Answer of Constellation Energy Generation, LLC in response to Transmission Owner's 07/20/2026 Request for Clarification
Read topic-matched comments in EL26-67
Topics in the text: Filing procedure · Connecting load and generation · Credit and exit
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
ANSWER OF CONSTELLATION ENERGY GENERATION, LLC
PDF bookmark · Topic match: Filing procedure
The Commission should accept Constellation’s answer to the Indicated PJM Transmission Owners’ requests for clarification because “[a]nswers to requests for clarifications are not barred by Rule 713 of the Commission’s Rules of Practice and Procedure.” Savion, LLC v.Read this passage Filed comments: Connecting load and generation
CONCLUSION
PDF bookmark
CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission deny the Transmission Owners’ Request for Clarification, but if the Commission nonetheless grants the request, it should make clear that PJM and the Transmission Owners should propose terms that…Read this passage
CERTIFICATE OF SERVICE
PDF bookmark
CERTIFICATE OF SERVICE I hereby certify that I have on this 4th day of August 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §…Read this passage