ER27-531-000 · 2026-11-16 · PJM Interconnection, L.L.C.
PJM files large-load tariff revisions and co-location compliance changes under section 205
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER27-____-000
PROPOSED TARIFF REVISIONS FOR LARGE LOADS AND ADDITIONAL
COMPLIANCE WITH CO-LOCATION ORDER AND REQUEST FOR
EXTENDED 60-DAY COMMENT PERIOD
Mark J. Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Norristown, PA 19403-2429
610-666-4707
mark.stanisz@pjm.com
Christopher B. Holt
Managing General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA 19403-2429
610-666-2368
christopher.holt@pjm.com
Wendy B. Warren
Ruth M. Porter
Alexander L. Peterson
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
202-393-1200
warren@wrightlaw.com
porter@wrightlaw.com
peterson@wrightlaw.com
Counsel for PJM Interconnection, L.L.C.
November 16, 2026PDF page 2
TABLE OF CONTENTS
I.
INTRODUCTION .................................................................................................. 7
II.
BACKGROUND .................................................................................................. 10
A.
2025 Show Cause Orders ...........................................................................10
1.
February Order ...............................................................................10
2.
December Order .............................................................................11
B.
Compliance Filings and Paper Hearing Procedure ....................................12
1.
Thirty-Day Compliance Filing .......................................................12
2.
Sixty-Day Compliance Filing ........................................................13
3.
Paper hearing procedures ...............................................................13
C.
June 2026 Orders .......................................................................................14
1.
Co-Location Order .........................................................................14
2.
Large Load Show Cause Order ......................................................15
D.
Partial Extension and Partial Compliance Filing .......................................16
E.
PJM’s Stakeholder Engagement Process ...................................................18
III.
OVERVIEW OF PROPOSED CHANGES .......................................................... 22
A.
Part III—NITS ...........................................................................................22
1.
NITS quantity for Large Load .......................................................22
2.
Information updates .......................................................................23
3.
50 MW limit on netting Behind the Meter Generation ..................24
B.
Part VIII—Fast Energization Process ........................................................27
1.
The Fast Energization Process is designed for speed and
accuracy .........................................................................................27
2.
The Fast Energization Process includes a Soft Close Date
and Early Application Engagement to improve the quality
of Applications and reduce disputes and litigation ........................30
3.
Timing of Fast Energization Process implementation and
the interim period ...........................................................................30
4.
PJM is eschewing parallel processes, to streamline for
speed and accuracy ........................................................................32
5.
PJM will maintain transparency of its study results ......................33
PDF page 3
ii
C.
Part XI—New Transmission Services .......................................................33
1.
Interim NITS ..................................................................................33
2.
Contract Demand Transmission Service ........................................37
3.
Common service provisions for Interim NITS and
Contract Demand Transmission Services ......................................42
4.
Pro Forma Service Agreement for Interim NITS
(Attachment F-3A) .........................................................................45
5.
Pro Forma Service Agreement for Contract Demand
Transmission Service (Attachment F-4) ........................................48
D.
Re-Filing Co-Located Load Compliance Changes ....................................50
1.
Prohibition on serving Co-Located Load from existing
generators .......................................................................................50
2.
Expansion of service to “Eligible Load” for load with
BTMG ............................................................................................52
3.
Elimination of new GIA requirement ............................................54
4.
Effective date only .........................................................................57
E.
Changes to Be Addressed in Future Filings ...............................................57
IV.
THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES
AS JUST AND REASONABLE .......................................................................... 59
A.
The Proposed Fast Energization Process Is Just and Reasonable
and Advances the Commission’s Categories for Reform in the
June 2026 Orders .......................................................................................59
B.
Core Features of the Fast Energization Process That Enhance the
Current Cycle Process ................................................................................60
1.
PJM’s current process provides only some visibility into
the transmission needs created by Large Loads .............................60
2.
Resource Adequacy requires getting new generation
online faster ....................................................................................60
3.
Incremental and parallel fixes are not enough – a singular
process for generation and transmission service requests
yields efficiencies...........................................................................61
4.
The Fast Energization Process is a single, unified process
that should be twice as fast as the current process .........................62
5.
Technology and early engagement speed the process ...................63
PDF page 4
iii
6.
Study consolidation preserves study rigor .....................................64
7.
Readiness requirements are moved to the front of the
process............................................................................................65
8.
A portfolio approach to system reinforcements provides
transparency and certainty .............................................................66
9.
Interim rights allow service to begin sooner ..................................67
C.
The Fast Energization Process Is Consistent with the Large Load
Show Cause Order’s Directives .................................................................68
1.
Timely, clear, and consistent study of transmission
service for large loads ....................................................................69
2.
Readiness requirements that deter speculative requests ................70
3.
Transparency regarding upgrades and their costs ..........................71
4.
Protection against cost shifting ......................................................71
5.
Transmission services that reflect flexible use of the
system ............................................................................................73
6.
Studying generation and transmission service requests to
serve Large Load together leverages technology and
innovation ......................................................................................73
7.
PJM’s proposal respects existing commercial
arrangements and provides for a clear transition from the
existing process to the Fast Energization Process..........................75
D.
The New Transmission Services Proposed in Part XI are Just and
Reasonable .................................................................................................77
E.
PJM’s Proposed Changes to NITS are Just and Reasonable .....................79
V.
EFFECTIVE DATE .............................................................................................. 82
VI.
CONSENT TO SEVERANCE OF ISSUES ......................................................... 82
VII.
DOCUMENTS ENCLOSED ................................................................................ 84
VIII.
CORRESPONDENCE AND COMMUNICATIONS .......................................... 85
IX.
SERVICE .............................................................................................................. 85
X.
CONCLUSION ..................................................................................................... 87
PDF page 5
1200 G Street, N.W., Suite 600
Washington, D.C. 20005-3898
Phone: 202.393.1200
Fax: 202.393.1240
wrightlaw.com
November 16, 2026
Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE, Room 1A
Washington, DC 20426
Re:
PJM Interconnection, L.L.C., Docket No. ER27-____-000
Proposed Tariff Revisions for Large Loads and Additional Compliance with
Co-Location Order and Request for Extended 60-Day Comment Period
Dear Secretary Reese:
Pursuant to section 205 of the Federal Power Act (“FPA”),1 part 35 of the Federal
Energy Regulatory Commission’s (“Commission”) regulations,2 and the August 14, 2026
letter order issued in Docket No. EL26-67-000,3 PJM Interconnection, L.L.C. (“PJM”)
hereby proposes revisions to Parts I, III, VI, VII, VIII, IX, X, and XI, and Attachments F-3,
F-3A, and F-4 of PJM’s Open Access Transmission Tariff (“Tariff”), and to Schedule 8 of
the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region
(“RAA”).4 With the reforms proposed here and the other filings being concurrently
1 16 U.S.C. § 824d.
2 18 C.F.R. part 35.
3 PJM Interconnection, L.L.C., 196 FERC ¶ 61,129, at P 10 (2026) (noting that to extent PJM submits “an
FPA section 205 filing addressing the Commission’s preliminary findings in the Show Cause Order on or
before November 16, 2026, then the obligation of the respondent(s) who have made such an FPA section 205
filing to file a response to the Show Cause Order will be suspended”).
4 The PJM Transmission Owners (“Transmission Owners”) are separately filing revisions to Tariff, Parts
VIII, IX, and XI to add provisions concerning the allocation of the costs of system reinforcements needed for
generator interconnection and transmission service for Eligible Loads and Large Loads, a cost-recovery
framework for those system reinforcements, and proposed rates for the three new transmission services PJM
proposes to offer. PJM concurrently is filing ride-through provisions for Large Computational Load to
mitigate against future incidents like the one that occurred July 22, 2026, in the PJM Region, along with other
proposed operational requirements and annual transmission service reporting requirements. That filing, and
all evidence submitted in support thereof, is incorporated by reference into this filing. Given the multiple
same-day filings and the fact that these filings are making changes, some of them overlapping, to over 100
PDF page 6
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 2
2
submitted today as described in Attachment D, PJM has responded fully to the Large Load
Show Cause Order and requests that the FPA section 206 aspect of the order be closed.
The Tariff revisions PJM proposes include:
• Revisions to the terms and conditions for Network Integration Transmission
Service (“NITS”)5 to impose new terms and conditions on Eligible Customers
taking transmission service on behalf of Eligible Load (including specifically
Co-Located Load and customers with Behind the Meter Generation (“BTMG”))
and Large Loads;6
• Revisions to Part VIII of the Tariff to create the new Fast Energization Process,
which will study together New Service Requests, including Generation
Interconnection Requests, and requests from Eligible Customers seeking
transmission service on behalf of Eligible Load and Large Load7 in a single,
12-month process;8
• Addition of the new Part XI to the Tariff, providing the terms and conditions
for new transmission services (Interim NITS, Firm Contract Demand (“FCD”)
Transmission
Service,
and
Non-Firm
Contract
Demand
(“NFCD”)
Tariff sections in nine parts of the Tariff, PJM expects it will need to make one or more clean-up filings in
the future to ensure the Tariff is clear, and commits to doing so. PJM will promptly submit a letter in Docket
Nos. EL25-49 and EL26-27 informing participants in those dockets of today’s tariff filings, some parts of
which are submitted in compliance with Commission directives and others of which are submitted pursuant
to Section 205 of the FPA. In an abundance of caution, PJM requests waiver of any regulation or filing
requirements relating to submissions in Docket Nos. EL25-49 and EL26-27 relating to today’s tariff
filings. Good cause exists to grant any necessary waivers because submission of these tariff filings in the
structure presented efficiently addresses the complexity of the overlapping filing obligations and differing
requested effective dates, PJM is requesting a sixty-day comment period and 120 day Commission action
date that affords interested participants reasonable time to engage in the tariff filing dockets.
5 Terms not otherwise defined herein shall have the meaning set forth in the Tariff, the RAA, or Amended
and Restated Operating Agreement of PJM Interconnection, L.L.C. (“Operating Agreement”).
6 See infra Section III.A.
7 The Commission accepted PJM’s definition of “Large Load” as “end-use customer(s) load that has a
cumulative peak load of 50 [megawatts (“MW”)] or greater at a single electrical site behind one or more
points of interconnection, where for configurations involving multiple affiliated load facilities or multiple
points of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-
mile radius will be considered a single electrical site as further described in the PJM Manuals” in its
October 9, 2026 order in Docket No. ER26-3515-000. PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at
PP 13, 24 (2026). That definition is now in the RAA, Article I, Definitions, and cross-referenced in Tariff,
Parts I and VIII. PJM Interconnection, L.L.C., Thirty-Day Compliance Filing to the Commission’s
October 9, 2026 Order on PJM’s Large Load Definition and Large Load Registry, Docket No.
ER26-3515-002 (Nov. 9, 2026).
8 See infra Section III.B.
PDF page 7
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 3
3
Transmission Service) available to Eligible Customers taking transmission
service on behalf of Eligible Load and Large Load;9 and
• Revised versions of Tariff provisions concerning Co-Located Load and BTMG
pending in Docket No. ER26-1479-002,10 which PJM has reevaluated and
revised in connection with its response to the Order Instituting Proceeding
Under Section 206 of the FPA (“Large Load Show Cause Order”).11
PJM’s proposed revisions address the Commission’s areas of concern in the Large
Load and Co-Located Load show cause proceedings: promotion of reliability; efficient
transmission service study processes; cost transparency and mitigation of cost-shifting;
flexible load service; accommodating Co-Located Loads and BTMG; and generation study
procedures for generators serving electrically proximate Large Loads and Co-Located
Loads. PJM proposes to add to its Tariff an enhanced process to identify and study
transmission service for new Large Loads. PJM will require Large Loads (i.e., loads over
50 MW at a single location) to be identified on a registry to set a baseline for the current
level of transmission service.12 PJM will then require any new requests for transmission
service or requests to increase existing service beyond the baseline level to apply for that
service and be studied.13 In evaluating such requests, PJM proposes to use a new, reformed
“Fast Energization Process,” to make the study process faster, even more focused on
9 See infra Section III.C.
10 See infra Section III.D. Revisions to these Tariff provisions were filed initially on August 17, 2026, PJM
Interconnection, L.L.C., Compliance Filing of PJM Interconnection, L.L.C. in Response to Order on
Rehearing, Clarification, Compliance Filing, and Paper Hearing in Docket Nos. EL25-49-002, et al, Docket
No. ER26-1479-002 (Aug. 17, 2026) (“August 17 Filing”), in compliance with the Commission’s
June 18, 2026 order in Docket Nos. EL25-49-000, et al. PJM Interconnection, L.L.C., 195 FERC ¶ 61,209
(“Co-Location Order”), notice of denial of reh’g by operation of law & providing for further consideration,
196 FERC ¶ 62,089 (2026). Earlier today, PJM filed a motion to withdraw the August 17 Filing in Docket
No. ER26-1479-002 so that it could file replacement revisions in this filing.
11 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, errata notice, 196 FERC ¶ 61,122, order dismissing
requests for reh’g & clarification, 196 FERC ¶ 61,214 (2026).
12 See Attachment A-1, Proposed Tariff, Part III, General.
13 See infra Section III.A.
PDF page 8
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 4
4
readiness and certainty, and provide enhanced transparency.14 The Fast Energization
Process proposes key reforms to the existing process to complete studies in 12 months.15
PJM’s Fast Energization Process will study requests for transmission service and
Generation Interconnection Requests together to optimize the Transmission System and
yield efficiencies for electrically proximate load and generation.16
PJM also proposes implementing the three new transmission services the
Commission put forward in a way that will ensure reliability, with technical and operational
limitations on withdrawals of energy by flexible Large Loads and Eligible Loads, and on
injections of energy by Eligible Generating Facilities.
In short, this filing responds in a unified fashion to two separate show cause orders,
one that has been ongoing for almost two years, with briefing and several compliance
filings required, and a second issued only five months ago, with overlapping concerns and
considerations. A chart detailing where each directive from the Co-Location Order and the
Large Load Show Cause Order (together, “June 2026 Orders”)17 is addressed is provided
as Attachment D to this filing.18 In light of the resulting scope and complexity of this filing,
PJM respectfully requests that the Commission establish a 60-day comment period for this
filing, to allow all interested parties sufficient time to review the proposed revisions and
for PJM to continue to engage with stakeholders after filing to potentially further improve
and augment the proposals set forth in this filing. PJM further requests a Commission
14 See infra Section III.B.
15 See infra Section III.B.
16 See infra Section III.B.
17 Co-Location Order, 195 FERC ¶ 61,209; Large Load Show Cause Order, 195 FERC ¶ 61,211.
18 See generally Attachment D, Chart Mapping Order Directives to Tariff Changes attached hereto.
PDF page 9
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 5
5
order on this filing within 120 days. The Commission’s full acceptance of this filing within
10 months of the date it is filed would likely be necessary to facilitate implementation in
time for Cycle 02.19
As PJM discussed in the PJM Abeyance Motion,20 the Commission’s June 2026
Orders presented certain interrelated and overlapping issues that PJM needed to address in
a holistic, coordinated manner.21 PJM noted in the PJM Abeyance Motion that the June
2026 Orders directed PJM to expand the availability of new transmission services, enhance
its Large Load study procedures, and detail the operational requirements and control
technologies that customers taking transmission service on behalf of certain loads must
use.22 PJM submitted a partial compliance filing on August 17, 2026, that addressed certain
directives of the Co-Location Order.23
Since the August 17 Filing, and as PJM worked on its response to the Large Load
Show Cause Order, PJM has determined that it must amend its earlier filing to comply with
the Co-Location Order to harmonize the treatment of Eligible Loads and Large Loads. PJM
therefore seeks an effective date of March 16, 2027, for certain Tariff revisions in Part VIII
relating to Eligible Loads and for the revisions in Part III and the new Part XI, to establish
available services as soon as practicable. PJM seeks an indefinite effective date for the
19 See infra Section III.B.3 (explaining that the Submission Window for the first Cycle under the Fast
Energization Process would open in late November 2027).
20 PJM Interconnection, L.L.C., Motion of PJM Interconnection, L.L.C. to Hold Proceeding in Abeyance and
Request for Shortened Answer Period and Expedited Treatment, Docket No. EL26-67-000, at 4-8 (July 28,
2026); PJM Interconnection, L.L.C, Motion for Extension of Time for Specified Compliance Requirements
and Request for Expedited Treatment of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al., at
4-8 (July 28, 2026) (“PJM Extension Motion”).
21 See supra note 10.
22 PJM Abeyance Motion at 4-5.
23 PJM Abeyance Motion at 1, 6-7; PJM Extension Motion at 1-2, 6-7.
PDF page 10
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 6
6
Fast Energization provisions of Part VIII, as the Fast Energization Process cannot begin
until Cycle 01 of PJM’s current interconnection process is sufficiently advanced.24
Each element of this proposal is just and reasonable. However, if the Commission
deems necessary, and to help facilitate the Commission’s acceptance of this filing without
delay so that PJM can comply expeditiously with the June 2026 Orders, PJM provides
notice that it consents to the Commission’s exercise of authority to sever any element of
the Proposed Tariff and RAA language to the extent necessary and permitted under sections
205 and 206 of the FPA and NRG Power Marketing, LLC v. FERC.25
PJM submits this filing pursuant to its independent authority to modify its Tariff
under FPA section 205 pursuant to Tariff, Part I, section 9.2(a) and the Consolidated
Transmission Owners Agreement (“CTOA”), section 7.5.1(ii), following the requisite
consultation specified under Tariff, Part I, section 9.2(b) and the CTOA, section 7.5.1(ii).
24 In order to avoid intervening proposed Tariff revisions from other filings potentially causing the Tariff
revisions herein to be overwritten, PJM has included revisions with proposed effective dates of
March 16, 2027, in certain of the Tariff sections with indefinite dates that are attached hereto as Attachment
A-2. Specifically, the changes proposed to the following Tariff sections with a proposed March 16, 2027
effective date have been added into the proposed revisions in the version of the marked Tariff with an
indefinite effective date: Tariff, Part VIII, section 400, Definitions C, E, N, P, and R; and Tariff, Part VIII,
sections 401, 403, 404, 406, 408, and 414. When PJM makes a compliance filing to establish the effective
date for the sections listed here that it is filing with indefinite effective dates, assuming they are accepted, it
will address the earlier language and update its status as well.
25 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017). As the Commission has often stated,
“[t]he United States Court of Appeals for the District of Columbia Circuit has held that, in certain
circumstances, the Commission has ‘authority to propose modifications to a utility’s [FPA section 205]
proposal if the utility consents to the modifications.’” N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051,
at P 22 n.36 (2024) (alteration in original) (citing NRG Power Mktg., 862 F.3d at 114-15); see Midcontinent
Indep. Sys. Operator, Inc., 180 FERC ¶ 61,141, at P 26 n.29 (2022) (same), order on reh’g, 182 FERC
¶ 61,096 (2023), aff’d sub nom., Entergy Ark., LLC v. FERC, 109 F.4th 583 (D.C. Cir. 2024); ISO New Eng.
Inc., 175 FERC ¶ 61,172, at P 16 n.20 (2021) (same).
PDF page 11
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 7
7
I.
