ER27-517-000 · 2026-11-16 · New York Independent System Operator, Inc.

NYISO files large-load integration procedures and market rules under section 205

NYISO files tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-517-000. They set up Large Load Integration Procedures, two new withdrawal services instead of the three PJM-style services, curtailment of non-firm service when the local price reaches $200/MWh, and a State Exempt Load Project exception for New York's resource adequacy rules. The New York transmission owners filed cost recovery terms separately.

Asks FERC to: Accept without modification, effective from February 1, 2027 to May 1, 2029 by part; keep the show cause case in abeyance, end it for NYISO on acceptance, and allow 28 days for comments.

Answers the order. Filed under section 205 to answer the E-12 show cause order for NYISO. The New York transmission owners and the non-incumbent owners filed their own parts separately the same day.

E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Define ‘large load’ (P 64, p. 41) E-12 NYISO: Timely study window (P 44, p. 31) E-12 NYISO: Proximate-generation service (P 121, p. 72) E-12 NYISO: Alternative transmission technologies (P 68, p. 79) E-12 NYISO: Cost transparency (P 73, p. 47)

Key points

  1. NYISO says the revisions fully answer FERC's concerns within its own filing rights.
    They are intended to fully satisfy the concerns raised by the Commission PDF p. 1
  2. It proposes Firm and Non-Firm Withdrawal Service rather than the three services FERC created for PJM.
    “Firm Withdrawal Service” and “Non-Firm Withdrawal Service” PDF p. 2
  3. NYISO explains why it will not adopt the three PJM co-location services.
    Part V explains why the NYISO is not proposing to adopt the three new transmission services that the Commission established in the PJM Co-Location Order PDF p. 3
  4. Non-firm service would be curtailed when the local price reaches $200 per megawatt-hour.
    establish a rule under which Non-Firm Withdrawal Service would be curtailed when the applicable nodal Locational- Based Marginal Price (“LBMP”) for a Large Load reaches $200 MW/h PDF p. 3
  5. A State Exempt Load Project exception is meant to respect the New York PSC's resource adequacy authority.
    the State Exempt Load Project exception, that is intended to reconcile the NYISO’s reliability responsibilities with the NYPSC’s resource adequacy authority PDF p. 2
  6. The New York transmission owners file a separate two-party cost recovery agreement.
    the NYTOs will submit a new two-party pro forma cost recovery agreement to address the cost- shifting issues discussed in the Show Cause Order PDF p. 3
  7. NYISO asks FERC to keep the show cause case in abeyance and end it for NYISO if the filing is accepted.
    If the Commission accepts this filing it should also issue an order terminating the Show Cause Order proceeding with respect to the NYISO. PDF p. 4
  8. Effective dates run from February 2027 to May 2029.
    the NYISO is requesting a February 1, 2027 effective date for the LLIP-related tariff provisions PDF p. 4
  9. NYISO asks for 28 days for comments instead of 21.
    the NYISO asks that the Commission briefly extend the comment period on this filing from the standard twenty-one days to twenty-eight days PDF p. 4
  10. The filing won the required supermajority of NYISO stakeholders.
    received the super- majority stakeholder approval required under the NYISO’s shared governance model PDF p. 4

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Consistent with the August 14, 2026 letter order (“Abeyance Order”)12 in the Show Cause Order proceeding, the NYISO respectfully requests in Part X below that the Commission hold the Section 206 proceedings initiated by the Show Cause Order in continued abeyance pending action on this filing.
Read this passage

TABLE OF CONTENTS

printed heading

TABLE OF CONTENTS I.
Read this passage

II. The NYISO’s Proposed Tariff Revisions to Establish and Implement Large Load

printed heading · Topic match: Reliability and curtailment

Study of Impacts to New York State Transmission System of an Affected System Eligible Customer’s Proposed Interconnection to Another Region’s Transmission System 69 III.
Read this passage

IV. The NYISO’s Proposed Tariff Revisions to Establish New Market Participation

printed heading

IV.
Read this passage

B. Market Rules Applicable to Full Withdrawal Service and Limited Withdrawal Service

printed heading

B.
Read this passage

V. The NYISO's Proposals Build on the NYISO's Established Transmission Model and

printed heading

V.
Read this passage

A. The NYISO’s Financial Transmission Service Model Enables the NYISO to Maximize

printed heading

A.
Read this passage

B. The NYISO’s Financial Reservation Model Promotes Economic Efficiency in the Use of

printed heading

B.
Read this passage

C. There Is No Need for the NYISO to Adopt the Transmission Services Established by the

printed heading

C.
Read this passage

VI. The NYTOs and the NTOs Are addressing certain show cause order issues in

printed heading · Topic match: Filing procedure

VI.
Read this passage

I. DOCUMENTS SUBMITTED

PDF bookmark

DOCUMENTS SUBMITTED The NYISO submits the following with this filing letter: 1.
Read this passage

II. The NYISO’s Proposed Tariff Revisions to Establish and Implement Large Load Integration Procedures

PDF bookmark

THE NYISO’S PROPOSED TARIFF REVISIONS TO ESTABLISH AND IMPLEMENT LARGE LOAD INTEGRATION PROCEDURES
Read this passage

A. Large Load

PDF bookmark

Large Load In the Show Cause Order, the Commission found that it would be reasonable to define a large load as “a new commercial or industrial customer, located at a single site behind one or more points of interconnection, and that has a peak load of 50 MW or greater and interconnects to the…
Read this passage

B. Proposed New Transmission Services for Large Loads

PDF bookmark · Topic match: Reliability and curtailment

See proposed Services Tariff § 4.1.6. 19 “Firm Withdrawal Service” shall be defined as “Transmission Service offered to a Large Load, or a portion thereof, that does not cause adverse impacts to resource adequacy and/or transmission security.” See proposed OATT Attach.
Read this passage

