ER27-531-000 · 2026-11-16 · PJM Interconnection, L.L.C.

PJM files large-load tariff revisions and co-location compliance changes under section 205

Back to sections and commentary

PDF page 1

UNITED STATES OF AMERICA 
BEFORE THE 
FEDERAL ENERGY REGULATORY COMMISSION 
 
 
 
 
PJM Interconnection, L.L.C.  
) 
Docket No. ER27-____-000 
 
 
 
 
 
 
PROPOSED TARIFF REVISIONS FOR LARGE LOADS AND ADDITIONAL 
COMPLIANCE WITH CO-LOCATION ORDER AND REQUEST FOR 
EXTENDED 60-DAY COMMENT PERIOD 
 
 
 
 
 
 
Mark J. Stanisz 
Associate General Counsel 
PJM Interconnection, L.L.C. 
2750 Monroe Blvd. 
Norristown, PA  19403-2429 
610-666-4707 
mark.stanisz@pjm.com    
 
Christopher B. Holt  
Managing General Counsel 
PJM Interconnection, L.L.C. 
2750 Monroe Blvd. 
Audubon, PA  19403-2429 
610-666-2368 
christopher.holt@pjm.com 
 
       Wendy B. Warren 
Ruth M. Porter 
Alexander L. Peterson 
Wright & Talisman, P.C. 
1200 G Street, NW, Suite 600 
Washington, DC  20005-3898 
202-393-1200 
warren@wrightlaw.com 
porter@wrightlaw.com 
peterson@wrightlaw.com 
 
 
Counsel for PJM Interconnection, L.L.C. 
 
November 16, 2026

PDF page 2

TABLE OF CONTENTS 
 
I. 
INTRODUCTION .................................................................................................. 7 
II. 
BACKGROUND .................................................................................................. 10 
A. 
2025 Show Cause Orders ...........................................................................10 
1. 
February Order ...............................................................................10 
2. 
December Order .............................................................................11 
B. 
Compliance Filings and Paper Hearing Procedure ....................................12 
1. 
Thirty-Day Compliance Filing .......................................................12 
2. 
Sixty-Day Compliance Filing ........................................................13 
3. 
Paper hearing procedures ...............................................................13 
C. 
June 2026 Orders .......................................................................................14 
1. 
Co-Location Order .........................................................................14 
2. 
Large Load Show Cause Order ......................................................15 
D. 
Partial Extension and Partial Compliance Filing .......................................16 
E. 
PJM’s Stakeholder Engagement Process ...................................................18 
III. 
OVERVIEW OF PROPOSED CHANGES .......................................................... 22 
A. 
Part III—NITS ...........................................................................................22 
1. 
NITS quantity for Large Load .......................................................22 
2. 
Information updates .......................................................................23 
3. 
50 MW limit on netting Behind the Meter Generation ..................24 
B. 
Part VIII—Fast Energization Process ........................................................27 
1. 
The Fast Energization Process is designed for speed and 
accuracy .........................................................................................27 
2. 
The Fast Energization Process includes a Soft Close Date 
and Early Application Engagement to improve the quality 
of Applications and reduce disputes and litigation ........................30 
3. 
Timing of Fast Energization Process implementation and 
the interim period ...........................................................................30 
4. 
PJM is eschewing parallel processes, to streamline for 
speed and accuracy ........................................................................32 
5. 
PJM will maintain transparency of its study results ......................33

PDF page 3

ii 
C. 
Part XI—New Transmission Services .......................................................33 
1. 
Interim NITS ..................................................................................33 
2. 
Contract Demand Transmission Service ........................................37 
3. 
Common service provisions for Interim NITS and 
Contract Demand Transmission Services ......................................42 
4. 
Pro Forma Service Agreement for Interim NITS 
(Attachment F-3A) .........................................................................45 
5. 
Pro Forma Service Agreement for Contract Demand 
Transmission Service (Attachment F-4) ........................................48 
D. 
Re-Filing Co-Located Load Compliance Changes ....................................50 
1. 
Prohibition on serving Co-Located Load from existing 
generators .......................................................................................50 
2. 
Expansion of service to “Eligible Load” for load with 
BTMG ............................................................................................52 
3. 
Elimination of new GIA requirement ............................................54 
4. 
Effective date only .........................................................................57 
E. 
Changes to Be Addressed in Future Filings ...............................................57 
IV. 
THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES 
AS JUST AND REASONABLE .......................................................................... 59 
A. 
The Proposed Fast Energization Process Is Just and Reasonable 
and Advances the Commission’s Categories for Reform in the 
June 2026 Orders .......................................................................................59 
B. 
Core Features of the Fast Energization Process That Enhance the 
Current Cycle Process ................................................................................60 
1. 
PJM’s current process provides only some visibility into 
the transmission needs created by Large Loads .............................60 
2. 
Resource Adequacy requires getting new generation 
online faster ....................................................................................60 
3. 
Incremental and parallel fixes are not enough – a singular 
process for generation and transmission service requests 
yields efficiencies...........................................................................61 
4. 
The Fast Energization Process is a single, unified process 
that should be twice as fast as the current process .........................62 
5. 
Technology and early engagement speed the process ...................63

PDF page 4

iii 
6. 
Study consolidation preserves study rigor .....................................64 
7. 
Readiness requirements are moved to the front of the 
process............................................................................................65 
8. 
A portfolio approach to system reinforcements provides 
transparency and certainty .............................................................66 
9. 
Interim rights allow service to begin sooner ..................................67 
C. 
The Fast Energization Process Is Consistent with the Large Load 
Show Cause Order’s Directives .................................................................68 
1. 
Timely, clear, and consistent study of transmission 
service for large loads ....................................................................69 
2. 
Readiness requirements that deter speculative requests ................70 
3. 
Transparency regarding upgrades and their costs ..........................71 
4. 
Protection against cost shifting ......................................................71 
5. 
Transmission services that reflect flexible use of the 
system ............................................................................................73 
6. 
Studying generation and transmission service requests to 
serve Large Load together leverages technology and 
innovation ......................................................................................73 
7. 
PJM’s proposal respects existing commercial 
arrangements and provides for a clear transition from the 
existing process to the Fast Energization Process..........................75 
D. 
The New Transmission Services Proposed in Part XI are Just and 
Reasonable .................................................................................................77 
E. 
PJM’s Proposed Changes to NITS are Just and Reasonable .....................79 
V. 
EFFECTIVE DATE .............................................................................................. 82 
VI. 
CONSENT TO SEVERANCE OF ISSUES ......................................................... 82 
VII. 
DOCUMENTS ENCLOSED ................................................................................ 84 
VIII. 
CORRESPONDENCE AND COMMUNICATIONS .......................................... 85 
IX. 
SERVICE .............................................................................................................. 85 
X. 
CONCLUSION ..................................................................................................... 87

PDF page 5

1200 G Street, N.W., Suite 600 
Washington, D.C.  20005-3898 
Phone: 202.393.1200 
Fax: 202.393.1240 
wrightlaw.com 
 
November 16, 2026 
 
 
Honorable Debbie-Anne A. Reese 
Secretary  
Federal Energy Regulatory Commission  
888 First Street, NE, Room 1A 
Washington, DC  20426 
 
Re: 
PJM Interconnection, L.L.C., Docket No. ER27-____-000  
Proposed Tariff Revisions for Large Loads and Additional Compliance with 
Co-Location Order and Request for Extended 60-Day Comment Period 
 
Dear Secretary Reese:  
Pursuant to section 205 of the Federal Power Act (“FPA”),1 part 35 of the Federal 
Energy Regulatory Commission’s (“Commission”) regulations,2 and the August 14, 2026 
letter order issued in Docket No. EL26-67-000,3 PJM Interconnection, L.L.C. (“PJM”) 
hereby proposes revisions to Parts I, III, VI, VII, VIII, IX, X, and XI, and Attachments F-3, 
F-3A, and F-4 of PJM’s Open Access Transmission Tariff (“Tariff”), and to Schedule 8 of 
the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region 
(“RAA”).4  With the reforms proposed here and the other filings being concurrently 
 
1 16 U.S.C. § 824d. 
2 18 C.F.R. part 35.   
3 PJM Interconnection, L.L.C., 196 FERC ¶ 61,129, at P 10 (2026) (noting that to extent PJM submits “an 
FPA section 205 filing addressing the Commission’s preliminary findings in the Show Cause Order on or 
before November 16, 2026, then the obligation of the respondent(s) who have made such an FPA section 205 
filing to file a response to the Show Cause Order will be suspended”). 
4 The PJM Transmission Owners (“Transmission Owners”) are separately filing revisions to Tariff, Parts 
VIII, IX, and XI to add provisions concerning the allocation of the costs of system reinforcements needed for 
generator interconnection and transmission service for Eligible Loads and Large Loads, a cost-recovery 
framework for those system reinforcements, and proposed rates for the three new transmission services PJM 
proposes to offer.  PJM concurrently is filing ride-through provisions for Large Computational Load to 
mitigate against future incidents like the one that occurred July 22, 2026, in the PJM Region, along with other 
proposed operational requirements and annual transmission service reporting requirements.  That filing, and 
all evidence submitted in support thereof, is incorporated by reference into this filing.  Given the multiple 
same-day filings and the fact that these filings are making changes, some of them overlapping, to over 100

PDF page 6

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 2 
 
2 
submitted today as described in Attachment D, PJM has responded fully to the Large Load 
Show Cause Order and requests that the FPA section 206 aspect of the order be closed.  
The Tariff revisions PJM proposes include: 
• Revisions to the terms and conditions for Network Integration Transmission 
Service (“NITS”)5 to impose new terms and conditions on Eligible Customers 
taking transmission service on behalf of Eligible Load (including specifically 
Co-Located Load and customers with Behind the Meter Generation (“BTMG”)) 
and Large Loads;6 
• Revisions to Part VIII of the Tariff to create the new Fast Energization Process, 
which will study together New Service Requests, including Generation 
Interconnection Requests, and requests from Eligible Customers seeking 
transmission service on behalf of Eligible Load and Large Load7 in a single, 
12-month process;8 
• Addition of the new Part XI to the Tariff, providing the terms and conditions 
for new transmission services (Interim NITS, Firm Contract Demand (“FCD”) 
Transmission 
Service, 
and 
Non-Firm 
Contract 
Demand 
(“NFCD”) 
 
Tariff sections in nine parts of the Tariff, PJM expects it will need to make one or more clean-up filings in 
the future to ensure the Tariff is clear, and commits to doing so.  PJM will promptly submit a letter in Docket 
Nos. EL25-49 and EL26-27 informing participants in those dockets of today’s tariff filings, some parts of 
which are submitted in compliance with Commission directives and others of which are submitted pursuant 
to Section 205 of the FPA.  In an abundance of caution, PJM requests waiver of any regulation or filing 
requirements relating to submissions in Docket Nos. EL25-49 and EL26-27 relating to today’s tariff 
filings.  Good cause exists to grant any necessary waivers because submission of these tariff filings in the 
structure presented efficiently addresses the complexity of the overlapping filing obligations and differing 
requested effective dates, PJM is requesting a sixty-day comment period and 120 day Commission action 
date that affords interested participants reasonable time to engage in the tariff filing dockets. 
5 Terms not otherwise defined herein shall have the meaning set forth in the Tariff, the RAA, or Amended 
and Restated Operating Agreement of PJM Interconnection, L.L.C. (“Operating Agreement”). 
6 See infra Section III.A. 
7 The Commission accepted PJM’s definition of “Large Load” as “end-use customer(s) load that has a 
cumulative peak load of 50 [megawatts (“MW”)] or greater at a single electrical site behind one or more 
points of interconnection, where for configurations involving multiple affiliated load facilities or multiple 
points of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-
mile radius will be considered a single electrical site as further described in the PJM Manuals” in its 
October 9, 2026 order in Docket No. ER26-3515-000.  PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at 
PP 13, 24 (2026).  That definition is now in the RAA, Article I, Definitions, and cross-referenced in Tariff, 
Parts I and VIII.  PJM Interconnection, L.L.C., Thirty-Day Compliance Filing to the Commission’s 
October 9, 2026 Order on PJM’s Large Load Definition and Large Load Registry, Docket No. 
ER26-3515-002 (Nov. 9, 2026). 
8 See infra Section III.B.

PDF page 7

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 3 
 
3 
Transmission Service) available to Eligible Customers taking transmission 
service on behalf of Eligible Load and Large Load;9 and 
• Revised versions of Tariff provisions concerning Co-Located Load and BTMG 
pending in Docket No. ER26-1479-002,10 which PJM has reevaluated and 
revised in connection with its response to the Order Instituting Proceeding 
Under Section 206 of the FPA (“Large Load Show Cause Order”).11 
PJM’s proposed revisions address the Commission’s areas of concern in the Large 
Load and Co-Located Load show cause proceedings:  promotion of reliability; efficient 
transmission service study processes; cost transparency and mitigation of cost-shifting; 
flexible load service; accommodating Co-Located Loads and BTMG; and generation study 
procedures for generators serving electrically proximate Large Loads and Co-Located 
Loads.  PJM proposes to add to its Tariff an enhanced process to identify and study 
transmission service for new Large Loads. PJM will require Large Loads (i.e., loads over 
50 MW at a single location) to be identified on a registry to set a baseline for the current 
level of transmission service.12  PJM will then require any new requests for transmission 
service or requests to increase existing service beyond the baseline level to apply for that 
service and be studied.13  In evaluating such requests, PJM proposes to use a new, reformed 
“Fast Energization Process,” to make the study process faster, even more focused on 
 
9 See infra Section III.C. 
10 See infra Section III.D.  Revisions to these Tariff provisions were filed initially on August 17, 2026, PJM 
Interconnection, L.L.C., Compliance Filing of PJM Interconnection, L.L.C. in Response to Order on 
Rehearing, Clarification, Compliance Filing, and Paper Hearing in Docket Nos. EL25-49-002, et al, Docket 
No. ER26-1479-002 (Aug. 17, 2026) (“August 17 Filing”), in compliance with the Commission’s 
June 18, 2026 order in Docket Nos. EL25-49-000, et al.  PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 
(“Co-Location Order”), notice of denial of reh’g by operation of law & providing for further consideration, 
196 FERC ¶ 62,089 (2026).  Earlier today, PJM filed a motion to withdraw the August 17 Filing in Docket 
No. ER26-1479-002 so that it could file replacement revisions in this filing. 
11 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, errata notice, 196 FERC ¶ 61,122, order dismissing 
requests for reh’g & clarification, 196 FERC ¶ 61,214 (2026). 
12 See Attachment A-1, Proposed Tariff, Part III, General. 
13 See infra Section III.A.

PDF page 8

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 4 
 
4 
readiness and certainty, and provide enhanced transparency.14  The Fast Energization 
Process proposes key reforms to the existing process to complete studies in 12 months.15  
PJM’s Fast Energization Process will study requests for transmission service and 
Generation Interconnection Requests together to optimize the Transmission System and 
yield efficiencies for electrically proximate load and generation.16     
PJM also proposes implementing the three new transmission services the 
Commission put forward in a way that will ensure reliability, with technical and operational 
limitations on withdrawals of energy by flexible Large Loads and Eligible Loads, and on 
injections of energy by Eligible Generating Facilities. 
In short, this filing responds in a unified fashion to two separate show cause orders, 
one that has been ongoing for almost two years, with briefing and several compliance 
filings required, and a second issued only five months ago, with overlapping concerns and 
considerations.  A chart detailing where each directive from the Co-Location Order and the 
Large Load Show Cause Order (together, “June 2026 Orders”)17 is addressed is provided 
as Attachment D to this filing.18  In light of the resulting scope and complexity of this filing, 
PJM respectfully requests that the Commission establish a 60-day comment period for this 
filing, to allow all interested parties sufficient time to review the proposed revisions and 
for PJM to continue to engage with stakeholders after filing to potentially further improve 
and augment the proposals set forth in this filing.  PJM further requests a Commission 
 
14 See infra Section III.B. 
15 See infra Section III.B. 
16 See infra Section III.B. 
17 Co-Location Order, 195 FERC ¶ 61,209; Large Load Show Cause Order, 195 FERC ¶ 61,211.  
18 See generally Attachment D, Chart Mapping Order Directives to Tariff Changes attached hereto.

PDF page 9

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 5 
 
5 
order on this filing within 120 days.  The Commission’s full acceptance of this filing within 
10 months of the date it is filed would likely be necessary to facilitate implementation in 
time for Cycle 02.19   
As PJM discussed in the PJM Abeyance Motion,20 the Commission’s June 2026 
Orders presented certain interrelated and overlapping issues that PJM needed to address in 
a holistic, coordinated manner.21  PJM noted in the PJM Abeyance Motion that the June 
2026 Orders directed PJM to expand the availability of new transmission services, enhance 
its Large Load study procedures, and detail the operational requirements and control 
technologies that customers taking transmission service on behalf of certain loads must 
use.22  PJM submitted a partial compliance filing on August 17, 2026, that addressed certain 
directives of the Co-Location Order.23   
Since the August 17 Filing, and as PJM worked on its response to the Large Load 
Show Cause Order, PJM has determined that it must amend its earlier filing to comply with 
the Co-Location Order to harmonize the treatment of Eligible Loads and Large Loads.  PJM 
therefore seeks an effective date of March 16, 2027, for certain Tariff revisions in Part VIII 
relating to Eligible Loads and for the revisions in Part III and the new Part XI, to establish 
available services as soon as practicable.  PJM seeks an indefinite effective date for the 
 
19 See infra Section III.B.3 (explaining that the Submission Window for the first Cycle under the Fast 
Energization Process would open in late November 2027). 
20 PJM Interconnection, L.L.C., Motion of PJM Interconnection, L.L.C. to Hold Proceeding in Abeyance and 
Request for Shortened Answer Period and Expedited Treatment, Docket No. EL26-67-000, at 4-8 (July 28, 
2026); PJM Interconnection, L.L.C, Motion for Extension of Time for Specified Compliance Requirements 
and Request for Expedited Treatment of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al., at 
4-8 (July 28, 2026) (“PJM Extension Motion”).  
21 See supra note 10. 
22 PJM Abeyance Motion at 4-5. 
23 PJM Abeyance Motion at 1, 6-7; PJM Extension Motion at 1-2, 6-7.

PDF page 10

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 6 
 
6 
Fast Energization provisions of Part VIII, as the Fast Energization Process cannot begin 
until Cycle 01 of PJM’s current interconnection process is sufficiently advanced.24 
Each element of this proposal is just and reasonable.  However, if the Commission 
deems necessary, and to help facilitate the Commission’s acceptance of this filing without 
delay so that PJM can comply expeditiously with the June 2026 Orders, PJM provides 
notice that it consents to the Commission’s exercise of authority to sever any element of 
the Proposed Tariff and RAA language to the extent necessary and permitted under sections 
205 and 206 of the FPA and NRG Power Marketing, LLC v. FERC.25  
PJM submits this filing pursuant to its independent authority to modify its Tariff 
under FPA section 205 pursuant to Tariff, Part I, section 9.2(a) and the Consolidated 
Transmission Owners Agreement (“CTOA”), section 7.5.1(ii), following the requisite 
consultation specified under Tariff, Part I, section 9.2(b) and the CTOA, section 7.5.1(ii). 
 
24  In order to avoid intervening proposed Tariff revisions from other filings potentially causing the Tariff 
revisions herein to be overwritten, PJM has included revisions with proposed effective dates of 
March 16, 2027, in certain of the Tariff sections with indefinite dates that are attached hereto as Attachment 
A-2.  Specifically, the changes proposed to the following Tariff sections with a proposed March 16, 2027 
effective date have been added into the proposed revisions in the version of the marked Tariff with an 
indefinite effective date:  Tariff, Part VIII, section 400, Definitions C, E, N, P, and R; and Tariff, Part VIII, 
sections 401, 403, 404, 406, 408, and 414.  When PJM makes a compliance filing to establish the effective 
date for the sections listed here that it is filing with indefinite effective dates, assuming they are accepted, it 
will address the earlier language and update its status as well.  
25 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).  As the Commission has often stated, 
“[t]he United States Court of Appeals for the District of Columbia Circuit has held that, in certain 
circumstances, the Commission has ‘authority to propose modifications to a utility’s [FPA section 205] 
proposal if the utility consents to the modifications.’”  N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051, 
at P 22 n.36 (2024) (alteration in original) (citing NRG Power Mktg., 862 F.3d at 114-15); see Midcontinent 
Indep. Sys. Operator, Inc., 180 FERC ¶ 61,141, at P 26 n.29 (2022) (same), order on reh’g, 182 FERC 
¶ 61,096 (2023), aff’d sub nom., Entergy Ark., LLC v. FERC, 109 F.4th 583 (D.C. Cir. 2024); ISO New Eng. 
Inc., 175 FERC ¶ 61,172, at P 16 n.20 (2021) (same).

