addition, MISO has not included language that has future effective dates of 6/1/2027, 9/1/2027, and 6/1/2029, 
under Docket Nos. ER26-1882-001, ER25-1886-000, and ER22-1640-003;-006, respectively. MISO has also 
removed language that has a future effective date of 6/12/2028 and is pending in Docket No. ER26-2825-000. If 
needed, MISO commits to file any revisions to comply with any Commission orders in these proceedings and 
MISO commits to make subsequent filings with the Commission to reflect the most up-to-date version of the 
then-current Tariff provisions prior to the effective dates of the language.

PDF page 66

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 66 
 
 
XI. 
COMMUNICATIONS 
 
MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of 
Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the 
designation of more than two persons for service on behalf of MISO in this proceeding and requests 
all communications related to this filing be directed to: 
 
For MISO: 
 
 
 
 
 
For MISO: 
 
Michael Kessler  
Managing Assistant General Counsel 
Christopher D. Supino 
Managing Senior Corporate Counsel 
Midcontinent 
Independent 
System 
Operator, Inc. 
720 City Center Drive  
Carmel, Indiana 46032  
Telephone: (317) 249-5400 
mkessler@misoenergy.org 
csupino@misoenergy.org  
James C.  Holsclaw 
Lauren A. Stenger 
Calfee, Halter & Griswold LLP 
3900 Salesforce Tower 
111 Monument Circle 
Indianapolis, Indiana 46204 
Telephone: (317) 308-4266 
jholsclaw@calfee.com  
lastenger@calfee.com 
 
For MISO Transmission Owners: 
 
Wendy N. Reed 
Anna Fernandez 
Wright & Talisman, P.C. 
1200 G Street, N.W 
Suite 600 
Washington, D.C. 20005 
Telephone: (202) 393-1200 
reed@wrightlaw.com 
fernandez@wrightlaw.com 
 
XII. 
NOTICE AND SERVICE 
 
MISO has served a copy of this filing electronically, including attachments, upon all Tariff 
customers, MISO Members, Member representatives of Transmission Owners and non-
Transmission Owners, as well as all state commissions within the MISO Region and the 
Organization of MISO States. The filing has been posted electronically on MISO’s website at 
https://www.misoenergy.org/legal/ferc-filings/ for other parties interested in this matter.    
 
MISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. § 
35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable 
requirement of 18 C.F.R. Part 35 for which waiver is not specifically requested, if necessary, in 
order to permit Commission acceptance of this filing.

PDF page 67

The Honorable Debbie-Anne Reese 
November 16, 2026 
Page 67 
 
XIII. 
CONCLUSION 
 
For all of the foregoing reasons, MISO respectfully requests that the Commission accept 
this filing and grant waiver of any Commission regulations the Commission deems in order for the 
Commission to accept it as proposed. 
Respectfully submitted, 
 
/s/ Michael Kessler 
Michael Kessler  
Managing Assistant General Counsel 
Christopher D. Supino 
Managing Senior Corporate Counsel 
Midcontinent Independent System  
Operator, Inc. 
720 City Center Drive  
Carmel, Indiana 46032  
Telephone: (317) 249-5400 
mkessler@misoenergy.org 
csupino@misoenergy.org 
 
James C.  Holsclaw 
Lauren A. Stenger 
Calfee, Halter & Griswold LLP 
3900 Salesforce Tower 
111 Monument Circle 
Indianapolis, Indiana 46204 
Telephone: (317) 308-4266 
jholsclaw@calfee.com  
lastenger@calfee.com  
 
Attorneys for the Midcontinent Independent 
System Operator, Inc. 
 
Wendy N. Reed 
Anna Fernandez 
Wright & Talisman, P.C. 
1200 G Street, N.W 
Suite 600 
Washington, D.C. 20005 
Telephone: (202) 393-1200 
reed@wrightlaw.com 
fernandez@wrightlaw.com 
 
Attorneys for the MISO Transmission Owners