C. Large Load Integration Procedures

PDF bookmark

Large Load Integration Procedures In the Show Cause Order, the Commission found that, notwithstanding the NYISO’s existing load interconnection requirements, the NYISO’s existing OATT appears to be unjust and unreasonable because it does not include provisions that address with sufficient clarity…
Read this passage

i. Key Elements of the Large Load Integration Procedures

PDF bookmark

Key Elements of the Large Load Integration Procedures
Read this passage

a) Clear and Detailed Procedures

PDF bookmark

a) Clear and Detailed Procedures The NYISO proposes in this filing to establish new Large Load Integration Procedures as described in detail in Parts II.D through III that set forth clear and detailed tariff requirements concerning the application for and the study of the proposed interconnection…
Read this passage

b) Effective Date and Transition Process

PDF bookmark

Reese November 16, 2026 Page 14 The NYISO proposes that the Large Load Integration Procedures have an effective date of February 1, 2027, as described in Parts II.D.ii and IX.
Read this passage

c) Timeframe of Large Load Integration Procedures

PDF bookmark · Topic match: Reliability and curtailment

These responsibilities include performing preliminary analyses and assessing the feasibility of proposed interconnections, studying the proposed interconnection of the Group of projects participating in the study, including their impacts on the resource adequacy and transmission security of the…
Read this passage

d) Role of Transmission Owners

PDF bookmark

d) Role of Transmission Owners The NYISO proposes to allocate the scope of responsibilities in the Large Load Integration Procedures between itself and the Transmission Owners as detailed in this filing letter.
Read this passage

e) Assessment of Reliability Impacts and Determinations of Withdrawal Service

PDF bookmark · Topic match: Reliability and curtailment

e) Assessment of Reliability Impacts and Determinations of Withdrawal Service The NYISO proposes that the interconnection of Large Loads must not adversely impact resource adequacy or transmission security.
Read this passage

f) State Exempt Large Load Projects

PDF bookmark · Topic match: Reliability and curtailment

f) State Exempt Large Load Projects After considering comments expressed by the New York State Department of Public Service (“NYDPS”) staff during the stakeholder process, the NYISO is proposing tariff language under which it would not include Large Load Projects identified by the NYDPS in the…
Read this passage

g) Application Process and Readiness Requirements

PDF bookmark

g) Application Process and Readiness Requirements The NYISO proposes to establish in Attachment LL detailed application requirements for a Large Load Project to participate in and advance through the Large Load Integration Study Process.
Read this passage

h) Study Process

PDF bookmark · Topic match: Reliability and curtailment

For Large Load Projects that elect to proceed in the study based on the results of the Initial Study Phase, the NYISO proposes to perform an Assessment of Load Integration as described in Part II.I.i that will evaluate the remaining projects applying the Resource Adequacy Impact Standard and…
Read this passage

i) Identification and Cost Allocation of Upgrades

PDF bookmark · Topic match: Cost allocation

i) Identification and Cost Allocation of Upgrades The NYISO proposes that each Large Load Project participating in the Large Load Integration Study Process will be responsible for the costs of the Attachment Facilities and Network Upgrades identified for the safe and reliable interconnection of the…
Read this passage

j) Alternative Transmission Technologies

PDF bookmark

j) Alternative Transmission Technologies As described in Part II.I.ii.b, the NYISO proposes that the Transmission Owner, in identifying Network Upgrades in the Facilities Study, consider whether an alternative transmission technology could reasonably be implemented to address the identified…
Read this passage

k) Transmission Services Agreement

PDF bookmark

k) Transmission Services Agreement As described in Part III.ii, the NYISO proposes to establish requirements for the Eligible Customer and the Large Load Project (if the Large Load Project is not its own Eligible Customer or Load Serving Entity) to enter into a Transmission Service Agreement with…
Read this passage

l) Operational Requirements

PDF bookmark

l) Operational Requirements As described in Part III.iii, the NYISO proposes to establish performance, protection and control, and operating requirements for Large Load Projects.
Read this passage

m) Adoption of Requirements from Standard Interconnection Procedures

PDF bookmark · Topic match: Cost allocation

In addition, the NYISO proposes to use the same or similar requirements as those included in its Standard Interconnection Procedures or elsewhere in its tariffs for study cost allocation, invoicing and payment requirements, confidentiality, dispute resolution, and other standard administrative…
Read this passage

ii. Overview of Large Load Integration Procedures

PDF bookmark · Topic match: Reliability and curtailment

To proceed with its Large Load Project, the Eligible Customer must accept its cost allocation for Attachment Facilities and Network Upgrades required for its project and post related security to the applicable Transmission Owner(s).
Read this passage

D. Scope and Effective Date of Large Load Integration Procedures

PDF bookmark

Scope and Effective Date of Large Load Integration Procedures
Read this passage

i. Application of Large Load Integration Procedures

PDF bookmark

In addition, the NYISO proposes that the procedures not apply to a 40 Proposed OATT Attach.
Read this passage

ii. Effective Date of Large Load Integration Procedures and Transition Requirements

PDF bookmark · Topic match: Connecting load and generation

Reese November 16, 2026 Page 23 minimizing disruptions to existing projects that have already completed or progressed to certain defined milestones in the NYISO’s existing load interconnection process.51 First, the NYISO proposes to retain the Queue Position of a load project in its Queue that, as…
Read this passage

iii. Pre-Application Reports

PDF bookmark

Pre-Application Reports The NYISO proposes to establish a process in the Large Load Integration Procedures by which an entity may request a Pre-Application Report for information regarding the proposed interconnection of a load project consistent with the definition of Large Load at a particular…
Read this passage

E. Large Load Integration Study Process Start Date and Timeframe

PDF bookmark

Large Load Integration Study Process Start Date and Timeframe
Read this passage

i. Large Load Integration Study Process Start Date

PDF bookmark · Topic match: Cost allocation

Large Load Integration Study Process Start Date The NYISO proposes to commence the Transition Large Load Integration Study Process, which is applicable to participants in Transition Group B, on June 1, 2027.78 The NYISO proposes to then commence the first regular Large Load Integration Study…
Read this passage

ii. Large Load Integration Study Process Timeframe and Process Overlap

PDF bookmark

Large Load Integration Study Process Timeframe and Process Overlap The NYISO proposes a timeframe of between approximately one year and six months and two years for the performance of the Large Load Integration Study Process cycle, which includes a 90-day time period to perform the System Impact…
Read this passage

F. Large Load Integration Request

PDF bookmark

Reese November 16, 2026 Page 29 Customers’ applications for transmission service on behalf of large loads on a rolling basis, (2) a non-refundable application fee, and sufficient readiness requirements that escalate at distinct phases of the study process to deter duplicative or speculative…
Read this passage

i. Application Process and Timeframe Requirements for Submission of Large Load Integration Request