PDF page 11

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 7 
 
7 
I. 
INTRODUCTION 
As it is elsewhere in the country, data center construction and operation is causing 
unprecedented load growth in the PJM Region.26  PJM’s 2025 long-term load forecast 
shows a peak load growth of 32 gigawatts (“GW”) from 2024 to 2030, with 30 GW of that 
growth coming from data centers.27  PJM’s 2026 long-term load forecast projects a 3.6% 
annual increase in its summer peak load over the next 10 years;28 in 2023, PJM projected 
just a 0.8% annual increase over a 10-15 year horizon.29  The extraordinary growth of data 
centers and other Large Loads presents unique reliability and resource adequacy challenges 
as compared to traditional loads.  Data centers have significant energy and capacity 
demands and can be built faster (12-18 months) than the generation and transmission 
facilities necessary to meet those demands.30  The North American Electric Reliability 
Corporation (“NERC”) recognizes this as a resource adequacy issue, explaining that Large 
Loads are “magnitudes larger than most loads historically seen on the system and 
 
26 RTEP 2024: Regional Transmission Expansion Plan, PJM Interconnection, L.L.C., 47 (Apr. 17, 2025), 
https://www.pjm.com/-/media/DotCom/library/reports-notices/2024-rtep/2024-rtep-report.pdf 
[https://perma.cc/PV4N-VA3P] (explaining that there is significant load growth in the PJM Balancing 
Authority Area due to new construction of data centers).  As the Commission also has recognized, Large 
Loads have unique operational characteristics, including significant load fluctuations.  As noted earlier, PJM 
is concurrently proposing ride through requirements and other operational requirements in a separate section 
205 filing.   
27 Letter from David E. Mills, PJM Board of Managers Chair, PJM Interconnection, L.L.C. to PJM 
Stakeholders, 1 (Aug. 8, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-
disclosures/2025/20250808-pjm-board-letter-re-implementation-of-critical-issue-fast-path-process-for-
large-load-additions.pdf [https://perma.cc/977B-93NW].  
28 PJM Resource Adequacy Planning Department, 2026 PJM Load Forecast Report, PJM Interconnection, 
L.L.C., 6 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-
load-report.pdf [https://perma.cc/6BPF-LJYA].  
29 PJM Resource Adequacy Planning Department, PJM Load Forecast Report: January 2023, PJM 
Interconnection, L.L.C.,  3 (Jan. 2023), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-
forecast/2023-load-report.ashx [https://perma.cc/XG66-PBQK].  
30 Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, North America 
Electric Reliability Corporation, 15-16 (July 2025), https://www.nerc.com/globalassets/who-we-
are/standing-committees/rstc/3_doc_white-paper-characteristics-and-risks-of-emerging-large-loads.pdf 
[https://perma.cc/HVX5-8J9V] (“NERC Large Loads White Paper”).

PDF page 12

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 8 
 
8 
proliferating more quickly than most historical load growth” and therefore “the need for 
additional generation may not have been planned for, and current system plans may not be 
able to meet it.”31  Additionally, unlike traditional loads, Large Loads can materialize and 
grow quickly in geographically concentrated areas,32 which makes them more difficult to 
plan for than other loads.33  In the Large Load Show Cause Order, the Commission 
recognized the material differences between Large Loads and other load categories, 
explaining that “integrating large loads poses specific challenges to transmission system 
operation given their size, operational behavior, and unique potential to impact the 
transmission system.”34  
To meet this moment, the Commission, on its own motion and in response to 
section 205 filings, has issued a number of landmark orders stimulating innovation and 
advancement.  In parallel, the PJM Five-Year Strategy released September 1, 2026, sets 
forth how PJM will lead during the next five years and beyond, with reliability as its North 
Star.35  The third objective of the PJM Five-Year Strategy, titled “Proactively Adapt 
Planning Processes,” includes multiple workstreams to achieve this objective.  These 
include:  (1) a one-year generation interconnection process; (2) incorporating Large Load 
 
31 NERC Large Loads White Paper at 16.  
32 See Declaration of Donald Bielak, P.E. on Behalf of PJM Interconnection, L.L.C. (Attachment C) ¶ 15 
(“Bielak Decl.”) (“Large Loads differ fundamentally from traditional loads in their size, pace of growth, and 
concentration, and they are presently the major source of load growth in the PJM Region.”). 
33 NERC Large Loads White Paper at 16 (“The arrival and timing of large loads is also frequently 
uncertain. . . .  Some proposed large loads do not materialize as planned: they may be canceled due to 
economic and financial challenges or other setbacks.  Due to the uncertainty of these large loads 
materializing, forecasting load for resource adequacy and transmission planning may be much more 
difficult.”).  
34 See Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 58.  
35 Corporate Strategy and Value, PJM Interconnection, L.L.C., https://www.pjm.com/about-pjm/corporate-
strategy-and-value [https://perma.cc/N92H-AQZ8] (last visited Nov. 14, 2026).

PDF page 13

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 9 
 
9 
forecasting and modeling into planning processes; (3) determining interim solutions for 
near-term reliability needs; and (4) creating a synchronized planning and interconnection 
process for greater efficiency and transparency.36  These objectives align closely with the 
Commission’s Large Load Show Cause Order, offering PJM an opportunity to accelerate 
its strategic timeline.   
Through this filing, PJM responds to the Large Load Show Cause Order, consistent 
with strategic objectives to proactively adapt PJM’s planning processes to deliver 
accelerated interconnection and transmission service and processes.  PJM proposes to 
efficiently, reliably, and transparently provide transmission service to both co-located and 
flexible Large Loads (i.e., Large Loads that are not co-located with generation, but are 
willing and able to limit their energy withdrawals from the Transmission System under 
certain conditions)37 and to quickly bring additional generation online to meet current and 
forecasted demand from Large Loads.  PJM further proposes Tariff revisions to provide 
just and reasonable terms and conditions of service for the provision of transmission 
service, including the new transmission services the Commission first advanced for Co-
Located Load in PJM and then proposed more broadly in show cause orders for all the 
jurisdictional Regional Transmission Organizations, including the Large Load Show Cause 
Order directed to PJM and Transmission Owners in the PJM Region.38   
PJM also seeks to meet the need for “speed to power” and accelerate its generation 
interconnection procedures to a one-year process by leveraging technology and process 
 
36 Shaping a Power Change: PJM Five-Year Strategy, PJM Interconnection, L.L.C., 9 (Aug. 2026), 
https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-
powerful-change-pjm-five-year-strategy.pdf [https://perma.cc/2RBY-MPLH]. 
37 See Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 85 n.178. 
38 See generally Large Load Show Cause Order, 195 FERC ¶ 61,211.

PDF page 14

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 10 
 
10 
efficiencies.  PJM will deliver at each turn of its new process non-binding good-faith 
estimates of the cost and time to construct facilities within 60-90 calendar days, consistent 
with the Commission’s findings in the Large Load Show Cause Order.39  To provide 
transmission service to Eligible Loads and Large Loads as contemplated in the June 2026 
Orders, PJM proposes to add transmission service requests to the existing New Service 
Request study process in Tariff, Part VIII, which will allow PJM to optimize upgrades to 
the Transmission System, eliminate duplicative upgrades, and offer timely transmission 
service and generator deliverability based on current system topology rather than requiring 
customers to wait on contingent upgrades to be built.  With the reforms proposed here and 
the supplemental filings PJM proposes to make, addressed in Section III.G below, PJM has 
responded fully to the Large Load Show Cause Order and requests that the FPA section 
206 aspect of the order be closed. 
II. 
BACKGROUND 
A. 
2025 Show Cause Orders 
1. 
February Order 
Following a technical conference discussing the co-location of large loads at 
generating facilities, the Commission initiated a show-cause proceeding against PJM and 
the Transmission Owners  on February 20, 2025 (“February Order”).40  In the February 
Order, the Commission expressed concern that PJM’s Tariff did not address co-location 
arrangements with sufficient clarity and consistency.41  The Commission made several 
 
39 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 63; Bielak Decl. ¶ 21.  
40 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, order on show cause, 193 FERC ¶ 61,217 (2025) 
(“December Order”), order on compliance, 195 FERC ¶ 61,030, order on reh’g, clarification, compliance & 
paper hearing, Co-Location Order,195 FERC ¶ 61,209. 
41 February Order, 190 FERC ¶ 61,115, at P 2.

PDF page 15

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 11 
 
11 
preliminary findings that the Tariff appeared to be unjust and unreasonable regarding co-
location arrangements, and it directed PJM and the Transmission Owners to respond to 
numerous questions addressing its concerns.42 
2. 
December Order 
On December 18, 2025, the Commission issued an order on show cause finding the 
Tariff unjust and unreasonable due to, among other reasons, the lack of specificity for the 
rates, terms, and conditions that apply to Interconnection Customers43 serving Co-Located 
Load and Eligible Customers taking transmission service on behalf of Co-Located Load.44  
The December Order directed PJM to make a compliance filing within 30 days to, among 
other things, clarify the rates, terms, and conditions that apply to an Interconnection 
Customer seeking to serve Co-Located Load with new generation.45  The December Order 
also directed PJM to make a compliance filing within 60 days to revise the Tariff in a 
number of ways, including to modify the retail BTMG netting rules to limit netting over a 
certain threshold46 and to require that an Eligible Customer taking transmission service on 
behalf of a Co-Located Load select at least one of three transmission services:  (1) NITS 
or Interim NITS; (2) FCD Transmission Service; or (3) and NFCD Transmission Service.47  
 
42 February Order, 190 FERC ¶ 61,115, at PP 74-75, 87-88. 
43 Under PJM’s current interconnection rules in Tariff, Parts VII, VIII, and IX, Interconnection Customers 
are referred to as “Project Developers.”  PJM uses in this filing the term used in its current interconnection 
rules, but it should be understood as consistent with the Commission’s references to Interconnection 
Customers.  
44 December Order, 193 FERC ¶ 61,217, at P 159. 
45 December Order, 193 FERC ¶ 61,217, at PP 232-35. 
46 December Order, 193 FERC ¶ 61,217, at P 221. 
47 December Order, 193 FERC ¶ 61,217, at P 193.

PDF page 16

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 12 
 
12 
The December Order established a paper hearing procedure to obtain additional 
evidence to determine the appropriate rates, terms, and conditions for these transmission 
services.48  The Commission required parties to address, among other things, the 
interconnection requirements and operational practices necessary to maintain system 
reliability if a Co-Located Load or associated generator trips offline and the eligibility 
requirements necessary for an Eligible Customer to take FCD or NFCD Transmission 
Service on behalf of Co-Located Load.49 
B. 
Compliance Filings and Paper Hearing Procedure 
1. 
Thirty-Day Compliance Filing 
On January 20, 2026, PJM made its 30-day compliance filing in Docket No. 
ER26-1088-000 pursuant to the December Order (“Thirty-Day Compliance Filing”).50  
Among other changes, the Thirty-Day Compliance Filing proposed to clarify that existing 
services in the Tariff could be used by Project Developers serving Co-Located Load, 
including Provisional Interconnection Service and Surplus Interconnection Service.51  The 
Thirty-Day Compliance Filing also clarified that Project Developers serving Co-Located 
Load can request interconnection service below nameplate capacity and accelerate the 
interconnection process under certain circumstances.52  The Commission accepted in part 
and rejected in part PJM’s compliance filing in an order on April 16, 2026;53 PJM 
 
48 See December Order, 193 FERC ¶ 61,217, at PP 194, 203, 207, 219. 
49 December Order, 193 FERC ¶ 61,217 at P 219(8), (10).  
50 PJM Interconnection, L.L.C., Thirty-Day Compliance Filing with Order on Show Cause of PJM 
Interconnection, L.L.C., Docket No. ER26-1088-000 (Jan. 20, 2026). 
51 Thirty-Day Compliance Filing at 5-7. 
52 Thirty-Day Compliance Filing at 4-5. 
53 PJM Interconnection, L.L.C., 195 FERC ¶ 61,030.

PDF page 17

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 13 
 
13 
submitted an additional compliance filing on May 18, 2026, to comply with the 
Commission’s order.54   
2. 
Sixty-Day Compliance Filing 
On February 23, 2026, PJM made its 60-day compliance filing in Docket No. 
ER26-1479-000 pursuant to the December Order (“Sixty-Day Compliance Filing”).55  The 
Sixty-Day Compliance Filing proposed Tariff revisions to, among other things:  (1) amend 
PJM’s BTMG Tariff provisions;56 (2) establish certain aspects of three new transmission 
services for Eligible Customers seeking to take service on behalf of Co-Located Load;57 
and (3) amend PJM’s Necessary Studies processes.58   
3. 
Paper hearing procedures 
PJM submitted an initial brief to address the Commission’s finding in the December 
Order that additional record evidence was needed to set the appropriate replacement rates, 
terms, and conditions for new transmission services for Eligible Customers serving Co-
Located Load, including for Interim NITS, FCD Transmission Service, and NFCD 
Transmission Service.59  PJM’s initial brief set forth the non-rate terms and conditions for 
these new transmission services along with illustrative Tariff language.  Various parties 
 
54 PJM Interconnection, L.L.C., Compliance Filing to the Commission’s April 16 Order on PJM’s Thirty-Day 
Compliance Filing with the Order to Show Cause of PJM Interconnection, L.L.C., Docket No. 
ER26-1088-001 (May 18, 2026). 
55 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open 
Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al. of PJM 
Interconnection, L.L.C., Docket No. ER26-1479-000 (Feb. 23, 2026) (“Sixty-Day Compliance Filing”). 
56 Sixty-Day Compliance Filing at 4-18. 
57 Sixty-Day Compliance Filing at 18-24. 
58 Sixty-Day Compliance Filing at 24-28. 
59 PJM Interconnection, L.L.C., Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Feb. 
23, 2026) (“PJM Initial Brief”).

PDF page 18

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 14 
 
14 
protested aspects of PJM’s illustrative Tariff language.60  PJM proposed certain 
refinements to the illustrative language in its reply brief.61 
C. 
June 2026 Orders 
1. 
Co-Location Order 
The Commission issued the Co-Location Order addressing the Sixty-Day 
Compliance Filing, the paper hearing submissions, and requests for rehearing and 
clarification of the December Order.62  The Co-Location Order accepted most of PJM’s 
proposed Tariff changes, but directed PJM to make a number of additional changes within 
60 days.63  Among other things, the Co-Location Order directed PJM to revise the Tariff 
to adopt more detailed study procedures for customers requesting FCD and/or NFCD 
Transmission Service that mirror existing cluster study procedures.64  The Co-Location 
Order also directed PJM to make new transmission services available to customers with 
BTMG that are willing and able to limit their withdrawals from the Transmission System.65  
To accomplish this, the Commission directed PJM to either add a definition of “Eligible 
Load” that encompasses customers serving Co-Located Load and customers serving load 
 
60 See, e.g., PJM Interconnection, L.L.C., Reply Brief of Joint Co-Location Developers and Motion to 
Intervene Out-of-Time of Calibrant, Convergent, U.S. Energy Storage Coalition, and Verrus, Docket Nos. 
EL25-49-000, et al., at 2 (Mar. 25, 2026); PJM Interconnection, L.L.C., Reply Brief and Protest of Enchanted 
Rock, Docket Nos. EL25-49-000, et al., at 7-9 (Mar. 25, 2026) (arguing that PJM’s proposal “renders Interim 
NITS entirely unworkable”); PJM Interconnection, L.L.C., Reply Brief of Advanced Energy United and 
Solar Energy Industries Association, Docket Nos. EL25-49-000, et al., at 6-10 (Mar. 25, 2026). 
61 PJM Interconnection, L.L.C., Reply Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et 
al., Attachment A (Redlines on Reply Brief to Illustrative Language for New Tariff, Part XI; Attachments F-
3A and F-4; and Other Illustrative Tariff Revisions), Illustrative Tariff, Part XI, Subpart A, section 701.1 
(Apr. 24, 2026) (“PJM Reply Brief”). 
62 See Co-Location Order, 195 FERC ¶ 61,209, at PP 1-2, 4-7.  
63 See, e.g., Co-Location Order, 195 FERC ¶ 61,209, at P 280 (directing PJM to revise Tariff to specify what 
information about Necessary Studies will be available in the PJM Manuals). 
64 Co-Location Order, 195 FERC ¶ 61,209, at P 370. 
65 Co-Location Order, 195 FERC ¶ 61,209, at P 91.

PDF page 19

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 15 
 
15 
with BTMG, or to propose comparable Tariff revisions.66  The Co-Location Order further 
required PJM to revise the Tariff to provide additional detail regarding the operational 
requirements and necessary control technologies to be employed for customers taking new 
transmission services on behalf of Eligible Load.67   
2. 
Large Load Show Cause Order 
The Large Load Show Cause Order found that several aspects of the Tariff appeared 
unjust and unreasonable because it lacked specific procedures for integrating large loads, 
including Large Load-specific procedures for interconnection studies, processing 
transmission service requests, and providing transmission service without cost shifting.68  
The Large Load Show Cause Order also found that the Tariff appeared to be unjust and 
unreasonable because it lacked transmission service options for customers serving large 
loads that are willing and able to limit their withdrawals from the Transmission System.69  
The Commission was specifically concerned whether the Tariff was just and reasonable 
without allowing customers to take Interim NITS, FCD Transmission Service, and/or 
NFCD Transmission Service on behalf of Eligible Load.70  The Commission also 
emphasized that, in the Co-Location Order, it approved a requirement that customers taking 
transmission service on behalf of Eligible Load must have necessary control technologies 
or protection systems to limit energy withdrawals to approved levels.71  The Large Load 
 
66 Co-Location Order, 195 FERC ¶ 61,209, at P 91. 
67 Co-Location Order, 195 FERC ¶ 61,209, at PP 482, 541. 
68 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 59-60, 65, 77. 
69 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 86.  
70 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 87.  
71 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 87 & n.189 (citing Co-Location Order, 195 FERC 
¶ 61,209, at P 480).

PDF page 20

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 16 
 
16 
Show Cause Order further found that PJM’s Tariff appeared to be unjust and unreasonable 
due to a lack of mechanisms to ensure that costs are not shifted between transmission 
customers.72 
To address these issues, the Large Load Show Cause Order directed PJM to make 
two compliance filings.73  First, the Large Load Show Cause Order directed PJM to submit 
an informational filing within 30 days to explain how PJM intends to ensure that it has 
adequate generation to serve existing and new large loads.74  Second, the Large Load Show 
Cause Order directed PJM to submit within 60 days a compliance filing explaining whether 
its Tariff remains just and reasonable in light of the issues identified in the order, or to 
propose Tariff changes that would remedy the identified concerns.75  The Commission 
noted that it would entertain requests to hold the show cause proceedings in abeyance if 
PJM demonstrated a plan to file changes pursuant to FPA section 205 to address the 
identified concerns.76 
D. 
Partial Extension and Partial Compliance Filing 
On July 28, 2026, PJM moved for a 90-day extension of time to meet certain Co-
Location Order requirements,77 and it simultaneously requested the Commission to hold 
the Large Load Show Cause Order proceedings in abeyance for 90 days.78  PJM explained 
that the June 2026 Orders contained certain interrelated and overlapping issues that must 
 
72 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 77. 
73 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 3-4. 
74 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 4. 
75 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 3. 
76 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 39. 
77 See generally PJM Extension Motion. 
78 See generally PJM Abeyance Motion.