INTRODUCTION
As it is elsewhere in the country, data center construction and operation is causing
unprecedented load growth in the PJM Region.26 PJM’s 2025 long-term load forecast
shows a peak load growth of 32 gigawatts (“GW”) from 2024 to 2030, with 30 GW of that
growth coming from data centers.27 PJM’s 2026 long-term load forecast projects a 3.6%
annual increase in its summer peak load over the next 10 years;28 in 2023, PJM projected
just a 0.8% annual increase over a 10-15 year horizon.29 The extraordinary growth of data
centers and other Large Loads presents unique reliability and resource adequacy challenges
as compared to traditional loads. Data centers have significant energy and capacity
demands and can be built faster (12-18 months) than the generation and transmission
facilities necessary to meet those demands.30 The North American Electric Reliability
Corporation (“NERC”) recognizes this as a resource adequacy issue, explaining that Large
Loads are “magnitudes larger than most loads historically seen on the system and
26 RTEP 2024: Regional Transmission Expansion Plan, PJM Interconnection, L.L.C., 47 (Apr. 17, 2025),
https://www.pjm.com/-/media/DotCom/library/reports-notices/2024-rtep/2024-rtep-report.pdf
[https://perma.cc/PV4N-VA3P] (explaining that there is significant load growth in the PJM Balancing
Authority Area due to new construction of data centers). As the Commission also has recognized, Large
Loads have unique operational characteristics, including significant load fluctuations. As noted earlier, PJM
is concurrently proposing ride through requirements and other operational requirements in a separate section
205 filing.
27 Letter from David E. Mills, PJM Board of Managers Chair, PJM Interconnection, L.L.C. to PJM
Stakeholders, 1 (Aug. 8, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-
disclosures/2025/20250808-pjm-board-letter-re-implementation-of-critical-issue-fast-path-process-for-
large-load-additions.pdf [https://perma.cc/977B-93NW].
28 PJM Resource Adequacy Planning Department, 2026 PJM Load Forecast Report, PJM Interconnection,
L.L.C., 6 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-
load-report.pdf [https://perma.cc/6BPF-LJYA].
29 PJM Resource Adequacy Planning Department, PJM Load Forecast Report: January 2023, PJM
Interconnection, L.L.C., 3 (Jan. 2023), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-
forecast/2023-load-report.ashx [https://perma.cc/XG66-PBQK].
30 Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, North America
Electric Reliability Corporation, 15-16 (July 2025), https://www.nerc.com/globalassets/who-we-
are/standing-committees/rstc/3_doc_white-paper-characteristics-and-risks-of-emerging-large-loads.pdf
[https://perma.cc/HVX5-8J9V] (“NERC Large Loads White Paper”).
PDF page 12
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 8
8
proliferating more quickly than most historical load growth” and therefore “the need for
additional generation may not have been planned for, and current system plans may not be
able to meet it.”31 Additionally, unlike traditional loads, Large Loads can materialize and
grow quickly in geographically concentrated areas,32 which makes them more difficult to
plan for than other loads.33 In the Large Load Show Cause Order, the Commission
recognized the material differences between Large Loads and other load categories,
explaining that “integrating large loads poses specific challenges to transmission system
operation given their size, operational behavior, and unique potential to impact the
transmission system.”34
To meet this moment, the Commission, on its own motion and in response to
section 205 filings, has issued a number of landmark orders stimulating innovation and
advancement. In parallel, the PJM Five-Year Strategy released September 1, 2026, sets
forth how PJM will lead during the next five years and beyond, with reliability as its North
Star.35 The third objective of the PJM Five-Year Strategy, titled “Proactively Adapt
Planning Processes,” includes multiple workstreams to achieve this objective. These
include: (1) a one-year generation interconnection process; (2) incorporating Large Load
31 NERC Large Loads White Paper at 16.
32 See Declaration of Donald Bielak, P.E. on Behalf of PJM Interconnection, L.L.C. (Attachment C) ¶ 15
(“Bielak Decl.”) (“Large Loads differ fundamentally from traditional loads in their size, pace of growth, and
concentration, and they are presently the major source of load growth in the PJM Region.”).
33 NERC Large Loads White Paper at 16 (“The arrival and timing of large loads is also frequently
uncertain. . . . Some proposed large loads do not materialize as planned: they may be canceled due to
economic and financial challenges or other setbacks. Due to the uncertainty of these large loads
materializing, forecasting load for resource adequacy and transmission planning may be much more
difficult.”).
34 See Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 58.
35 Corporate Strategy and Value, PJM Interconnection, L.L.C., https://www.pjm.com/about-pjm/corporate-
strategy-and-value [https://perma.cc/N92H-AQZ8] (last visited Nov. 14, 2026).
PDF page 13
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 9
9
forecasting and modeling into planning processes; (3) determining interim solutions for
near-term reliability needs; and (4) creating a synchronized planning and interconnection
process for greater efficiency and transparency.36 These objectives align closely with the
Commission’s Large Load Show Cause Order, offering PJM an opportunity to accelerate
its strategic timeline.
Through this filing, PJM responds to the Large Load Show Cause Order, consistent
with strategic objectives to proactively adapt PJM’s planning processes to deliver
accelerated interconnection and transmission service and processes. PJM proposes to
efficiently, reliably, and transparently provide transmission service to both co-located and
flexible Large Loads (i.e., Large Loads that are not co-located with generation, but are
willing and able to limit their energy withdrawals from the Transmission System under
certain conditions)37 and to quickly bring additional generation online to meet current and
forecasted demand from Large Loads. PJM further proposes Tariff revisions to provide
just and reasonable terms and conditions of service for the provision of transmission
service, including the new transmission services the Commission first advanced for Co-
Located Load in PJM and then proposed more broadly in show cause orders for all the
jurisdictional Regional Transmission Organizations, including the Large Load Show Cause
Order directed to PJM and Transmission Owners in the PJM Region.38
PJM also seeks to meet the need for “speed to power” and accelerate its generation
interconnection procedures to a one-year process by leveraging technology and process
36 Shaping a Power Change: PJM Five-Year Strategy, PJM Interconnection, L.L.C., 9 (Aug. 2026),
https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-
powerful-change-pjm-five-year-strategy.pdf [https://perma.cc/2RBY-MPLH].
37 See Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 85 n.178.
38 See generally Large Load Show Cause Order, 195 FERC ¶ 61,211.
PDF page 14
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 10
10
efficiencies. PJM will deliver at each turn of its new process non-binding good-faith
estimates of the cost and time to construct facilities within 60-90 calendar days, consistent
with the Commission’s findings in the Large Load Show Cause Order.39 To provide
transmission service to Eligible Loads and Large Loads as contemplated in the June 2026
Orders, PJM proposes to add transmission service requests to the existing New Service
Request study process in Tariff, Part VIII, which will allow PJM to optimize upgrades to
the Transmission System, eliminate duplicative upgrades, and offer timely transmission
service and generator deliverability based on current system topology rather than requiring
customers to wait on contingent upgrades to be built. With the reforms proposed here and
the supplemental filings PJM proposes to make, addressed in Section III.G below, PJM has
responded fully to the Large Load Show Cause Order and requests that the FPA section
206 aspect of the order be closed.
II.
BACKGROUND
A.
2025 Show Cause Orders
1.
February Order
Following a technical conference discussing the co-location of large loads at
generating facilities, the Commission initiated a show-cause proceeding against PJM and
the Transmission Owners on February 20, 2025 (“February Order”).40 In the February
Order, the Commission expressed concern that PJM’s Tariff did not address co-location
arrangements with sufficient clarity and consistency.41 The Commission made several
39 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 63; Bielak Decl. ¶ 21.
40 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, order on show cause, 193 FERC ¶ 61,217 (2025)
(“December Order”), order on compliance, 195 FERC ¶ 61,030, order on reh’g, clarification, compliance &
paper hearing, Co-Location Order,195 FERC ¶ 61,209.
41 February Order, 190 FERC ¶ 61,115, at P 2.
PDF page 15
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 11
11
preliminary findings that the Tariff appeared to be unjust and unreasonable regarding co-
location arrangements, and it directed PJM and the Transmission Owners to respond to
numerous questions addressing its concerns.42
2.
December Order
On December 18, 2025, the Commission issued an order on show cause finding the
Tariff unjust and unreasonable due to, among other reasons, the lack of specificity for the
rates, terms, and conditions that apply to Interconnection Customers43 serving Co-Located
Load and Eligible Customers taking transmission service on behalf of Co-Located Load.44
The December Order directed PJM to make a compliance filing within 30 days to, among
other things, clarify the rates, terms, and conditions that apply to an Interconnection
Customer seeking to serve Co-Located Load with new generation.45 The December Order
also directed PJM to make a compliance filing within 60 days to revise the Tariff in a
number of ways, including to modify the retail BTMG netting rules to limit netting over a
certain threshold46 and to require that an Eligible Customer taking transmission service on
behalf of a Co-Located Load select at least one of three transmission services: (1) NITS
or Interim NITS; (2) FCD Transmission Service; or (3) and NFCD Transmission Service.47
42 February Order, 190 FERC ¶ 61,115, at PP 74-75, 87-88.
43 Under PJM’s current interconnection rules in Tariff, Parts VII, VIII, and IX, Interconnection Customers
are referred to as “Project Developers.” PJM uses in this filing the term used in its current interconnection
rules, but it should be understood as consistent with the Commission’s references to Interconnection
Customers.
44 December Order, 193 FERC ¶ 61,217, at P 159.
45 December Order, 193 FERC ¶ 61,217, at PP 232-35.
46 December Order, 193 FERC ¶ 61,217, at P 221.
47 December Order, 193 FERC ¶ 61,217, at P 193.
PDF page 16
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 12
12
The December Order established a paper hearing procedure to obtain additional
evidence to determine the appropriate rates, terms, and conditions for these transmission
services.48 The Commission required parties to address, among other things, the
interconnection requirements and operational practices necessary to maintain system
reliability if a Co-Located Load or associated generator trips offline and the eligibility
requirements necessary for an Eligible Customer to take FCD or NFCD Transmission
Service on behalf of Co-Located Load.49
B.
Compliance Filings and Paper Hearing Procedure
1.
Thirty-Day Compliance Filing
On January 20, 2026, PJM made its 30-day compliance filing in Docket No.
ER26-1088-000 pursuant to the December Order (“Thirty-Day Compliance Filing”).50
Among other changes, the Thirty-Day Compliance Filing proposed to clarify that existing
services in the Tariff could be used by Project Developers serving Co-Located Load,
including Provisional Interconnection Service and Surplus Interconnection Service.51 The
Thirty-Day Compliance Filing also clarified that Project Developers serving Co-Located
Load can request interconnection service below nameplate capacity and accelerate the
interconnection process under certain circumstances.52 The Commission accepted in part
and rejected in part PJM’s compliance filing in an order on April 16, 2026;53 PJM
48 See December Order, 193 FERC ¶ 61,217, at PP 194, 203, 207, 219.
49 December Order, 193 FERC ¶ 61,217 at P 219(8), (10).
50 PJM Interconnection, L.L.C., Thirty-Day Compliance Filing with Order on Show Cause of PJM
Interconnection, L.L.C., Docket No. ER26-1088-000 (Jan. 20, 2026).
51 Thirty-Day Compliance Filing at 5-7.
52 Thirty-Day Compliance Filing at 4-5.
53 PJM Interconnection, L.L.C., 195 FERC ¶ 61,030.
PDF page 17
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 13
13
submitted an additional compliance filing on May 18, 2026, to comply with the
Commission’s order.54
2.
Sixty-Day Compliance Filing
On February 23, 2026, PJM made its 60-day compliance filing in Docket No.
ER26-1479-000 pursuant to the December Order (“Sixty-Day Compliance Filing”).55 The
Sixty-Day Compliance Filing proposed Tariff revisions to, among other things: (1) amend
PJM’s BTMG Tariff provisions;56 (2) establish certain aspects of three new transmission
services for Eligible Customers seeking to take service on behalf of Co-Located Load;57
and (3) amend PJM’s Necessary Studies processes.58
3.
Paper hearing procedures
PJM submitted an initial brief to address the Commission’s finding in the December
Order that additional record evidence was needed to set the appropriate replacement rates,
terms, and conditions for new transmission services for Eligible Customers serving Co-
Located Load, including for Interim NITS, FCD Transmission Service, and NFCD
Transmission Service.59 PJM’s initial brief set forth the non-rate terms and conditions for
these new transmission services along with illustrative Tariff language. Various parties
54 PJM Interconnection, L.L.C., Compliance Filing to the Commission’s April 16 Order on PJM’s Thirty-Day
Compliance Filing with the Order to Show Cause of PJM Interconnection, L.L.C., Docket No.
ER26-1088-001 (May 18, 2026).
55 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open
Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al. of PJM
Interconnection, L.L.C., Docket No. ER26-1479-000 (Feb. 23, 2026) (“Sixty-Day Compliance Filing”).
56 Sixty-Day Compliance Filing at 4-18.
57 Sixty-Day Compliance Filing at 18-24.
58 Sixty-Day Compliance Filing at 24-28.
59 PJM Interconnection, L.L.C., Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Feb.
23, 2026) (“PJM Initial Brief”).
PDF page 18
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 14
14
protested aspects of PJM’s illustrative Tariff language.60 PJM proposed certain
refinements to the illustrative language in its reply brief.61
C.
June 2026 Orders
1.
Co-Location Order
The Commission issued the Co-Location Order addressing the Sixty-Day
Compliance Filing, the paper hearing submissions, and requests for rehearing and
clarification of the December Order.62 The Co-Location Order accepted most of PJM’s
proposed Tariff changes, but directed PJM to make a number of additional changes within
60 days.63 Among other things, the Co-Location Order directed PJM to revise the Tariff
to adopt more detailed study procedures for customers requesting FCD and/or NFCD
Transmission Service that mirror existing cluster study procedures.64 The Co-Location
Order also directed PJM to make new transmission services available to customers with
BTMG that are willing and able to limit their withdrawals from the Transmission System.65
To accomplish this, the Commission directed PJM to either add a definition of “Eligible
Load” that encompasses customers serving Co-Located Load and customers serving load
60 See, e.g., PJM Interconnection, L.L.C., Reply Brief of Joint Co-Location Developers and Motion to
Intervene Out-of-Time of Calibrant, Convergent, U.S. Energy Storage Coalition, and Verrus, Docket Nos.
EL25-49-000, et al., at 2 (Mar. 25, 2026); PJM Interconnection, L.L.C., Reply Brief and Protest of Enchanted
Rock, Docket Nos. EL25-49-000, et al., at 7-9 (Mar. 25, 2026) (arguing that PJM’s proposal “renders Interim
NITS entirely unworkable”); PJM Interconnection, L.L.C., Reply Brief of Advanced Energy United and
Solar Energy Industries Association, Docket Nos. EL25-49-000, et al., at 6-10 (Mar. 25, 2026).
61 PJM Interconnection, L.L.C., Reply Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et
al., Attachment A (Redlines on Reply Brief to Illustrative Language for New Tariff, Part XI; Attachments F-
3A and F-4; and Other Illustrative Tariff Revisions), Illustrative Tariff, Part XI, Subpart A, section 701.1
(Apr. 24, 2026) (“PJM Reply Brief”).
62 See Co-Location Order, 195 FERC ¶ 61,209, at PP 1-2, 4-7.
63 See, e.g., Co-Location Order, 195 FERC ¶ 61,209, at P 280 (directing PJM to revise Tariff to specify what
information about Necessary Studies will be available in the PJM Manuals).
64 Co-Location Order, 195 FERC ¶ 61,209, at P 370.
65 Co-Location Order, 195 FERC ¶ 61,209, at P 91.
PDF page 19
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 15
15
with BTMG, or to propose comparable Tariff revisions.66 The Co-Location Order further
required PJM to revise the Tariff to provide additional detail regarding the operational
requirements and necessary control technologies to be employed for customers taking new
transmission services on behalf of Eligible Load.67
2.
Large Load Show Cause Order
The Large Load Show Cause Order found that several aspects of the Tariff appeared
unjust and unreasonable because it lacked specific procedures for integrating large loads,
including Large Load-specific procedures for interconnection studies, processing
transmission service requests, and providing transmission service without cost shifting.68
The Large Load Show Cause Order also found that the Tariff appeared to be unjust and
unreasonable because it lacked transmission service options for customers serving large
loads that are willing and able to limit their withdrawals from the Transmission System.69
The Commission was specifically concerned whether the Tariff was just and reasonable
without allowing customers to take Interim NITS, FCD Transmission Service, and/or
NFCD Transmission Service on behalf of Eligible Load.70 The Commission also
emphasized that, in the Co-Location Order, it approved a requirement that customers taking
transmission service on behalf of Eligible Load must have necessary control technologies
or protection systems to limit energy withdrawals to approved levels.71 The Large Load
66 Co-Location Order, 195 FERC ¶ 61,209, at P 91.
67 Co-Location Order, 195 FERC ¶ 61,209, at PP 482, 541.
68 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 59-60, 65, 77.
69 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 86.
70 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 87.
71 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 87 & n.189 (citing Co-Location Order, 195 FERC
¶ 61,209, at P 480).
PDF page 20
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 16
16
Show Cause Order further found that PJM’s Tariff appeared to be unjust and unreasonable
due to a lack of mechanisms to ensure that costs are not shifted between transmission
customers.72
To address these issues, the Large Load Show Cause Order directed PJM to make
two compliance filings.73 First, the Large Load Show Cause Order directed PJM to submit
an informational filing within 30 days to explain how PJM intends to ensure that it has
adequate generation to serve existing and new large loads.74 Second, the Large Load Show
Cause Order directed PJM to submit within 60 days a compliance filing explaining whether
its Tariff remains just and reasonable in light of the issues identified in the order, or to
propose Tariff changes that would remedy the identified concerns.75 The Commission
noted that it would entertain requests to hold the show cause proceedings in abeyance if
PJM demonstrated a plan to file changes pursuant to FPA section 205 to address the
identified concerns.76
D.
Partial Extension and Partial Compliance Filing
On July 28, 2026, PJM moved for a 90-day extension of time to meet certain Co-
Location Order requirements,77 and it simultaneously requested the Commission to hold
the Large Load Show Cause Order proceedings in abeyance for 90 days.78 PJM explained
that the June 2026 Orders contained certain interrelated and overlapping issues that must
72 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 77.
73 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 3-4.
74 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 4.
75 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 3.
76 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 39.
77 See generally PJM Extension Motion.
78 See generally PJM Abeyance Motion.
PDF page 21
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 17
17
be addressed on a holistic basis, which required additional time and stakeholder
engagement.79 For example, PJM noted that the June 2026 Orders both directed PJM to
expand the availability of new transmission services, enhance its Large Load study
procedures, and detail the operational requirements and control technologies that
customers taking transmission service on behalf of certain loads must use.80 PJM
committed to submitting a partial compliance filing by August 17, 2026, that addressed
certain directives of the Co-Location Order.81 The Commission granted PJM’s requests on
August 14, 2026.82
Pursuant to its commitment, PJM made a partial compliance filing on August 17,
2026, in Docket No. ER26-1479-002 to address many of the Co-Location Order’s
directives, including by proposing to add the term Eligible Load to the Tariff to encompass
both Co-Located Load and load with BTMG; adopting various modifications to the terms
and conditions for Interim NITS; modifying the definition of Retail BTMG to eliminate
the 50 MW nameplate limit for netting; and removing the requirement for existing
customers to execute a new Generation Interconnection Agreement (“GIA”) to serve Co-
Located Load.83
79 PJM Abeyance Motion at 4-8; PJM Extension Motion at 4-8.
80 PJM Abeyance Motion at 4-5.
81 PJM Abeyance Motion at 1, 6-7; PJM Extension Motion at 1-2, 6-7.
82 PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et al. (Aug. 14,
2026).