PDF bookmark

Application Process and Timeframe Requirements for Submission of Large Load Integration Request The NYISO proposes to require that an Eligible Customer submit a Large Load Integration Request and satisfy additional entry requirements for a Large Load Project to enter a Large Load Integration Study…
Read this passage

ii. Submission Requirements for Large Load Integration Requests

PDF bookmark

Submission Requirements for Large Load Integration Requests The NYISO proposes that an Eligible Customer be required to submit the following information and data, fees, and deposits for purposes of entering the Large Load Integration Study Process.
Read this passage

a) Request Form

PDF bookmark

The NYISO’s proposed approach is consistent with its restriction of the submission of mutually exclusive Interconnection Requests in its Standard Interconnection Procedures.
Read this passage

b) Application Fee

PDF bookmark

Reese November 16, 2026 Page 31 The Eligible Customer must submit a non-refundable Application Fee in cash in the amount of $10,000 to account for expenses incurred in assessing the Large Load Integration Request.100 As described in the Nguyen Affidavit, the proposed Application Fee aligns with the…
Read this passage

c) Study Deposit

PDF bookmark

c) Study Deposit The Eligible Customer must submit certain Study Deposits for the Large Load Integration Study Process.
Read this passage

d) Readiness Requirements/ Site Control

PDF bookmark · Topic match: Cost allocation

As described in the Nguyen Affidavit, an Eligible Customer’s satisfaction of these requirements provides reasonable evidence of meaningful progress and financial commitment in the development of the Large Load Project.109 For purposes of the Site Control requirements, the NYISO proposes to define…
Read this passage

e) Additional Submission Requirements

PDF bookmark

e) Additional Submission Requirements The Eligible Customer must indicate whether it will be using an Associated Resource as further described in Part II.G.i.a.112 If so, the Eligible Customer must submit to the NYISO an Associated Resource Attestation Form in the form set forth in Appendix 7 to…
Read this passage

iii. Review and Validation of Large Load Integration Requests

PDF bookmark

Review and Validation of Large Load Integration Requests The NYISO proposes to establish requirements for the review and validation of Large Load Integration Requests.
Read this passage

iv. Study Agreement

PDF bookmark

Study Agreement The NYISO proposes to require the Eligible Customer to enter into a study agreement – the Large Load Integration Study Agreement – for the Large Load Integration Study Process with the NYISO, the Connecting Transmission Owner, and any identified Affected Transmission Owner(s) or…
Read this passage

v. Queue Position

PDF bookmark · Topic match: Connecting load and generation

Reese November 16, 2026 Page 36 The NYISO proposes to establish a Load Queue for projects participating in the Large Load Integration Study Process.133 The NYISO will assign a Load Queue Position for a Large Load Integration Request based upon the date and time of the NYISO’s receipt of the…
Read this passage

vi. Modifications

PDF bookmark

Modifications The NYISO proposes to establish requirements in the Large Load Integration Procedures for an Eligible Customer to request that the NYISO evaluate whether the Eligible Customer’s proposed modification to its existing load interconnected to or proposing to interconnect to the New York…
Read this passage

a) Modification Review Process

PDF bookmark · Topic match: Connecting load and generation

To request a modification, an Eligible Customer must submit to the NYISO: (i) a Load Modification Request in the form of Appendix 3 to this 133 Id. § 44.1 (definition of Load Queue). 134 Id. §§ 44.1 (definition of Load Queue Position), 44.7.1.1. 135 Proposed OATT Attach.
Read this passage

b) Modifications During Large Load Integration Study Process

PDF bookmark

The proposed modification must be accompanied by any resulting updates to the models included in such requests to the extent required in the Load Modification Request.
Read this passage

c) Material Modifications

PDF bookmark

c) Material Modifications Notwithstanding the modification review process, the NYISO proposes that the following modifications will be considered a Material Modification and require the submission of a Large Load Integration Request under the Large Load Integration Procedures.152 First, the NYISO…
Read this passage

vii. Withdrawal

PDF bookmark · Topic match: Connecting load and generation

If the Eligible Customer disputes the withdrawal and loss of its Load Queue Position, then during Dispute Resolution, the Eligible Customer’s Large Load Integration Request is eliminated from the Load Queue until such time that the outcome of Dispute Resolution would restore its Load Queue Position.
Read this passage

G. Assessment of Reliability Impacts and Determination of Withdrawal Service

PDF bookmark

Assessment of Reliability Impacts and Determination of Withdrawal Service
Read this passage

i. Determination of Withdrawal Service

PDF bookmark · Topic match: Reliability and curtailment

Determination of Withdrawal Service The NYISO proposes to determine the amounts of Firm Withdrawal Service and Non- Firm Withdrawal Service for each Large Load Project and, if requested, to determine eligibility to be classified as Zero Withdrawal Service Load, based on both the resource adequacy…
Read this passage

a) Addressing Adverse Impacts Under Resource Adequacy Impact Standard

PDF bookmark · Topic match: Reliability and curtailment

For a Resource to be eligible to be an Associated Resource, the Resource: (i) must complete the interconnection study process and obtain sufficient Capacity Resource Interconnection Service rights, except if the Partner Resource is a Demand Side Resource, (ii) must be a proposed project that does…
Read this passage

b) Addressing Violations Under Transmission Security Standard

PDF bookmark

Reese November 16, 2026 Page 43 Yes (without proceeding with Network Upgrades required for Firm Service)* Non-Firm Yes (with Network Upgrades required for Firm Service)* Firm (once Network Upgrades enter service) * The Large Load Project must proceed with the construction of those Network Upgrades…
Read this passage

c) Withdrawal Service Based on Results Under Both Resource Adequacy Impact Standard and Transmission Security Standard