PDF page 21

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 17 
 
17 
be addressed on a holistic basis, which required additional time and stakeholder 
engagement.79  For example, PJM noted that the June 2026 Orders both directed PJM to 
expand the availability of new transmission services, enhance its Large Load study 
procedures, and detail the operational requirements and control technologies that 
customers taking transmission service on behalf of certain loads must use.80  PJM 
committed to submitting a partial compliance filing by August 17, 2026, that addressed 
certain directives of the Co-Location Order.81  The Commission granted PJM’s requests on 
August 14, 2026.82 
Pursuant to its commitment, PJM made a partial compliance filing on August 17, 
2026, in Docket No. ER26-1479-002 to address many of the Co-Location Order’s 
directives, including by proposing to add the term Eligible Load to the Tariff to encompass 
both Co-Located Load and load with BTMG; adopting various modifications to the terms 
and conditions for Interim NITS; modifying the definition of Retail BTMG to eliminate 
the 50 MW nameplate limit for netting; and removing the requirement for existing 
customers to execute a new Generation Interconnection Agreement (“GIA”) to serve Co-
Located Load.83 
 
79 PJM Abeyance Motion at 4-8; PJM Extension Motion at 4-8.  
80 PJM Abeyance Motion at 4-5. 
81 PJM Abeyance Motion at 1, 6-7; PJM Extension Motion at 1-2, 6-7. 
82 PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et al. (Aug. 14, 
2026). 
83 See generally August 17 Filing.

PDF page 22

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 18 
 
18 
E. 
PJM’s Stakeholder Engagement Process 
PJM held engagement sessions to inform stakeholders about the June 2026 Orders 
and solicit feedback on the proposed Tariff revisions PJM would file in response to those 
orders.  PJM’s stakeholder engagement process is detailed below: 
• July 30, 2026, Co-Located Load Order Workshop (“CLLOW”):  PJM 
presented on the June 2026 Orders and explained PJM’s proposed compliance 
approach.84  
• August 18, 2026, CLLOW:  PJM provided an update on its June 2026 Orders 
compliance strategy.  PJM presented its proposed Large Load Show Cause 
Order compliance framework85 and discussed the overlap between Large Load, 
Co-Located Load, and load with BTMG.86  PJM solicited and received 
stakeholder feedback on its presentation.87 
• September 16, 2026, CLLOW:  PJM presented its proposed process for 
integrating Large Loads with the Transmission System, pursuant to the Large 
 
84 See Co-Located Load Order Workshop, PJM Interconnection, L.L.C., https://www.pjm.com/committees-
and-groups/workshops/cllsco [https://perma.cc/B3FW-BRLM] (last visited Nov. 12, 2026) (follow “Meeting 
Materials” subheading; then choose “2026” from dropdown; then choose “7.30.2026 – Co-Located Load 
Order Workshop”; then select and click “Download”).  
85 Donnie Bielak, Show Cause for Large Loads Framework, PJM Interconnection, L.L.C. (Aug. 18, 2026), 
20260818-item-03---show-cause-for-large-loads-framework---presentation.pdf 
[https://perma.cc/V2Q3-
A9NT]. 
86 See Tim Horger, Overlap of Large Load, Co-Located Load and Load with BTMG, PJM Interconnection, 
L.L.C. 
(Aug. 
18, 
2026), 
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20260818/20260818-item-02---overlap-of-large-load-co-located-load-and-
load-with-btmg---presentation.pdf [https://perma.cc/XQ8A-M3PU]. 
87 See August 18 Co-Located Load Order Workshop Stakeholder Feedback Poll Responses, PJM 
Interconnection, 
L.L.C. 
(Aug. 
18, 
2026), 
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20260818/20260818-august-18-co-located-load-order-workshop-
stakeholder-feedback-poll-responses-received-by-8-28-26-final.pdf [https://perma.cc/V7NB-9RR5].

PDF page 23

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 19 
 
19 
Load Show Cause Order.88  PJM solicited and received stakeholder feedback 
on its presentation.89 
• September 30, 2026, CLLOW:  PJM presented its proposed Large Load study 
process and received stakeholder feedback.90 
• October 5, 2026, CLLOW:  PJM presented and solicited feedback on certain 
draft Tariff redlines to comply with the June 2026 Orders PJM gave a 
presentation on proposed Eligible Load Curtailment priority by transmission 
service type.91 
• October 16, 2026, CLLOW:  PJM presented and solicited feedback on certain 
draft Tariff redlines to comply with the June 2026 Orders.92  
• October 26, 2026, CLLOW:  PJM presented on proposed Tariff redlines 
associated with its new transmission services.93  PJM also discussed its 
 
88 See Donnie Bielak, Show Cause for Large Loads Framework, PJM Interconnection, L.L.C. (Sep. 16, 2026), 
https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260916/20260916-
item-03---show-cause-for-large-loads-approach---presentation.pdf [https://perma.cc/YLW3-DGTK]. 
89 See September 16 Co-Located Load Order Workshop Stakeholder Feedback Poll Responses, PJM 
Interconnection, 
L.L.C. 
(Sep. 
16, 
2026), 
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20260916/20260916-september-16-co-located-load-order-workshop-
stakeholder-feedback-poll-responses-received-by-9-22-26.pdf [https://perma.cc/CM3H-E66H]. 
90 Donnie Bielak, Show Cause for Large Loads Framework, PJM Interconnection, L.L.C. (Sep. 30, 2026), 
https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260930/20260930-
item-02---show-cause-for-large-loads-approach---presentation.pdf [https://perma.cc/FB8W-CDDV].  
91 Chris Pilong, Operationalizing Flexible Large Loads: Curtailment Overview, PJM Interconnection, L.L.C. 
(Oct. 
5, 
2026), 
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261005/20261005-item-02---operationalizing-flexible-large-loads-
curtailment-overview---presentation.pdf [https://perma.cc/FTM9-LLB6]. 
92 See Item 02 – Draft Tariff Revisions – Redline, PJM Interconnection, L.L.C. (Oct. 15, 2026), 
https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20261016/20261016-
item-02---draft-tariff-revisions---redline.pdf [https://perma.cc/K3V7-7G28] (presenting redline Tariff 
revisions at the October 16, 2026 CLLOW).  
93 See, e.g., Item 02 – Tariff Part XI New Transmission Services – Redlines, PJM Interconnection, L.L.C. 
(Oct. 
26, 
2026), 
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261026/20261026-item-02---tariff-part-xi-new-transmission-services---

PDF page 24

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 20 
 
20 
proposed Fast Energization Process, which would require PJM to annually 
study all (i) generation and Merchant Transmission Interconnection requests; 
and (ii) Large Load and Long Term Firm Transmission Service requests in a 
single cluster over a 12-month period.94  In Section III below, PJM describes its 
Fast Energization Process proposal and associated Tariff revisions in detail.  
Additionally, the Transmission Owners discussed proposed transmission rates, 
cost allocation, and a cost-recovery framework, to be separately filed.95  
• October 28, 2026, Markets and Reliability Committee:  PJM discussed its 
proposed response to the Large Load Show Cause Order, including its Fast 
Energization Process proposal.96  
• November 5, 2026, Special Members Committee:  PJM provided notice in 
accordance with Tariff, Part I, section 9.2(b) regarding its proposed Tariff 
 
redlines.pdf [https://perma.cc/WF4R-RKYC] (presenting redline Tariff revisions at the October 26, 2026 
CLLOW).  
94 Donnie Bielak, Fast Energization, PJM Interconnection, L.L.C. (Oct. 26, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/workshops/cllsco/2026/20261026/20261026-item-03---1-fast-
energization---presentation.pdf [https://perma.cc/VSE5-5235].  
95 See Notice of PJM Transmission Owners Consultation with the Members Committee Regarding Proposed 
Revisions to the PJM Tariff, PJM Interconnection, L.L.C. (Oct. 9, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/workshops/cllsco/2026/20261026/20261026-item-04---pjm-to-large-
load-mc-consultation-notice.pdf [https://perma.cc/MT5Z-GKR7].  
96 Donnie Bielak et al., Large Load Show Cause Response, PJM Interconnection, L.L.C. (Oct. 28, 2026), 
https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20261028/20261028-
item-06---large-load-show-cause-response---presentation.pdf [https://perma.cc/58FJ-VLAZ].

PDF page 25

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 21 
 
21 
revisions to comply with the June 2026 Orders,97 including its Fast Energization 
proposal.98  
• November 6, 2026, TOA-AC: 
PJM provided notice to the Transmission 
Owners in accordance with Tariff, Part I, section 9.2(b) regarding its proposed 
Tariff revisions to comply with the June 2026 Orders, including its Fast 
Energization proposal.99 
• November 12, 2026, CLLOW:  PJM discussed its proposed revisions to the 
Tariff and RAA to implement its Fast Energization proposal.  PJM provided 
draft Tariff and RAA redlines to stakeholders for discussion.100 
PJM intends to schedule additional stakeholder sessions after the submission of this 
filing to continue the process of education and discussion on the proposal submitted here.  
In particular, PJM is planning sessions on at least November 23, 2026, and December 15, 
2026, to answer stakeholder questions and receive feedback.  
 
97 
See 
Meeting 
Details, 
PJM 
Interconnection, 
L.L.C. 
(Nov. 
5, 
2026), 
https://www.pjm.com/forms/registration/Meeting%20Registration.aspx?ID=%7b1045ffcd-c613-47d7-
90be-24f2afa0c1c4%7d [https://perma.cc/N8TQ-ELZR] (November 5, 2026 Special Members Committee 
Meeting Materials).  
98 Donnie Bielak, Fast Energization, PJM Interconnection, L.L.C. (Nov. 5, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/committees/mc/2026/20261105-special/item-01---1-fast-energization--
-presentation.pdf [https://perma.cc/Z87G-9U6R].  
99 See TOA-AC Meeting Agenda, PJM Interconnection, L.L.C. (Nov. 6, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/committees/toa-ac/2026/20261106-special/agenda.pdf 
[https://perma.cc/FK73-PBGQ].  
100 See, e.g., Item 02 – Tariff Part XI New Transmission Services – Redlines, PJM Interconnection, L.L.C. 
(Nov. 
11, 
2026), 
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261112/20261112-item-02---tariff-revisions-part-xi-new-transmission-
services-november-11-draft---redline.pdf [https://perma.cc/7VBQ-P2RQ]; Item 02 – RAA Schedule 8 – 
Redlines, PJM Interconnection, L.L.C. (Nov. 11, 2026), https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261112/20261112-item-02---raa-revisions-schedule-8-november-11-
draft--redline.pdf [https://perma.cc/579S-MCKS].

PDF page 26

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 22 
 
22 
III. 
OVERVIEW OF PROPOSED CHANGES 
A. 
Part III—NITS 
PJM is proposing certain changes to the terms and conditions of NITS in Part III to 
ensure that PJM is appropriately studying, planning, and upgrading the Transmission 
System for Large Load growth.  Currently, there is no limit on a Network Customer’s load 
growth when taking NITS, including for Large Load.101  Under the current process, PJM 
plans the Transmission System based on the yearly load forecast, including adjustments to 
account for Large Loads.102  To promote efficiency and transparency for Large Load 
additions, PJM is proposing the new Fast Energization study process in Part VIII as 
discussed below.103  However, certain changes to Part III are needed to ensure that Large 
Load is captured in that study process. 
1. 
NITS quantity for Large Load  
PJM is proposing to add language to capture the existing level of NITS being 
provided to Network Customers serving Large Loads.  In this regard, Part III would now 
specify that “[t]he amount of Regional Network Integration Transmission Service 
provisioned to Network Customers for serving Large Loads are at levels specified in an 
effective Service Agreement or, if not specified therein, as reflected on the Large Load 
Registry per the terms of the Reliability Assurance Agreement, Schedule 11.B.1.”104  The 
RAA now requires all Large Load in the PJM Region to be registered as of March 1, 
 
101 See, e.g., Tariff, Part III, section 31.6. 
102 See generally RAA, Schedule 8 (setting Unforced Capacity Obligations based on Obligation Peak Load 
with Load Adjustments); Operating Agreement, Schedule 6 (specifying procedures for PJM’s Regional 
Transmission Expansion Plan (“RTEP”) Protocol). 
103 See infra Section III.B. 
104 Attachment A-1, Proposed Tariff, Part III, General.

PDF page 27

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 23 
 
23 
2027.105  This addition to Part III is necessary to set a baseline of the Large Load currently 
being served via NITS to allow PJM to study future Large Load additions. 
2. 
Information updates 
The Tariff currently provides for Network Customers to provide PJM with annual 
updates on its Network Load and Network Resources forecasts, consistent with the 
information provided in its Application for NITS, including any information provided 
under Tariff, Part III, section 29.2(ix) pursuant to the Transmission Provider’s planning 
process in Operating Agreement, Schedule 6, but does not require the Network Customer 
to file an Application for those changes.106  Because NITS is available to Eligible 
Customers taking service on behalf of Eligible Load, PJM is proposing to add language to 
clarify that the annual information updates Network Customers provide must include 
changes to Eligible Load and, as applicable, the Eligible Generating Facility serving that 
load.107  Further, PJM’s Tariff remains unchanged in that the Network Customer must 
provide PJM with timely notice of material changes relating to the Network Customer’s 
Network Load (including any Network Load that is Large Load), and the Network 
Customer’s Transmission System or other aspects of its facilities or operations affecting 
PJM’s ability to provide reliable service.108  This obligation, in tandem with the obligation 
 
105 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48; PJM Interconnection, L.L.C., Thirty-Day 
Compliance Filing to the Commission’s October 9, 2026 Order on PJM’s Large Load Definition and Large 
Load Registry, Docket No. ER26-3515-002 (Nov. 9, 2026). 
106 See Tariff, Part III, section 31.6. 
107 Attachment A-1, Proposed Tariff, Part III, section 31.6. 
108 Id.

PDF page 28

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 24 
 
24 
to also update the Large Load Registry means that PJM and others will have a clearer 
picture of the Large Load on its system.109   
Going forward, Large Load growth for NITS customers will require an Application 
to be studied through the Fast Energization Process.110  Accordingly, PJM is proposing to 
strike the language in section 31.6 that suggests an Application would not be required for 
such changes (i.e., “[e]ven if an Application is no longer required”).111 
3. 
50 MW limit on netting Behind the Meter Generation 
The Commission directed PJM to allow Eligible Customers with Retail BTMG to 
net up to 50 MW of Retail BTMG from their load, subjection to certain exclusions for a 
three-year transition provision, to grandfather existing commercial arrangements, and for 
Cogeneration Facilities with load that follows the facility.112  Consistent with this directive, 
PJM is proposing a revised definition of Retail BTMG that eliminates the rejected 50 MW 
nameplate limit and other netting exemptions from the definition.113  In addition, PJM is 
proposing revisions to Part III, section 34.2 and Schedule 8 of the RAA to implement the 
50 MW netting limit.114   
Currently, there is no limit to Retail BTMG’s daily load reduction for purposes of 
calculating capacity requirements under the RAA or transmission service charges under 
 
109 RAA, Schedule 11.B.1 (accepted in PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48).. 
110 See infra Section III.B. 
111 Attachment A-1, Proposed Tariff, Part III, section 31.6. 
112 Co-Location Order, 195 FERC ¶ 61,209, at PP 207, 220. 
113 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – R - S) (adding the definition of “Retail 
Behind The Meter Generation”); Proposed Tariff, Part VIII, Subpart A, section 400, Definitions R. 
114 Attachment A-1, Proposed Tariff, Part III, section 34.2; Proposed Tariff, RAA, Schedule 8.

PDF page 29

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 25 
 
25 
the Tariff.115  Any load that is served by operating BTMG is simply not included in the 
daily load of the Network Customer.116  Pursuant to the Commission’s directive,117 PJM is 
proposing revisions to section 34.2 that would limit the daily load reduction from Retail 
BTMG to 50 MW effective March 16, 2027 based on the status of the BTMG as of 
December 18, 2025, unless an exemption applies.118  As directed, PJM has included three 
exemptions from the netting limit.  First, the 50 MW limit would not apply for a three-year 
transition period for existing Retail BTMG that was used to serve load as of December 18, 
2025.119  Second, the 50 MW netting limit would not apply to Retail BTMG that was 
owned, operated and/or contracted for as of December 18, 2025, for the current term 
remaining under any contract to effectuate the Retail BTMG arrangement (including any 
renewal, amendment, or extension per the contract’s terms).120  To qualify for this 
exemption, the retail load served by the Retail BTMG must be on the Large Load Registry, 
the Retail BTMG must be registered with the Transmission Provider in accordance with 
the PJM Manuals, and the Network Customer must comply with any requests for 
information to verify eligibility.121   
PJM is proposing that the load be added to the Large Load Registry and that Retail 
BTMG be registered to track utilization of the netting exemptions for settlement and 
 
115 Tariff, Part III, section 34.2 (“The daily load of a Network Customer does not include load served by 
operating Behind The Meter Generation.”). 
116 Tariff, Part III, section 34.2. 
117 Co-Location Order, 195 FERC ¶ 61,209, at PP 207, 220. 
118 Attachment A-1, Proposed Tariff, Part III, section 34.2(B). 
119 Attachment A-1, Proposed Tariff, Part III, section 34.2(C). 
120 Attachment A-1, Proposed Tariff, Part III, section 34.2(D). 
121 Attachment A-1, Proposed Tariff, Part III, section 34.2(D).

PDF page 30

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 26 
 
26 
resource planning purposes.  The 50 MW netting limit will not apply to a Cogeneration 
Facility (consistent with the requirements of the Public Utility Regulatory Policies Act of 
1978) that is integrated with the retail load it serves such that if the Cogeneration Facility 
trips offline, the retail load follows.122  To qualify, the retail load must be on the Large 
Load Registry, the Retail BTMG must be registered, the Network Customer must certify 
eligibility, the Network Customer must comply with requests for information to verify 
eligibility, and the Network Customer must update PJM in the event it no longer qualifies 
for the exemption.123  PJM also reserves the right to periodically audit compliance with 
these requirements.124 
To effectuate the netting limit for the purpose of capacity cost allocation, PJM is 
proposing changes to RAA, Schedule 8 to incorporate the netting limits into the calculation 
of Obligation Peak Load for purposes of determining the Unforced Capacity 
Obligations.125  Currently, the Daily Unforced Capacity Obligation of a Party to the RAA 
is calculated by taking the Party’s Obligation Peak Load and applying scaling factors.126  
The Obligation Peak Load is calculated by taking the daily summation of the Party’s 
weather adjusted coincident summer peak for the last Delivery Year for the end-users in 
the Zone, net of BTMG.127  Because PJM is proposing to limit BTMG netting to 50 MW 
except in specific circumstances, PJM is proposing to add language in RAA, Schedule 8 to 
 
122 Attachment A-1, Proposed Tariff, Part III, section 34.2(E). 
123 Attachment A-1, Proposed Tariff, Part III, sections 34.2(E)(a)-(e). 
124 Attachment A-1, Proposed Tariff, Part III, section 34.2(F). 
125 Attachment A-1, Proposed Tariff, RAA, Schedule 8. 
126 RAA, Schedule 8(A). 
127 RAA, Schedule 8(A).

PDF page 31

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 27 
 
27 
incorporate those netting limits into the Obligation Peak Load calculation for settlement 
and planning purposes.128 
B. 
Part VIII—Fast Energization Process 
Consistent with the Commission’s directives to establish a study process for Large 
Load and to avoid duplicating system reinforcements for generator interconnection and 
transmission service for Large Loads,129 and with PJM’s strategic objectives,130 PJM 
proposes to evaluate requests for Transmission Service on behalf of Eligible Loads and 
Large Loads as part of its Tariff, Part VIII procedures for studying the interconnection of 
Generating Facilities and Merchant Transmission and the provision of Long Term Firm 
Transmission Service.  PJM further proposes new reforms to Tariff, Part VIII to speed up 
the studies, increase readiness requirements, and increase certainty as to responsibility for 
upgrades.  PJM calls the resulting process the “Fast Energization Process,” as it is designed 
both to get Generating Facilities online quickly and provide transmission service to Eligible 
Loads and Large Loads efficiently through a single, one-year process. 
1. 
The Fast Energization Process is designed for speed and accuracy. 
The Fast Energization Process would supplant the current interconnection process’s 
three System Impact Study phases with an accelerated Screening Phase and a single System 
Impact Study.131  This shift from three System Impact Studies to one will greatly expedite 
the interconnection process.  The one System Impact Study in the Fast Energization 
 
128 Attachment A-1, Proposed RAA, Schedule 8(A). 
129 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 60. 
130 See supra Section I discussion of PJM’s Five-Year Strategy and its objectives. 
131 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401 (Applications for Cycle Process 
Introduction); Proposed Tariff, Part VIII, Subpart C, section 404(B)(1) (Introduction); Proposed Tariff, Part 
VIII, Subpart C, section 405(B) (Phase I or Screening Phase); Proposed Tariff, Part VIII, Subpart C, section 
409 (Phase III or System Impact Study Phase).