83 See generally August 17 Filing.
PDF page 22
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 18
18
E.
PJM’s Stakeholder Engagement Process
PJM held engagement sessions to inform stakeholders about the June 2026 Orders
and solicit feedback on the proposed Tariff revisions PJM would file in response to those
orders. PJM’s stakeholder engagement process is detailed below:
• July 30, 2026, Co-Located Load Order Workshop (“CLLOW”): PJM
presented on the June 2026 Orders and explained PJM’s proposed compliance
approach.84
• August 18, 2026, CLLOW: PJM provided an update on its June 2026 Orders
compliance strategy. PJM presented its proposed Large Load Show Cause
Order compliance framework85 and discussed the overlap between Large Load,
Co-Located Load, and load with BTMG.86 PJM solicited and received
stakeholder feedback on its presentation.87
• September 16, 2026, CLLOW: PJM presented its proposed process for
integrating Large Loads with the Transmission System, pursuant to the Large
84 See Co-Located Load Order Workshop, PJM Interconnection, L.L.C., https://www.pjm.com/committees-
and-groups/workshops/cllsco [https://perma.cc/B3FW-BRLM] (last visited Nov. 12, 2026) (follow “Meeting
Materials” subheading; then choose “2026” from dropdown; then choose “7.30.2026 – Co-Located Load
Order Workshop”; then select and click “Download”).
85 Donnie Bielak, Show Cause for Large Loads Framework, PJM Interconnection, L.L.C. (Aug. 18, 2026),
20260818-item-03---show-cause-for-large-loads-framework---presentation.pdf
[https://perma.cc/V2Q3-
A9NT].
86 See Tim Horger, Overlap of Large Load, Co-Located Load and Load with BTMG, PJM Interconnection,
L.L.C.
(Aug.
18,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20260818/20260818-item-02---overlap-of-large-load-co-located-load-and-
load-with-btmg---presentation.pdf [https://perma.cc/XQ8A-M3PU].
87 See August 18 Co-Located Load Order Workshop Stakeholder Feedback Poll Responses, PJM
Interconnection,
L.L.C.
(Aug.
18,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20260818/20260818-august-18-co-located-load-order-workshop-
stakeholder-feedback-poll-responses-received-by-8-28-26-final.pdf [https://perma.cc/V7NB-9RR5].
PDF page 23
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 19
19
Load Show Cause Order.88 PJM solicited and received stakeholder feedback
on its presentation.89
• September 30, 2026, CLLOW: PJM presented its proposed Large Load study
process and received stakeholder feedback.90
• October 5, 2026, CLLOW: PJM presented and solicited feedback on certain
draft Tariff redlines to comply with the June 2026 Orders PJM gave a
presentation on proposed Eligible Load Curtailment priority by transmission
service type.91
• October 16, 2026, CLLOW: PJM presented and solicited feedback on certain
draft Tariff redlines to comply with the June 2026 Orders.92
• October 26, 2026, CLLOW: PJM presented on proposed Tariff redlines
associated with its new transmission services.93 PJM also discussed its
88 See Donnie Bielak, Show Cause for Large Loads Framework, PJM Interconnection, L.L.C. (Sep. 16, 2026),
https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260916/20260916-
item-03---show-cause-for-large-loads-approach---presentation.pdf [https://perma.cc/YLW3-DGTK].
89 See September 16 Co-Located Load Order Workshop Stakeholder Feedback Poll Responses, PJM
Interconnection,
L.L.C.
(Sep.
16,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20260916/20260916-september-16-co-located-load-order-workshop-
stakeholder-feedback-poll-responses-received-by-9-22-26.pdf [https://perma.cc/CM3H-E66H].
90 Donnie Bielak, Show Cause for Large Loads Framework, PJM Interconnection, L.L.C. (Sep. 30, 2026),
https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260930/20260930-
item-02---show-cause-for-large-loads-approach---presentation.pdf [https://perma.cc/FB8W-CDDV].
91 Chris Pilong, Operationalizing Flexible Large Loads: Curtailment Overview, PJM Interconnection, L.L.C.
(Oct.
5,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261005/20261005-item-02---operationalizing-flexible-large-loads-
curtailment-overview---presentation.pdf [https://perma.cc/FTM9-LLB6].
92 See Item 02 – Draft Tariff Revisions – Redline, PJM Interconnection, L.L.C. (Oct. 15, 2026),
https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20261016/20261016-
item-02---draft-tariff-revisions---redline.pdf [https://perma.cc/K3V7-7G28] (presenting redline Tariff
revisions at the October 16, 2026 CLLOW).
93 See, e.g., Item 02 – Tariff Part XI New Transmission Services – Redlines, PJM Interconnection, L.L.C.
(Oct.
26,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261026/20261026-item-02---tariff-part-xi-new-transmission-services---
PDF page 24
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 20
20
proposed Fast Energization Process, which would require PJM to annually
study all (i) generation and Merchant Transmission Interconnection requests;
and (ii) Large Load and Long Term Firm Transmission Service requests in a
single cluster over a 12-month period.94 In Section III below, PJM describes its
Fast Energization Process proposal and associated Tariff revisions in detail.
Additionally, the Transmission Owners discussed proposed transmission rates,
cost allocation, and a cost-recovery framework, to be separately filed.95
• October 28, 2026, Markets and Reliability Committee: PJM discussed its
proposed response to the Large Load Show Cause Order, including its Fast
Energization Process proposal.96
• November 5, 2026, Special Members Committee: PJM provided notice in
accordance with Tariff, Part I, section 9.2(b) regarding its proposed Tariff
redlines.pdf [https://perma.cc/WF4R-RKYC] (presenting redline Tariff revisions at the October 26, 2026
CLLOW).
94 Donnie Bielak, Fast Energization, PJM Interconnection, L.L.C. (Oct. 26, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/workshops/cllsco/2026/20261026/20261026-item-03---1-fast-
energization---presentation.pdf [https://perma.cc/VSE5-5235].
95 See Notice of PJM Transmission Owners Consultation with the Members Committee Regarding Proposed
Revisions to the PJM Tariff, PJM Interconnection, L.L.C. (Oct. 9, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/workshops/cllsco/2026/20261026/20261026-item-04---pjm-to-large-
load-mc-consultation-notice.pdf [https://perma.cc/MT5Z-GKR7].
96 Donnie Bielak et al., Large Load Show Cause Response, PJM Interconnection, L.L.C. (Oct. 28, 2026),
https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20261028/20261028-
item-06---large-load-show-cause-response---presentation.pdf [https://perma.cc/58FJ-VLAZ].
PDF page 25
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 21
21
revisions to comply with the June 2026 Orders,97 including its Fast Energization
proposal.98
• November 6, 2026, TOA-AC:
PJM provided notice to the Transmission
Owners in accordance with Tariff, Part I, section 9.2(b) regarding its proposed
Tariff revisions to comply with the June 2026 Orders, including its Fast
Energization proposal.99
• November 12, 2026, CLLOW: PJM discussed its proposed revisions to the
Tariff and RAA to implement its Fast Energization proposal. PJM provided
draft Tariff and RAA redlines to stakeholders for discussion.100
PJM intends to schedule additional stakeholder sessions after the submission of this
filing to continue the process of education and discussion on the proposal submitted here.
In particular, PJM is planning sessions on at least November 23, 2026, and December 15,
2026, to answer stakeholder questions and receive feedback.
97
See
Meeting
Details,
PJM
Interconnection,
L.L.C.
(Nov.
5,
2026),
https://www.pjm.com/forms/registration/Meeting%20Registration.aspx?ID=%7b1045ffcd-c613-47d7-
90be-24f2afa0c1c4%7d [https://perma.cc/N8TQ-ELZR] (November 5, 2026 Special Members Committee
Meeting Materials).
98 Donnie Bielak, Fast Energization, PJM Interconnection, L.L.C. (Nov. 5, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/committees/mc/2026/20261105-special/item-01---1-fast-energization--
-presentation.pdf [https://perma.cc/Z87G-9U6R].
99 See TOA-AC Meeting Agenda, PJM Interconnection, L.L.C. (Nov. 6, 2026), https://www.pjm.com/-
/media/DotCom/committees-groups/committees/toa-ac/2026/20261106-special/agenda.pdf
[https://perma.cc/FK73-PBGQ].
100 See, e.g., Item 02 – Tariff Part XI New Transmission Services – Redlines, PJM Interconnection, L.L.C.
(Nov.
11,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261112/20261112-item-02---tariff-revisions-part-xi-new-transmission-
services-november-11-draft---redline.pdf [https://perma.cc/7VBQ-P2RQ]; Item 02 – RAA Schedule 8 –
Redlines, PJM Interconnection, L.L.C. (Nov. 11, 2026), https://www.pjm.com/-/media/DotCom/committees-
groups/workshops/cllsco/2026/20261112/20261112-item-02---raa-revisions-schedule-8-november-11-
draft--redline.pdf [https://perma.cc/579S-MCKS].
PDF page 26
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 22
22
III.
OVERVIEW OF PROPOSED CHANGES
A.
Part III—NITS
PJM is proposing certain changes to the terms and conditions of NITS in Part III to
ensure that PJM is appropriately studying, planning, and upgrading the Transmission
System for Large Load growth. Currently, there is no limit on a Network Customer’s load
growth when taking NITS, including for Large Load.101 Under the current process, PJM
plans the Transmission System based on the yearly load forecast, including adjustments to
account for Large Loads.102 To promote efficiency and transparency for Large Load
additions, PJM is proposing the new Fast Energization study process in Part VIII as
discussed below.103 However, certain changes to Part III are needed to ensure that Large
Load is captured in that study process.
1.
NITS quantity for Large Load
PJM is proposing to add language to capture the existing level of NITS being
provided to Network Customers serving Large Loads. In this regard, Part III would now
specify that “[t]he amount of Regional Network Integration Transmission Service
provisioned to Network Customers for serving Large Loads are at levels specified in an
effective Service Agreement or, if not specified therein, as reflected on the Large Load
Registry per the terms of the Reliability Assurance Agreement, Schedule 11.B.1.”104 The
RAA now requires all Large Load in the PJM Region to be registered as of March 1,
101 See, e.g., Tariff, Part III, section 31.6.
102 See generally RAA, Schedule 8 (setting Unforced Capacity Obligations based on Obligation Peak Load
with Load Adjustments); Operating Agreement, Schedule 6 (specifying procedures for PJM’s Regional
Transmission Expansion Plan (“RTEP”) Protocol).
103 See infra Section III.B.
104 Attachment A-1, Proposed Tariff, Part III, General.
PDF page 27
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 23
23
2027.105 This addition to Part III is necessary to set a baseline of the Large Load currently
being served via NITS to allow PJM to study future Large Load additions.
2.
Information updates
The Tariff currently provides for Network Customers to provide PJM with annual
updates on its Network Load and Network Resources forecasts, consistent with the
information provided in its Application for NITS, including any information provided
under Tariff, Part III, section 29.2(ix) pursuant to the Transmission Provider’s planning
process in Operating Agreement, Schedule 6, but does not require the Network Customer
to file an Application for those changes.106 Because NITS is available to Eligible
Customers taking service on behalf of Eligible Load, PJM is proposing to add language to
clarify that the annual information updates Network Customers provide must include
changes to Eligible Load and, as applicable, the Eligible Generating Facility serving that
load.107 Further, PJM’s Tariff remains unchanged in that the Network Customer must
provide PJM with timely notice of material changes relating to the Network Customer’s
Network Load (including any Network Load that is Large Load), and the Network
Customer’s Transmission System or other aspects of its facilities or operations affecting
PJM’s ability to provide reliable service.108 This obligation, in tandem with the obligation
105 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48; PJM Interconnection, L.L.C., Thirty-Day
Compliance Filing to the Commission’s October 9, 2026 Order on PJM’s Large Load Definition and Large
Load Registry, Docket No. ER26-3515-002 (Nov. 9, 2026).
106 See Tariff, Part III, section 31.6.
107 Attachment A-1, Proposed Tariff, Part III, section 31.6.
108 Id.
PDF page 28
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 24
24
to also update the Large Load Registry means that PJM and others will have a clearer
picture of the Large Load on its system.109
Going forward, Large Load growth for NITS customers will require an Application
to be studied through the Fast Energization Process.110 Accordingly, PJM is proposing to
strike the language in section 31.6 that suggests an Application would not be required for
such changes (i.e., “[e]ven if an Application is no longer required”).111
3.
50 MW limit on netting Behind the Meter Generation
The Commission directed PJM to allow Eligible Customers with Retail BTMG to
net up to 50 MW of Retail BTMG from their load, subjection to certain exclusions for a
three-year transition provision, to grandfather existing commercial arrangements, and for
Cogeneration Facilities with load that follows the facility.112 Consistent with this directive,
PJM is proposing a revised definition of Retail BTMG that eliminates the rejected 50 MW
nameplate limit and other netting exemptions from the definition.113 In addition, PJM is
proposing revisions to Part III, section 34.2 and Schedule 8 of the RAA to implement the
50 MW netting limit.114
Currently, there is no limit to Retail BTMG’s daily load reduction for purposes of
calculating capacity requirements under the RAA or transmission service charges under
109 RAA, Schedule 11.B.1 (accepted in PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48)..
110 See infra Section III.B.
111 Attachment A-1, Proposed Tariff, Part III, section 31.6.
112 Co-Location Order, 195 FERC ¶ 61,209, at PP 207, 220.
113 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – R - S) (adding the definition of “Retail
Behind The Meter Generation”); Proposed Tariff, Part VIII, Subpart A, section 400, Definitions R.
114 Attachment A-1, Proposed Tariff, Part III, section 34.2; Proposed Tariff, RAA, Schedule 8.
PDF page 29
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 25
25
the Tariff.115 Any load that is served by operating BTMG is simply not included in the
daily load of the Network Customer.116 Pursuant to the Commission’s directive,117 PJM is
proposing revisions to section 34.2 that would limit the daily load reduction from Retail
BTMG to 50 MW effective March 16, 2027 based on the status of the BTMG as of
December 18, 2025, unless an exemption applies.118 As directed, PJM has included three
exemptions from the netting limit. First, the 50 MW limit would not apply for a three-year
transition period for existing Retail BTMG that was used to serve load as of December 18,
2025.119 Second, the 50 MW netting limit would not apply to Retail BTMG that was
owned, operated and/or contracted for as of December 18, 2025, for the current term
remaining under any contract to effectuate the Retail BTMG arrangement (including any
renewal, amendment, or extension per the contract’s terms).120 To qualify for this
exemption, the retail load served by the Retail BTMG must be on the Large Load Registry,
the Retail BTMG must be registered with the Transmission Provider in accordance with
the PJM Manuals, and the Network Customer must comply with any requests for
information to verify eligibility.121
PJM is proposing that the load be added to the Large Load Registry and that Retail
BTMG be registered to track utilization of the netting exemptions for settlement and
115 Tariff, Part III, section 34.2 (“The daily load of a Network Customer does not include load served by
operating Behind The Meter Generation.”).
116 Tariff, Part III, section 34.2.
117 Co-Location Order, 195 FERC ¶ 61,209, at PP 207, 220.
118 Attachment A-1, Proposed Tariff, Part III, section 34.2(B).
119 Attachment A-1, Proposed Tariff, Part III, section 34.2(C).
120 Attachment A-1, Proposed Tariff, Part III, section 34.2(D).
121 Attachment A-1, Proposed Tariff, Part III, section 34.2(D).
PDF page 30
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 26
26
resource planning purposes. The 50 MW netting limit will not apply to a Cogeneration
Facility (consistent with the requirements of the Public Utility Regulatory Policies Act of
1978) that is integrated with the retail load it serves such that if the Cogeneration Facility
trips offline, the retail load follows.122 To qualify, the retail load must be on the Large
Load Registry, the Retail BTMG must be registered, the Network Customer must certify
eligibility, the Network Customer must comply with requests for information to verify
eligibility, and the Network Customer must update PJM in the event it no longer qualifies
for the exemption.123 PJM also reserves the right to periodically audit compliance with
these requirements.124
To effectuate the netting limit for the purpose of capacity cost allocation, PJM is
proposing changes to RAA, Schedule 8 to incorporate the netting limits into the calculation
of Obligation Peak Load for purposes of determining the Unforced Capacity
Obligations.125 Currently, the Daily Unforced Capacity Obligation of a Party to the RAA
is calculated by taking the Party’s Obligation Peak Load and applying scaling factors.126
The Obligation Peak Load is calculated by taking the daily summation of the Party’s
weather adjusted coincident summer peak for the last Delivery Year for the end-users in
the Zone, net of BTMG.127 Because PJM is proposing to limit BTMG netting to 50 MW
except in specific circumstances, PJM is proposing to add language in RAA, Schedule 8 to
122 Attachment A-1, Proposed Tariff, Part III, section 34.2(E).
123 Attachment A-1, Proposed Tariff, Part III, sections 34.2(E)(a)-(e).
124 Attachment A-1, Proposed Tariff, Part III, section 34.2(F).
125 Attachment A-1, Proposed Tariff, RAA, Schedule 8.
126 RAA, Schedule 8(A).
127 RAA, Schedule 8(A).
PDF page 31
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 27
27
incorporate those netting limits into the Obligation Peak Load calculation for settlement
and planning purposes.128
B.
Part VIII—Fast Energization Process
Consistent with the Commission’s directives to establish a study process for Large
Load and to avoid duplicating system reinforcements for generator interconnection and
transmission service for Large Loads,129 and with PJM’s strategic objectives,130 PJM
proposes to evaluate requests for Transmission Service on behalf of Eligible Loads and
Large Loads as part of its Tariff, Part VIII procedures for studying the interconnection of
Generating Facilities and Merchant Transmission and the provision of Long Term Firm
Transmission Service. PJM further proposes new reforms to Tariff, Part VIII to speed up
the studies, increase readiness requirements, and increase certainty as to responsibility for
upgrades. PJM calls the resulting process the “Fast Energization Process,” as it is designed
both to get Generating Facilities online quickly and provide transmission service to Eligible
Loads and Large Loads efficiently through a single, one-year process.
1.
The Fast Energization Process is designed for speed and accuracy.
The Fast Energization Process would supplant the current interconnection process’s
three System Impact Study phases with an accelerated Screening Phase and a single System
Impact Study.131 This shift from three System Impact Studies to one will greatly expedite
the interconnection process. The one System Impact Study in the Fast Energization
128 Attachment A-1, Proposed RAA, Schedule 8(A).
129 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 60.
130 See supra Section I discussion of PJM’s Five-Year Strategy and its objectives.
131 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401 (Applications for Cycle Process
Introduction); Proposed Tariff, Part VIII, Subpart C, section 404(B)(1) (Introduction); Proposed Tariff, Part
VIII, Subpart C, section 405(B) (Phase I or Screening Phase); Proposed Tariff, Part VIII, Subpart C, section
409 (Phase III or System Impact Study Phase).