PDF bookmark · Topic match: Reliability and curtailment

c) Withdrawal Service Based on Results Under Both Resource Adequacy Impact Standard and Transmission Security Standard The NYISO’s final determination concerning Withdrawal Service will be based on both the results of the analyses using the Resource Adequacy Impact Standard and the Transmission…
Read this passage

d) LIPA Exception Regarding Non-Firm Withdrawal Service

PDF bookmark

d) LIPA Exception Regarding Non-Firm Withdrawal Service The NYISO proposes to include in its Withdrawal Service requirements, to the extent accepted by the Commission, the following exception requested by the Long Island Power Authority concerning the application of Non-Firm Withdrawal Service for…
Read this passage

ii. Resource Adequacy Impact Standard

PDF bookmark · Topic match: Reliability and curtailment

Resource Adequacy Impact Standard The NYISO proposes to establish a Resource Adequacy Impact Standard to evaluate the impact of each Large Load Project on the resource adequacy of the New York Control Area using probabilistic evaluations consistent with the Applicable Reliability Requirements,…
Read this passage

a) Resource Adequacy Impact Standard Except for State Exempt Large Load Projects

PDF bookmark · Topic match: Reliability and curtailment

The NYISO proposes to apply the Resource Adequacy Impact Standard in the following manner to determine the amount of Non-Firm Withdrawal Service and Firm Withdrawal Service that the Large Load Project is eligible for based on resource adequacy impacts to the New York Control Area.186 The NYISO will…
Read this passage

b) Resource Adequacy Impact Standard for State Exempt Large Load Projects

PDF bookmark · Topic match: Reliability and curtailment

If the collective impact of the State Exempt Large Load Projects within a Group does not violate the resource adequacy criterion contained in the NYSRC Reliability Rules for years 1 through 5 of the study, then those projects will be eligible for Firm Withdrawal Service in their full requested…
Read this passage

c) The State Exempt Large Load Projects Proposal Is Consistent with Cooperative Federalism

PDF bookmark · Topic match: Reliability and curtailment

c) The State Exempt Large Load Projects Proposal Is Consistent with Cooperative Federalism The NYPSC stated in the Show Cause Order proceeding that the FPA gives it the primary role in ensuring the adequacy of generation resources in New York, and that it intends to exercise its authority with…
Read this passage

iii. Transmission Security Standard

PDF bookmark · Topic match: Reliability and curtailment

Transmission Security Standard The NYISO proposes to establish a Transmission Security Standard to evaluate the impact of each Large Load Project on the transmission security of the New York Control Area as described below and in the Nguyen Affidavit.211 The NYISO proposes that the Transmission…
Read this passage

H. Initial Study Phase

PDF bookmark

Initial Study Phase 217 Id. § 44.8.2.3. 218 Id. § 44.8.2.4.1. 219 Proposed OATT Attach.
Read this passage

i. Overview of New Study Process

PDF bookmark

In particular, the NYISO proposes an Initial Study Phase as described in this Part II.H in which the NYISO and Transmission Owners will perform certain initial analyses of the proposed interconnection and a System Impact Study.
Read this passage

ii. Initial Study Phase Overview

PDF bookmark · Topic match: Reliability and curtailment

For Initial Study Round 1, the Resource Adequacy and Modeling Period and the System Impact Study will be performed for the Large Load Projects in Group 1, and for Initial Study Round 2, the Resource Adequacy and Modeling Period and the System Impact Study will be performed for the Large Load…
Read this passage

iii. Resource Adequacy and Modeling Period

PDF bookmark · Topic match: Reliability and curtailment

Reese November 16, 2026 Page 53 The NYISO proposes that the Resource Adequacy and Modeling Period consist of the following three components: (i) the RAMP Part 1 Process as described in Part II.H.iv, (ii) the SIS Entry Decision Period as described in Part II.H.v, and (iii) the RAMP Part 2 Process as…
Read this passage

iv. RAMP Part 1 Process

PDF bookmark · Topic match: Reliability and curtailment

RAMP Part 1 Process The NYISO proposes that the RAMP Part 1 Process include the following elements to develop information for the System Impact Study and provide the Eligible Customer with initial information concerning its proposed interconnection.245 In particular, the NYISO will develop the base…
Read this passage

a) Transmission Owner Responsibilities in the RAMP Part 1 Process

PDF bookmark · Topic match: Reliability and curtailment

a) Transmission Owner Responsibilities in the RAMP Part 1 Process The NYISO proposes to establish a Physical Infeasibility Screening in the Large Load Integration Study Process by which the Connecting Transmission Owner and any Affected Transmission Owner will review the proposed interconnection of…
Read this passage

b) NYISO Responsibilities in RAMP Part 1 Process

PDF bookmark · Topic match: Reliability and curtailment

The NYISO will also conduct a Resource Adequacy Evaluation of each Large Load Project to evaluate the adverse impact of the interconnection of the Large Load Project and any Associated Resource identified in the Large Load Integration Request for the project on the resource adequacy of the New York…
Read this passage

v. SIS Entry Decision Period

PDF bookmark

SIS Entry Decision Period The NYISO proposes to establish an SIS Entry Decision Period in which an Eligible Customer may assess the information determined in the RAMP Part 1 Process and elect whether its Large Load Project will proceed to be evaluated in a System Impact Study or be withdrawn from…
Read this passage

vi. RAMP Part 2 Process

PDF bookmark · Topic match: Connecting load and generation

RAMP Part 2 Process The NYISO proposes to establish a RAMP Part 2 Process prior to the System Impact Study to update materials based on the results of the SIS Entry Decision Period and to meet with the projects that elected to proceed to the System Impact Study.267 The scheduled duration of the…
Read this passage

vii. System Impact Study

PDF bookmark

System Impact Study The NYISO proposes to perform, in coordination with Connecting Transmission Owner(s) and Affected Transmission Owner(s), a System Impact Study for the Group of Large Load Projects for that Large Load Integration Study Process that satisfied the requirements in the SIS Entry…
Read this passage

a) Performance of System Impact Study

PDF bookmark

a) Performance of System Impact Study The NYISO proposes that the System Impact Study be performed on a combined basis for the Group of Large Load Projects that satisfied the requirements to proceed to the study.279 The performance of the System Impact Study will be divided between the NYISO and…
Read this passage

b) Review of System Impact Study Report

PDF bookmark

b) Review of System Impact Study Report The NYISO proposes that it will provide, in coordination with the Connecting Transmission Owner(s) and Affected Transmission Owner(s), the draft System Impact Study Report to the Eligible Customer(s) which Large Load Project(s) are in the Group studied in the…
Read this passage

viii. ALI Entry Decision Period

PDF bookmark · Topic match: Reliability and curtailment

The ALI Entry Decision Period for Group 1 may commence as soon as practicable but no sooner than the completion of the Facilities Study conducted by the Transmission Owner(s) for the previous cycle (i) if there are no validated Large Load Integration Requests seeking to participate in Group 2…
Read this passage