PDF page 32

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 28 
 
28 
Process is preceded by a Screening Phase, during which PJM and Transmission Owners 
will provide two “turns” of system impact analysis with preliminary desk-side estimates 
for system upgrade costs and construction durations.132  After each of these turns of 
analysis, there will be a Decision Point—a period during which Project Developers and 
Eligible Customers can choose whether or not to proceed and, if they are proceeding, 
commit Readiness Deposits.133  This accelerated Screening Phase will extend for 
approximately four months, thereby providing two quick rounds of analysis that each take 
less than 60 days and get actionable information to Project Developers and Eligible 
Customers quickly.134 
 
 
132 Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404(B)(1) (Introduction); Proposed Tariff, 
Part VIII, Subpart C, section 405(B) (Phase I or Screening Phase); Proposed Tariff, Part VIII, Subpart C, 
section 409 (Phase III or System Impact Study Phase).  
133 Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404(B)(1) (Introduction); Proposed Tariff, 
Part VIII, Subpart C, section 406(C) (Decision Point I); Proposed Tariff, Part VIII, Subpart C, section 408(C) 
(Decision Point II). 
134 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 63 (directing PJM to explain whether the Tariff 
remains just and reasonable without processes for a study deadline of no more than 60 to 90 calendar days).

PDF page 33

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 29 
 
29 
The Fast Energization Process will create additional time savings by having the 
Final Agreement Phase begin at the same time the System Impact Study Phase begins.135  
The process will also be expedited by imposing higher readiness requirements in the 
Application and having Readiness Deposits posted with the Applications and at risk at 
Decision Points I and II, earlier in the interconnection process than they currently are.136  
Higher and earlier readiness requirements and Readiness Deposits will better screen out 
speculative projects and ensure that projects that advance through the Fast Energization 
Process and enter into an interconnection-related service agreement are truly ready to start 
construction of their facility, complete construction, and get their facility in service.137 
Finally, PJM has been and plans to continue to make investments in automation 
and technology to facilitate expediting the interconnection process.  As described in the 
Bielak Declaration, PJM has been evaluating Tapestry, an AI-powered interconnection 
platform, and is close to the point at which it can trust results produced by the platform 
without parallel human verification.138  This evaluation and PJM’s own significant 
automation efforts have given PJM the confidence to work on developing a suite of 
automation that will enhance existing technology applications and also deploy technologies 
into new areas.139  PJM is focusing particularly on improving its modeling platform, to turn 
 
135 See Attachment A-2, Proposed Tariff, Part VIII, Subpart D, section 411(C)(1) (“The Final Agreement 
Negotiation Phase shall run concurrently with the System Impact Study Phase.”).  
136 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, sections 401(D)(1)-(3) (Required Study 
Deposits and Readiness Deposits); Proposed Tariff, Part VIII, Subpart C, section 406(C) (Decision Point I); 
Proposed Tariff, Part VIII, Subpart C, section 408(C) (Decision Point II). 
137 Bielak Decl. ¶ 7. 
138 Bielak Decl. ¶ 19. 
139 Bielak Decl. ¶ 19.

PDF page 34

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 30 
 
30 
around grid studies more quickly, and on developing quality assurance tools to continue to 
drive high quality study results in a shorter period of time.140 
2. 
The Fast Energization Process includes a Soft Close Date and Early 
Application Engagement to improve the quality of Applications and 
reduce disputes and litigation. 
The Fast Energization Process includes a 14-week period between the Soft Close 
Date and the Application Deadline, called the Early Application Engagement, during which 
PJM will work with Applicants to improve their Applications.141  This collaborative 
process will include PJM testing and giving feedback on Applicants’ models, and giving 
guidance as to readiness.142  This will result in cleaner Applications that can be validated 
quickly, thereby reducing disputes and litigation, with time-saving benefits for all 
concerned, including the Commission.143 
3. 
Timing of Fast Energization Process implementation and the 
interim period 
PJM proposes to implement the Fast Energization Process once the current Cycle 
reaches the end of Decision Point II, consistent with the current Tariff timeline for opening 
a new Cycle.144  PJM thus proposes to open the Submission Window for the Fast 
Energization Process the next Business Day after Decision Point II of Cycle 01 ends.145  
 
140 Bielak Decl. ¶ 19. 
141 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 Definitions E (defining Early 
Application Engagement); Proposed Tariff, Part VIII, Subpart B, section 403(E)(2) (Early Application 
Engagement, Kickoff Calls, and Scoping Meetings). 
142 Attachment A-2, Proposed Tariff, Part VIII, Subpart B, section 403(E)(2) (Early Application Engagement, 
Kickoff Calls, and Scoping Meetings). 
143 See Bielak Decl. ¶ 20. 
144 See Tariff, Part VIII, Subpart B, section 403(A) (under the current Cycle process, PJM opens the 
Application window for the next Cycle when the current Cycle reaches Phase III). 
145 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A) (“Part VIII of the Tariff applies . 
. . to valid Eligible Customer for Load Requests, submitted on or after the next Business Day after the close 
of Decision Point II of Cycle 01.”).

PDF page 35

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 31 
 
31 
This is expected to be late November 2027.146  At that time, all the pending Applications 
submitted for Cycle 02 under the existing process will be re-submitted for new Cycle 02 
under the Fast Energization Process.147  Opening the Submission Window in late 
November 2027 would result in a Soft Close Date in early May 2028,148 followed by Early 
Application Engagement,149 and an Application Deadline for the new Cycle 02 in 
August 2028.150  The first Fast Energization Cycle would therefore finish in 2029. 
During the interim period until the Fast Energization Process is in effect, PJM will 
use the Necessary Studies process, as directed in the Co-Location proceedings.151  Once 
the Fast Energization Process is in effect, all Eligible Customer requests for transmission 
service to serve load, including Co-Located Load, will proceed through the Fast 
Energization Process.152 
 
146 See Stacey Nestel, Cycle 01 Application, PJM Interconnection, L.L.C., 2 (Jan. 2026), 
https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/ips/2026/20260126/20260126-
item-05---cycle-1-application-requirements-and-nextgen-process.pdf [https://perma.cc/6RJL-DWPF]. 
147 Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404(A)(8).  Requests to transfer Capacity 
Interconnection Rights in existing Cycle 02 Applications will be carried over to the new Cycle 02.  Id. 
148 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 (Definitions S) (Soft Close Date).  
149 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 (Definitions E) (Early Application 
Engagement). 
150 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 (Definitions A) (Application 
Deadline). 
151 December Order, 193 FERC ¶ 61,217, at P 226; Co-Location Order, 195 FERC ¶ 61,209, at P 284. 
152 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(a) (effective 12/31/9998) 
(“[P]lanned modifications that include the addition of an Eligible Load or Large Load configuration must be 
studied as part of the Fast Energization process set forth in this Tariff, Part VIII.”).

PDF page 36

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 32 
 
32 
4. 
PJM is eschewing parallel processes, to streamline for speed and 
accuracy.  
As part of the effort to streamline for speed, PJM proposes to eliminate 
Replacement Generation Interconnection Service.153  Replacement Generation 
Interconnection Service was developed to address the delay in processing Generation 
Interconnection Requests during the transition from the old, serial process to the current 
clustered Cycle process.154  That delay was particularly a problem for generators seeking 
to transfer Capacity Interconnection Rights from a deactivating resource to a New Service 
Request, because Capacity Interconnection Rights must be transferred within one year of 
deactivation of a resource.155  With the Fast Energization Process taking only a year, there 
will no longer be a need for Replacement Generation Interconnection Service as a separate 
parallel process.  Parallel processes, despite their value and benefit, increase complexity 
and tend to slow down processing; therefore PJM proposes to limit their use.156 
PJM also proposes to return the Necessary Studies process to its former role of 
addressing modifications to projects covered by existing, effective service agreements once 
the Fast Energization Process is in effect,157 as Eligible Loads and Eligible Generation can 
be studied more comprehensively through the main study process and do not need another 
separate parallel study process.  PJM proposes to add the same Necessary Studies process 
 
153 Attachment A-2, Proposed Tariff, Part VIII, Subpart J, sections 437(A)-(B) (requiring Replacement 
Generation Interconnection Service Requests to be made prior to the next Business Day after the close of 
Decision Point II of Cycle 01).   
154 Bielak Decl. ¶ 14. 
155 See Tariff, Part VIII, Subpart E, section 426(C)(3). 
156 Bielak Decl. ¶¶ 15, 18.  Along those lines, PJM also intends to open a stakeholder process in the first or 
second quarter of 2027 to explore improvements to Surplus Interconnection Service, another parallel process 
that has a negative impact on processing speed. 
157 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(a) (effective 12/31/9998).

PDF page 37

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 33 
 
33 
for studying Eligible Customer-driven modifications to existing, effective Transmission 
Service Agreements for changes to the characteristics of Eligible Load and Large Load to 
the Necessary Studies process, however, as such changes require study to protect the 
Transmission System.158  
5. 
PJM will maintain transparency of its study results 
PJM will continue to identify the system reinforcements needed to interconnect 
Generating Facilities and provide transmission service to loads, the drivers of those 
reinforcements and their capital costs.  PJM’s studies will use a proportional impact 
methodology, consistent with Order No. 2023.159 And PJM will post information regarding 
the reinforcements and their drivers and capital costs at the end of each Cycle on pjm.com 
in a publicly accessible, searchable format.160  The allocation and recovery of those costs 
is in the control of the Transmission Owners because they have filing rights as to cost 
allocation, cost recovery, and rate design. 
C. 
Part XI—New Transmission Services 
1. 
Interim NITS 
Consistent with the Commission’s directive to make the new transmission services 
available to Eligible Customers serving load with BTMG,161 PJM is proposing in Part XI, 
Subpart A to offer Interim NITS to Eligible Customers serving “Eligible Load,” which 
 
158 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(a) (effective 12/31/9998).  
159 See Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404.  
160 See, e.g., Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 409(B)(2) (requiring System 
Impact Study results to be publicly available on PJM’s website).  
161 Co-Location Order, 195 FERC ¶ 61,209, at P 91.

PDF page 38

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 34 
 
34 
encompasses both Co-Located Load and load with BTMG.162  PJM is also making Interim 
NITS available to Large Loads.163  The Part XI, Subpart A largely adopts the terms and 
conditions proposed during the paper hearing process in Docket No. EL25-49-000,164 but 
in a streamlined, reorganized format and with certain Commission-directed changes and 
other clarifications.  The Commission generally found in the Co-Location Order that the 
Interim NITS rules PJM had proposed were just and reasonable.165 
Section 701 describes the general nature of Interim NITS and restrictions on its 
use.166  Interim NITS is a transmission service that allows Eligible Customers serving 
Eligible Load or Large Load to utilize head room on the system as-available on an 
interruptible basis to a specific Delivery Point while awaiting the completion of system 
upgrades necessary to provide full NITS.167  Interim NITS is an energy-only service (i.e., 
it is not capacity backed).168  Interim NITS is not available to Eligible Customers serving 
Eligible Load or Large Loads with FCD or NFCD Transmission Service.169  In addition, 
Interim NITS may not be utilized by Eligible Customers to serve loads other than the 
designated Eligible Load or Large Load.170  Finally, PJM reserves the right to curtail 
 
162 Attachment A-1, Proposed Tariff, Part XI, Subpart A, sections 700-03; Proposed Tariff, Part I, Definitions 
– E - F (Eligible Load). 
163 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.1. 
164 See generally PJM Initial Brief, Attachment A (Illustrative Language for New Tariff, Part XI; Attachments 
F-3A and F-4; and Other Illustrative Tariff Revisions) (Feb. 23, 2026); PJM Reply Brief, Attachment A 
(Redlines on Reply Brief to Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and 
Other Illustrative Tariff Revisions). 
165 See Co-Location Order, 195 FERC ¶ 61,209, at PP 263-68, 571. 
166 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701. 
167 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.1. 
168 See Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.2. 
169 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.3. 
170 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.4.

PDF page 39

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 35 
 
35 
Interim NITS, consistent with Good Utility Practice, for the purpose of making upgrades, 
modifications, or repairs to Transmission Owner or Generation Owner lines, substations, 
generators, or facilities or to respond to adverse system conditions.171 
Section 702 lays out the requirements for initiating Interim NITS.172  Eligible 
Customers may apply for Interim NITS at the same time as NITS by submitting an 
Application pursuant to the procedures in Part VIII.173  The Transmission Service 
Agreement for Interim NITS is in the form provided in Attachment F-3A.174  Such eligible 
Customers must also meet conditions precedent for service including complying with the 
PJM Credit Policy, executing a Transmission Service Agreement with operational 
procedures and necessary control technologies to limit withdrawals from the system, and 
certifying that the Eligible Customer is willing and able to limit withdrawals from the 
Transmission System for the Eligible Load when directed by Transmission Provider, and 
constructing any facilities on the customer’s side of the Delivery Point to receive the 
delivery of energy.175  Consistent with the Co-Location Order,176 PJM clarified that Interim 
NITS will terminate and be converted automatically to NITS once the Transmission 
Provider performs an analysis to verify the system can accommodate the firm load and 
updates its internal systems to reflect the relevant upgrades needed to provide the requested 
 
171 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.5. 
172 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702. 
173 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.1. 
174 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.2. 
175 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.3. 
176 Co-Location Order, 195 FERC ¶ 61,209, at P 571.

PDF page 40

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 36 
 
36 
level of service on a firm basis.177  The language concerning performing an updated 
analysis and updating the relevant internal system updates was added to clarify that the 
conversion does not happen automatically the moment upgrades are physically complete 
but must first be reflected in PJM’s internal systems.  In addition to termination for 
conversion to NITS, Interim NITS may be terminated to the extent the Eligible Load or 
Large Load is disqualified from receiving service pursuant to Part XI, Subpart C, section 
719.5 due to multiple failures to follow Curtailment directives or misoperation of necessary 
control technologies.178  Interim NITS may also be terminated to the extent an Eligible 
Customer is in breach of its obligations under the Transmission Service Agreement (e.g., 
failure to update Transmission Provider regarding material changes to the Eligible Load or 
Large Load).179  Finally, Interim NITS may be terminated on another date mutually agreed 
by the parties.180 
Consistent with the allocation of filing rights between PJM and Transmission 
Owners,181 PJM understands the Transmission Owners have filed transmission rates for 
 
177 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(a); Proposed Tariff, Attachment F-
3A.  
178 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(b). 
179 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(c). 
180 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(d). 
181 CTOA, Rate Schedule FERC No. 42; see also Atl. City Elec. Co., 190 FERC ¶ 61,109, at P 3 (2025) 
(providing history and authority for the CTOA under Pennsylvania-New Jersey-Maryland Interconnection, 
105 FERC ¶ 61,294 (2003) (“Atlantic City Settlement Order”), order on compliance, 108 FERC ¶ 61,033 
(2004) by explaining that “[i]n the Atlantic City Settlement Order, the Commission explained that the 
settlement agreement essentially divides filing rights between ‘rate-related filings and terms and conditions-
related filings – with the PJM [Transmission Owners] filing the former and PJM the latter’”); Atl. City Elec. 
Co., 190 FERC ¶ 61,109, at P 4 (“[I]ndividual transmission owners do not have a right to file under FPA 
section 205 to modify ‘terms and conditions of the PJM Tariff’. . . .”); Atl. City Elec. Co. v. FERC, 295 F.3d 
1, 6 (D.C. Cir. 2002) (explaining that the initial Settlement Agreement between PJM and Transmission 
Owners “established procedures for changes to rate design and other tariff terms for transmission services.  
It permitted the transmission owners to file changes in transmission service rate design and non-rate terms 
and conditions to the tariff under section 205.”).

PDF page 41

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 37 
 
37 
Interim NITS.182  In addition to such rates, Eligible Customers taking Interim NITS on 
behalf of Eligible Load or Large Load will be assessed certain other charges that are within 
PJM’s filing authority, consistent with the charges assessed to loads taking NITS.183  
Accordingly, PJM would assess Eligible Customers taking Interim NITS on behalf of 
Eligible Load or Large Load:  
• administrative services charges under Schedule 1A, Schedule 9, and 
Schedule 10 of the Tariff;184 
• Ancillary Services charges in accordance with Part I, section 3;185 
• Black Start Service charges in accordance with Tariff, Schedule 6A;186  
• any redispatch costs as set forth in Tariff, Attachment K;187 and 
• any applicable Transmission Enhancement Charges in accordance with Tariff, 
Schedule 12.188 
2. 
Contract Demand Transmission Service 
Part XI, Subpart B, sections 708 through 711 and 714 through 715 provide the terms 
and conditions for the Contract Demand Transmission Services.189  As explained in section 
708, Contract Demand Transmission Service allows an Eligible Customer to take 
transmission service on behalf of Eligible Load or Large Load that is willing and able to 
 
182 PJM Interconnection, L.L.C., PJM Transmission Owners’ Partial Compliance Filing, Docket No. 
ER26-3537-000 (Aug. 17, 2026).  
183 See Co-Location Order, 195 FERC ¶ 61,209, at P 573. 
184 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4. 
185 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4. 
186 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4. 
187 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.2. 
188 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4. 
189 Attachment A-1, Proposed Tariff, Part XI, Subpart B, sections 708-11, 714-15.

PDF page 42

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 38 
 
38 
limit withdrawals from the Transmission System.190  FCD Transmission Service provides 
energy and capacity up to a specified, defined MW level.191  NFCD Transmission Service 
provides energy procured by Transmission Provider on an as-available basis up to a 
specified, predetermined level.192   
To be eligible for Contract Demand Transmission Service, any given Eligible Load 
or Large Load cannot be served by Interim NITS or NITS or have a pending Application 
for the same.193  To prevent toggling between FCD Transmission Service and NFCD 
Transmission Service to avoid capacity costs, an Eligible Customer shall not be eligible to 
take NFCD Transmission Service on behalf of any given portion of an Eligible Load or 
Large Load it previously served with FCD Transmission Service for five years following 
the effective date of the relevant Transmission Service Agreement.194  As with Interim 
NITS, Contract Demand Transmission Service may not be used for sales of energy or 
capacity to loads other than the Eligible Load or Large Load designated in the Transmission 
Service Agreement.195  Also, Transmission Provider may Curtail Contract Demand 
Transmission Service, consistent with Good Utility Practice, to make or support upgrades, 
modifications, or maintenance to Transmission Owner or Generation Owner lines, 
 
190 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 708(a). 
191 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 708(b). 
192 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 708(b). 
193 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.3.  This approach is consistent with the 
Commission’s holdings that a customer cannot take NITS for only a portion of its load behind a delivery 
point.  See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 196 (2025). 
194 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.3. 
195 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.4.

PDF page 43

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 39 
 
39 
substations, and equipment or as needed due to adverse conditions on the Transmission 
System.196 
To initiate Contract Demand Transmission Service on behalf of a designated 
Eligible Load or Large Load, the Eligible Customer must apply pursuant to the procedures 
in Tariff, Part VIII.197  Note that even to the extent an entity intends to serve Eligible Load 
or Large Load entirely through Co-Located Generation and does not wish to take 
Transmission Service, the entity must still apply and take service for zero MW pursuant to 
a Transmission Service Agreement to account for the provision of ancillary services.198  
The Transmission Service Agreement for Contract Demand Transmission Service is in the 
form provided in Attachment F-4.199   
Eligible Customers must meet the following conditions precedent to receive 
Contract Demand Transmission Service:  (i) make a valid request pursuant to Part VIII; (ii) 
verify that the designated Eligible Load or Large Load has not been served by an Eligible 
Customer taking NITS or Interim NITS or applied for such service on behalf of the load; 
(iii) the Eligible Customer has complied with the PJM Credit Policy; (iv) the Eligible 
Customer has executed a Transmission Service Agreement in the form provided in 
Attachment F-4, which includes operational procedures and necessary control technologies 
to limit energy withdrawals; (v) the Eligible Customer is in compliance with all applicable 
technical requirements; (vi) the Eligible Customer constructed any facilities on its side of 
the Delivery Point necessary to receive the delivery of energy; (vii) the Eligible Customer 
 
196 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.5. 
197 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.1. 
198 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.1. 
199 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.2.

