ER27-526-000 · 2026-11-16 · Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners

MISO and its transmission owners file large-load review, cost recovery and transmission service revisions under section 205

MISO and its transmission owners file tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-526-000. The filing adds a Large Load Project Review with a $250,000 application fee, two pro forma cost recovery agreements, a public dashboard, and two new services, Firm Service Step Up and Interim NITS.

Asks FERC to: Accept the revisions effective February 14, 2027, 90 days after filing, with a 30-day comment period.

Answers the order. Filed under section 205 by MISO and its transmission owners to answer the E-8 show cause order for MISO, alongside the companion GRITS filing and MISO's earlier large-load filings.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Application / study / operating requirements (P 6(a), p. 6) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Minimum cost recovery / security (P 119, p. 74) E-8 MISO: Alternative transmission technologies (P 119, p. 74)

Key points

  1. MISO says this filing, the companion GRITS filing and its pending large-load filings together answer FERC's concerns.
    MISO’s other pending Large Load filings fully addresses the concerns identified by the Commission PDF p. 5
  2. It builds on earlier filings already pending: zero-injection agreements, reliability requirements and the resource study.
    MISO has already filed several proposals responsive to the Show Cause Order that are currently pending before the Commission PDF p. 4
  3. A new Large Load Project Review would study every large-load service request, with deposits and milestones to deter speculative ones.
    The LLPR also includes deposits, project milestones, and other safeguards designed to discourage speculative Large Load requests. PDF p. 5
  4. Applicants pay a $250,000 non-refundable fee.
    a non-refundable application fee of $250,000 PDF p. 14
  5. Large-load customers would bear the cost of the upgrades built for them through cost recovery agreements.
    designed to ensure that the costs incurred to provide Transmission Service to Large Load Transmission Customers, including the costs of Large Load Upgrades (defined herein), are born by such customers PDF p. 5
  6. MISO would publish the location and estimated costs of large loads on a dashboard.
    The results of the LLPR periodically will be published to provide transparency into the location and estimated costs associated with Large Load facilities in the MISO region PDF p. 5
  7. Two new services, Firm Service Step Up and Interim NITS, would let customers take service in stages as they build out.
    The new Transmission Services available to Large Loads include Firm Service Step Up and Interim Non-Firm NITS service. PDF p. 5
  8. Loads of 200 MW or more partnered with a generator for at least 15 years go through the resource study instead.
    If the Large Load is greater than or equal to 200 MW and has formally partnered with a generator for a minimum of fifteen years, then the applicants will go through the LARS study process. PDF p. 15
  9. MISO says states and stakeholders did not agree on everything.
    While full alignment was not achieved on every aspect of the proposals PDF p. 4
  10. MISO asks for a February 14, 2027 effective date and a 30-day comment period.
    MISO requests that the Commission accept the proposed revisions effective 90 days from the date of this filing (i.e., February 14, 2027). PDF p. 3

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

The Honorable Debbie-Anne Reese November 16, 2026 Page 3 Transmission Customers resulting from a Transmission Customer’s taking of Transmission Service on behalf of a Large Load.10 MISO requests that the Commission accept the proposed revisions effective 90 days from the date of this filing (i.e.,…
Read this passage

I. EXECUTIVE SUMMARY

printed heading

I.
Read this passage

EXECUTIVE SUMMARY

printed heading · Topic match: Cost allocation

The LLPR also includes deposits, project milestones, and other safeguards designed to discourage speculative Large Load requests. • Large Load Transparency Dashboard – The results of the LLPR periodically will be published to provide transparency into the location and estimated costs associated…
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

BACKGROUND

printed heading

BACKGROUND This omnibus filing brings together the history and substance of MISO’s response to the Commission’s Show Cause Order.
Read this passage

A. The changing nature of load growth in the MISO region.

printed heading · Topic match: Reliability and curtailment

MISO must assess the transmission facilities needed to serve new demand, understand how the Load will behave during normal operations and system disturbances, and coordinate the addition of resources needed to support resource adequacy.
Read this passage

