PJM files large-load tariff revisions and co-location compliance changes under section 205
PJM files tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-531-000. It proposes a 12-month Fast Energization Process that studies generators and large loads together, three new transmission services for large and co-located loads, a 50 MW limit on netting behind-the-meter generation, and a refiled version of its August 17 co-location compliance changes.
Asks FERC to: Accept the revisions, mostly effective March 16, 2027 with Fast Energization on an indefinite date; allow 60 days for comments, rule within 120 days, and close the section 206 case.
Answers the order. Filed under section 205 to answer the E-7 show cause order for PJM. It also refiles PJM's E-2 co-location compliance changes, replacing the August 17 filing PJM withdrew the same day.
E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Application / study process (P 6(a), p. 7) E-7 PJM: Service for flexible loads (P 85, p. 56) E-7 PJM: Alternative transmission technologies (P 70, p. 70) E-2 PJM: Interim NITS (P 2, p. 3) E-2 PJM: Retail BTMG netting rewritten (P 4, p. 3) E-2 PJM: One of three new co-location services (P 2, p. 3)
Key points
- PJM says this filing and its same-day companions answer the show cause order in full, and asks FERC to close the section 206 proceeding.
PJM has responded fully to the Large Load Show Cause Order and requests that the FPA section 206 aspect of the order be closed PDF p. 6
- Generator interconnection requests and large-load service requests would be studied together in one 12-month process.
which will study together New Service Requests, including Generation Interconnection Requests, and requests from Eligible Customers seeking transmission service on behalf of Eligible Load PDF p. 6
- PJM says the new process should take half the time of today's cycle process.
The process will take half the time of the Cycle process. PDF p. 66
- The first Fast Energization submission window would not open until late November 2027.
the Submission Window for the first Cycle under the Fast Energization Process would open in late November 2027 PDF p. 9
- PJM says full acceptance within ten months is likely needed to use the process for Cycle 02.
The Commission’s full acceptance of this filing within 10 months of the date it is filed would likely be necessary to facilitate implementation in time for Cycle 02. PDF p. 9
- New services, NITS changes and Eligible Load changes would take effect March 16, 2027; the Fast Energization provisions on an indefinite date.
PJM therefore seeks an effective date of March 16, 2027, for certain Tariff revisions in Part VIII relating to Eligible Loads and for the revisions in Part III and the new Part XI PDF p. 9
- PJM withdrew its August 17 co-location compliance filing the same day and refiles revised versions here.
Earlier today, PJM filed a motion to withdraw the August 17 Filing in Docket No. ER26-1479-002 so that it could file replacement revisions in this filing. PDF p. 7
- Customers with retail behind-the-meter generation could net no more than 50 MW of it from their load, as the co-location order directed.
PJM is proposing revisions to Part III, section 34.2 and Schedule 8 of the RAA to implement the 50 MW netting limit. PDF p. 28
- Interim NITS would let large and co-located loads use spare capacity on an interruptible basis.
Interim NITS is a transmission service that allows Eligible Customers serving Eligible Load or Large Load to utilize head room on the system as-available on an interruptible basis PDF p. 38
- PJM's transmission owners file cost allocation, the cost recovery framework and rates for the new services separately.
The PJM Transmission Owners (“Transmission Owners”) are separately filing revisions to Tariff, Parts VIII, IX, and XI PDF p. 5
Topics in the text: Connecting load and generation · Reliability and curtailment · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
TABLE OF CONTENTS
printed heading · Topic match: Connecting load and generation
TABLE OF CONTENTS I.Read this passage
IV. THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES
printed heading
IV.Read this passage
A. The Proposed Fast Energization Process Is Just and Reasonable
printed heading
A.Read this passage
B. Core Features of the Fast Energization Process That Enhance the
printed heading · Topic match: Reliability and curtailment
Incremental and parallel fixes are not enough – a singular process for generation and transmission service requests yields efficiencies...........................................................................61 4.Read this passage
C. The Fast Energization Process Is Consistent with the Large Load
printed heading · Topic match: Cost allocation
Readiness requirements that deter speculative requests ................70 3.Read this passage
D. The New Transmission Services Proposed in Part XI are Just and
printed heading · Topic match: Filing procedure
PJM will require Large Loads (i.e., loads over 50 MW at a single location) to be identified on a registry to set a baseline for the current level of transmission service.12 PJM will then require any new requests for transmission service or requests to increase existing service beyond the baseline…Read this passage
I. INTRODUCTION
printed heading
I.Read this passage
INTRODUCTION
printed heading · Topic match: Reliability and curtailment