PDF page 44

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 40 
 
40 
has completed any necessary certification requirements in accordance with the PJM 
Manuals; (viii) the Eligible Customer has executed the PJM Governing Agreements; and 
(ix) in the case of an Eligible Load served by an Eligible Generating Facility, the Eligible 
Customer verifies that no portion of the Eligible Generating Facility dedicated to serving 
the Eligible Load has Capacity Interconnection Rights.200  
Contract Demand Transmission Service will generally continue without expiration, 
but may be terminated in certain circumstances.201  First, Contract Demand Transmission 
Service may be terminated to the extent an incumbent Eligible Customer is being replaced 
by a successor Eligible Customer.202  Second, an Eligible Customer may terminate FCD 
Transmission Service by providing PJM with 42 months’ notice prior to the 
commencement of the Delivery Year.203  Third, Contract Demand Transmission Service 
may be terminated to the extent the Eligible Load or Large Load is disqualified from 
receiving service pursuant to Part XI, Subpart C, section 719.5 due to multiple failures to 
follow Curtailment directives or misoperation of necessary control technologies.204  Fourth, 
the Eligible Customer is in breach of its obligations under the Transmission Service 
Agreement (e.g., failure to update Transmission Provider regarding material changes to the 
Eligible Load or Large Load).205  Fifth, Contract Demand Transmission Service may be 
terminated on another date mutually agreed by the parties.206  Sixth, NFCD Transmission 
 
200 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.3. 
201 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711. 
202 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(a). 
203 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(b). 
204 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(c). 
205 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(d). 
206 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(e).

PDF page 45

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 41 
 
41 
Service may be terminated when system upgrades necessary to provide FCD Transmission 
Service are completed and placed in service.207 
Consistent with the allocation of rights between PJM and Transmission Owners,208 
PJM understands the Transmission Owners will be making a separate filing transmission 
rates for FCD Transmission Service and NFCD Transmission Service.  In addition to such 
rates, Eligible Customers will be assessed other charges Contract Demand Transmission 
Service that are within PJM’s filing authority.  Accordingly, PJM will assess Eligible 
Customers taking FCD Transmission Service on behalf of Eligible Load or Large Load:  
• administrative services charges under Schedule 1A, Schedule 9, and Schedule 
10 of the Tariff, based on the total quantity of megawatt-hours (“MWh”) of 
FCD Transmission Service specified in the Transmission Service Agreement, 
except in the case of any capacity-related charges under these schedules, which 
shall be based on the Eligible Customer’s Unforced Capacity Obligation;209 
• Ancillary Services charges, except for Regulation, based on the total quantity 
in MWhs of FCD Transmission Service specified in the Transmission Service 
Agreement in accordance with Part I, section 3;210 
• Regulation charges based on gross demand of the Eligible Load;211 
• Black Start Service charges based on the gross demand in accordance with 
Tariff, Schedule 6A;212  
• any redispatch costs as set forth in Tariff, Attachment K;213 and 
 
207 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(f). 
208 See supra note 95. 
209 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5. 
210 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5. 
211 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5. 
212 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5. 
213 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.3.

PDF page 46

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 42 
 
42 
• any applicable Transmission Enhancement Charges in accordance with Tariff, 
Schedule 12.214 
For Eligible Customers taking NFCD Transmission Service on behalf of Eligible 
Load or Large Load, PJM would assess:  
• administrative services charges under Schedule 1A, Schedule 9, and Schedule 
10 of the Tariff, based on the total quantity of MWhs of reserved NFCD 
Transmission Service, except any capacity-related charges under these 
schedules will not apply;215 
• Ancillary Services charges, except for Regulation, based on the total quantity 
in MWhs of reserved NFCD Transmission Service in accordance with Tariff, 
Part I, section 3;216 
• To the extent the Eligible Customer does not have an effective Transmission 
Service Agreement for FCD Transmission Service, Black Start Service charges 
based on the gross demand in accordance with Tariff, Schedule 6A;217  
• any redispatch costs as set forth in Tariff, Attachment K;218 and 
• To the extent the Eligible Customer does not have an effective Transmission 
Service Agreement for FCD Transmission Service, Regulation charges based 
on the gross demand of the Eligible Load or Large Load.219 
3. 
Common service provisions for Interim NITS and Contract Demand 
Transmission Services 
As proposed, Tariff, Part XI, Subpart C now provides the common service 
provisions for Part XI transmission services including requirements for control 
technologies, protection schemes, technical requirements, and facility construction.  
Service under Part XI is conditioned upon the Eligible Customer constructing, maintaining, 
 
214 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5. 
215 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4. 
216 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4. 
217 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4. 
218 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.2. 
219 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4.

PDF page 47

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 43 
 
43 
and operating the facilities and necessary control technologies and protection systems to 
take service and ensure that the Eligible Customer limits its withdrawals from the 
system.220  Those necessary control technologies may include fully redundant special 
protection schemes in accordance with the PJM Manuals.221  Necessary control 
technologies and special protection schemes must be developed in accordance with the 
PJM Manuals and consistent with Transmission Owner technical requirements and may be 
modified from time to time.222  In addition, Eligible Customers must meet the relevant 
technical requirements for service including the installation of necessary hardware and 
software to limit energy withdrawals, provisioning an operations center and qualified 
personnel, and demonstration of operational control.223 
Consistent with the Commission’s directive,224 PJM revised the Curtailment 
language to clarify the relative priority for the various services.225  FCD Transmission 
Service will be treated as equivalent to NITS and Firm Point-to-Point Transmission 
Services for purposes of Curtailment.226  Interim NITS, NFCD Transmission Service, and 
Non-Firm Point-to-Point Service will be treated as equivalent for purposes of 
Curtailment.227  Transmission Provider will prioritize reservations for Curtailment based 
on their contribution to exceedances of system limits as specified in the PJM Manuals.228  
 
220 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 716. 
221 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 717. 
222 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 717. 
223 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 718.1. 
224 Co-Location Order, 195 FERC ¶ 61,209, at P 555. 
225 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719. 
226 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.2. 
227 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.4. 
228 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.4.

PDF page 48

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 44 
 
44 
As directed,229 PJM also added language to specify that Eligible Customers subject to 
Curtailment may use a Co-Located Generating Facility to serve Co-Located Load provided 
the facility either has not obtained interconnection service yet or the facility is not a 
Capacity Resource.230  Consistent with the Co-Location Order,231 PJM added language in 
section 719.5 and to the Part I definition of Curtailment to clarify that with respect to Tariff, 
Part XI, its Curtailment authority includes the authority to curtail Interim NITS and NFCD 
Transmission Service for capacity or reserve shortages.232 
Consistent with the Commission’s directive,233 PJM revised the operational 
penalties for failure to follow dispatch instructions or misoperation of control 
technologies.234  Eligible Customers taking Interim NITS or Contract Demand 
Transmission Service are subject to operational penalties in the event that the Eligible 
Customer’s necessary control technology or protection system scheme misoperates.235  
After one instance of misoperation, the Eligible Customer will be prohibited from taking 
transmission service or otherwise withdrawing energy from the Transmission System 
pursuant to the relevant Transmission Service Agreement for a period up to 120 days from 
misoperation, which may be shortened or extended per mutual agreement.236  The up to 
120-day pause pending evaluation of the misoperation of the necessary control technology 
 
229 Co-Location Order, 195 FERC ¶ 61,209, at P 576. 
230Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 705.2. 
231 Co-Location Order, 195 FERC ¶ 61,209, at P 551. 
232 Attachment A-1,  Proposed Tariff, Part I, section 1 (Definitions – C - D); Proposed Tariff, Part XI, Subpart 
C, section 719.5. 
233 Co-Location Order, 195 FERC ¶ 61,209, at PP 516, 523-24, 527. 
234 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5. 
235 Attachment A-1, Proposed Tariff, Part XI, Subpart C, sections 719.5(a)-(b). 
236 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5(b).

PDF page 49

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 45 
 
45 
or protection system scheme is consistent with NERC requirements for an investigation 
into the operation of a Remedial Action Schemes (e.g., PRC-004-6 and PRC-012-02).237  
Such a pause in service will allow PJM (and the affected Transmission Owner(s), as 
necessary) time to investigate, identify, and implement necessary fixes to better protect the 
Transmission System, while respecting the Eligible Customer’s desire to retain this type of 
service based on its promised willingness to limit energy withdrawals.  In the event a 
necessary control technology or protection system misoperates a second time, the Eligible 
Customer’s Transmission Service Agreement for that Eligible Load shall be terminated.238  
Similarly, Eligible Customers that fail to respond to established Load Shedding and 
Curtailment procedures shall be prohibited from taking service under the relevant 
Transmission Service Agreement for a period of up to 120 days.239  
4. 
Pro Forma Service Agreement for Interim NITS (Attachment F-3A) 
Because Interim NITS is by definition a temporary service that will convert into 
NITS, the pro forma service agreement is a combined Interim NITS/NITS agreement for 
Eligible Customers taking Interim NITS or NITS on behalf of Eligible Loads or Large 
Loads.240  Any Eligible Customer taking these services on behalf of Eligible Loads or Large 
Loads would execute Attachment F-3A.241  In addition to the general terms carried over 
 
237 PRC-004-6 – Protection System Misoperation Identification and Correction, North American Electric 
Reliability 
Corporation 
(June 
12, 
2025), 
https://www.nerc.com/globalassets/standards/reliability-
standards/prc/prc-004-6.pdf [https://perma.cc/EV9E-JYWQ]; PRC-012-2 – Remedial Action Schemes, North 
American 
Electric 
Reliability 
Corporation 
(June 
12, 
2025), 
https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012-2.pdf 
[https://perma.cc/9KFL-HHNU]. 
238 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5(b). 
239 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5(a). 
240 Attachment A-1, Proposed Tariff, Part XI, Subpart A, sections 701.1, 702.4(a). 
241 Attachment A-1, Proposed Tariff, Attachment F-3A.  The existing pro forma NITS Service Agreement is 
located at Tariff, Attachment F-3.

PDF page 50

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 46 
 
46 
from the pro forma NITS Service Agreement (Attachment F-3), PJM has added terms 
specific to Interim NITS and serving Eligible Loads and Large Loads.  When an Eligible 
Customer takes Interim NITS while awaiting upgrades for NITS, Attachment F-3A 
specifies that NITS will not commence until the necessary upgrades are complete, 
Transmission Provider has performed an updated analysis to verify the Transmission 
System can accommodate the firm load, and the Transmission Provider has updated the 
relevant systems pursuant to its internal procedures.242  Because PJM will have to ensure 
the Transmission System can accommodate the specific Eligible Load or Large Load being 
served by the Eligible Customer, Attachment F-3A requires certain details about that load 
to be specified in the Agreement.  Attachment F-3A requires the specific Eligible Load or 
Large Load being served to be identified, the load’s gross demand to be specified, and, as 
applicable, information regarding the Eligible Generating Facility serving the load to be 
listed, including its Maximum Facility Output.243  The Eligible Customer is also required 
to specify a Delivery Point for Interim NITS and submit a single-line diagram.244   
Because Interim NITS requires the Eligible Customer to be willing and able to limit 
withdrawals from the system, Attachment F-3A includes terms to implement such 
limitations.  First, Attachment F-3A specifies the amount of Interim NITS provided245 and 
requires the Eligible Customer to certify that it is willing and able to limit its usage of the 
Transmission System consistent with the terms of the Agreement and when requested by 
 
242 Attachment A-1, Proposed Tariff, Attachment F-3A, sections 2.0-3.0. 
243 Attachment A-1, Proposed Tariff, Attachment F-3A. 
244 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, section 
1.0; Proposed Tariff, Attachment F-3A, Schedule A. 
245 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, section 
1.0.

PDF page 51

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 47 
 
47 
the Transmission Provider.246  The Agreement also includes a placeholder to list the 
necessary control technologies and operational practices that will be required prior to the 
commencement of Interim NITS.247  Finally, the agreement prohibits the Eligible Customer 
from making any material modifications to the load being served without the Transmission 
Provider’s prior written agreement.248  To the extent modifications to the Load Facility are 
planned, the Agreement requires the Eligible Customer to provide PJM notice to allow 
PJM to initiate the Necessary Studies process.249  In the event PJM determines that a 
planned modification would have a permanent material impact on the Transmission System 
or would constitute a material modification, Network Customer shall then withdraw the 
proposed modification or proceed with a new Eligible Customer for Load Request for the 
modification.250  Finally, the Agreement provides that if an Eligible Customer fails to 
timely inform the Transmission Provider of or obtain Transmission Provider’s written 
agreement for a material change in (i) the demand characteristics of the Load Facility; or 
(ii) the supply characteristics of the Eligible Generating Facility may constitute a breach to 
the Agreement and the Agreement may be terminated.251 
 
246 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0. 
247 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, sections 
4.0-5.0. 
248 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0. 
249 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0. 
250 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0. 
251 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0.

PDF page 52

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 48 
 
48 
5. 
Pro Forma Service Agreement for Contract Demand Transmission 
Service (Attachment F-4) 
Attachment F-4, the pro forma agreement for Contract Demand Transmission 
Service, governs both FCD and NFCD Transmission Services.252  Attachment F-4 is the 
pro forma agreement for Eligible Customers taking FCD or NFCD Service on behalf of 
Eligible Loads or Large Loads.253  Any Eligible Customer taking these services on behalf 
of Eligible Loads or Large Loads would execute Attachment F-4.254  In addition to the 
general terms carried over from the pro forma NITS Service Agreement (Attachment F-3), 
PJM has added terms specific to Contract Demand Transmission Service and serving 
Eligible Loads and Large Loads.  When an Eligible Customer takes NFCD Transmission 
Service while awaiting upgrades for FCD Transmission Service, Attachment F-4 specifies 
that FCD Transmission Service will not commence until the upgrades are complete, 
Transmission Provider has performed an updated analysis to verify the Transmission 
System can accommodate the firm load, and the Transmission Provider has updated the 
relevant systems pursuant to its internal procedures.255  Like with Interim NITS, because 
PJM will have to ensure the Transmission System can accommodate the specific Eligible 
Load or Large Load being served by the Eligible Customer, Attachment F-4 requires 
certain details about that load to be specified in the Agreement.  Attachment F-4 requires 
the specific Eligible Load or Large Load being served to be identified, the load’s gross 
demand to be specified, and, as applicable, information regarding the Eligible Generating 
 
252 Attachment A-1, Proposed Tariff, Attachment F-4.   
253 Attachment A-1, Proposed Tariff, Part XI, Subpart B, sections 708(a), 710.3(iv). 
254 Attachment A-1, Proposed Tariff, Attachment F-4; Proposed Tariff, Part XI, Subpart B, sections 708(a), 
710.3(iv).  
255 Attachment A-1, Proposed Tariff, Attachment F-4, sections 2.0-3.0.

PDF page 53

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 49 
 
49 
Facility serving the load to be listed, including its Maximum Facility Output.256  The 
Eligible Customer is also required to specify a Delivery Point for the Contract Demand 
Transmission Service and submit a single-line diagram.257 
Because Contract Demand Transmission Service requires the Eligible Customer to 
limit withdrawals from the system (as with Interim NITS), Attachment F-4 includes terms 
to implement such limitations.  First, Attachment F-4 specifies the amount of FCD 
Transmission Service and NFCD Transmission Service being provided258 and requires the 
Eligible Customer to certify that it is willing and able to limit its usage of the Transmission 
System consistent with the terms of the Agreement and when requested by the 
Transmission Provider.259  The Agreement also includes a placeholder to list the necessary 
control technologies and operational practices that will be required prior to the 
commencement of service.260  Finally, the agreement prohibits the Eligible Customer from 
making any material modifications to the load being served without the Transmission 
Provider’s prior written agreement.261  To the extent modifications to the Load Facility are 
planned, the Agreement requires the Eligible Customer to provide PJM notice to allow 
PJM to initiate the Necessary Studies process.262  In the event PJM determines that a 
 
256 Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission 
Service, sections 2.0-3.0. 
257 Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission 
Service, section 1.0; Proposed Tariff, Attachment F-4, Schedule A. 
258 Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission 
Service, section 1.0. 
259 Attachment A-1, Proposed Tariff, Attachment F-4, section 5.0. 
260Attachment A-1,  Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission 
Service, sections 4.0-5.0. 
261 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0. 
262 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0.

PDF page 54

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 50 
 
50 
planned modification would have a permanent material impact on the Transmission System 
or would constitute a material modification, Network Customer shall then withdraw the 
proposed modification or proceed with a new Eligible Customer for Load Request for the 
modification.263  Finally, the Agreement provides that if an Eligible Customer fails to 
timely inform the Transmission Provider of or obtain Transmission Provider’s written 
agreement for a material change in (i) the demand characteristics of the Load Facility; or 
(ii) the supply characteristics of the Eligible Generating Facility may constitute a breach of 
the Agreement and the Agreement may be terminated.264 
D. 
Re-Filing Co-Located Load Compliance Changes 
A number of proposed changes in this filing address compliance directives from 
the Co-Location Order and were previously filed on August 17, 2026.265  PJM filed a 
motion with the Commission earlier today seeking leave to withdraw that filing in favor of 
this one due to the overlapping nature of many of the changes.266  A number of the proposed 
changes from the August 17 Filing are being re-filed here.  Attachment D provides a chart 
detailing where each directive from the June 2026 Orders is addressed in this filing.267 
1. 
Prohibition on serving Co-Located Load from existing generators 
The Co-Location Order directed PJM to explain in its compliance filing how its 
changes will prohibit Interconnection Customers from serving Co-Located Loads from 
new and existing generators until all necessary Network Upgrades, control technologies 
 
263 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0. 
264 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0. 
265 See August 17 Filing. 
266 PJM Interconnection, L.L.C., Motion to Withdraw Filing and Terminate Proceeding in Deference to New 
Docket of PJM Interconnection, L.L.C., Docket No. ER26-1479-002 (Nov. 16, 2026). 
267 See generally Attachment D, Chart Mapping Order Directives to Tariff Changes.

PDF page 55

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 51 
 
51 
and/or protection systems, and metering are complete and in service.268  This FPA section 
205 filing fulfils PJM’s compliance obligations and obviates the need for a separate 
compliance filing by proposing to add Necessary Study references and provisions to Parts 
I, III, VI, and VII, and to direct Generation Project Developers seeking to serve Co-Located 
Load with an existing Co-Located Generating Facility to the Necessary Study process in 
Part VIII, Subpart A, section 401(H)(3).269  In its Sixty-Day Compliance Filing, PJM 
proposed to add language to Part VIII for the Necessary Study process to preclude a Project 
Developer from implementing any planned modifications to its facilities until the 
Necessary Studies are completed and the amended GIA reflecting the results of such 
studies is fully executed and effective; the Sixty-Day Compliance Filing also provided that 
service to the Co-Located Load could not begin until “all required Network Upgrades, 
necessary control technologies and protection systems, and metering identified as 
necessary are complete and in service.”270  Thus, the Tariff would now require that all 
Interconnection Customers and Generation Project Developers seeking to serve Co-
Located Load, whether with existing or new Generating Facilities:  (1) provide advance 
written notice to PJM and the relevant Transmission Owner; (2) go through the Necessary 
Study process in Part VIII of the Tariff; and (3) not begin serving Eligible Load until the 
 
268 Co-Location Order, 195 FERC ¶ 61,209, at P 285. 
269 See Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – L-M-N) (adding the definitions of 
“Necessary Study” and “Necessary Studies Agreement”); Proposed Tariff, Part III (General) (addition of 
notice requirement); Proposed Tariff, Part VI, Subpart B, section 212 (same); Proposed Tariff, Part VII, 
Subpart A, section 301(A)(7)(c) (same).   
270 Sixty-Day Compliance Filing, Proposed Tariff Revisions (Attachments A & B), Part VIII, Subpart A, 
sections 401(H)(3)(a), 401(H)(3)(b)(iii).  In this filing, PJM proposes to further clarify in Proposed Tariff, 
Part VIII, the Necessary Study process by amending the listing of required and necessary equipment changes 
to instead reference “the entire scope of work required under that . . . Generation Interconnection Agreement.”  
Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(d).  This ensures that all items determined to be 
necessary and therefore captured in the amended GIA are complete before the Project Developer may begin 
serving Eligible Load.