i. Assessment of Load Integration

PDF bookmark · Topic match: Connecting load and generation

The Eligible Customer must submit to the NYISO any requested change to the Point of Interconnection through a Load Modification Request.
Read this passage

a) Base Case for Assessment of Load Integration

PDF bookmark · Topic match: Reliability and curtailment

a) Base Case for Assessment of Load Integration The NYISO proposes to use for the base cases of the Assessment of Load Integration, as applicable, the base cases described in Parts II.G.ii and II.G.iii above for the performance of the Resource Adequacy Impact Standard and Transmission Security…
Read this passage

b) ALI Part 1 Study

PDF bookmark · Topic match: Cost allocation

b) ALI Part 1 Study The NYISO proposes for the ALI Part 1 Study that it will evaluate the impact on the Bulk Electric System of the proposed interconnection of the Large Load Projects that satisfied the requirements to enter the Assessment of Load Integration.321 For this evaluation, the NYISO will…
Read this passage

c) ALI Part 2 Study

PDF bookmark

c) ALI Part 2 Study For the ALI Part 2 Study, the NYISO will review and confirm that the Non-Local Network Upgrades designed by Transmission Owners in the Facilities Studies resolve the violation(s) identified in the ALI Part 1 Study and do not result in new violations.330 If a Transmission Owner…
Read this passage

ii. Facilities Study

PDF bookmark

Reese November 16, 2026 Page 64 The NYISO proposes that the Facilities Studies for a Large Load Project be performed, as applicable, by the Connecting Transmission Owner to which system the project proposes to interconnect and any Affected Transmission Owner which system is impacted by the…
Read this passage

a) Performance of Facilities Study

PDF bookmark

a) Performance of Facilities Study The Connecting Transmission Owner will coordinate with any Affected Transmission Owners and Affected System Operators concerning the performance of the Facilities Studies.338 The applicable Transmission Owner may group Large Load Projects as appropriate for the…
Read this passage

b) Consideration of Alternative Transmission Technologies

PDF bookmark

b) Consideration of Alternative Transmission Technologies In the Show Cause Order, the Commission directed the NYISO to propose tariff revisions to require (1) the evaluation of alternative transmission technologies as potential solutions to accommodate an Eligible Customer’s request for…
Read this passage

c) Completion of Facilities Study

PDF bookmark · Topic match: Cost allocation

Reese November 16, 2026 Page 67 whether the Eligible Customer for the Large Load Project accepted its cost allocation for any Network Upgrades and posted the related security.354
Read this passage

iii. Conclusion of Large Load Integration Study Process

PDF bookmark

Conclusion of Large Load Integration Study Process In the Show Cause Order, the Commission indicated that the NYISO’s current tariff appears unjust and unreasonable because it does not require the provision of data on NYISO’s website in a single location and in an easily accessible format that is…
Read this passage

J. Affected Systems

PDF bookmark

Affected Systems The NYISO proposes tariff revisions in Attachment LL to address how Affected System impacts of load interconnections will be assessed within the New York Control Area and how the NYISO will coordinate with neighboring regions – External Affected Systems – concerning the impacts of…
Read this passage

i. Coordination with Affected Systems within the New York Control Area

PDF bookmark

Coordination with Affected Systems within the New York Control Area The NYISO proposes to coordinate the conduct of any studies required to determine the impact of the Large Load Integration Request on Affected Systems within the New York Control 354 Id. § 44.12.1.9. 355 Show Cause Order at P 82.…
Read this passage

ii. Coordination with External Affected Systems

PDF bookmark

Coordination with External Affected Systems The NYISO proposes to establish requirements concerning how it will coordinate with its neighboring regions – External Affected Systems – concerning the coordination and study of the impacts of load projects proposing to interconnect in New York or in a…
Read this passage

iii. Study of Impacts to New York State Transmission System of an Affected System Eligible Customer’s Proposed Interconnection to Another Region’s Transmission System

PDF bookmark

Study of Impacts to New York State Transmission System of an Affected System Eligible Customer’s Proposed Interconnection to Another Region’s Transmission System The NYISO proposes to establish its responsibilities when it receives notification that a customer in another region – an Affected System…
Read this passage

a) Response to Notification

PDF bookmark

a) Response to Notification When the NYISO receives initial notification based on the applicable interconnection study or restudy in another region that an Affected System Eligible Customer’s proposed interconnection of a load project to another region’s transmission system may impact the New York…
Read this passage

b) Affected System Load Queue Position

PDF bookmark · Topic match: Connecting load and generation

Reese November 16, 2026 Page 70 The NYISO proposes to assign an Affected System Load Queue Position to Affected System Eligible Customer(s) that require(s) an Affected System Load Study.374 The Affected System Load Queue Position will be assigned based upon the date of execution of the Affected…
Read this passage

c) Affected System Load Study Agreement

PDF bookmark · Topic match: Connecting load and generation

c) Affected System Load Study Agreement The NYISO proposes to provide to Affected System Eligible Customer(s) an Affected System Load Study Agreement or a Multiparty Affected System Load Study Agreement, as applicable, within 10 Business Days of the NYISO sharing the schedule for the Affected…
Read this passage

d) Scope of Affected System Load Study

PDF bookmark

d) Scope of Affected System Load Study For the Affected System Load Study, the NYISO proposes to use the most recent of the base case of the latest in time Assessment of Load Integration or Short-Term Reliability Process that is available at the time of the commencement of the Affected System Load…
Read this passage

e) Evaluation of Affected System Network Upgrades

PDF bookmark · Topic match: Cost allocation

The Affected System Network Upgrades may proceed directly to be evaluated in the Facilities Study in the Transmission Interconnection Procedures.400 The Affected System Eligible Customer must satisfy the requirements in Attachment P of the ISO OATT concerning the Affected System Network Upgrades,…
Read this passage

III. Post-Study Requirements

PDF bookmark

III.
Read this passage

i. Post-Study Agreements

PDF bookmark

Reese November 16, 2026 Page 73 The NYISO proposes that following the completion of the Facilities Study the Eligible Customer for the Large Load Project may elect to continue with the proposed interconnection of its Large Load Project by (i) entering into an interconnection agreement with the…
Read this passage

ii. Transmission Service Agreement for Firm and Non-Firm Withdrawal Service for Large Loads