B. MISO’s existing processes and the development of a dedicated stakeholder forum.

printed heading · Topic match: Reliability and curtailment

ER26-3650-000, at 2- 3 (Aug. 28, 2026) (“IRR Transmittal”). 13 Informational Report at 1-3; Motion of MISO to Hold Proceeding in Abeyance and Request for Shortened Comment Period and Expedited Treatment, Docket No.
Read this passage

C. The Show Cause Order and the opportunity to develop regional solutions.

printed heading · Topic match: Filing procedure

The Show Cause Order also contemplated development of regional solutions through FPA section 205 filings and allowed requests for an abeyance of up to 14 Furnish Testimony at 17-18. 15 MISO, Transmittal Letter, Expedited Resource Addition Study, Docket No.
Read this passage

D. The earlier filings and the matters reserved for further development.

printed heading · Topic match: Connecting load and generation

MISO introduced the coordinated study concept at the July 16, 2026 LLWG meeting and sought feedback on eligibility, readiness, and protections against speculative requests.
Read this passage

E. The additional provisions now presented in this omnibus filing.

printed heading · Topic match: Connecting load and generation

The LLPR includes standardized applications, recurring study cycles, identification of necessary Upgrades, and the integration of the proposed interconnection reliability requirements.31 While only Transmission Owners were eligible to submit requests to the EPR process, MISO is proposing that only…
Read this passage

III. LARGE LOAD APPLICATION AND STUDY PROCESS

printed heading

The Honorable Debbie-Anne Reese November 16, 2026 Page 12 to provide Transmission Service to Large Load Transmission Customers.37 LLPR also promotes accountability, deters speculative or duplicative requests for Large Load-driven requests for Transmission Service, and provides transparency…
Read this passage

A. New Definitions for the LLPR Process

printed heading

Gudeman (“Gudeman Testimony) (describing the pro forma cost recovery agreements). 39 Furnish Testimony at 5. 40 In the transmittal letter, MISO paraphrases the LLPR process definitions, but the full definitions of each of these terms may be found in Section D.1.c.i of Attachment FF.
Read this passage

B. Applicability and Participant Responsibilities.

printed heading · Topic match: Connecting load and generation

LLPR builds from and adapts MISO’s existing Expedited Project Review (“EPR”) process and will be the required core study process for all requests for Transmission Service made on behalf of or in order to serve Large Loads.
Read this passage

C. LLPR Study Cadence, Timing, and Application Requirements—Attachment FF

printed heading · Topic match: Connecting load and generation

While the Large Load Application may only be submitted by the Transmission Customer, other parties including the Transmission Owner and the Large Load customer must all provide required information as part of the application.
Read this passage

D. Model Building and Coordination with MTEP and Existing Processes—

printed heading

Model Building and Coordination with MTEP and Existing Processes— Attachment FF Section I.D.1.c.iii.d Pursuant to proposed Section I.D.1.c.iii.d, MISO will commence developing models for all LLPR studies no later than five (5) business days after the conclusion of cure period.82 MISO will use…
Read this passage

E. The LLPR System Impact Study—Attachment FF Section I.D.1.c.iii.e.

printed heading

The Honorable Debbie-Anne Reese November 16, 2026 Page 20 MISO will post all the Large Load Applications that will be included in the upcoming LLPR System Impact Study to its MTEP webpage on its public website, thus facilitating the transparency requirements identified in the Show Cause Order.89 In…
Read this passage

F. Tender and Processing of the Cost Recovery Agreements—Attachment FF

printed heading

MISO proposes the date of filing of an unexecuted or nonconforming filing as point where the application should be deemed approved for inclusion in MTEP as reasonable compromise between providing certainty in modeling for the next LLPR study cycle and maintain the accelerated study cadence…
Read this passage

G. Resubmission of Withdrawn Applications—Attachment FF Sections I.D.1.c.iii.g

printed heading

The Large Load Transmission Customer may submit a new Large Load Application to MISO but must identify what information has 105 While this date does not provide as much certainty as the date of Commission acceptance, a project is still more likely to be developed after a service agreement is filed…
Read this passage