PDF page 32
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 28
28
Process is preceded by a Screening Phase, during which PJM and Transmission Owners
will provide two “turns” of system impact analysis with preliminary desk-side estimates
for system upgrade costs and construction durations.132 After each of these turns of
analysis, there will be a Decision Point—a period during which Project Developers and
Eligible Customers can choose whether or not to proceed and, if they are proceeding,
commit Readiness Deposits.133 This accelerated Screening Phase will extend for
approximately four months, thereby providing two quick rounds of analysis that each take
less than 60 days and get actionable information to Project Developers and Eligible
Customers quickly.134
132 Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404(B)(1) (Introduction); Proposed Tariff,
Part VIII, Subpart C, section 405(B) (Phase I or Screening Phase); Proposed Tariff, Part VIII, Subpart C,
section 409 (Phase III or System Impact Study Phase).
133 Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404(B)(1) (Introduction); Proposed Tariff,
Part VIII, Subpart C, section 406(C) (Decision Point I); Proposed Tariff, Part VIII, Subpart C, section 408(C)
(Decision Point II).
134 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 63 (directing PJM to explain whether the Tariff
remains just and reasonable without processes for a study deadline of no more than 60 to 90 calendar days).
PDF page 33
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 29
29
The Fast Energization Process will create additional time savings by having the
Final Agreement Phase begin at the same time the System Impact Study Phase begins.135
The process will also be expedited by imposing higher readiness requirements in the
Application and having Readiness Deposits posted with the Applications and at risk at
Decision Points I and II, earlier in the interconnection process than they currently are.136
Higher and earlier readiness requirements and Readiness Deposits will better screen out
speculative projects and ensure that projects that advance through the Fast Energization
Process and enter into an interconnection-related service agreement are truly ready to start
construction of their facility, complete construction, and get their facility in service.137
Finally, PJM has been and plans to continue to make investments in automation
and technology to facilitate expediting the interconnection process. As described in the
Bielak Declaration, PJM has been evaluating Tapestry, an AI-powered interconnection
platform, and is close to the point at which it can trust results produced by the platform
without parallel human verification.138 This evaluation and PJM’s own significant
automation efforts have given PJM the confidence to work on developing a suite of
automation that will enhance existing technology applications and also deploy technologies
into new areas.139 PJM is focusing particularly on improving its modeling platform, to turn
135 See Attachment A-2, Proposed Tariff, Part VIII, Subpart D, section 411(C)(1) (“The Final Agreement
Negotiation Phase shall run concurrently with the System Impact Study Phase.”).
136 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, sections 401(D)(1)-(3) (Required Study
Deposits and Readiness Deposits); Proposed Tariff, Part VIII, Subpart C, section 406(C) (Decision Point I);
Proposed Tariff, Part VIII, Subpart C, section 408(C) (Decision Point II).
137 Bielak Decl. ¶ 7.
138 Bielak Decl. ¶ 19.
139 Bielak Decl. ¶ 19.
PDF page 34
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 30
30
around grid studies more quickly, and on developing quality assurance tools to continue to
drive high quality study results in a shorter period of time.140
2.
The Fast Energization Process includes a Soft Close Date and Early
Application Engagement to improve the quality of Applications and
reduce disputes and litigation.
The Fast Energization Process includes a 14-week period between the Soft Close
Date and the Application Deadline, called the Early Application Engagement, during which
PJM will work with Applicants to improve their Applications.141 This collaborative
process will include PJM testing and giving feedback on Applicants’ models, and giving
guidance as to readiness.142 This will result in cleaner Applications that can be validated
quickly, thereby reducing disputes and litigation, with time-saving benefits for all
concerned, including the Commission.143
3.
Timing of Fast Energization Process implementation and the
interim period
PJM proposes to implement the Fast Energization Process once the current Cycle
reaches the end of Decision Point II, consistent with the current Tariff timeline for opening
a new Cycle.144 PJM thus proposes to open the Submission Window for the Fast
Energization Process the next Business Day after Decision Point II of Cycle 01 ends.145
140 Bielak Decl. ¶ 19.
141 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 Definitions E (defining Early
Application Engagement); Proposed Tariff, Part VIII, Subpart B, section 403(E)(2) (Early Application
Engagement, Kickoff Calls, and Scoping Meetings).
142 Attachment A-2, Proposed Tariff, Part VIII, Subpart B, section 403(E)(2) (Early Application Engagement,
Kickoff Calls, and Scoping Meetings).
143 See Bielak Decl. ¶ 20.
144 See Tariff, Part VIII, Subpart B, section 403(A) (under the current Cycle process, PJM opens the
Application window for the next Cycle when the current Cycle reaches Phase III).
145 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A) (“Part VIII of the Tariff applies .
. . to valid Eligible Customer for Load Requests, submitted on or after the next Business Day after the close
of Decision Point II of Cycle 01.”).
PDF page 35
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 31
31
This is expected to be late November 2027.146 At that time, all the pending Applications
submitted for Cycle 02 under the existing process will be re-submitted for new Cycle 02
under the Fast Energization Process.147 Opening the Submission Window in late
November 2027 would result in a Soft Close Date in early May 2028,148 followed by Early
Application Engagement,149 and an Application Deadline for the new Cycle 02 in
August 2028.150 The first Fast Energization Cycle would therefore finish in 2029.
During the interim period until the Fast Energization Process is in effect, PJM will
use the Necessary Studies process, as directed in the Co-Location proceedings.151 Once
the Fast Energization Process is in effect, all Eligible Customer requests for transmission
service to serve load, including Co-Located Load, will proceed through the Fast
Energization Process.152
146 See Stacey Nestel, Cycle 01 Application, PJM Interconnection, L.L.C., 2 (Jan. 2026),
https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/ips/2026/20260126/20260126-
item-05---cycle-1-application-requirements-and-nextgen-process.pdf [https://perma.cc/6RJL-DWPF].
147 Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404(A)(8). Requests to transfer Capacity
Interconnection Rights in existing Cycle 02 Applications will be carried over to the new Cycle 02. Id.
148 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 (Definitions S) (Soft Close Date).
149 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 (Definitions E) (Early Application
Engagement).
150 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 400 (Definitions A) (Application
Deadline).
151 December Order, 193 FERC ¶ 61,217, at P 226; Co-Location Order, 195 FERC ¶ 61,209, at P 284.
152 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(a) (effective 12/31/9998)
(“[P]lanned modifications that include the addition of an Eligible Load or Large Load configuration must be
studied as part of the Fast Energization process set forth in this Tariff, Part VIII.”).
PDF page 36
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 32
32
4.
PJM is eschewing parallel processes, to streamline for speed and
accuracy.
As part of the effort to streamline for speed, PJM proposes to eliminate
Replacement Generation Interconnection Service.153 Replacement Generation
Interconnection Service was developed to address the delay in processing Generation
Interconnection Requests during the transition from the old, serial process to the current
clustered Cycle process.154 That delay was particularly a problem for generators seeking
to transfer Capacity Interconnection Rights from a deactivating resource to a New Service
Request, because Capacity Interconnection Rights must be transferred within one year of
deactivation of a resource.155 With the Fast Energization Process taking only a year, there
will no longer be a need for Replacement Generation Interconnection Service as a separate
parallel process. Parallel processes, despite their value and benefit, increase complexity
and tend to slow down processing; therefore PJM proposes to limit their use.156
PJM also proposes to return the Necessary Studies process to its former role of
addressing modifications to projects covered by existing, effective service agreements once
the Fast Energization Process is in effect,157 as Eligible Loads and Eligible Generation can
be studied more comprehensively through the main study process and do not need another
separate parallel study process. PJM proposes to add the same Necessary Studies process
153 Attachment A-2, Proposed Tariff, Part VIII, Subpart J, sections 437(A)-(B) (requiring Replacement
Generation Interconnection Service Requests to be made prior to the next Business Day after the close of
Decision Point II of Cycle 01).
154 Bielak Decl. ¶ 14.
155 See Tariff, Part VIII, Subpart E, section 426(C)(3).
156 Bielak Decl. ¶¶ 15, 18. Along those lines, PJM also intends to open a stakeholder process in the first or
second quarter of 2027 to explore improvements to Surplus Interconnection Service, another parallel process
that has a negative impact on processing speed.
157 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(a) (effective 12/31/9998).
PDF page 37
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 33
33
for studying Eligible Customer-driven modifications to existing, effective Transmission
Service Agreements for changes to the characteristics of Eligible Load and Large Load to
the Necessary Studies process, however, as such changes require study to protect the
Transmission System.158
5.
PJM will maintain transparency of its study results
PJM will continue to identify the system reinforcements needed to interconnect
Generating Facilities and provide transmission service to loads, the drivers of those
reinforcements and their capital costs. PJM’s studies will use a proportional impact
methodology, consistent with Order No. 2023.159 And PJM will post information regarding
the reinforcements and their drivers and capital costs at the end of each Cycle on pjm.com
in a publicly accessible, searchable format.160 The allocation and recovery of those costs
is in the control of the Transmission Owners because they have filing rights as to cost
allocation, cost recovery, and rate design.
C.
Part XI—New Transmission Services
1.
Interim NITS
Consistent with the Commission’s directive to make the new transmission services
available to Eligible Customers serving load with BTMG,161 PJM is proposing in Part XI,
Subpart A to offer Interim NITS to Eligible Customers serving “Eligible Load,” which
158 See Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(a) (effective 12/31/9998).
159 See Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404.
160 See, e.g., Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 409(B)(2) (requiring System
Impact Study results to be publicly available on PJM’s website).
161 Co-Location Order, 195 FERC ¶ 61,209, at P 91.
PDF page 38
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 34
34
encompasses both Co-Located Load and load with BTMG.162 PJM is also making Interim
NITS available to Large Loads.163 The Part XI, Subpart A largely adopts the terms and
conditions proposed during the paper hearing process in Docket No. EL25-49-000,164 but
in a streamlined, reorganized format and with certain Commission-directed changes and
other clarifications. The Commission generally found in the Co-Location Order that the
Interim NITS rules PJM had proposed were just and reasonable.165
Section 701 describes the general nature of Interim NITS and restrictions on its
use.166 Interim NITS is a transmission service that allows Eligible Customers serving
Eligible Load or Large Load to utilize head room on the system as-available on an
interruptible basis to a specific Delivery Point while awaiting the completion of system
upgrades necessary to provide full NITS.167 Interim NITS is an energy-only service (i.e.,
it is not capacity backed).168 Interim NITS is not available to Eligible Customers serving
Eligible Load or Large Loads with FCD or NFCD Transmission Service.169 In addition,
Interim NITS may not be utilized by Eligible Customers to serve loads other than the
designated Eligible Load or Large Load.170 Finally, PJM reserves the right to curtail
162 Attachment A-1, Proposed Tariff, Part XI, Subpart A, sections 700-03; Proposed Tariff, Part I, Definitions
– E - F (Eligible Load).
163 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.1.
164 See generally PJM Initial Brief, Attachment A (Illustrative Language for New Tariff, Part XI; Attachments
F-3A and F-4; and Other Illustrative Tariff Revisions) (Feb. 23, 2026); PJM Reply Brief, Attachment A
(Redlines on Reply Brief to Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and
Other Illustrative Tariff Revisions).
165 See Co-Location Order, 195 FERC ¶ 61,209, at PP 263-68, 571.
166 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.
167 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.1.
168 See Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.2.
169 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.3.
170 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.4.
PDF page 39
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 35
35
Interim NITS, consistent with Good Utility Practice, for the purpose of making upgrades,
modifications, or repairs to Transmission Owner or Generation Owner lines, substations,
generators, or facilities or to respond to adverse system conditions.171
Section 702 lays out the requirements for initiating Interim NITS.172 Eligible
Customers may apply for Interim NITS at the same time as NITS by submitting an
Application pursuant to the procedures in Part VIII.173 The Transmission Service
Agreement for Interim NITS is in the form provided in Attachment F-3A.174 Such eligible
Customers must also meet conditions precedent for service including complying with the
PJM Credit Policy, executing a Transmission Service Agreement with operational
procedures and necessary control technologies to limit withdrawals from the system, and
certifying that the Eligible Customer is willing and able to limit withdrawals from the
Transmission System for the Eligible Load when directed by Transmission Provider, and
constructing any facilities on the customer’s side of the Delivery Point to receive the
delivery of energy.175 Consistent with the Co-Location Order,176 PJM clarified that Interim
NITS will terminate and be converted automatically to NITS once the Transmission
Provider performs an analysis to verify the system can accommodate the firm load and
updates its internal systems to reflect the relevant upgrades needed to provide the requested
171 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 701.5.
172 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.
173 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.1.
174 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.2.
175 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.3.
176 Co-Location Order, 195 FERC ¶ 61,209, at P 571.
PDF page 40
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 36
36
level of service on a firm basis.177 The language concerning performing an updated
analysis and updating the relevant internal system updates was added to clarify that the
conversion does not happen automatically the moment upgrades are physically complete
but must first be reflected in PJM’s internal systems. In addition to termination for
conversion to NITS, Interim NITS may be terminated to the extent the Eligible Load or
Large Load is disqualified from receiving service pursuant to Part XI, Subpart C, section
719.5 due to multiple failures to follow Curtailment directives or misoperation of necessary
control technologies.178 Interim NITS may also be terminated to the extent an Eligible
Customer is in breach of its obligations under the Transmission Service Agreement (e.g.,
failure to update Transmission Provider regarding material changes to the Eligible Load or
Large Load).179 Finally, Interim NITS may be terminated on another date mutually agreed
by the parties.180
Consistent with the allocation of filing rights between PJM and Transmission
Owners,181 PJM understands the Transmission Owners have filed transmission rates for
177 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(a); Proposed Tariff, Attachment F-
3A.
178 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(b).
179 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(c).
180 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 702.4(d).
181 CTOA, Rate Schedule FERC No. 42; see also Atl. City Elec. Co., 190 FERC ¶ 61,109, at P 3 (2025)
(providing history and authority for the CTOA under Pennsylvania-New Jersey-Maryland Interconnection,
105 FERC ¶ 61,294 (2003) (“Atlantic City Settlement Order”), order on compliance, 108 FERC ¶ 61,033
(2004) by explaining that “[i]n the Atlantic City Settlement Order, the Commission explained that the
settlement agreement essentially divides filing rights between ‘rate-related filings and terms and conditions-
related filings – with the PJM [Transmission Owners] filing the former and PJM the latter’”); Atl. City Elec.
Co., 190 FERC ¶ 61,109, at P 4 (“[I]ndividual transmission owners do not have a right to file under FPA
section 205 to modify ‘terms and conditions of the PJM Tariff’. . . .”); Atl. City Elec. Co. v. FERC, 295 F.3d
1, 6 (D.C. Cir. 2002) (explaining that the initial Settlement Agreement between PJM and Transmission
Owners “established procedures for changes to rate design and other tariff terms for transmission services.
It permitted the transmission owners to file changes in transmission service rate design and non-rate terms
and conditions to the tariff under section 205.”).
PDF page 41
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 37
37
Interim NITS.182 In addition to such rates, Eligible Customers taking Interim NITS on
behalf of Eligible Load or Large Load will be assessed certain other charges that are within
PJM’s filing authority, consistent with the charges assessed to loads taking NITS.183
Accordingly, PJM would assess Eligible Customers taking Interim NITS on behalf of
Eligible Load or Large Load:
• administrative services charges under Schedule 1A, Schedule 9, and
Schedule 10 of the Tariff;184
• Ancillary Services charges in accordance with Part I, section 3;185
• Black Start Service charges in accordance with Tariff, Schedule 6A;186
• any redispatch costs as set forth in Tariff, Attachment K;187 and
• any applicable Transmission Enhancement Charges in accordance with Tariff,
Schedule 12.188
2.
Contract Demand Transmission Service
Part XI, Subpart B, sections 708 through 711 and 714 through 715 provide the terms
and conditions for the Contract Demand Transmission Services.189 As explained in section
708, Contract Demand Transmission Service allows an Eligible Customer to take
transmission service on behalf of Eligible Load or Large Load that is willing and able to
182 PJM Interconnection, L.L.C., PJM Transmission Owners’ Partial Compliance Filing, Docket No.
ER26-3537-000 (Aug. 17, 2026).
183 See Co-Location Order, 195 FERC ¶ 61,209, at P 573.
184 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4.
185 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4.
186 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4.
187 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.2.
188 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 703.4.
189 Attachment A-1, Proposed Tariff, Part XI, Subpart B, sections 708-11, 714-15.
PDF page 42
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 38
38
limit withdrawals from the Transmission System.190 FCD Transmission Service provides
energy and capacity up to a specified, defined MW level.191 NFCD Transmission Service
provides energy procured by Transmission Provider on an as-available basis up to a
specified, predetermined level.192
To be eligible for Contract Demand Transmission Service, any given Eligible Load
or Large Load cannot be served by Interim NITS or NITS or have a pending Application
for the same.193 To prevent toggling between FCD Transmission Service and NFCD
Transmission Service to avoid capacity costs, an Eligible Customer shall not be eligible to
take NFCD Transmission Service on behalf of any given portion of an Eligible Load or
Large Load it previously served with FCD Transmission Service for five years following
the effective date of the relevant Transmission Service Agreement.194 As with Interim
NITS, Contract Demand Transmission Service may not be used for sales of energy or
capacity to loads other than the Eligible Load or Large Load designated in the Transmission
Service Agreement.195 Also, Transmission Provider may Curtail Contract Demand
Transmission Service, consistent with Good Utility Practice, to make or support upgrades,
modifications, or maintenance to Transmission Owner or Generation Owner lines,
190 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 708(a).
191 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 708(b).
192 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 708(b).
193 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.3. This approach is consistent with the
Commission’s holdings that a customer cannot take NITS for only a portion of its load behind a delivery
point. See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 196 (2025).
194 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.3.
195 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.4.
PDF page 43
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 39
39
substations, and equipment or as needed due to adverse conditions on the Transmission
System.196
To initiate Contract Demand Transmission Service on behalf of a designated
Eligible Load or Large Load, the Eligible Customer must apply pursuant to the procedures
in Tariff, Part VIII.197 Note that even to the extent an entity intends to serve Eligible Load
or Large Load entirely through Co-Located Generation and does not wish to take
Transmission Service, the entity must still apply and take service for zero MW pursuant to
a Transmission Service Agreement to account for the provision of ancillary services.198
The Transmission Service Agreement for Contract Demand Transmission Service is in the
form provided in Attachment F-4.199
Eligible Customers must meet the following conditions precedent to receive
Contract Demand Transmission Service: (i) make a valid request pursuant to Part VIII; (ii)
verify that the designated Eligible Load or Large Load has not been served by an Eligible
Customer taking NITS or Interim NITS or applied for such service on behalf of the load;
(iii) the Eligible Customer has complied with the PJM Credit Policy; (iv) the Eligible
Customer has executed a Transmission Service Agreement in the form provided in
Attachment F-4, which includes operational procedures and necessary control technologies
to limit energy withdrawals; (v) the Eligible Customer is in compliance with all applicable
technical requirements; (vi) the Eligible Customer constructed any facilities on its side of
the Delivery Point necessary to receive the delivery of energy; (vii) the Eligible Customer
196 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 709.5.
197 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.1.
198 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.1.
199 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.2.