PDF bookmark

Transmission Service Agreement for Firm and Non-Firm Withdrawal Service for Large Loads In the Show Cause Order, the Commission preliminarily found the NYISO’s tariff to be unjust and unreasonable because it lacks pro forma provisions in a transmission service agreement between NYISO and the…
Read this passage

a) Process for Entering into Transmission Service Agreement

PDF bookmark

a) Process for Entering into Transmission Service Agreement The NYISO proposes to require the Eligible Customer and the Large Load (if the Large Load is not its own Eligible Customer or Load Serving Entity) to enter into a Transmission Service Agreement with the NYISO.406 The NYISO will offer the…
Read this passage

b) Pro Forma Transmission Service Agreement

PDF bookmark · Topic match: Reliability and curtailment

b) Pro Forma Transmission Service Agreement The NYISO proposes to establish a new, pro forma Transmission Service Agreement for Large Loads obtaining Firm Withdrawal Service or Non-Firm Withdrawal Service.
Read this passage

iii. Large Load Performance, Protection and Control, and Monitoring Requirements

PDF bookmark

The NYISO proposes to define Applicable Reliability Standards for Attachment LL as “the requirements and guidelines of the Applicable Reliability Councils, and the Transmission District to which the Large Load is directly interconnected, as those requirements and guidelines are amended and modified…
Read this passage

iv. Status of Large Load Project and Associated Network Upgrades

PDF bookmark

The NYISO proposes to define Computational Large Load as “a Large Load Project that primarily consists of information technology infrastructure used for: (i) creating, executing, and delivering software applications and services, (ii) artificial intelligence training, development, and delivery,…
Read this passage

B. Additional Requirements

PDF bookmark

B.
Read this passage

i. Study Cost Allocation, Invoicing, and Deposit Requirements

PDF bookmark · Topic match: Cost allocation

Study Cost Allocation, Invoicing, and Deposit Requirements The NYISO proposes to establish tariff requirements that describe the Eligible Customer’s cost responsibilities for the study work in the Large Load Integration Procedures, the invoicing and payment requirements for these study costs, and…
Read this passage

a) Study Cost Responsibility and Allocation of Study Costs

PDF bookmark · Topic match: Cost allocation

a) Study Cost Responsibility and Allocation of Study Costs The NYISO proposes that it will charge, and the Eligible Customer will pay, the actual costs of the study work incurred by the NYISO and Transmission Owner for the Large Load Integration Study Process, after the Eligible Customer has…
Read this passage

b) Invoicing and Payment Requirements

PDF bookmark

b) Invoicing and Payment Requirements The NYISO proposes to invoice an Eligible Customer on a monthly basis for study costs.443 A monthly invoicing approach is consistent with how the NYISO invoices customers in its other interconnection process and provides transparency to customers of their study…
Read this passage

c) Requirements Applicable to Fees and Deposits

PDF bookmark · Topic match: Credit and exit

c) Requirements Applicable to Fees and Deposits The NYISO proposes to permit entities to provide their required deposits (e.g., Study Deposits, Readiness Deposits) for the Large Load Integration Study Process in the form of cash, a letter of credit, or a surety bond, while they must satisfy any…
Read this passage

ii. Confidentiality Requirements

PDF bookmark · Topic match: Registry access

Confidentiality Requirements The NYISO proposes to include in its Large Load Integration Procedures requirements concerning the treatment of Confidential Information exchanged by the parties during the administration of the procedures.456 In particular, the NYISO proposes to use the same 450…
Read this passage

iii. Dispute Resolution Requirements

PDF bookmark

Dispute Resolution Requirements The NYISO proposes to establish that a party may address a dispute that arises out of or in connection with the Large Load Integration Procedures or their performance in accordance with its standard dispute resolution procedures set forth in Article 11 of the NYISO’s…
Read this passage

iv. Third Party Conducting Studies

PDF bookmark

Third Party Conducting Studies The NYISO proposes to establish requirements for the use of third parties to conduct study work under the Large Load Integration Procedures that is generally consistent with the similar requirements for its Standard Interconnection Procedures.461 In particular, the…
Read this passage

v. Additional Requirements

PDF bookmark

Additional Requirements The NYISO proposes to include in the Large Load Integration Procedures certain process requirements concerning data requirements, limitations of liability, and reserved rights that are based on related requirements in its Standard Interconnection Procedures in Attachment HH…
Read this passage

IV. The NYISO’s Proposed Tariff Revisions to Establish New Market Participation Provisions Applicable to Large Loads

PDF bookmark

THE NYISO’S PROPOSED TARIFF REVISIONS TO ESTABLISH NEW MARKET PARTICIPATION PROVISIONS APPLICABLE TO LARGE LOADS
Read this passage

A. Overview of Key Market Design Elements

PDF bookmark · Topic match: Connecting load and generation

The parties must treat Confidential Information in accordance with the confidentiality requirements for the Large Load Integration Procedures, and the NYISO and Connecting Transmission Owner may require that Eligible Customers and password-protected website users sign a non-disclosure agreement…
Read this passage

B. Market Rules Applicable to Full Withdrawal Service and Limited Withdrawal Service Loads

PDF bookmark

Market Rules Applicable to Full Withdrawal Service and Limited Withdrawal Service Loads 484 See Services Tariff § 2.3. 485 See proposed Services Tariff § 4.2.1.9.1; see also id. §§ 4.4.1.1, 4.4.1.2, 4.4.2.1. 486 See proposed Services Tariff § 21.4.7. 487 “Gross Load” shall be defined at the actual…
Read this passage

i. Firm Withdrawal Service Loads

PDF bookmark

Firm Withdrawal Service Loads Large Loads that are eligible to receive Firm Withdrawal Service for their full amount of Load are fully represented in the Load forecasts that inform the IRM, LCRs, and ultimately ICAP auction outcomes, and submit traditional Load bids according to existing Load…
Read this passage

ii. Limited Withdrawal Service Loads

PDF bookmark

Limited Withdrawal Service Loads “Limited Withdrawal Service Loads” are Large Loads that are taking some amount of Non-Firm Withdrawal Service and/or are, in part or in full, a Zero Withdrawal Service Load.
Read this passage

a) Exclusion of Limited Withdrawal Service Large Loads from Capacity Forecasts and Capacity Markets