H. Stakeholder Forums—Attachment FF Sections I.D.1.c.iii.h.

printed heading

Stakeholder Forums—Attachment FF Sections I.D.1.c.iii.h.
Read this passage

I. Cost Recovery Agreements—Attachment FF Section I.D.1.c.iii.i.

printed heading · Topic match: Connecting load and generation

ER27-25, all LARS Associated Transmission Customers that submit LARS Applications for inclusion in a LARS cycle with a kickoff date on or after February 14, 2027, shall execute or request the unexecuted and/or non-conforming filing of the LL-CRA and/or LLITO-CRA, as applicable, for all Network…
Read this passage

IV. COST RECOVERY AGREEMENT AND COST TRANSPARENCY

printed heading · Topic match: Connecting load and generation

ER27-25-000 (“LARS Answer”) at 15. 124 This proposed language is severable from LARS because acceptance LARS was designed to work even with existing processes and then be integrated with the reforms contained in this filing once accepted by the Commission..
Read this passage

A. Cost Recovery Agreements

printed heading · Topic match: Cost allocation

MISO proposes two complementary pro forma cost recovery agreements to establish the Large Load Transmission Customer’s financial responsibility for the Large Load Upgrades identified through the LLPR study process.
Read this passage

B. MISO Large Load Dashboard—Attachment FF, Section I.D.1.c.iv

printed heading

Transmission Owners must provide MISO with information that may be publicly posted on its website including: 1) the aggregate amount of proposed Large Load additions by Large Load Transmission Customers, including in each Transmission Pricing Zone; 2) the planned Large Load Upgrades needed to…
Read this passage

C. Just and Reasonable Treatment.

printed heading · Topic match: Cost allocation

Put plainly, under the proposed framework, the Large Load Transmission Customer is always responsible for the costs of the Large Load Network Upgrade(s), thus, mitigating cost shifts to other Transmission Customers, consistent with the Show Cause Order.170 166 Furnish Testimony at 25-26. 167 Show…
Read this passage

V. TRANSMISSION SERVICE OFFERINGS

printed heading

V.
Read this passage

A. Overview and service selection.

printed heading · Topic match: Reliability and curtailment

MISO proposes transmission service options that distinguish a customer seeking temporary non-firm transmission service while progressing toward full NITS from a customer electing an ongoing permanent firm and non-firm service mix.
Read this passage

B. Firm Service Step Up.

printed heading

The FSSU process is designed to allow a Transmission Customer to obtain NITS in increments before all upgrades supporting its ultimate NITS requirement have been completed.
Read this passage

C. Interim NITS.

printed heading · Topic match: Reliability and curtailment

These distinctions preserve the relationship between the service quantity and the market and congestion benefits associated with firm service.177 Interim NITS directly responds to the Commission’s preliminary finding that MISO’s Tariff lacks transmission services reflecting Eligible Customers…
Read this passage

D. Reliability and rate treatment.

printed heading · Topic match: Reliability and curtailment

These provisions support the different curtailment priorities and protect the reliability expectations associated with firm service.
Read this passage

VI. LEGAL SHOWING AND RESPONSE TO THE SHOW CAUSE ORDER

printed heading · Topic match: Filing procedure

LLPR identifies what the customer must submit and how the requested service is studied.
Read this passage

A. Existing commercial arrangements and transition.

printed heading · Topic match: Filing procedure

Paragraph 123 of the Show Cause Order asks how implementation should account for existing agreements and agreements nearing execution.
Read this passage

B. Effects on regional and local planning.

printed heading

Paragraph 124 asks how the new services affect planning, including uncertainty concerning the type, location, and quantity of flexible load.
Read this passage

C. Cost recovery and financial security.

printed heading · Topic match: Cost allocation

In response to Show Cause Order’s concern regarding cost shifting among transmission customers related to large loads, MISO and the MISO Transmission Owners propose the Tariff revisions and pro forma LL-CRA and ITO-CRA described in Section IV.A of this transmittal.
Read this passage

D. Alternative transmission technologies.

printed heading

Because this consideration is a part of the LLPR study, the basis for the proposed solution and alternatives considered will be included in the final LLPR Study report.196 Because LLPR will be the required core process for evaluation of all requests for Transmission Service to serve Large Loads,…
Read this passage