PDF page 56

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 52 
 
52 
entire scope of the work under their GIA as amended after the Necessary Study process is 
complete.  These combined revisions ensure that all these entities are treated comparably 
and the prohibition on serving Co-Located Loads before all the necessary upgrades and 
equipment changes are complete is enforced across the board.271 
2. 
Expansion of service to “Eligible Load” for load with BTMG 
The Co-Location Order directed PJM to expand the availability of the December 
Order’s new transmission services to Network Customers serving load with BTMG that 
are willing and able to limit their withdrawals from the Transmission System under certain 
circumstances.272  The Commission directed PJM to either add a definition of “Eligible 
Load” or propose other changes to implement this directive.273  Consistent with this 
directive, PJM is proposing to add the term Eligible Load to the Tariff to encompass both 
Co-Located Load and Load with BTMG.274  To that end, PJM is proposing to add to the 
Tariff, Part I, section 1, Definitions the term “Eligible Load” defined as “Co-Located Load 
or load connected to Behind the Meter Generation.”275  Further consistent with the 
Commission’s directive to propose other Tariff changes necessary to expand the 
 
271 PJM also proposes herein formatting and language changes to the Necessary Study provisions in Part VIII, 
Subpart A, section 401(H)(3), to make clear that the Necessary Study process applies to all Project 
Developers that plan to make modifications to their facilities, “including but not limited to a Project 
Developer whose planned modifications include an Eligible Load configuration.”  Attachment A-1, Proposed 
Tariff, Part VIII, Subpart A, section 401(H)(3)(a).  PJM further proposes minor, ministerial changes to Tariff, 
Part VIII to spell out the term “Generation Interconnection Agreement” and replace “PJM” with 
“Transmission Provider,” as appropriate.  See, e.g., Attachment A-1, Proposed Tariff, Part VIII, Subpart C, 
section 408(A)(2)(e)(i)(j)(iv); Proposed Tariff, Part VIII, Subpart E, sections 414(B)(2), 414(B)(4)(c). 
272 Co-Location Order, 195 FERC ¶ 61,209, at P 91. 
273 Co-Location Order, 195 FERC ¶ 61,209, at P 91. 
274 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – E - F) (adding the definition of “Eligible 
Load”). 
275 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – E - F) (adding the definition of “Eligible 
Load”).

PDF page 57

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 53 
 
53 
availability of these new services, PJM is proposing to add to the term “Eligible Generating 
Facility” to the Tariff to encompass both a Co-Located Generating Facility or Retail 
BTMG.276  In addition, PJM is proposing conforming changes to replace “Co-Located 
Load” with “Eligible Load” and “Co-Located Generator” with “Eligible Generator” and 
other clarifying changes in Tariff Part I, section 1 (Definitions),277 Part III (Network 
Integration Transmission Service),278 Part VI (Administration and Study of New Service 
Requests),279 Part VII (Transition Cycle Generation Interconnection Procedure),280 Part 
VIII (New Rules Generation Interconnection Procedure),281 Part IX (Forms of 
 
276 “‘Eligible Load’ shall mean Co-Located Load or load connected to Behind the Meter Generation.  
‘Eligible Generating Facility’ shall mean a Co-Located Generating Facility or Behind the Meter Generation.”  
Proposed Tariff, Part I, section 1 (Definitions – E - F) (defining “Eligible Load” and “Eligible Generating 
Facility”). 
277 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – O - P - Q) (updating the definition of 
“Provisional Interconnection Service” to reference “Eligible Load” instead of just “Co-Located Load”). 
278 Attachment A-1, Proposed Tariff, Part III, section 28.1 (replacing “Co-Located Load” with “Eligible 
Load”); section 29.1 (allowing customers to take NITS on behalf of “Eligible Load” instead of “Co-Located 
Load”); Proposed Tariff, Part III, section 29.2 (replacing “Co-Located Load” with “Eligible Load” in 
Application procedures); Proposed Tariff, Part III, section 31.6 (replacing “Co-Located Load” with “Eligible 
Load” in annual load and resource information update). 
279 Attachment A-1, Proposed Tariff, Part VI, Subpart B, section 212 (adding language in Part VI, Subpart 
B, section 212 regarding the Necessary Study process in Part VIII for Generating Facilities to reference 
service to Eligible Loads). 
280 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions E (adding the definitions 
for “Eligible Load” and “Eligible Generating Facility”); Proposed Tariff, Part VII, Subpart A, section 300, 
Definitions P (revising the definition of “Provisional Interconnection Service” to reference “Eligible 
Generating Facility” and “Eligible Load”). 
281 Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 400, Definitions E (adding the definitions 
for “Eligible Load” and “Eligible Generating Facility”); Proposed Tariff, Part VIII, Subpart A, section 400, 
Definitions P (updating the definition of “Provisional Interconnection Service” to reference “Eligible 
Generating Facility” and “Eligible Load”); Proposed Tariff, Part VIII, Subpart A, section 401 (revising the 
Application requirements to allow Eligible Generating Facilities serving Eligible Load and clarifying the 
Necessary Studies process applies to Eligible Load); Proposed Tariff, Part VIII, Subpart B, section 403 
(revising the Application rules to allow Eligible Generating Facilities serving Eligible Load); Proposed 
Tariff, Part VIII, Subpart C, section 404 (updating the System Impact Studies to contemplate service to 
Eligible Load); Proposed Tariff, Part VIII, Subpart C, section 406 (updating the acceleration language to 
allow acceleration of new service requests for new facilities or increases the generation capability in existing 
facilities to serve Eligible Load); Proposed Tariff., Part VIII, Subpart C, section 408 (same); Proposed Tariff, 
Part VIII, Subpart E, section 413 (updating the language permitting service requests below the Maximum 
Facility Output for new facilities or increases the generation capability in existing facilities that will serve

PDF page 58

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 54 
 
54 
Interconnection-Related Agreements),282 and Part XI, Subpart A (Interim Network 
Integration Transmission Service).283 
3. 
Elimination of new GIA requirement 
PJM previously proposed to require all Eligible Customers that intend to serve Co-
Located Load with a new or existing Co-Located Generating Facility to enter into a new 
GIA pursuant to Part VIII of the Tariff, which was revised to include additional details 
regarding the Necessary Studies process.284  The Co-Location Order rejected this proposal 
for customers with existing service agreements and directed PJM to add language 
concerning the Necessary Study process to Tariff, Parts VI and VII to allow customers with 
existing service agreements to modify those agreements.285  Accordingly, PJM is proposing 
changes to allow customers that obtained service agreements pursuant to Parts VI and VII 
to modify those agreements pursuant to the Necessary Study process in Part VIII.286  
 
Eligible Load); Proposed Tariff, Part VIII, Subpart E, section 414 (updating the language to permit Surplus 
Interconnection Service for Eligible Load). 
282 Attachment A-1, Proposed Tariff, Part IX, Subpart A (Form of Application and Studies Agreement), 
section 1 (revising section 1 of the Application and Studies Agreement to collect Applicant information for 
an Eligible Generating Facility serving Eligible Load); Proposed Tariff, Part IX, Subpart A (Form of 
Application and Studies Agreement), section 3.17 (changing “PJM” to “Transmission Provider” and 
clarifying all transmission service requests in the PJM Region are subject to the same deliverability tests); 
Proposed Tariff, Part IX, Subpart B, GIA Appendices and Schedules, Schedule O (updating Schedule O to 
replace “Eligible Load” with “Eligible Generating Facility”); Proposed Tariff, Part XI, Subpart G, Necessary 
Studies Agreement (updating the Necessary Studies Agreement to reference “Eligible Load” and “Eligible 
Generating Facility”).  
283Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 700 (updating references to “Co-Located 
Load” to “Eligible Load”); Proposed Tariff, Part XI, Subpart A, section 701.1 (same); Proposed Tariff, Part 
XI, Subpart A, section 701.2 (same); Proposed Tariff, Part XI, Subpart A, section 701.3 (same); Proposed 
Tariff, Part XI, Subpart A, section 702.1 (same); Proposed Tariff, Part XI, Subpart A, section 702.4 (same); 
Proposed Tariff, Part XI, Subpart A, section 703 (same). 
284 See Co-Location Order, 195 FERC ¶ 61,209, at P 284; Attachment A-1, Proposed Tariff, Part VIII, Subpart 
A, section 401(H)(3). 
285 Co-Location Order, 195 FERC ¶ 61,209, at P 311. 
286 See supra note 58 concerning addition of Necessary Study language to Parts I, III, VI, and VII; 
Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 401(I).  PJM also proposes to cross-reference 
Tariff, Part VIII, Subpart L, section 439, Provisional Interconnection Service, added in the Thirty-Day 
Compliance Filing, in Parts VI and VII to clarify that Provisional Interconnection Service is available to

PDF page 59

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 55 
 
55 
For Interconnection Customers that utilized the Part VI process, because Part VI 
does not contain discrete definitions, PJM is revising the proposed definition of Co-Located 
Generating Facility in Part I to include an existing Customer Facility that is physically 
connected to Co-Located Load to incorporate the relevant terms from Part VI.287  As 
explained above, to ensure that existing Interconnection Customers with effective 
Interconnection Service Agreements (“ISA”) do not serve Co-Located Load until all 
necessary upgrades and equipment are in place,288 PJM is also adding to the Co-Located 
Generating Facility definition a requirement to provide advance written notice to the 
Transmission Provider and Transmission Owner to initiate the Necessary Study process 
pursuant to Part VIII, Subpart A, section 401(H)(3)(b) to use a Customer Facility to serve 
Co-Located Load.289  In addition, PJM is adding language to mirror this Necessary Study 
process requirement in Part VI, Subpart B, section 212.290  Finally, PJM has updated the 
pro forma Necessary Studies Agreement to include language for Queue No., reference 
Part VI for ISAs, incorporate references to Interconnection Customers throughout, and 
 
entities that obtained Interconnection Service under those Parts.  See Attachment A-1, Proposed Tariff, Part 
I, section 1 (Definitions – O - P - Q) (updating the definition of “Provisional Interconnection Service”); 
Proposed Tariff, Part VII, Subpart A, section 300, Definitions P (same); Proposed Tariff, Part VIII, Subpart 
A, section 400, Definitions P (same).  
287 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – C - D) (revising the definition of “Co-
Located Generating Facility”). 
288 Co-Location Order, 195 FERC ¶ 61,209, at P 285. 
289 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – C - D) (adding to the definition of “Co-
Located Generating Facility”). 
290 Attachment A-1, Proposed Tariff, Part VI, Subpart B, section 212.  PJM also proposes to add new Tariff, 
Part VIII, Subpart A, section 401(I) to clarify that Interconnection Customers with ISAs under Tariff, Part 
VI may utilize the Part VIII Necessary Study process and will be referred to as Project Developers or 
Generation Project Developers and their agreements referred to as GIAs when doing so.

PDF page 60

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 56 
 
56 
reference Tariff, Attachment O, Appendix 2, section 3 in paragraph 5 concerning the 
purpose of the Necessary Studies.291 
For Generation Project Developers that utilized the Part VII Transition Cycle 
Interconnection Process, PJM is proposing to modify the definition of Co-Located 
Generating Facility to include both an existing and planned Generating Facility.292  
Consistent with the proposed changes in Part VI, PJM is adding a requirement to provide 
Transmission Provider and Transmission Owner with advance written notice to initiate the 
Necessary Study process pursuant to Part VIII, Subpart A, section 401(H)(3)(b) in the event 
a Generation Project Developer with an effective GIA intends to use a Generation Facility 
to serve Co-Located Load.293  PJM is also adding this advance notice requirement for the 
Necessary Study process to Tariff, Part VII, Subpart A, section 301(A)(7)(c).294  Finally, 
PJM is proposing a definition of Co-Located Load that references the relevant terms for 
Part VII of the Tariff (i.e., Generating Facility and Project Developer).295 
 
291 Attachment A-1, Proposed Tariff, Part IX, Subpart G, Necessary Studies Agreement. 
292 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions C (definition of Co-
Located Generating Facility). 
293 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions C (definition of Co-
Located Generating Facility). 
294 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 301(A)(7)(c); Proposed Tariff, Subpart A, 
section 300, Definitions N. 
295 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions C.

PDF page 61

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 57 
 
57 
4. 
Effective date only 
In addition, PJM previously proposed compliance changes that were accepted in 
the Co-Location Order without an effective date.296  Accordingly, PJM is re-filing the 
following Tariff records with a proposed effective date of March 16, 2027: 
• Part I, section 1, Definitions – A-B (BTMG);297  
• Part III, section 34.3 (Netting of Non-Retail BTMG);298 
• Part VII, Subpart A, section 300, Definitions B (BTMG);299 
• Part VIII, Subpart A, section 400, Definitions B (BTMG);300 and 
• Part VIII, Subpart A, section 400, Definitions N (Necessary Study).301 
E. 
Changes to Be Addressed in Future Filings 
PJM has identified certain changes to be addressed in future filings.  PJM will need 
to amend Schedule 1 of the Operating Agreement to allocate Auction Revenue Rights to 
FCD Transmission Service customers and may need to make conforming changes to the 
RAA regarding Capacity Market and load forecast effects of the new services.  If, after 
further stakeholder engagement or Commission direction, it appears prudent or necessary 
to further clarify this matter in a filing, PJM will do so.  
 
296 See, e.g., Co-Location Order, 195 FERC ¶ 61,209, at P 207 n.519; Sixty-Day Compliance Filing at 35. 
297 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – A - B) (updating the definition of “Behind 
the Meter Generation”); Co-Location Order, 195 FERC ¶ 61,209, at P 207 n.519. 
298 Attachment A-1, Proposed Tariff, Part III, section 34.3. 
299 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions B. 
300 Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 400, Definitions B. 
301 Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 400, Definitions N; Co-Location Order, 
195 FERC ¶ 61,209, at P 280 n.670.

PDF page 62

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 58 
 
58 
Other than the form of Necessary Studies Agreement, initially filed in the 
August 17 Filing,302 that PJM is re-filing here because it will be needed in the interim 
period before the Fast Energization Process begins, PJM is not proposing to revise the 
forms of interconnection-related service agreements in Tariff, Part IX (e.g., the form of 
Application and Studies Agreement, the GIA, the Wholesale Market Participation 
Agreement, and others) in this filing.  PJM plans to file revisions to those forms in a later, 
supplemental filing, once the Commission has ruled on or provided guidance concerning 
the Tariff revisions to Part VIII proposed herein.  In that supplemental filing, PJM also will 
propose other revisions to the interconnection-related service agreement in Tariff, Part IX 
to streamline the service agreement negotiation and contracting process, based on lessons 
learned to date in the Transition Period and in Cycle 01 and on PJM’s automation efforts.  
Finally, depending on the Commission’s rulings or guidance on the cost recovery 
provisions the Transmission Owners are filing concurrently, PJM will need to add to the 
Tariff a form of agreement for PJM to hold Project Developers’ post-commercial operation 
Security, as required to support the Transmission Owners’ fees charged to Project 
Developers.303   
PJM is filing separately today a motion for additional abeyance so that it can make 
these supplemental filings. 
 
302 August 17 Filing, Attachment A, Tariff, Part IX, Subpart G. 
303 See Attachment A-2, Proposed Tariff, Part VIII, Subpart D, section 411(C).

PDF page 63

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 59 
 
59 
IV. 
THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES AS 
JUST AND REASONABLE. 
A. 
The Proposed Fast Energization Process Is Just and Reasonable and 
Advances the Commission’s Categories for Reform in the June 2026 
Orders 
The Fast Energization Process is just and reasonable for four principal reasons.  
First, it is designed to address and promote meaningful improvement in response to real 
challenges facing the grid: insufficiently fast interconnection processes for load and 
generation, parallel and duplicative study processes, speculative requests, limited visibility 
into the drivers of transmission upgrades, and an ongoing resource adequacy shortfall.  
Second, it is built on a unifying design that studies generation and load together, shortens 
the process by half, and moves readiness and financial commitments to the front of the 
process to promote readiness to build.  Third, it preserves the first-ready, first-served 
principle from recent interconnection study process reforms (consistent with Order No. 
2023)304 and adds greater transparency and cost certainty.  Fourth, its core features track 
the directives of the Large Load Show Cause Order.305  The Commission need not find that 
PJM’s proposal is the only reasonable approach in order to accept it, only that PJM’s 
proposal is a just and reasonable one.306 
 
304 Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC 
¶ 61,054, limited order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g & clarification, Order No. 
2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134 (2024), aff’d sub nom., Advanced Energy 
United v. FERC, 185 F.4th 186 (D.C. Cir. 2026). 
305 See Attachment D, Chart Mapping Order Directives to Tariff Changes, at 17-25. 
306 Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (“Cities of Bethany”); see ISO New Eng. 
Inc., 114 FERC ¶ 61,315, at P 33 & n.35 (2006) (citing Pub. Serv. Co. of N.M. v. FERC, 832 F.2d 1201, 1211 
(10th Cir. 1987); Cities of Bethany at 1136); Oxy USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) 
(citing Cities of Bethany at 1136); cf. S. Cal. Edison Co., 73 FERC ¶ 61,219, at 61,608 n.73 (1995) (“Having 
found the Plan to be just and reasonable, there is no need to consider in any detail the alternative plans 
proposed by the Joint Protesters.” (citing Cities of Bethany at 1136)).

PDF page 64

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 60 
 
60 
B. 
Core Features of the Fast Energization Process That Enhance the 
Current Cycle Process 
1. 
PJM’s current process provides only some visibility into the 
transmission needs created by Large Loads 
Under the current planning processes, transmission service for Large Loads is 
subsumed within PJM’s RTEP.  System reinforcements needed to serve Large Loads are 
identified through separate processes, including the Transmission Owners’ processes (e.g., 
Attachment M-3 and Form 715 planning processes) and PJM’s Do No Harm process, and 
are “trued up” as load interconnection projects are incorporated into the RTEP.307  PJM’s 
proposal provides more visibility into the transmission build-out driven by Large Loads so 
that PJM can ensure sufficient transmission capability exists in the timeframe in which a 
Large Load plans to come online.  Studying transmission service together with generation 
interconnection will allow PJM and the Transmission Owners to be more transparent about 
the drivers of the reinforcements required to serve Large Loads.308 
2. 
Resource Adequacy requires getting new generation online faster. 
PJM continues to need additional generating capacity to maintain reliable service 
for the 67 million people in the PJM Region and to serve new Large Loads.  As PJM’s 
Five-Year Strategy recognizes, “in today’s environment, reliability is not possible without 
resource adequacy.”309  The 2028/2029 Base Residual Auction Report shows that the 
shortfall of capacity supply needed to meet demand, plus an adequate reserve margin, has 
grown year over year, despite a net increase of 1,294.4 MW of Installed Capacity between 
 
307 Bielak Decl. ¶ 11. 
308 Id. 
309 Shaping a Power Change: PJM Five-Year Strategy, PJM Interconnection, L.L.C., 1 (Aug. 2026), 
https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-
… [https://perma.cc/2RBY-MPLH].