PDF bookmark · Topic match: Reliability and curtailment

Because Large Loads receiving Non-Firm Withdrawal Service are non-firm customers, it is appropriate that the NYISO is not obliged to redispatch to continue service to them until the curtailment threshold described in Part IV.B.ii.b below is reached.
Read this passage

b) The Non-Firm Bid Cap and Out-of-Merit Requirements for Limited Withdrawal Service Loads

PDF bookmark · Topic match: Reliability and curtailment

In order to effectuate this price cap, and to ensure that Large Loads taking NFWS are responding to the $200/MWh nodal LBMP curtailment threshold in Real-Time as mandated by the terms of their Withdrawal Service, NYISO proposes to model these Loads as negative generation, akin to the way it models…
Read this passage

c) Excluding Limited Withdrawal Service Loads from Participation as Demand Side Resources

PDF bookmark · Topic match: Reliability and curtailment

Non-Firm Withdrawal Service Large Loads, by definition, are not entitled to consume Energy from the system at any time.
Read this passage

d) Market Participation Provisions Applicable to Limited Withdrawal Service Loads that Receive “Partial” Firm Withdrawal Service

PDF bookmark

d) Market Participation Provisions Applicable to Limited Withdrawal Service Loads that Receive “Partial” Firm Withdrawal Service As previously stated, Large Loads taking some amount of Firm Withdrawal Service along with some amount of Non-Firm Withdrawal Service and/or that are partially Zero…
Read this passage

e) Market Rules Applicable to Zero Withdrawal Service Loads (“ZWSL”)

PDF bookmark · Topic match: Cost allocation

They are therefore not required to obtain Energy Resource Interconnection Service (“ERIS”) or CRIS.
Read this passage

f) Allocating Costs to Large Loads on a Gross Load Basis

PDF bookmark · Topic match: Cost allocation

Reese November 16, 2026 Page 96 black start services, creating a risk that Eligible Load may benefit from these services without contributing to cost recovery for such services.522 In response to the Commission’s concern, and to ensure that Eligible Customers taking transmission service on behalf…
Read this passage

g) The System Reliability Benefit Fee

PDF bookmark · Topic match: Cost allocation

g) The System Reliability Benefit Fee The NYISO proposes to assess a System Reliability Benefit Fee (“SRBF”) under new OATT Section 6.24.
Read this passage

C. Proposed Large Load Operating Requirements

PDF bookmark

Proposed Large Load Operating Requirements The NYISO proposes to revise Sections 3.5.2 and 13 of the Services Tariff to require Transmission Customers taking service on behalf of Large Loads to submit the following information to the NYISO: (i) six-second Real-Time telemetry; (ii) hourly…
Read this passage

D. Additional CLLC Rules

PDF bookmark

D.
Read this passage

i. Overview and Eligibility

PDF bookmark

Overview and Eligibility As noted above, the NYISO is proposing to establish and describe a new market participation model in the Services Tariff for Co-Located Arrangements535—the Co-Located and Limited Load Configuration (“CLLC”) framework.
Read this passage

ii. CLLC-Specific Definitions

PDF bookmark · Topic match: Connecting load and generation

The Co-Located Resource(s) in a CLLC shall participate in the ISO-administered Installed Capacity market as a single ICAP Supplier referred to as a Composite Co-Located Resource.536 535 A Co-Located Arrangement is an agreement between a Co-Located Load and a Co-Located Resource(s) that are…
Read this passage

iii. CLLC-Specific Metering and Telemetry Requirements

PDF bookmark · Topic match: Connecting load and generation

This section would provide that a CLLC shall be metered by the Transmission Owner it is interconnected to or in whose Load Zone it is located, and Energy injections and withdrawals at the Point of Interconnection shall be metered separately and directly and be submitted to the ISO by the…
Read this passage

iv. CLLC-Specific Energy Market Rules

PDF bookmark · Topic match: Connecting load and generation

CLLC-Specific Energy Market Rules The NYISO proposes several changes to its Day-Ahead and Real-Time Market rules to schedule and dispatch a CLLC as a single Resource and limit its withdrawals to levels consistent with its Withdrawal Service rights.
Read this passage

v. CLLC-Specific Capacity Market Rules

PDF bookmark

CLLC-Specific Capacity Market Rules The NYISO proposes various tariff changes related to CLLC participation in its capacity market.
Read this passage

vi. CLLC-Specific Settlement Rules

PDF bookmark

Reese November 16, 2026 Page 105 be determined from real-time revenue grade meters and telemetry, and that CLLCs are subject to the withdrawal balancing rules subject to the zero MW breakpoint.569 The NYISO proposes to revise Sections 18.2.1.2 (Attachment C) and 25.2.28 (Attachment J) to the…
Read this passage

E. Deviation Charges for CLLCs that Fail to Follow NYISO’s Dispatch Instructions

PDF bookmark

Deviation Charges for CLLCs that Fail to Follow NYISO’s Dispatch Instructions The NYISO is proposing to add a new Section 15.3B (“Rate Schedule 3-B”) to the Services Tariff to assess new deviation charges to CLLCs that do not follow the NYISO’s dispatch instructions/basepoints when net withdrawing…
Read this passage

i. Overwithdrawal MW x Max (MPRCDAM, MPRCRT) x Length of Interval in seconds 3600 seconds

PDF bookmark

Overwithdrawal MW x Max (MPRCDAM, MPRCRT) x Length of Interval in seconds 3600 seconds572 Under Section 15.3B.2 (Underwithdrawal Charges), a CLLC that withdraws less than its scheduled Energy withdrawals minus the tolerance will pay a corresponding underwithdrawal charge calculated as follows:
Read this passage

ii. Underwithdrawal MW x Max (MPRCDAM, MPRCRT) x Length of Interval in seconds 3600 seconds

PDF bookmark · Topic match: Reliability and curtailment

When a Generator today deviates from its basepoints, such deviations must be corrected for through the dispatch of additional Regulation capacity, which incurs a systemwide cost.
Read this passage

F. The Associated Resource Arrangements and the Capacity Region Construct

PDF bookmark · Topic match: Connecting load and generation

The Co-Located Resource(s) and the associated Co-Located Load must be behind the same Point of Interconnection and must jointly submit an attestation in accordance with Section 44.6.3.5 of Attachment LL of the ISO OATT.
Read this passage