E. Generation participation and Resource Adequacy

printed heading · Topic match: Connecting load and generation

The filing requests Network Resource Interconnection Service, limits the requested interconnection service to 150 percent of the paired load’s peak demand, and requires the load and generation to be located in the same Local Resource Zone.
Read this passage

VII. DESCRIPTION OF PROPOSED TARIFF REVISIONS

printed heading · Topic match: Reliability and curtailment

The language filed in the proposed Tariff revisions shall control in the event of any discrepancies between the information provided in this table and the proposed Tariff revisions.
Read this passage

I. Introduction

printed heading

Introduction Provides that a Large Load Transmission Customer must submit an application for LLPR review for Transmission Service to serve a Large Load as described in Attachment FF.
Read this passage

III. Network Integration Transmission

printed heading · Topic match: Reliability and curtailment

Further provides that a Large Load Transmission Customer taking The Honorable Debbie-Anne Reese November 16, 2026 Page 51 Interim NITS may not schedule delivery of Energy to a Large Load in excess of the aggregate level of Firm Transmission Service and Non-Firm Transmission Service. 33.5 –…
Read this passage

Attachment F

printed heading

Attachment F Form of Service Agreement For Network Service New Exhibit 2 adds transaction specification sheet for Large Load NITS that records the requested service, start date, and required upgrades.
Read this passage

Attachment G

printed heading · Topic match: Cost allocation

The Honorable Debbie-Anne Reese November 16, 2026 Page 57 Pro Forma LL-CRA and LLITO-CRA Requires a Large Load Transmission Customer to enter into a LL-CRA and/or LLITO- CRA listing the required Large Load Network Upgrades, to limit cost shifting, and reduce speculative requests.
Read this passage

VIII. STAKEHOLDER ENGAGEMENT

printed heading · Topic match: Connecting load and generation

The same load information and reliability assumptions must support the study process, the service election, and the operating agreement.
Read this passage

A. Cost Transparency and Recovery

printed heading · Topic match: Cost allocation

As previously discussed, throughout January and May of 2026, stakeholders raised cost transparency concerns while MISO concentrated on reliability requirements and expedited 205 Abeyance Motion at 8–13 (explaining the need to align individual solutions with one another and existing MISO…
Read this passage

B. LLPR

printed heading

LLPR At the August 27, 2026, LLWG meeting, MISO proposed a new Large Load Project Review (“LLPR”) process to integrate requirements from the Show Cause Order, incorporate enhancements from broader large-load efforts, and preserve the core functions of reliable integration.218 The initial design…
Read this passage

C. Interim NITS

printed heading · Topic match: Reliability and curtailment

It now allowed requests through Transmission Owner and Load Serving Entity coordination following MTEP approval, the ability to request several incremental load blocks, and a 36-month horizon.
Read this passage

IX. DOCUMENTS SUBMITTED IN THIS FILING

printed heading

DOCUMENTS SUBMITTED IN THIS FILING In addition to this Transmittal Letter, this submission includes the following materials, with the final tab and exhibit designations identified in the filing index: Tab A – Redline Tariff235 Tab B – Clean Tariff Tab C – Testimony of Jeanna Furnish Tab D –…
Read this passage

X. EFFECTIVE DATE AND REQUEST FOR WAIVER

printed heading

EFFECTIVE DATE AND REQUEST FOR WAIVER MISO requests that the proposed revisions become effective 90-days from the date of filing (i.e., February 14, 2027).
Read this passage

XI. COMMUNICATIONS

printed heading

COMMUNICATIONS MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all…
Read this passage

XII. NOTICE AND SERVICE

printed heading

MISO also requests waiver of Section 35.13 of the Commission’s regulations, 18 C.F.R. § 35.13 (2026), to the extent applicable to this filing, and requests waiver of any other applicable requirement of 18 C.F.R.
Read this passage

XIII. CONCLUSION

printed heading

XIII.
Read this passage

CONCLUSION

printed heading

CONCLUSION For all of the foregoing reasons, MISO respectfully requests that the Commission accept this filing and grant waiver of any Commission regulations the Commission deems in order for the Commission to accept it as proposed.