PDF page 65

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 61 
 
61 
the 2027/2028 and 2028/2029 auctions.  New supply has not kept pace with rapid Large 
Load growth.310 
Although PJM has 47 GW of generation with signed agreements, many of those 
projects are not being built or are slowed by state permitting and supply chain backlogs.  
The factor that PJM Planning can influence is the interconnection process.311  Speeding up 
that process is therefore the most effective step PJM can take, because faster study results 
allow developers to shift their focus to more viable projects and may lessen or remove other 
barriers, such as permitting and siting approvals.312 
3. 
Incremental and parallel fixes are not enough – a singular process 
for generation and transmission service requests yields efficiencies. 
To facilitate the interconnection of additional generation capacity, PJM has already 
adopted the Expedited Interconnection Track, Replacement Generation Interconnection 
Service, and the Reliability Resource Initiative.  These measures are beneficial but were 
designed largely to manage PJM’s transition from the old serial queue process to the Cycle 
process, and a significant volume of Generation Interconnection Requests remains.313  PJM 
seeks to avoid adding separate parallel processes for provisioning transmission service to 
Eligible Load and Large Load, having experienced the complications that parallel 
processes can cause.  Moreover, Large Loads differ fundamentally from traditional load 
growth in size, pace, and concentration, and they are the only major source of load 
growth.314  Limiting study of transmission service for Large Loads to a separate process 
 
310 Bielak Decl. ¶ 12. 
311 Bielak Decl. ¶ 13. 
312 Bielak Decl. ¶ 15. 
313 Bielak Decl. ¶ 14. 
314 Bielak Decl. ¶ 15.

PDF page 66

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 62 
 
62 
from Generation Interconnection Requests would likely lead to a sub-optimal build-out of 
the Transmission System that would place unnecessary costs on existing loads.315 
Studying new Generation Interconnection Requests and new Large Load 
transmission service requests together speeds up interconnection, helps ensure that new 
generation is deliverable to new Large Loads, allows the costs of needed transmission 
enhancements to be determined efficiently, and allows those costs to be accurately 
allocated to the cost causers.316 
4. 
The Fast Energization Process is a single, unified process that 
should be twice as fast as the current process. 
PJM proposes to consolidate Generation and Merchant Transmission 
Interconnection with Long-Term Firm and Large Load Transmission Service studies into 
a singular 12-month process.  The process will take half the time of the Cycle process.317  
It replaces the three complete System Impact Studies of the current process with an 
accelerated screening window, consisting of two turns of system impact analysis and a 
single System Impact Study.318  Each turn of the screening window provides planning-level 
estimates of the system reinforcements needed for the portfolio of generation projects and 
transmission service requests, called “Interconnection Reliability Reinforcements” 
(“IRR”).319  Each turn produces a non-binding good-faith estimate of the cost and the time 
 
315 Bielak Decl. ¶ 15. 
316 Bielak Decl. ¶ 16. 
317 Bielak Decl. ¶¶ 9, 17. 
318 Bielak Decl. ¶ 21. 
319 Bielak Decl. ¶ 21.

PDF page 67

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 63 
 
63 
to construct the needed facilities within 60-90 calendar days.320  Figure 1 illustrates the 
new process. 
 
Figure 1: The Fast Energization Process321 
The expedited screening window gives developers and customers solution feedback 
very early, while the decision points require a demonstration of readiness to proceed.322  
5. 
Technology and early engagement speed the process. 
PJM will use technology to speed up project data review, power flow and dynamic 
studies, and agreement drafting.  PJM has been vetting Tapestry, an AI-powered 
interconnection platform, in its current process and is nearing the point at which it can trust 
the platform’s results without parallel human verification.323  PJM is also developing a 
suite of automation, including improvements to its modeling platform, analytics platforms 
 
320 Bielak Decl. ¶ 21. 
321 Bielak Decl. ¶ 21. 
322 Bielak Decl. ¶ 18. 
323 Bielak Decl. ¶ 19.

PDF page 68

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 64 
 
64 
to turn around grid studies more quickly, and result interpretation and quality assurance 
tools to preserve study quality in a shorter period.324 
The process also includes Early Application Engagement.325  Between the Soft 
Close Date and the Application Deadline, PJM will answer Applicants’ questions, test and 
provide feedback on their models, and help them complete their Applications.326  This 
engagement should improve the quality of Applications, allow PJM’s post-deadline review 
to be quick, reduce disputes over Application review, deficiency notices, and cure efforts, 
and produce more Applications for truly viable and ready projects.327  The improvement is 
much needed: at present, only five percent of Applications submitted to PJM are correct 
and complete when first submitted.328 
6. 
Study consolidation preserves study rigor 
Faster does not mean less rigorous.  The System Impact Study is the equivalent of 
the Phase III System Impact Study in the current Cycle process.329  PJM will perform load 
flow, stability, and short circuit analyses across summer, winter, and light load scenarios 
and will ensure that all reliability issues are addressed and that the correct amount of 
transmission service has been provisioned.330  Negotiation of service agreements begins 
during the System Impact Study Phase, which further reduces the total time needed.331 
 
324 Bielak Decl. ¶¶ 9, 19. 
325 Bielak Decl. ¶ 20. 
326 Bielak Decl. ¶ 20. 
327 Bielak Decl. ¶ 20. 
328 Bielak Decl. ¶ 20. 
329 Bielak Decl. ¶ 22. 
330 Bielak Decl. ¶ 22. 
331 Bielak Decl. ¶ 22.

PDF page 69

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 65 
 
65 
7. 
Readiness requirements are moved to the front of the process. 
The Fast Energization Process continues the current Cycle process’s emphasis on 
readiness but moves many requirements into the Application rather than spreading them 
over three phases.  The financial commitments are likewise moved up in time.  Eligible 
Customers seeking transmission service on behalf of Large Loads must enter into a 
Transmission Owner Cost Recovery Agreement to enter the process.332  Project Developers 
must submit Readiness Deposits in full with the Application, and those deposits become at 
risk at decision points in the Screening Phase.333  Physical changes to projects and load are 
not allowed after Application, because they would require changes to the dynamic models 
submitted with the Application and the new process leaves no time to revise individual 
models and the cluster model.  A developer or customer wishing to change its project or 
load must withdraw and resubmit in the next Cycle.334 
These requirements screen out speculative projects and help ensure that projects 
that enter an interconnection-related service agreement are truly ready to start construction, 
complete construction and commissioning on a timely basis, and enter service.335  They 
also preserve the first-ready, first-served paradigm of the current Cycle process.336 
 
332 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A) (“To initiate an Eligible Customer 
for Load Request, an Eligible Customer must provide to Transmission Provider the relevant Transmission 
Owner or Electric Distributor authorization for the Eligible Customer for Load Request to be studied in the 
relevant Cycle, as well as an executed Cost Recovery Agreement with the relevant Transmission Owner.”). 
333 Bielak Decl. ¶ 23. 
334 Id. 
335 Bielak Decl. ¶ 7. 
336 Id. ¶ 17.

PDF page 70

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 66 
 
66 
8. 
A portfolio approach to system reinforcements provides 
transparency and certainty. 
The Fast Energization Process moves PJM away from identifying specific upgrades 
and tying them to specific projects.  PJM instead will analyze upgrades and reinforcements 
as enabling the entire Cycle cohort of generation projects and transmission service requests.  
The resulting IRRs are optimized for the whole Cycle, which eliminates overlapping or 
duplicative upgrades for generation and load.  This approach also allows a fractional 
amount of generating capacity to become deliverable faster and with greater certainty, 
rather than only upon completion of all required Network Upgrades.337 
Transparency.  The Transmission Owners hold the filing rights for cost allocation 
and cost recovery and are addressing those matters in Tariff revisions filed concurrently.  
PJM will continue to provide transparency as to required system topology, the drivers of 
the need for the IRRs, and their capital costs.  Consistent with the Large Load Show Cause 
Order, PJM will post this information on pjm.com in a single, accessible, searchable 
location.338 
Certainty.  Because Project Developers will be responsible for a share of the total 
cost of the portfolio of IRRs, rather than for specific upgrades, optimization should reduce 
both total cost and volatility in a developer’s cost responsibility.  If a Project Developer’s 
cost responsibility nonetheless rises above the amount determined at Decision Point II, the 
Tariff now includes a certainty framework to limit exposure to the increase.339  Figure 2 
compares the current and new processes. 
 
337 Bielak Decl. ¶ 24. 
338 Bielak Decl. ¶ 25; Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A)(2). 
339 Bielak Decl. ¶ 26.

PDF page 71

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 67 
 
67 
 
Figure 2: Current process compared with the Fast Energization Process340  
9. 
Interim rights allow service to begin sooner. 
Because PJM will not tie service to completion of specific “contingent upgrades,” 
the final service agreements will include a schedule of interim deliverability for Project 
Developers or a schedule of interim withdrawal rights for Eligible Customers, based on the 
current Transmission System topology.341  The schedules set a minimum level of injection 
or withdrawal rights based on the available studies and anticipated Transmission System 
conditions in future years.342   PJM will then annually reassess and update the interim rights 
based on updated system conditions (i.e., as raise the MW value if more IRRs are built or 
queue projects withdraw).343 
 
340 Bielak Decl. ¶ 26. 
341 Bielak Decl. ¶ 27; Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A)(1). 
342 Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A)(1). 
343 Bielak Decl. ¶ 27.

PDF page 72

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 68 
 
68 
C. 
The Fast Energization Process Is Consistent with the Large Load Show 
Cause Order’s Directives. 
In the Large Load Show Cause Order, the Commission preliminarily found that 
PJM’s Tariff appears unjust and unreasonable without certain provisions and encouraged 
PJM to address those concerns through a section 205 filing.344  The Fast Energization 
Process addresses the opportunities as summarized below and discussed in the following 
sections.   
Large Load Show Cause 
Order opportunity 
Fast Energization Process feature 
Study transmission service 
for Eligible Customers on 
behalf of large loads clearly 
and consistently, within 60-
90 days345 
 
Single Tariff-defined process; two screening turns, each 
producing a non-binding good-faith estimate of cost and 
construction time within 60-90 calendar days; a single 
System Impact Study346  
 
Application 
process 
with 
readiness requirements that 
deter 
speculative 
or 
duplicative requests347 
Readiness requirements moved to the Application; 
Readiness Deposits submitted in full and at risk at 
decision points; Cost Recovery Agreement required to 
enter; no physical changes after Application; Early 
Application Engagement348  
 
Transparency on Network 
Upgrade drivers and costs, 
posted in a single, accessible, 
searchable location349  
 
PJM will post required system topology, the drivers of 
need, and capital costs on pjm.com in a single, 
searchable location350  
 
Mitigate cost-shifting risk 
through a cost 
recovery 
agreement351  
Transmission Owner Cost Recovery Agreement 
required of Eligible Customers for Large Load requests; 
Transmission Owners are addressing cost allocation and 
 
344 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 3, 38. 
345 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 41, 63. 
346 Bielak Decl. ¶¶ 17, 21-22; Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404. 
347 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 59. 
348 Bielak Decl. ¶¶ 7, 18, 20, 23; Attachment A-2, Proposed Tariff, Part VIII, section 401-404. 
349 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 66-67, 71-76. 
350 Bielak Decl. ¶ 25. 
351 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 77-84.

PDF page 73

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 69 
 
69 
Large Load Show Cause 
Order opportunity 
Fast Energization Process feature 
recovery in their concurrent filing; Readiness Deposits 
for Project Developers352  
 
Transmission services 
reflecting flexible large 
loads353 
NITS, Interim NITS, NFCD Transmission Service, 
FCD Transmission Service schedules for Eligible 
Loads and Large Loads354  
 
Generator interconnection 
that accounts for electrically 
proximate large load355  
Generation and load studied together in one Cycle; 
IRRs optimized for the whole cohort; interim 
deliverability schedules356  
 
 
1. 
Timely, clear, and consistent study of transmission service for large 
loads 
One of the Commission’s principal concerns was that PJM’s Tariff lacked 
sufficiently clear and consistent provisions on how transmission service to Eligible 
Customers on behalf of large loads will be studied.  The Commission concluded that a 
study process culminating in a report with a non-binding good-faith estimate of the cost 
and time to construct needed facilities should take no more than 60-90 calendar days.357   
The Fast Energization Process addresses this concern by placing Large Load 
transmission service requests in the same defined, Tariff-based process as generation and 
long-term firm service.  Each screening turn produces a non-binding good-faith estimate 
of cost and construction time within 60-90 calendar days, and the System Impact Study 
 
352 Bielak Decl. ¶¶ 23, 25; Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401. 
353 Bielak Decl. ¶ 27. 
354 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 85-87; Attachment A-1 Proposed Tariff, Part 
XI, Subpart A, section 700; Proposed Tariff, Part XI, Subpart B, section 708. 
355 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 88-101. 
356 Bielak Decl. ¶¶ 6, 10, 16, 24, 27; Attachment A-2, Proposed Tariff, Part VIII, sections 401, 404, 440. 
357 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 41, 50-51, 63.

PDF page 74

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 70 
 
70 
then confirms that all reliability issues are addressed and that the correct amount of 
transmission service is provisioned.358 
The Commission also recognized that the Transmission Owners may be primarily 
responsible for load studies and stated that it does not seek to alter the allocation of rights 
and responsibilities among PJM and the Transmission Owners.359  The Fast Energization 
Process is consistent with that statement.  It enhances PJM’s own study process, and the 
Transmission Owners are submitting their cost allocation and cost recovery revisions 
separately, because they hold those filing rights.360 
2. 
Readiness requirements that deter speculative requests 
The Commission expressed concern that the Tariff fails to deter speculative or 
duplicative requests and observed that clear study procedures with readiness requirements, 
including meaningful milestones and financial commitments, can help ensure that requests 
are viable.361  The Fast Energization Process accomplishes this objective. It moves 
readiness requirements and financial commitments into the Application,362 requires a 
Transmission Owner Cost Recovery Agreement from Eligible Customers seeking service 
on behalf of Large Loads to enter the process,363 places Readiness Deposits at risk at 
 
358 Bielak Decl. ¶¶ 10, 21-22. 
359 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 52. 
360 Bielak Decl. ¶ 25. 
361 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 56, 59. 
362 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(D)(1)(b). 
363 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A).

PDF page 75

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 71 
 
71 
decision points,364 and bars physical changes after Application.365 Early Application 
Engagement further improves the quality of Applications from the outset.366 
3. 
Transparency regarding upgrades and their costs 
The Commission preliminarily found that cost transparency measures are needed 
so that stakeholders, including state regulators, can understand the Network Upgrades, and 
their costs, needed to serve large loads.367  It stated that this information should be posted 
on PJM’s website in a single location, in an accessible and searchable format.368  PJM will 
post the required system topology, the drivers of the need for the IRRs, and their capital 
costs on pjm.com in a single, accessible, and searchable location.369  Studying generation 
and transmission service together also makes the drivers of reinforcements more visible.370  
Further, the Fast Energization Process will result in changes to the Large Load Adjustment 
process in PJM’s load forecasting procedures, impacting the number of RTEP projects 
needed because of Large Loads that are then cost allocated to ratepayers generally.371 
4. 
Protection against cost shifting 
The Commission was concerned that, absent adequate mechanisms, costs incurred 
to serve large loads that do not materialize could be shifted to other transmission customers, 
and it preliminarily found that a cost recovery agreement with a minimum contribution and 
 
364 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(2A). 
365 Attachment A-2, Proposed Tariff, Part VIII, Subpart B, section 403. 
366 Bielak Decl. ¶¶ 18, 20, 23. 
367 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 71-76.  
368 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 66-67, 71-76. 
369 Bielak Decl. ¶ 25. 
370 Id. ¶ 11. 
371 Bielak Decl. ¶¶ 15, 24.

PDF page 76

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 72 
 
72 
financial security appears necessary.372  The Fast Energization Process requires Eligible 
Customers seeking service on behalf of Large Loads to enter into a Transmission Owner 
Cost Recovery Agreement as a condition of entering the process, and it requires Project 
Developers to post Readiness Deposits in full with their Applications.373  Because the 
Transmission Owners hold the filing rights for cost allocation and cost recovery, they 
address those matters in their concurrent Tariff revisions.374  The portfolio approach and 
the certainty framework also reduce the risk of cost swings during the process.375 
At its core, the Fast Energization Process’s cost allocation mechanism will address 
the cost allocation for incremental system adjustments necessary to meet reliability drivers 
and needs of the Process’s transmission service and generation project clusters.  There will 
no longer be any direct tie between an individual project (generation or transmission 
service) and specific “upgrade facilities.”376  Instead, what will be identified in the Fast 
Energization Process is the “percentage cost responsibility” based on a proportional impact 
method, consistent with Order No. 2023, as to the collective Cycle portfolio.  Armed with 
this information, states pursuant to their retail rate authority may elect to cost allocate IRR 
among particular loads in each of their particular states.  PJM’s process therefore offers a 
means to “give state public utility commissions and other state regulators the information 
necessary to allow them to understand which transmission costs are caused by which 
 
372 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 66, 77-84. 
373 Bielak Decl. ¶ 23. 
374 Id. ¶ 25. 
375 Id. ¶¶ 17, 24, 26. 
376 Bielak Decl. ¶ 23.

PDF page 77

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 73 
 
73 
transmission customers, so that they can sub-allocate these costs to the appropriate retail 
customers.”377   
5. 
Transmission services that reflect flexible use of the system 
The Commission preliminarily found that new transmission services should be 
available to reflect the operational reality that some large loads are willing and able to limit 
their use of the Transmission System, including an interim service while Network 
Upgrades are constructed.378  The Fast Energization Process provides for interim rights in 
the final service agreements.379  For interim deliverability, the Transmission Provider will 
determine a schedule of the minimum injection and withdrawal limits based on anticipated 
Transmission System conditions that will then be reassessed with an annual study.380  PJM 
estimates that it can begin provisioning these rights as proposed in 2029 after commencing 
Application and study processes later on in 2027.381  These rights will be revised 
periodically to increase the minimums as IRRs are completed or projects withdraw.382 
6. 
Studying generation and transmission service requests to serve 
Large Load together leverages technology and innovation. 
The Commission recognized that studying new load and new generation together 
can present system benefits, speed interconnection, and enable more accurate and cost-
effective transmission solutions, and it asked PJM to consider how its interconnection 
 
377 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 70. 
378 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 85-87. 
379 Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A). 
380 Attachment A-2, Proposed Tariff, Part VIII, Subpart L, sections 440(A)(1)-(2). 
381 See supra Section III.B.3. 
382 Bielak Decl. ¶ 27; Proposed Tariff, Part VIII, Subpart L, section 440(A)(2).

PDF page 78

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 74 
 
74 
processes should reflect those benefits.383  The Fast Energization Process is built on that 
premise.  It studies generation, Merchant Transmission, Long-Term Firm, and Large Load 
Transmission Service requests in one Cycle.  It optimizes the IRRs for the whole Cycle 
and eliminates overlapping or duplicative upgrades for generation and load.  PJM identifies 
leveraging co-location and electrical proximity as one of the innovations of the process.384  
This integrated process will harness synergies in study results that reflect both transmission 
service and generation impacts, resulting in potentially lower Network Upgrade and IRR 
needs at early stages of the project life cycle. 
Because of the unique characteristics of Large Load, it is essential for PJM to study 
Generation Interconnection Requests and Large Load Transmission Service requests 
together through the Fast Energization Process.385  Large Loads are fundamentally different 
than traditional categories of load; they have significantly greater energy and capacity 
demands, these demands grow quickly, and the demand Large Loads are more 
geographically concentrated than from traditional loads.386  Given these characteristics, the 
provision of new transmission service—on a firm basis—to Large Loads generally requires 
transmission enhancements or expansions.  Large Loads are causing much of the load 
growth in the PJM Region and generation development is struggling to keep up,387 which 
 
383 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 88-91, 95-101. 
384 Bielak Decl. ¶¶ 6, 10, 16, 24. 
385 Bielak Decl. ¶ 16.  
386 Bielak Decl. ¶ 15; see also PJM’s concurrently-submitted Section 205 filing relating to ride-through, other 
operational requirements, and the annual transmission services report and the related exhibits attached 
thereto, which is incorporated by reference into this filing.  
387 Bielak Decl. ¶¶ 12-13, 15.

PDF page 79

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 75 
 
75 
poses unique challenges for the Transmission System.388  PJM’s current approach of 
evaluating interconnecting generation and providing transmission service to Large Load 
through distinct processes,389 makes it difficult to optimally build out the Transmission 
System considering the new challenges posed by Large Load.390 
Through the Fast Energization Process, PJM will holistically study the 
Transmission System impacts of generation and Large Load and optimize transmission 
enhancements that serve both simultaneously.391  The efficiencies from this combined 
study process will speed up generation interconnection and ensure that generation is 
deliverable to new Large Loads, PJM selects Transmission System upgrades efficiently, 
and the causers of Transmission System upgrades pay for the costs.392  Ultimately, this is 
a just and reasonable approach for evaluating how the transmission system needs to be 
updated to accommodate the transmission service needs of Large Loads in an efficient and 
cost effective manner. 
7. 
PJM’s proposal respects existing commercial arrangements and 
provides for a clear transition from the existing process to the Fast 
Energization Process. 
In the interim period before the Fast Energization Process commences in full, 
PJM’s proposed revisions to Tariff, Part VIII, Subpart A, section 401 set forth which 
transmission service requests will proceed under the existing planning regime and which 
 
388 See Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 58 (“[I]ntegrating large loads poses specific 
challenges to transmission system operation given their size, operational behavior, and unique potential to 
impact the transmission system.”). 
389 Bielak Decl. ¶¶ 11, 13-14. 
390 Bielak Decl. ¶ 15.  
391 Bielak Decl. ¶ 16. 
392 Bielak Decl. ¶ 16.