PJM proposes to efficiently, reliably, and transparently provide transmission service to both co-located and flexible Large Loads (i.e., Large Loads that are not co-located with generation, but are willing and able to limit their energy withdrawals from the Transmission System under certain…Read this passage
II. BACKGROUND
printed heading
II.Read this passage
BACKGROUND
printed heading · Topic match: Connecting load and generation
December Order On December 18, 2025, the Commission issued an order on show cause finding the Tariff unjust and unreasonable due to, among other reasons, the lack of specificity for the rates, terms, and conditions that apply to Interconnection Customers43 serving Co-Located Load and Eligible…Read this passage
B. Compliance Filings and Paper Hearing Procedure
printed heading · Topic match: Connecting load and generation
ER26-1088-000 pursuant to the December Order (“Thirty-Day Compliance Filing”).50 Among other changes, the Thirty-Day Compliance Filing proposed to clarify that existing services in the Tariff could be used by Project Developers serving Co-Located Load, including Provisional Interconnection Service…Read this passage
C. June 2026 Orders
printed heading · Topic match: Filing procedure
Co-Location Order The Commission issued the Co-Location Order addressing the Sixty-Day Compliance Filing, the paper hearing submissions, and requests for rehearing and clarification of the December Order.62 The Co-Location Order accepted most of PJM’s proposed Tariff changes, but directed PJM to…Read this passage
D. Partial Extension and Partial Compliance Filing
printed heading · Topic match: Filing procedure
Partial Extension and Partial Compliance Filing On July 28, 2026, PJM moved for a 90-day extension of time to meet certain Co- Location Order requirements,77 and it simultaneously requested the Commission to hold the Large Load Show Cause Order proceedings in abeyance for 90 days.78 PJM explained…Read this passage
E. PJM’s Stakeholder Engagement Process
printed heading · Topic match: Connecting load and generation
PJM presented its proposed Large Load Show Cause Order compliance framework85 and discussed the overlap between Large Load, Co-Located Load, and load with BTMG.86 PJM solicited and received stakeholder feedback on its presentation.87 • September 16, 2026, CLLOW: PJM presented its proposed process…Read this passage
III. OVERVIEW OF PROPOSED CHANGES
printed heading
III.Read this passage
A. Part III—NITS
printed heading · Topic match: Registry access
First, the 50 MW limit would not apply for a three-year transition period for existing Retail BTMG that was used to serve load as of December 18, 2025.119 Second, the 50 MW netting limit would not apply to Retail BTMG that was owned, operated and/or contracted for as of December 18, 2025, for the…Read this passage
B. Part VIII—Fast Energization Process
printed heading · Topic match: Connecting load and generation
As part of the effort to streamline for speed, PJM proposes to eliminate Replacement Generation Interconnection Service.153 Replacement Generation Interconnection Service was developed to address the delay in processing Generation Interconnection Requests during the transition from the old, serial…Read this passage
C. Part XI—New Transmission Services
printed heading · Topic match: Connecting load and generation
Reese, Secretary November 16, 2026 Page 36 36 level of service on a firm basis.177 The language concerning performing an updated analysis and updating the relevant internal system updates was added to clarify that the conversion does not happen automatically the moment upgrades are physically…Read this passage
Attachment F-4, which includes operational procedures and necessary control technologies
printed heading · Topic match: Reliability and curtailment
Reese, Secretary November 16, 2026 Page 43 43 and operating the facilities and necessary control technologies and protection systems to take service and ensure that the Eligible Customer limits its withdrawals from the system.220 Those necessary control technologies may include fully redundant…Read this passage
Attachment F-4, the pro forma agreement for Contract Demand Transmission
printed heading
Reese, Secretary November 16, 2026 Page 50 50 planned modification would have a permanent material impact on the Transmission System or would constitute a material modification, Network Customer shall then withdraw the proposed modification or proceed with a new Eligible Customer for Load Request…Read this passage
D. Re-Filing Co-Located Load Compliance Changes
printed heading · Topic match: Connecting load and generation
Reese, Secretary November 16, 2026 Page 53 53 availability of these new services, PJM is proposing to add to the term “Eligible Generating Facility” to the Tariff to encompass both a Co-Located Generating Facility or Retail BTMG.276 In addition, PJM is proposing conforming changes to replace…Read this passage
Attachment A-1, Proposed Tariff, Part VIII, Subpart A, section 401(I). PJM also proposes to cross-reference
printed heading · Topic match: Connecting load and generation
PJM also proposes to cross-reference Tariff, Part VIII, Subpart L, section 439, Provisional Interconnection Service, added in the Thirty-Day Compliance Filing, in Parts VI and VII to clarify that Provisional Interconnection Service is available to Honorable Debbie-Anne A.Read this passage
E. Changes to Be Addressed in Future Filings