PDF page 44
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 40
40
has completed any necessary certification requirements in accordance with the PJM
Manuals; (viii) the Eligible Customer has executed the PJM Governing Agreements; and
(ix) in the case of an Eligible Load served by an Eligible Generating Facility, the Eligible
Customer verifies that no portion of the Eligible Generating Facility dedicated to serving
the Eligible Load has Capacity Interconnection Rights.200
Contract Demand Transmission Service will generally continue without expiration,
but may be terminated in certain circumstances.201 First, Contract Demand Transmission
Service may be terminated to the extent an incumbent Eligible Customer is being replaced
by a successor Eligible Customer.202 Second, an Eligible Customer may terminate FCD
Transmission Service by providing PJM with 42 months’ notice prior to the
commencement of the Delivery Year.203 Third, Contract Demand Transmission Service
may be terminated to the extent the Eligible Load or Large Load is disqualified from
receiving service pursuant to Part XI, Subpart C, section 719.5 due to multiple failures to
follow Curtailment directives or misoperation of necessary control technologies.204 Fourth,
the Eligible Customer is in breach of its obligations under the Transmission Service
Agreement (e.g., failure to update Transmission Provider regarding material changes to the
Eligible Load or Large Load).205 Fifth, Contract Demand Transmission Service may be
terminated on another date mutually agreed by the parties.206 Sixth, NFCD Transmission
200 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 710.3.
201 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711.
202 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(a).
203 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(b).
204 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(c).
205 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(d).
206 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(e).
PDF page 45
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 41
41
Service may be terminated when system upgrades necessary to provide FCD Transmission
Service are completed and placed in service.207
Consistent with the allocation of rights between PJM and Transmission Owners,208
PJM understands the Transmission Owners will be making a separate filing transmission
rates for FCD Transmission Service and NFCD Transmission Service. In addition to such
rates, Eligible Customers will be assessed other charges Contract Demand Transmission
Service that are within PJM’s filing authority. Accordingly, PJM will assess Eligible
Customers taking FCD Transmission Service on behalf of Eligible Load or Large Load:
• administrative services charges under Schedule 1A, Schedule 9, and Schedule
10 of the Tariff, based on the total quantity of megawatt-hours (“MWh”) of
FCD Transmission Service specified in the Transmission Service Agreement,
except in the case of any capacity-related charges under these schedules, which
shall be based on the Eligible Customer’s Unforced Capacity Obligation;209
• Ancillary Services charges, except for Regulation, based on the total quantity
in MWhs of FCD Transmission Service specified in the Transmission Service
Agreement in accordance with Part I, section 3;210
• Regulation charges based on gross demand of the Eligible Load;211
• Black Start Service charges based on the gross demand in accordance with
Tariff, Schedule 6A;212
• any redispatch costs as set forth in Tariff, Attachment K;213 and
207 Attachment A-1, Proposed Tariff, Part XI, Subpart B, section 711(f).
208 See supra note 95.
209 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5.
210 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5.
211 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5.
212 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5.
213 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.3.
PDF page 46
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 42
42
• any applicable Transmission Enhancement Charges in accordance with Tariff,
Schedule 12.214
For Eligible Customers taking NFCD Transmission Service on behalf of Eligible
Load or Large Load, PJM would assess:
• administrative services charges under Schedule 1A, Schedule 9, and Schedule
10 of the Tariff, based on the total quantity of MWhs of reserved NFCD
Transmission Service, except any capacity-related charges under these
schedules will not apply;215
• Ancillary Services charges, except for Regulation, based on the total quantity
in MWhs of reserved NFCD Transmission Service in accordance with Tariff,
Part I, section 3;216
• To the extent the Eligible Customer does not have an effective Transmission
Service Agreement for FCD Transmission Service, Black Start Service charges
based on the gross demand in accordance with Tariff, Schedule 6A;217
• any redispatch costs as set forth in Tariff, Attachment K;218 and
• To the extent the Eligible Customer does not have an effective Transmission
Service Agreement for FCD Transmission Service, Regulation charges based
on the gross demand of the Eligible Load or Large Load.219
3.
Common service provisions for Interim NITS and Contract Demand
Transmission Services
As proposed, Tariff, Part XI, Subpart C now provides the common service
provisions for Part XI transmission services including requirements for control
technologies, protection schemes, technical requirements, and facility construction.
Service under Part XI is conditioned upon the Eligible Customer constructing, maintaining,
214 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 714.5.
215 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4.
216 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4.
217 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4.
218 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.2.
219 Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 715.4.
PDF page 47
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 43
43
and operating the facilities and necessary control technologies and protection systems to
take service and ensure that the Eligible Customer limits its withdrawals from the
system.220 Those necessary control technologies may include fully redundant special
protection schemes in accordance with the PJM Manuals.221 Necessary control
technologies and special protection schemes must be developed in accordance with the
PJM Manuals and consistent with Transmission Owner technical requirements and may be
modified from time to time.222 In addition, Eligible Customers must meet the relevant
technical requirements for service including the installation of necessary hardware and
software to limit energy withdrawals, provisioning an operations center and qualified
personnel, and demonstration of operational control.223
Consistent with the Commission’s directive,224 PJM revised the Curtailment
language to clarify the relative priority for the various services.225 FCD Transmission
Service will be treated as equivalent to NITS and Firm Point-to-Point Transmission
Services for purposes of Curtailment.226 Interim NITS, NFCD Transmission Service, and
Non-Firm Point-to-Point Service will be treated as equivalent for purposes of
Curtailment.227 Transmission Provider will prioritize reservations for Curtailment based
on their contribution to exceedances of system limits as specified in the PJM Manuals.228
220 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 716.
221 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 717.
222 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 717.
223 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 718.1.
224 Co-Location Order, 195 FERC ¶ 61,209, at P 555.
225 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.
226 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.2.
227 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.4.
228 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.4.
PDF page 48
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 44
44
As directed,229 PJM also added language to specify that Eligible Customers subject to
Curtailment may use a Co-Located Generating Facility to serve Co-Located Load provided
the facility either has not obtained interconnection service yet or the facility is not a
Capacity Resource.230 Consistent with the Co-Location Order,231 PJM added language in
section 719.5 and to the Part I definition of Curtailment to clarify that with respect to Tariff,
Part XI, its Curtailment authority includes the authority to curtail Interim NITS and NFCD
Transmission Service for capacity or reserve shortages.232
Consistent with the Commission’s directive,233 PJM revised the operational
penalties for failure to follow dispatch instructions or misoperation of control
technologies.234 Eligible Customers taking Interim NITS or Contract Demand
Transmission Service are subject to operational penalties in the event that the Eligible
Customer’s necessary control technology or protection system scheme misoperates.235
After one instance of misoperation, the Eligible Customer will be prohibited from taking
transmission service or otherwise withdrawing energy from the Transmission System
pursuant to the relevant Transmission Service Agreement for a period up to 120 days from
misoperation, which may be shortened or extended per mutual agreement.236 The up to
120-day pause pending evaluation of the misoperation of the necessary control technology
229 Co-Location Order, 195 FERC ¶ 61,209, at P 576.
230Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 705.2.
231 Co-Location Order, 195 FERC ¶ 61,209, at P 551.
232 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – C - D); Proposed Tariff, Part XI, Subpart
C, section 719.5.
233 Co-Location Order, 195 FERC ¶ 61,209, at PP 516, 523-24, 527.
234 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5.
235 Attachment A-1, Proposed Tariff, Part XI, Subpart C, sections 719.5(a)-(b).
236 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5(b).
PDF page 49
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 45
45
or protection system scheme is consistent with NERC requirements for an investigation
into the operation of a Remedial Action Schemes (e.g., PRC-004-6 and PRC-012-02).237
Such a pause in service will allow PJM (and the affected Transmission Owner(s), as
necessary) time to investigate, identify, and implement necessary fixes to better protect the
Transmission System, while respecting the Eligible Customer’s desire to retain this type of
service based on its promised willingness to limit energy withdrawals. In the event a
necessary control technology or protection system misoperates a second time, the Eligible
Customer’s Transmission Service Agreement for that Eligible Load shall be terminated.238
Similarly, Eligible Customers that fail to respond to established Load Shedding and
Curtailment procedures shall be prohibited from taking service under the relevant
Transmission Service Agreement for a period of up to 120 days.239
4.
Pro Forma Service Agreement for Interim NITS (Attachment F-3A)
Because Interim NITS is by definition a temporary service that will convert into
NITS, the pro forma service agreement is a combined Interim NITS/NITS agreement for
Eligible Customers taking Interim NITS or NITS on behalf of Eligible Loads or Large
Loads.240 Any Eligible Customer taking these services on behalf of Eligible Loads or Large
Loads would execute Attachment F-3A.241 In addition to the general terms carried over
237 PRC-004-6 – Protection System Misoperation Identification and Correction, North American Electric
Reliability
Corporation
(June
12,
2025),
https://www.nerc.com/globalassets/standards/reliability-
standards/prc/prc-004-6.pdf [https://perma.cc/EV9E-JYWQ]; PRC-012-2 – Remedial Action Schemes, North
American
Electric
Reliability
Corporation
(June
12,
2025),
https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012-2.pdf
[https://perma.cc/9KFL-HHNU].
238 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5(b).
239 See Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5(a).
240 Attachment A-1, Proposed Tariff, Part XI, Subpart A, sections 701.1, 702.4(a).
241 Attachment A-1, Proposed Tariff, Attachment F-3A. The existing pro forma NITS Service Agreement is
located at Tariff, Attachment F-3.
PDF page 50
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 46
46
from the pro forma NITS Service Agreement (Attachment F-3), PJM has added terms
specific to Interim NITS and serving Eligible Loads and Large Loads. When an Eligible
Customer takes Interim NITS while awaiting upgrades for NITS, Attachment F-3A
specifies that NITS will not commence until the necessary upgrades are complete,
Transmission Provider has performed an updated analysis to verify the Transmission
System can accommodate the firm load, and the Transmission Provider has updated the
relevant systems pursuant to its internal procedures.242 Because PJM will have to ensure
the Transmission System can accommodate the specific Eligible Load or Large Load being
served by the Eligible Customer, Attachment F-3A requires certain details about that load
to be specified in the Agreement. Attachment F-3A requires the specific Eligible Load or
Large Load being served to be identified, the load’s gross demand to be specified, and, as
applicable, information regarding the Eligible Generating Facility serving the load to be
listed, including its Maximum Facility Output.243 The Eligible Customer is also required
to specify a Delivery Point for Interim NITS and submit a single-line diagram.244
Because Interim NITS requires the Eligible Customer to be willing and able to limit
withdrawals from the system, Attachment F-3A includes terms to implement such
limitations. First, Attachment F-3A specifies the amount of Interim NITS provided245 and
requires the Eligible Customer to certify that it is willing and able to limit its usage of the
Transmission System consistent with the terms of the Agreement and when requested by
242 Attachment A-1, Proposed Tariff, Attachment F-3A, sections 2.0-3.0.
243 Attachment A-1, Proposed Tariff, Attachment F-3A.
244 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, section
1.0; Proposed Tariff, Attachment F-3A, Schedule A.
245 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, section
1.0.
PDF page 51
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 47
47
the Transmission Provider.246 The Agreement also includes a placeholder to list the
necessary control technologies and operational practices that will be required prior to the
commencement of Interim NITS.247 Finally, the agreement prohibits the Eligible Customer
from making any material modifications to the load being served without the Transmission
Provider’s prior written agreement.248 To the extent modifications to the Load Facility are
planned, the Agreement requires the Eligible Customer to provide PJM notice to allow
PJM to initiate the Necessary Studies process.249 In the event PJM determines that a
planned modification would have a permanent material impact on the Transmission System
or would constitute a material modification, Network Customer shall then withdraw the
proposed modification or proceed with a new Eligible Customer for Load Request for the
modification.250 Finally, the Agreement provides that if an Eligible Customer fails to
timely inform the Transmission Provider of or obtain Transmission Provider’s written
agreement for a material change in (i) the demand characteristics of the Load Facility; or
(ii) the supply characteristics of the Eligible Generating Facility may constitute a breach to
the Agreement and the Agreement may be terminated.251
246 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0.
247 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, sections
4.0-5.0.
248 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0.
249 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0.
250 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0.
251 Attachment A-1, Proposed Tariff, Attachment F-3A, section 4.0.
PDF page 52
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 48
48
5.
Pro Forma Service Agreement for Contract Demand Transmission
Service (Attachment F-4)
Attachment F-4, the pro forma agreement for Contract Demand Transmission
Service, governs both FCD and NFCD Transmission Services.252 Attachment F-4 is the
pro forma agreement for Eligible Customers taking FCD or NFCD Service on behalf of
Eligible Loads or Large Loads.253 Any Eligible Customer taking these services on behalf
of Eligible Loads or Large Loads would execute Attachment F-4.254 In addition to the
general terms carried over from the pro forma NITS Service Agreement (Attachment F-3),
PJM has added terms specific to Contract Demand Transmission Service and serving
Eligible Loads and Large Loads. When an Eligible Customer takes NFCD Transmission
Service while awaiting upgrades for FCD Transmission Service, Attachment F-4 specifies
that FCD Transmission Service will not commence until the upgrades are complete,
Transmission Provider has performed an updated analysis to verify the Transmission
System can accommodate the firm load, and the Transmission Provider has updated the
relevant systems pursuant to its internal procedures.255 Like with Interim NITS, because
PJM will have to ensure the Transmission System can accommodate the specific Eligible
Load or Large Load being served by the Eligible Customer, Attachment F-4 requires
certain details about that load to be specified in the Agreement. Attachment F-4 requires
the specific Eligible Load or Large Load being served to be identified, the load’s gross
demand to be specified, and, as applicable, information regarding the Eligible Generating
252 Attachment A-1, Proposed Tariff, Attachment F-4.
253 Attachment A-1, Proposed Tariff, Part XI, Subpart B, sections 708(a), 710.3(iv).
254 Attachment A-1, Proposed Tariff, Attachment F-4; Proposed Tariff, Part XI, Subpart B, sections 708(a),
710.3(iv).
255 Attachment A-1, Proposed Tariff, Attachment F-4, sections 2.0-3.0.
PDF page 53
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 49
49
Facility serving the load to be listed, including its Maximum Facility Output.256 The
Eligible Customer is also required to specify a Delivery Point for the Contract Demand
Transmission Service and submit a single-line diagram.257
Because Contract Demand Transmission Service requires the Eligible Customer to
limit withdrawals from the system (as with Interim NITS), Attachment F-4 includes terms
to implement such limitations. First, Attachment F-4 specifies the amount of FCD
Transmission Service and NFCD Transmission Service being provided258 and requires the
Eligible Customer to certify that it is willing and able to limit its usage of the Transmission
System consistent with the terms of the Agreement and when requested by the
Transmission Provider.259 The Agreement also includes a placeholder to list the necessary
control technologies and operational practices that will be required prior to the
commencement of service.260 Finally, the agreement prohibits the Eligible Customer from
making any material modifications to the load being served without the Transmission
Provider’s prior written agreement.261 To the extent modifications to the Load Facility are
planned, the Agreement requires the Eligible Customer to provide PJM notice to allow
PJM to initiate the Necessary Studies process.262 In the event PJM determines that a
256 Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission
Service, sections 2.0-3.0.
257 Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission
Service, section 1.0; Proposed Tariff, Attachment F-4, Schedule A.
258 Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission
Service, section 1.0.
259 Attachment A-1, Proposed Tariff, Attachment F-4, section 5.0.
260Attachment A-1, Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission
Service, sections 4.0-5.0.
261 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0.
262 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0.
PDF page 54
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 50
50
planned modification would have a permanent material impact on the Transmission System
or would constitute a material modification, Network Customer shall then withdraw the
proposed modification or proceed with a new Eligible Customer for Load Request for the
modification.263 Finally, the Agreement provides that if an Eligible Customer fails to
timely inform the Transmission Provider of or obtain Transmission Provider’s written
agreement for a material change in (i) the demand characteristics of the Load Facility; or
(ii) the supply characteristics of the Eligible Generating Facility may constitute a breach of
the Agreement and the Agreement may be terminated.264
D.
Re-Filing Co-Located Load Compliance Changes
A number of proposed changes in this filing address compliance directives from
the Co-Location Order and were previously filed on August 17, 2026.265 PJM filed a
motion with the Commission earlier today seeking leave to withdraw that filing in favor of
this one due to the overlapping nature of many of the changes.266 A number of the proposed
changes from the August 17 Filing are being re-filed here. Attachment D provides a chart
detailing where each directive from the June 2026 Orders is addressed in this filing.267
1.
Prohibition on serving Co-Located Load from existing generators
The Co-Location Order directed PJM to explain in its compliance filing how its
changes will prohibit Interconnection Customers from serving Co-Located Loads from
new and existing generators until all necessary Network Upgrades, control technologies
263 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0.
264 Attachment A-1, Proposed Tariff, Attachment F-4, section 4.0.
265 See August 17 Filing.
266 PJM Interconnection, L.L.C., Motion to Withdraw Filing and Terminate Proceeding in Deference to New
Docket of PJM Interconnection, L.L.C., Docket No. ER26-1479-002 (Nov. 16, 2026).
267 See generally Attachment D, Chart Mapping Order Directives to Tariff Changes.
PDF page 55
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 51
51
and/or protection systems, and metering are complete and in service.268 This FPA section
205 filing fulfils PJM’s compliance obligations and obviates the need for a separate
compliance filing by proposing to add Necessary Study references and provisions to Parts
I, III, VI, and VII, and to direct Generation Project Developers seeking to serve Co-Located
Load with an existing Co-Located Generating Facility to the Necessary Study process in
Part VIII, Subpart A, section 401(H)(3).269 In its Sixty-Day Compliance Filing, PJM
proposed to add language to Part VIII for the Necessary Study process to preclude a Project
Developer from implementing any planned modifications to its facilities until the
Necessary Studies are completed and the amended GIA reflecting the results of such
studies is fully executed and effective; the Sixty-Day Compliance Filing also provided that
service to the Co-Located Load could not begin until “all required Network Upgrades,
necessary control technologies and protection systems, and metering identified as
necessary are complete and in service.”270 Thus, the Tariff would now require that all
Interconnection Customers and Generation Project Developers seeking to serve Co-
Located Load, whether with existing or new Generating Facilities: (1) provide advance
written notice to PJM and the relevant Transmission Owner; (2) go through the Necessary
Study process in Part VIII of the Tariff; and (3) not begin serving Eligible Load until the
268 Co-Location Order, 195 FERC ¶ 61,209, at P 285.
269 See Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – L-M-N) (adding the definitions of
“Necessary Study” and “Necessary Studies Agreement”); Proposed Tariff, Part III (General) (addition of
notice requirement); Proposed Tariff, Part VI, Subpart B, section 212 (same); Proposed Tariff, Part VII,
Subpart A, section 301(A)(7)(c) (same).
270 Sixty-Day Compliance Filing, Proposed Tariff Revisions (Attachments A & B), Part VIII, Subpart A,
sections 401(H)(3)(a), 401(H)(3)(b)(iii). In this filing, PJM proposes to further clarify in Proposed Tariff,
Part VIII, the Necessary Study process by amending the listing of required and necessary equipment changes
to instead reference “the entire scope of work required under that . . . Generation Interconnection Agreement.”