PDF page 80

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 76 
 
76 
service requests will proceed under the Fast Energization Process.393  This framework 
provides transparency to the market as to what must be done, and by when.  It respects 
existing commercial arrangements and affords a 13-month runway for arrangements in 
potential development but not yet finalized.  Eligible Customers have more than 
13-months’ notice to “complete[] the applicable . . . retail load interconnection study” to 
be treated under legacy constructs, or be processed under the new Fast Energization 
Process.394   
PJM specifically proposes a January 1, 2028 date for “completion” to accommodate 
the 2028 load forecast.  Setting a January 1, 2028 date ensures that the planning done under 
the status quo process is included in Large Load Adjustments submitted to PJM and thus 
properly reflected in the load forecast.395  The framework is also just and reasonable 
because “completion” is defined in terms of two objective criteria:  one technical (retail 
load study completion date) and one legal (date of execution of required agreements by all 
applicable parties).  Thus, under this framework, whether something has been “completed” 
is plainly understood, thus offering parties a path and timeline to develop plans.   
PJM’s proposal also enhances transparency consistent with the Commission’s 
stated goals.396  Those customers seeking transmission service on behalf of Large Loads 
must submit (or have others submit on their behalf) the information necessary to populate 
the Large Load Registry no later than 30 calendar days after the retail load interconnection 
 
393 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A). 
394 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A). 
395 Resource Adequacy Planning, PJM Manual 19:  Load Forecasting and Analysis, PJM Interconnection, 
L.L.C., § 3 (rev. 39, June 30, 2026), https://www.pjm.com/-/media/DotCom/documents/manuals/m19.pdf 
[https://perma.cc/4M4A-UD9N]; id. § 3.1 (“The forecast is . . . released prior to each Planning Period, 
typically in January.”).   
396 See, e.g., Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 76.

PDF page 81

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 77 
 
77 
study is deemed “complete.”397  This requirement promotes timely and accurate disclosure 
to those parties with access to the Registry of all new Large Load requests prior to even 
coming into service.  States, PJM, and other relevant stakeholders can inform decisions 
based upon these timely data submittals.  Further, stakeholders can then follow the study 
results for such requests, including the costs eventually allocated to them. 
Because of the value in ensuring planning under the existing process is reflected in 
the 2028 load forecast, the framework also provides for a streamlined and expedited dispute 
resolution framework to drive prompt clarity for Eligible Customers, PJM, and others about 
which requests will proceed under the Fast Energization Process.398  If Tariff-established 
deadlines and information for initiating Alternative Dispute Resolution and seeking 
Commission relief are not honored, or if litigation is timely commenced and resolved, then 
Eligible Customers submitting service requests will know that they will proceed under the 
Fast Energization Process without delay, which will reduce the risk that the 2028 load 
forecast report is delayed.   
D. 
The New Transmission Services Proposed in Part XI are Just and 
Reasonable. 
PJM has proposed to implement the three new transmission services as directed by 
the Commission.  PJM’s proposed implementation of these new services is just and 
reasonable.  PJM is proposing to make Interim NITS, FCD Transmission Service, and 
NFCD Transmission Service available to any Eligible Customer taking service on behalf 
 
397 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A). See also RAA, Schedule 
11,B.1 (accepted in PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48, filed on compliance in PJM 
Interconnection L.L.C., Thirty-Day Compliance Filing to the Commission’s October 9, 2026 Order on PJM’s 
Large Load Definition and Large Load Registry, Docket No. ER26-3515-002 (Nov. 9, 2026). 
398 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A).

PDF page 82

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 78 
 
78 
of an Eligible Load or Large Load.399  Because these services require an Eligible Customer 
to be willing and able to limit withdrawals from the Transmission System, PJM has 
proposed reasonable terms and conditions specific to these services.  To ensure the 
reliability of the Transmission System, Eligible Customers taking these services will be 
required to meet technical requirements demonstrating their ability to limit their 
withdrawals as a condition precedent.400  As part of these technical requirements, Eligible 
Customers must have necessary control technologies to limit their withdrawals from the 
Transmission System as specified in their Transmission Service Agreement, which may 
include protection schemes where appropriate.401  The Transmission Service Agreement 
will also specify any necessary operating procedures.402  Eligible Customers will also be 
required to demonstrate operational control to comply with instructions to reduce 
withdrawals from the system within five minutes when directed to do so.403  Consistent 
with the Commission’s directive,404 to the extent an Eligible Customer fails to follow a 
Curtailment instruction or the necessary control technologies misoperate, PJM is proposing 
a 120-day pause in service after the first instance, and to terminate the relevant 
Transmission Service Agreement after the second instance.405  Finally, PJM will be 
 
399 See Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 700; Proposed Tariff, Part XI, Subpart 
B, section 708. 
400 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 718. 
401 Attachment A-1, Proposed Tariff, Part XI, Subpart C, sections 717, 718.1. 
402 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, section 
5.0; Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission Service, section 5.0. 
403 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 718.1. 
404 Co-Location Order, 195 FERC ¶ 61,209, at PP 515, 519.  
405 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5.

PDF page 83

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 79 
 
79 
addressing ride-through requirements for Large Computational Load and other operational 
requirements for such loads in a separate filing being submitted today.  
E. 
PJM’s Proposed Changes to NITS are Just and Reasonable. 
Consistent with the Commission’s directives, PJM has proposed just and 
reasonable revisions to the terms and conditions for NITS to ensure that Large Load is 
appropriately studied for transmission service and accounted for in PJM’s transmission 
planning processes.406  PJM is proposing to quantify the current level of NITS being 
provided to Large Loads using the Large Load Registry.407  When approving the Large 
Load Registry, the Commission recognized that it would “provide PJM with the 
information necessary to address the operational impacts of Large Loads on the PJM 
transmission system.”408  The proposal will therefore allow PJM to establish a baseline 
regarding the current level of NITS being provided to Network Customers serving Large 
Loads.  PJM would then require an Eligible Customer to submit an application for any 
increase above the existing level of NITS for Large Loads.409  To that end,  PJM is 
proposing to strike the language in Tariff, Part III, section 31.6 that suggests an Application 
would not be required for changes reflected in these annual updates.410  Striking this 
 
406 See supra Section III.A.  
407 Attachment A-1, Proposed Tariff, Part III, General (“The amount of Regional Network Integration 
Transmission Service provisioned to Network Customers for serving Large Loads are at levels specified in 
an effective Service Agreement or, if not specified therein, as reflected on the Large Load Registry per the 
terms of the Reliability Assurance Agreement, Schedule 11.B.1”). 
408 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48.  
409 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, sections 400, Definitions E (defining Eligible 
Customer for Load Request as “a request by an Eligible Customer seeking Network Integration Transmission 
Service or Transmission Service on behalf of an Eligible Load or Large Load”); Attachment A-2, Proposed 
Tariff, Part VIII, Subpart C, sections 404(E). 
410 Attachment A-1, Proposed Tariff, Part III, section 31.6.

PDF page 84

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 80 
 
80 
language clarifies PJM’s proposal to require Large Loads that seek to grow above existing 
service levels to submit an Application to be studied through the Fast Energization Process.  
Further, regarding BTMG, the Commission directed PJM to “create a materiality 
threshold that allows Network Customers to net from their Network Load up to 50 MW of 
load served by using BTMG at a single electrical location.”411  Consistent with that 
directive, PJM proposes revisions to Part III, section 34.2 and Schedule 8 of the RAA to 
implement the 50 MW netting limit effective December 18, 2025, unless an exemption 
applies.412  PJM also proposes three exclusions to the 50 MW netting limit, as directed by 
the Commission.  
First, the Commission directed PJM establish a transition period of three years for 
Network Customers currently using PJM’s existing retail BTMG netting rules.413  PJM 
therefore proposes to exempt existing Retail BTMG that was used to serve load as of 
December 18, 2025 (i.e., the date of the December Order) from the BTMG netting limit 
during a three-year transition period.414  
Second, the Commission directed PJM to propose Tariff revisions to grant legacy 
treatment to entities with existing contracts for the specific purpose of effectuating a 
BTMG arrangement for the current term remaining under the existing contract. 415  PJM 
therefore proposes to exempt Retail BTMG owned or contracted for as of December 18, 
2025 to continue netting without the limit for the remaining term of the contract 
 
411 Co-Location Order, 195 FERC ¶ 61,209, at P 220.  
412 Attachment A-1, Proposed Tariff, Part III, section 34.2; Proposed Tariff, RAA, Schedule 8. 
413 December Order, 193 FERC ¶ 61,217, at P 223. 
414 Attachment A-1, Proposed Tariff, Part III, section 34.2(C). 
415 December Order, 193 FERC ¶ 61,217, at P 224.

PDF page 85

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 81 
 
81 
effectuating the BTMG arrangement.416  The Commission approved a three-year transition 
period and provisions granting legacy treatment in the Co-Location Order, as applied to 
PJM’s previously proposed BTMG netting proposal.417 
Third, the Commission directed PJM to include a process to exempt Cogeneration 
Facilities from its BTMG netting rules “if they demonstrate that they are integrated with 
load such that, when their generating facility trips offline, the load follows.”418  Consistent 
with this directive, PJM is proposing to exempt Cogeneration Facilities from its netting 
rules, subject to certain requirements to ensure the Cogeneration Facility is integrated with 
the retail load it serves such that if the Cogeneration Facility trips offline the retail load 
follows,419 including potential audits for compliance with these requirements.420 
To be eligible for the existing contractual arrangement or Cogeneration 
exemptions, PJM is proposing to require that the Large Load be on the Large Load Registry 
and the Retail BTMG be registered to allow PJM to account for the limit for settlement and 
billing purposes.421  To that end, PJM is also proposing revisions to RAA, Schedule 8 to 
ensure the netting limits are reflected in the Obligation Peak Load calculation.422  Taken 
together, these changes enhance PJM visibility into operating Retail BTMG in the region 
for planning purposes, while respecting existing commercial arrangements. 
 
416 Attachment A-1, Proposed Tariff, Part III, section 34.2(D). 
417 Co-Location Order, 195 FERC ¶ 61,209, at PP 232-33.  
418 Co-Location Order, 195 FERC ¶ 61,209, at P 240. 
419 Attachment A-1, Proposed Tariff, Part III, sections 34.2(E)(a)-(e). 
420 Attachment A-1, Proposed Tariff, Part III, section 34.2(F). 
421 Attachment A-1, Proposed Tariff, Part III, sections 34.2(D)-(E). 
422 Attachment A-1, Proposed RAA, Schedule 8.

PDF page 86

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 82 
 
82 
V. 
EFFECTIVE DATE 
PJM requests that the Commission accept the proposed revisions in Parts I, III, VI, 
VII, IX, XI, Attachment F-3, Attachment F-3A, Attachment F-4, and parts of Part VIII to 
the Tariff to become effective March 16, 2027, which is not less than 60 days, nor more 
than 120 days, prior to the submission of this filing.423  For those Part VIII revisions 
associated with the Fast Energization Process rather than compliance with the Co-Location 
Order (for which PJM requests a March 16, 2027 effective date), PJM requests an indefinite 
effective date of 12/31/9998, to allow PJM to make those provisions effective when the 
current Cycle, Cycle 01, reaches a sufficiently advanced stage so the next Cycle may begin.  
That point will be the next Business Day after the close of Decision Point II of Cycle 01, 
which PJM anticipates will occur in late November 2027.424  PJM will submit a compliance 
filing to provide the Commission with the effective date of Part VIII once that date is 
known. 
PJM does not believe any waivers of the Commission’s Regulations are needed to 
permit its filing to become effective as proposed.  In addition, to the extent the Commission 
determines that any other waivers are required, PJM respectfully requests the Commission 
grant such waivers as are necessary in order that the Tariff and RAA revisions may be 
made effective as proposed. 
VI. 
CONSENT TO SEVERANCE OF ISSUES 
PJM consents to the Commission’s exercise of authority to sever the Proposed 
Tariff and RAA language, as needed and permitted under the FPA and NRG Power 
 
423 18 C.F.R. § 35.3(a)(1).  
424 Planning, PJM Interconnection, L.L.C., Cycle Timeline (Oct. 23, 2026), https://www.pjm.com/planning 
[https://perma.cc/J283-5CFS].

PDF page 87

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 83 
 
83 
Marketing.425  Under FPA section 205, the Commission is in a “passive and reactive role” 
that requires it to accept or reject a utility’s proposed rate scheme.426  The Commission is 
prohibited from imposing modifications that “result in an ‘entirely different rate design’ 
than the utility’s original proposal or the utility's prior rate scheme.”427  However, the 
Commission has some authority to propose modifications to a utility’s proposal if the utility 
consents to the modifications.428  The Commission has used this authority to sever discrete 
portions of a utility’s proposed rate scheme, approving certain portions and rejecting 
others.429  By contrast, in NRG Power Marketing, the United States Court of Appeals for 
the District of Columbia determined that the Commission improperly modified PJM’s 
proposed rate scheme where the Commission’s modifications “went in the opposite 
direction” and “followed a ‘completely different strategy’ than PJM’s proposal.”430  In that 
circumstance, the Commission’s modifications violated section 205, even with PJM’s 
consent, because the Commission proposed an “entirely different rate design” that market 
participants did not have adequate notice of or opportunity to comment on.431  
If it deems necessary, PJM consents to the Commission exercising authority to 
sever each element of the Tariff and RAA revisions proposed herein.  PJM’s Proposed 
Tariff and RAA revisions are not an integrated package that must be viewed as a whole 
 
425 See NRG Power Mktg., LLC, 862 F.3d 108. 
426 Hecate Energy LLC v. FERC, 126 F.4th 660, 667 (D.C. Cir. 2025) (quoting Advanced Energy Mgmt. All. 
v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017)). 
427 NRG Power Mktg., 862 F.3d at 115 (quoting W. Res., Inc. v. FERC, 9 F.3d 1568, 1578 (D.C. Cir. 1993)).  
428 NRG Power Mktg., 862 F.3d at 115-16.  
429 See, e.g., PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at PP 13-15; Pub. Serv. Co. of Colo., 94 
FERC ¶ 61,135, at PP 28, 56 (2026). 
430 NRG Power Mktg., 862 F.3d at 116 (quoting W. Res., Inc., 9 F.3d at 1579). 
431 NRG Power Mktg., 862 F.3d at 116 (quoting W. Res., Inc., 9 F.3d at 1578).

PDF page 88

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 84 
 
84 
and accepted together;432 instead, each element of PJM’s proposal individually advances 
PJM’s overarching objective to comply with the June 2026 Orders and to safely and 
reliably integrate Large Loads and Co-Located Loads with the Transmission System.  
Therefore, the Commission will not go “in the opposite direction” or deploy “a completely 
different strategy” by severing certain elements of PJM’s proposal.433  Stakeholders will 
have the opportunity to comment in this proceeding on all individual elements of PJM’s 
proposal that could be severed, eliminating any prior notice concerns.  Further, through 
this pre-emptive grant of authority pursuant to which the Commission may sever each 
element of the proposal, stakeholders are on notice of potential changes to the proposal as 
filed and will have the opportunity to comment as they feel necessary and appropriate. 
Although PJM consents to make each element of the proposed revisions to the 
Tariff and RAA severable, PJM has demonstrated that each element of its proposal is just 
and reasonable.  Notwithstanding PJM’s grant of authority to sever, PJM urges the 
Commission to accept all revisions as proposed so that PJM may commence compliance 
with the directives of the June 2026 Orders and begin preparations for the Fast Energization 
Process as quickly as possible.  
VII. 
DOCUMENTS ENCLOSED 
 
In addition to this transmittal letter, PJM encloses the following: 
1. 
Attachment A-1: Marked March 16, 2027 Effective Date Proposed Tariff 
Revisions; 
 
432 See PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 15 (refusing to sever certain elements of PJM’s 
proposal, despite PJM providing consent to sever, because those elements “represent an integrated package 
that must be viewed as a whole”). 
433 NRG Power Mktg., 862 F.3d at 116.

PDF page 89

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 85 
 
85 
2. 
Attachment B-1: Marked Indefinite Effective Date Proposed Tariff 
Revisions; 
3. 
Attachment A-2:   Clean March 16, 2027 Effective Date Proposed Tariff 
Revisions;  
4. 
Attachment B-2: Clean Indefinite Effective Date Proposed Tariff 
Revisions; 
5. 
Attachment C: 
Declaration of Donald Bielak, P.E.; and 
6. 
Attachment D: 
Chart Mapping Order Directives to Tariff Changes.  
VIII. CORRESPONDENCE AND COMMUNICATIONS 
 
Correspondence and communications with respect to this filing should be sent to, 
and PJM requests the Secretary to include on the official service list, the following:434 
Mark J. Stanisz 
Associate General Counsel 
PJM Interconnection, L.L.C. 
2750 Monroe Blvd. 
Norristown, PA  19403-2429 
610-666-4707 
mark.stanisz@pjm.com    
 
Wendy B. Warren 
Ruth M. Porter 
Alexander L. Peterson 
Wright & Talisman, P.C. 
1200 G Street, NW, Suite 600 
Washington, DC  20005-3898 
202-393-1200  
warren@wrightlaw.com 
porter@wrightlaw.com 
peterson@wrightlaw.com 
Christopher B. Holt  
Managing Counsel 
PJM Interconnection, L.L.C.  
2750 Monroe Blvd, 
Audubon, PA  19403-2429 
610-666-2368 
christopher.holt@pjm.com  
 
 
IX. 
SERVICE 
 
PJM has served a copy of this filing on all PJM Members and on the affected state 
utility regulatory commissions in the PJM Region by posting this filing electronically.  In 
 
434 To the extent necessary, PJM requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice 
and Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official 
service list for this proceeding.

PDF page 90

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 86 
 
86 
accordance with the Commission’s regulations,435  PJM will post a copy of this filing to 
the Commission filings section on its internet site, https://pjm.com/library/filing-order, and 
will send an email on the same date as this filing to all PJM Members and all state utility 
regulatory commissions in the PJM Region,436 alerting them that this filing has been made 
by PJM and is available by following such link.  If the document is not immediately 
available by using the referenced link, the document will be available through the 
referenced link within 24 hours of the filing. 
 
435 See 18 C.F.R. §§ 35.2(e) & 385.2010(f)(3). 
436 PJM already maintains, updates, and regularly uses email lists for all PJM Members and affected state 
commissions.

PDF page 91

Honorable Debbie-Anne A. Reese, Secretary  
November 16, 2026 
Page 87 
 
87 
X. 
CONCLUSION 
 
PJM respectfully requests that the Commission:  (i) accept the proposed revisions 
to its Tariff and the RAA to effectuate PJM’s new Fast Energization Process to study 
generation and load together in a one-year process and offer new transmission services to 
Co-Located Load, BTMG, and flexible Large Load; and (ii) deem the Large Load Show 
Cause Order’s FPA section 206 aspect closed. 
Respectfully submitted, 
/s/ Wendy B. Warren 
 
Mark J. Stanisz 
Associate General Counsel 
PJM Interconnection, L.L.C. 
2750 Monroe Blvd. 
Norristown, PA  19403-2429 
610-666-4707 
mark.stanisz@pjm.com    
 
Christopher B. Holt  
Managing General Counsel 
PJM Interconnection, L.L.C. 
2750 Monroe Blvd. 
Audubon, PA  19403-2429 
610-666-2368 
christopher.holt@pjm.com 
 
       Wendy B. Warren 
Ruth M. Porter 
Alexander L. Peterson 
Wright & Talisman, P.C. 
1200 G Street, NW, Suite 600 
Washington, DC  20005-3898 
202-393-1200 
warren@wrightlaw.com 
porter@wrightlaw.com 
peterson@wrightlaw.com 
 
 
Counsel for PJM Interconnection, L.L.C. 
November 16, 2026