printed heading · Topic match: Filing procedure
Finally, depending on the Commission’s rulings or guidance on the cost recovery provisions the Transmission Owners are filing concurrently, PJM will need to add to the Tariff a form of agreement for PJM to hold Project Developers’ post-commercial operation Security, as required to support the…Read this passage
IV. THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES AS
printed heading
THE COMMISSION SHOULD ACCEPT THE PROPOSED CHANGES AS JUST AND REASONABLE.Read this passage
A. The Proposed Fast Energization Process Is Just and Reasonable and
printed heading · Topic match: Reliability and curtailment
First, it is designed to address and promote meaningful improvement in response to real challenges facing the grid: insufficiently fast interconnection processes for load and generation, parallel and duplicative study processes, speculative requests, limited visibility into the drivers of…Read this passage
B. Core Features of the Fast Energization Process That Enhance the
printed heading
Core Features of the Fast Energization Process That Enhance the Current Cycle Process 1.Read this passage
Attachment M-3 and Form 715 planning processes) and PJM’s Do No Harm process, and
printed heading · Topic match: Reliability and curtailment
Incremental and parallel fixes are not enough – a singular process for generation and transmission service requests yields efficiencies.Read this passage
C. The Fast Energization Process Is Consistent with the Large Load Show
printed heading · Topic match: Cost allocation
Reese, Secretary November 16, 2026 Page 77 77 study is deemed “complete.”397 This requirement promotes timely and accurate disclosure to those parties with access to the Registry of all new Large Load requests prior to even coming into service.Read this passage
D. The New Transmission Services Proposed in Part XI are Just and
printed heading · Topic match: Registry access
To ensure the reliability of the Transmission System, Eligible Customers taking these services will be required to meet technical requirements demonstrating their ability to limit their withdrawals as a condition precedent.400 As part of these technical requirements, Eligible Customers must have…Read this passage
E. PJM’s Proposed Changes to NITS are Just and Reasonable.
printed heading · Topic match: Registry access
Further, regarding BTMG, the Commission directed PJM to “create a materiality threshold that allows Network Customers to net from their Network Load up to 50 MW of load served by using BTMG at a single electrical location.”411 Consistent with that directive, PJM proposes revisions to Part III,…Read this passage
V. EFFECTIVE DATE
printed heading
In addition, to the extent the Commission determines that any other waivers are required, PJM respectfully requests the Commission grant such waivers as are necessary in order that the Tariff and RAA revisions may be made effective as proposed.Read this passage
VI. CONSENT TO SEVERANCE OF ISSUES
printed heading
PJM’s Proposed Tariff and RAA revisions are not an integrated package that must be viewed as a whole 425 See NRG Power Mktg., LLC, 862 F.3d 108. 426 Hecate Energy LLC v.Read this passage
VII. DOCUMENTS ENCLOSED
printed heading
DOCUMENTS ENCLOSED In addition to this transmittal letter, PJM encloses the following: 1.Read this passage
Attachment A-1: Marked March 16, 2027 Effective Date Proposed Tariff
printed heading
Attachment A-1: Marked March 16, 2027 Effective Date Proposed Tariff Revisions; 432 See PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at P 15 (refusing to sever certain elements of PJM’s proposal, despite PJM providing consent to sever, because those elements “represent an integrated package that…Read this passage
Attachment B-1: Marked Indefinite Effective Date Proposed Tariff
printed heading
Attachment B-1: Marked Indefinite Effective Date Proposed Tariff Revisions; 3.Read this passage
Attachment A-2: Clean March 16, 2027 Effective Date Proposed Tariff
printed heading
Attachment A-2: Clean March 16, 2027 Effective Date Proposed Tariff Revisions; 4.Read this passage
Attachment B-2: Clean Indefinite Effective Date Proposed Tariff
printed heading
Attachment B-2: Clean Indefinite Effective Date Proposed Tariff Revisions; 5.Read this passage
Attachment C:
printed heading
Attachment C: Declaration of Donald Bielak, P.E.; and 6.Read this passage
Attachment D:
printed heading
Attachment D: Chart Mapping Order Directives to Tariff Changes.Read this passage
VIII. CORRESPONDENCE AND COMMUNICATIONS
printed heading
CORRESPONDENCE AND COMMUNICATIONS Correspondence and communications with respect to this filing should be sent to, and PJM requests the Secretary to include on the official service list, the following:434 Mark J.Read this passage
IX. SERVICE
printed heading
In 434 To the extent necessary, PJM requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official service list for this proceeding.Read this passage
X. CONCLUSION
printed heading
X.Read this passage
CONCLUSION
printed heading · Topic match: Connecting load and generation
CONCLUSION PJM respectfully requests that the Commission: (i) accept the proposed revisions to its Tariff and the RAA to effectuate PJM’s new Fast Energization Process to study generation and load together in a one-year process and offer new transmission services to Co-Located Load, BTMG, and…Read this passage