Proposed Tariff, Part VIII, Subpart A, section 401(H)(3)(d). This ensures that all items determined to be
necessary and therefore captured in the amended GIA are complete before the Project Developer may begin
serving Eligible Load.
PDF page 56
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 52
52
entire scope of the work under their GIA as amended after the Necessary Study process is
complete. These combined revisions ensure that all these entities are treated comparably
and the prohibition on serving Co-Located Loads before all the necessary upgrades and
equipment changes are complete is enforced across the board.271
2.
Expansion of service to “Eligible Load” for load with BTMG
The Co-Location Order directed PJM to expand the availability of the December
Order’s new transmission services to Network Customers serving load with BTMG that
are willing and able to limit their withdrawals from the Transmission System under certain
circumstances.272 The Commission directed PJM to either add a definition of “Eligible
Load” or propose other changes to implement this directive.273 Consistent with this
directive, PJM is proposing to add the term Eligible Load to the Tariff to encompass both
Co-Located Load and Load with BTMG.274 To that end, PJM is proposing to add to the
Tariff, Part I, section 1, Definitions the term “Eligible Load” defined as “Co-Located Load
or load connected to Behind the Meter Generation.”275 Further consistent with the
Commission’s directive to propose other Tariff changes necessary to expand the
271 PJM also proposes herein formatting and language changes to the Necessary Study provisions in Part VIII,
Subpart A, section 401(H)(3), to make clear that the Necessary Study process applies to all Project
Developers that plan to make modifications to their facilities, “including but not limited to a Project
Developer whose planned modifications include an Eligible Load configuration.” Attachment A-1, Proposed
Tariff, Part VIII, Subpart A, section 401(H)(3)(a). PJM further proposes minor, ministerial changes to Tariff,
Part VIII to spell out the term “Generation Interconnection Agreement” and replace “PJM” with
“Transmission Provider,” as appropriate. See, e.g., Attachment A-1, Proposed Tariff, Part VIII, Subpart C,
section 408(A)(2)(e)(i)(j)(iv); Proposed Tariff, Part VIII, Subpart E, sections 414(B)(2), 414(B)(4)(c).
272 Co-Location Order, 195 FERC ¶ 61,209, at P 91.
273 Co-Location Order, 195 FERC ¶ 61,209, at P 91.
274 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – E - F) (adding the definition of “Eligible
Load”).
275 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – E - F) (adding the definition of “Eligible
Load”).
PDF page 57
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 53
53
availability of these new services, PJM is proposing to add to the term “Eligible Generating
Facility” to the Tariff to encompass both a Co-Located Generating Facility or Retail
BTMG.276 In addition, PJM is proposing conforming changes to replace “Co-Located
Load” with “Eligible Load” and “Co-Located Generator” with “Eligible Generator” and
other clarifying changes in Tariff Part I, section 1 (Definitions),277 Part III (Network
Integration Transmission Service),278 Part VI (Administration and Study of New Service
Requests),279 Part VII (Transition Cycle Generation Interconnection Procedure),280 Part
VIII (New Rules Generation Interconnection Procedure),281 Part IX (Forms of
276 “‘Eligible Load’ shall mean Co-Located Load or load connected to Behind the Meter Generation.
‘Eligible Generating Facility’ shall mean a Co-Located Generating Facility or Behind the Meter Generation.”
Proposed Tariff, Part I, section 1 (Definitions – E - F) (defining “Eligible Load” and “Eligible Generating
Facility”).
277 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – O - P - Q) (updating the definition of
“Provisional Interconnection Service” to reference “Eligible Load” instead of just “Co-Located Load”).
278 Attachment A-1, Proposed Tariff, Part III, section 28.1 (replacing “Co-Located Load” with “Eligible
Load”); section 29.1 (allowing customers to take NITS on behalf of “Eligible Load” instead of “Co-Located
Load”); Proposed Tariff, Part III, section 29.2 (replacing “Co-Located Load” with “Eligible Load” in
Application procedures); Proposed Tariff, Part III, section 31.6 (replacing “Co-Located Load” with “Eligible
Load” in annual load and resource information update).
279 Attachment A-1, Proposed Tariff, Part VI, Subpart B, section 212 (adding language in Part VI, Subpart
B, section 212 regarding the Necessary Study process in Part VIII for Generating Facilities to reference
service to Eligible Loads).
280 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions E (adding the definitions
for “Eligible Load” and “Eligible Generating Facility”); Proposed Tariff, Part VII, Subpart A, section 300,
Definitions P (revising the definition of “Provisional Interconnection Service” to reference “Eligible
Generating Facility” and “Eligible Load”).
281 Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 400, Definitions E (adding the definitions
for “Eligible Load” and “Eligible Generating Facility”); Proposed Tariff, Part VIII, Subpart A, section 400,
Definitions P (updating the definition of “Provisional Interconnection Service” to reference “Eligible
Generating Facility” and “Eligible Load”); Proposed Tariff, Part VIII, Subpart A, section 401 (revising the
Application requirements to allow Eligible Generating Facilities serving Eligible Load and clarifying the
Necessary Studies process applies to Eligible Load); Proposed Tariff, Part VIII, Subpart B, section 403
(revising the Application rules to allow Eligible Generating Facilities serving Eligible Load); Proposed
Tariff, Part VIII, Subpart C, section 404 (updating the System Impact Studies to contemplate service to
Eligible Load); Proposed Tariff, Part VIII, Subpart C, section 406 (updating the acceleration language to
allow acceleration of new service requests for new facilities or increases the generation capability in existing
facilities to serve Eligible Load); Proposed Tariff., Part VIII, Subpart C, section 408 (same); Proposed Tariff,
Part VIII, Subpart E, section 413 (updating the language permitting service requests below the Maximum
Facility Output for new facilities or increases the generation capability in existing facilities that will serve
PDF page 58
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 54
54
Interconnection-Related Agreements),282 and Part XI, Subpart A (Interim Network
Integration Transmission Service).283
3.
Elimination of new GIA requirement
PJM previously proposed to require all Eligible Customers that intend to serve Co-
Located Load with a new or existing Co-Located Generating Facility to enter into a new
GIA pursuant to Part VIII of the Tariff, which was revised to include additional details
regarding the Necessary Studies process.284 The Co-Location Order rejected this proposal
for customers with existing service agreements and directed PJM to add language
concerning the Necessary Study process to Tariff, Parts VI and VII to allow customers with
existing service agreements to modify those agreements.285 Accordingly, PJM is proposing
changes to allow customers that obtained service agreements pursuant to Parts VI and VII
to modify those agreements pursuant to the Necessary Study process in Part VIII.286
Eligible Load); Proposed Tariff, Part VIII, Subpart E, section 414 (updating the language to permit Surplus
Interconnection Service for Eligible Load).
282 Attachment A-1, Proposed Tariff, Part IX, Subpart A (Form of Application and Studies Agreement),
section 1 (revising section 1 of the Application and Studies Agreement to collect Applicant information for
an Eligible Generating Facility serving Eligible Load); Proposed Tariff, Part IX, Subpart A (Form of
Application and Studies Agreement), section 3.17 (changing “PJM” to “Transmission Provider” and
clarifying all transmission service requests in the PJM Region are subject to the same deliverability tests);
Proposed Tariff, Part IX, Subpart B, GIA Appendices and Schedules, Schedule O (updating Schedule O to
replace “Eligible Load” with “Eligible Generating Facility”); Proposed Tariff, Part XI, Subpart G, Necessary
Studies Agreement (updating the Necessary Studies Agreement to reference “Eligible Load” and “Eligible
Generating Facility”).
283Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 700 (updating references to “Co-Located
Load” to “Eligible Load”); Proposed Tariff, Part XI, Subpart A, section 701.1 (same); Proposed Tariff, Part
XI, Subpart A, section 701.2 (same); Proposed Tariff, Part XI, Subpart A, section 701.3 (same); Proposed
Tariff, Part XI, Subpart A, section 702.1 (same); Proposed Tariff, Part XI, Subpart A, section 702.4 (same);
Proposed Tariff, Part XI, Subpart A, section 703 (same).
284 See Co-Location Order, 195 FERC ¶ 61,209, at P 284; Attachment A-1, Proposed Tariff, Part VIII, Subpart
A, section 401(H)(3).
285 Co-Location Order, 195 FERC ¶ 61,209, at P 311.
286 See supra note 58 concerning addition of Necessary Study language to Parts I, III, VI, and VII;
Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 401(I). PJM also proposes to cross-reference
Tariff, Part VIII, Subpart L, section 439, Provisional Interconnection Service, added in the Thirty-Day
Compliance Filing, in Parts VI and VII to clarify that Provisional Interconnection Service is available to
PDF page 59
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 55
55
For Interconnection Customers that utilized the Part VI process, because Part VI
does not contain discrete definitions, PJM is revising the proposed definition of Co-Located
Generating Facility in Part I to include an existing Customer Facility that is physically
connected to Co-Located Load to incorporate the relevant terms from Part VI.287 As
explained above, to ensure that existing Interconnection Customers with effective
Interconnection Service Agreements (“ISA”) do not serve Co-Located Load until all
necessary upgrades and equipment are in place,288 PJM is also adding to the Co-Located
Generating Facility definition a requirement to provide advance written notice to the
Transmission Provider and Transmission Owner to initiate the Necessary Study process
pursuant to Part VIII, Subpart A, section 401(H)(3)(b) to use a Customer Facility to serve
Co-Located Load.289 In addition, PJM is adding language to mirror this Necessary Study
process requirement in Part VI, Subpart B, section 212.290 Finally, PJM has updated the
pro forma Necessary Studies Agreement to include language for Queue No., reference
Part VI for ISAs, incorporate references to Interconnection Customers throughout, and
entities that obtained Interconnection Service under those Parts. See Attachment A-1, Proposed Tariff, Part
I, section 1 (Definitions – O - P - Q) (updating the definition of “Provisional Interconnection Service”);
Proposed Tariff, Part VII, Subpart A, section 300, Definitions P (same); Proposed Tariff, Part VIII, Subpart
A, section 400, Definitions P (same).
287 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – C - D) (revising the definition of “Co-
Located Generating Facility”).
288 Co-Location Order, 195 FERC ¶ 61,209, at P 285.
289 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – C - D) (adding to the definition of “Co-
Located Generating Facility”).
290 Attachment A-1, Proposed Tariff, Part VI, Subpart B, section 212. PJM also proposes to add new Tariff,
Part VIII, Subpart A, section 401(I) to clarify that Interconnection Customers with ISAs under Tariff, Part
VI may utilize the Part VIII Necessary Study process and will be referred to as Project Developers or
Generation Project Developers and their agreements referred to as GIAs when doing so.
PDF page 60
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 56
56
reference Tariff, Attachment O, Appendix 2, section 3 in paragraph 5 concerning the
purpose of the Necessary Studies.291
For Generation Project Developers that utilized the Part VII Transition Cycle
Interconnection Process, PJM is proposing to modify the definition of Co-Located
Generating Facility to include both an existing and planned Generating Facility.292
Consistent with the proposed changes in Part VI, PJM is adding a requirement to provide
Transmission Provider and Transmission Owner with advance written notice to initiate the
Necessary Study process pursuant to Part VIII, Subpart A, section 401(H)(3)(b) in the event
a Generation Project Developer with an effective GIA intends to use a Generation Facility
to serve Co-Located Load.293 PJM is also adding this advance notice requirement for the
Necessary Study process to Tariff, Part VII, Subpart A, section 301(A)(7)(c).294 Finally,
PJM is proposing a definition of Co-Located Load that references the relevant terms for
Part VII of the Tariff (i.e., Generating Facility and Project Developer).295
291 Attachment A-1, Proposed Tariff, Part IX, Subpart G, Necessary Studies Agreement.
292 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions C (definition of Co-
Located Generating Facility).
293 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions C (definition of Co-
Located Generating Facility).
294 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 301(A)(7)(c); Proposed Tariff, Subpart A,
section 300, Definitions N.
295 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions C.
PDF page 61
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 57
57
4.
Effective date only
In addition, PJM previously proposed compliance changes that were accepted in
the Co-Location Order without an effective date.296 Accordingly, PJM is re-filing the
following Tariff records with a proposed effective date of March 16, 2027:
• Part I, section 1, Definitions – A-B (BTMG);297
• Part III, section 34.3 (Netting of Non-Retail BTMG);298
• Part VII, Subpart A, section 300, Definitions B (BTMG);299
• Part VIII, Subpart A, section 400, Definitions B (BTMG);300 and
• Part VIII, Subpart A, section 400, Definitions N (Necessary Study).301
E.
Changes to Be Addressed in Future Filings
PJM has identified certain changes to be addressed in future filings. PJM will need
to amend Schedule 1 of the Operating Agreement to allocate Auction Revenue Rights to
FCD Transmission Service customers and may need to make conforming changes to the
RAA regarding Capacity Market and load forecast effects of the new services. If, after
further stakeholder engagement or Commission direction, it appears prudent or necessary
to further clarify this matter in a filing, PJM will do so.
296 See, e.g., Co-Location Order, 195 FERC ¶ 61,209, at P 207 n.519; Sixty-Day Compliance Filing at 35.
297 Attachment A-1, Proposed Tariff, Part I, section 1 (Definitions – A - B) (updating the definition of “Behind
the Meter Generation”); Co-Location Order, 195 FERC ¶ 61,209, at P 207 n.519.
298 Attachment A-1, Proposed Tariff, Part III, section 34.3.
299 Attachment A-1, Proposed Tariff, Part VII, Subpart A, section 300, Definitions B.
300 Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 400, Definitions B.
301 Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 400, Definitions N; Co-Location Order,
195 FERC ¶ 61,209, at P 280 n.670.
PDF page 62
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 58
58
Other than the form of Necessary Studies Agreement, initially filed in the
August 17 Filing,302 that PJM is re-filing here because it will be needed in the interim
period before the Fast Energization Process begins, PJM is not proposing to revise the
forms of interconnection-related service agreements in Tariff, Part IX (e.g., the form of
Application and Studies Agreement, the GIA, the Wholesale Market Participation
Agreement, and others) in this filing. PJM plans to file revisions to those forms in a later,
supplemental filing, once the Commission has ruled on or provided guidance concerning
the Tariff revisions to Part VIII proposed herein. In that supplemental filing, PJM also will
propose other revisions to the interconnection-related service agreement in Tariff, Part IX
to streamline the service agreement negotiation and contracting process, based on lessons
learned to date in the Transition Period and in Cycle 01 and on PJM’s automation efforts.
Finally, depending on the Commission’s rulings or guidance on the cost recovery
provisions the Transmission Owners are filing concurrently, PJM will need to add to the
Tariff a form of agreement for PJM to hold Project Developers’ post-commercial operation
Security, as required to support the Transmission Owners’ fees charged to Project
Developers.303
PJM is filing separately today a motion for additional abeyance so that it can make
these supplemental filings.
302 August 17 Filing, Attachment A, Tariff, Part IX, Subpart G.
303 See Attachment A-2, Proposed Tariff, Part VIII, Subpart D, section 411(C).
PDF page 63
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 59
59
IV.
THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES AS
JUST AND REASONABLE.
A.
The Proposed Fast Energization Process Is Just and Reasonable and
Advances the Commission’s Categories for Reform in the June 2026
Orders
The Fast Energization Process is just and reasonable for four principal reasons.
First, it is designed to address and promote meaningful improvement in response to real
challenges facing the grid: insufficiently fast interconnection processes for load and
generation, parallel and duplicative study processes, speculative requests, limited visibility
into the drivers of transmission upgrades, and an ongoing resource adequacy shortfall.
Second, it is built on a unifying design that studies generation and load together, shortens
the process by half, and moves readiness and financial commitments to the front of the
process to promote readiness to build. Third, it preserves the first-ready, first-served
principle from recent interconnection study process reforms (consistent with Order No.
2023)304 and adds greater transparency and cost certainty. Fourth, its core features track
the directives of the Large Load Show Cause Order.305 The Commission need not find that
PJM’s proposal is the only reasonable approach in order to accept it, only that PJM’s
proposal is a just and reasonable one.306
304 Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC
¶ 61,054, limited order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g & clarification, Order No.
2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134 (2024), aff’d sub nom., Advanced Energy
United v. FERC, 185 F.4th 186 (D.C. Cir. 2026).
305 See Attachment D, Chart Mapping Order Directives to Tariff Changes, at 17-25.
306 Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (“Cities of Bethany”); see ISO New Eng.
Inc., 114 FERC ¶ 61,315, at P 33 & n.35 (2006) (citing Pub. Serv. Co. of N.M. v. FERC, 832 F.2d 1201, 1211
(10th Cir. 1987); Cities of Bethany at 1136); Oxy USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995)
(citing Cities of Bethany at 1136); cf. S. Cal. Edison Co., 73 FERC ¶ 61,219, at 61,608 n.73 (1995) (“Having
found the Plan to be just and reasonable, there is no need to consider in any detail the alternative plans
proposed by the Joint Protesters.” (citing Cities of Bethany at 1136)).
PDF page 64
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 60
60
B.
Core Features of the Fast Energization Process That Enhance the
Current Cycle Process
1.
PJM’s current process provides only some visibility into the
transmission needs created by Large Loads
Under the current planning processes, transmission service for Large Loads is
subsumed within PJM’s RTEP. System reinforcements needed to serve Large Loads are
identified through separate processes, including the Transmission Owners’ processes (e.g.,
Attachment M-3 and Form 715 planning processes) and PJM’s Do No Harm process, and
are “trued up” as load interconnection projects are incorporated into the RTEP.307 PJM’s
proposal provides more visibility into the transmission build-out driven by Large Loads so
that PJM can ensure sufficient transmission capability exists in the timeframe in which a
Large Load plans to come online. Studying transmission service together with generation
interconnection will allow PJM and the Transmission Owners to be more transparent about
the drivers of the reinforcements required to serve Large Loads.308
2.
Resource Adequacy requires getting new generation online faster.
PJM continues to need additional generating capacity to maintain reliable service
for the 67 million people in the PJM Region and to serve new Large Loads. As PJM’s
Five-Year Strategy recognizes, “in today’s environment, reliability is not possible without
resource adequacy.”309 The 2028/2029 Base Residual Auction Report shows that the
shortfall of capacity supply needed to meet demand, plus an adequate reserve margin, has
grown year over year, despite a net increase of 1,294.4 MW of Installed Capacity between
307 Bielak Decl. ¶ 11.
308 Id.
309 Shaping a Power Change: PJM Five-Year Strategy, PJM Interconnection, L.L.C., 1 (Aug. 2026),
https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-
… [https://perma.cc/2RBY-MPLH].
PDF page 65
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 61
61
the 2027/2028 and 2028/2029 auctions. New supply has not kept pace with rapid Large
Load growth.310
Although PJM has 47 GW of generation with signed agreements, many of those
projects are not being built or are slowed by state permitting and supply chain backlogs.
The factor that PJM Planning can influence is the interconnection process.311 Speeding up
that process is therefore the most effective step PJM can take, because faster study results
allow developers to shift their focus to more viable projects and may lessen or remove other
barriers, such as permitting and siting approvals.312
3.
Incremental and parallel fixes are not enough – a singular process
for generation and transmission service requests yields efficiencies.