G. DSR/Aggregation Rules

PDF bookmark · Topic match: Connecting load and generation

A Large Load is not eligible to participate in the ISO Administered Markets as a Demand Side Resource if it is a Limited Withdrawal Service Load.” Proposed Services Tariff Section 2.4. 586 Proposed OATT Part 3A § 3.A.1.2. 587 The NYISO proposes to define “Associated Resource” as “a Co-Located…
Read this passage

H. DER Modeling Improvements and Baseline Enhancements

PDF bookmark

The NYISO also proposes to require Demand Side Resources participating in the DER Participation Model to use “Meter Before/Meter After” baselining methodology to measure the amount of Demand Reduction provided in the first hour of Demand Side Resource dispatch.597 The use of Meter Before/Meter…
Read this passage

I. Sunsetting the NYISO’s BTM:NG Resource Program

PDF bookmark

As such, the NYISO proposes to sunset the program, and transition its existing participants to another participation model.
Read this passage

J. Proposed Revisions to the NYISO’s Market Power Mitigation Measures

PDF bookmark

Proposed Revisions to the NYISO’s Market Power Mitigation Measures
Read this passage

i. Revisions to the “Buyer-Side” Capacity Market Power Mitigation Measures

PDF bookmark · Topic match: Reliability and curtailment

Reese November 16, 2026 Page 114 Commission precedent that market power mitigation rules must balance investor and consumer interests by avoiding both over-mitigation and artificial price suppression.604 The two exclusions that the NYISO is proposing now are considerably narrower in scope than the…
Read this passage

ii. Additional Market Power Mitigation Measures Changes for CLLCs

PDF bookmark

Additional Market Power Mitigation Measures Changes for CLLCs The NYISO also proposes to revise Section 23 of the Services Tariff (Attachment H) to clarify the applicability of existing market power mitigation rules to CLLCs.
Read this passage

V. THE NYISO’S PROPOSALS BUILD ON THE NYISO’S ESTABLISHED TRANSMISISON MODEL AND MARKET STRUCTURES AND DO NOT NEED TO INCORPORATE THE PJM CO-LOCATION ORDER’S TRANSMISSION SERVICES

PDF bookmark

THE NYISO’S PROPOSALS BUILD ON THE NYISO’S ESTABLISHED TRANSMISISON MODEL AND MARKET STRUCTURES AND DO NOT NEED TO INCORPORATE THE PJM CO-LOCATION ORDER’S TRANSMISSION SERVICES The Commission has repeatedly determined, the NYISO’s financial reservation based transmission service (“Financial…
Read this passage

A. The NYISO’s Financial Transmission Service Model Enables the NYISO to Maximize the Use of the Transmission System Efficiently and to Support Flexible Service for Large Loads

PDF bookmark

The NYISO’s Financial Transmission Service Model Enables the NYISO to Maximize the Use of the Transmission System Efficiently and to Support Flexible Service for Large Loads The NYISO does not accept or facilitate reservations of physical transmission service within the NYCA.
Read this passage

B. The NYISO’s Financial Reservation Model Promotes Economic Efficiency in the Use of the Transmission System and Resources

PDF bookmark

ER11- 2459-000 at p. 15 (December 21, 2010) (“the NYISO proposes to affirmatively indicate that Non-Firm Transmission Service is unavailable for internal Transactions”). 623 New York Independent System Operator, Inc., Letter Order, Docket No.
Read this passage

C. There Is No Need for the NYISO to Adopt the Transmission Services Established by the PJM Co-Location Order

PDF bookmark · Topic match: Cost allocation

Similarly, the NYISO proposes to offer its new Non-Firm Withdrawal Service as an option to allow new Large Loads to connect to the grid faster and without the potential delays required to mitigate adverse impacts to resource adequacy and/or transmission security.
Read this passage

VI. the NYTOs and the NTOs Are addressing certain show cause order issues in Separate FPA Section 205 Filings

PDF bookmark · Topic match: Cost allocation

Subsequently, the Abeyance Order granted both the NYTOs and the NTOs additional time to make such filings.
Read this passage

VII. The FPA Section 205 Standard of Review and Severability

PDF bookmark · Topic match: Reliability and curtailment

The NYISO’s proposal addresses a large number of operationally and legally complex questions in the context of the resource adequacy challenges facing New York.
Read this passage

VIII. Stakeholder Approval

PDF bookmark · Topic match: Filing procedure

STAKEHOLDER APPROVAL The NYISO used the additional time provided by the Abeyance Order to conduct an expedited, extensive, and ultimately successful stakeholder process.
Read this passage

IX. Requested Effective Dates

PDF bookmark

REQUESTED EFFECTIVE DATES The NYISO respectfully requests a February 1, 2027 effective date for proposed OATT Attachment LL, i.e., the new LLIP, all new defined terms referenced in Attachment LL, Section 3A of the OATT, all other OATT and Services Tariff revisions directly related to Attachment LL…
Read this passage

X. Request to Continue Abeyance of Show Cause Proceedings

PDF bookmark · Topic match: Filing procedure

In addition, the NYISO requests that if the Commission were to require the NYISO to make additional tariff revisions before accepting the NYISO’s proposals under FPA Section 205 that it hold the Show Cause proceedings in further abeyance for a reasonable time to give the NYISO an opportunity to…
Read this passage

XI. Request for Extended Comment Period

PDF bookmark · Topic match: Filing procedure

REQUEST FOR EXTENDED COMMENT PERIOD The NYISO respectfully requests that the Commission extend the standard 21-day comment period for FPA section 205 filings by one week.
Read this passage

XII. Communications and Correspondence

PDF bookmark

COMMUNICATIONS AND CORRESPONDENCE All communications and service with regard to this filing should be directed to: Robert E.
Read this passage

XIII. Service

PDF bookmark

SERVICE The NYISO will send an electronic link to this filing to the official representative of each of its customers, to each participant on its stakeholder committees, to the New York Public Service Commission, and to the New Jersey Board of Public Utilities.
Read this passage

XIV. Conclusion

PDF bookmark · Topic match: Filing procedure

CONCLUSION Wherefore, the NYISO respectfully requests that the Commission accept the revisions proposed in this filing as just, reasonable, and not unduly discriminatory without requiring any modifications or initiating additional procedures.
Read this passage