To facilitate the interconnection of additional generation capacity, PJM has already
adopted the Expedited Interconnection Track, Replacement Generation Interconnection
Service, and the Reliability Resource Initiative. These measures are beneficial but were
designed largely to manage PJM’s transition from the old serial queue process to the Cycle
process, and a significant volume of Generation Interconnection Requests remains.313 PJM
seeks to avoid adding separate parallel processes for provisioning transmission service to
Eligible Load and Large Load, having experienced the complications that parallel
processes can cause. Moreover, Large Loads differ fundamentally from traditional load
growth in size, pace, and concentration, and they are the only major source of load
growth.314 Limiting study of transmission service for Large Loads to a separate process
310 Bielak Decl. ¶ 12.
311 Bielak Decl. ¶ 13.
312 Bielak Decl. ¶ 15.
313 Bielak Decl. ¶ 14.
314 Bielak Decl. ¶ 15.
PDF page 66
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 62
62
from Generation Interconnection Requests would likely lead to a sub-optimal build-out of
the Transmission System that would place unnecessary costs on existing loads.315
Studying new Generation Interconnection Requests and new Large Load
transmission service requests together speeds up interconnection, helps ensure that new
generation is deliverable to new Large Loads, allows the costs of needed transmission
enhancements to be determined efficiently, and allows those costs to be accurately
allocated to the cost causers.316
4.
The Fast Energization Process is a single, unified process that
should be twice as fast as the current process.
PJM proposes to consolidate Generation and Merchant Transmission
Interconnection with Long-Term Firm and Large Load Transmission Service studies into
a singular 12-month process. The process will take half the time of the Cycle process.317
It replaces the three complete System Impact Studies of the current process with an
accelerated screening window, consisting of two turns of system impact analysis and a
single System Impact Study.318 Each turn of the screening window provides planning-level
estimates of the system reinforcements needed for the portfolio of generation projects and
transmission service requests, called “Interconnection Reliability Reinforcements”
(“IRR”).319 Each turn produces a non-binding good-faith estimate of the cost and the time
315 Bielak Decl. ¶ 15.
316 Bielak Decl. ¶ 16.
317 Bielak Decl. ¶¶ 9, 17.
318 Bielak Decl. ¶ 21.
319 Bielak Decl. ¶ 21.
PDF page 67
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 63
63
to construct the needed facilities within 60-90 calendar days.320 Figure 1 illustrates the
new process.
Figure 1: The Fast Energization Process321
The expedited screening window gives developers and customers solution feedback
very early, while the decision points require a demonstration of readiness to proceed.322
5.
Technology and early engagement speed the process.
PJM will use technology to speed up project data review, power flow and dynamic
studies, and agreement drafting. PJM has been vetting Tapestry, an AI-powered
interconnection platform, in its current process and is nearing the point at which it can trust
the platform’s results without parallel human verification.323 PJM is also developing a
suite of automation, including improvements to its modeling platform, analytics platforms
320 Bielak Decl. ¶ 21.
321 Bielak Decl. ¶ 21.
322 Bielak Decl. ¶ 18.
323 Bielak Decl. ¶ 19.
PDF page 68
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 64
64
to turn around grid studies more quickly, and result interpretation and quality assurance
tools to preserve study quality in a shorter period.324
The process also includes Early Application Engagement.325 Between the Soft
Close Date and the Application Deadline, PJM will answer Applicants’ questions, test and
provide feedback on their models, and help them complete their Applications.326 This
engagement should improve the quality of Applications, allow PJM’s post-deadline review
to be quick, reduce disputes over Application review, deficiency notices, and cure efforts,
and produce more Applications for truly viable and ready projects.327 The improvement is
much needed: at present, only five percent of Applications submitted to PJM are correct
and complete when first submitted.328
6.
Study consolidation preserves study rigor
Faster does not mean less rigorous. The System Impact Study is the equivalent of
the Phase III System Impact Study in the current Cycle process.329 PJM will perform load
flow, stability, and short circuit analyses across summer, winter, and light load scenarios
and will ensure that all reliability issues are addressed and that the correct amount of
transmission service has been provisioned.330 Negotiation of service agreements begins
during the System Impact Study Phase, which further reduces the total time needed.331
324 Bielak Decl. ¶¶ 9, 19.
325 Bielak Decl. ¶ 20.
326 Bielak Decl. ¶ 20.
327 Bielak Decl. ¶ 20.
328 Bielak Decl. ¶ 20.
329 Bielak Decl. ¶ 22.
330 Bielak Decl. ¶ 22.
331 Bielak Decl. ¶ 22.
PDF page 69
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 65
65
7.
Readiness requirements are moved to the front of the process.
The Fast Energization Process continues the current Cycle process’s emphasis on
readiness but moves many requirements into the Application rather than spreading them
over three phases. The financial commitments are likewise moved up in time. Eligible
Customers seeking transmission service on behalf of Large Loads must enter into a
Transmission Owner Cost Recovery Agreement to enter the process.332 Project Developers
must submit Readiness Deposits in full with the Application, and those deposits become at
risk at decision points in the Screening Phase.333 Physical changes to projects and load are
not allowed after Application, because they would require changes to the dynamic models
submitted with the Application and the new process leaves no time to revise individual
models and the cluster model. A developer or customer wishing to change its project or
load must withdraw and resubmit in the next Cycle.334
These requirements screen out speculative projects and help ensure that projects
that enter an interconnection-related service agreement are truly ready to start construction,
complete construction and commissioning on a timely basis, and enter service.335 They
also preserve the first-ready, first-served paradigm of the current Cycle process.336
332 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A) (“To initiate an Eligible Customer
for Load Request, an Eligible Customer must provide to Transmission Provider the relevant Transmission
Owner or Electric Distributor authorization for the Eligible Customer for Load Request to be studied in the
relevant Cycle, as well as an executed Cost Recovery Agreement with the relevant Transmission Owner.”).
333 Bielak Decl. ¶ 23.
334 Id.
335 Bielak Decl. ¶ 7.
336 Id. ¶ 17.
PDF page 70
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 66
66
8.
A portfolio approach to system reinforcements provides
transparency and certainty.
The Fast Energization Process moves PJM away from identifying specific upgrades
and tying them to specific projects. PJM instead will analyze upgrades and reinforcements
as enabling the entire Cycle cohort of generation projects and transmission service requests.
The resulting IRRs are optimized for the whole Cycle, which eliminates overlapping or
duplicative upgrades for generation and load. This approach also allows a fractional
amount of generating capacity to become deliverable faster and with greater certainty,
rather than only upon completion of all required Network Upgrades.337
Transparency. The Transmission Owners hold the filing rights for cost allocation
and cost recovery and are addressing those matters in Tariff revisions filed concurrently.
PJM will continue to provide transparency as to required system topology, the drivers of
the need for the IRRs, and their capital costs. Consistent with the Large Load Show Cause
Order, PJM will post this information on pjm.com in a single, accessible, searchable
location.338
Certainty. Because Project Developers will be responsible for a share of the total
cost of the portfolio of IRRs, rather than for specific upgrades, optimization should reduce
both total cost and volatility in a developer’s cost responsibility. If a Project Developer’s
cost responsibility nonetheless rises above the amount determined at Decision Point II, the
Tariff now includes a certainty framework to limit exposure to the increase.339 Figure 2
compares the current and new processes.
337 Bielak Decl. ¶ 24.
338 Bielak Decl. ¶ 25; Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A)(2).
339 Bielak Decl. ¶ 26.
PDF page 71
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 67
67
Figure 2: Current process compared with the Fast Energization Process340
9.
Interim rights allow service to begin sooner.
Because PJM will not tie service to completion of specific “contingent upgrades,”
the final service agreements will include a schedule of interim deliverability for Project
Developers or a schedule of interim withdrawal rights for Eligible Customers, based on the
current Transmission System topology.341 The schedules set a minimum level of injection
or withdrawal rights based on the available studies and anticipated Transmission System
conditions in future years.342 PJM will then annually reassess and update the interim rights
based on updated system conditions (i.e., as raise the MW value if more IRRs are built or
queue projects withdraw).343
340 Bielak Decl. ¶ 26.
341 Bielak Decl. ¶ 27; Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A)(1).
342 Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A)(1).
343 Bielak Decl. ¶ 27.
PDF page 72
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 68
68
C.
The Fast Energization Process Is Consistent with the Large Load Show
Cause Order’s Directives.
In the Large Load Show Cause Order, the Commission preliminarily found that
PJM’s Tariff appears unjust and unreasonable without certain provisions and encouraged
PJM to address those concerns through a section 205 filing.344 The Fast Energization
Process addresses the opportunities as summarized below and discussed in the following
sections.
Large Load Show Cause
Order opportunity
Fast Energization Process feature
Study transmission service
for Eligible Customers on
behalf of large loads clearly
and consistently, within 60-
90 days345
Single Tariff-defined process; two screening turns, each
producing a non-binding good-faith estimate of cost and
construction time within 60-90 calendar days; a single
System Impact Study346
Application
process
with
readiness requirements that
deter
speculative
or
duplicative requests347
Readiness requirements moved to the Application;
Readiness Deposits submitted in full and at risk at
decision points; Cost Recovery Agreement required to
enter; no physical changes after Application; Early
Application Engagement348
Transparency on Network
Upgrade drivers and costs,
posted in a single, accessible,
searchable location349
PJM will post required system topology, the drivers of
need, and capital costs on pjm.com in a single,
searchable location350
Mitigate cost-shifting risk
through a cost
recovery
agreement351
Transmission Owner Cost Recovery Agreement
required of Eligible Customers for Large Load requests;
Transmission Owners are addressing cost allocation and
344 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 3, 38.
345 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 41, 63.
346 Bielak Decl. ¶¶ 17, 21-22; Attachment A-2, Proposed Tariff, Part VIII, Subpart C, section 404.
347 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 59.
348 Bielak Decl. ¶¶ 7, 18, 20, 23; Attachment A-2, Proposed Tariff, Part VIII, section 401-404.
349 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 66-67, 71-76.
350 Bielak Decl. ¶ 25.
351 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 77-84.
PDF page 73
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 69
69
Large Load Show Cause
Order opportunity
Fast Energization Process feature
recovery in their concurrent filing; Readiness Deposits
for Project Developers352
Transmission services
reflecting flexible large
loads353
NITS, Interim NITS, NFCD Transmission Service,
FCD Transmission Service schedules for Eligible
Loads and Large Loads354
Generator interconnection
that accounts for electrically
proximate large load355
Generation and load studied together in one Cycle;
IRRs optimized for the whole cohort; interim
deliverability schedules356
1.
Timely, clear, and consistent study of transmission service for large
loads
One of the Commission’s principal concerns was that PJM’s Tariff lacked
sufficiently clear and consistent provisions on how transmission service to Eligible
Customers on behalf of large loads will be studied. The Commission concluded that a
study process culminating in a report with a non-binding good-faith estimate of the cost
and time to construct needed facilities should take no more than 60-90 calendar days.357
The Fast Energization Process addresses this concern by placing Large Load
transmission service requests in the same defined, Tariff-based process as generation and
long-term firm service. Each screening turn produces a non-binding good-faith estimate
of cost and construction time within 60-90 calendar days, and the System Impact Study
352 Bielak Decl. ¶¶ 23, 25; Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401.
353 Bielak Decl. ¶ 27.
354 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 85-87; Attachment A-1 Proposed Tariff, Part
XI, Subpart A, section 700; Proposed Tariff, Part XI, Subpart B, section 708.
355 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 88-101.
356 Bielak Decl. ¶¶ 6, 10, 16, 24, 27; Attachment A-2, Proposed Tariff, Part VIII, sections 401, 404, 440.
357 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 41, 50-51, 63.
PDF page 74
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 70
70
then confirms that all reliability issues are addressed and that the correct amount of
transmission service is provisioned.358
The Commission also recognized that the Transmission Owners may be primarily
responsible for load studies and stated that it does not seek to alter the allocation of rights
and responsibilities among PJM and the Transmission Owners.359 The Fast Energization
Process is consistent with that statement. It enhances PJM’s own study process, and the
Transmission Owners are submitting their cost allocation and cost recovery revisions
separately, because they hold those filing rights.360
2.
Readiness requirements that deter speculative requests
The Commission expressed concern that the Tariff fails to deter speculative or
duplicative requests and observed that clear study procedures with readiness requirements,
including meaningful milestones and financial commitments, can help ensure that requests
are viable.361 The Fast Energization Process accomplishes this objective. It moves
readiness requirements and financial commitments into the Application,362 requires a
Transmission Owner Cost Recovery Agreement from Eligible Customers seeking service
on behalf of Large Loads to enter the process,363 places Readiness Deposits at risk at
358 Bielak Decl. ¶¶ 10, 21-22.
359 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 52.
360 Bielak Decl. ¶ 25.
361 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 56, 59.
362 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(D)(1)(b).
363 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A).
PDF page 75
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 71
71
decision points,364 and bars physical changes after Application.365 Early Application
Engagement further improves the quality of Applications from the outset.366
3.
Transparency regarding upgrades and their costs
The Commission preliminarily found that cost transparency measures are needed
so that stakeholders, including state regulators, can understand the Network Upgrades, and
their costs, needed to serve large loads.367 It stated that this information should be posted
on PJM’s website in a single location, in an accessible and searchable format.368 PJM will
post the required system topology, the drivers of the need for the IRRs, and their capital
costs on pjm.com in a single, accessible, and searchable location.369 Studying generation
and transmission service together also makes the drivers of reinforcements more visible.370
Further, the Fast Energization Process will result in changes to the Large Load Adjustment
process in PJM’s load forecasting procedures, impacting the number of RTEP projects
needed because of Large Loads that are then cost allocated to ratepayers generally.371
4.
Protection against cost shifting
The Commission was concerned that, absent adequate mechanisms, costs incurred
to serve large loads that do not materialize could be shifted to other transmission customers,
and it preliminarily found that a cost recovery agreement with a minimum contribution and
364 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(2A).
365 Attachment A-2, Proposed Tariff, Part VIII, Subpart B, section 403.
366 Bielak Decl. ¶¶ 18, 20, 23.
367 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 71-76.
368 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 66-67, 71-76.
369 Bielak Decl. ¶ 25.
370 Id. ¶ 11.
371 Bielak Decl. ¶¶ 15, 24.
PDF page 76
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 72
72
financial security appears necessary.372 The Fast Energization Process requires Eligible
Customers seeking service on behalf of Large Loads to enter into a Transmission Owner
Cost Recovery Agreement as a condition of entering the process, and it requires Project
Developers to post Readiness Deposits in full with their Applications.373 Because the
Transmission Owners hold the filing rights for cost allocation and cost recovery, they
address those matters in their concurrent Tariff revisions.374 The portfolio approach and
the certainty framework also reduce the risk of cost swings during the process.375
At its core, the Fast Energization Process’s cost allocation mechanism will address
the cost allocation for incremental system adjustments necessary to meet reliability drivers
and needs of the Process’s transmission service and generation project clusters. There will
no longer be any direct tie between an individual project (generation or transmission
service) and specific “upgrade facilities.”376 Instead, what will be identified in the Fast
Energization Process is the “percentage cost responsibility” based on a proportional impact
method, consistent with Order No. 2023, as to the collective Cycle portfolio. Armed with
this information, states pursuant to their retail rate authority may elect to cost allocate IRR
among particular loads in each of their particular states. PJM’s process therefore offers a
means to “give state public utility commissions and other state regulators the information
necessary to allow them to understand which transmission costs are caused by which
372 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 66, 77-84.
373 Bielak Decl. ¶ 23.
374 Id. ¶ 25.
375 Id. ¶¶ 17, 24, 26.
376 Bielak Decl. ¶ 23.
PDF page 77
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 73
73
transmission customers, so that they can sub-allocate these costs to the appropriate retail
customers.”377
5.
Transmission services that reflect flexible use of the system
The Commission preliminarily found that new transmission services should be
available to reflect the operational reality that some large loads are willing and able to limit
their use of the Transmission System, including an interim service while Network
Upgrades are constructed.378 The Fast Energization Process provides for interim rights in
the final service agreements.379 For interim deliverability, the Transmission Provider will
determine a schedule of the minimum injection and withdrawal limits based on anticipated
Transmission System conditions that will then be reassessed with an annual study.380 PJM
estimates that it can begin provisioning these rights as proposed in 2029 after commencing
Application and study processes later on in 2027.381 These rights will be revised
periodically to increase the minimums as IRRs are completed or projects withdraw.382
6.
Studying generation and transmission service requests to serve
Large Load together leverages technology and innovation.
The Commission recognized that studying new load and new generation together
can present system benefits, speed interconnection, and enable more accurate and cost-
effective transmission solutions, and it asked PJM to consider how its interconnection
377 Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 70.
378 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 85-87.
379 Attachment A-2, Proposed Tariff, Part VIII, Subpart L, section 440(A).
380 Attachment A-2, Proposed Tariff, Part VIII, Subpart L, sections 440(A)(1)-(2).
381 See supra Section III.B.3.
382 Bielak Decl. ¶ 27; Proposed Tariff, Part VIII, Subpart L, section 440(A)(2).
PDF page 78
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 74
74
processes should reflect those benefits.383 The Fast Energization Process is built on that
premise. It studies generation, Merchant Transmission, Long-Term Firm, and Large Load
Transmission Service requests in one Cycle. It optimizes the IRRs for the whole Cycle
and eliminates overlapping or duplicative upgrades for generation and load. PJM identifies
leveraging co-location and electrical proximity as one of the innovations of the process.384
This integrated process will harness synergies in study results that reflect both transmission
service and generation impacts, resulting in potentially lower Network Upgrade and IRR
needs at early stages of the project life cycle.
Because of the unique characteristics of Large Load, it is essential for PJM to study
Generation Interconnection Requests and Large Load Transmission Service requests
together through the Fast Energization Process.385 Large Loads are fundamentally different
than traditional categories of load; they have significantly greater energy and capacity
demands, these demands grow quickly, and the demand Large Loads are more
geographically concentrated than from traditional loads.386 Given these characteristics, the
provision of new transmission service—on a firm basis—to Large Loads generally requires
transmission enhancements or expansions. Large Loads are causing much of the load
growth in the PJM Region and generation development is struggling to keep up,387 which
383 Large Load Show Cause Order, 195 FERC ¶ 61,211, at PP 88-91, 95-101.
384 Bielak Decl. ¶¶ 6, 10, 16, 24.
385 Bielak Decl. ¶ 16.
386 Bielak Decl. ¶ 15; see also PJM’s concurrently-submitted Section 205 filing relating to ride-through, other
operational requirements, and the annual transmission services report and the related exhibits attached
thereto, which is incorporated by reference into this filing.
387 Bielak Decl. ¶¶ 12-13, 15.
PDF page 79
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 75
75
poses unique challenges for the Transmission System.388 PJM’s current approach of
evaluating interconnecting generation and providing transmission service to Large Load
through distinct processes,389 makes it difficult to optimally build out the Transmission
System considering the new challenges posed by Large Load.390
Through the Fast Energization Process, PJM will holistically study the
Transmission System impacts of generation and Large Load and optimize transmission
enhancements that serve both simultaneously.391 The efficiencies from this combined
study process will speed up generation interconnection and ensure that generation is
deliverable to new Large Loads, PJM selects Transmission System upgrades efficiently,
and the causers of Transmission System upgrades pay for the costs.392 Ultimately, this is
a just and reasonable approach for evaluating how the transmission system needs to be
updated to accommodate the transmission service needs of Large Loads in an efficient and
cost effective manner.
7.
PJM’s proposal respects existing commercial arrangements and
provides for a clear transition from the existing process to the Fast
Energization Process.
In the interim period before the Fast Energization Process commences in full,
PJM’s proposed revisions to Tariff, Part VIII, Subpart A, section 401 set forth which
transmission service requests will proceed under the existing planning regime and which
388 See Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 58 (“[I]ntegrating large loads poses specific
challenges to transmission system operation given their size, operational behavior, and unique potential to
impact the transmission system.”).
389 Bielak Decl. ¶¶ 11, 13-14.
390 Bielak Decl. ¶ 15.
391 Bielak Decl. ¶ 16.
392 Bielak Decl. ¶ 16.
PDF page 80
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 76
76
service requests will proceed under the Fast Energization Process.393 This framework
provides transparency to the market as to what must be done, and by when. It respects
existing commercial arrangements and affords a 13-month runway for arrangements in
potential development but not yet finalized. Eligible Customers have more than
13-months’ notice to “complete[] the applicable . . . retail load interconnection study” to
be treated under legacy constructs, or be processed under the new Fast Energization
Process.394
PJM specifically proposes a January 1, 2028 date for “completion” to accommodate
the 2028 load forecast. Setting a January 1, 2028 date ensures that the planning done under
the status quo process is included in Large Load Adjustments submitted to PJM and thus
properly reflected in the load forecast.395 The framework is also just and reasonable
because “completion” is defined in terms of two objective criteria: one technical (retail
load study completion date) and one legal (date of execution of required agreements by all
applicable parties). Thus, under this framework, whether something has been “completed”
is plainly understood, thus offering parties a path and timeline to develop plans.
PJM’s proposal also enhances transparency consistent with the Commission’s
stated goals.396 Those customers seeking transmission service on behalf of Large Loads
must submit (or have others submit on their behalf) the information necessary to populate
the Large Load Registry no later than 30 calendar days after the retail load interconnection
393 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A).
394 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A).
395 Resource Adequacy Planning, PJM Manual 19: Load Forecasting and Analysis, PJM Interconnection,
L.L.C., § 3 (rev. 39, June 30, 2026), https://www.pjm.com/-/media/DotCom/documents/manuals/m19.pdf
[https://perma.cc/4M4A-UD9N]; id. § 3.1 (“The forecast is . . . released prior to each Planning Period,
typically in January.”).
396 See, e.g., Large Load Show Cause Order, 195 FERC ¶ 61,211, at P 76.
PDF page 81
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 77
77
study is deemed “complete.”397 This requirement promotes timely and accurate disclosure
to those parties with access to the Registry of all new Large Load requests prior to even
coming into service. States, PJM, and other relevant stakeholders can inform decisions
based upon these timely data submittals. Further, stakeholders can then follow the study
results for such requests, including the costs eventually allocated to them.
Because of the value in ensuring planning under the existing process is reflected in
the 2028 load forecast, the framework also provides for a streamlined and expedited dispute
resolution framework to drive prompt clarity for Eligible Customers, PJM, and others about
which requests will proceed under the Fast Energization Process.398 If Tariff-established
deadlines and information for initiating Alternative Dispute Resolution and seeking
Commission relief are not honored, or if litigation is timely commenced and resolved, then
Eligible Customers submitting service requests will know that they will proceed under the
Fast Energization Process without delay, which will reduce the risk that the 2028 load
forecast report is delayed.
D.
The New Transmission Services Proposed in Part XI are Just and
Reasonable.
PJM has proposed to implement the three new transmission services as directed by
the Commission. PJM’s proposed implementation of these new services is just and
reasonable. PJM is proposing to make Interim NITS, FCD Transmission Service, and
NFCD Transmission Service available to any Eligible Customer taking service on behalf
397 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A). See also RAA, Schedule
11,B.1 (accepted in PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48, filed on compliance in PJM
Interconnection L.L.C., Thirty-Day Compliance Filing to the Commission’s October 9, 2026 Order on PJM’s
Large Load Definition and Large Load Registry, Docket No. ER26-3515-002 (Nov. 9, 2026).
398 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, section 401(A).
PDF page 82
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 78
78
of an Eligible Load or Large Load.399 Because these services require an Eligible Customer
to be willing and able to limit withdrawals from the Transmission System, PJM has
proposed reasonable terms and conditions specific to these services. To ensure the
reliability of the Transmission System, Eligible Customers taking these services will be
required to meet technical requirements demonstrating their ability to limit their
withdrawals as a condition precedent.400 As part of these technical requirements, Eligible
Customers must have necessary control technologies to limit their withdrawals from the
Transmission System as specified in their Transmission Service Agreement, which may
include protection schemes where appropriate.401 The Transmission Service Agreement
will also specify any necessary operating procedures.402 Eligible Customers will also be
required to demonstrate operational control to comply with instructions to reduce
withdrawals from the system within five minutes when directed to do so.403 Consistent
with the Commission’s directive,404 to the extent an Eligible Customer fails to follow a
Curtailment instruction or the necessary control technologies misoperate, PJM is proposing
a 120-day pause in service after the first instance, and to terminate the relevant
Transmission Service Agreement after the second instance.405 Finally, PJM will be
399 See Attachment A-1, Proposed Tariff, Part XI, Subpart A, section 700; Proposed Tariff, Part XI, Subpart
B, section 708.
400 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 718.
401 Attachment A-1, Proposed Tariff, Part XI, Subpart C, sections 717, 718.1.
402 Attachment A-1, Proposed Tariff, Attachment F-3A, Specifications for Interim Regional NITS, section
5.0; Proposed Tariff, Attachment F-4, Specifications for Contract Demand Transmission Service, section 5.0.
403 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 718.1.
404 Co-Location Order, 195 FERC ¶ 61,209, at PP 515, 519.
405 Attachment A-1, Proposed Tariff, Part XI, Subpart C, section 719.5.
PDF page 83
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 79
79
addressing ride-through requirements for Large Computational Load and other operational
requirements for such loads in a separate filing being submitted today.
E.
PJM’s Proposed Changes to NITS are Just and Reasonable.
Consistent with the Commission’s directives, PJM has proposed just and
reasonable revisions to the terms and conditions for NITS to ensure that Large Load is
appropriately studied for transmission service and accounted for in PJM’s transmission
planning processes.406 PJM is proposing to quantify the current level of NITS being
provided to Large Loads using the Large Load Registry.407 When approving the Large
Load Registry, the Commission recognized that it would “provide PJM with the
information necessary to address the operational impacts of Large Loads on the PJM
transmission system.”408 The proposal will therefore allow PJM to establish a baseline
regarding the current level of NITS being provided to Network Customers serving Large
Loads. PJM would then require an Eligible Customer to submit an application for any
increase above the existing level of NITS for Large Loads.409 To that end, PJM is
proposing to strike the language in Tariff, Part III, section 31.6 that suggests an Application
would not be required for changes reflected in these annual updates.410 Striking this
406 See supra Section III.A.
407 Attachment A-1, Proposed Tariff, Part III, General (“The amount of Regional Network Integration
Transmission Service provisioned to Network Customers for serving Large Loads are at levels specified in
an effective Service Agreement or, if not specified therein, as reflected on the Large Load Registry per the
terms of the Reliability Assurance Agreement, Schedule 11.B.1”).
408 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 48.
409 Attachment A-2, Proposed Tariff, Part VIII, Subpart A, sections 400, Definitions E (defining Eligible
Customer for Load Request as “a request by an Eligible Customer seeking Network Integration Transmission
Service or Transmission Service on behalf of an Eligible Load or Large Load”); Attachment A-2, Proposed
Tariff, Part VIII, Subpart C, sections 404(E).
410 Attachment A-1, Proposed Tariff, Part III, section 31.6.
PDF page 84
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 80
80
language clarifies PJM’s proposal to require Large Loads that seek to grow above existing
service levels to submit an Application to be studied through the Fast Energization Process.
Further, regarding BTMG, the Commission directed PJM to “create a materiality
threshold that allows Network Customers to net from their Network Load up to 50 MW of
load served by using BTMG at a single electrical location.”411 Consistent with that
directive, PJM proposes revisions to Part III, section 34.2 and Schedule 8 of the RAA to
implement the 50 MW netting limit effective December 18, 2025, unless an exemption
applies.412 PJM also proposes three exclusions to the 50 MW netting limit, as directed by
the Commission.
First, the Commission directed PJM establish a transition period of three years for
Network Customers currently using PJM’s existing retail BTMG netting rules.413 PJM
therefore proposes to exempt existing Retail BTMG that was used to serve load as of
December 18, 2025 (i.e., the date of the December Order) from the BTMG netting limit
during a three-year transition period.414
Second, the Commission directed PJM to propose Tariff revisions to grant legacy
treatment to entities with existing contracts for the specific purpose of effectuating a
BTMG arrangement for the current term remaining under the existing contract. 415 PJM
therefore proposes to exempt Retail BTMG owned or contracted for as of December 18,
2025 to continue netting without the limit for the remaining term of the contract
411 Co-Location Order, 195 FERC ¶ 61,209, at P 220.
412 Attachment A-1, Proposed Tariff, Part III, section 34.2; Proposed Tariff, RAA, Schedule 8.
413 December Order, 193 FERC ¶ 61,217, at P 223.
414 Attachment A-1, Proposed Tariff, Part III, section 34.2(C).
415 December Order, 193 FERC ¶ 61,217, at P 224.
PDF page 85
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 81
81
effectuating the BTMG arrangement.416 The Commission approved a three-year transition
period and provisions granting legacy treatment in the Co-Location Order, as applied to
PJM’s previously proposed BTMG netting proposal.417
Third, the Commission directed PJM to include a process to exempt Cogeneration
Facilities from its BTMG netting rules “if they demonstrate that they are integrated with
load such that, when their generating facility trips offline, the load follows.”418 Consistent
with this directive, PJM is proposing to exempt Cogeneration Facilities from its netting
rules, subject to certain requirements to ensure the Cogeneration Facility is integrated with
the retail load it serves such that if the Cogeneration Facility trips offline the retail load
follows,419 including potential audits for compliance with these requirements.420
To be eligible for the existing contractual arrangement or Cogeneration
exemptions, PJM is proposing to require that the Large Load be on the Large Load Registry
and the Retail BTMG be registered to allow PJM to account for the limit for settlement and
billing purposes.421 To that end, PJM is also proposing revisions to RAA, Schedule 8 to
ensure the netting limits are reflected in the Obligation Peak Load calculation.422 Taken
together, these changes enhance PJM visibility into operating Retail BTMG in the region
for planning purposes, while respecting existing commercial arrangements.
416 Attachment A-1, Proposed Tariff, Part III, section 34.2(D).
417 Co-Location Order, 195 FERC ¶ 61,209, at PP 232-33.
418 Co-Location Order, 195 FERC ¶ 61,209, at P 240.
419 Attachment A-1, Proposed Tariff, Part III, sections 34.2(E)(a)-(e).
420 Attachment A-1, Proposed Tariff, Part III, section 34.2(F).
421 Attachment A-1, Proposed Tariff, Part III, sections 34.2(D)-(E).
422 Attachment A-1, Proposed RAA, Schedule 8.
PDF page 86
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 82
82
V.
EFFECTIVE DATE
PJM requests that the Commission accept the proposed revisions in Parts I, III, VI,
VII, IX, XI, Attachment F-3, Attachment F-3A, Attachment F-4, and parts of Part VIII to
the Tariff to become effective March 16, 2027, which is not less than 60 days, nor more
than 120 days, prior to the submission of this filing.423 For those Part VIII revisions
associated with the Fast Energization Process rather than compliance with the Co-Location
Order (for which PJM requests a March 16, 2027 effective date), PJM requests an indefinite
effective date of 12/31/9998, to allow PJM to make those provisions effective when the
current Cycle, Cycle 01, reaches a sufficiently advanced stage so the next Cycle may begin.
That point will be the next Business Day after the close of Decision Point II of Cycle 01,
which PJM anticipates will occur in late November 2027.424 PJM will submit a compliance
filing to provide the Commission with the effective date of Part VIII once that date is
known.
PJM does not believe any waivers of the Commission’s Regulations are needed to
permit its filing to become effective as proposed. In addition, to the extent the Commission
determines that any other waivers are required, PJM respectfully requests the Commission
grant such waivers as are necessary in order that the Tariff and RAA revisions may be
made effective as proposed.
VI.
CONSENT TO SEVERANCE OF ISSUES
PJM consents to the Commission’s exercise of authority to sever the Proposed
Tariff and RAA language, as needed and permitted under the FPA and NRG Power
423 18 C.F.R. § 35.3(a)(1).
424 Planning, PJM Interconnection, L.L.C., Cycle Timeline (Oct. 23, 2026), https://www.pjm.com/planning
[https://perma.cc/J283-5CFS].
PDF page 87
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 83
83
Marketing.425 Under FPA section 205, the Commission is in a “passive and reactive role”
that requires it to accept or reject a utility’s proposed rate scheme.426 The Commission is
prohibited from imposing modifications that “result in an ‘entirely different rate design’
than the utility’s original proposal or the utility's prior rate scheme.”427 However, the
Commission has some authority to propose modifications to a utility’s proposal if the utility
consents to the modifications.428 The Commission has used this authority to sever discrete
portions of a utility’s proposed rate scheme, approving certain portions and rejecting
others.429 By contrast, in NRG Power Marketing, the United States Court of Appeals for
the District of Columbia determined that the Commission improperly modified PJM’s
proposed rate scheme where the Commission’s modifications “went in the opposite
direction” and “followed a ‘completely different strategy’ than PJM’s proposal.”430 In that
circumstance, the Commission’s modifications violated section 205, even with PJM’s
consent, because the Commission proposed an “entirely different rate design” that market
participants did not have adequate notice of or opportunity to comment on.431
If it deems necessary, PJM consents to the Commission exercising authority to
sever each element of the Tariff and RAA revisions proposed herein. PJM’s Proposed
Tariff and RAA revisions are not an integrated package that must be viewed as a whole
425 See NRG Power Mktg., LLC, 862 F.3d 108.
426 Hecate Energy LLC v. FERC, 126 F.4th 660, 667 (D.C. Cir. 2025) (quoting Advanced Energy Mgmt. All.
v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017)).
427 NRG Power Mktg., 862 F.3d at 115 (quoting W. Res., Inc. v. FERC, 9 F.3d 1568, 1578 (D.C. Cir. 1993)).
428 NRG Power Mktg., 862 F.3d at 115-16.
429 See, e.g., PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at PP 13-15; Pub. Serv. Co. of Colo., 94
FERC ¶ 61,135, at PP 28, 56 (2026).
430 NRG Power Mktg., 862 F.3d at 116 (quoting W. Res., Inc., 9 F.3d at 1579).
431 NRG Power Mktg., 862 F.3d at 116 (quoting W. Res., Inc., 9 F.3d at 1578).
PDF page 88
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 84
84
and accepted together;432 instead, each element of PJM’s proposal individually advances
PJM’s overarching objective to comply with the June 2026 Orders and to safely and
reliably integrate Large Loads and Co-Located Loads with the Transmission System.
Therefore, the Commission will not go “in the opposite direction” or deploy “a completely
different strategy” by severing certain elements of PJM’s proposal.433 Stakeholders will
have the opportunity to comment in this proceeding on all individual elements of PJM’s
proposal that could be severed, eliminating any prior notice concerns. Further, through
this pre-emptive grant of authority pursuant to which the Commission may sever each
element of the proposal, stakeholders are on notice of potential changes to the proposal as
filed and will have the opportunity to comment as they feel necessary and appropriate.
Although PJM consents to make each element of the proposed revisions to the
Tariff and RAA severable, PJM has demonstrated that each element of its proposal is just
and reasonable. Notwithstanding PJM’s grant of authority to sever, PJM urges the
Commission to accept all revisions as proposed so that PJM may commence compliance
with the directives of the June 2026 Orders and begin preparations for the Fast Energization
Process as quickly as possible.
VII.
DOCUMENTS ENCLOSED
In addition to this transmittal letter, PJM encloses the following:
1.
Attachment A-1: Marked March 16, 2027 Effective Date Proposed Tariff
Revisions;
432 See PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 15 (refusing to sever certain elements of PJM’s
proposal, despite PJM providing consent to sever, because those elements “represent an integrated package
that must be viewed as a whole”).
433 NRG Power Mktg., 862 F.3d at 116.
PDF page 89
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 85
85
2.
Attachment B-1: Marked Indefinite Effective Date Proposed Tariff
Revisions;
3.
Attachment A-2: Clean March 16, 2027 Effective Date Proposed Tariff
Revisions;
4.
Attachment B-2: Clean Indefinite Effective Date Proposed Tariff
Revisions;
5.
Attachment C:
Declaration of Donald Bielak, P.E.; and
6.
Attachment D:
Chart Mapping Order Directives to Tariff Changes.
VIII. CORRESPONDENCE AND COMMUNICATIONS
Correspondence and communications with respect to this filing should be sent to,
and PJM requests the Secretary to include on the official service list, the following:434
Mark J. Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Norristown, PA 19403-2429
610-666-4707
mark.stanisz@pjm.com
Wendy B. Warren
Ruth M. Porter
Alexander L. Peterson
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
202-393-1200
warren@wrightlaw.com
porter@wrightlaw.com
peterson@wrightlaw.com
Christopher B. Holt
Managing Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd,
Audubon, PA 19403-2429
610-666-2368
christopher.holt@pjm.com
IX.
SERVICE
PJM has served a copy of this filing on all PJM Members and on the affected state
utility regulatory commissions in the PJM Region by posting this filing electronically. In
434 To the extent necessary, PJM requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice
and Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official
service list for this proceeding.
PDF page 90
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 86
86
accordance with the Commission’s regulations,435 PJM will post a copy of this filing to
the Commission filings section on its internet site, https://pjm.com/library/filing-order, and
will send an email on the same date as this filing to all PJM Members and all state utility
regulatory commissions in the PJM Region,436 alerting them that this filing has been made
by PJM and is available by following such link. If the document is not immediately
available by using the referenced link, the document will be available through the
referenced link within 24 hours of the filing.
435 See 18 C.F.R. §§ 35.2(e) & 385.2010(f)(3).
436 PJM already maintains, updates, and regularly uses email lists for all PJM Members and affected state
commissions.
PDF page 91
Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 87
87
X.
CONCLUSION
PJM respectfully requests that the Commission: (i) accept the proposed revisions
to its Tariff and the RAA to effectuate PJM’s new Fast Energization Process to study
generation and load together in a one-year process and offer new transmission services to
Co-Located Load, BTMG, and flexible Large Load; and (ii) deem the Large Load Show
Cause Order’s FPA section 206 aspect closed.
Respectfully submitted,
/s/ Wendy B. Warren
Mark J. Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Norristown, PA 19403-2429
610-666-4707
mark.stanisz@pjm.com
Christopher B. Holt
Managing General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA 19403-2429
610-666-2368
christopher.holt@pjm.com
Wendy B. Warren
Ruth M. Porter
Alexander L. Peterson
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
202-393-1200
warren@wrightlaw.com
porter@wrightlaw.com
peterson@wrightlaw.com
Counsel for PJM Interconnection, L.L.C.
November 16, 2026